indonesia wind sector impact assessment
DESCRIPTION
Discussion on wind energy prospects in IndonesiaTRANSCRIPT
-
WIND POWER EVACUATION
Indonesia Clean Energy Development (ICED) projectIndonesia Wind Sector Impact Assessment
Presented by:Dr. Balaraman, Ph.D.
-
Preamble The amount of wind generation is growing rapidly and wind farms
are growing in size and complexity. Wind farms are being installed consisting of hundreds of units, with
the wind farm capable of producing hundreds of MW. The location of a wind farm is selected primarily based on good
wind conditions. Good wind conditions often coincide with relatively remote parts of the power
system. Thus the operation of the wind farm and its response to
disturbances or other changing conditions on the power system isbecoming of increasing concern
These concerns will continue to grow in importance as the amountof wind generation increases.
2
-
Wind power major integration issues- Variability & Relatively Uncertain Not despatchable as easily as conventional power
plants. Location specific Generally faraway from load centers Capacity credits during system peaks & wind power
absorption during system minimum loads for generation planning.
Need for grid support for reactive power. Changed in Grid/Grid operation for reliable wind power
evacuation
-
Wind Energy Development Indonesia Implementation of wind energy technology in Indonesia is
around 1.6MW installed capacity. implementation of wind energy systems is typically seen in
remote area / location or islands, and they are frequentlyinstalled as part of R & D project.
Area along the coastal/shore of northern and southern partof Java Island, eastern part of Madura island, south andnorth Sulawesi island, east Lombok island etc, have seensome activity for electricity generation from wind. Some ofthem for stand alone system and hybrid
4
-
Wind Energy Development Indonesia
Project activity initiated to develop wind farm ofaround 300 MW install capacity for near future atseveral sites at Bantul Sukabumi Lebak South Sulawesi (Jeneponto and Sidrap) East Nusa Tenggara (Oelbubuk)
5
-
Wind Energy Potential in Indonesia Summary data from conducted activity on wind resources assessment and research that have been
selected for 166 sites (source: Soeripno Martosaputro, (WHyPGen Project) )
6
Resources potential
Wind Speed at 50 m
Wind Power density, at 50m, (W/sq.m)
Number of sites
Provinces
Marginal 3-4 5 >150 35 Banten, DKI, Central and West Java, DIY, East and West Nusa Tenggara, South and North Sulawesi, Maluku
-
Wind farm potential sites
7
-
Other Potential Sites in Sulawesi
North Sulawesi Gorontalo South Sulawesi South East Sulawesi
8
-
Important considerations for wind integration studies
i. Location of Wind Potential vis--vis Load centers inthe state
ii. Diurnal variation of wind generation vis--visdemand variation
iii. Wind Potential Tapped/Untapped Vis--vis existingor projected state demand
iv. Peak Wind Generation Season vis--vis Systemdemand Peak/Minimum during peak wind season
v. Region wise wind potential vis--vis local powerdemand
-
Important considerations for wind integration studies
v. Diversities in peak wind generationbetween WF/regions and possible totalwind power Injection in to the Grid
vi. Other RE variable/uncertain generation likesolar in the wind rich regions/state
vii. Conventional generation in wind regionsviii. Present grid infrastructure in wind region
500kV, 275kV, 150kV etc..
-
Power flow analysis
Power flow analysis - an integral part of systemplanning and operation.
The electrical system is modeled by buses withgenerators and loads that are interconnected bybranches and transformers.
The steady-state solution of the network determinesthe bus voltages from which the active and reactivepower flow in branches can be calculated
11
-
Understanding power flow problem formulation
Goal of a power flow study-to obtain voltage angle and magnitudeinformation for each bus in a power system for specified load andgenerator real power and voltage conditions.
In power flow problem, it is assumed that the real power P and reactive power Q at each Load Bus are
known. For this reason, Load Buses are known as PQ Buses. For Generator Buses, the real power generated PG and the voltage magnitude
|V| is known. For the Slack Bus, the voltage magnitude |V| and voltage phase are known.
Therefore, for each Load Bus, the voltage magnitude and angle are unknownand must be solved for; for each Generator Bus, the voltage angle must besolved for; there are no variables that must be solved for the Slack Bus
12
-
Modeling Wind Farms for Load Flow Studies The objective of a load flow calculation is to determine flows on
transmission lines and transformers and voltages on power systembuses.
From the standpoint of the wind farm, these studies are primarily todetermine if the generated power can be transmitted successfully tothe loads or purchasing entity without loading or voltage problems.
The modeling of the ability (or lack of ability) of the wind farm to controlvoltage through control of the reactive power output of the units is veryimportant as well.
Modeling of the wind farm can be considered to have two potentiallevels of representation- Detailed modeling Equivalent modeling as seen from the system
13
-
Modeling Wind Farms for Load Flow Studies A detailed model of the wind farm-
representing individual units and theconnections between these units andthe system.
Detailed model would thus consist of,say, a hundred or more buses and asimilar number of lines.
Very detailed data on the systemconnecting the wind turbine/generators would need to be suppliedby the developer.
These detailed models can be used todetermine voltages and flows withinthe wind farm, as well as the injectioninto the utility grid.
The model can be used to check/design voltage control or reactivepower strategies in the wind farm.
14
-
Modeling Wind Farms for Load Flow Studies
Equivalent modeling the concern is not on the individual wind turbines but on the aggregate
effect of the entire farm on the power system. individual generators are lumped into equivalent machines, generally
represented at the collector buses. Thus size of system representation of the wind farm is reduced to a few
buses and the data requirements are significantly reduced. This level of modeling is often used in system studies where the effects of
the injection into the system on system flows and voltages are the concern,and internal wind farm conditions do not need to be determined
Therefore for the large scale wind penetration studies, detailed modeling maynot be required and thus lumped representation in which an equivalent of thewind farm with PQ bus modeling, would suffice for the evacuation studies
15
-
Evacuation study scenarios renewable energy projects like wind are generally located in remote
locations from load centers and may require long transmission linesto major load centers.
If the local substation loads are low, then the entire wind generationmay have to be transported to the nearest major grid sub-station -this ability of the network has to be checked in the evacuationstudies of wind to avoid backing down of wind generation.
Generally, annual system peak loads generally occur in summermonths (may be due to high cooling demand, agriculture andindustrial/commercial loads)- for wind power evacuation studies areto be analyzed for system peak loads during peak wind generationperiod.
16
-
Evacuation study scenarios
The corresponding minimum load during peak windseason that may occur in night hours when windgenerations hit the peak is another importantscenario that has to be analyzed.
The network data collection therefore has to includethe wind generation pattern month on month andlocal sub-station loads for the corresponding periodsso as to carry out wind power integration studies forthese critical scenarios.
17
-
Key Tasks Involved Data collection and quality checking Portfolio development: determining scenarios to be studied and base
case for comparisons Impact of wind power on short term reserves as statistical data analysis Running capacity resource adequacy analysis to assess capacity value of
wind power Running production cost simulations to see how wind power impacts the
scheduling & dispatch of conventional generation, and operational costs ofthe system
Running transmission network simulations to see that the transmissionnetwork is adequate
Running iterations based on initial results if there is need to change thegeneration or transmission portfolio or operational practices
Analyzing the data and presenting the results
-
Critical scenarios to be analyzed for wind power evacuation
19
Sl. No. Wind generation System demand Local demand Local conventionalLocal non-
conventional
1 Peak wind season
Maximum system demand during peak wind season
corresponding local load Maximum Maximum
2 Peak wind season
Minimum system demand during peak wind season
corresponding local load
corresponding conventional generation
Minimum
3 Peak wind season
Maximum system demand during peak wind season
local S/S light load in peak wind generation Maximum Maximum
4 Peak wind season
Minimum system demand during peak wind season
local S/S light load in peak wind generation
corresponding conventional generation
Minimum
5Off-Peak
wind season
Maximum system demand during off-peak wind
season
corresponding local load Maximum Maximum
6Off-Peak
wind season
Minimum system demand during off-peak wind
season
corresponding local load
corresponding conventional generation
Minimum
-
Sulawesi system analysis
20
-
Year
2015 Sidrap 70MW
2019Jeneponto-1 62.5MW
Jeneponto-2 64.5MW
Wind Farms Planned in South Sulawesi
-
Wind Farm Sites South Sulawesi
Sidrap
Jeneponto
-
Wind Farm DetailsSl. No. Particulars Details
1Name of the wind farm
projectSidrap Jeneponto 1 Jeneponto 2
2 Capacity of wind farm 70MW 62.5 MW 64.8 MW
3Wind generator make &
turbine capacity in MW
Goldwind / 2.5MW
WTGGE / 2.5MW GE / 1.62MW
4 Name of the developer UPC Renewables
PT Energi Angin Indonesia (Consortium Indo
Wind Power Holdings Pte Ltd, Kencana
Energy, IFC)
PT Energi Angin Mandiri (Consortium
Indo Wind Power Holdings Pte Ltd,
Kencana Energy, IFC)
5
Name of the
region/province of the wind
farm
Sulawesi SelatanSulawesi Selatan, Jeneponto regency,
Bangkala subdistrict
Sulawesi Selatan, Jeneponto regency,
Turatea sub district
6 Name of town/village Not available Desa Tombo Tombolo Desa Mangepong
7Assumed year of
commissioning of wind farm
2015 (based on the
initial information
collected during site
visit of IWE)
2016 2017/18
8 Size of the land (hectares) Not available 600 600
9 Current land use Not available Corn farming (one crop cycle per year) Farming
10 Assumedcompletion date Not availableFinancial closure Q3 2014, COD 31 March
2016
Financial closure Q3 2014, COD 31
March 2016
11 Current status of project Not available
Location permit (regency), Principle permit
(regency), Principle permit (BKPMD) are
obtained, the environmental and social
impact assessment under the IFC's
performance standards are expected by
February 2014
Location permit (regency), Principle
permit (regency) are obtained
12Co-ordinates of wind farm
pooling substation Not available S0536'11.77" E11936'14.14" S0535'00" E11943'00"
-
Wind Farm Pooling SubstationsSl. No. Particulars Sidrap Jeneponto 1 Jeneponto 2
1 MVA Rating 85 72 72
2 Number of transformers 1 1 1
3 Voltage level in kV 150/33 150/33 150/33
5% Positive sequence impedance on its
own rating15 15 15
6% Zero sequence impedance on its
own rating15 15 15
7 Winding configuration Star grounded/Delta Star grounded/Delta Star grounded/Delta
8Type of tap changer (On load or Off-
load)On-load On-load On-load
9 Total number of taps 21 21 21
10 Nominal tap 11 11 11
11 Minimum tap range in pu 12.5% 12.5% 12.5%
12 Maximum tap range in pu 12.5% 12.5% 12.5%
-
Existing Power Generation around Sidrap
Conventional generations: Sengkang combined cycle power plant
2x42.5MW(GT) + 1x50MW(ST) + 2x60MW(GT) + 1x60MW(ST)
Baru 2x50MW thermal power plant Suppa 6x10.8MW diesel power plant
-
Existing Transmission System around Sidrap
Sidrap 150/20 kV substation Sengkang 150/20 kV
substation Sopeng 150/20 kV substation Makale 150/20 kV substation Pare 150/20 kV substation Maros 150/20 kV substation
150kV, 19.1km D/C hawk conductor line from Sidrap substation to Pare substation.
150kV, 53.8km D/C hawk conductor line from Sidrap substation to Sopengsubstation.
150kV, 62.33km D/C 2xzebra conductor line from Sengkangsubstation to Sidrap substation.
150kV, 126.54km D/C 2xzebra conductor line from Sidrap substation to Maros substation.
150kV, 105.48km D/C zebra conductor line from Sidrap substation to Makale substation.
Substations Transmission Lines
-
Existing Power Generation around Jeneponto
Conventional generations:
Jeneponto - 2x125MW thermal power plant
Tallasa 115MW MFO power plant
Sungguminasa 25MW MFO power plant
-
Existing Transmission System around Jeneponto
Jeneponto 150/20 kV substation Bulukumba 150/20 kV
substation Tallasa 150/20 kV substation Sinjai 150/20 kV substation Sungguminasa 150/20 kV
substation
150kV, 46.35km D/C hawk conductor line from Jenepontosubstation to Bulukumbasubstation.
150kV, 24.5km D/Chawkconductor line from Jenepontosubstation to Punagaya Tip.
150kV, 19.1km D/C 2xzebra conductor line from PunagayaTip to Tallasa substation.
150kV, 63.87km S/C hawk conductor line from Bulukumbasubstation to Sinjai substation.
150kV, 137.2km S/C hawk conductor line from Bulukumbasubstation to Bone substation.
Substations Transmission Lines
-
Transmission Line Parameters
Sl. No. Conductor typeVoltage in
kV
Positive sequence Zero sequenceThermal
rating in
MVA/ckt
R
(ohm / km/ckt)
X
(ohm /
km/ckt)
B/2
(mho /
km/ckt)
R
(ohm /
km/ckt)
X
(ohm /
km/ckt)
B/2
(mho /
km/ckt)
1 ACSR Hawk 120a 70 0.23602 0.43327 9.42E-07 0.268 1.272 4.87E-07 48.5
2 ACSR Hawk 120b 30kV 30 0.29899 0.42587 1.11E-06 0.268 1.272 1.11E-06 20.78
3 ACSR Hawk 240a 150 0.118 0.424 1.50E-06 0.268 1.272 7.30E-07 155.88
4 ACSR_Hawk_240b 150 0.118 0.424 1.50E-06 0.268 1.272 7.30E-07 155.88
5 ACSR_Hawk_240c 150 0.118 0.424 1.50E-06 0.268 1.272 7.30E-07 155.88
6 ACSR Hawk 240d 150 0.1183 0.424 1.50E-06 0.268 1.272 7.30E-07 155.88
7 ACSR Hawk 240e 150 0.1183 0.424 1.50E-06 0.268 1.272 7.30E-07 155.88
8 ACSR Hawk 240f 150 0.119 0.424 1.50E-06 0.268 1.272 7.30E-07 155.88
9 ACSR Hawk 240g 150 0.0897 0.3222 1.50E-06 0.268 1.272 7.30E-07 155.88
10 ACSR Hawk 240h 150 0.236 0.4333 1.50E-06 0.268 1.272 7.30E-07 155.88
11 ACSR Zebra 430a 150 0.067 0.4026 1.50E-06 0.268 1.272 7.30E-07 207.84
12 ACSR 2xZebra 430b 150 0.0397 0.272 3.00E-06 0.268 1.272 9.11E-07 415.68
13ACSR 2xHawk 24 sq.
mm
1500.059 0.2807 2.09E-06 0.3207 1.197 1.27E-06 311.76
142xZebra 430sq.mm
275kV
2750.0397 0.2952 2.00E-06 0.2688 1.141 9.11E-07 762.1
15 XLPE 400sq. mm 150 0.0619 0.1414 2.12E-05 0.1547 0.3535 1.90E-05 137.69
16 XLPE Cu325 sq.mm 70 0.0781 0.132 3.14E-05 0.1953 0.33 2.83E-05 56.98
-
Managing variability and uncertainty
Wind power is variable and relatively unpredictable by nature To know the power output at 10minute intervals with certainty is
a challenge. WPPs are treated as must-run in some of the utility grid codes
due to the absence of fuel input unless grid security is at stake. Grid shall be designed to absorb wind generation by backing
down conventional generating sources Compensate for loss of wind energy by ramping up other
generation sources. In South Sulawesi, at present spinning reserves are available
through reservoir hydropower plant which is attractive from anoperational perspective, as it can be ramped up or down.
-
Assumptions in the System Study
System Parameters Sidrap WPP to be commissioned in 2015 Jeneponto-1 and Jeneponto-2 WPP to be
commissioned in 2016 and 2017 respectively Study is carried out for 2015 and 2019 conditions
-
Assumptions in the System Study
Transmission network details Interconnection of Sulteng system (central) with South
Sulawesi i.e., through interconnection of 275kV PosoHydroelectric transmission with Palopo is considered forthe year 2015
Transmission system for 2015 network condition has beenmodeled based on the comments provided by PLN ondata report & RUPTL 2012-21 report.
Transmission system for 2019 network condition has beenmodeled based on the RUPTL 2012-21 report exceptSulsel Baru 2 power plant.
-
Assumptions in the System Study
System demand and load model System demand for the year 2015 & 2019 included in
RUPTL document are used in the study Loads are modeled as constant power type i.e.,
demand would be independent of voltage variation.
-
Assumptions in the System Study
Wind Farm Sites For the steady state analysis, simple modeling of
wind farm sites is considered and for the impactanalysis, wind farm collector system on 33kV voltagelevel is not modeled. Power is injected at 1 pf
Sidrap WPP Sidrap PLN S/S 150kV line isassumed to be 15km
100% capacity factor is considered for maximumwind generation
-
Assumptions in the System Study
Load Generation Balance Hydro machines are scheduled to accommodate the
variations in wind generation Minimum system demand scenario (2019), 1 unit of
thermal generator from Jeneponto expansion,Punagaya & Sulsel power plants are kept off
-
Assumptions in the System Study
Load Flow Analysis N-1 contingency refers to transmission line outage.
Generation & transformer outage is not considered inthe study.
Steady state analysis has been examined byconsidering the loadability and voltage profile limitsas per the Sulawesi grid code.
10% voltage profile limits for various bus voltage areconsidered as indicated in Sulawesi grid code.
-
Load Generation Balance Scenario WPP Profile
-
Typical wind generation variation over a day -projection
38
0
10
20
30
40
50
60
70
0
:
0
0
:
0
0
0
:
3
0
:
0
0
1
:
0
0
:
0
0
1
:
3
0
:
0
0
2
:
0
0
:
0
0
2
:
3
0
:
0
0
3
:
0
0
:
0
0
3
:
3
0
:
0
0
4
:
0
0
:
0
0
4
:
3
0
:
0
0
5
:
0
0
:
0
0
5
:
3
0
:
0
0
6
:
0
0
:
0
0
6
:
3
0
:
0
0
7
:
0
0
:
0
0
7
:
3
0
:
0
0
8
:
0
0
:
0
0
8
:
3
0
:
0
0
9
:
0
0
:
0
0
9
:
3
0
:
0
0
1
0
:
0
0
:
0
0
1
0
:
3
0
:
0
0
1
1
:
0
0
:
0
0
1
1
:
3
0
:
0
0
1
2
:
0
0
:
0
0
1
2
:
3
0
:
0
0
1
3
:
0
0
:
0
0
1
3
:
3
0
:
0
0
1
4
:
0
0
:
0
0
1
4
:
3
0
:
0
0
1
5
:
0
0
:
0
0
1
5
:
3
0
:
0
0
1
6
:
0
0
:
0
0
1
6
:
3
0
:
0
0
1
7
:
0
0
:
0
0
1
7
:
3
0
:
0
0
1
8
:
0
0
:
0
0
1
8
:
3
0
:
0
0
1
9
:
0
0
:
0
0
1
9
:
3
0
:
0
0
2
0
:
0
0
:
0
0
2
0
:
3
0
:
0
0
2
1
:
0
0
:
0
0
2
1
:
3
0
:
0
0
2
2
:
0
0
:
0
0
2
2
:
3
0
:
0
0
2
3
:
0
0
:
0
0
2
3
:
3
0
:
0
0
W
i
n
d
g
e
n
e
r
a
t
i
o
n
Time in hour
-
Load Generation Balance Scenario Max. Load Profile
Load profile of Sulselrabar for the year 2012 & 2013
-
Load Generation Balance Scenario Load Duration Curve
Load duration curve of Sulselrabar for the year 2012
0
100
200
300
400
500
600
700
800
1
2
1
1
4
2
1
6
3
1
8
4
1
1
0
5
1
1
2
6
1
1
4
7
1
1
6
8
1
1
8
9
1
2
1
0
1
2
3
1
1
2
5
2
1
2
7
3
1
2
9
4
1
3
1
5
1
3
3
6
1
3
5
7
1
3
7
8
1
3
9
9
1
4
2
0
1
4
4
1
1
4
6
2
1
4
8
3
1
5
0
4
1
5
2
5
1
5
4
6
1
5
6
7
1
5
8
8
1
6
0
9
1
6
3
0
1
6
5
1
1
6
7
2
1
6
9
3
1
7
1
4
1
7
3
5
1
7
5
6
1
7
7
7
1
7
9
8
1
8
1
9
1
8
4
0
1
8
6
1
1
L
o
a
d
i
n
M
W
Various instants of the year
Load duration curve of Sulselrabar for the year 2012
-
System demand variation during a typical day of maximum wind generation
41
-
Fuel Mix
Fuel Mix for 2012 Condition Fuel Mix for 2013 Condition
-
MiPower Load Flow Models and Scenarios
Stage-1: Year 2015 Sulawesi transmission system, with total 70MW wind farm capacity (with Sidrap site)
Stage-2: Year 2019 Sulawesi transmission system, with total 197.3MW wind farm capacity(all three sites)
-
Inter Province Network Connections in 2015
-
Inter Province Network Connections in 2019
-
Cases Considered for Load Flow AnalysisDemand scenario
Time
period in
a day
Wind generationDescription
Year
2015
Year
2019
Maximum system demand during
the month of December in MW1300 2266
18:00 hrs
to 21.00
hrs
Maximum wind generation - 100%
Minimum wind generation - 3%
Average wind generation - 29%
Minimum system demand during the
months of January & February in
MW
607 1029
3:00hrs
to
5:00hrs
Maximum wind generation -100%
Minimum wind generation - 1%
Average wind generation - 77%
Average system demand -
throughout the year in MW870 1560
9:00 hrs
to 11:00
hrs
Maximum wind generation - 100%
Minimum wind generation - 3%
Average wind generation -39%
-
Demand Profile
Sl. No. Province name
2015 network condition - demand 2019 network condition - demand
Maximum
(MW)
Minimum
(MW)
Average
(MW)
Maximum
(MW)
Minimum
(MW)
Average
(MW)
1 South Sulawesi 914 384 585 1303 547 834
2 West Sulawesi 54 23 35 91 38 58
3 Central Sulawesi 150 63 96 274 115 175
4 Southeast Sulawesi - - - 217 91 139
A Sub-Total* 1119 470 716 1885 792 1206
Big industrial loads in South
Sulawesi
1 Tonasa 39 16 25 39 16 25
2 Barwaja 5 2 3 5 2 3
3 Bosowa 32 13 20 32 13 20
4 Keera LNG Plant 105 105 105 105 105 105
5Banteang smelter
plant- - - 200 100 200
B Sub-total* 181 137 154 381 237 354
Total (A+B) 1300 607 870 2266 1029 1560
-
Generation Schedule 2015 Condition
-
Fuel Mix for 2015 Condition
-
Generation Schedule 2019 Condition
-
Fuel Mix for 2019 Condition
-
Load Flow Study List of Cases
-
Results of Load Flow Study Stage 1 (2015)
-
Results of Load Flow Study Stage 2 (2019)
-
Inference- Load Flow Study (2015) With Sidrap 70MW wind integration in 2015 system voltages and line
loadings are within acceptable limits The system voltages and loading are acceptable during N-1 contingency
scenario In 2015 maximum wind penetration is 5.4% during maximum demand
condition and 11.5% during minimum demand condition Import of power from Central Sulawesi to South Sulawesi reduces from
76MW in Scenario -2 (minimum wind generation & maximum demand) to32MW in Scenario-1 (maximum wind generation & system demand).
To have the load generation balance during varying wind generation frommaximum to minimum, reserve capacity is accommodated through2x63MW Bakaru & 3x65MW Poso hydro generations
-
Inference- Load Flow Study (2019) With Jeneponto wind farms integrated in 2019 the system voltages & line loadinggs are
within acceptable limits The system voltages and loading are acceptable during N-1 contingency scenario In 2019 maximum wind penetration is 8.7% during maximum demand condition and
19.1% during minimum demand condition Import of power from Central Sulawesi to South Sulawesi reduces from 112MW in
Scenario -2 (minimum wind generation & maximum demand) to 78MW in Scenario-1(maximum wind generation & system demand). Also import of power from West Sulawesito South Sulawesi reduces from 316MW in Scenario -2 to 220MW in Scenario-1
To have the load generation balance during varying wind generation from maximum tominimum, reserve capacity is accommodated through 2x63MW Bakaru, 3x65MW Poso,3x150MW Karama, 2x55MW Bontobatu, 2x45MW Malea hydro generations
-
Discussions ???
57
-
For further information please contact:Office Address of ICED-USAID
(Indonesia Clean Energy Development United States Agency for International Development) ICED-USAID Jakarta Office: Tifa Building, 5th Floor, Jl. Kuningan Barat No. 26 Jakarta 12710;
Phone/Facsimile: +62 21 52964445/ 52964446 ICED-USAID Medan Office: Jl. Tengku Daud No. 7A Medan 20152;
Phone/Facsimile: +62 61 4519675/ 4519058 Contact Person:
Dr. Pramod Jain.President, Innovative Wind Energy, Inc.
[email protected]. Balaraman K.
CGM, [email protected] 58