  • 8/11/2019 Industrial Crane Building

    1/18

    1

    NASCC 2009- CSD Track

    Design of an Industrial Crane

    Building Session 5

    CSD Presenter:

    Jim Fisher

    2

    Design of anIndustrial Crane Building

    Session 5

    Roof and Wall Design

    Standing Seam Roof Considerations

    Joist Design

    Gravity

    Uplift

    Ponding

    Girt Design (Endwalls and Sidewalls)

    Rake Beam Design

    Wind Column Design

    OMF Lateral Bracing Design

  • 8/11/2019 Industrial Crane Building

    2/18

    3

    Review of Design Criteria

    4

    Project Description

    50 ton, top running crane, Class D

    Quantity: 1 per aisle

    Hook height: 45 ft

    Roof type: Standing Seam on Joists

    Wall type: R- panel with continuous Zs Automatic Sprinkler System

  • 8/11/2019 Industrial Crane Building

    3/18

    5

    Project Location

    City: Sparks

    State: Nevada

    County: Washoe

    Latitude:39.53

    Longitude: -119.74

    6

    Codes and Standards

    Building Code: IBC 2006

    Minimum Design Loads For Buildings And OtherStructures (ASCE 7-05)

    Building Department Contact: John Smith

    Date: July 6, 2008

    Local Ordinances: None

    Wind Speed: 90 mph Wind Exposure: C

  • 8/11/2019 Industrial Crane Building

    4/18

    7

    Local Code Requirements

    Ground Snow Load: 15 psf

    Frost Depth: 24 in.

    Seismic Spectral Acceleration:

    Ss = 1.476%g

    S1 = 0.562%g

    8

    Loads

    ROOF DEAD LOAD

    Roofing (SSR) 2.0 psf

    Insulation 1.0 psf

    Roof Bracing 1.0 psf

    Joists 3.0 psf

    Joist Girders 3.0 psf

    Columns 6.0 psf

    MEP Allowance 3.0 psf

    Miscellaneous 4.0 psf

    Total 23.0 psf

    WALL DEAD LOAD 3.0 psf

    (Includes Girts)

  • 8/11/2019 Industrial Crane Building

    5/18

    9

    Loads

    ROOF LIVE LOADS 20.0 psf (reduceable)

    SNOW LOADS Ground Snow Load (Pg): 15.0 psf

    Importance Factor, I = 1.0

    Terrain Factor: C

    Thermal Factor, Ct: 1.0

    Exposure Factor, Ce, partially exposed: 1.0

    Flat Roof Snow Load: Pf= 0.7(P

    g)(I)(C

    e) = 10.5 psf