INDOT Intelligent Design andConstruction (IDC)
Derek Fuller, INDOT e-Construction SpecialistChris Martin, INDOT Highway Engineer – Road Design
Andrew Pangallo, INDOT Field Engineer
2019 Purdue Road School March 6, 2019
![Page 2: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/2.jpg)
Mission Statement
• The use of intelligent 3D CAD models to support the lifecycle of transportation assets (roads and bridges) that provides predictive analysis and reporting capabilities that is data driven and allows the agency to make better operational and strategic management decisions.
![Page 3: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/3.jpg)
The Business Opportunity
Figure 5.2 Asset data flow in the current practice at INDOT.
Figure 5.3 The suggested data flow.
![Page 4: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/4.jpg)
IDC Areas of Emphasis• Intelligent Design / Automated Machine Guidance (AMG)
• Transition from 2D plan sets to 3D design models
• e-Construction• Transition to Paperless construction
• Asset Management• Better utilization of data from Design and Construction for Operations and Maintenance
![Page 5: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/5.jpg)
e-Construction and Partnering FHWA Peer Exchange• Hosted FHWA e-Construction and Partnering Peer Exchange
• August 2018• Topics
• 3D CAD Model as Contract Document• Utah DOT
• e-Ticketing for Materials Delivery• Pennsylvania DOT
• ROI e-Construction • Oregon DOT
• ROI 3D CAD Models• Wisconsin DOT
![Page 6: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/6.jpg)
Asset Management• Progress to date:
• RFID Tag Proof of Capability study• September 2017• Small Culverts, Panel and Sheet signs• Presented the results to the INDOT asset owners
• WMS and ESRI Roads and Highways integration• Ongoing to overcome integration issues
• Transportation Asset Management Plan• Draft version released April 2018• FHWA approved draft version Fall 2018
![Page 7: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/7.jpg)
Intelligent Design / AMG• Progress to date:
• SS4 OpenRoads migration from SS2 InRoads• Completed training for INDOT staff August 2016• March 2017, SS2 InRoads removed from user computers except those working on older projects• Central Office Road Design has completed projects using SS4 OpenRoads creating 3D Models
• Provided ContextCapture training to INDOT Land and Aerial Survey Office (LASO)• December 2017, Bentley Systems, Inc.• ContextCapture allows UAV / Drone / LiDAR / Conventional Survey data to be combined to created a 3D
Mesh• Provided Subsurface Utility Drainage Analysis (SUDA) best practices and software overview to
INDOT Hydraulics and Road Design groups • January 2018, Bentley Systems, Inc.• SUDA is 3D modeling software for utilities
![Page 8: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/8.jpg)
Intelligent Design / AMG• SS4 OpenRoads
• SS4 OpenRoads migration from SS2 InRoads• Design in SS4 began July 2016 select Central Office Road Designers• Migration of existing projects less than seamless
• Existing projects in SS2 remain in SS2• IRD point controls often lost in translation
• New designs in SS4 • Improved 3d Design• Improved Cross Sections• Non-perpendicular template areas much improved• Better Visualization• Steps on the Path to Connect Edition ORD
![Page 9: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/9.jpg)
Intelligent Design / AMG• Example 3d Design model
• Intersection Improvement• Geospatially located Survey Data• Typical template design in 3d• Turning areas modeled
• Simplified irregular design areas• Surface Templates and Terrain Models
• Underdrain and Drainage Tie in• Accurate models of both existing and proposed underdrains• Simplified special grade calculation• Tie in to existing
![Page 10: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/10.jpg)
Intelligent Design / AMG
![Page 11: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/11.jpg)
Intelligent Design / AMG
![Page 12: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/12.jpg)
Intelligent Design / AMG
![Page 13: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/13.jpg)
Intelligent Design / AMG• SS4 SUDA
• Provided Subsurface Utility Drainage Analysis (SUDA) best practices and software overview to INDOT Hydraulics and Road Design groups
• January 2018, Bentley Systems, Inc.• SUDA is 3D modeling software for utilities
• Using lessons learned from best Practices Analysis• Aware of the large configuration effort required, we did the following simple alternative• Implemented SUDA on unofficial pilot project• Local configuration of SUDA for 3d location• Clash Detection was primary goal• Hydraulic flow modeling not considered
![Page 14: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/14.jpg)
Intelligent Design / AMG• Example SUDA
• Urban small structure replacement• Numerous Existing Utilities• Proposed Structure larger than existing
• Existing Dual pipe arches failing• Reinforced Concrete Box replacement
• Possible Conflicts Identified• Sanitary Sewer 24” immediately underneath existing pipes• Sewer Interceptor backfill loss under structures• Fiber likely runs under (through new) structures• Gas likely runs under (through new) structures• Water likely conflicts with new structure• Power Pole foundation in close proximity to structure excavation area
![Page 15: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/15.jpg)
Intelligent Design / AMG
![Page 16: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/16.jpg)
Intelligent Design / AMG
![Page 17: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/17.jpg)
Intelligent Design / AMG
![Page 18: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/18.jpg)
Intelligent Design / AMG
![Page 19: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/19.jpg)
Intelligent Design / AMG
![Page 20: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/20.jpg)
Intelligent Design / AMG• Ongoing Efforts
• Improved Patching Table• Locate Patching Geographically• Remove guesswork for Field Employees• Leverage ESRI ArcCollector App• Better utilization of Pavement distress scanning data
• LiDAR • Make use of Oregon DOT lessons• Improved accuracy • Better Design tolerances• Cost savings with less change orders
• Bentley Open Roads Designer ORD • Workspace Migration• Plan Pilot project• Implementation
![Page 21: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/21.jpg)
eConstruction Projects
Intelligent Design and
Construction
AASHTOWareProject PWL Wizard
eFCR HMA Tracker
![Page 22: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/22.jpg)
eConstruction Projects
Quality Checklists eTicketing OnDemand
Training
GPS/Rover Grade Control
Digital As-Builts/Asset
Management
![Page 23: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/23.jpg)
Legacy Project Information Flows
Design
ConstructionInspection
Operations & Maintenance
Construction Drawings
Redline As-builts
Built Environment
![Page 24: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/24.jpg)
Information Mobility Goals
Design
ConstructionInspection
Operations & Maintenance
Built Environment
• Streamline Field Inspection– Easy to use
• Click onto graphics to access specs, check lists & forms
• Graphical indexing and status visualization of all inspections
• Queries, benchmarking, audits, litigation research and analytics
• Automated population of Asset Management databases
![Page 25: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/25.jpg)
Construction Inspection
![Page 26: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/26.jpg)
Field Review – View Settings
Default top view showing current location
View commands
![Page 27: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/27.jpg)
Field Review – View Settings
Select view up-station command
Resulting view
Walk controls
Walk icon
![Page 28: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/28.jpg)
Field Review
Adjust view composition based on Specs and Item Extensions
Scroll down
![Page 29: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/29.jpg)
Field Review
SS1: 611E10400
Inspections
AdminInstallation Plan >
FieldExcavation >Installation >Backfill >
AdminPost Installation >
>>
>
611E10400-24" CONDUIT, TYPE BPull out Inspections panel Inspection regimen
appropriate for component type
![Page 30: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/30.jpg)
Field Review – DocumentationFirst Point
Entirety
No Portion
>AdminInstallation Plan
Quality FormField
ExcavationQuality FormQuantity FormWorksheet Form
Installation >Backfill >
>
>>
New InspectionInspections
611E10400-24" CONDUIT, TYPE B
StationDocumentationCancel Save
Item 611 Pipe
Quality form for Admin Installation Plan automatically appears without selecting because only option currently available
Save
Bookmark Expand
Select bookmark to access specs
![Page 31: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/31.jpg)
Field Review – Admin > Installation Plan
>AdminInstallation Plan
Quality FormField
ExcavationQuality FormQuantity FormWorksheet Form
Installation >Backfill >
>
>>
Inspections611E10400-24" CONDUIT, TYPE B
Marker
First Point
Entirety
No Portion
Station
Could alternately select entire component length
Use markers, data points & key-ins to graphically define inspection limits.
Item 611 Pipe
Fill out and save form
Item 611 Pipe
![Page 32: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/32.jpg)
Field Review – Admin > Installation Plan
Graphical definition of inspection limits not required in this case as the entire component length is default when saving form
Inspections611E10400-24" CONDUIT, TYPE B
Green color indicates that all checklist items on quality form for Installation Plan passed
Field Excavation, Installation and Backfill now available for inspection. Field Post Installation remains unavailable
AdminInstallation Plan
Quality Form14-Jan-19
FieldExcavation
Quality FormQuantity FormWorksheet Form
Installation >
>>
>>
>
Can change inspection form and limits on the day of inspection. Afterward, the inspection is locked.
![Page 33: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/33.jpg)
Field Review – Field > Excavation
Indicator placed at defined length
Station
Second PointLength 36
>>
>>Admin
Installation PlanQuality Form >
FieldExcavation
Quality FormQuantity FormWorksheet Form
Installation >Backfill >
AdminInstallation Plan
Quality Form >Field
ExcavationQuality Form >Quantity FormWorksheet Form
Installation >Backfill >
Inspections611E10400-24" CONDUIT, TYPE B
Red color denotes failed inspection item
Keyin length
Item 611 Pipe
Save form
Fill out form
![Page 34: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/34.jpg)
Field Review – Field > Installation
Inspections611E10400-24" CONDUIT, TYPE B
AdminInstallation Plan >
FieldExcavation >Installation
Quality FormQuantity FormWorkflow Form
BackfillQuality Form
>>
>
>
Item 611 Pipe
Item 611 Pipe
Save
Fill out form. Note TBD indicates incomplete.
![Page 35: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/35.jpg)
>
>
Other Forms: Field > Installation > Worksheet FormInspections
611E10400-24" CONDUIT, TYPE B
Admin >Field
Excavation >Installation
Quality FormQuantity FormWorksheet Form 1Worksheet Form 2
Backfill >Admin >
![Page 36: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/36.jpg)
Field Review
Inspections
AdminPre Paving >
FieldPre Paving >Tack Coat (407) >During Paving >Post Paving >
AdminPost Paving >
>>
>
442E10100-Asphalt Conc IntermediatePull out Inspections panel Inspection regimen
appropriate for component type
![Page 37: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/37.jpg)
Field Review – New Inspection Geometry Definition
Create other paving areas
Area
![Page 38: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/38.jpg)
Inspection Office
![Page 39: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/39.jpg)
Bituminous Concrete Density Determination
Inspection Office – Failed Inspections
Configuration
Element to Spec Mapping
SpecChart: Failed Inspections
Click onto pie slice
Both failed asphalt inspection workflows with the Contractor
Of the two failed asphalt inspections, one ‘Reported’ and one ‘In Progress’
![Page 40: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/40.jpg)
Bituminous Concrete Density Determination
Inspection Office – Failed Inspections
Configuration
Element to Spec Mapping
SpecChart: Failed Inspections
Select element
Chart reflects selected element
![Page 41: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/41.jpg)
Bituminous Concrete Density Determination
Inspection Office – Failed Inspections
Configuration
Element to Spec Mapping
SpecChart: Failed Inspections
To review failed quality questions, a forms push button appears if single element or single pie slice selected
Corresponding element highlights when scrolling through inspection instances
Item 611 Pipe
Cancel SaveDesign Quantity: 47 m, Measured to Date: 22 m, Paid to Date: 10 m
Resulting modal shows inspection form
If chart pie slice selected that represents multiple inspections, scroll arrows become available
![Page 42: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/42.jpg)
Bituminous Concrete Density Determination
Inspection Office – Failed Inspections
Configuration
Element to Spec Mapping
SpecChart: Photos
Photo location references
Currently selected photo
Currently selected photo
![Page 43: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/43.jpg)
Bituminous Concrete Density Determination
Element to Spec Mapping
Inspection Office – Status Visualization
Configuration
Chart: Overall – Status Viz Table
Select chart with table that summarizes inspections
Not Started
Inspected & Failed
Begin Date: End Date:
Inspected & Approved
Select element
inspection summary table
Corresponding inspection highlights
Select icon to show inspection form
![Page 44: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/44.jpg)
Construction Inspection Application
![Page 45: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/45.jpg)
Quality Checklists - Grouping
![Page 46: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/46.jpg)
Quality Checklists - Cross Referencing
![Page 47: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/47.jpg)
Quality Checklists – Pictures or Videos
![Page 48: INDOT Intelligent Design and Construction (IDC)](https://reader034.vdocuments.site/reader034/viewer/2022042421/6260208e28dd5e741b6ef428/html5/thumbnails/48.jpg)
Questions?