innovation through carbon
TRANSCRIPT
Innovation through Carbon
ICE/APM Prestige lecture
Chris NewsomeDirector of Asset ManagementAnglian Water
1st July 2013
Driving Innovation through Carbon Reduction
ICE/APM Prestige lecture
Chris NewsomeDirector of Asset ManagementAnglian Water
1st July 2013
Our Love Every Drop goals
Backed up by over 100 commitments
and measures
Halve our embodied carbon in new assets we
build by 2015 from a 2010
baseline
Reduce our operational
carbon emissions by 10% in real terms by 2015
from 2010 baseline
Moving beyond operational carbon
Operational carbonEmbodied carbon
Most forward looking organisations are
reducing operational carbon.
Leading organisations are reducing embodied
and operational carbon.
487,659 Tonnes annual greenhouse gas emissions (of CO2e)
£45,568bn Gross asset value (replacement cost)
Around 2bn 5 year capital investment programme
Our carbon
footprint
Managing Embodied Carbon
Don’t build
Build less
Use materials with lower
embodied carbon
Use fewer materials/reduce waste
Process
Tools
Governance
Perceived barriers ?
??
Belief – Back of a ‘fag packet’ calculation and a public platform
• Example HPPE SDR17 in road• Pipe material only 11% of total
CO2e• 89% for excavation, laying,
backfillPipe Material
Excavation
Laying
Backfill and re-instatement
B
D
C
Ground level
Pipe OD
C1
C2
C3
C4
D1
9
Future Opportunity : Sustainable drainage systems..
10
Proof of Concept – ‘Our First Standard Product’ : the Wootton booster…….
Simplified design process and procurement
Installation reduced from 15 days to 1 day
Reduced waste and re-work
Time on site reduced by 50% - 3 weeks
Highest quality, consistently, at a lower cost
Health & Safety risks reduced
11
Orthophosphoric acid dosingThe Mark II product provides a reduced footprint dosing plant. Savings are made by buying in bulk (enabled by programme visibility) and by reducing the amount of design, installation and commissioning. Saving of 23% on the cost of the product coreSaving of ~10% on embodied carbon
AMP 5 Standard Products : Focus on Carbon & Cost
Air valvesSmaller and lighter than traditional AVs and more efficient.Saving of 36% on the cost of the product coreSaving of 93% on embodied carbon
Valve chambersA telescopic sheath for the valve spindle eliminates the need for a traditional chamber and reduces installation time. Saving of 50% on the cost of the product coreSaving of 27% on embodied carbon
P removal1 tank instead of 2 and reduced footprint. Saving of greater than 15% on product coreTargeting 50% reduction in embodied carbon
High efficiency aerationApproximately 30% less air is needed with this product, resulting in corresponding lower energy requirements for the blowers.Savings of 86% on Whole Life CostSavings of 25% on Whole Life Carbon
PolydosingCost saving of 15% on product coreSaving of 12% on embodied carbon
Precast concretePrecast concrete units provide a more cost effective solution than plastic for certain
ground conditions.28% cost saving
19% reduction in embodied carbon(50% reduction with cement replacement)
Structured plastic with conventional bedding
Lower cost solution with lower embodied carbon, but still requires bedding and surround
to be craned into position.34% cost saving
39% reduction in embodied carbon
Conventional in-situ reinforced concreteConventional techniques are labour and materials intensive.
Structured plastic in curved trenchA specially fabricated bucket enables a curved-
bottom trench to be dug, making significant savings on imported bedding and surround
materials.38% cost saving
50% reduction in embodied carbon(55% reduction with SMR)
Early AMP 5 : Innovation in our supply chain
Joint ICE and APM Prestige Lecture
Precast concretePrecast concrete units provide a more cost effective solution than plastic for certain ground conditions.28% cost saving19% reduction in embodied carbon(50% reduction with cement replacement)
Structured plastic with conventional beddingLower cost solution with lower embodied carbon, but still requires bedding and surround to be craned into position.
34% cost saving39% reduction in embodied carbon
Conventional in-situ reinforced concreteConventional techniques are labour and materials intensive.
Structured plastic in curved trenchA specially fabricated bucket enables a curved-bottom trench to
be dug, making significant savings on imported bedding and surround materials.
38% cost saving50% reduction in embodied carbon
(55% reduction with SMR)
Early AMP 5 : Innovation in our supply chain
Refurbish verses Replace Foulsham Water Treatment Works
Contact Tank
Existing Contact/Balance Tank•Damage to internal coating•Unable to isolate for refurbishment•Integral high lift pumping station•Isolated Public Water Supply Zone•Main storage for the zone•Proposed solution was new contact tank/balance tank/pumping station on new land adjacent to site
Use materials with lower embodied carbon
Use fewer materials/reduce waste
• Low Carbon Challenge Solution•Temporary tanks to allow isolation•Shotblast & re-coat existing tank•Original design 166 tonnes embodied carbon•New design 3 tonnes embodied carbon•Saving in embodied carbon and reduction in use of finite materials from the environment
15
Sustainable Design
Bedford Treatment Works
• 30,000 population growth • Proposal cost £24m• Affordability £17m• Sustainable Solution £14m• Embodied Carbon
- 66%• Operational carbon
-170%
PRODUCT DEVELOPMENT Standard Orthophosphoric Acid dosing
product.
BUILD OFFSITEOrthophosphoric Acid
dosing unit built offsite.
CARBON CHALLENGE Rapid Gravity Filters elevated on steelwork to
remove the requirement for extensive earthworks or interstage pumping.
Carbon Reduction
60%
CARBON CHALLENGERapid Gravity Filters installed outside
instead of in a building.Carbon Reduction
80%
Raithby Water Treatment Works
Bracebridge BoosterBuild Off-Site
• Resilience Scheme• Proposal cost : £3.0m• Sustainable Solution : £2.3m (-23%)• Embodied Carbon : - 38%• Operational Carbon : - 23 t/c02e p.a.
• Build off site strategy• Above ground solution• Liaison with operational
and network teams • Early planner
engagement• Consistent objectives
across the supply chain
Uttons Drove STW
Growth Scheme• Proposal cost : £11.7m• Sustainable Solution : £10m (-15%)• Embodied Carbon : - 48%
• Build off site strategy• Concrete to steel solution
• Each tank constructed in 9 days verses 3 months forecast
• Duplicate function of single assets (tank walls, walkways & roads, etc)
• Consistent objectives across the supply chain
Uttons Drove Aeration Tanks
Uttons Drove Inlet Works
What happened : REDUCED CARBON REDUCED COST
• Design engineers rose to the challenge– Released from focus on cost and standard design
• Key Framework Partners & suppliers energised to deliver low carbon solutions
• Strong link between lower embodied carbon and lower CAPEX• Design engineers and suppliers challenged AWS to improve measurement
& management– Strong illustration that reducing carbon matters to them !
Embodied Carbon and CAPEX percentage change 100% CAPEX = baseline , 100% Embodied carbon = baseline
0
20
40
60
80
100
120
140
160
180
200
220
240
260
0 20 40 60 80 100 120 140 160 180 200 220 240 260
CAPEX (%)
EMBODIED CARBON %
Line joining average CAPEX and EMBODIED CARBON saving points
Target low cost low carbon area
Water Innovation Network (WIN)
• Drive innovation into the water industry through the supply chain
– Delivery of capital and operational efficiencies– Service improvements– Sustainability and environmental impact– Over 300 organisations (inc. SME’s & new businesses)
engaged – 10 ideas exploited in AW– Open Innovation in action
Carbon Mitigation Challenge
0
100
200
300
400
500
600
700
2005/6 2006/7 2007/8 2008/9 2009/10 2010/11 2011/12 2012/13 2013/14 2014/15
k/t
CO
2e Non-CO2 process
emissions
Purchased Green
Transport
Other fuels
Electricity
481 485 478 498 494
45 k/t CO2e saving
FBP
10% Reduction in Real Terms
10% Reporting Reduction
Pathfinder AMP 6 :
Sustainability Toolkit
• New sustainability toolkit informs the decision making process of a project
• It ensures engineers are aware of their impact on sustainability during the design phase of a project
• Provides them with the information to assess the interrelationship between carbon, waste, cost and water usage
Building Momentum to : Reduce Carbon Reduce Cost
Infrastructure Carbon Review:
Main Report
November 2013
Cross industry leadership on Carbon
0
Infrastructure Carbon Review:
Main Report
3.1
Green Construction Board