industry presentation 7, industry perpective on ...providing guidance for designers and regulators...

5
1 Industry Perspective on Computerized Procedures and Adequacy of Current Guidance Discussion with NRC TWG #5 May 21, 2008 Washington, DC

Upload: others

Post on 26-Jun-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Industry Presentation 7, Industry Perpective on ...providing guidance for designers and regulators for consistent and predictable regulation • Examples of areas where additional

1

Industry Perspective on Computerized Procedures and Adequacy of Current

Guidance

Discussion with NRC TWG #5

May 21, 2008Washington, DC

Page 2: Industry Presentation 7, Industry Perpective on ...providing guidance for designers and regulators for consistent and predictable regulation • Examples of areas where additional

2© 2008 Electric Power Research Institute, Inc. All rights reserved.

Computerized Procedures are Here and More are Coming

• Computerized procedures (CPs) being used in some plants today

• CPs of different types will be part of new plant designs requiring review by NRC – as we have just heard

• Clear trends

– Increasing use of CPs

– Increasing level of functionality, ranging from:• Electronic procedures – replicas of paper-based procedures

• Computer-based procedures – incorporating live data, soft controls, step logic processing

• Procedure-based automation – CP system executing multiple steps in sequence, on command by operator, until reaching a hold point

Page 3: Industry Presentation 7, Industry Perpective on ...providing guidance for designers and regulators for consistent and predictable regulation • Examples of areas where additional

3© 2008 Electric Power Research Institute, Inc. All rights reserved.

Need for Additional Regulatory Guidance

• Interim Staff Guidance (ISG) recently issued by NRC

• Industry has commented that ISG does not go far enough in providing guidance for designers and regulators for consistent and predictable regulation

• Examples of areas where additional guidance is needed:– Criteria for design, implementation and qualification that are

applicable to different levels of functionality (e.g., EP, CBP, PBA)

– Criteria and guidance for automated processing of procedure step logic

– Guidance on maintenance and configuration management of CPs

– Guidance and criteria for procedure-based automation

Page 4: Industry Presentation 7, Industry Perpective on ...providing guidance for designers and regulators for consistent and predictable regulation • Examples of areas where additional

4© 2008 Electric Power Research Institute, Inc. All rights reserved.

Conclusion

• To achieve a consistent and predictable regulatory process, more definitive guidance is needed:

– Designers and owners of CP systems need to understand the criteria that should be applied to those systems

– NRC reviewers will need definitive criteria by which to judge adequacy of CP systems they will be reviewing

• Industry has prepared a technical report to provide the needed guidance

– NRC review and endorsement of this technical report is needed in the near term to support new plant reviews

– Will reduce NRC effort in doing reviews

Page 5: Industry Presentation 7, Industry Perpective on ...providing guidance for designers and regulators for consistent and predictable regulation • Examples of areas where additional

5© 2008 Electric Power Research Institute, Inc. All rights reserved.

Questions?