innovation through carbon

27
Innovation through Carbon ICE/APM Prestige lecture Chris Newsome Director of Asset Management Anglian Water 1 st July 2013

Upload: association-for-project-management

Post on 20-Jun-2015

829 views

Category:

Business


0 download

TRANSCRIPT

Page 1: Innovation through carbon

Innovation through Carbon

ICE/APM Prestige lecture

Chris NewsomeDirector of Asset ManagementAnglian Water

1st July 2013

Page 2: Innovation through carbon

Driving Innovation through Carbon Reduction

ICE/APM Prestige lecture

Chris NewsomeDirector of Asset ManagementAnglian Water

1st July 2013

Page 3: Innovation through carbon
Page 4: Innovation through carbon

Our Love Every Drop goals

Backed up by over 100 commitments

and measures

Page 5: Innovation through carbon

Halve our embodied carbon in new assets we

build by 2015 from a 2010

baseline

Reduce our operational

carbon emissions by 10% in real terms by 2015

from 2010 baseline

Page 6: Innovation through carbon

Moving beyond operational carbon

Operational carbonEmbodied carbon

Most forward looking organisations are

reducing operational carbon.

Leading organisations are reducing embodied

and operational carbon.

487,659 Tonnes annual greenhouse gas emissions (of CO2e)

£45,568bn Gross asset value (replacement cost)

Around 2bn 5 year capital investment programme

Our carbon

footprint

Page 7: Innovation through carbon

Managing Embodied Carbon

Don’t build

Build less

Use materials with lower

embodied carbon

Use fewer materials/reduce waste

Process

Tools

Governance

Perceived barriers ?

??

Page 8: Innovation through carbon

Belief – Back of a ‘fag packet’ calculation and a public platform

• Example HPPE SDR17 in road• Pipe material only 11% of total

CO2e• 89% for excavation, laying,

backfillPipe Material

Excavation

Laying

Backfill and re-instatement

B

D

C

Ground level

Pipe OD

C1

C2

C3

C4

D1

Page 9: Innovation through carbon

9

Future Opportunity : Sustainable drainage systems..

Page 10: Innovation through carbon

10

Proof of Concept – ‘Our First Standard Product’ : the Wootton booster…….

Simplified design process and procurement

Installation reduced from 15 days to 1 day

Reduced waste and re-work

Time on site reduced by 50% - 3 weeks

Highest quality, consistently, at a lower cost

Health & Safety risks reduced

Page 11: Innovation through carbon

11

Orthophosphoric acid dosingThe Mark II product provides a reduced footprint dosing plant. Savings are made by buying in bulk (enabled by programme visibility) and by reducing the amount of design, installation and commissioning. Saving of 23% on the cost of the product coreSaving of ~10% on embodied carbon

AMP 5 Standard Products : Focus on Carbon & Cost

Air valvesSmaller and lighter than traditional AVs and more efficient.Saving of 36% on the cost of the product coreSaving of 93% on embodied carbon

Valve chambersA telescopic sheath for the valve spindle eliminates the need for a traditional chamber and reduces installation time. Saving of 50% on the cost of the product coreSaving of 27% on embodied carbon

P removal1 tank instead of 2 and reduced footprint. Saving of greater than 15% on product coreTargeting 50% reduction in embodied carbon

High efficiency aerationApproximately 30% less air is needed with this product, resulting in corresponding lower energy requirements for the blowers.Savings of 86% on Whole Life CostSavings of 25% on Whole Life Carbon

PolydosingCost saving of 15% on product coreSaving of 12% on embodied carbon

Page 12: Innovation through carbon

Precast concretePrecast concrete units provide a more cost effective solution than plastic for certain

ground conditions.28% cost saving

19% reduction in embodied carbon(50% reduction with cement replacement)

Structured plastic with conventional bedding

Lower cost solution with lower embodied carbon, but still requires bedding and surround

to be craned into position.34% cost saving

39% reduction in embodied carbon

Conventional in-situ reinforced concreteConventional techniques are labour and materials intensive.

Structured plastic in curved trenchA specially fabricated bucket enables a curved-

bottom trench to be dug, making significant savings on imported bedding and surround

materials.38% cost saving

50% reduction in embodied carbon(55% reduction with SMR)

Early AMP 5 : Innovation in our supply chain

Page 13: Innovation through carbon

Joint ICE and APM Prestige Lecture

Precast concretePrecast concrete units provide a more cost effective solution than plastic for certain ground conditions.28% cost saving19% reduction in embodied carbon(50% reduction with cement replacement)

Structured plastic with conventional beddingLower cost solution with lower embodied carbon, but still requires bedding and surround to be craned into position.

34% cost saving39% reduction in embodied carbon

Conventional in-situ reinforced concreteConventional techniques are labour and materials intensive.

Structured plastic in curved trenchA specially fabricated bucket enables a curved-bottom trench to

be dug, making significant savings on imported bedding and surround materials.

38% cost saving50% reduction in embodied carbon

(55% reduction with SMR)

Early AMP 5 : Innovation in our supply chain

Page 14: Innovation through carbon

Refurbish verses Replace Foulsham Water Treatment Works

Contact Tank

Existing Contact/Balance Tank•Damage to internal coating•Unable to isolate for refurbishment•Integral high lift pumping station•Isolated Public Water Supply Zone•Main storage for the zone•Proposed solution was new contact tank/balance tank/pumping station on new land adjacent to site

Use materials with lower embodied carbon

Use fewer materials/reduce waste

• Low Carbon Challenge Solution•Temporary tanks to allow isolation•Shotblast & re-coat existing tank•Original design 166 tonnes embodied carbon•New design 3 tonnes embodied carbon•Saving in embodied carbon and reduction in use of finite materials from the environment

Page 15: Innovation through carbon

15

Sustainable Design

Bedford Treatment Works

• 30,000 population growth • Proposal cost £24m• Affordability £17m• Sustainable Solution £14m• Embodied Carbon

- 66%• Operational carbon

-170%

Page 16: Innovation through carbon

PRODUCT DEVELOPMENT Standard Orthophosphoric Acid dosing

product.

BUILD OFFSITEOrthophosphoric Acid

dosing unit built offsite.

CARBON CHALLENGE Rapid Gravity Filters elevated on steelwork to

remove the requirement for extensive earthworks or interstage pumping.

Carbon Reduction

60%

CARBON CHALLENGERapid Gravity Filters installed outside

instead of in a building.Carbon Reduction

80%

Raithby Water Treatment Works

Page 17: Innovation through carbon

Bracebridge BoosterBuild Off-Site

• Resilience Scheme• Proposal cost : £3.0m• Sustainable Solution : £2.3m (-23%)• Embodied Carbon : - 38%• Operational Carbon : - 23 t/c02e p.a.

• Build off site strategy• Above ground solution• Liaison with operational

and network teams • Early planner

engagement• Consistent objectives

across the supply chain

Page 18: Innovation through carbon

Uttons Drove STW

Growth Scheme• Proposal cost : £11.7m• Sustainable Solution : £10m (-15%)• Embodied Carbon : - 48%

• Build off site strategy• Concrete to steel solution

• Each tank constructed in 9 days verses 3 months forecast

• Duplicate function of single assets (tank walls, walkways & roads, etc)

• Consistent objectives across the supply chain

Uttons Drove Aeration Tanks

Uttons Drove Inlet Works

Page 19: Innovation through carbon

What happened : REDUCED CARBON REDUCED COST

• Design engineers rose to the challenge– Released from focus on cost and standard design

• Key Framework Partners & suppliers energised to deliver low carbon solutions

• Strong link between lower embodied carbon and lower CAPEX• Design engineers and suppliers challenged AWS to improve measurement

& management– Strong illustration that reducing carbon matters to them !

Embodied Carbon and CAPEX percentage change 100% CAPEX = baseline , 100% Embodied carbon = baseline

0

20

40

60

80

100

120

140

160

180

200

220

240

260

0 20 40 60 80 100 120 140 160 180 200 220 240 260

CAPEX (%)

EMBODIED CARBON %

Line joining average CAPEX and EMBODIED CARBON saving points

Target low cost low carbon area

Page 20: Innovation through carbon

Water Innovation Network (WIN)

• Drive innovation into the water industry through the supply chain

– Delivery of capital and operational efficiencies– Service improvements– Sustainability and environmental impact– Over 300 organisations (inc. SME’s & new businesses)

engaged – 10 ideas exploited in AW– Open Innovation in action

Page 21: Innovation through carbon

Carbon Mitigation Challenge

0

100

200

300

400

500

600

700

2005/6 2006/7 2007/8 2008/9 2009/10 2010/11 2011/12 2012/13 2013/14 2014/15

k/t

CO

2e Non-CO2 process

emissions

Purchased Green

Transport

Other fuels

Electricity

481 485 478 498 494

45 k/t CO2e saving

FBP

10% Reduction in Real Terms

10% Reporting Reduction

Page 22: Innovation through carbon

Pathfinder AMP 6 :

Sustainability Toolkit

• New sustainability toolkit informs the decision making process of a project

• It ensures engineers are aware of their impact on sustainability during the design phase of a project

• Provides them with the information to assess the interrelationship between carbon, waste, cost and water usage

Page 23: Innovation through carbon

Building Momentum to : Reduce Carbon Reduce Cost

Infrastructure Carbon Review:

Main Report

November 2013

Page 24: Innovation through carbon
Page 25: Innovation through carbon
Page 26: Innovation through carbon
Page 27: Innovation through carbon

Cross industry leadership on Carbon

0

Infrastructure Carbon Review:

Main Report

3.1

Green Construction Board