in the world trade organization panel proceedings · 2019-04-29 · in the world trade organization...
TRANSCRIPT
In the World Trade Organization
Panel Proceedings
EUROPEAN UNION AND ITS MEMBER STATES – CERTAIN
MEASURES RELATING TO THE ENERGY SECTOR
(DS476)
Second Written Submission
by the European Union
Non-Confidential Version
Geneva, 21 November 2016
EU and its Member States – Energy Package Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- i -
TABLE OF CONTENTS
1. INTRODUCTION ....................................................................................................... 1
2. UNBUNDLING .......................................................................................................... 1
2.1. Claim VII: Russia's claim that the implementation of the unbundling
requirement in the domestic laws of Croatia, Hungary and Lithuania
violates the commitments under Article XVI of the GATS in respect of
these countries (Russia's claims 1 to 3) ............................................................. 1
2.1.1. Introduction ......................................................................................... 2
2.1.2. EU's response to Russia's arguments that the unbundling
requirement would violate Article XVI of the GATS ......................... 2
2.1.2.1 Sub-paragraph (e) (Russia's Claim 1) .................................. 2
2.1.2.2 Sub-paragraph (a) (Russia's Claim 2) .................................. 7
2.1.2.3 Sub-paragraph (f) (Russia's Claim 3) .................................. 8
2.1.3. EU's response to Russia's arguments that the unbundling
requirement is not justified under Articles XIV(a) or (c) .................. 10
2.1.3.1 Article XIV(a) of the GATS .............................................. 10
COMPETITION IN THE ENERGY SECTOR IS A FUNDAMENTAL 2.1.3.1.1
INTEREST OF EU SOCIETY .......................................................................................... 10
NO ALTERNATIVE MEASURES ARE REASONABLY 2.1.3.1.2
AVAILABLE TO ACHIEVE THE OBJECTIVE ............................................................ 11
THE UNBUNDLING REQUIREMENT MEETS THE CONDITIONS 2.1.3.1.3
OF THE CHAPEAU OF ARTICLE XIV ......................................................................... 14
2.1.3.2 Article XIV(c) of the GATS .............................................. 15
2.2. Claim VIII: The public body specification in Article 9(6) of Directive
2009/73 violates neither de jure nor de facto the national treatment
obligation in Article XVII of the GATS (Russia's Claims 4 and 5) ................ 16
2.2.1. Introduction ....................................................................................... 16
2.2.2. Article 9(6) is not de jure discriminatory .......................................... 17
2.2.3. Article 9(6) is not de facto discriminatory ........................................ 18
2.3. Claim IX: The unbundling measure does not violate the most favoured
nation obligation in Article II:1 of the GATS (Russia's claim 6) .................... 21
2.3.1. Introduction ....................................................................................... 21
2.3.2. The treatment service suppliers receive must be assessed in
each EU Member State individually .................................................. 22
2.3.3. The imposition of the OU model does not alter the competitive
position of pipeline transport service suppliers ................................. 25
2.3.4. Russia cannot demonstrate that the alleged negative
competitive impact of OU (quod non) is predominantly on
Russian service suppliers ................................................................... 27
2.3.4.1 Russia asks the Panel to disregard 15 years of WTO
jurisprudence ..................................................................... 27
EU and its Member States – Energy Package Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- ii -
2.3.4.2 Russia cannot demonstrate that any alleged
detrimental impact of the unbundling requirement
(quod non) is predominantly on the group of pipeline
transmission service suppliers from Russia ....................... 28
2.3.4.3 Russia's "evidence" on the implementation of the
unbundling requirement in the Member States is
critically flawed. ................................................................ 29
2.4. Claim X: Russia's claim under Article III:4 of the GATT 1994 (Russia's
claim 8) ............................................................................................................ 31
2.4.1. Introduction ....................................................................................... 31
2.4.2. The treatment of gas of different origins must be assessed in
each EU Member State individually .................................................. 32
2.4.3. Russia cannot show that a particular unbundling model
translates into a competitive disadvantage for gas of a certain
origin .................................................................................................. 33
2.4.4. The alleged negative competitive impact of the unbundling
requirement (quod non) is not predominantly on the group of
Russian gas ........................................................................................ 36
2.4.4.1 Russia's argument disregards established WTO
jurisprudence and ignores the essence of unbundling ....... 36
2.4.4.2 Abundant evidence shows the absence of a link
between the unbundling model and the volume of
Russian imports ................................................................. 38
2.4.4.3 Russia's "evidence" allegedly linking an unbundling
model to gas volumes is critically flawed ......................... 39
THERE IS NO LINK BETWEEN THE UNBUNDLING MODEL 2.4.4.3.1
AND RUSSIAN GAS IMPORTS ..................................................................................... 39
THERE IS NO LINK BETWEEN THE UNBUNDLING MODEL 2.4.4.3.2
AND EU-PRODUCED GAS VOLUMES ........................................................................ 41
THERE IS NO LINK BETWEEN THE UNBUNDLING MODEL 2.4.4.3.3
AND GAS VOLUMES IMPORTED FROM OTHER THIRD COUNTRIES ................ 43
2.5. Claim XI: Russia's claim under Article I:1 of the GATT 1994 (Russia's
claim 10) .......................................................................................................... 47
2.6. Claim XII: Russia's claim of violation of Article I:1 of the GATT 1994
because the Directive would accord natural gas of other third countries
imported through LNG facilities and upstream pipeline networks an
advantage not extended to Russian Gas (Russia's Claims 12 and 13) ............. 47
2.6.1. Introduction ....................................................................................... 47
2.6.2. The LNG measure does not violate Article I:1 of the GATT
1994 (Russia's claim 12) .................................................................... 48
2.6.2.1 LNG and natural gas are not "like" ................................... 49
2.6.2.2 Russia cannot demonstrate that the LNG measure
alters the competitive position of gas imported from
Russia ................................................................................ 50
EU and its Member States – Energy Package Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- iii -
2.6.3. The upstream pipeline networks measure does not violate
Article I:1 of the GATT 1994 (Russia's claim 13) ............................ 52
2.6.3.1 Upstream pipeline networks have a different nature
and role than transmission pipelines.................................. 52
2.6.3.2 Russia errs when claiming that Russian pipelines
would never be eligible to qualify as upstream
pipeline networks .............................................................. 55
THE LEGISLATIVE HISTORY CONTRADICTS RUSSIA'S 2.6.3.2.1
ALLEGATION THAT THE "UPSTREAM PIPELINES NETWORKS"
DEFINITION IS "TAILORED TO APPLY SOLELY TO NORWEGIAN
PIPELINES" ...................................................................................................................... 55
SEVERAL FACTS CONTRADICT RUSSIA'S ALLEGATION THAT 2.6.3.2.2
THE UPSTREAM PIPELINE NETWORKS DEFINITION WILL NEVER BE
AVAILABLE FOR RUSSIAN PIPELINES ..................................................................... 57
2.6.3.3 Russia cannot demonstrate that gas carried through
an upstream pipeline network has a competitive
advantage over gas carried through a transmission
pipeline .............................................................................. 59
2.7. Claim XIII: Russia's claim of violation of Article III:4 of the GATT
1994 because the Directive would accord Russian gas treatment less
favourable than like domestic gas transported via upstream pipeline
networks (Russia's claim 14) ........................................................................... 61
3. THIRD COUNTRY CERTIFICATION ................................................................... 61
3.1. Claim XIV: Article XVII GATS (Russia's Claim 15) ..................................... 61
3.1.1. The policy objective pursued by the SoS certification
requirement falls within the scope of Article XIV (a) GATS ........... 62
3.1.1.1 SoS is a "fundamental interest" of the EU society, as
reflected in EU's law and policies ..................................... 62
3.1.1.2 TSOs controlled by persons of third countries pose a
genuine and sufficiently serious threat to SoS in the
EU ...................................................................................... 64
3.1.2. The SoS certification requirement is necessary to achieve its
policy objective ................................................................................. 68
3.1.2.1 Relative importance of the objective ................................. 68
3.1.2.2 Contribution to the objective ............................................. 68
3.1.2.3 Restrictiveness of the measure .......................................... 69
3.1.2.4 Alternative measures ......................................................... 69
3.1.3. The SoS certification requirement is applied in conformity
with the requirements of the chapeau ............................................... 72
3.2. Claims under Article XVII GATS concerning other requirements
imposed by Hungary and Lithuania (Included in Russia's Claim 15) ............. 73
3.3. Claim XV: Article II:1 GATS (Russia's Claims 16 and 17) ........................... 74
3.3.1. The de jure claim ............................................................................... 74
EU and its Member States – Energy Package Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- iv -
3.3.2. The de facto claim ............................................................................. 74
3.3.2.1 Terms of reference ............................................................. 74
3.3.2.2 Europolgaz is not a service supplier - Gaz-System is
not a Russian service supplier ........................................... 75
3.3.2.3 Legal status of the Commission opinions .......................... 76
3.3.2.4 Article 54 of the Gas Directive .......................................... 77
3.3.2.5 The delays in the certification of Gaz-System do not
affect conditions of competition to its detriment ............... 80
3.3.2.6 Press release of the European Parliament's press
service on the occasion of the adoption of the TEP .......... 82
3.4. Claim XVI: Article III:4 GATT (Russia's Claim 18) ...................................... 82
3.5. Claim XVII: Article VI:1 GATS (Russia's claim 19) ..................................... 83
3.6. Claim XVII bis: Article VI:5 GATS (Russia's claim 20) ................................ 84
3.6.1. Relationship between Articles VI:4 and VI:5 GATS and
Article XVII GATS ........................................................................... 84
3.6.2. Letter (b) of Article VI:4 GATS ........................................................ 84
3.6.3. Letter (c) of Article VI:4 GATS ........................................................ 86
4. INFRASTRUCTURE EXEMPTIONS ..................................................................... 87
4.1. Introduction ..................................................................................................... 87
4.2. The exemption for new major infrastructure ................................................... 88
4.3. Claim XVIII: Russia’s claim under Article X:3(a) of the GATT 1994
(Russia's claim 21) ........................................................................................... 89
4.4. Claim XIX: Russia’s claim under Article I:1 of the GATT 1994
(Russia’s claim 22) .......................................................................................... 96
4.5. Claim XIX: Russia’s claim under Article I:1 of the GATT 1994
(Russia’s claim 23) .......................................................................................... 99
4.6. Claim XIX: Russia’s claim under Article I:1 of the GATT 1994
(Russia’s claim 24) ........................................................................................ 101
4.7. Claim XX: Russia’s claim under Article II:1 of the GATS (Russia’s
claim 25) ........................................................................................................ 101
4.8. Claim XXI: Russia’s claim under Article I:1 of the GATT 1994 in
respect of upstream pipeline networks (Russia’s claim 26) .......................... 103
4.9. Claim XXII: Russia’s claim under Article II:1 of the GATS in respect
of upstream pipeline networks (Russia’s 27) ................................................ 104
4.10. Claim XXIII: Russia’s claim under Article XI:1 of the GATT 1994
(Russia’s claim 28) ........................................................................................ 104
5. PROJECTS OF COMMON INTEREST ................................................................ 108
5.1. Meaning of "Russian project" ....................................................................... 108
5.2. Claim XXIV: Article II:1 GATS (Russia's Claim 29)................................... 110
5.2.1. De iure claim ................................................................................... 110
5.2.2. De facto claim .................................................................................. 111
5.2.3. The [[ ]] project ............................................................................... 112
EU and its Member States – Energy Package Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- v -
5.3. Claims XXV and XXVI: Article III:4 GATT and Article I:1 GATT
(Russia's claims 30 and 31) ........................................................................... 115
5.3.1. De iure claims .................................................................................. 115
5.3.2. De facto claims ................................................................................ 117
5.3.3. In the alternative, the TEN – E measure is justified under
Article XX j) GATT ........................................................................ 119
5.3.3.1 Introduction ..................................................................... 119
5.3.3.2 Legal standard ................................................................. 120
THE "FIRST TIER" ...................................................................................... 120 5.3.3.2.1
THE "SECOND TIER" ................................................................................. 123 5.3.3.2.2
BURDEN OF PROOF ................................................................................... 124 5.3.3.2.3
5.3.3.3 Gas is a product in "short supply" in the European
Union ............................................................................... 124
5.3.3.4 The TEN-E measure is essential for the acquisition
and distribution of gas ..................................................... 127
RELATIVE IMPORTANCE OF THE OBJECTIVE ................................... 127 5.3.3.4.1
CONTRIBUTION TO THE OBJECTIVE .................................................... 127 5.3.3.4.2
TRADE - RESTRICTIVENESS OF THE MEASURE ................................ 128 5.3.3.4.3
ALTERNATIVE MEASURES ..................................................................... 129 5.3.3.4.4
5.3.3.5 The TEN – E measure is consistent with the
principle that all Members are entitled to an
equitable share of the international supply of gas ........... 129
5.3.3.6 The aspects of the TEN – E measure challenged by
Russia are temporary in nature ........................................ 129
5.3.3.7 The TEN – E measure is applied consistently with
the chapeau of Article XX GATT ................................... 130
6. CONCLUSION ....................................................................................................... 130
EU and its Member States – Energy Package Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- vi -
TABLE OF CASES CITED
Short Title Full Case Title and Citation
Argentina – Financial Services Panel Report, Argentina – Measures Relating to Trade in Goods and Services, WT/DS453/R and
Add.1, adopted 9 May 2016, as modified by Appellate Body Report WT/DS453/AB/R
Argentina – Financial Services Appellate Body Report, Argentina – Measures Relating to Trade in Goods and Services,
WT/DS453/AB/R and Add.1, adopted 9 May 2016
Brazil – Retreaded Tyres Appellate Body Report, Brazil – Measures Affecting Imports of Retreaded Tyres, WT/DS332/AB/R,
adopted 17 December 2007, DSR 2007:IV, p. 1527
Chile – Alcoholic Beverages Appellate Body Report, Chile – Taxes on Alcoholic Beverages, WT/DS87/AB/R, WT/DS110/AB/R,
adopted 12 January 2000, DSR 2000:I, p. 281
China – Electronic Payment Services Panel Report, China – Certain Measures Affecting Electronic Payment Services, WT/DS413/R and
Add.1, adopted 31 August 2012, DSR 2012:X, p. 5305
China – Publications and Audiovisual
Products
Panel Report, China – Measures Affecting Trading Rights and Distribution Services for Certain
Publications and Audiovisual Entertainment Products, WT/DS363/R and Corr.1, adopted 19
January 2010, as modified by Appellate Body Report WT/DS363/AB/R, DSR 2010:II, p. 261
China – Publications and Audiovisual
Products Appellate Body Report, China – Measures Affecting Trading Rights and Distribution Services for
Certain Publications and Audiovisual Entertainment Products, WT/DS363/AB/R, adopted 19
January 2010, DSR 2010:I, p. 3
Colombia – Ports of Entry Panel Report, Colombia – Indicative Prices and Restrictions on Ports of Entry, WT/DS366/R and
Corr.1, adopted 20 May 2009, DSR 2009:VI, p. 2535
Dominican Republic – Import and
Sale of Cigarettes Appellate Body Report, Dominican Republic – Measures Affecting the Importation and Internal
Sale of Cigarettes, WT/DS302/AB/R, adopted 19 May 2005, DSR 2005:XV, p. 7367
EC – Asbestos Appellate Body Report, European Communities – Measures Affecting Asbestos and Asbestos-
Containing Products, WT/DS135/AB/R, adopted 5 April 2001, DSR 2001:VII, p. 3243
EC – Computer Equipment Appellate Body Report, European Communities – Customs Classification of Certain Computer
Equipment, WT/DS62/AB/R, WT/DS67/AB/R, WT/DS68/AB/R, adopted 22 June 1998, DSR
1998:V, p. 1851
EC – Seal Products Appellate Body Reports, European Communities – Measures Prohibiting the Importation and
Marketing of Seal Products, WT/DS400/AB/R / WT/DS401/AB/R, adopted 18 June 2014, DSR
2014:I, p. 7
EC – Seal Products Appellate Body Reports, European Communities – Measures Prohibiting the Importation and
Marketing of Seal Products, WT/DS400/AB/R / WT/DS401/AB/R, adopted 18 June 2014, DSR
2014:I, p. 7
EC – Selected Customs Matters Appellate Body Report, European Communities – Selected Customs Matters, WT/DS315/AB/R,
adopted 11 December 2006, DSR 2006:IX, p. 3791
India – Solar Cells Appellate Body Report, India – Certain Measures Relating to Solar Cells and Solar Modules,
WT/DS456/AB/R and Add.1, circulated to WTO Members 16 September 2016 [adoption pending]
Korea – Various Measures on Beef Appellate Body Report, Korea – Measures Affecting Imports of Fresh, Chilled and Frozen Beef,
WT/DS161/AB/R, WT/DS169/AB/R, adopted 10 January 2001, DSR 2001:I, p. 5
Philippines – Distilled Spirits Appellate Body Reports, Philippines – Taxes on Distilled Spirits, WT/DS396/AB/R /
WT/DS403/AB/R, adopted 20 January 2012, DSR 2012:VIII, p. 4163
Thailand – Cigarettes (Philippines) Appellate Body Report, Thailand – Customs and Fiscal Measures on Cigarettes from the
Philippines, WT/DS371/AB/R, adopted 15 July 2011, DSR 2011:IV, p. 2203
US – Clove Cigarettes Appellate Body Report, United States – Measures Affecting the Production and Sale of Clove
Cigarettes, WT/DS406/AB/R, adopted 24 April 2012, DSR 2012: XI, p. 5751
US – Gambling Panel Report, United States – Measures Affecting the Cross-Border Supply of Gambling and Betting
Services, WT/DS285/R, adopted 20 April 2005, as modified by Appellate Body Report
WT/DS285/AB/R, DSR 2005:XII, p. 5797
US – Gambling Appellate Body Report, United States – Measures Affecting the Cross-Border Supply of Gambling
and Betting Services, WT/DS285/AB/R, adopted 20 April 2005, DSR 2005:XII, p. 5663 (and
Corr.1, DSR 2006:XII, p. 5475)
US – Gasoline Appellate Body Report, United States – Standards for Reformulated and Conventional Gasoline,
WT/DS2/AB/R, adopted 20 May 1996, DSR 1996:I, p. 3
US – Lamb Appellate Body Report, United States – Safeguard Measures on Imports of Fresh, Chilled or Frozen
Lamb Meat from New Zealand and Australia, WT/DS177/AB/R, WT/DS178/AB/R, adopted 16
May 2001, DSR 2001:IX, p. 4051
US – Tuna II (Mexico) Appellate Body Report, United States – Measures Concerning the Importation, Marketing and Sale
of Tuna and Tuna Products, WT/DS381/AB/R, adopted 13 June 2012, DSR 2012:IV, p. 1837
EU and its Member States – Energy Package Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- vii -
LIST OF ABBREVIATIONS
Abbreviation Full Name
AEEG Regulatory Authority for Electricity Gas and Water (Italy)
BEMIP Baltic Energy Market Interconnection Plan
BNetzA Bundesnetzagentur (German NRA)
BOTAS Boru Hatlari ile Petrol Tasima AS
CEF Connecting Europe Facility
Commission European Commission
CRE Commission de régulation de l'énergie (French NRA)
DESFA Hellenic Gas Transmission System Operator S.A.
ENTSO European Network of Transmission System Operators for Gas
ERO Energy Regulatory Office (Polish NRA)
EU European Union
Europolgaz EuRoPol Gaz S.A.
GASCADE GASCADE Gastransport GmbH
GATS General Agreement on Trade in Services
GATT 1994 General Agreement on Tariffs and Trade 1994
Gaz-System Gazociągów Przesyłowych Gaz-System Spółka Akcyjna
HHI Herfindahl-Hirschman Index
IEA International Energy Agency
IGA Intergovernmental Agreement
ISO Independent System Operator
ITO Independent Transmission Operator
jordgas Jordgas Transport GmbH
LNG Liquefied natural gas
LSO LNG System Operator
MEP Member of the European Parliament
EU and its Member States – Energy Package Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- viii -
Abbreviation Full Name
MFN Most Favoured Nation
Nabucco NABUCCO Gas Pipeline International GmbH
NEL Nordeuropaische Erdgas-Leitung
NRA National Regulatory Authority
NSI North-South Interconnections in Central-East and South-East Europe
ONTRAS ONTRAS Gastransport GmbH
OPAL Ostsee-Pipeline-Anbindungs-Leitung – Baltic Sea Pipeline Link
OU model Ownership Unbundling model
PCI Project of Common Interest
RAE Regulatory Authority for Energy (Greece)
Russia Russian Federation
SOCAR State Oil Company of the Azerbaijan Republic
SoS Security of supply
TAP Trans Adriatic Pipeline AG
TEN-E Trans-European Energy Networks
TEU Treaty on European Union
TFEU Treaty on the Functioning of the European Union
TIGF Transport et Infrastructures Gaz France
TPA Third party access
TSO Transmission system operator
UGS Underground Gas Storage
UK United Kingdom of Great Britain and Northern Ireland
UPN Upstream Pipeline Network
VIU Vertically Integrated Undertaking
VNG Verbundnetz Gas AG
WTO World Trade Organization
EU and its Member States – Energy Package Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- ix -
TABLE OF EXHIBITS
Exhibit No. Title
EU-102 Schematic overview of unbundling models in Directive 2009/73/EC
EU-103 Case COMP/M.6111– Huaneng/OTPPB/Intergen, decision of 11 February 2011
EU-104 Case COMP/M.6082 – China National Bluestar/Elkem, decision of 31 March 2011
EU-105 Case COMP/M.6151 – Petrochina/Ineos/JV, decision of 13 May 2011
EU-106 Case COMP/M.6113 – DSM/Sinochem/JV, decision of 19 May 2011
EU-107 Case COMP/M.6141 – China National Agrochemical Corporation/Koor
Industries/Makhteshim Agan Industries, decision of 3 October 2011
EU-108 Russian Gas Imports in the EU (all Member States) 2009-2014, Eurostat
EU-109 Russian Gas Imports in Germany
EU-110 Shareholdings in TSOs in the EU (BCI)
EU-111 Country Factsheet Belgium
EU-112 Country Factsheet Denmark
EU-113 Country Factsheet Sweden
EU-114 Country Factsheet The Netherlands
EU-115
Gazprom's supplies to Germany climb 20.4 per cent in October,
http://www.gazprom.com/press/news/2016/november/article290994/, Boosting
Supplies, http://www.gazprom.com/press/reports/2016/increases-delivery/
EU-116 Gas imports in the EU – all external suppliers 2009-2014, Eurostat
EU-117 Overview of cross border point capacity, ENTSO-G
EU-118 EU Member States' gas production 2005-2014, Eurostat
EU-119 International Energy Agency, Germany,
http://www.iea.org/publications/freepublications/publication/germanyoss.pdf
EU-120
International Energy Agency, Energy Policies of IEA Countries. The Netherlands.
2014 Review,
http://www.iea.org/publications/freepublications/publication/Netherlands2014.pdf
EU-121 Norwegian gas imports in the EU in 2014 - all Member States, Eurostat
EU-122
EU Staff working paper SWD(2016)23,
https://ec.europa.eu/energy/sites/ener/files/documents/1_EN_autre_document_travail_
service_part1_v3.pdf
EU and its Member States – Energy Package Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- x -
Exhibit No. Title
EU-123
Capacities available at certain LNG terminals: Montoir (owned by Elengy, a
subsidiary of Engie),
https://www.elengy.com/images/contenu/contratsetoperations/capacitesprimaires/ELE
NGY_publications_Montoir_2016_11_10.pdf
EU-124
Capacities available at certain LNG terminals: Fos-Tonkin,
https://www.elengy.com/images/contenu/contratsetoperations/capacitesprimaires/ELE
NGY_publications_FosTonkin_2016_11_10.pdf
EU-125
Elengy signs a transshipment long-term contract with Novatek Gas & Power, press
release, https://www.elengy.com/en/news/news/commercial/150-elengy-signs-a-
transshipment-long-term-contract-with-novatek-gas-power.html
EU-126 Basics of Russian Gas Market Regulations,
http://www.fief.ru/img/files/5_Basic_of_RU_Gas_Market_Regulations.pdf
EU-127 Commission proposal for the First Gas Directive (Directive 98/30/EC), Brussels,
21.02. 1992
EU-128 Drafting history of the First Gas Directive (Directive 98/30/EC) (BCI)
EU-129
Directive 94/22/EC of the European Parliament and of the Council of 30 May 1994 on
the conditions for granting and using authorizations for the prospection, exploration
and production of hydrocarbons. Brussels 30.5.94, L164/3
EU-130
The Norwegian Gas Transportation System, Statoil 2012,
http://www.statoil.com/AnnualReport2012/en/OurOperations/BusinessAreas/Marketin
gProcessingAndRenewableEnergy/NaturalGas/Pages/TheNorwegianGasTransportatio
nSystem.aspx
EU-131
Decree of the President of the Russian Federation No 1285 of 11 September 2012 on
measures to protect the interests of the Russian Federation in the performance of
foreign economic activity by Russian legal persons and implementing measures
EU-132
Commission Opinion of 26 March 2013 pursuant to Article 3(1) of Regulation (EC)
No 715/2009 and Article 10(6) of Directive 2009/73/EC – United Kingdom –
Certification of Interconnector UK Limited
EU-133
Press release: European Network of Transmission System Operators for Gas
(ENTSOG) publishes an addendum to the Annex A of the Ten Year Network
Development Plan 2015, 29 June 2015,
http://www.entsog.eu/public/uploads/files/publications/Press%20Releases/2015/PR00
90-15_150629_Press%20Release_TYNDP2015_Addendum.pdf
EU-134 Guide for Applicants issued by the Innovations and Networks Executive Agency. Call
for proposals CEF-Eenergy-2016-2. June 2016
EU-135 List of actions selected for receiving assistance under the first CEF Energy 2015 call
for proposals
EU-136
"Is Europe's gas supply threatened by the Ukraine crisis?" Jon Henley, The Guardian,
03.03.2014 https://www.theguardian.com/world/2014/mar/03/europes-gas-supply-
ukraine-crisis-russsia-pipelin
EU and its Member States – Energy Package Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- xi -
Exhibit No. Title
EU-137
The Russian-Ukrainian gas crisis of January 2006, Jonathan Stern, Oxford Institute
for Energy Studies, 16.01.2006, p. 9. https://www.oxfordenergy.org/wpcms/wp-
content/uploads/2011/01/Jan2006-RussiaUkraineGasCrisis-JonathanStern.pdf
EU-138 "Russia vows to end gas shortage" in BBC News, 02.01.2006.
http://news.bbc.co.uk/2/hi/europe/4574630.stm
EU-139
Ukrainian gas dispute of January 2009: a comprehensive assessment, Oxford Institute
for Energy Studies, February 2009, p. 22,
http://citeseerx.ist.psu.edu/viewdoc/download?doi=10.1.1.443.8094&rep=rep1&type=
pdf.
EU-140 Press Release: "Member State general situation according the significance of impact",
European Commission, 09.01.2009
EU-141
The Impact of the Russia–Ukraine Gas Crisis in South Eastern Europe, Aleksandar
Kovacevic, Oxford Institute for Energy Studies, March 2009, pp. 11-12,
https://www.oxfordenergy.org/wpcms/wp-content/uploads/2010/11/NG29-
TheImpactoftheRussiaUkrainianCrisisinSouthEasternEurope-AleksandarKovacevic-
2009.pdf
EU-142 Import statistics for the period 2005-2015, Eurostat and IEA
EU-143 Commission’s comments to the Gate Terminal exemption decision. Exemption
decision No. G/2006/01. Brussels 26.03.2007
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 1 -
1. INTRODUCTION
1. In this dispute, the Russian Federation ("Russia") challenges as allegedly WTO-
inconsistent several aspects of the European Union's Third Energy Package. As
explained by the European Union, this Package has as objective to create a well-
interconnected and competitive European Union gas market, based on free market
and free competition principles.1 The fundamental question that the Panel has to
answer in this dispute is whether the WTO obligations prohibit a WTO Member to
take measures to avoid that a monopoly distorts free and fair competition in the
market and restricts competitors from having access to the market. The European
Union finds it hard to believe that this would be the result, let alone the intention,
of the WTO obligations.
2. In this second written submission, the EU responds in detail to all arguments raised
by Russia in Russia's oral statements at the panel hearing on 5 and 6 September
2016 as well as in its responses to the Panel's questions of 12 October 2016.
3. This submission consists of four main sections, dealing with unbundling (Section
2), third country certification (Section 3), infrastructure exemptions (Section 4),
and the TEN – E measure (Section 5). The European Union has maintained the
structure it relied upon in its first written submission because it believes this
structure corresponds to the claims included in Russia's Panel Request. The
European Union recalls that Russia has sought to expand the number of claims in
its responses of 12 October 2016. In the cases where the Panel has considered that
these claims are within its terms of reference,2 the European Union has also
labelled these claims with the number Russia used in its response to Panel
Question 5.
2. UNBUNDLING
2.1. CLAIM VII: RUSSIA'S CLAIM THAT THE IMPLEMENTATION OF THE UNBUNDLING
REQUIREMENT IN THE DOMESTIC LAWS OF CROATIA, HUNGARY AND LITHUANIA
VIOLATES THE COMMITMENTS UNDER ARTICLE XVI OF THE GATS IN RESPECT OF THESE
COUNTRIES (RUSSIA'S CLAIMS 1 TO 3)
1 Commission Communication on an Energy Policy for Europe (Exhibit EU - 14), p. 6; EU's first
written submission, paras. 14-33.
2 See Preliminary Ruling by the Panel of 10 November 2016.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 2 -
2.1.1. Introduction
4. Russia first argues that the unbundling requirement, as implemented in the laws of
Croatia, Hungary and Lithuania, is inconsistent with the EU's market access
commitments for "pipeline transmission services" under paragraphs (e), (a) and (f)
Article XVI:2 of the GATS in respect of these countries.
5. However, Russia's interpretation of the market access obligation in Article
XVI:2(e), (a) and (f) is entirely misguided. The European Union rebuts Russia's
arguments in respect of each of these sub-paragraphs in turn (sub-section 2.1.2)
and then turns to Russia's response to the EU's justification in case the Panel would
find that the unbundling measure in Croatia's, Hungary's and Lithuania's
implementing laws would violate these Members' commitments in respect of
Article XVI of the GATS (sub-section 2.1.3).
2.1.2. EU's response to Russia's arguments that the unbundling
requirement would violate Article XVI of the GATS
2.1.2.1 Sub-paragraph (e) (Russia's Claim 1)
6. Russia's first claim is that the unbundling requirement qualifies as a measure
"which restrict[s] or require[s] specific types of legal entity or joint venture
through which a service supplier may supply a service", prohibited under sub-
paragraph (e) of Article XVI:2 of the GATS, to the extent a commitment was
made. However, the unbundling requirement in Directive 2009/73/EC does not
limit the type of legal entity the service supplier can use.3
7. It specifies only certain characteristics of an undertaking providing pipeline
transport services.4 This unbundling requirement, which aims to eliminate any
conflict of interests between the activities of transmission and the activities of
production and supply, does not in any way determine or limit the type of legal
entity that a service supplier may use to provide pipeline transmission services in
the EU territory. Rather, what is disciplined is the combination of activities –
3 See also Japan's third party written submission, para. 15.
4 See EU's first written submission, paras.106-119; EU's opening statement of 5 September 2016,
paras. 14-15.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 3 -
production/supply and transmission – that cannot be deployed simultaneously.5
Therefore, the unbundling requirement is not a measure of the type specified in
Article XVI:2(e) of the GATS and thus does not violate any of the EU's
commitments under this provision.
8. In Russia's responses to the Panel's questions, Russia seeks to challenge the
European Union's (as well as Japan's6) legal interpretation of sub-paragraph (e) of
Article XVI:2 of the GATS, namely that this provision only prohibits measures
that require specific types of legal entity to be used to provide a service, or that
prohibit the use of a certain type of legal entity. Hence, sub-paragraph (e) does not
cover measures that lay down characteristics of the legal entity.
9. Russia argues for an extremely broad scope of sub-paragraph (e), which would
cover, in Russia's misguided opinion, any measure that somehow would affect the
possibility of a service supplier from one WTO Member to provide services
through commercial presence in a host WTO Member. Russia suggests that sub-
paragraph (e) would cover "other creative measures, including unbundling, that
Members such as the EU have designed in the past two decades to restrict market
access in sectors such as pipeline transport services".7
10. Russia thereby ignores that the unbundling requirement does not limit the market
access for pipeline transport service providers. This requirement only prohibits a
pipeline transport service provider to control at the same time production and/or
supply (i.e. sale) of gas.
11. Moreover, such interpretation ignores the plain words of sub-paragraph (e), which
only covers measures that restrict or require the use of a specific type of legal
entity through which a service supplier may supply a service. It also ignores past
WTO jurisprudence that has stressed the exhaustive nature of the list of measures
5 See also WTO Secretariat note of 31 January 2005, which provides exactly such measures as
examples of measures that do not fall within the scope of Article XVI of the GATS, but rather
within the scope of Article VI:4 of the GATS. Working Party on Domestic Regulation, Examples
of measures to be addressed by Disciplines under GATS Article VI:4. Informal Note by the
Secretariat, Revision, 31 January 2005, JOB(02)/20/Rev.10 (Exhibit EU - 40).
6 See Japan's third party submission, paras. 14-15.
7 Russia's answers of 12 October 2016, para. 380.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 4 -
in Article XVI:2 of the GATS,8 precisely to respect the delicate balance carefully
sought by the drafters of the GATS between the right to regulate and the principle
of trade liberalisation.
12. In its argumentation, Russia incorrectly focuses on vertically integrated
undertakings that would want to provide pipeline transport services in Croatia,
Hungary and Lithuania. However, in case of service supply through mode 3, the
"legal entity" that Article XVI:2(e) is concerned with is the legal entity that is
created in the host territory of the Member States to supply a service.9 It does not
concern the VIU. Japan correctly explains that the term "types of legal entity"
under sub-paragraph (e) of Article XVI:2 of the GATS only concerns the corporate
form of the entity itself through which a service is provided (the commercial
presence), and not the broader structure of the group of companies, or the
assignment of ownership or control.10
Russia explicitly agrees with this
interpretation when it states that "the 'specific types of legal entity' referred to in
sub-paragraph (e) is simply another way to describe different forms of commercial
presence".11
All Russia's arguments, which focus on the VIU rather than the
commercial presence, can thus be dismissed.
13. Other than agreeing with the EU and Japan, Russia makes no further effort to
explain the meaning of "legal entity" in sub-paragraph (e) and thus to identify the
limits of the scope of this sub-paragraph. Rather, Russia merely argues that the
reference to "specific types of legal entity" in sub-paragraph (e) is "broader in
scope than the concept of 'juridical person'".12
Russia seeks to stress that the list of
types of legal entities in Article XXVIII(l) ("corporation, trust, partnership, joint
venture, sole proprietorship or association") is "non-exhaustive".13
While the
European Union never denied that there may be other "legal entities" than the ones
8 See Panel Report, US – Gambling, para. 6.298; Panel Report, China ‒ Publications and Audiovisual
Products, para. 7.1353; Panel Report, China – Electronic Payment Services, para. 7.629; and Panel
Report, Argentina – Financial Services, para. 7.418.
9 See EU's first written submission, para. 112.
10 Japan's third-party submission, para. 15; EU's answers of 12 October 2016, paras. 222-223.
11 Russia's answers of 12 October 2016, para. 378.
12 Russia's answers of 12 October 2016, para. 387.
13 Russia's answers of 12 October 2016, para. 387.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 5 -
listed in Article XXVIII(l), the European Union does not consider that the
unbundling requirement challenged by Russia restricts or requires the use of a
specific type of legal entity to provide the services. In fact, the WTO Working
Party on Domestic Regulation has explicitly identified measures that are very
similar to the unbundling requirement as not falling with the scope of Article XVI,
but rather within the scope of Article VI:4 of the GATS, i.e. prohibitions to
combine certain activities.14
Such measures lay down characteristics of the service
supplier.
14. In its responses to the Panel's questions, Russia seeks in vain for measures that
would impose the use of a specific type of legal entity, taking words in Croatia's
and Lithuania's implementing laws out of context and arguing that they would be
different from the unbundling requirement in the Directive. In particular, Russia
argues that Article 14(1) of Croatia's Gas Market Act, which concerns ownership
unbundling,15
would differ from Article 9(1) of the Directive.16
According to
Russia, the requirement that the transmission system operator "shall be organized
as a legal entity, independently of other activities in the gas sector" would mean
that it imposes the use of a "specific type of legal entity".17
Yet, by merely
focusing on the words "shall be organized as a legal entity", Russia ignores that the
TSO can take the form of any type of legal entity. Ownership unbundling in
Croatia's law merely requires that the TSO is "independent[] of other activities in
the gas sector". Croatia's law is exactly in line with Article 9(1) of the Directive.
The requirement thus concerns the characteristics of the service supplier.
15. Russia makes the same mistake in respect of Article 17(4) of Croatia's Gas Market
Act, which concerns the ITO model, arguing that, since Article 18(6) of this Act
14 See Working Party on Domestic Regulation, Examples of measures to be addressed by Disciplines
under GATS Article VI:4. Informal Note by the Secretariat, Revision, 31 January 2005,
JOB(02)/20/Rev.10 (Exhibit EU - 40), referring to: (i) Licensing is conditional upon the observance
of the prohibition for service suppliers in the wholesale sub-sector to undertake retailing activities
simultaneously and (ii) License is conditional upon the observance of the prohibition for service
suppliers acting in the fixed telephony sub-sector to undertake activities in the mobile telephony
sub-sector simultaneously.
15 It does not concern ISO, as Russia erroneously suggests in paragraph 13(a)(i) of its answers of 12
October 2016.
16 Russia's answers of 12 October 2016, para. 13(a)(i).
17 Russia's answers of 12 October 2016, para. 13.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 6 -
requires an ITO to "have a special corporate identity, communication, brand name
and business premises clearly separating it from the parent company in the system
of the vertically integrated undertaking", it would impose the use of a specific type
of legal entity.18
Once again, Russia only focuses on the phrase "have a special
corporate identity, communication, brand name and business premises", ignoring
that the essence of the requirement is that the ITO must be "clearly separat[ed]
from the parent company". Again, any type of legal entity is permitted, but the
ITO must be "separate" from the parent undertaking. This is not a measure within
the scope of Article XVI:2(e) of the GATS.
16. Russia further errs when claiming that Article 2(6) of Croatia's Energy Activities
Act, which provides a definition of an ITO, violates Article XVI:2(e) of the
GATS. Russia argues that the requirement that an ITO is "an independent
company separate from a vertically integrated undertaking" would "support[]"
Russia's Article XVI:2(e) claim.19
Yet, once again, there is no requirement to use a
specific legal entity through which the service must be supplied. The only
requirement is that the TSO is "independent" and thus "separate from a vertically
integrated undertaking", which imposes characteristics of the service supplier.
17. Russia also cites Article 41(2) of Lithuania's Law on Natural Gas, which requires
that:
An undertaking performing any of the functions of production or
supply in any other country whose transmission system is
connected to the natural gas transmission system of the Republic
of Lithuania shall not be entitled directly or indirectly to exercise
control or exercise any right over a transmission system operator.
18. The European Union has already explained in its first written submission that
Russia errs when suggesting that this is an additional requirement, not contained in
the Directive.20
This provision follows immediately Article 41(1) of the Law on
Natural Gas, which copies the language contained in Article 9(1) of Directive
2009/73/EC. Article 41(2) clarifies that the prohibition established under Article
41(1) is also applicable in cases where the undertakings perform the respective
18 Russia's answers of 12 October 2016, para. 13(a)(ii).
19 Russia's answers of 12 October 2016, para. 13(b).
20 Russia's answers of 12 October 2016, para. 15(c); Russia's first written submission, para. 198.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 7 -
production or supply activities in any other countries which are interconnected
with Lithuania. The unbundling requirement thus does not only apply to
undertakings established in Lithuania. The provision merely specifies what is
already the case under the Directive: namely that no TSO in the territory of
Lithuania may be controlled by the same person that also performs any of the
functions of production or supply; or that can appoint members of the supervisory
board, administrative board or other bodies legally representing the TSO, while at
the same time exercising directly or indirectly control or any right over an
undertaking performing any of the functions of production or supply.21
19. Russia thus also errs when claiming in its responses to Panel Question 3 that this
measure restricts the specific types of legal entity through which a service supplier
may supply its pipeline transport services in Lithuania, in violation of Article
XVI:2(e) of the GATS. The measure merely specifies that the unbundling
requirement also applies in cases where the undertakings perform the respective
production or supply activities in any other countries which are interconnected
with Lithuania. The unbundling requirement is not a measure of the type defined
in sub-paragraph (e).
2.1.2.2 Sub-paragraph (a) (Russia's Claim 2)
20. Russia also argues that the unbundling measures in the domestic laws of Croatia
and Lithuania have the effect of limiting the number of service suppliers, in
violation of Article XVI:2(a) of the GATS.
21. Yet, Russia makes an incorrect interpretation of sub-paragraph (a) of the GATS
that does not fit with the facts at hand. Measures covered by sub-paragraph (a) are
measures intended specifically to limit the number of "service suppliers".22
It does
not cover measures that "indirectly give rise to a quantitative limitation on service
suppliers".23
To qualify as a measure under sub-paragraph (a), the core
characteristic of the measure must be to limit the number of service suppliers.24
21 EU's first written submission, para. 114.
22 Panel Report, Argentina – Financial Services, para. 7.421.
23 Panel Report, Argentina – Financial Services, para. 7.420. This point was not appealed.
24 Japan's third party written submission, para. 11.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 8 -
22. Russia argues that under Article XVI:2(a), "consideration should be given to the
substance and effect of a challenged measure and not just its formal
construction".25
Yet, the Appellate Body has precisely stressed that it disagreed
with an interpretation of Article XVI:2(a) of the GATS that any measure having a
quantitative effect would fall within the scope of sub-paragraph (a). The Appellate
Body indeed considered that it disagreed that "the words 'in the form of' [in Article
XVI:2(a)] should be ignored or replaced by the words 'that have the effect of'".26
23. The unbundling requirement does not, in any way, limit the number of service
suppliers that may supply pipeline transport services in the EU, nor does it impose
a monopoly supplier. There is an unlimited number of pipeline transport service
suppliers that can be certified as transmission service operators in Croatia and
Lithuania. The European Union has explained in its first written submission that
there is nothing in Croatia's27
or Lithuania's implementing laws,28
challenged by
Russia, that would limit the number of pipeline transport service suppliers in those
EU Member States.
24. The European Union also recalls that Russia's claim regarding Article 20(5) of
Lithuania's Law on Natural Gas is outside the Panel's terms of reference,29
also
when it concerns its suggestion that it would violate Article XVI:2(a) of the
GATS.30
2.1.2.3 Sub-paragraph (f) (Russia's Claim 3)
25. A final market access claim that Russia makes in respect of the unbundling
requirement is that it would violate sub-paragraph (f) of Article XVI:2 of the
GATS.
26. Yet, prohibited limitations under this sub-paragraph are maximum percentage
limits on foreign shareholding, or a maximum percentage limit of the total value of
25 Russia's answers of 12 October 2016, para. 25 (emphasis added).
26 Appellate Body Report, US – Gambling, para. 232.
27 EU's first written submission, paras. 132-133.
28 EU's first written submission, paras. 134-13
29 EU's Comments Regarding Terms of Reference, 21 October 2016, paras. 12, 28-34.
30 Russia's answers of 12 October 2016, para. 15(a).
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 9 -
individual or aggregate foreign investment. Sub-paragraph (f) is thus not
concerned with all limitations on capital participation, but is specifically concerned
with limitations tied to the fact that the capital originates outside of the Member
adopting the limitation.31
The unbundling requirement does not impose a
"limitation on the participation of foreign capital"32
and is neither "expressly [nor
indirectly] discriminatory".33
27. The Panel has noted that only sub-paragraph (f) of Article XVI:2 mentions the
word "foreign", no less than three times, in comparison with the other five sub-
paragraphs of Article XVI:2, which do not mention this word at all.34
This contrast
precisely supports the European Union's interpretation that sub-paragraph (f)
prohibits only limitations tied to the fact that the capital originates outside of the
Member adopting the limitation. Once again, Russia engages in an overly broad
interpretation of the scope of the measures defined in sub-paragraphs (a) to (f) of
Article XVI:2 of the GATS.
28. Russia's arguments are not based on the interpretation of the words in sub-
paragraph (f), but merely on Russia's suggestion that historically governments
have tended to impose restrictions on foreign direct investment.35
The European
Union fails to understand why this would imply that the word "foreign" could now
be read out of the text of sub-paragraph (f).
29. Russia also engages in inappropriate speculation on what a Member would do
when it has made a limitation with regard to its market access commitments that
would permit it to maintain a monopoly or exclusive service suppliers. Russia
claims that it "does not seem likely … that a Member would establish a foreign
person as a monopoly service supplier or exclusive supplier in its territory".36
This
statement by Russia is symptomatic of Russia's unfounded assumption – which
infects all its arguments – that WTO Members have a bias against foreign service
31 See Japan's third party written submission, para. 18.
32 Panel Report, China – Publications and Audiovisual Products, para. 7.1394 (emphasis added).
33 Panel Report, China – Electronic Payment Services, para. 7.653.
34 Panel's Question No. 89.
35 Russia's answers of 12 October 2016, para. 390.
36 Russia's answers of 12 October 2016, para. 394.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 10 -
suppliers. Yet, beyond speculation, Russia is unable to support its assumptions
with evidence.
30. In any event, the unbundling requirement – if it would limit investment at all –
applies without distinction to domestic and foreign investment. Such measure is
not covered by the prohibition in sub-paragraph (f) of Article XVI:2 of the GATS.
2.1.3. EU's response to Russia's arguments that the unbundling
requirement is not justified under Articles XIV(a) or (c)
31. The European Union has demonstrated in its first written submission that, even if
the Panel would consider that the unbundling measures in Croatia's, Hungary's and
Lithuania's domestic laws violate the market access commitments under sub-
paragraphs (e), (a) or (f) (quod non), the unbundling requirement is justified under
Articles XIV(a)37
and (c)38
of the GATS.
2.1.3.1 Article XIV(a) of the GATS
Competition in the energy sector is a fundamental 2.1.3.1.1
interest of EU society
32. The unbundling measure is necessary to maintain public order, consistent with
Article XIV(a) of the GATS. Competition in the energy sector, leading to
enhanced network access and increased investment, is a "fundamental interest of
society in the European Union".
33. Russia suggests that the EU has not demonstrated "how competition relates to the
'public order' or a fundamental interest of society or how the TEP unbundling
measures promote competition".39
Such suggestions are simply false. The
European Union has demonstrated, with reference to the provisions in the Treaty
Establishing the European Union, the Treaty on the Functioning of the European
Union, EU Regulations, competition decisions by the EU Commission, case-law of
the Court of Justice of the EU, and EU Commission communications and studies,40
that competition in the energy market is a "fundamental interest" of society in the
37 EU's first written submission, paras. 156-205.
38 EU's first written submission, paras. 206-220.
39 Russia's first oral statement, para. 17.
40 EU's first written submission, paras. 180-188, and the references in the footnotes to those
paragraphs.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 11 -
European Union and thus falls within the European Union's public order, as
clarified in footnote 5 to Article XIV(a) of the GATS. The European Union has
also demonstrated that the lack of effective unbundling of network and supply
activities poses a genuine and sufficiently serious threat to competition in the
energy market, showing how different attempts, preceding the Third Energy
Package, to improve competition in the energy sector were proven to be
insufficient. This was also demonstrated through the study in the Commission's
sector inquiry.41
The European Union has finally also demonstrated that the
unbundling requirement is manifestly "apt to make a material contribution" to the
achievement of increased competition in the energy sector.42
Russia did not and
cannot rebut any of this evidence.
No alternative measures are reasonably available to 2.1.3.1.2
achieve the objective
34. With regard to the existence of alternative measures that would achieve the
objective of ensuring and increasing competition and investment in the energy
market of the EU to the same extent as the unbundling requirement, Russia
suggests that "any contribution attributed by the EU to the unbundling measures is
already achieved by other laws".43
In its response to Panel Question 100, Russia
clarifies that it "does not argue that the existence of 'other laws' makes it such that
the unbundling requirement does not contribute in any way to competition or to
securing compliance with the TPA requirements of Article 32 of the Directive".44
Russia thereby already admits that the unbundling measure does contribute to the
stated objective.
35. Moreover, the "other laws" that Russia attempts to identify are not reasonably
available alternatives that achieve the objective to the same extent as the
unbundling measure. Russia suggests that the TPA requirement in Article 32 of the
Directive would be sufficient to prevent that TSOs provide privileged access to the
network for certain energy companies that are linked to VIUs and would impede
41 EU's first written submission, paras. 189-193.
42 EU's first written submission, paras. 194-199.
43 Russia's first oral statement, para. 18.
44 Russia's answers of 12 October 2016, para. 420.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 12 -
access to other gas producers and sellers. Russia also suggest that the obligation in
Article 22(7) of the Directive for TSOs to execute investments identified in their
ten-year network development plans would be sufficient to ensure sufficient
investment in infrastructure to safeguard competition.45
Russia errs. First, it should
be noted that Article 22 (7) does not even apply to all TSOs, but is part of the ITO
framework. It is thus not an alternative to unbundling, but part of the conditions of
one of the unbundling models. Second, past experience in the EU irrefutably
shows that these obligations, on their own, were insufficient to achieve these
objectives for transmission pipeline networks and that effective separation of
networks from activities of production and supply is necessary.46
36. It should also be recalled that, in addition to the strong link between unbundling
and TPA, unbundling has broader aims and implications than ensuring TPA.
Eliminating possible conflicts of interests between transmission and
production/supply activities in the TSO ensures that sufficient investments in the
network will be carried out, that all potential suppliers can access the network
which contributes to security of supply and better choices for consumers, etc. It is
thus incorrect to consider TPA and unbundling as equivalent or duplicating rules.
37. The separation of transmission, on the one hand, and production and supply
interests, on the other hand, is achieved through the three unbundling models that
the Directive sets out.47
These three models are each of them necessary to achieve
the objective of ensuring and increasing competition in the energy sector.
45 Russia's first oral statement, para. 18.
46 See Recitals (6) and (7) of Directive 2009/73/EC and Communication from the Commission
Inquiry pursuant to Article 17 of Regulation (EC) No 1/2003 into the European gas and electricity
sectors (Final Report), COM (2006) 851, http://eur-lex.europa.eu/legal-
content/EN/TXT/?uri=COM:2006:0851:FIN, para. 1 (Exhibit EU - 11) and a more detailed
Commission staff working document accompanying the Communication from the Commission -
Inquiry pursuant to Article 17 of Regulation (EC) No 1/2003 into the European gas and electricity
sectors (Final Report) (COM (2006) 851 final),
http://eur-lex.europa.eu/legal-content/EN/TXT/?uri=celex:52006SC1724 (Exhibit EU - 12). Key
arguments uncovered in the course of the investigation relating to the deficiencies of the existing
legal unbundling requirements are summarized in a Competition Policy Newsletter of Spring 2007,
http://ec.europa.eu/competition/publications/cpn/2007_1_23.pdf (Exhibit EU - 13) and see
Commission Communication on an Energy Policy for Europe, http://eur-
lex.europa.eu/LexUriServ/LexUriServ.do?uri=COM:2007:0001:FIN:EN:PDF (Exhibit EU - 14).
47 For ease of comprehension, the EU provides a schematic overview of the main characteristics of the
unbundling models as Exhibit EU-102.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 13 -
38. Russia errs already when claiming that the three models under the unbundling
measure have "a restrictive impact on international commerce, contrary to the
requirement of Article XIV(a)"48
(a "requirement" that Russia does not specify
further). However, the unbundling requirement does not, in any way, limit the
number of pipeline transmission services or suppliers that may serve the EU
market. Any transmission service supplier can still access the EU market, provided
that it does not control production and/or supply (i.e. sale) at the same time. The
fact that a VIU may have to "restructure",49
does not limit the supply of services.
Moreover, there is no obligation for a VIU to "divest their EU businesses
altogether".50
39. Further, Russia also focuses on the alleged (and illegal) possibilities for abusing
control over transmission in case of the ISO and ITO models to suggest that these
models would be less restrictive than ownership unbundling. The European Union
has demonstrated in detail that one unbundling model cannot be considered to be
"less restrictive" than another and that none of the models allows producers or
suppliers to control the manner in which the TSO operates the network and grants
access to it.51
Russia's arguments in fact reveal that it does not consider that the
unbundling requirement leads to a limited volume of pipeline transport services or
the number of suppliers.52
Rather, the "restrictiveness" that Russia complains
about is the inability to control gas producing/supplying competitors' access to the
transmission network and thus abuse the monopolistic position of the transmission
system operator. This is not the "trade restriction" WTO law protects against.
Moreover, none of the unbundling models allows the TSO to discriminate between
system users, in favour of its related producers or suppliers. To the opposite, such
a discrimination would be a clear violation of EU law53
– of the TSO obligations
under all unbundling models, as well as of the EU rules for non-discriminatory
48 Russia's first oral statement, para. 20.
49 Russia's first oral statement, para. 20.
50 Russia's first oral statement, para. 20.
51 EU's first written submission, paras. 306-337.
52 See Russia's first oral statement, para. 20: Russia admits that "[t]he unbundling measures may not
expressly limit the volume of pipeline transport services or the number of suppliers".
53 See the explicit prohibition in Article 13((1)(b) of Directive 2009/73/EC for a TSO to discriminate
again system users, particularly in favour of its related undertakings, when operating the system.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 14 -
third party access and capacity allocation. The EU finds it rather worrying that the
alleged "advantage" of the ISO and ITO models which Russia claims would exist
only if EU law is violated.
40. Each of the three models achieves the objective of ensuring and increasing
competition and investment in the energy market of the EU to the same extent. To
the extent that the degree of structural separation required is less, this is
compensated by intense behavioural requirements, increased regulatory oversight
and compliance burdens to achieve the same degree of effective unbundling as
ownership unbundling. Indeed, in the case of ownership unbundling, enforcement
costs and compliance burden for the undertaking are much less than in case of the
ITO model.54
It is therefore entirely incorrect to suggest that the ISO or ITO
models would be less restrictive than ownership unbundling. In terms of
compliance burden for the undertaking and enforcement costs, OU is the most
effective and least restrictive tool.55
The unbundling requirement meets the conditions of 2.1.3.1.3
the Chapeau of Article XIV
41. Russia finally suggests that the EU "barely mention[ed]"56
the requirements in the
Chapeau of Article XIV(a) of the GATS. Yet, as the European Union
demonstrated extensively in its submissions – and Russia failed to rebut – the
unbundling requirements in the domestic laws by Croatia, Hungary and Lithuania
challenged by Russia under Article XVI do not discriminate against Russian
suppliers. Each pipeline transport service supplier that provides or wants to
provide pipeline transport services in one of these EU Member States is subject to
exactly the same unbundling requirements in that Member State. If the Member
State has implemented OU only (e.g. Lithuania), all suppliers are subject to that
requirement. If the Member State has implemented also the ISO and ITO models
(e.g. Hungary and Croatia), the service suppliers could rely on either of these
models (provided the time limit of 3 September 2009 is respected). There is no
discrimination, let alone any arbitrary or unjustifiable discrimination.
54 EU's first written submission, para. 319; EU's answers of 12 October 2016, paras. 156-157.
55 Recital (8) of Directive 2009/73/EC.
56 Russia's first oral statement, para. 23.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 15 -
2.1.3.2 Article XIV(c) of the GATS
42. The European Union has also demonstrated that the unbundling requirements in
the Directive, as implemented in the domestic laws of Croatia, Hungary and
Lithuania, are necessary to secure compliance with the third party access
obligation in Article 32 of the Directive, as implemented in the domestic laws of
Croatia, Hungary and Lithuania, and thus also justified under Article XIV(c) of the
GATS.57
43. Russia states that its "response to the EU's assertions [under Article XIV(c)] is the
same [as to the EU's Article XIV(a) defence]".58
As explained with respect to
Article XIV(a), the European Union contests that the contribution of the
unbundling requirement to TPA and enhanced investment is sufficiently achieved
by the other laws that Russia identifies. Evidence based on historical experience
with different past measures shows exactly the opposite.59
44. Moreover, Russia's argument is also logically flawed because it claims that the
compliance with the TPA requirement in Article 32 of the Directive can be
ensured by the existence of the TPA requirement itself. Yet, it is the unbundling
requirement in the Directive (in particular Articles 9, 14-15, and Chapter IV of the
Directive), implemented in the different Member States, that ensures compliance
with Article 32 of the Directive, as implemented by the Member States.
45. The TPA rule requires that all system users have access to the system under non-
discriminatory terms, i.e. the intended regulatory outcome. The unbundling rules
on the other hand, provide one of the mechanisms how this outcome is ensured via
elimination of the conflicts of interests between transmission and
production/supply activities at the level of the TSO or its shareholders. Such rules
are necessary in the context of transmission activities because transmission
networks are natural monopolies and so there is a high risk for discriminatory
behaviour in the operation of the network. There are also other rules in Directive
2009/73/EC and Regulation (EC) No 715/2009, apart from TSO unbundling,
57 EU's first written submission, paras. 206-220.
58 Russia's first oral statement, para. 27.
59 See paragraph 35, above.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 16 -
which aim to ensure TPA to the transmission network, e.g. rules on how tariffs for
access to the transmission network must be calculated and approved, rules on how
capacity will be allocated, etc. Thus while Article 32 sets the general principle of
TPA which is underpinning the entire EU gas market legislation, it does not
eliminate the need for further rules in order to guarantee that the principle is
applied and respected.
46. The European Union also disputes60
Russia's objection that the unbundling
measure cannot ensure compliance with the TPA obligation because "they are in
fact a part of the same regime".61
A provision in a law or regulation may secure
compliance with an obligation in another provision of the same law or regulation.
This has been explicitly recognized by the panel in Argentina – Financial Services,
when it stressed that Panama had not challenged the two relevant laws as a whole,
but rather specific provisions of the laws.62
The panel stated that the fact that
certain provisions in the laws at issue were inconsistent with the GATS did not
mean that this resulted in the GATS inconsistency of the other provisions of these
two instruments.63
The panel thus accepted that certain provisions in a law that
were found to be inconsistent with the GATS could still be justified if they were
necessary to secure compliance with other provisions in the same law. The
Appellate Body upheld the panel's analysis in this regard.64
2.2. CLAIM VIII: THE PUBLIC BODY SPECIFICATION IN ARTICLE 9(6) OF DIRECTIVE 2009/73
VIOLATES NEITHER DE JURE NOR DE FACTO THE NATIONAL TREATMENT OBLIGATION IN
ARTICLE XVII OF THE GATS (RUSSIA'S CLAIMS 4 AND 5)
2.2.1. Introduction
47. Russia has challenged the public body specification in Article 9(6) of Directive
2009/73/EC, implemented in Croatia's, Hungary's and Lithuania's domestic laws,
as allegedly inconsistent with these EU Member States' national treatment
obligation in Article XVII:1 of the GATS. Russia claims that this measure is both
60 EU's responses of 12 October 2016, paras. 237-238.
61 Russia's responses of 12 October 2016, para. 410.
62 Panel Report, Argentina – Financial Services, para. 7.621.
63 Panel Report, Argentina – Financial Services, para. 7.622.
64 Appellate Body Report, Argentina – Financial Services, para. 6.241.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 17 -
de jure and de facto discriminatory (Russia now labels this as claims 4 and 5).65
The European Union has demonstrated that this claim is based on an incorrect and
selective reading of Article 9(6) and is not supported by the facts.
2.2.2. Article 9(6) is not de jure discriminatory
48. Russia claims that Article 9(6) of the Directive, implemented in the domestic laws
of Croatia, Hungary and Lithuania, "arbitrarily exempts government-owned and
controlled VIUs from the requirements of both the OU and ISO unbundling
models".66
49. However, as the European Union has explained, the public body specification is
not an exemption but precisely extends the unbundling requirement to the public
sector.67
The European Union thereby respects the principle of non-discrimination
between public and private sectors.68
The public sector does not escape the
application of the unbundling requirement (in particular paragraphs (a), (b), (c) and
(d) of Article 9(1) and Articles 9(2), 9(3) and 9(7) of the Directive). Such
application is ensured because the NRA must assess, in addition to whether all
unbundling requirements are met, whether the two public bodies controlling the
TSO, on the one hand, and a production or supply undertaking, on the other hand,
are truly separate, i.e. the public bodies must be independent from one another and
not under common influence of another public entity. The Commission also makes
such assessment in its Opinion on draft certification decisions submitted by NRAs
in accordance with Articles 10 and 11 of Directive 2009/73/EC. Effective
separation of transmission, on the one hand, and production and supply (i.e. sale)
interests, on the other hand, is thus ensured.
50. In fact, the absence of Article 9(6) of the Directive would have meant either that
public bodies are not subject to unbundling, or would have amounted to a
requirement to privatise transmission and production/supply activities in order to
65 Russia's responses of 12 October 2016, paras. 28 and 29.
66 Russia's first oral statement, para. 28.
67 EU's responses of 12 October 2016, paras. 3-5; EU's first written submission, paras. 223-226.
68 See Recital (20) to the Directive.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 18 -
comply with the unbundling rules (which would not have been possible due to EU-
constitutional reasons, as explained below).
51. Russia claims that "the Member State government" is one "person" and that thus
there is no unbundling under Article 9(6) for public bodies.69
Russia thereby
ignores that the Article 9(6) precisely requires that the NRA of the Member State
providing certification ensure that there are indeed two separate public bodies
exercising control over a transmission system operator or over a transmission
system on the one hand, and over an undertaking exercising any of the functions of
production or supply on the other. This must be demonstrated by the TSO to the
NRA.70
Whether the public bodies are "truly separate", and thus not under the
common influence of another public entity in violation of the unbundling rules,71
is
assessed by the NRA as well as by the Commission, based on a detailed
examination of the State's constitutional and administrative law.72
Russia's
argument that TSOs in the public sector would be exempt from the unbundling
requirement is thus entirely incorrect. The Commission certification opinions
concerning cases where Article 9(6) has been applied clearly evidence that no such
exemption exists and that Russia aims to misrepresent the nature of Article 9(6) by
persistently incorrectly qualifying it as an "exemption".
2.2.3. Article 9(6) is not de facto discriminatory
52. Russia further errs when claiming that the public body specification in Article 9(6)
is de facto discriminatory. There is nothing in this provision, or in the Directive in
69 Russia's first oral statement, para. 29; Russia's responses of 12 October 2016, para. 3.
70 EU's responses of 12 October 2016, para. 33.
71 Commission Interpretative Note on Directive 2009/72/EC concerning common rules for the internal
Market in electricity and Directive 2009/73/EC concerning common rules for the internal market in
natural gas. The unbundling regime, 22 January 2010, p. 10 (Exhibit EU - 42).
72 See for instance, Commission Opinion of 9 January 2012 pursuant to Article 3(1) of Regulation
(EC) No 715/2009 and Article 10(6) of Directive 2009/73/EC - Denmark - Certification of
Energinet.dk (gas), C(2012) 88 final, pp. 3-5 (Exhibit EU - 51); Commission Opinion of 1 July
2013 pursuant to Article 3(1) of Regulation (EC) No 715/2009 and Article 10(6) of Directive
2009/73/EC – the Netherlands - Certification of Gas Transport Services B.V., C(2013) 4205 final,
pp. 2-5 (Exhibit EU - 52); Commission Opinion of 17 February 2015 pursuant to Article 3(1) of
Regulation (EC) No 715/2009 and Article 10(6) of Directive 2009/73/EC – Hungary – Certification
of Magyar Gáz Tranzit Zrt., C(2015) 1046 final, pp. 3-4 (Exhibit EU - 53); Commission Opinion of
23 March 2015 pursuant to Article 3(1) of Regulation (EC) No 715/2009 and Article 10(6) of
Directive 2009/73/EC - Lithuania - Amber Grid, C(2015) 2135 final, pp. 1-3 (Exhibit EU - 54).
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 19 -
general, that indicates that third country public bodies cannot rely on Article 9(6)
when seeking certification under Articles 10 and 11 of the Directive. Russia
nevertheless asserts that Article 9(6) of the Directive was "designed to permit
Member States to own and control their entire transmission and supply systems".73
Russia does not provide a single piece of evidence to prove its asserted intention of
this provision.
53. On the contrary, all available evidence demonstrates that third country public
bodies can also rely on this provision. First, the text of Article 9(6) of the Directive
refers not only to "the Member State", but also, in addition, to "another public
body".
54. Second, The European Union notes that the phrase "Member States (or other
public bodies)" also figures in paragraph 192 of the Commission's Merger
Jurisdictional Notice.74
The notice provides that for the purpose of calculating
turnover in Merger Control:
Member States (or other public bodies) are not considered as
‘undertakings’ under Article 5(4) simply because they have
interests in other undertakings which satisfy the conditions of
Article 5(4). Therefore, for the purposes of calculating turnover of
State-owned undertakings, account is only taken of those
undertakings which belong to the same economic unit, having the
same independent power of decision. Thus, where a State-owned
company is not subject to any coordination with other State-
controlled holdings, it should be treated as independent for the
purposes of Article 5, and the turnover of other companies owned
by that State should not be taken into account. Where, however,
several State-owned companies are under the same independent
centre of commercial decision-making, then the turnover of those
businesses should be considered part of the group of the
undertaking concerned for the purposes of Article 5.75
55. Hence, the jurisdictional notice uses exactly the same term as the Gas Directive:
"Member States or other public bodies". The European Commission has applied
those rules to undertakings owned by the Chinese state in several merger control
73 Russia's first oral statement, para. 31.
74 Commission Consolidated Jurisdictional Notice under Council Regulation (EC) No 139/2004 on
the control of concentrations between undertakings , Official Journal C 095, 16/04/2008 P 1-48,
http://eur-lex.europa.eu/LexUriServ/LexUriServ.do?uri=OJ:C:2008:095:0001:0048:EN:PDF
(Exhibit EU-101).
75 Emphasis added.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 20 -
decisions.76
This demonstrates that this language used in Article 9(6) was intended
to extend the provision also to third country public bodies. The public body
specification in Article 9(6) is thus not de jure discriminatory.
56. Russia also claims that this provision results in de facto discrimination because –
according to Russia – Croatia, Hungary and Lithuania, through separate
government agencies or public bodies, actually own and control both the TSO and
supply infrastructure.77
As the European Union has explained in paragraph 51
above, the government does not "control" the TSO and the supply infrastructure.
The TSO must demonstrate to the NRA and the Commission that there are public
bodies that are truly separate and that these bodies fully comply with the
unbundling rules.
57. The European Union has also explained that there is an EU-constitutional reason
for not requiring a State to sell the network to a privately owned company, and
thus to privatise. As Russia itself accepts,78
such would be contrary to Article 345
of the TFEU, which reads:
The treaties shall in no way prejudice the rules in Member States governing the
system of property ownership.
58. Finally, the fact that there has not yet been an example where a third country TSO
has sought to rely on Article 9(6) of the Directive when seeking certification under
Articles 10 and 11 of the Directive, and that there are, at present, only a few
examples of application with regard to public bodies in EU Member States, does
not mean that this provision is de facto discriminatory. Whether situations would
arise where the application of Article 9(6) would be sought by a third country TSO
depends on factual circumstances that the EU legislation does not control. In fact,
Russia itself recognises that no Russian entity has sought to unbundle in
76 See for example Cases COMP/M.6111– Huaneng/OTPPB/Intergen, decision of 11 February 2011
(Exhibit EU-103); COMP/M.6082 – China National Bluestar/Elkem, decision of 31 March 2011
(Exhibit EU-104); COMP/M.6151 – Petrochina/Ineos/JV, decision of 13 May 2011 (Exhibit EU-
105); COMP/M.6113 – DSM/Sinochem/JV, decision of 19 May 2011 (Exhibit EU-106); and Case
COMP/M.6141 – China National Agrochemical Corporation/Koor Industries/Makhteshim Agan
Industries, decision of 3 October 2011 (Exhibit EU-107).
77 Russia's responses of 12 October 2016, para. 29.
78 Russia's responses of 12 October 2016, para. 68.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 21 -
accordance with Article 9(6) or pursuant to the corresponding provision in an EU
Member State’s implementing legislation.79
59. The European Union recalls that the Appellate Body in EC – Seal Products
stressed that, when assessing a measure under a non-discrimination obligation, a
panel looks at the "design, structure and expected operation" of the measure and
that the "focus of the analysis is on the impact of a measure on competitive
opportunities for like imported products, rather than the actual trade effects of a
measure".80
Therefore, even if there are at present no transmission system
operators in Croatia, Hungary or Lithuania that are controlled by third country
governments, nothing in the "design, structure and expected operation" of Article
9(6), or in the implementing measures by Croatia, Hungary or Lithuania, suggests
that third country-controlled transmission system operators would be excluded
from relying on this provision. The European Union refers to its detailed – and
unrebutted – discussion of the application of the unbundling requirement in
Hungary, Croatia and Lithuania in its first written submission.81
2.3. CLAIM IX: THE UNBUNDLING MEASURE DOES NOT VIOLATE THE MOST FAVOURED
NATION OBLIGATION IN ARTICLE II:1 OF THE GATS (RUSSIA'S CLAIM 6)
2.3.1. Introduction
60. Russia also brings a de facto discrimination claim under Article II:1 of the GATS
against the unbundling measure in Directive 2009/73/EC.82
61. Despite the fact that Russia specified that the "unbundling measure in the Directive
is the only measure relevant to this claim", in its responses of 12 October 2016,
Russia added to its "as such" claim against the unbundling measure in the
Directive an "as applied" claim, arguing that Russia "challenges the specific
instance of application of the unbundling measure in Lithuania by the EU and
Lithuania", whereby "Lithuania revoked the license of the Gazprom-jointly
controlled TSO in Lithuania".83
The Panel nevertheless decided in its Preliminary
79 Russia's responses of 12 October 2016, para. 71.
80 Appellate Body Report, EC – Seal Products, para. 5.95 (footnote 1019) (emphasis in original).
81 EU's first written submission, paras. 234-248.
82 Russia's first written submission, para. 307.
83 Russia's responses of 12 October 2016, para. 33.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 22 -
Ruling of 10 November 2016 that this claim ("Claim 7") falls outside the Panel's
terms of reference.84
62. Russia's discrimination claim is unfounded. It is based on an entirely erroneous
understanding of the law and is not supported by the facts.
2.3.2. The treatment service suppliers receive must be assessed in each
EU Member State individually
63. Russia's claim of discrimination is entirely based on the fact that not all Member
States have implemented all three unbundling models provided for in the
Directive. Russia asserts that there would be a violation of the MFN obligation in
Article II:1 of the GATS because a pipeline transport service supplier seeking
access to one Member State would be able to choose between OU, ISO or ITO,
whereas a pipeline transport service supplier in another Member State would only
have the possibility to seek certification under the OU model.
64. Yet, the Directive that Russia has challenged does not determine whether each
individual EU Member State must only implement OU or also the ISO or ITO
models, let alone whether TSOs must choose one or the other model when seeking
certification. It is entirely up for each Member State to decide whether to
implement OU only or also the other unbundling models. Next, it is entirely up to
each TSO to decide under which of the unbundling models set out in national law
to apply for certification before the national regulatory authority. Therefore, the
treatment that a pipeline transport service supplier receives is determined by the
legislation of the Member State implementing the unbundling requirement. That
treatment in the specific Member State is the basis for the MFN assessment. Given
that all service suppliers from all WTO Members are subject to the same
unbundling requirement in the Member State, there is no MFN violation.
65. It is wholly incorrect to compare the treatment received in one EU Member State
with the treatment received in another EU Member State. That would involve in
fact a comparison of the treatment offered by different measures. If a complainant
would want to assess the MFN treatment throughout the European Union, such
assessment can only be based on the treatment offered by a measure that lays
84 Preliminary Ruling by the Panel of 10 November 2016, para. 2.2.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 23 -
down such treatment for the entire EU. This would be a Regulation, which by
definition does not require further implementation in the Member States, or
provisions in a Directive that do not permit any options for the Member States for
implementing the measure, and do not involve minimum harmonisation (i.e.
Member States would not have the right to add requirements). The European
Union has explained that, indeed, the regulatory jurisdiction from which a
challenged measure emanates must determine the treatment that is compared.85
In
case of the unbundling requirement in Regulation 2009/73/EC, the relevant
provisions (Articles 9, 14-15 and Chapter IV) do not distinguish based on the
origin of the pipeline transport service supplier. There is thus no MFN violation.
66. Russia's claim follows an unsubstantiated assertion that the Member States (Russia
in fact only refers to Lithuania) and the European Union "acted together"86
in a
"calculated"87
process to adopt a Directive that would discriminate against pipeline
transport service suppliers from certain WTO Members.
67. However, Russia does not provide any evidence to demonstrate that such supposed
"conspiracy" exists. Moreover, the facts directly contradict Russia's assertion.
Russia presents an isolated, incomplete and incorrect overview of the unbundling
regime in the Member States, focusing on the unbundling process in Lithuania and
failing to mention the cases where Russian shareholdings in the TSO have been
subject to the ITO model or have been exempted from the unbundling
requirements. There are several examples where TSOs or transmission system
owners in which Gazprom has shareholdings have made use of the ITO or ISO
model.
68. The European Union recalls that Germany is – and was already before the
adoption of the Gas Directive in 2009 – the largest gas market in the European
Union and the largest export market for Gazprom.88
Yet, Germany has
implemented all three unbundling models. Moreover, three TSOs where Gazprom
85 EU's responses of 12 October 2016, paras. 102-105; EU's first written submission, paras. 289-297.
86 Russia's responses of 12 October 2016, para. 31.
87 Russia's first oral statement, para. 38.
88 Russian Gas Imports in the EU (all Member States) 2009-2014 (Eurostat Statistics), (Exhibit EU-
108) and Russian Gas Imports in Germany, (Exhibit EU-109).
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 24 -
has joint control or shareholdings have been certified as ITOs, i.e. GASCADE
Gastransport GmbH, NEL Gastransport GmbH and ONTRAS.89
In addition, the
Opal pipeline which operates under an exemption framework in Germany is not
operated by an unbundled TSO. If the unbundling requirement in the Directive that
Russia now challenges would have been designed to treat pipeline transport
service suppliers from one particular WTO Member less favourably, the Directive
would have allowed for the implementation of the OU model only, or Germany –
where Gazprom's interests were the most significant – would have implemented
the OU model only (under Russia's erroneous assumption that the OU would have
a negative competitive impact, quod non). None of this is the case.
69. Furthermore, three of the Member States where Gazprom had considerable
shareholdings in the TSO at the time of adoption of the Directive – Estonia,
Finland and Latvia – were granted derogations from the unbundling rules as
isolated markets under Article 49(1) of the Directive. If the intention of the
Directive has been to "attack" Russian shareholdings in TSOs, as Russia seems to
allege, no such derogations would have been granted.90
70. Moreover, even in Lithuania, there is no element in the challenged Directive that
compelled Gazprom to stop providing its pipeline transport services in Lithuania.
Russia suggests that the EU has "enable[d] individual Member States like
Lithuania to require the OU model".91
However, Lithuania did not need any
"enabling" by the EU to impose OU. It could have done so without the existence
of any EU measure. Nothing in Russia's story allegedly explaining the background
for the adoption of Lithuania's energy laws92
demonstrates any "acting together" of
89 EU's first written submission, para. 338-341. While Russia stresses the implementation of the ITO
model in France, it mentions its implementation in Germany only to claim that it has been applied
to the TSO jorgas, but omits to mention the more numerous TSOs with Russian shareholding in
Germany that have used the model (Russia's responses of 12 October 2016, paras. 33 and 35)
90 Latvia has subsequently transposed the OU model because the conditions for the exemption in
Article 49(1) to remain in place were no longer met. Estonia on the other hand has decided to apply
unbundling and not make use of the derogation, which under the Directive it is free to do. In any
event, in both cases, nothing has prevented Gazprom from keeping passive minority rights in the
TSO, as allowed under OU rules. Moreover, Finland, where Gazprom had a substantial
shareholding in the TSO, still applies the derogation. While Gazprom has in 2015 decided to sell its
shares to the Finnish state in 2015, in the absence of application of the unbundling rules in Finland,
this choice evidently cannot be attributed to the EU legislation.
91 Russia's first oral statement, para. 38.
92 Russia's responses of 12 October 2016, paras. 152-188.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 25 -
the European Union and Lithuania. Gazprom could still provide pipeline transport
services in Lithuania, provided it ensured it did not control an undertaking
performing any of the functions of production or supply. The same conditions
apply to any other Russian gas producer or supplier. In fact, this obligation applies
indeed to all pipeline transport service suppliers in Lithuania. There is thus no
MFN violation.
71. Finally, apart from not being supported by the facts at all, Russia's allegations that
the EU and the Member States somehow "conspired" in the adoption in
implementation of the unbundling models in the Directive in order to discriminate
against Russian pipeline transport service suppliers is simply unrealistic. Neither
could the EU have known at the time of adoption of the Directive which Member
State would implement which model several years later (using its sovereign
decision-making process), nor could the EU or its Member States have predicted
how shareholdings in TSO and transmission system owner would develop at the
time the certification of TSOs was to take place, again several years later.
2.3.3. The imposition of the OU model does not alter the competitive
position of pipeline transport service suppliers
72. Russia alleges that, because Lithuania only permits the OU model, "a VIU is
restricted from maintaining anything more than a limited, minority ownership
interest in the transmission system".93
The critical flaw in Russia's argument is that
it equates "a VIU" with "a pipeline transport service supplier". A VIU is a
corporate structure that combines different, separate, activities which may include
pipeline transport, production, and supply (i.e. sale) of gas. A pipeline transport
service supplier is the TSO that operates the transmission network transporting the
natural gas. The question that must be answered under Article II:1 of the GATS is
to what extent a service supplier from a certain origin is treated less favourably
because of the OU requirement, when compared to service suppliers that can rely
on the ITO or ISO models.94
Does the type of unbundling model alter the service
suppliers' competitive relationship?
93 Russia's first oral statement, para. 40.
94 The European Union recalls that it does not agree that such comparison can be made between and
among EU Member States, since the appropriate point of comparison is the regulatory jurisdiction
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 26 -
73. Russia's argument is completely based on the fact that a service supplier that is
part of a VIU would, under OU, no longer be able to control access to its
transmission pipelines,95
and thus no longer be able to give privileged access to
related producers or suppliers that are part of the VIU or foreclose access to
competing producers and sellers of gas that are not part of the VIU.
74. This argumentation is based on a fundamental misrepresentation of the unbundling
rules. First, as already explained by the EU, in the ISO model, the TSO (i.e. ISO)
cannot be controlled by the VIU in any event. It is the system owner which could
be part of a VIU, but even this is not necessarily the case in the ISO model.96
Setting this aside, the Russian argumentation implies that the ISO and ITO models
would allow the service supplier, i.e. the TSO, to favour its relating undertakings
(producers and suppliers in the VIU) when giving access to the transmission
network and allocating the transmission capacity. However, such actions that
involve discrimination amongst system users and an abuse of a monopoly position
are not only equally prohibited under ITO and ISO rules, but will also result in a
clear violation of EU law.97
To the extent that structural separation is less far-
going under these models, this is compensated with strict behavioural requirements
and increased regulatory oversight.98
75. Second, Russia also errs when claiming that there would be financial benefits
when a pipeline transport service supplier would operate under the ISO or ITO
models. Faced with the obligation in the Directive that natural gas undertakings
that has adopted the measure. The European Union discusses this comparison only in subsidiary
order.
95 Russia's first oral statement, para. 40.
96 EU's first written submission, para. 318.
97 Article 13(1)(b) of Directive 2009/73/EC, which sets out TSO tasks applicable to all TSOs
irrespective of the unbundling model they apply, explicitly prohibits the TSO to discriminate
between system users or classes of system users, particularly in favour of its related undertakings.
Any discrimination by the TSO between system users will also go against the requirements of
Article 32 of Directive 2009/73/EC for granting third party access under non-discriminatory terms,
also applicable to all TSOs, irrespective of the unbundling model applied. Article 17(2)(c) of
Directive 2009/73/EC, part of the ITO rules, explicitly requires the ITO to grant and manage third-
party access on a non-discriminatory basis between system users or classes of system users. Article
14(4) of Directive 2009/73/EC, part of the ISO rules, explicitly requires that it will be the ISO, i.e.
the TSO and not the system owner (which can in the ISO model be part of a VIU) that has to
manage third party access, precisely in order to eliminate risk for discrimination by the system
owner in relation to related suppliers and producers.
98 EU’s first written submission, paras. 315-322.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 27 -
must separate their accounts for each of their transmission, distribution, LNG and
storage activities,99
and the prohibition to cross-subsidise between transmission
and other activities,100
Russia has nothing more to say than that it “is not in a
position to assess this claim fully"101
and that “money is fungible”.102
Money is
indeed fungible, and that is precisely why the obligation of separation of accounts
and the prohibition to cross-subsidise, in combination with the unbundling
requirement, are imposed.103
2.3.4. Russia cannot demonstrate that the alleged negative competitive
impact of OU (quod non) is predominantly on Russian service
suppliers
2.3.4.1 Russia asks the Panel to disregard 15 years of WTO
jurisprudence
76. In order to bring a de facto discrimination claim under Article II:1 of the GATS,
Russia needs to (i) show the group of negatively affected service suppliers, and the
group of positively affected (or unaffected) service suppliers; and (ii) demonstrate
that the negatively affected group contains predominantly service suppliers of
Russian origin.104
77. This approach to de facto discrimination claims is firmly established in WTO case-
law,105
where it was indeed stressed by the Appellate Body that WTO Members
may draw distinctions between products which have been found to be "like",
without, for this reason alone, according to the group of "like" imported products
"less favourable treatment" than that accorded to the group of "like" domestic
products.106
This same reasoning applies to the MFN obligation in the GATS: the
non-discrimination obligation does not require Members to accord no less
99 Article 31 of Directive 2009/73/EC.
100 Article 41(1)(f) of Directive 2009/73/EC.
101 Russia’s responses of 12 October 2016, para. 507.
102 Russia’s responses of 12 October 2016, para. 509.
103 EU’s first written submission, para. 323-324.
104 EU’s responses of 12 October 2016; EU's first written submission, paras. 301-303.
105 See Appellate Body Report, US – Tuna II (Mexico), paras. 214-215, 221, 231; Appellate Body
Report, US – Clove Cigarettes, paras. 178-180, 193; Appellate Body Report, EC – Asbestos, para.
100; Appellate Body Report, Chile – Alcoholic Beverages, para. 67.
106 Appellate Body Report, EC – Asbestos, para. 100.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 28 -
favourable treatment to each and every service or service supplier from one
Member as compared to each and every like service or supplier from another
country. Under the national treatment and MFN obligations, an aggregate
assessment must be made and it is insufficient to find one or a few products that
are treated less favourably.
78. Russia requests the Panel to disregard 15 years of WTO jurisprudence, arguing
that the application of a measure "on one occasion can be sufficient to restrict the
competitive opportunities of a foreign service supplier".107
Russia cannot provide
any reason why the legal standard for assessing less favourable treatment under the
non-discrimination obligations in the GATS would be different from that under the
non-discrimination obligations in the GATT 1994.
2.3.4.2 Russia cannot demonstrate that any alleged detrimental
impact of the unbundling requirement (quod non) is predominantly
on the group of pipeline transmission service suppliers from Russia
79. Russia also cannot demonstrate that any alleged detrimental impact (if that would
exist at all – quod non) of the unbundling requirement would be predominantly on
the group of pipeline transmission service suppliers from Russia. Russian gas
transport service suppliers are also active in Member States that have implemented
the ITO models. Russian pipeline transport services suppliers in Germany have
made use of the ITO model108
and gas transport service suppliers with substantial
Russian shareholdings have benefitted from derogations from the unbundling rules
granted to Latvia and Finland.109
80. Table 1, below, provides an overview of the unbundling models in each Member
State. It also indicates Russian pipeline transport service suppliers that have relied
on the ITO model or benefitted from exemptions. This evidence shows that OU is
not predominantly imposed on the group of Russian service suppliers. The
European Union also provides a more detailed Table in its Exhibit EU-110 (BCI)
107 Russia's responses of 12 October 2016, para. 196.
108 EU's first written submission, paras. 338-341.
109 See paragraph 69, above.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 29 -
with the exact shareholdings in TSOs in the EU, as a response to the table
presented by Russia110
which is erroneous or incomplete in many instances.111
[[ ]]
2.3.4.3 Russia's "evidence" on the implementation of the
unbundling requirement in the Member States is critically flawed.
81. The European Union objects to the large number of incorrect factual allegations
made by Russia throughout its responses, and in particular in its response to Panel
Question 12, as regards the transposition of the OU rules in the EU Member
States. The following errors are a selection of main errors.
82. The allegation that as a result of the transposition of the Directive in Lithuania,
Estonia, UK, Belgium and Latvia, Gazprom was "forced"112
to dispose of its
shares in TSOs in these countries is wholly incorrect. Gazprom could have kept
passive minority rights in the TSOs, which would have been compatible with the
OU rules and this has been done by other producers/suppliers.113
Gazprom has
chosen to sell its shares instead which has been its own decision.
83. Russia also incorrectly claims that "only Gazprom"114
has been subject to OU.
Shareholders from the EU and from third countries active in production and supply
have been similarly affected by the OU rules.
84. For example, in the case of the certification of the Interconnector I-UK cited by
Russia as an example of the alleged effects of OU, it is evident that the other third
110 Russia's responses of 12 October 2016, para. 98 (Exhibit RUS-118).
111 For example, the table incorrectly indicates that in the case of the Yamal pipeline in Poland the
Russian shareholding is in the ISO, i.e. the TSO, while this is not the case. Russia jointly controls
the system owner for Yamal, Europolgaz, but has no shareholdings in the TSO (i.e. the ISO) which
is Gazsystem. Similarly, the Russian table omits to list a number of Russian shareholdings such as
in the case of Opal, as well as the exemption from unbundling granted under Article 49(1) of
Directive 2009/73/EC to Finland, Latvia and Estonia – countries with Russian shareholdings in the
TSOs at the time of adoption of the Directive. The table also fails to indicate the unbundling models
transposed in all Member States and thus available to TSOs on their territories.
112 Russia's responses of 12 October 2016, para. 98.
113 Sonatrach has accepted such limitation for its shareholdings in the TSO Reganosa in Spain.
114 Russia's responses of 12 October 2016, para. 98.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 30 -
country shareholder ConocoPhillips had to comply with exactly the same rules as
Gazprom.115
85. In Italy, the TSO Snam SA was required to switch to ownership unbundling after
their successful but temporary certification under the ITO model and Eni SpA sold
its interest in the company.
86. Shareholdings from other third countries have been subject to OU as well, for
example in Spain, Portugal and France. Indeed, in order to comply with OU in the
case of the TSO Reagnosa in Spain, the rights of shareholders (including the third
country shareholder Sonatrach) were modified to be passive financial rights with
no influence or voting power. In Portugal, the TSO REN Gasodutos SA, wherein
several third country persons have shareholdings, the ownership structure and
rights of individual shareholders were changed (e.g. regarding Board Members) in
order to comply with OU. In the case of the TSO TIGF in France, where GIC
Private Limited (100% controlled by the Ministry of Finance of Singapore) had a
shareholding, OU took place.
87. Furthermore, while Russia fails to acknowledge it, the Member States that have
transposed OU only – Belgium, Denmark, Lithuania, the Netherlands and Sweden
– apply this regime without distinction to all TSOs on their territories and to all
producers/suppliers which wish to attain or keep shareholdings in the TSOs or the
transmission systems. For example, E.ON had to comply with the OU rules in
Lithuania just as Gazprom had to. These Member States produce gas (for instance
the Netherlands, who is the biggest gas producer amongst the EU Members States,
as well as Denmark) and/or import gas from other third countries but Russia (for
instance Belgium imports gas from Norway and Qatar,116
Denmark imports gas
from Norway,117
Sweden imports gas from Denmark,118
the Netherlands imports
115 Moreover, the need to comply with OU in respect of the interconnector I-UK did not result from the
fact that only OU has been transposed in the UK (in fact, the UK has transposed also other models),
but from the fact that the interconnector was a new transmission system which was not part of a
VIU in September 2009. Because of the time limit in Article 9(8) of the Directive this
interconnector could not have been certified under the ISO or ITO model.
116 Country Factsheet Belgium, http://eur-lex.europa.eu/legal-
content/EN/TXT/PDF/?uri=CELEX:52015SC0209&from=EN, p. 3 (Exhibit EU-111).
117 Country Factsheet Denmark, http://eur-lex.europa.eu/legal-
content/EN/TXT/PDF/?uri=CELEX:52015SC0221&from=EN, p. 3 (Exhibit EU-112).
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 31 -
gas from Norway119
). Accordingly, EU gas producers and suppliers as well as
producers and suppliers from other third countries but Russia need to equally
observe the OU rules as long as they wish to have shareholdings in the TSO or the
transmission network in those Member States.
2.4. CLAIM X: RUSSIA'S CLAIM UNDER ARTICLE III:4 OF THE GATT 1994 (RUSSIA'S CLAIM 8)
2.4.1. Introduction
88. Russia's discrimination claims under the GATT 1994 also fail on all accounts.120
In making its arguments, Russia again provides an erroneous interpretation of
WTO law. Moreover, Russia also misrepresents the factual aspects of the
unbundling requirement, suggesting that ownership unbundling imposed on
pipeline transport service suppliers means that this would be to the detriment of
Russian gas.
89. In reality, the unbundling requirement has as objective to increase competition in
the market and improve investment in infrastructure. Gas producers and suppliers,
no matter their origin (including Russian), can sell their gas without any limitation
into the EU market. That is precisely the objective of the unbundling requirement.
In fact, evidence shows that the import of gas from Russia into the European
Union has increased since the third energy package entered into force. According
to Eurostat data, imports of gas from Russia to the EU have increased from 114
bcm in 2009 to 115 bcm in 2014.121
In addition, recent Gazprom news items have
highlighted Gazprom's successes in selling record gas volumes to the EU122
and
Russia is the biggest supplier of gas to the EU.123
118 Country Factsheet Sweden, http://eur-lex.europa.eu/legal-
content/EN/TXT/PDF/?uri=CELEX:52015SC0240&from=EN, p. 3 (Exhibit EU-113).
119 Country Factsheet Netherlands, http://eur-lex.europa.eu/legal-
content/EN/TXT/PDF/?uri=CELEX:52015SC0241&from=EN, p. 3 (Exhibit EU-114).
120 The European Union recalls that the Panel ruled that Russia's claims 9 and 11 are outside the
Panel's terms of reference. Preliminary Ruling by the Panel of 10 November 2016, para. 2.2.
121 Russian Gas Imports in the EU (all Member States) 2009-2014, (Exhibit EU-108).
122 Gazprom's supplies to Germany climb 20.4 per cent in October,
http://www.gazprom.com/press/news/2016/november/article290994/, Boosting Supplies,
http://www.gazprom.com/press/reports/2016/increases-delivery/ (Exhibit EU-115).
123 Gas imports in the EU – all external suppliers 2009-2014, (Exhibit EU-116).
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 32 -
2.4.2. The treatment of gas of different origins must be assessed in
each EU Member State individually
90. Also with respect to its GATT-claims, Russia makes the mistake to compare
treatment that imported gas would receive in different Member States. Yet, by
doing so, Russia is in fact comparing different measures: each Member State has
implemented ownership unbundling into its own domestic laws. It is each Member
State's domestic laws that determine the treatment gas would receive and it is in
each Member State that the treatment must be assessed. EU-wide treatment could
only be assessed in case the measure at issue was an EU Regulation or a provision
in a Directive that would not allow for any diversity in Member State
implementation.
91. Contrary to what Russia suggests, this has nothing to do with "the EU be[ing]
allowed simply to wash its hands of MFN responsibility".124
Permitting Member
States to choose how to implement certain EU requirements is perfectly in line
with the principle of subsidiarity and proportionality in EU law. Article 5(1) of the
TEU indeed provides:
The use of Union competences is governed by the principles of subsidiarity
and proportionality.
92. EU measures must not interfere more into the Member States' national regulatory
autonomy than to the extent necessary to achieve the objectives pursued. EU
action will only be undertaken if the objective cannot be achieved to the same
extent by individual Member State action and can be better achieved at Union
level.125
In fact, Russia's argument suggests that such an approach, which forms
the hallmark of EU law, would not be acceptable: all EU measures would
necessarily need to be Regulations (rather than Directives) involving full
harmonisation without any discretion for Member States to adopt implementing
measures that achieve the objectives set out in the EU measure.
93. Moreover, Russia also errs when claiming that the European Union attempts "to
fragmentize"126
the EU market for natural gas. The European Union has explained
124 Russia's first oral statement, para. 38.
125 See Protocol No 2 to the TEU on the Application of the Principles of Subsidiarity and
Proportionality.
126 Russia's responses of 12 October 2016, para. 209.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 33 -
that there is no negative competitive impact of ownership unbundling at all
because (i) OU is not more restrictive than the ISO or ITO models127
and (ii)
Russia has not demonstrated that a measure that regulates a service supplier, i.e.
the TSO, also affects trade in gas.128
94. Russian gas can be imported in any Member State without any restriction and there
is no reason why import in one Member State would be preferred over another. In
fact, many TSOs transport Russian gas without any Russian shareholdings in these
TSOs and many even exclusively or mainly Russian gas.129
Hence, Russia's
argument on the "fragmentation" of the market is simply irrelevant.
2.4.3. Russia cannot show that a particular unbundling model
translates into a competitive disadvantage for gas of a certain
origin
95. At the time of writing this second written submission, Russia has still failed to
explain how a particular unbundling model, which applies to a pipeline transport
service supplier, could translate into a competitive disadvantage for gas of a
certain origin, when the essence of unbundling is precisely to enable free
competition between gas of any origin.
96. Russia does not hide that it considers the control over the TSO as the competitive
advantage that producers and sellers of gas would lose when faced with the
unbundling requirement.130
Russia thereby once more reveals that it attacks the
127 See paragraphs 72-75, above.
128 EU's first written submission, paras. 361-362. Russia keeps stressing an incorrectly assumed
automatic link between the regulation of pipeline transport service providers and trade in gas,
arguing that "whenever a measure affects either the service through which a product such as natural
gas is supplied to the market, or the service suppliers that supply the product, that measure will
automatically also affect the 'sale, offering for sale, purchase, transportation, distribution or use' of
that product". According to Russia, this "is so because these are the very functions carried out by
the service suppliers that sell, transport or distribute that product". (Russia's responses of 12
October 2016, para. 463.) Russia once again confuses the supply of natural gas to the market –
which is the sale of the gas (a good) – with the supply of transport services – which is a service.
The European Union has explained in detail in its first written submission that the sale of a gas
must not be confused with the distinct service of pipeline transport. (See EU's first written
submission, paras. 50-80.) Moreover, as Japan rightly noted, Russia's "automatic link" presumption
risks annihilating any limitations that WTO Members have inscribed with respect to their service
commitments, affecting the legitimate expectations of WTO Members. (EU's responses of 12
October 2016, para. 307, referring to Japan's third party submission, paras. 41-42.).
129 EU's first written submission, para. 622.
130 Russia's responses of 12 October 2016, paras. 473-475, 493-495.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 34 -
very essence of the unbundling requirement: it believes that its gas producers must
be able to illegally exploit a monopoly position in the EU and foreclose access to
transmission networks for gas from competing producers. Its reference to the
Commissions actions against Engie131
only reaffirms that, through its WTO
challenge, it seeks to safeguard such illegal, anti-competitive conduct for its
producers, in particular Gazprom (given the exclusive rights it enjoys for exporting
pipeline gas under Russian law). The European Union finds it hard to believe that
restricting free trade and competition would be the purpose, and effect, of the
WTO obligations.
97. Russia also suggests that one of its gas producers, Gazprom, "had to give up all
transport fees and other revenue associated with the TSO".132
However, the
obligation to separate accounts for each of the transmission, distribution, LNG and
storage activities of a VIU,133
and the prohibition to cross-subsidise between
transmission and other activities,134
shows that, even if a gas producer would own
a transmission network, the "benefit of transport fees and other revenue associated
with the TSO" could not provide a competitive benefit to the producer. Moreover,
nothing in EU law prevents other Russian gas producers from exporting gas to the
EU. The only limitations to such possibility come from the export monopoly for
pipeline gas applied by Russia itself.
98. Faced with the fact that the rules on third party access further prevent TSOs that
operate under the ISO or ITO models from foreclosing access to gas from
competitors or treating more favourably related undertakings,135
Russia only states
that the "TPA requirements do not meaningfully mitigate the detrimental impact
on natural gas that stem from a VIU in one part of the EU, such as Germany
[where the ITO model was available to Russian-owned TSOs], compared to a
131 Russia's responses of 12 October 2016, paras. 480-781, 495.
132 Russia's responses of 12 October 2016, paras. 474, 494.
133 Article 31 of Directive 2009/73/EC.
134 Article 41(1)(f) of Directive 2009/73/EC.
135 See in particular Panel's Questions 115 and 116, which refer to the "effects on natural gas that
would otherwise stem from any control a natural gas suppliers or producer may be able to exercise
over an ISO or ITO, over a LSO, or over the operator of an upstream pipeline network".
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 35 -
VIU, such as Gazprom in Lithuania [where only OU is available]".136
Yet, Russia
does not provide any explanation why TPA requirements would be not meaningful.
99. The contrary is true: gas from any origin can access each EU Member State
without any limitation, no matter the unbundling model that this Member State has
implemented. Any limitation that a TSO would impose would simply be illegal.
Russia acknowledges this itself, when it states that "the TPA provision requires
that all TSOs grant access to the system to all eligible customers, including supply
undertakings".137
Hence, the unbundling requirement in the Directive, no matter
the unbundling model that is implemented, does not alter the conditions of
competition in the EU to the detriment of Russian gas. Nothing in the law of the
EU and its Member States prevents Russian gas produced by Russian gas
producers from being imported in the Union and transported over the transmission
pipeline networks, just like gas from any other origin.
100. Russia's comparison of the specific situation in Lithuania with the situation in
Germany or France does not show any competitive disadvantage for Russian gas
either.138
Russian producers are in no way limited as to the volume of gas it can
sell on the Lithuanian market, just as in Germany and France. Just as to any
Russian (or other) gas producer, this also applies to Gazprom, who may continue
importing the volume of gas to Lithuania demanded by the consumers in the
market. Gazprom is in fact doing so, including under its new marketing strategy of
using auctions.139
The volume of Russian gas imported in Lithuania is entirely
determined by the availability of alternative sources of supply and the competition
in the market and not by the unbundling measure challenged by Russia.140
136 Russia's responses of 12 October 2016, para. 505.
137 Russia's responses of 12 October 2016, para. 506.
138 Russia's responses of 12 October 2016, paras. 474-475, 494-495.
139 See EU's first written submission, paras. 370-371.
140 The European Union recalls that the TSO does not control or decide on the volume of gas to be
imported or on the source of gas to be transmitted via its system, but simply transports the gas - and
due to the TPA principle - gives access to the system to all suppliers and to gas of all origin. Its role
is merely of a transporter. Thus whether a Russian or another non-EU country does or does not
have shares in the TSO and what model the TSO applies is irrelevant to how much gas Russia or
the other third country could export to the Member State where the TSO operates. Due to the TPA
principle all suppliers are able to access the transmission network under non-discriminatory terms.
Therefore, the volume of gas Russia or another WTO member exports to the EU, the source from
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 36 -
2.4.4. The alleged negative competitive impact of the unbundling
requirement (quod non) is not predominantly on the group of
Russian gas
2.4.4.1 Russia's argument disregards established WTO
jurisprudence and ignores the essence of unbundling
101. The European Union recalls again that WTO jurisprudence141
has firmly
established that a complainant bringing a de facto discrimination claim under
Articles I and III:4 of the GATT 1994, must (i) show the group of negatively
affected goods, and the group of positively affected (or unaffected) goods; and (ii)
demonstrate that the negatively affected group contains predominantly Russian
gas.142
102. This aggregate approach is precisely to avoid that a measure that happens to have a
negative impact on the competitive conditions of one good on one occasion would
be found to be discriminatory, whereas in reality there is no "genuine relationship"
between the measure at issue and the adverse impact on competitive
opportunities.143
There is no reason to deviate from this well-established WTO
jurisprudence in the present case.
103. The European Union has demonstrated that the particular unbundling model that
applies in a specific EU Member State does not affect the competitive position of
gas sold in that Member State, no matter the origin of that gas.144
Each TSO is
obliged to provide gas from any origin access to its transport infrastructure. There
is thus no link between the origin of the TSO and the origin of the gas that that
TSO transports.145
The third party access obligation in the Directive requires all
TSOs in the EU to give access, and thus transport through the network they
which an EU Member State imports gas, does not depend on the unbundling model that the TSO
but on other, market and economic factors.
141 See Appellate Body Report, US – Tuna II (Mexico), paras. 214-215, 221, 231; Appellate Body
Report, US – Clove Cigarettes, paras. 178-180, 193; Appellate Body Report, EC – Asbestos, para.
100; Appellate Body Report, Chile – Alcoholic Beverages, para. 67.
142 EU’s responses of 12 October 2016; EU's first written submission, paras. 301-303.
143 Appellate Body Report, Thailand – Cigarettes (Philippines), para. 134.
144 See paragraphs 95-100, above.
145 EU's responses of 12 October 2016, paras. 52-54.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 37 -
operate, gas of any origin (be it produced in the EU, in Russia or in any other third
country) and of any producer (domestic, Russian or from another third country).
104. The unbundling rules safeguard this third party access principle and ensure the
independent operation of the network. If the TSO, when operating the network and
giving access to it, is giving preferential treatment to certain producers, or to gas of
a certain origin, this would in fact indicate that the TSO tasks and the unbundling
rules, as well as third party access rules, are violated.
105. For this reason already, all of Russia's answers to Panel's Question 25 should be
dismissed. Russia's answers assume that all of the gas that is carried by the
infrastructure of a Russian VIU would be Russian, all of the gas carried by the
infrastructure of a domestic EU VIU would be from EU origin, and all of the gas
carried by infrastructure of a VIU of another origin, would be from that origin.
Because of the above-cited obligations, this assumption is entirely incorrect.
106. Russia's response that the GATT does not require Russia to demonstrate that a link
exists between the origin of gas that flows through a pipeline and the origin of the
service supplier146
misses the point entirely. It is Russia that claims that certain
unbundling models have a detrimental impact on the competitive position of gas of
a certain origin. It is then only reasonable that Russia would explain why a
particular unbundling model, imposed on a service suppliers of any certain origin
that operate in an EU Member State, would necessarily affect the competitive
position of gas of a certain origin. Russia bears the evidentiary burden to
demonstrate this link between the origin of the service supplier, to which the
unbundling requirement applies, and the origin of gas.
107. Such required demonstration has nothing to do with the "introduc[tion] of an
effects test", as Russia wrongly alleges.147
Russia needs to demonstrate how the
imposition of a particular unbundling model in a Member State necessarily
modifies the conditions of competition of gas of a certain (i.e. Russian) origin.
Russia indeed admits that it "is necessary to show only that the unbundling
measure … distorts the conditions of competition to the detriment of Russian
146 Russia's responses of 12 October 2016, para. 510.
147 Russia's responses of 12 October 2016, para. 511.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 38 -
gas".148
Yet, this is precisely what Russia has failed to do. The Appellate Body has
indeed confirmed that under GATT Articles I:1 and III:4, the focus of the analysis
is on the impact of a measure on competitive opportunities for like products. The
Directive, and in particular the unbundling measure, guarantees the competitive
opportunities of gas from any origin, including Russian. Gas, no matter its origin
can enter freely the market of the EU Member States and TSOs cannot foreclose
access of gas of a certain origin.
2.4.4.2 Abundant evidence shows the absence of a link between
the unbundling model and the volume of Russian imports
108. The facts clearly evidence that there is no link between the unbundling model
applied in a Member State and the presence of and volume of Russian imports (or
imports from any other source).
109. This is already demonstrated when one examines the unbundling models available
in the different Member States together with the figures for Russian gas imports
into the EU since the adoption of the Third Energy Package in 2009 until 2014.
The European Union has presented this evidence in Exhibit EU-108.
110. Apart from the most apparent fact – namely that Russian imports into the EU in
total have not decreased since 2009 but are indeed set to reach record levels
according to the assessment of Gazprom top management149
– the lack of a link is
also evidenced by looking at the concrete situation of individual Member States.
111. By way of example, taking the Member States which have transposed OU only –
Belgium, Denmark, the Netherlands, Sweden and Lithuania – one observes that
Russian imports in these countries increased with 30 % from 2009 to 2014. The
share of Russian imports in these countries compared to the total gas imports in
these countries increased from 11.8% in 2009 to 15.42% in 2014. Similarly, the
share of Russian imports in these countries compared to all Russian imports in the
EU increased from 5.99% in 2009 to 7.73% in 2014.
148 Russia's responses of 12 October 2016, para. 511.
149 Boosting Supplies, http://www.gazprom.com/press/reports/2016/increases-delivery/ (Exhibit EU-
115).
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 39 -
112. If there were decreases in Russian imports at all, those were in Member States
where OU played no role or that were even exempted from unbundling. For
example, in Finland (which applies an exemption from the unbundling rules under
Article 49(1) of Directive 2009/73/EC) Russian imports decreased from 4.28 bcm
in 2009 to 3.06 in 2014. Russian imports have also decreased in Luxembourg
which similarly has an unbundling exemption under the Directive. Imports in
Slovakia, which has transposed all unbundling models, also decreased from 5.83
bcm in 2014 to 4.76 bcm.
113. At the same time, there are examples of Member States where Russia has no
shareholding in the TSO and which have increased their imports of Russian gas,
e.g. Italy and Bulgaria (the latter in fact importing only Russian gas).
2.4.4.3 Russia's "evidence" allegedly linking an unbundling
model to gas volumes is critically flawed
114. Furthermore, the link that Russia alleges between unbundling models, on the one
hand, and the volume of imports, on the other hand, is in no way evidenced by the
data Russia has presented.
There is no link between the unbundling model and 2.4.4.3.1
Russian gas imports
115. In reply to Panel Question 25a), in order to demonstrate the alleged disadvantage
of the OU model as opposed to the ITO and ISO model, Russia alleges that
"Russian natural gas can now be supplied in the EU by TSOs owned by the VIU
that produced that natural gas only in (a) Germany, if supplied via the Greifswald
entry point, either by Opal .. or by NEL..; and (b) Latvia, if supplied by Latvijas
Gaze".150
Russia further argues that the capacity of the above entry points in
Germany and Latvia corresponds to 25% of the capacity of all entry points for
Russian gas.151
Russia refers to Exhibit RUS-127.
116. First, this assertion is directly contradicted by Gazprom's own information
disclosure about its recent gas auction in March 2016 on the Lithuanian-
150 Russia's responses of 12 October 2016, para. 126.
151 Russia's responses of 12 October 2016, para. 127.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 40 -
Belorussian border.152
The EU submits an overview153
of cross-border pipeline
capacity between third countries and Europe that could be used to import gas
produced in Russia to EU Member States. Based on this evidence, the EU finds no
percentages that would correspond to the figures in Russia's submission. In fact,
according to our calculations, based on ENTSOG 2016 transmission capacity map,
Russian undertakings control TSOs operating points which amount to around 30 %
of the capacity of operating interconnection points which are entry points to the
EU gas network for Russian gas.
117. Irrespective of that, the assumption on which Russia's arguments in reply to
question 25a) are based is wrong. Russia seems to suggest that (i) it cannot
transport its gas through TSOs that it does not own as part of a VIU, or that (ii) if a
VIU owns a TSO, it will enjoy a privilege as it can transport more gas through the
TSO's network than its competitors and have easier access to the capacity at the
entry point which the TSO operates.
118. Russia's first suggestion is incorrect because EU law imposes a third party access
obligation and Russian gas is in reality transported by many TSOs in the EU in
which Russian entities have no shareholding's at all.154
119. Russia's second suggestion is also incorrect. Russia seeks to misrepresent the
effects of the unbundling rules and claims a link between the unbundling model
applied by a TSO and the volume of imports a VIU can make into the EU. Such
link which would only exist if EU rules are violated by the TSO and the VIU.
Once again, the EU stresses that there is no correlation between a VIU owning a
TSO and the amount of gas the supplier branch of that VIU might import into the
EU market and transport through that TSO. Under EU law the supply branch of a
VIU enjoys no privilege vis-a-vis other suppliers on the market as regards access
to the transmission network or booking a certain amount of the capacity for
transporting gas via the TSO network.
152 Gazprom Export's gas auction for Baltic States completed,
http://www.gazprom.com/about/subsidiaries/news/2016/march/article269297/ (Exhibit EU-62).
153 Overview of cross border point capacity, (Exhibit EU-117)
154 EU's First Written Submission, para 622.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 41 -
120. To the contrary, such privilege is explicitly prohibited under all unbundling
models. The EU rules on third party access155
and capacity allocation156
(also
applicable to all models) require the TSO – irrespective of who its owner is – to
give access to the network to all system users under non-discriminatory conditions
and to allocate the capacity at the interconnection point it operates under strict and
detailed procedures which guarantee non-discriminatory access to the capacity to
all market plays. These rules apply irrespective of the origin of the supplier that
wants to access the network and book capacity for transporting the gas into the
EU, be it from the EU, Russia or another third country.
121. Trying to show a non-existent privilege, Russia claims that TSOs "control" entry
points, thus implying the TSO can decide on discriminatory behaviour. Yet, TSOs
do not "control" but rather "operate" such entry points into the transmission
system. This distinction is important as they cannot arbitrarily decide to whom and
under what conditions to give access. The EU framework on third party access and
capacity allocation sets out detailed rules in this regard in order to ensure non-
discriminatory access for all network users.
There is no link between the unbundling model and 2.4.4.3.2
EU-produced gas volumes
122. Further, Russia's allegation in its response to Panel Question 25b) that "92% of the
EU-origin gas in the EU in 2015 has been supplied by VIU that produced that gas
while at the same time having an interest in TSOs operating under the ITO/ISO
models"157
is based on a table (in Exhibit RUS-123) that Russia fabricated in a
misleading way, and that shows several critical flaws. It does not prove at all
Russia's allegation.158
Therefore, the Panel should dismiss this table as well as
Russia's allegation.
123. First, the table presented by Russia suggests that the source is Eurostat. However,
none of the information presented in the different columns comes from Eurostat. In
fact, the only data which seems to be based on Eurostat figures is the 2nd
column
155 Article 32 of the Gas Directive 2009/73/EC, Article 14 of Regulation (EC) No 715/2009.
156 Article 16 of Regulation (EC) No 715/2009.
157 Russia's responses of 12 October 2016, para. 130.
158 Russia's responses of 12 October 2016 (Exhibit RUS-118).
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 42 -
with figures for domestic production in each Member State. Yet, even for these
figures no concrete year has been provided. The EU provides a table with
production volumes in each EU Member State from 2005 until 2014 based on
Eurostat data which do not match the figures provided by Russia (Exhibit EU-
118).159
124. Second, regarding the list of producers in each Member State (3rd
column), the
table conveniently mentions only certain producers (no indication of the source on
which this list of producers is based) in the Member State, namely those which are
part of a VIU that at the same time has transmission interests. It fails to list other
producers in the Member States.
125. For example, the Russia indicates only 3 producers for Germany: Bayerngas,
Engie and BEB Erdgas and Erdol GmbH. However, these are neither all, not even
the biggest producers.160
126. Similarly, Russia's table conveniently indicates for the Netherlands – the biggest
domestic gas producer in the EU – only one company, Engie, while ignoring other
producers.161
As a result of this selective approach, the table incorrectly assumes
that all production in the listed Member States comes from the listed producers.
This is entirely wrong and annuls all conclusions that Russia seeks to draw from
the table.
159 EU Member States' gas production 2005-2014 (Exhibit EU-118).
160 The information from the International Energy Agency specifies: "With regard to the production
tier, there are five main companies producing natural gas in Germany. Exxon Mobil accounts for
approximately 46% of indigenous production; Shell for 22%; RWE for 15%; Wintershall for 9%;
and GDF for 5%. There is also a small number of natural gas importing companies including: E.ON
Ruhrgas, Wingas, Shell Deutschland, ExxonMobil, Verbundnetz Gas (VNG), RWE and
Bayerngas." See International Energy Agency, Energy Policies of IEA Countries. The Netherlands.
2014 Review, http://www.iea.org/publications/freepublications/publication/germanyoss.pdf, p. 20,
(Exhibit EU-119).
161 The information from the International Energy Agency provides: "On the upstream side, the largest
producer is NAM, the Nederlandse Aardolie Maatschappij, a 50/50 joint venture of Royal
Dutch/Shell and ExxonMobil. Shell is the operator within this joint venture […]. NAM produces
gas from the Groningen field, which represents two-thirds of total production, and also produces
almost half of gas from small fields. In recent years, a number of other companies moved into the
Dutch market. Other producers include Wintershall, Total, GDF Suez, Chevron. These gas
producers can market the gas by themselves. If they do not want to, they can also decide to offer
their gas to GasTerra. In this case GasTerra has the legal obligation to purchase the gas at a price
that is reasonable and reflects its market." See International Energy Agency,
http://www.iea.org/publications/freepublications/publication/Netherlands2014.pdf, p. 140, (Exhibit
EU-120).
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 43 -
127. Third, the table wrongly assumes that all production of a given supplier (part of a
VIU) in the Member State of production (3rd
column) is exported to the Member
State where the ISO/ITO is located (4th
column). This is not only incorrect but also
illogical. The gas produced could be used for domestic consumption in the
Member State of production or be exported to an entirely different EU Member
State (or even third country) and is not necessarily exported to the Member State
where the TSO is located. Because the gas producer is prohibited by EU
legislation to obtain any privileged access to the network of the TSO, it will export
the gas to that Member State where that network is located only if there is an
economic rationale to do so, i.e. if there is demand and if it can offer competitive
prices. The direction of exports has thus no link to the unbundling model applied
by the TSO.
128. Moreover, the table does not substantiate this wrong assumption in any way with
references to sources. While Russia refers to Eurostat as its sole source of
information for this table, Eurostat data does not provide figures for the amount of
gas that each gas producer in the EU sells in the country of production and the
amounts exported to other Member States. In fact, such figures generally constitute
commercial secrets.
129. Fourth, the 4th
column refers to "TSOs controlled by the gas producers under
ITO/ISO model". As explained in the EU first written submission, under the ISO
model, it is not the TSO but the system owner which could be a subsidiary of the
VIU and so in the ISO model the VIU cannot be considered to control the TSO.
130. Fifth, as a result of the incorrect data and false assumptions listed above, the final,
5th
column of the table, which indicates as figures of "gas produced by VIU subject
to ITO/ISO" all of the production in the respective Member State, is entirely
incorrect and should be dismissed by the Panel.
There is no link between the unbundling model and 2.4.4.3.3
gas volumes imported from other third countries
131. The data concerning gas from third countries (Exhibit RUS-125 Excel Sheet on
Gas Imports) provided by Russia in its reply to Panel Question 25c), by which
Russia seeks to demonstrate an alleged disadvantage stemming from the
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 44 -
unbundling rules for Russian gas, is equally flawed and does not support the
allegations Russia makes.
132. Before considering the tables Russia provided in Exhibit RUS-125, it is important
to stress a striking mistake in Russia's description of the facts. Russia's statement
that Russian gas is not transported and supplied by a VIU that is involved at the
same time in the production and supply of natural gas162
is wholly wrong.
Gascade, NEL and Opal transport Russian gas and the TSOs that operate them are
controlled by Gazprom. In the past, before Gazprom decided to dispose of its
shares in the TSO, this was the case also with the Finnish TSO Gasum, as well as
the TSOs in Estonia and Lithuania and the interconnector I-UK between Belgium
and the UK. Gazprom could have kept passive minority shareholdings under the
OU model in these TSOs but has decided not to do so.
133. In any event, the data presented by Russia as two tables in Exhibit RUS-125 for
pipeline and LNG gas do not evidence in any way whatsoever any discrimination
against Russian gas. This is due to critically wrong presumptions on which the
tables are based. As a result, these tables cannot not lead to the calculations and
conclusions made by Russia, for instance that "up to 56 % of the Norwegian gas is
extracted, supplied and transported within the EU by the VIUs".163
134. First, the table on pipeline gas selectively lists certain produces in Norway and
Libya and omit others (e.g. Shell, ExxonMobil, Total). On this basis, the table
incorrectly suggests that the entire production in Norway and Libya that is
exported to the EU comes from the listed producers. The Russian figures also
seem to include Norwegian LNG, even though the table is entitled "pipeline gas"
(the table refers to all Norwegian gas imports into the EU and these do not come
from pipeline gas only).
135. Moreover, it is incomprehensible that Statoil appears as a gas producer in Norway
and at the same time (in the table presented as Exhibit RUS-123 – Excel Sheet on
Gas Production) as a gas producer in the UK. While Statoil has indeed activities
both in Norway and the UK, Russia fails to distinguish in any way in terms of
162 Russia's responses of 12 October 2016, para. 135.
163 Russia's responses of 12 October 2016, para. 136.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 45 -
figures the different volumes of gas that correspond to production in the EU and
outside the EU and conveniently uses Statoil in both tables. Similarly, Engie is
presented as a producer in Norway and a producer in the Netherlands and the UK,
without any distinction in the volumes.
136. Second, the table on pipeline gas incorrectly indicates that all of the gas exported
to the EU by Norway (presented as all the gas produced by the listed producers
which, as just explained, is incorrect) is exported to the Member State where the
TSO in which the gas producer has shareholdings is located. The table thus
suggests that all Norwegian exports to the EU go to Germany, Austria, France,
Italy. This is simply incorrect. Apart from being illogical, it is contradicted by the
facts. Based on Eurostat data, Austria did not import any Norwegian gas in 2014.
Most importantly, Norwegian gas in 2014 was imported by a number of EU
Member States not mentioned at all in the table – Belgium, Czech Republic,
Denmark, Greece, Spain, Lithuania, Luxembourg, Poland, Portugal, the
Netherlands, and the UK.164
In fact, the Member States which imported Norwegian
gas in 2014 and are not mentioned in the table amounted for over 50 % of all
Norwegian imports. The table simply omits to reflect this.
137. Furthermore, the table also seems to imply (like the table contained in Exhibit
RUS-123 on pipeline gas imports in the EU) that the TSOs indicated in the 4th
column are all the TSOs in the indicated Member States, so the gas transported via
these TSOs (incorrectly presented to be all the gas coming from the indicated
producers) would equal the share of these Member States' imports of Norwegian
gas to the EU. This is yet another mistake.
138. In particular, the table considers only jorgas as TSO in Germany, only ITG as TSO
in Italy, only GRTgaz as TSO in France. There are many more TSOs in these
Member States as acknowledged even in Russia's own table of TSOs
shareholdings (Exhibit RUS-118). It is thus wrong to assume that the indicated
producers rely exclusively on the pipelines where the VIU has shareholdings. To
illustrate this with few examples:
164 Norwegian gas imports in the EU in 2014 - all Member States, (Exhibit EU-121).
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 46 -
Russia relies on the assumption that all gas exported by Statoil to Germany is
transported through jordgas' pipeline. In fact, jordgas owns only the NETRA
pipeline, which runs from Dornum on the German North Sea Coast towards
Steinitz. This pipeline has no exit points, but rather feeds into the Gaspool
balancing area, where the gas has to enter pipeline owned by another company
to reach any exit points. The idea that Statoil is somehow relying on its own
grid exclusively is thus unfeasible.
In a similar pattern, the pipeline owned by ITG in Italy, alleged by Russia to be
used for the supply of pipeline gas to Italy from Edison Group's production in
Libya, is in fact a mere 83km connection between a LNG regasification facility
and the remainder of the Italian gas network. There is no possibility of using
this pipeline to supply pipeline gas from Libya to Italy, or even to supply
regasified LNG to anyone without using another operator's network.
Further, Engie owns GRTgas and production facilities in the North Sea. To
supply gas to France however, Engie has to use the Gassco network.
The fact that the Italian State owns shares in both Eni and Snam is equally
irrelevant. Snam is certified under the OU model, requiring the Italian State to
separate control of the two companies in two independent public bodies that
are not under control of one single higher authority. There is also no automatic
correlation between Eni's production and the gas supplied to Italy: Eni is not
the sole producer in Libya and other such producers have equal access to
Snam's pipeline capacity.
Crucially, the gas Statoil transports from the fields to the EU markets is via a
system in which statoil has but a 5% minority shareholding.165
139. The same type of misrepresentation applies to the table in Exhibit RUS-125 for the
LNG sector:
In the case of Algeria, only Sonatrach exports gas and it is thus entirely
inconceivable how Engie would use its interests in LNG terminals for its own
export operation from Algeria.
165 The pipelines are owned by the Gassled consortium in which Statoil has a 5% shareholding and
operated by Gassco in which Statoil has no shareholding.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 47 -
In turn, Sonatrach had to accept a limitation of its shareholder rights in
Reganosa to passive financial rights in order to maintain them. This is to
ensure there is no Sonatrach influence on the access to market infrastructure.
In the case of LNG exports from Qatar to UK, those flow through several LNG
terminals, including those owned by National Grid, demonstrating that there is
no correlation between ownership and use of infrastructure. This is evidenced
by the Russian table itself – Nigeria, Norway, Trinidad and Peru are listed as
exporters of LNG to the EU, while they apparently do not have any ownership
in the LNG terminals. The same applies to the US which, while not mentioned
in the table, also exports LNG to the EU.
2.5. CLAIM XI: RUSSIA'S CLAIM UNDER ARTICLE I:1 OF THE GATT 1994 (RUSSIA'S CLAIM
10)
140. Russia's claim under Article I:1 of the GATT 1994 against the unbundling measure
in the Directive suffers from the same flaws as set out in the previous Section with
regard to the claim under Article III:4. The MFN treatment must be assessed in the
Member State that has implemented the unbundling requirement, according to the
domestic law of that Member State. Russia has also failed to explain how a
particular unbundling model, which applies to a pipeline transport service supplier,
would translate into a competitive disadvantage for gas of a certain origin. Finally,
Russia has also failed to demonstrate that the impact of the unbundling
requirement is predominantly on the group of Russian gas.
2.6. CLAIM XII: RUSSIA'S CLAIM OF VIOLATION OF ARTICLE I:1 OF THE GATT 1994
BECAUSE THE DIRECTIVE WOULD ACCORD NATURAL GAS OF OTHER THIRD COUNTRIES
IMPORTED THROUGH LNG FACILITIES AND UPSTREAM PIPELINE NETWORKS AN
ADVANTAGE NOT EXTENDED TO RUSSIAN GAS (RUSSIA'S CLAIMS 12 AND 13)
2.6.1. Introduction
141. Russia makes further discrimination claims under Article I:1 of the GATT 1994 in
respect of the specific application of the unbundling requirement to LNG and
upstream pipeline networks. The European Union discusses first LNG (sub-section
2.6.2) and thereafter upstream pipeline networks (sub-section 2.6.3).
142. Before considering the claims in more detail, it should be stressed that the LNG
and upstream measures do not have the nature of "exemptions" from a generally
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 48 -
applicable unbundling rule in the Third Package, contrary to what Russia alleges.
The Gas Directive sets out a whole and comprehensive legal regime for the
operation of all types of gas infrastructure in the EU. It contains specific rules for
an exhaustive list of the different types of gas infrastructure (transmission
pipelines, upstream pipelines, LNG facilities, storage facilities, distribution
pipelines, etc.). There are no infrastructure categories which remain out-with the
Directive; all natural gas facilities must be classified within this exhaustive list.
143. While all of the above-mentioned sets of rules share the core principle of third
party access, the rules are not identical. The differences are necessary in view of
the specific functions that the different infrastructures and their operators carry
out. Such differences in the rules applicable to divergent infrastructures are
common for many jurisdictions, including Russia's own regulatory framework.
2.6.2. The LNG measure does not violate Article I:1 of the GATT
1994 (Russia's claim 12)
144. Russia claims that the provisions in the Directive relating to LNG facilities accord
"an advantage to third-country natural gas imported and placed on the EU market
by LSOs through LNG facilities that is not granted immediately and
unconditionally to Russian natural gas imported and sold on the EU market via
various pipelines that were subject to the unbundling requirement".166
145. The European Union recalls that the objective difference between LNG facilities
and transmission pipelines is clear: a transmission network is a natural monopoly.
In contrast, this is not the case for LNG facilities. LNG facilities can be
constructed in any location, provided there is sea access. They can operate in
competition with one another. TSOs are required to connect new LNG terminals
on the basis of a non-discriminatory and transparent procedure.167
146. Operators of LNG facilities are obliged to ensure third party access, according to
Article 32 of the Directive and Article 15 of the Gas Regulation (EC) 715/2009,
meaning that gas from any source and supplier can access the LNG terminal under
non-discriminatory terms. This includes, in particular, the obligation of non-
166 Russia's responses of 12 October 2016, para. 38
167 EU's responses of 12 October 2016, paras. 7-8; EU's first written submission, paras. 427-436.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 49 -
discrimination between system users, as well as the obligation to provide
necessary information (Article 13(1)(b)-(d)), and obligations to allocate the
capacity under transparent and non-discriminatory mechanisms.168
If an LNG
operator is also a TSO, the TSO unbundling and certification requirements in
Articles 9-11 apply in full.
2.6.2.1 LNG and natural gas are not "like"
147. Russia's discrimination claim already fails because it compares the treatment of
LNG and natural gas, which are not "like" products. To determine the "likeness",
the Panel should rely on the following criteria: (i) the product's properties, nature
and quality; (ii) the end-uses of the products; (iii) consumers' tastes and habits;
and, (iv) the tariff classification of the products.169
The question is whether
consumers would consider the products in question to be in a competitive
relationship.170
148. The European Union has explained that LNG situates itself at a different stage in
the gas production process than natural gas.171
The European Union recalls that the
Appellate Body in US – Lamb upheld the panel's finding that "a raw material or
input that is used to produce [a] product" (i.e. live lamb), on the one hand, and the
product itself (i.e. lamb meat), on the other hand, are not "like or directly
competitive products" within the meaning of Article 4.1(a) of the Agreement on
Safeguards.172
The European Union considers that the same analysis underlying
the Appellate Body's finding in US – Lamb applies to LNG and natural gas: two
products at different stages in the production process, namely LNG and natural
gas, are not "like or directly competitive products".
149. The physical characteristics of LNG and natural gas are different: LNG is liquid,
while natural gas is in gaseous form. Moreover, the end-use of LGN and natural
gas is different: LNG is used as fuel for ships. Moreover, consumers of LNG
168 Article 17 of Regulation (EC) 715/2009.
169 Report of the Working Party on Border Tax Adjustments, BISD 18S/97, para. 18.
170 Appellate Body Report, US – Clove Cigarettes, para. 120; Appellate Body Report, Philippines –
Distilled Spirits, para. 125; Appellate Body Report, EC – Asbestos, para. 99.
171 EU's responses of 12 October 2016, para. 280.
172 Appellate Body Report, US – Lamb, paras. 77-96.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 50 -
purchase this product in order to transport it by ships or trucks and trade or store
LNG. Finally, LNG and natural gas have a different tariff classification. LNG is
classified under HS 2711.11 while natural gas is classified under HS 2711.21.173
All this evidence demonstrates that LNG and natural gas are not "like" products.
2.6.2.2 Russia cannot demonstrate that the LNG measure alters
the competitive position of gas imported from Russia
150. The European Union recalls that the provisions in the Directive relating to LNG –
which apply to suppliers of LNG services – do not distinguish based on the origin
of gas. Hence, Russia cannot demonstrate that the LNG measure alters the
competitive position of gas imported from Russia.174
151. Russia argues that because "VIUs are exempted from the requirement to unbundle
their LSO's", the Directive "accords natural gas originating in third-countries and
imported and placed on the EU market through EU-based LNG facilities, such of
[sic] those of Engie S.A. ('Engie') in France, an advantage within the meaning of
GATT Art I:1 that is not granted immediately and unconditionally to Russian
gas".175
Once again, Russia claims that the competitive disadvantage that Russian
gas would suffer from would be the lost opportunity to control the access to the
transmission network.176
Russia believes there is "enhanced access to the European
gas market" for other third country gas than Russian gas.177
152. However, Russia thereby entirely ignores that operators of LNG facilities are
subject to the third party access requirement and related capacity allocation rules
and thus fails to recognise that limiting access to gas of a certain origin to a LNG
facility is simply illegal for such operators. The provisions in the Directive relating
to LNG facilities do not treat gas from other origins than Russian origin more
favourably than Russian gas. Russia has in fact itself pointed to action undertaken
by the Commission to address anti-competitive behaviour by Engie.178
This
173 EU's first written submission, paras. 360, 437.
174 EU's first written submission, paras. 439-446.
175 Russia's responses of 12 October 2016, para. 476.
176 Russia's responses of 12 October 2016, paras. 478-482; Russia's first oral statement, para. 52.
177 Russia's responses of 12 October 2016, para. 478.
178 Russia's responses of 12 October 2016, para. 480.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 51 -
demonstrates precisely that it is not legal for LSOs, like TSOs, to restrict access to
the market.
153. Hence, nothing prevents Russian gas from being imported via LNG terminals in
the EU. Russian gas has, just like gas from any other origin, the possibility to be
imported in the EU via LNG facilities or via the transmission network. Russia
argues in its Response in paragraphs 482 and 503 that "Even if Russian gas were
ordinarily converted to LNG, it cannot access the majority of capacity at Engie's
LNG facilities. Moreover, since TSO capacity in France is based on an automatic
right to enter the transmission network, the majority of transmission capacity
connected to the three Engie-controlled LNG facilities is thus used for Engie's
gas."
154. While it is correct that the French terminals, operated by the Engie subsidiary
Elengy, are underwritten by long-term contracts, there are – due to effective
congestion management measures – significant capacities available to other market
players looking for capacity. EU national regulatory authorities have also been
closely working together to develop such third-party access and congestion
management regimes at essentially all EU terminals. The average rate of LNG
terminal utilisation in Europe (of total installed capacity) has decreased since
2010, from 53% to 25% in 2013. In 2014, no more than 19% of the total send out
capacity was used (compared with a global average of 33 %).179
Therefore, market
players can access a significant share of the yearly 200 bcm regasification capacity
at the EU LNG terminals either because there is readily available capacities (e.g.
no long-term bookings), or because holders of long-term bookings are incentivized
to relinquish their capacity in case they do not make use of it.
155. Hence, publically available information indicates that the terminals are far from
being congested and there are capacities available on various terminals that could
be booked by any entity and for gas of any source.180
The fact that there are no
179 See EU Staff working paper SWD(2016)23
https://ec.europa.eu/energy/sites/ener/files/documents/1_EN_autre_document_travail_service_part1
_v3.pdf. (Exhibit EU-122). GIE, the EU organization of gas infrastructure operators, has also set up
ALSI, the LNG transparency platform, which shows clearly the availabilities at each EU terminal:
https://alsi.gie.eu/#/
180 For example, the capacities available at the following terminals can be found in: Capacities
available at certain LNG terminals: Montoir (owned by Elengy, a subsidiary of Engie):
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 52 -
obstacles for Russian companies to use the terminals is also evidenced by the fact
that the Russian company Novatek Gas & Power has an agreement with Elengy to
use Montoir LNG facilities.181
2.6.3. The upstream pipeline networks measure does not violate
Article I:1 of the GATT 1994 (Russia's claim 13)
156. Russia also claims that the provisions in the Directive relating to upstream pipeline
networks violate Article I:1 of the GATT 1994.182
Russia argues that these
provisions, of which it erroneously claims Russian pipelines cannot benefit,
modify the conditions of competition to the detriment of Russian gas.183
2.6.3.1 Upstream pipeline networks have a different nature and
role than transmission pipelines
157. The European Union recalls that the reason why specific provisions apply to
upstream pipeline networks is that upstream pipeline networks are directly linked
to the production fields.184
The upstream pipelines thus have the sole role of
ensuring that gas from the upstream production (and production-related) facilities
– be they on- or offshore – are transported to the interconnected transmission
system from where the gas is taken either directly downstream to customers in a
given market or across several borders to other markets.
158. An upstream pipeline is inherently linked to proprietary gas production. It is
ancillary to the production of natural gas and operates, in normal circumstances, in
no direct competition with any other gas producer. It is used to transport the non-
fungible gas from the production field to the processing plant (where the gas is
made fungible) or to a terminal or to a final coastal landing terminal, at which
https://www.elengy.com/images/contenu/contratsetoperations/capacitesprimaires/ELENGY_public
ations_Montoir_2016_11_10.pdf (Exhibit EU-123); Capacities available at certain LNG terminals:
Fos-Tonkin:
https://www.elengy.com/images/contenu/contratsetoperations/capacitesprimaires/ELENGY_public
ations_FosTonkin_2016_11_10.pdf (Exhibit EU-124).
181 Elengy signs a transshipment long-term contract with Novatek Gas and Power,
https://www.elengy.com/en/news/news/commercial/150-elengy-signs-a-transshipment-long-term-
contract-with-novatek-gas-power.html (Exhibit EU-125).
182 Russia's responses of 12 October 2016, para. 39.
183 Russia's first oral statement, para. 54.
184 EU's first written submission, para. 450.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 53 -
point it enters a competitive arena to compete with other sources of fungible gas.
There is often only one producer on a production site (field) and the capacity of the
pipeline is tailored to the production capacity. Hence, there is generally no risk of
foreclosure of competing gas producing or supplying undertakings.185
159. In the exceptional case where there would be such a risk, Article 34 of the
Directive – requiring Member States to ensure that natural gas undertakings and
eligible customers are able to obtain access to these networks – applies.
160. As explained, the regulatory framework on upstream pipeline networks is based on
their objective technical and economic specificities compared to other gas
infrastructure and in particular transmission pipelines.
161. Russia fails to address the core rationale about the different role of upstream
pipelines networks vis-à-vis transmission pipelines. Russia seeks to ignore this
point by focusing on the issue of where the processing plant is located in upstream
pipeline networks. However, what is characterising upstream pipeline networks is
not where the processing plant is located but the fact that they are inherently linked
to the "upstream" sector, i.e. the production of gas. Upstream pipeline networks
are dedicated lines that convey gas either to a processing plant or terminal (where
the gas will be processed) or to a final coastal landing terminal (where the pressure
is reduced and the gas is filtered and heated before being injected into a
transmission network). They are situated alongside production facilities and
connect these facilities to the transmission system.
162. Upstream pipeline networks thus could be seen as a "one-way highway" (after all,
gas does not flow toward the production facility but from it) that is tailored to the
capacity of the linked production facility or facilities. Upstream pipeline networks
have the sole purpose of bringing the gas from the production site to a
transmission network (and not directly to a customer), so that the gas can be
transmitted further downstream. A transmission pipeline, though it may flow in a
predominant direction, may reverse its dominant flow for commercial reasons,186
or may flow contractually in both directions simultaneously because the
185 EU's responses of 12 October 2016, para. 10; EU's first written submission, para. 450.
186 Transmission pipelines can be reversed to flow gas backwards.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 54 -
transmission system is comprised of pipelines linking both systems and customers
to those systems. It is clear that a pipeline that is ancillary to production will never
reverse its dominant physical flow.
163. Transmission pipelines concern a further sector downstream – they connect
markets downstream. They collect gas from all possible sources (upstream pipeline
networks, storage facility, processing plant, LNG terminal, etc.), often allowing
flow of gas in both directions of a pipeline, connect to customers, distribution
networks or storage facilities as exit points and have capacity tailored to the
customers and markets they serve.
164. As a result of their different nature and function, the risk to competition in the case
of upstream pipeline networks and transmission pipelines is very different. Due to
their capacity being designed for the production capacity of the production
facilities at their starting point, upstream pipeline networks generally do not
operate in a competitive environment: they are constructed along with production
facilities and cater to the latter specifically. Hence, the use of such networks is of
interest only for the owners of the production sites in question.
165. Moreover, unlike transmission pipelines, upstream pipeline networks do not
deliver gas to individual customers. Therefore, they do not constitute essential
facilities or natural monopolies that would hinder the development of a
competitive market.
166. Furthermore, whereas the shippers in a transmission network compete for the
limited capacity of that network, or for the capacity of an interconnector between
two transmission networks, this is typically not the case for upstream pipeline
networks. Being built to cater to specific production sites, their capacity of
upstream pipelines is matched to the expected level of production of such sites.
Conversely, the design of a transmission network is not directly driven by the
capacity requirements of shippers to flow gas around the network, which would
indeed be impossible, given the wide variety of entry and exit points in such a
system and the complexity resulting from trading between the various participants.
This necessarily leads to situations where shippers compete for access to the
capacity of the transmission system.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 55 -
167. The EU rules reflect the above-mentioned technical and economic differences and
resulting different risk for discrimination in the operation of the upstream pipeline
networks. In fact, the distinction between upstream pipeline networks and
transmission networks is not a novelty of the Third Package, but has existed in EU
legislation since the so-called First Energy Package, i.e. Directive 98/30/EC of the
European Parliament and of the Council of 22 June 1998 concerning common
rules for the internal market in natural gas. Such a distinction between upstream
and downstream (transmission) segments is well known in gas and oil activities. In
fact, Russia's own regulatory framework seems to recognise this same
distinction.187
2.6.3.2 Russia errs when claiming that Russian pipelines would
never be eligible to qualify as upstream pipeline networks
168. Russia alleges that only "pipelines owned and controlled by the Norwegian
companies delivering Norwegian and EU-origin natural gas to the EU"188
can be
upstream pipeline networks, and "not any pipelines that deliver gas of Russian or
any other origin to the EU".189
According to Russia, there are "no examples of
Russian pipelines qualifying as upstream pipeline networks under the Directive
even though such pipelines, their operators and the gas they deliver are identical to
the Norwegian pipelines concerned".190
169. The European Union strongly contests Russia's allegations.
The legislative history contradicts Russia's 2.6.3.2.1
allegation that the "upstream pipelines networks" definition is
"tailored to apply solely to Norwegian pipelines"
170. Russia seeks to portray the "upstream pipeline networks" definition as being
"drafted by the Norwegian government" and "tailored to apply solely to the
187 See Basics of Russian Gas Market Regulations,
http://www.fief.ru/img/files/5_Basic_of_RU_Gas_Market_Regulations.pdf (Exhibit EU-126),
referring to "Upstream (exploration & production)", "Midstream (processing, transmission,
storage)" and "Downstream (distribution, supply & use)" segments and the different Russian legal
instruments applicable to them.
188 Russia's responses of 12 October 2016, para. 92.
189 Russia's responses of 12 October 2016, para. 92.
190 Russia's responses of 12 October 2016, para. 92.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 56 -
Norwegian pipelines".191
However, the documents that Russia cites are not EU
documents.192
171. In fact, the drafting history of Directive 98/30/EC indicates that the intention of
including the definition of upstream pipeline networks has been precisely the
opposite to what Russia alleges. This definition193
and the corresponding
substantive provision in Article 23 of the Directive have been included not in order
to exempt upstream pipeline networks from the regime of the Directive, but in
order to subject such upstream pipeline networks to legal requirements of third
party access.
172. The original Commission proposal for the Directive did not include rules on
upstream pipeline networks.194
It defined "transmission" as "the transport of
natural gas through a high pressure pipeline in view of its delivery to customers".
In the adoption process for the Directive, it became clear that such a definition
could not include pipelines coming directly from the production field and carrying
the gas to the transmission networks, since, as discussed above, in view of their
function, such pipelines do not deliver gas to customers.
173. It was however considered necessary that such pipelines are also covered by the
regime of the Directive so that a comprehensive legal regime for non-
discriminatory access to all types of gas infrastructure was set out. For these
reasons, the definition of upstream pipeline networks and the corresponding
requirement for fair and open access to such infrastructure were included in Article
191 Russia's responses of 12 October 2016, para. 193.
192 None of the "Reports" that Russia cites in its response to Panel's Question 10 is an EU document,
but rather a UK source. However, even those documents indicate that the reasons for introducing
the regime of upstream pipeline had been the different competitive concerns that exist in case of
such pipelines and in case of transmission pipelines. These documents also mention that such a
view has been supported by the gas industry and this has been the case precisely because, as
explained above, the distinction between upstream, midstream and downstream gas sectors exists
objectively in the gas sector. Moreover, the reason why the Norwegian offshore pipelines might be
mentioned in documents, such as those invoked by Russia, issued close to the adoption of the
Directive is that such pipelines already existed at the time of the adoption of the Directive. In
contrast, no Russian offshore pipelines existed at the time, which would explain why they are not
mentioned in any documents from that period. Indeed, the Russian offshore pipeline – Nord Stream
1 (the on-shore extension of which are the exempted Opal pipeline and the regulated NEL pipeline),
was built and became operational years later - in 2012.
193 Article 2 Nr. 2 Directive 98/30/EC.
194 Commission proposal for the First Gas Directive (Directive 98/30/EC), (Exhibit EU-127).
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 57 -
23 of Directive 98/30/EC as adopted. It is evident from the drafting history of the
Directive that the inclusion of such rules has been motivated by a desire to
"achieve a competitive market in natural gas", taking into account the "economic,
technical and operational characteristics of such networks"195
which are not
identical to those of transmission pipelines and which necessitated that the rules
for upstream pipeline networks and transmission pipelines are not identical.196
Several facts contradict Russia's allegation that the 2.6.3.2.2
upstream pipeline networks definition will never be available for
Russian pipelines
174. Setting the legislative history aside, this portrayal by Russia that the upstream
pipeline networks definition will never be available to Russian pipelines is
contradicted by several facts.
175. First, access to the productive regions of the EU is open to Russian companies and
is governed by the Hydrocarbons Licensing Directive,197
under which non-
discriminatory awards of production licenses (and the therefore ancillary right to
build upstream pipelines) is unconditional.198
176. Second, contrary to what Russia argues, the EU definition of upstream pipeline
networks is not overly broad, but in line with the industry understanding of
upstream pipelines. There are many industry definitions similar to the EU one.199
195 Drafting history of the First Gas Directive (Directive 98/30/EC), (Exhibit EU-128) (BCI).
196 See also Recital 25 of Directive 98/30/EC, which indicates that the rationale for the rules on
upstream pipeline networks is based on their operational and economic characteristics: "Whereas,
in order to achieve a competitive market in natural gas, provision should be made for access to
upstream pipeline networks; whereas separate treatment is required as respects such access to
upstream pipeline networks, having regard, in particular, to the special economic, technical and
operational characteristics relating to such networks; whereas the provisions of this Directive do not
in any event affect national taxation rules".
197 Directive 94/22/EC of the European Parliament and of the Council of 30 May 1994 on the
conditions for granting and using authorizations for the prospection, exploration and production of
hydrocarbons (Exhibit EU-129).
198 The European Union has never exercised the powers in Article 8 (3) of the Directive.
199 E.g. https://www.eia.gov/pub/oil_gas/natural_gas/analysis_publications/ngpipeline/process.htm'
"Gathering Lines – These small-diameter pipelines move natural gas from the wellhead to the
natural gas processing plant or to an interconnection with a larger mainline pipeline";
http://www.spectraenergy.com/Natural-Gas-Oil-101/Glossary-of-Energy-Terms/G/ "Gathering
Line – Network-like pipeline that transports natural gas from individual wellheads to a compressor
station, treating or processing plant or main trunk transmission line. Gathering lines are generally
relatively short in length, operate at a relatively low pressure, and are small in diameter.";
http://www.gie.eu/KC/gasinfrastructure.html "Upstream pipeline – Underground or undersea gas
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 58 -
The logic of these definitions is that an upstream pipeline or a gathering pipeline
has to be treated as such until it brings the gas to a market where connections with
transmission pipeline exists, so that the gas could be transported further
downstream to markets and consumers by transmission pipelines. This connection
could happen already at a processing plant but could happen also at a later stage,
i.e. if the processing plant is located very close to the production site.
177. Third, if there are currently no Russian pipelines that qualify as upstream
pipelines, this is because they do not meet the conditions of the definition. The
reason why the existing Russian pipelines would not fall under the definition of
upstream pipeline networks is not related to the part of this definition challenged
by Russia (that upstream pipeline networks are not only those that connect to a
processing plant but also a final coastal landing terminal) but to the very beginning
of the definition – the fact that upstream pipeline networks connect a production
facility.
178. In fact, Russia itself does not dispute this element of the definition. Russia notes
that "no Russian pipelines are currently 'used to convey natural gas from one or
more such [gas production] projects to a processing plant or terminal or final
coastal landing terminal'".200
According to Russia, this is because "Russian
pipelines that transport Russian-origin gas typically travel overland from Russia to
the EU" and "[e]n route, the Russian gas transported via these pipelines enters the
Russian transmission system."201
This is precisely why it is justified not to treat
these pipelines as "upstream pipeline networks". The underlying reason for the
specific rules for upstream pipeline networks (i.e. the operational specificities and
the related absence of a comparable competitive concern applicable to
transmission pipelines) is thus entirely absent for the current Russian pipelines,
which form a large and interlinked transmission system: the existing Russian
pipelines are connecting a transmission network to another transmission network
rather than a production facility to a transmission network.
pipelines used for the transportation of natural gas from production fields to transmission
networks".
200 Russia's responses of 12 October 2016, para. 92.
201 Russia's responses of 12 October 2016, para. 92.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 59 -
179. This would have also applied to the planned Southstream project subsequently
cancelled by Russia, to which Russia refers in its responses to the Panel's
questions.202
Southstream would, in fact, have been linked to the Russian
transmission system and the gas transported via SouthStream, after having been
transported for long distances in the general transmission system, combined with
gas from many fields, and using gas storage, would not have been directly
dependent on the current output of any particular gas field.
180. Hence, nothing in the definition prevents that a Russian pipeline that would
directly connect a gas production field in Russia to a processing plant or terminal
or final coastal landing terminal would be qualified as an upstream pipeline
network. In such case, the relevant provisions in the Directive, including the
obligation in Article 34 for Member States to ensure that natural gas undertakings
are able to obtain access to upstream pipeline networks, would apply.
181. Russia is also mistaken when it suggests that Gassco in Norway "is free to develop
its export pipeline network and to control the supply and placement of its gas on
the EU market as it sees fit".203
In practical terms, the Norwegian offshore
pipelines are operated under third party access rules by Gassco,204
as mandated by
Article 34 of the Directive.
2.6.3.3 Russia cannot demonstrate that gas carried through an
upstream pipeline network has a competitive advantage over gas
carried through a transmission pipeline
182. Russia has not demonstrated that the application of Directive 2009/73/EC to
upstream pipeline networks modifies the conditions of competition to the
detriment of gas from Russia. There is no reason why the application of the
unbundling requirement to transmission pipelines would translate into a
competitive disadvantage for gas carried over such pipelines when compared to
gas carried over an upstream network, where only the Member State obligation to
202 Russia's responses of 12 October 2016, para. 96.
203 Russia's responses of 12 October 2016, para. 95.
204 Pursuant to the Norwegian legislation such as the Act relating to petroleum activities. See also the
information available at: The Norwegian Gas Transportation System,
http://www.statoil.com/AnnualReport2012/en/OurOperations/BusinessAreas/MarketingProcessing
AndRenewableEnergy/NaturalGas/Pages/TheNorwegianGasTransportationSystem.aspx (Exhibit
EU-130).
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 60 -
ensure access for competitors according to the provisions in Article 34 of the
Directive applies.
183. Russia in fact argues, once more, that Russian gas producers should be able to
control access to transmission networks in order to foreclose competition in the
gas market,205
leading to higher prices and less choice for consumers. This would
undermine the very core of free competition in the EU market for gas. The
European Union has also explained that, pursuant to Article 34 of the Directive,
Member States have the obligation to ensure competition and prevent the abuse of
a dominant position.206
Hence, equal opportunities are guaranteed to all gas, no
matter its origin.
184. Russia also misleadingly suggests that the "EU has acknowledged the 'increases in
costs and loss of efficiency' that Gassco would have been subject to"207
if certain
of its pipelines would, rather than being upstream pipeline networks, be qualified
as transmission pipelines. Russia first of all suggests that this statement originates
with the EU, while, in fact, it merely paraphrases (incorrectly) Norway's and gas
industries' views on the First Gas Directive, summarized in a UK House of Lords
paper of November 1997.
185. Moreover, Russia takes the phrase "increases in costs and loss of efficiency" out of
its context, suggesting that objections were made against applying the First Gas
Directive also upstream because it would allegedly deprive the upstream
undertakings from monopoly profits. The contrary was in fact argued: precisely
because there was a "lack of any upstream monopoly and the presence of many
smaller, cost-sensitive enterprises", extending the scope of the Directive upstream
"would do little to contribute to the EU's objectives of increasing competition" in
gas markets in the EU.208
This is perfectly in line with the rationale that the
European Union has explained for not extending the unbundling requirement to
upstream pipeline networks: the competitive concern that exists for transmission
205 Russia's responses of 12 October 2016, paras. 95, 484.
206 EU's first written submission, para. 457; EU's responses of 12 October 2016, para. 9.
207 Russia's responses of 12 October 2016, para. 484, referring to Exhibit RUS-116.
208 Exhibit RUS-116, para. 47.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 61 -
pipelines is not present, save for exceptional situations, for upstream pipeline
networks.
186. Moreover, the statements also signal the "technical complexities" and concerns
that arise from allowing, under all circumstances, other gas producers to connect to
the upstream pipeline network.209
Applying the First Gas Directive to upstream
pipeline networks would lead to "increases in costs and loss of efficiency" of the
undertakings because the production at the gas field would be disrupted when
other companies would connect to the pipeline directly connecting the gas field to
the processing plant, terminal and final coastal landing terminal, after which the
pressure could be controlled. Hence, the reason for not extending the Directive
upstream was not to enable gas producers to increase prices for consumers. It was
to ensure that gas extraction would remain technically possible.
2.7. CLAIM XIII: RUSSIA'S CLAIM OF VIOLATION OF ARTICLE III:4 OF THE GATT 1994
BECAUSE THE DIRECTIVE WOULD ACCORD RUSSIAN GAS TREATMENT LESS FAVOURABLE
THAN LIKE DOMESTIC GAS TRANSPORTED VIA UPSTREAM PIPELINE NETWORKS (RUSSIA'S
CLAIM 14)
187. Russia also makes a discrimination claim with respect to upstream pipeline
networks under Article III:4 of the GATT 1994. As explained in the European
Union's first written submission,210
and for the same reasons as explained in
paragraphs 156-186, above, Russia's claim must fail: Russia errs when claiming
that Russian pipelines would never be eligible to qualify as upstream pipeline
networks. Further, Russia cannot demonstrate that the measure at issue provides a
competitive advantage to domestic EU gas when compared to imported gas.
3. THIRD COUNTRY CERTIFICATION
3.1. CLAIM XIV: ARTICLE XVII GATS (RUSSIA'S CLAIM 15)
188. For the reasons set out in the EU's first written submission211
, the SoS certification
requirement provided for in Article 11 of the Gas Directive is justified under
Article XIV(a) GATS. More precisely, the European Union has demonstrated that:
209 Exhibit RUS-116, para. 47.
210 EU's first written submission, para. 450.
211 EU's first written submission, paras. 475-544.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 62 -
i) the policy objective pursued by the SoS certification requirement falls within the
scope of Article XIV (a) GATS; ii) the SoS certification requirement is necessary
to achieve its policy objective; and iii) the SoS certification requirement is applied
in conformity with the requirements of the chapeau of Article XIV GATS.
3.1.1. The policy objective pursued by the SoS certification
requirement falls within the scope of Article XIV (a) GATS
189. The European Union has shown that the security of supply of energy is a
"fundamental interest" of the EU society, as reflected in the EU's law and policies;
and that foreign control of TSOs and transmission system owners poses "genuine
and sufficiently serious threats" to such fundamental interest, as required by
footnote 5 to Article XIV (a) GATS.212
3.1.1.1 SoS is a "fundamental interest" of the EU society, as
reflected in EU's law and policies
190. In its first oral statement, Russia said that "Russia does not necessarily agree that
SoS is an EU fundamental interest".213
By way of justification for this cryptic
assertion, Russia limited itself to state that:
The Directive and Member State laws do not define SoS, nor
describe how it relates either to Article 11, and the third-country
certification provision, or to the prospects of foreign persons
controlling TSOs.214
191. The European Union fails to see why the absence of a legal definition of SoS in
the Gas Directive, or in the transposing laws of the EU Member States, should
have the implication that SoS cannot qualify as a "fundamental interest" of the
European Union. As explained in the EU's first written submission215
, SoS is one
of the core objectives of the EU's energy policy referred to in Article 194 TFEU
and underpins all the legislation enacted by the European Union in the field of
energy. In any event, while Article 11 of the Gas Directive does not define the
notion of SoS, that provision and the accompanying recital do provide criteria for
212 EU's first written submission, paras. 478-526.
213 Russia's first oral statement, para. 59. Underlining added.
214 Russia's first oral statement, para. 59.
215 EU's first written submission, paras. 490-491
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 63 -
applying that notion216
. Moreover, the notion of SoS is addressed in numerous
provisions of the EU's energy legislation, all of which provide context for the
interpretation of Article 11 of the Gas Directive217
. Further guidance can be drawn
from policy documents, as well as from the certification opinions and decisions
already issued by the Commission and the NRAs under Article 11 of the Gas
Directive.218
192. As regards Russia's second objection, the relationship between SoS and Article 11
of the Gas Directive (and the third-country certification provision stipulated
therein) is apparent from the express terms of that provision and has been
described in detail in the EU's first written submission.219
To recall, Article 11(3)
of the Gas Directive sets forth the substantive requirements for the certification of
TSOs within the scope of Article 11. It provides that the certification is to be
refused in two instances: when the entity concerned does not comply with the
relevant unbundling requirements of Article 9220
; and, when it has not been
demonstrated
[…] to the regulatory authority or to another competent authority
designated by the Member State that granting certification will
not put at risk the security of energy supply of the Member State
and the Community.221
193. Thus, by its own express terms, the SoS requirement included in Article 11 of the
Gas Directive is specifically aimed at ensuring the security of gas supply in the
European Union.
194. Lastly, the European Union does not understand what Russia means by the
"prospects of foreign persons controlling TSOs" or how the relationship between
SoS and those "prospects" would be relevant in order to determine whether SoS is
a fundamental interest of the European Union.
216 EU's first written submission, paras. 468-471 and 636-637.
217 EU's first written submission, para. 638.
218 EU's first written submission, paras. 639-640.
219 EU's first written submission, paras. 465-467.
220 Article 11(3) a) of Directive 2009/73/EC.
221 Article 11(3) b) of Directive 2009/73/EC.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 64 -
195. In its response to Panel Question 96, Russia attempts a new and different line of
argument. Building upon an observation submitted by Japan, Russia contends that
SoS is an instrument or means to achieve other interests, such as ensuring the
health, life, security and well-being of EU citizens. According to Russia, "it is in
fact the latter concepts that are fundamental interests of the EU society"222
, rather
than ensuring SoS. The European Union finds this distinction artificious and,
ultimately, irrelevant.
196. Russia objects that the concept of SoS is "too general and overly broad"223
to
qualify as a fundamental interest of society. Yet the fundamental interests
identified by Russia are much broader. Indeed, those interests are so broad that
most, if not all, other interests of society could easily be characterized as
instruments or means to achieve them. For example, the panel in US – Gambling
agreed with the United States that preventing criminal activity was a fundamental
interest of the United States.224
Yet, just like SoS, that interest could be regarded as
a means or instrument to protect the life, health, security and well-being of the
U.S. citizens.
3.1.1.2 TSOs controlled by persons of third countries pose a
genuine and sufficiently serious threat to SoS in the EU
197. As explained in the EU's first written submission225
, foreign control of a TSO or,
where it is a different entity, of the transmission system owner poses "genuine and
sufficiently serious threats" to SoS in the European Union. The existence of such
threats can be inferred from the interaction of the following circumstances:
TSOs and transmission system owners play a critical role in ensuring SoS. For
that reason, they may undermine SoS, either by failing to comply with the legal
obligations imposed upon them by the EU energy legislation in order to ensure
SoS, or by failing to act in accordance with their own commercial interest,
222 Russia's response to Panel Question 96, para. 408.
223 Russia's response to Panel Question 96, para. 408.
224 Panel report, US – Gambling, para. 6.469.
225 EU's first written submission, paras. 507-526.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 65 -
contrary to the assumption on which the market based mechanisms stipulated
in that legislation are premised;226
foreign governments have the means to require or induce effectively the TSOs
and transmission system owners controlled by them or by their nationals to
undermine the EU's SoS policies in the fashion described in the previous
bullet;227
and
under certain circumstances, foreign governments have strong incentives to
require or induce the TSOs and transmission system owners controlled by them
or by their nationals to undermine the EU's SoS policies in the ways described
in the first bullet by using the means mentioned in the second bullet.228
198. The threats to SoS are compounded by the fact that, where the TSO or the
transmission system owner is controlled by the government or by persons of a
third country, it will be more difficult in practice for the EU authorities to enforce
effectively the legal obligations imposed by EU law upon the TSOs or the
transmission system owner with a view to ensuring SoS.229
199. Russia contends that the threats to SoS described by the European Union are
"neither genuine nor sufficiently serious"230
and that "the threats highlighted by the
EU are based on pure speculation rather than evidence".231
200. The European Union observes that Russia does not appear to contest that TSOs
and transmission system owners play a critical role in ensuring SoS, or that foreign
governments have the necessary means to require or induce the TSOs and
transmission system owners controlled by them or by their nationals to act in ways
that have the effect of undermining the EU's SoS policies. Nor does Russia dispute
that, where the TSO or transmission system owner is controlled by a government
or by persons of a third country, it will be more difficult to enforce effectively the
obligations imposed by EU law with regard to SoS.
226 EU's first written submission, paras. 496-506 and 512-513.
227 EU's first written submission, paras. 514-519.
228 EU's first written submission, paras. 511-513.
229 EU's first written submission, paras. 520-526.
230 Russia's first oral statement, para. 61.
231 Russia's first oral statement, para. 60.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 66 -
201. Instead, the thrust of Russia's objections is the allegation that the European Union
merely "speculates"232
that third-country governments may have incentives to
undermine the EU's SoS policies and that the European Union "presents no
evidence that such threats actually exist"233
. Russia does not specify what kind of
evidence should be provided by the European Union to establish the existence of
threats to SoS. Nonetheless, Russia appears to believe that only evidence of actual
disruptions of supply could be relevant for that purpose.
202. Russia's objections disregard the way in which the SoS certification requirement
operates and the reasons which led to its introduction. The threats that the SoS
certification requirement seeks to prevent are largely the result of the liberalisation
measures introduced by the Third Energy Package, of which the SoS certification
requirement is an essential component. Traditionally, the gas transmission markets
of the EU Member States have been dominated by vertically integrated
monopolists controlled by the EU Member States themselves or by persons of the
EU Member States. In that context the threats to SoS resulting from foreign
control of gas undertakings were, depending on the EU Member State, inexistent
or at least very limited. The Third Energy Package, and in particular the
unbundling requirements, has opened new opportunities to foreign investment in
the EU gas transmission market. The European Union welcomes that investment,
which will, as a general rule, contribute to enhance competition and SoS. In
exceptional cases, however, foreign TSOs may, for the reasons recalled above,
pose a genuine threat to SoS. Hence the need to put in place, as part of the Third
Energy Package, a specific mechanism for the certification of third country
controlled TSOs in order to assess in each case whether the TSO concerned poses
a threat to SoS. That mechanism operates in a preventive manner. In other words,
it seeks to detect and prevent ex ante disruptions of supply rather than addressing
the effects of those disruptions once they have already materialised.
203. For the above reasons, the European Union cannot be required to prove, in order to
substantiate the existence of the threats to SoS described above, that such threats
have already materialised in the past. Rather, it is enough for the European Union
232 Russia's first oral statement, para. 60.
233 Russia's first oral statement, para. 60
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 67 -
to show that the existence of such threats can be reasonably inferred from the
attendant facts. The European Union has done so by showing that the threats to
SoS which it has identified result from potential actions or omissions by foreign
governments which are well within the powers of those foreign governments and
which, moreover, would be in those foreign governments' own interest under
plausible circumstances.
204. More precisely, the European Union has explained why the interests of foreign
governments may come into direct conflict with the interests of the European
Union in ensuring SoS. For example, to say that a country supplying gas to the
European Union may have an interest in limiting supplies from other countries to
the European Union, so as to maximise its own exports, is not mere speculation,
but a reasonable inference based on reasonable expectations about the rational
behaviour of a foreign government. Nor is it mere speculation to say that the
government of a third country facing a shortage will have an interest in diverting
supplies of gas to its own territory at the expense of the users in the European
Union. It is also not speculative to say that a foreign government may seek to use
its control over the supply of energy products in order to advance its foreign policy
objectives. There are well-known examples of this: from the oil embargo in 1973
to the interruption of gas supplies to Ukraine (and, as a result, to the European
Union) in 2006 and, again, in 2009.
205. The European Union agrees that in many cases third country TSOs will not pose a
threat to the EU's SoS. But in assessing the seriousness of a threat for the purposes
of Article XIV (a) GATS account must be taken not only of the frequency with
which a threat may materialise, but also of the potential gravity of the effects,
should the threat materialise in one case. The effects of even an isolated and
temporary disruption of the supply of gas may be very severe, which justifies the
introduction of a preventive mechanism to detect and address in advance all threats
of disruption.
206. Russia further notes that "requiring Gazprom to satisfy the third country
certification requirements in the EU would not address the EU's concerns with
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 68 -
supply disruptions outside the EU".234
However, the EU's concerns extend also to
the threats of disruption within the European Union. Moreover, the interruption of
gas supplies to Ukraine in 2006 and 2009 provides a compelling illustration of
how foreign governments may find in their own interest to disrupt gas supplies to
another country in order to advance their foreign policy objectives, one of the
types of threats to SoS identified by the European Union.
3.1.2. The SoS certification requirement is necessary to achieve its
policy objective
3.1.2.1 Relative importance of the objective
207. Russia has not contested that that the objective of ensuring SoS is considered of
fundamental importance by the European Union.235
3.1.2.2 Contribution to the objective
208. Russia contends that the SoS certification requirement "makes no contribution,
material or otherwise, to ensuring SoS"236
. By way of justification for this
sweeping assertion, Russia limits itself to argue that "the EU has numerous other
mechanisms in place to address its alleged concerns".237
Russia then cites some
legal provisions included in the Third Energy Package which impose obligations
on all TSOs and other gas undertakings in order to ensure SoS.238
209. Russia's argument fails to recognise the concerns which the SoS certification
requirement seeks to address. The European Union has explained in detail239
that
the Third Energy Package does impose numerous obligations on all TSOs and
other gas undertakings (irrespective of whether they are controlled by EU persons
or persons of third countries) in order to ensure SoS. The threats to SoS identified
by the European Union stem from the fact that the governments of third countries
may require or induce the TSOs or transmission system owners controlled by them
234 Russia's first oral statement, para. 60.
235 See EU's first written submission, para. 527.
236 Russia's first oral statement, para. 61.
237 Russia's first oral statement, para. 62.
238 Russia's first oral statement, para. 62.
239 EU's first written submission, paras. 496-506.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 69 -
or by persons of those third countries to act in a manner that undermines the EU's
SoS policies, inter alia by failing to comply with the legal obligations to which
Russia refers. The mere existence of those legal obligations does not, therefore,
render superfluous the SoS certification requirement. That requirement is
necessary in order to detect and address in advance the risk that TSOs and
transmission system owners controlled by governments or persons of third
countries will not comply with such obligations.
3.1.2.3 Restrictiveness of the measure
210. Russia argues that the SoS certification measure is trade-restrictive because it
creates "uncertainty".240
But such uncertainty is inherent in any ex-ante
authorization mechanism. Moreover, in the case at hand it is reasonably
circumscribed because the competent authorities must decide within the time-
limits provided in Article 11 of the Gas Directive, which are the same as those
applicable to the certification of other TSOs under Article 10.
211. Russia further argues that the SoS certification measure is trade restrictive because
it "grants Member States essentially unlimited discretion".241
As shown by the
European Union in its response to Russia's claim under Article VI:1 GATS,
however, this allegation is baseless.242
212. Russia also argues that the SoS certification requirement is trade restrictive
because "the Commission recommends restrictions, leading to decisions that
unfairly restrict the supply of services from some Members compared to others".243
Again, as shown by the European Union in its response to Russia's various claims
under Article II:2 GATS, this allegation is unfounded.244
3.1.2.4 Alternative measures
213. The European Union considers that there are no reasonably available alternative
measures which, while being less trade restrictive, would make an equivalent
240 Russia's oral statement, para. 63.
241 Russia's oral statement, para. 63.
242 EU's first written submission, paras. 636-641.
243 Russia's oral statement, para. 63.
244 EU's first written submission, paras.585-616.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 70 -
contribution to achieving the desired level of protection.245
In accordance with
well-established case law, it is for Russia to identify possible alternative
measures.246
214. In its first oral statement Russia said that the European Union could have required
as an alternative measure, the "same set of procedures from all operators,
regardless of origin"247
. As explained in the EU's response to Panel Question 105,
this suggestion is most unclear and fails manifestly to meet Russia's burden of
proof.
215. As an additional alternative measure, Russia mentioned the enactment of what
Russia calls a "blocking statute".248
According to Russia, the European Union
would have used this approach in Council Regulation (EC) No 2271/96.249
However, as explained below, that regulation has a very different purpose and
operates in a very different way.250
216. In essence, Council Regulation (EC) No 2271/96 provides that EU companies and
persons residing in the European Union shall not comply with certain extra-
territorial laws adopted by other countries which affect international trade between
the European Union and third-countries (other than the countries enacting the
extra-territorial laws). This prohibition was enacted because those extra-territorial
laws were regarded by the European Union as incompatible with international law.
Prior to the enactment of Council Regulation (EC) No 2271/96, the EU companies
and persons concerned were not prohibited under EU law from complying with the
extra-territorial laws at issue. In other words, Council Regulation (EC) No 2271/96
does not purport to enforce pre-existing obligations of EU companies and persons
under domestic EU law, but rather to impose upon them a new obligation under
245 Appellate Body Report, US – Gambling, para. 308. See also e.g. Appellate Body Report, Brazil –
Retreaded Tyres, para. 156; and Appellate Body Report, EC – Seal Products, paras. 5.169 and
5.261. 246 Appellate Body Report, Brazil – Retreaded Tyres, para. 156. 247 Russia's first oral statement, para. 62.
248 Russia's first oral statement, para. 62.
249 Russia's first oral statement, para. 62. See also Russia's response to Panel Question 101, paras.422-
423.
250 A copy of Council Regulation (EC) No 2271/96 has been provided by Russia as Exhibit RUS –
156.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 71 -
domestic EU law in order to counter the effects of a violation of international law
by a third country.
217. In contrast, the "blocking statute" envisaged by Russia would seek to ensure
compliance with already existing obligations under domestic EU law. In Russia's
own words, its proposed "blocking statute" "would have put the legal onus in the
EU company to comply with EU law".251
But this is wholly unnecessary: TSOs
controlled by third country governments or persons of a third country already have
"the legal onus" to comply with existing EU legal provisions under the Third
Energy Package aimed at ensuring SoS. The "blocking statute" proposed by Russia
would thus merely add a superfluous layer of domestic EU regulation. It would fail
to address the EU's concern that foreign governments may require or induce TSOs
controlled by those governments or by persons of those third countries not to
comply with existing EU legislation. Just like a foreign government can require or
induce a third country TSO not to comply with the obligations of the Third Energy
Package aimed at ensuring SoS, it could do the same with regard to the "blocking
statute" proposed by Russia. Indeed, nothing would prevent the third country
concerned from enacting its own "blocking statute" in order to block compliance
with the "blocking statute" proposed by Russia.252
218. To illustrate this with an example, the European Union recalls that at the first
hearing Russia's counsel emphasised that "Gazprom is Russia and Russia is
Gazprom". In view of this identity, could the European Union really trust that
Gazprom/Russia (or any other gas suppliers controlled and owned by a third
251 Russia's response to Panel Question 101, para. 423.
252 This is more than a mere theoretical possibility. For example, Russia already has in place what
amounts to a "blocking statute". In 2012 the government of the Russian Federation adopted a
presidential decree on "Measures to protect the interests of the Russian Federation when Russian
legal entities engage in foreign economic activity". This decree stipulates that certain Russian
entities of "strategic importance" (which include Gazprom), and their daughter companies, shall not
comply with certain types of requirements imposed on them by a foreign country or organisation
without the prior consent of the Russian government. The types of requirements in respect of which
the companies of strategic importance need prior consent include the requirement to provide
information about their activities; the requirement to make changes to contracts with foreign
counterparts or to other documents relating to their commercial policy in foreign countries; and the
requirement to dispose of stakes held in foreign organisations, the right to carry out business
activities in foreign countries and immovable property situated abroad. See Decree of the President
of Russian Federation No 1285 of 11 September 2012 on Measures to protect the interests of the
Russian Federation when Russian legal entities engage in foreign economic activity and
implementing measures (Exhibit EU-131).
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 72 -
country) would choose to comply with Russia's proposed EU blocking statute,
rather than with the instructions received from Russia/Gazprom, which
instructions could take the form of a "counter-blocking statute"? Of course, with
this theoretical example the European Union is not suggesting that the TSOs
controlled by the Russian government (or by the governments of other third
countries, such as Norway's Statoil, Azerbaijan's SOCAR or Algeria's Sonatrach)
could never be certified under Article 11 of the Gas Directive.253
Nevertheless, this
example illustrates the obvious limitations of the alternative measure identified by
Russia.
219. For the above reasons, the European Union submits that the "blocking statute"
proposed by Russia would fail to address the threats to SoS identified by the
European Union and, to the extent that it did, it would fail to achieve the same
level of protection against those threats as the SoS certification requirement.
3.1.3. The SoS certification requirement is applied in conformity with
the requirements of the chapeau
220. Russia contends that the SoS certification requirement is not applied in conformity
with the chapeau of Article XIV GATS because it discriminates de iure in favour
of domestic services and service suppliers254
and this difference in treatment
cannot be "rationally related" to its stated policy objective of ensuring SoS.255
221. Russia is wrong on both counts. As explained in the EU's first written
submission256
, the TSOs controlled by persons of an EU Member State do not pose
comparable threats to the EU's SoS. For that reason, the difference in treatment
between them is fully consistent with the objective pursued by the SoS
certification requirement. For the same reason, that difference in treatment does
not amount to "arbitrary or unjustifiable discrimination" within the meaning of the
chapeau.
253 It is recalled that, so far, no Russian TSO has applied for certification under Article 11 of the Gas
Directive. In the case of Gaz-System, where the transmission owner was jointly owned and
controlled by Gazprom, the Polish NRA did grant the certification.
254 Russia's first oral statement, para. 66.
255 Russia's first oral statement, para. 65.
256 EU's first written submission, paras. 535-540.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 73 -
222. Russia does not address the argument and evidence submitted by the European
Union in order to show that domestic and foreign TSOs do not pose comparable
threats to the EU's SoS. Instead, Russia dismisses out of hand that argument and
evidence by asserting that the European Union has not shown that third country
control of TSOs poses any "realistic threat" to SoS.257
The European Union has
demonstrated, however, that Russia's premise is incorrect.258
223. Russia further contends that the SoS certification requirement has been applied
inconsistently with the chapeau because "certain TSO and transmission systems in
which it has interests have been subjected to more restrictive EU certification
conditions than those of other foreign owners"259
and refers to its claims under
Article II:1 GATS. However, as shown by the European Union260
, those claims are
wholly unfounded. The SoS certification requirement does not discriminate, either
de iure or de facto, between service suppliers of different WTO Members, let
alone discriminate in an "arbitrary or unjustifiable" manner.
224. Lastly, Russia argues that discrimination results in part from "ambiguities in the
third country certification standard and the broad discretion granted on NRAS and
the Commission"261
and refers to its claims under Article VI:1 GATS. Again,
however, the European Union has shown that those claims are without
foundation.262
3.2. CLAIMS UNDER ARTICLE XVII GATS CONCERNING OTHER REQUIREMENTS IMPOSED BY
HUNGARY AND LITHUANIA (INCLUDED IN RUSSIA'S CLAIM 15)
225. The European Union reiterates its view that Russia's claims against Articles 20(5)
and 29(4)(3) of Lithuania's Law on Natural Gas and Article 123 of Hungary's Act
on Natural Gas Supply are outside the Panel's terms of reference. 263
The European
257 Russia's first oral statement, para. 65.
258 See Section 3.1.2, above.
259 Russia's first oral statement, para. 66.
260 EU's first written submission, paras. 571-573 and 575-616.
261 Russia's first oral statement, para. 66.
262 EU's first written submission, paras. 632-641.
263 EU's first written submission, paras. 546-551 and 553-556; EU's comments regarding terms of
reference, paras. 27-45.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 74 -
Union takes note of the Panel's decision not to rule at this stage on the preliminary
objections raised by the European Union with regard to each of these three claims.
226. The European Union further notes that Russia has not addressed the EU's rebuttal
on the substance to these three claims.264
3.3. CLAIM XV: ARTICLE II:1 GATS (RUSSIA'S CLAIMS 16 AND 17)
3.3.1. The de jure claim
227. The European Union recalls that the Panel has ruled that the claim under Article
II:1 GATS developed in paragraphs 449-454 of Russia's first written submission
falls outside the Panel's terms of reference.
228. Russia has not submitted any argument or evidence in support of the de iure claim
under Article II:1 GATS set out in the first full paragraph on the third page of
Russia's Panel request. The European Union understands that Russia is not
pursuing this claim.
3.3.2. The de facto claim
3.3.2.1 Terms of reference
229. The European Union notes that Russia has clarified that, contrary to what it had
stated in its response to Panel Question 5, Russia does not challenge under Article
II:2 GATS the third country certification measure as applied in a number of
instances. Instead, Russia challenges that measure as such on a de facto basis.265
230. The European Union, nevertheless, reiterates its view that this claim is outside the
Panel's terms of reference to the extent that Russia alleges that the European Union
applies a more stringent SoS assessment for the certification under Article 11 of
the Gas Directive of Russian TSOs than in the case of TSOs of other countries,
such as TIGF and DESFA. As explained by the European Union266
, this "problem"
is different from the "problem" raised by Russia in its Panel request, where Russia
264 EU's first written submission, paras. 552, 557-558 and 560-562 and EU's response to Panel
Question 102.
265 Russia's response to the EU's comments on terms of reference, paras. 49-51.
266 EU's first written submission, paras. 578-581 and EU's comments regarding terms of reference,
paras. 51-59.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 75 -
claimed that the European Union had acted inconsistently with Article II:1 GATS
by exempting from Article 11 of the Gas Directive the TSOs of other countries.
The European Union takes note that the Panel has declined to rule on this
objection at this stage.
231. In its response to the EU comments on terms of reference, Russia does not address
the objection raised by the European Union. Instead, it seeks to sidestep the issue
by attributing to the European Union the view that Russia should have identified
all relevant evidence in its Panel request267
. It will be obvious to the Panel,
however, that this is by no means the EU's position. The European Union does not
contest that Russia would be entitled to submit additional evidence in support of
the claim set forth in its Panel request, in particular in the form of further examples
of decisions or opinions concerning TSOs of third countries which were not taken
pursuant to Article 11 of the Gas Directive. However, the TIGF and DESFA
opinions do not constitute evidence in support of that claim. Instead, as shown by
the European Union, they constitute evidence in support of a separate and different
claim which was not presented at all in the Panel request, let alone presented in a
sufficiently "clear" manner.
3.3.2.2 Europolgaz is not a service supplier - Gaz-System is not
a Russian service supplier
232. As explained in the EU's first written submission268
, whereas Gazprom controls
jointly Europolgaz (the owner of the Polish section of the Yamal pipeline), neither
Gazprom nor Eurpolgaz operate Yamal. Instead, Yamal is operated by Gaz-
System under the ISO model. Thus, the relevant "service supplier" within the
meaning of Article II:1 GATS is Gaz-System and not Gazprom/Europolgaz. Gaz-
System is a service supplier of Poland and not of Russia. Therefore, even if the
measure provided less favourable treatment to Gaz-System (quod non), such
difference in treatment would fall outside the scope of Article II:1 GATS.
233. In its response to Panel Question 284, Russia appears to suggest that
Gazprom/Europolgaz is a service supplier because, even though it does not
267 Russia's response to the EU's comments regarding terms of reference, para. 56.
268 EU's first written submission, paras. 582-584.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 76 -
provide transmission services, it continues to provide "supply services ".269
For
the reasons explained elsewhere, the European Union considers that what Russia
calls "supply services" are not services at all.270
Therefore, it remains true that the
only service supplier is Gaz-System, which is not a Russian service supplier.
234. Russia further suggests that Gazprom/Europolgaz must be deemed a service
supplier because the Gas Directive imposes certain "cooperation" obligations on
the transmission system owner which “require some degree of active participation
on the part of the system owner to facilitate operation of the system by the ISO”.
271 Russia thus implies that in the ISO model the system owner is involved in the
operation of the system. This is plainly incorrect. While the system owner has
certain obligations under the ISO model, it is clear that the tasks of TSO are
performed by the ISO and not by the system owner. Such obligations do not confer
upon the transmission system owner the possibility to influence the decision-
making of the TSO. In fact, such influence is explicitly prohibited by the Gas
Directive.272
Therefore, again, it remains true that Gaz-System is the sole service
supplier.
3.3.2.3 Legal status of the Commission opinions
235. As explained by the European Union, Commission opinions (including the
opinions issued pursuant to Article 11 of the Gas Directive) are never legally
binding.273
Russia's insistence to the contrary is thoroughly misguided and
disregards fundamental provisions of the TFEU.
236. The passage from the "Commission's facts sheet on Intergovernmental Agreements
on Energy" quoted by Russia in its response to Panel Question 20274
lends no
269 Russia's response to Panel Question 55, para. 284.
270 See footnote 128, above and EU's first written submission, paras. 361-362.
271 Russia's response to Panel Question 55, para. 284.
272 See Article 14(4) of Directive 2009/73/EC, which provides that:
Each independent system operator shall be responsible for granting and managing third-party
access […] the independent system operator shall act as a transmission system operator in
accordance with this Chapter. The transmission system owner shall not be responsible for granting
and managing third-party access, nor for investment planning.
273 EU's response to Panel Question 20, paras. 39-43.
274 Russia's response to Panel Question 20, para. 118.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 77 -
support to Russia's allegations. To begin with, it is obvious that the legal effects of
the Commission opinions under Article 11 of the Directive cannot be properly
determined on the basis of a mere "facts sheet" without any legal status, which
furthermore concerns a Commission proposal relating to an entirely different legal
instrument.
237. Moreover, the passage quoted by Russia does not say or imply anywhere that
failure by an EU Member State to follow a Commission opinion constitutes in and
of itself an infringement of EU law. The sentence underlined by Russia merely
says that, "should a Member State decide to sign an IGA that would be
incompatible with EU law, the Commission would have the possibility to launch
infringement procedures". This sentence is but a mere restatement of the
Commission's general powers under Article 258 TFEU to launch infringement
proceedings whenever it considers that an EU Member State has failed to comply
with any provision of EU law (e.g. with the provisions of the TFEU or of
secondary legislation in the field of energy or public procurement). That sentence
does not have the implication that Commission opinions on the compatibility of
the IGAs with EU law are binding upon the EU Member States. If the Commission
considers that an IGA is incompatible with EU law, it may, as the "guardian of the
Treaties"275
, bring infringement proceedings against the EU Member State
concerned before the Court of Justice in accordance with Article 258 TFEU. But in
those proceedings the Commission will have to show that the IGA is incompatible
with EU law, rather than with the Commission's own previous opinion.
238. Similarly, the Commission cannot bring infringement proceedings against a EU
Member State on the mere ground that a certification decision pursuant to Article
11 of the Gas Directive is incompatible with a Commission opinion. Instead, the
Commission would have to establish that the certification decision is incompatible
with Article 11 as such.
3.3.2.4 Article 54 of the Gas Directive
239. In its first written submission, Russia alleged that jordgas and NABUCCO had
received more favourable treatment than Gaz-System because the competent NRA
275 Cf. Article 17(1) of the TEU.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 78 -
had not conducted a SoS assessment pursuant to Article 11 of the Gas Directive,
even though (according to Russia) both jordgas and NABUCCO are controlled by
persons of third countries.276
240. The European Union has explained277
that Russia's complaint is misguided
because it overlooks that, in accordance with Article 54(1), second subparagraph,
of the Gas Directive, the third country certification regime set forth in Article 11 of
Directive 2009/73/EC did not become applicable until 3 March 2013. For that
reason, all the certifications requested prior to that date were dealt with exclusively
under Article 10 of the Directive, regardless of the nationality of the persons who
controlled the transmission system or the TSO. The applications for the
certification of both jordgas and NABUCCO were made before 3 March 2013,
whereas Gaz-System's application was filed after that date.
241. In its response to Panel Question 73, Russia implies that the date of 3 March 2013
was selected by the EU legislators with the deliberate purpose of exempting
jordgas and NABUCCO from Article 11 of the Gas Directive278
. Russia provides
no evidence to substantiate this accusation. Moreover, Russia's allegations are
contradicted by the following facts:
242. First, it is not uncommon in EU legislation to stipulate different dates of
application for different provisions of the same legal instrument. Often, like in this
case, this is done in order to allow the implementing authorities more time to
prepare themselves adequately for the application of particularly novel or complex
provisions.
243. Second, as of the date of adoption of the Directive on 13 July 2009, the EU
authorities could not have possibly anticipated which TSOs would file applications
before and after 3 March 2013. Nor could they possibly have anticipated the origin
of the persons that would control each TSO at the time where it chooses to file for
certification.
276 Russia's first written submission, para. 465
277 EU's first written submission, paras. 597-599 and 605.
278 Russia's response to Panel Question 73, para. 322.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 79 -
244. Third, the certifications opinions and decisions concerning GASCADE279
and
NEL Gastransport280
, two TSOs owned to 49.98 % and jointly controlled by
Gazprom, were based exclusively on Article 10 of the Directive and do not include
a SoS assessment in accordance with Article 11, because their applications for
certification were submitted prior to 3 March 2013.
245. Fourth, had an application for certification of Gaz-System being filed before 3
March 2013, it would have been processed in accordance with Article 10 of the
Gas Directive instead of Article 11 (as in the case of GASCADE and NEL
Gastransort mentioned above). The European Union notes that Europolgaz was set
up in 1993 and that Gaz-System was entrusted with the operation of the Yamal
pipeline already in October 2010. As of 2009 the European Union could not have
anticipated that Gaz-System would not file for certification before 3 March 2013.
246. Fifth, as already explained by the European Union281
, BOTAS' minority
shareholding did not translate into joint control of NABUCCO. Therefore, even if
NABUCCO had filed for certification after 3 March 2013, that application would
have had to be examined under Article 10 of the Gas Directive. Similarly, the
applications for certification of ONTRAS282
and I-UK283
, where Gazprom had
minority shareholdings not conferring control, were examined under Article 10 of
the Gas Directive.
247. Sixth, the jordgas certification decision relates exclusively to the operation by
jordgas of the NETRA pipeline. Any application by jordgas made after 3 March
2013 relating to other systems would have to be processed under Article 11 of the
Directive.
279 Commission Opinion of 3 December 2012 pursuant to Article 3(1) of Regulation (EC) No
715/2009 and Article 10 of Directive 2009/73/EC - Germany - Certification of GASCADE
Gastransport GmbH, p. 2 (Exhibit EU - 59).
280 Commission opinion of 18 October 2013 on BnetzA's draft certification decisions for NEL,
Gasunie Ostsee and Fluxys (Exhibit EU - 78).
281 EU's first written submission, para. 606.
282 See Commission Opinion of 3 December 2012 pursuant to Article 3(1) of Regulation (EC) No
715/2009 and Article 10(6) of Directive 2009/73/EC – Germany – Certification of ONTRAS VNG
Gastransport GmbH (Exhibit EU – 60).
283 See Commission Opinion of 26 March 2013 pursuant to Article 3(1) of Regulation (EC) No
715/2009 and Article 10(6) of Directive 2009/73/EC – United Kingdom – Certification of
Interconnector UK Limited (Exhibit EU-132).
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 80 -
248. The European Union is at a loss to understand the new issue raised by Russia with
regard to the certification of Lietuvos in its response to Panel Question 73284
,
where Russia contends that in Lithuania the third country certification measure
"actually applied as of 1 November 2011" because the deadline for completing the
unbundling of Lietuvos was set as 31 October 2014. As a result, according to
Russia, "Lietuvos was legally precluded from applying for designation as a TSO,
and thus for third country certification, prior to that date".285
249. The SoS certification requirement stipulated in Article 11 of the Gas Directive is
different from the unbundling requirements and applies to all entities within the
scope of the provision, irrespective of the unbundling model. Article 11 of the Gas
Directive was transposed into Lithuania's law by Article 29 of Lithuania's Law on
Natural Gas. Whereas that law entered into force on 1 August 2011, its Article 29
only became applicable from 3 March 2013, as provided for in Article 54 of the
Gas Directive.
250. Russia appears to allege that Lietuvos was precluded from coming into compliance
with the ownership unbundling requirements before the deadline set out in
Lithuania's Law on Natural Gas. This allegation is baseless, as all relevant
deadlines were designating latest dates of compliance and nothing in Lithuanian
law or decisions of Lithuanian authorities precluded Lietuvos from complying
with the requirements and applying for certification at any earlier date.
251. Moreover, Russia does not explain why the alleged facts would amount to
discrimination prohibited by Article II:1 GATS. Nor does Russia explain how that
allegation would support Russia's contention that Lithuania "actually applied" the
third country certification measure as of 1 November 2011.
3.3.2.5 The delays in the certification of Gaz-System do not
affect conditions of competition to its detriment
284 Russia's response to Panel Question 73, para. 324. See also Russia's response to the EU' comments
regarding the terms of reference, para. 52.
285 Russia's response to the EU' comments regarding the terms of reference, para.52.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 81 -
252. As explained in the EU's first written submission286
, Gaz-System was certified by
the Polish NRA on 19 May 2015. The European Union further noted that Russia
had not explained, far less proven, how, in view of this fact, the Commission
certification opinions continued to distort the competitive conditions to the
detriment of Gaz-System (assuming that they ever did so) after the date of
establishment of the Panel (18 July 2015).
253. In response to the Panel Question 30 a), Russia concedes that Gaz-System was
certified by the Polish NRA on 19 May 2015.287
Yet, in response to a further
question from the Panel, Russia is manifestly unable to explain how the
Commission certification opinions continue to affect conditions of competition to
Gaz-System's detriment.288
254. In essence, Russia argues that "the Commission's original delay in issuing a
decision increased the uncertainty regarding Gazprom's supply of its service".289
At the outset, the European Union recalls once again that the Commission does not
issue legally binding decisions, but opinions. Whereas the certification process of
Gaz-System took longer than in the case of DESFA, this reflected the deficiencies
of the initial draft decision notified by ERO, which, unlike RAE's draft decision
concerning DESFA, contained no SoS assessment at all. In turn, this can be
attributed to the particular complexity and novelty of the facts to be assessed in the
case of Gaz-System. Similar delays have occurred also in other cases concerning
the certification of TSOs under Article 10 of Directive 2009/73/EC.
255. Russia has not provided any evidence that the operation of Gaz-System was
impaired in any manner during the process of certification. Gaz-System had
operated Yamal as a TSO well before the application was filed, continued to do so
throughout the certification process and is still doing so at present, without any
apparent interruption or reduction of activity.
256. At any rate, any uncertainty resulting from the delay in issuing the final decision
would have been definitively removed by the Polish NRA's final decision of 19
286 EU's first written submission, paras. 589-594.
287 Russia's response to Panel Question 30 a), para. 146.
288 Russia's response to Panel Question 30 b).
289 Russia's response to Panel Question 30 b), para. 146.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 82 -
May 2015. Therefore, such uncertainty could not continue to affect conditions of
competition to the detriment of Gaz-System as of the date when the Panel was
established.
3.3.2.6 Press release of the European Parliament's press service
on the occasion of the adoption of the TEP
257. In its first oral statement, Russia cited a press release issued by the press service of
the European Parliament as evidence that Article 11 of the Gas Directive was
enacted with the subjective intent of discriminating against Gazprom.290
258. Needless to say, the press releases of the EP's office press have no legal status
whatsoever under EU law. Nor do they commit in any manner the European
Parliament or its members.
259. Moreover, contrary to Russia's assertions291
, the text quoted by Russia is not part
of the press release issued by the EP's press office "upon the adoption of the Third
Energy Package". Instead, it is part of an earlier press release describing the
personal views expressed by one MEP (Mr. La Russa), who acted as rapporteur for
the Industry Committee. That release was issued while the Commission proposal
(which differed from the current text of Article 11 of the Gas Directive) was still
being debated by the EU Council and the EP and, therefore, cannot be read as a
description of the current text of the Directive.
260. In any event, the press release makes it clear that the envisaged clause would apply
equally to all "foreign companies", rather than to Gazprom alone. If the press
release refers explicitly to Gazprom it is probably because at the time Gazprom
had more shareholdings in EU gas undertakings than other third country entities
and because, as mentioned in the press release, Russia/Gazprom was the most
vocal opponent to the envisaged provision while the proposal was still being
debated by the European Parliament.
3.4. CLAIM XVI: ARTICLE III:4 GATT (RUSSIA'S CLAIM 18)
261. Russia has conceded that this claim is outside the Panel's terms of reference.
290 Russia's first oral statement, para. 68.
291 Russia's first oral statement, para. 68.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 83 -
3.5. CLAIM XVII: ARTICLE VI:1 GATS (RUSSIA'S CLAIM 19)
262. In response to Panel Question 85, Russia has clarified that the relevant "acts of
administration" for the purposes of its claim under Article VI:1 GATS are the
national laws enacted by Croatia, Hungary and Lithuania in order to transpose
Article 11 of the Gas Directive, rather than any subsequent act of application of
those laws.292
263. As recalled in the EU's first written submission293
, the Appellate Body has
clarified in EC – Customs Matters that claims under Article X:3(a) GATT may be
addressed not only against the "administration" as such of a legal instrument, but
also against "a legal instrument that regulates the application or implementation of
that instrument".294
In such case, however, the complaining party bears a special
burden of proof. According to the Appellate Body:
If a WTO Member challenges under Article X:3(a) the
substantive content of a legal instrument that regulates the
administration of a legal instrument of the kind described in
Article X:1, it will have to prove that this instrument necessarily
leads to a lack of uniform, impartial, or reasonable administration.
It is not sufficient for the complaining party merely to cite the
provisions of that legal instrument. The complainant must
discharge the burden of substantiating how and why those
provisions necessarily lead to impermissible administration of the
legal instrument of the kind described in Article X:l. 295
264. Russia's claim under Article VI:1 GATS is not addressed against any provision of
Article 11 of the Gas Directive (or of the legal instruments of the EU Member
States concerned transposing that provision into their national laws) that "regulates
the application or implementation" of the SoS certification requirement. Rather,
Russia's claim is addressed against the substantive content of the SoS certification
requirement as such. Therefore, Russia's claim falls outside the scope of Article
VI:1 GATS.
265. Even assuming ad arguendo that Russia's claim could be characterized as being
addressed against legal provisions "that regulat[e] the application or
292 Russia's response to Panel Question 85, paras. 367-371.
293 EU's first written submission, para. 630.
294 Appellate Body Report, EC – Customs Matters, para. 200.
295 Appellate Body Report, EC – Customs Matters, para. 201.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 84 -
implementation" of the SoS certification requirement, Russia has not met the
burden of proof described by the Appellate Body in EC - Customs. Indeed, Russia
has not shown "why and how" the terms of Article 11 of the Gas Directive
"necessarily lead to an impermissible administration" of that provision. Instead,
Russia limits itself, time and again, to "cite the provisions" of Article 11 of the Gas
Directive and the transposing laws of the Member States concerned and to assert,
without providing any evidence, that the terms of those provisions are not
sufficiently precise. This is not enough to meet Russia's burden of proof. In any
event, as explained in the EU's first written submission296
, Russia's allegations that
the notion of SoS is insufficiently precise are unwarranted.
3.6. CLAIM XVII BIS: ARTICLE VI:5 GATS (RUSSIA'S CLAIM 20)
266. Under this heading, the European Union will address various arguments raised by
Russia in its responses to Panel Questions 79 to 84.
3.6.1. Relationship between Articles VI:4 and VI:5 GATS and Article
XVII GATS
267. In response to Panel Question 79, Russia argues that the SoS certification measure
constitutes an "unnecessary barrier to trade in services" within the meaning of
Article VI:4 GATS for the very same reason already invoked by Russia in support
of its previous claim under Article XVII GATS against the same measure, i.e.
because, according to Russia, the SoS certification requirement discriminates
between domestic service suppliers and services and those of other Members.297
Yet, as explained by the European Union in response to the same Panel Question,
that type of "trade barrier" is specifically addressed by Article XVII GATS and is
to be examined exclusively under that provision.298
3.6.2. Letter (b) of Article VI:4 GATS
268. In response to Panel Question 80, Russia argues that the Disciplines on Domestic
Regulation in the Accountancy Sector (the "Accountancy Disciplines") are
296 EU's first written submission, paras. 636-641.
297 Russia's response to Panel Question 79, para. 348.
298 EU's response to Panel Question 79, paras. 196-197.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 85 -
irrelevant because they are not applicable to the service sector at issue. It is, of
course, true that the Accountancy Disciplines do not apply to the service sector at
issue in this dispute (i.e. pipeline transmission services for gas). But this does not
mean that the Accountancy Disciplines are irrelevant for the interpretation of the
GATS provisions invoked by Russia. As explained by the European Union299
, the
Accountancy Disciplines are relevant for that purpose because they implement
Article VI:5 GATS and reflect the Member's shared understanding of letter (b) of
Article VI:4 GATS. As further explained by the European Union, that
understanding contradicts the reading of that provision put forward by Russia in
support of its claims.
269. In response to the Panel Questions 81 and 82, Russia agrees with Japan that the
"quality" of the services at issue includes "the ability to provide a stable and
reliable supply of energy reliability".300
Russia goes on to assert that the measure
at issue is "more burdensome" than necessary to ensure that objective. But it
makes no meaningful effort to substantiate this assertion, even though it is
undisputed that Russia bears the burden of proof under Article VI:5 GATS.301
Instead, Russia limits itself to make vague and imprecise references to its previous
arguments in response to the EU's defence under Article XIV(a) GATS with
regard to Russia's claim under Article XVII.302
The European Union has already
addressed comprehensively those arguments in section 3.1.1 of this submission.
270. It may be noted, however, that in response to Panel Question 78, Russia appears to
depart from its previous arguments in response to the EU's defence under Article
XIV(a) GATS by identifying as an additional alternative a measure "requiring
either the ISO or ITO models, or even permitting only the OU model".303
In the
absence of any explanation by Russia, the European Union is at a loss to
understand the relevance of this allegedly alternative measure. Russia's claim
under Article VI:4 GATS is not addressed against the "unbundling measure", but
299 EU's response to Panel Question 80, paras. 198-203.
300 Russia's responses to Panel Question 81, para 355; and to Panel Question 82, para. 358.
301 See Russia's response to Panel Question 83, para. 361.
302 See Russia's responses to Panel Question 78, para. 336: Panel Question 79, para. 348; and Panel
Question 83, para. 362
303 Russia's response to Panel Question 78, para. 336.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 86 -
only and exclusively against the "third country certification measure". The
European Union fails to understand how an alternative to the "unbundling
measure" could provide at the same time an alternative to the third country
certification measure.
3.6.3. Letter (c) of Article VI:4 GATS
271. Russia objects that the Secretariat background paper (S/WPPS/W/9, of 11
September 1999) cited by the European Union is "expressly intended to address
only the accountancy sector"304
. This is simply incorrect.
272. Russia further argues that, "even if the definitions of the Secretariat's background
are applied"305
, the third country certification measure would be a licensing
procedure to the extent that it requires the applicants to provide information in
support of their applications. According to Russia, although Article 11 of the Gas
Directive (and the transposing laws of the three EU Member States concerned) do
not specify such information, this requirement would violate Article VI:5(c) GATS
because applicants are required to provide "far more information than domestic
applicants must provide under Article 10 of the Directive".306
273. Russia's assertion that applicants under Article 11 of the Gas Directive must
provide "far more information" is, of course, mere speculation. In any event, the
fact that applications under Article 11 had to be supported with "far more"
information than applications under Article 10 would not amount to a violation of
Article VI:4(c) GATS. Rather, in order to establish a violation of that provision,
Russia would have to show that that the amount of information required from the
applicants under Article 11 of the Gas Directive goes beyond what is necessary in
order to ensure compliance with the underlying "licensing requirements" provided
for in Article 11 (including the SoS certification requirement), so that the
requirement to provide information creates a trade restriction on its own, beyond
that resulting from the underlying licensing requirements. Russia has not even
attempted to prove this.
304 Russia's response to Panel Question 78, para. 338.
305 Russia's response to Panel Question 78, para. 340.
306 Russia's response to Panel Question 78, para. 340.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 87 -
4. INFRASTRUCTURE EXEMPTIONS
4.1. INTRODUCTION
274. Russia contends that the Directive, in addition to the exemption for new major
infrastructure laid down in Article 36, provides for a separate exemption applying
to upstream pipeline networks. According to Russia, upstream pipeline networks
as defined in Article 2(2) of the Directive are fully exempt from the unbundling,
third-party access and tariff regulation provisions.307
275. Russia argues, moreover, that LNG facilities are granted automatic and
discriminatory exemptions from the unbundling provisions of the Directive
pursuant to Articles 9 and 2(20), as well as to Articles 2(2), 2(12) and 2(13).
276. Russia’s contentions, which assert the existence of various "exemptions" from the
EU Directive’s main obligations in addition to the exemption for new major
infrastructure in Article 36, are unsupported. They deliberately ignore the text of
the provisions defining upstream pipeline networks and LNG facilities, as well as
the reasons why those types of gas infrastructure should be subject to specific
rules. Those specific rules are not identical to the rules to which transmission
pipelines are subject, notably the requirement for unbundling of transmission from
production and supply activities. However, they share common requirements, such
as third-party access.
277. More precisely, the purpose of Russia’s assertions in this respect is not to
challenge the WTO-consistency of any specific rules applying to upstream
pipeline networks or LNG facilities, but rather to contest from this angle the
general obligations through which the Directive ensures a level playing field for all
gas undertakings participating in the EU market. As the recitals of the EU
Directive make abundantly clear, non-discriminatory access to gas transmission
networks plays a crucial role in this regard. Unbundling, third-party access and
regulated tariffs’ obligations are tools for achieving the objectives of the EU
Directive.
307 Russia's responses to written questions from the Panel to the parties following the first substantive
meeting, paras. 16-18.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 88 -
278. By arguing that there are several "exemptions" to those generally applicable
obligations, Russia suggests that the EU legislation is somewhat illogical. This is
however a misguided and misguiding suggestion. The recitals of the EU Directive
explain the reasons why different rules apply to different types of gas
infrastructure and why the risk of discriminatory behaviour in the operation of
transmission pipelines and networks (which have the nature of a natural
monopoly) is the highest and thus necessitates a requirement for unbundling of
transmission from production and supply interests to be put in place. This is
reflected in the exemption for new major infrastructure, which allows derogations
to the generally applicable obligations in order to promote investment in
interconnectors, as well as in LNG and storage facilities.308
The flexibility built
into the EU Directive does not undermine the rationale for the obligations it
imposes on gas undertakings. It shows, on the contrary, that those obligations only
apply to the extent they are necessary to serve the objectives of the Directive,
creating a well-functioning and sustainable gas market with competitive prices,
new business opportunities and more cross-border trade.309
4.2. THE EXEMPTION FOR NEW MAJOR INFRASTRUCTURE
279. At paragraph 20 of its responses to the Panel’s questions, Russia summarizes
various claims concerning the exemption for new major infrastructure in Article 36
of the EU Directive. As noted in the European Union’s comments of 21 October
2016 regarding terms of reference, one of these claims was not included in
Russia’s request for the establishment of a panel and is therefore outside the
Panel’s terms of reference. The claim under Article X:3 (a) of the GATT 1994,
also mentioned at paragraph 46 of Russia’s responses to the Panel’s questions,
challenges the administration of the infrastructure exemption measure in general,
on the basis of specific instances of application of the measure by the Commission.
However, in the fourth full paragraph of page 4 of its Panel Request, Russia only
identified the OPAL gas release requirement as the measure violating Article
X:3(a).
308 See recital (35) of Directive 2009/73/EC.
309 See recitals (1) and (35) of Directive 2009/73/EC.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 89 -
4.3. CLAIM XVIII: RUSSIA’S CLAIM UNDER ARTICLE X:3(A) OF THE GATT 1994 (RUSSIA'S
CLAIM 21)
280. According to what is now presented as Claim 21, Russia contends that the
European Union has failed to administer the infrastructure exemption measure in a
uniform, impartial or reasonable manner.
281. The European Union has pointed out that the Article X:3(a) claim initially
concerned exclusively the 3bcm gas release requirement imposed as a condition
for the exemption granted to OPAL. In the conclusions of its preliminary ruling of
10 November 2016, the Panel has confirmed that the measure challenged by
Russia’s Claim 21 must be understood as limited to the imposition of the 3bcm gas
release requirement as described on page 4 of the panel request.310
282. Nonetheless, Russia’s arguments in support of this claim continue to focus on the
two conditions attached to that individual exemption decision. The comparison
with other individual decisions adopted pursuant to Article 36 of Directive
2009/73/EC (or Article 22 of Directive 2003/55/EC) is more of a prop to force a
review by the Panel of the OPAL decision, than it is a demonstration of an
unreasonable administration of the exemption for new major infrastructure.
283. As a preliminary point, the European Union will recall that it disputes the
characterization of Article 36 of Directive 2009/73/EC, which is undoubtedly a
measure of general application, as a measure “affecting” the sale, distribution and
transportation of natural gas within the meaning of Article X:1 of the GATT 1994.
While the infrastructure exemption measure indirectly enhances competitive
opportunities for all market players and increases cross-border trade,311
its effects
on the volumes and prices of domestic and imported products are however more
indirect and remote. A number of other factors and considerations will determine
to what extent the infrastructure will be used and the source or sources of the
natural gas flowing through it.
310 Preliminary ruling by the Panel (Conclusions), para. 2.3.
311 See recitals (1) and (35) of Directive 2009/73/EC.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 90 -
284. The European Union must underline that Russia has not explained, let alone
proven, the effects on the sale, distribution and transportation of natural gas that it
ascribes to the exemption for new major infrastructure.
285. In addition, the European Union has also pointed out that individual exemption
decisions, such as the OPAL decision, are not measures of general application and
cannot, for that reason, be challenged under Article X:3(a) of the GATT 1994.312
286. As regards the substance of the claim, Russia asserts that the OPAL exemption
decision is an example of clear misapplication of the Directive in violation of
Article X:3(a).313
287. Without prejudice to its views on the admissibility of that claim, the European
Union will reiterate, first, that the OPAL exemption decision is perfectly in line
with the criteria set out in Article 22(1) of Directive 2003/55/EC which require,
notably, that the exemption is not detrimental to competition. To ensure that this is
the case, Article 22(3)(b)(ii) provided:
In deciding to grant an exemption consideration shall be given, on
a case by case basis, to the need to impose conditions regarding
the duration of the exemption and non-discriminatory access to
the interconnector.314
288. Second, the conditions attached to the OPAL exemption are perfectly in line with
previous Commission practice, in particular the exemption decisions concerning
312 EU’s first written submission, paras. 689 and 693.
313 Russia’s responses to written questions from the Panel to the parties following the first substantive
meeting, para. 569.
314 The Explanatory Note, paras. 11 and 12 (Exhibit RUS-27) explain further:
(11) When assessing exemption requests national authorities have to strike a balance between the
objectives of, on the one hand, promoting infrastructure investment and, on the other, ensuring
competition through fair, non-discriminatory access to infrastructure which is one of the key
principles of energy market liberalisation.
(12) Based on the above considerations, the national authorities need to assess exemption requests
for new major infrastructure on a case by case basis. It is the particular characteristics of the
investment project and of the markets concerned that determine the need and the scope of a possible
exemption. When assessing an exemption request, the national authority needs to investigate in
detail the impact of the specific exemption on competition, security of supply and the functioning
of the internal market. Moreover, the national authority should take into account the risk of creating
a competitive distortion between regulated and exempted infrastructure. To ensure a consistent
application of the exemption practice and to safeguard the wider European interest, the Commission
reviews the national exemption decisions.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 91 -
different sections of the Nabucco pipeline. They are also in line with and very
similar to the conditions subsequently attached to the TAP exemption.
289. Thus, for example, in the Commission’s exemption decision concerning the
Austrian section of the Nabucco pipeline, the following conditions were imposed:
In order to ensure […] that the project enhances competition, the
Austrian regulator is requested to amend its exemption decision to
include the following conditions:
I. […]
II. (a) An undertaking which holds a dominant position in one or
more of the relevant upstream or downstream gas markets
comprising the Austrian Control Area East (Regelzone Ost) shall
not be allowed to book more than 50% of the total capacity at the
exit points in the Austrian section of the Nabucco pipeline.
For the calculation of the capacity cap, undertakings belonging to
the same group (such as OMV and Econgas) shall be considered
together.
(b) In the event of overbooking, capacity allocation shall take
place in a transparent and non-discriminatory procedure, for
example on a pro rata basis, which shall ensure that each bidder is
allocated a minimum amount of capacity.
(c) Where due to the lack of interest by other parties, the capacity
cap prevents the expansion of the pipeline or causes existing
capacity to remain idle, a derogation from the capacity cap shall
apply on condition that the party concerned shall offer the volume
of gas relating to the capacity it holds in excess of the 50% cap to
the market in an open, transparent and non-discriminatory
procedure which is subject to the approval of the regulatory
authority.
The gas volume to be offered to the market shall be calculated as
follows: the percentage points of booked annual capacity in
excess of 50% (e.g. 5% in the case of 55%) shall be divided by
the total share of annual capacity booked by the undertaking
concerned (e.g. 55%). The resulting value (e.g. 9.09%) shall be
multiplied with the total amount of gas which the undertaking
imports through the Nabucco pipeline into Austria in a given year.
III. If the shareholders of Nabucco International change compared
to the situation as described in the application, or if any of the
existing shareholders is acquired by another undertaking,
Nabucco International shall notify such change to E-Control. E-
Control in collaboration with the competent regulatory and
competition authorities shall then evaluate the competitive effects
of this change. Where the change implies the strengthening of a
dominant position in Austria or in a neighbouring country, E-
Control shall impose a capacity cap to counter the negative effect
on competition. Where a change in shareholding is notifiable
under the EC Merger Regulation, it shall not be notified to E-
Control.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 92 -
Therefore by virtue of Article 22(4) of the Gas Directive
55/2003/EC, the Commission hereby requests the E-Control to
amend its exemption decision accordingly within four weeks
upon receipt of the present letter and to inform the Commission of
this action.”315
290. In the case of the exemption granted to the TAP pipeline, the Commission
imposed the following condition, among several others:
Condition 4.7.2 in the Joint Opinion shall be amended.
The amended condition shall read:
[…]
4.7.2
[…]
Capacity caps for dominant players in Italy – For the prevention
of the development of a dominant market positions or the
reinforcement of existing dominant positions in the Italian gas
market, without prejudice of requirements established by Article 2
of the Italian decree dated March 13th 2013, the following
conditions shall also apply:
(i) Any undertaking with a share of 40% or larger in any relevant
product market for the supply of gas in Italy, or on the upstream
market of supplying gas for Italy, shall not be allowed to reserve
more than 50% of the capacity on the TAP exit point in Italy.
(ii) In the event that two or more undertakings together hold a
market share of at least 80% and each of these undertakings have
a market share of more than 20% in any relevant product market
for the supply of gas in Italy, or on the upstream market of
supplying gas for Italy, AEEG will have the right to impose a
capacity cap on these undertakings on the TAP exit point in Italy.
(iii) Where, due to lack of interest by other parties, the capacity
caps in (i) and (ii) above prevent the expansion of the pipeline or
causes existing capacity to remain idle, a derogation from the
capacity caps of (i) and (ii) shall apply on the condition that the
undertaking(s) concerned offer to the market the entire volume of
gas in excess of the capacity that the undertaking(s) hold in an
open, transparent and non-discriminatory procedure. The gas
volume release shall be followed by a corresponding capacity
release. The gas volume release and the capacity release will be
subject to a procedure approved by AEEG.
iv) For the calculation of the market share and the percentage of
the capacity cap undertakings belonging to the same group of
companies shall be considered together. The market share shall be
calculated as the average of the last two consecutive years.
315 Exhibit RUS-83, p. 14 and 15.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 93 -
(v) Only in case the imposition of the gas and capacity release
will give rise to a situation where the undertaking(s) concerned
has/ve no incentives to utilise the capacity above the capacity cap
imposed, on request of the undertaking concerned or on its own
initiative, AEEG can provide a temporary derogation to provide
for the gas and capacity release. Such derogation shall be subject
to other conditions that maintain the competition enhancing
effects of the investment for competition. Such a derogation is
given by the Regulatory authority, after consulting the National
Competition authority.”316
291. It is therefore abundantly clear that the conditions attached to the OPAL decision
are by no means exceptional. On the contrary, capacity caps imposed on
undertakings holding a dominant position on the relevant gas markets are rather
standard conditions, as specified in the Commission’s Explanatory Note. Referring
to conditions that can be imposed to ensure that the project enhances competition,
the Commission mentions the following type of condition, among others:
A limitation of the maximum percentage of capacity that can be
allocated to an undertaking with significant market power in the
relevant market(s). The condition can be combined with the
requirement to release the capacity share or corresponding gas
volumes exceeding the defined maximum percentage.317
292. Given the predictability of conditions such as the ones imposed on OPAL, it is
difficult to understand why Russia complains so much about those conditions. It is
even more difficult to understand how Russia can pretend that “[t]he EU has
completely failed to justify the discriminatory manner in which the Commission
imposed not only the 50% capacity cap on the OPAL exemption, but also the
3bcm/year gas release requirement, while imposing vague and much less
restrictive conditions on the TAP, Nabucco and Poseidon exemptions and no
conditions whatsoever on the TPA exemptions for LNG facilities such as Dragon
and South Hook in the UK.”318
Statements such as this one are simply baffling.
293. Russia chooses to ignore the detailed explanations that the Commission provided
in the text of the OPAL exemption decision itself, which is fully reasoned. Russia
declines to acknowledge the similarities between the conditions imposed on the
Nabucco and TAP projects, reproduced above, and the conditions imposed on
316 Exhibit RUS-10, p. 59 and 60.
317 Explanatory Note, para. 39.2 (Exhibit RUS-27).
318 Russia’s responses to written questions from the Panel to the parties following the first substantive
meeting, para. 573.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 94 -
OPAL. Russia singles out two decisions exempting LNG facilities where the
Commission found no need to impose similar capacity caps, while failing to note
that, for example in the case of the Dutch LNG terminal Gate, such conditions
were indeed imposed.319
294. The European Union can only draw the attention of the Panel to all these elements
that Russia has intentionally overlooked. They clearly demonstrate that the
conditions imposed on the OPAL decision do not constitute an instance of
unreasonable administration of the infrastructure exemption measure.
295. In its responses to the Panel, Russia argues that Gazprom’s status as a dominant
undertaking in the Czech Republic should have been considered irrelevant because
“Russian gas transported via OPAL does not even enter the Czech gas market; it
flows directly into the Gazelle pipeline and across the Czech Republic back into
Germany and onward to France via the Megal pipeline.”320
296. Russia also argues “that much of the rationale offered by the EU – which was
flawed at the time of the OPAL decision – totally disappeared after the Gazelle
pipeline was completed and all of the gas being transported via OPAL was
required to be transited across the Czech Republic, back into Germany and
onwards to France and elsewhere”.321
297. The European Union considers this statement puzzling and utterly confusing. It is
true that at the time of the OPAL decision, the Gazelle pipeline was planned. It is
important to note, however, that in 2009 construction of the Gazelle pipeline had
not yet started and, in fact it was only completed in 2013. The Commission took
account of existing plans to link OPAL to Gazelle, but obviously could not assume
that all gas flown through OPAL was to be transported onwards via Gazelle and
would not reach the Czech market. The conditions imposed on OPAL aimed at
ensuring that the exemption would not strengthen and further entrench the
dominant positions already held by Gazprom and RWE Transgas in the Czech
319 Commission’s comments to the Gate Terminal exemption decision (Exhibit EU-143).
320 Russia’s responses to written questions from the Panel to the parties following the first substantive
meeting, para. 547.
321 Russia’s responses to written questions from the Panel to the parties following the first substantive
meeting, para. 574.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 95 -
Republic. None of the conditions imposed on either the OPAL or the Gazelle
exemptions require all the gas transported on OPAL to be transported onwards into
Germany or France. Quite the opposite. One of the conditions attached to the
Gazelle exemption is that the addressee of the exemption decision enables
sufficient bi-directional capacity on Gazelle to safeguard the security of supply of
the Czech market in emergencies based on an opinion of the Competent Authority
in the Czech Republic.322
It is therefore unclear why Russia asserts that “all of the
gas being transported via OPAL was required to be transited across the Czech
Republic, back into Germany and onwards to France and elsewhere”.323
Such
requirement is certainly not imposed by the European Union.
298. Russia accuses the European Union of refusing to consider rescinding or
modifying the conditions attached to the OPAL exemption, which it incorrectly
characterises as “discriminatory restrictions on the volume of gas that may be
imported and transported over OPAL”. 324
299. The European Union has already demonstrated, and will insist on this point below,
when rebutting the claim made by Russia under Article XI:1 of the GATT 1994,
that nothing in the conditions imposed on the OPAL exemption restricts the
volumes of gas that can be transported on OPAL. The restrictions concern
exclusively the supply of pipeline transport services on OPAL by Gazprom and
related companies.
300. Russia also refers to the “the EU’s discriminatory objective of reducing reliance on
Russian gas and pipeline transport services”.325
301. Nothing in the European Union’s administration of the infrastructure exemption
measure seeks to reduce imports of Russian gas or the supply of Russian pipeline
transport services. The first criterion listed in Article 36 of the EU Directive for
322 Commission’s exemption decisions Gazelle I and Gazelle II, Article 3 (Exhibits RUS-81 and RUS-
87)
323 Russia’s responses to written questions from the Panel to the parties following the first substantive
meeting, para. 574.
324 Russia’s responses to written questions from the Panel to the parties following the first substantive
meeting, para. 574.
325 Russia’s responses to written questions from the Panel to the parties following the first substantive
meeting, para. 575.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 96 -
granting an exemption is that the investment in new major gas infrastructure must
enhance competition in gas supply and enhance security of supply. The objectives
of increasing competition and security of supply in the EU gas markets are quite
different from the objective identified by Russia in its attempt to assemble a claim
of violation of Article X:3(a) of the GATT 1994.
302. Because Russia’s claim is in part outside the terms of reference of the Panel, does
not meet the requirements of Article X:1 and is in the whole unsubstantiated, it
must fail.
4.4. CLAIM XIX: RUSSIA’S CLAIM UNDER ARTICLE I:1 OF THE GATT 1994 (RUSSIA’S CLAIM
22)
303. Russia’s Claim 22 concerns the infrastructure exemption measure as implemented
by the decision of the BNetzA denying an exemption to the NEL pipeline. Russia
claims that Russian natural gas is accorded de facto less favorable treatment than
like gas of other third-countries, in violation of Article I:1 of the GATT 1994.
304. Russia argues that, as implemented, the infrastructure exemption measure provides
NEL and Russian gas transported via NEL different treatment than Gazelle, TAP
and like Azeri gas transported via TAP. It also contends that, in denying the NEL
exemption, both BNetzA and the Commission narrowly interpreted the
infrastructure exemption measure, including the definition of “interconnector” and
“new” infrastructure.326
In its responses to the Panel’s questions, Russia specifies
that its “Claim 22 challenges the manner in which the EU applied or implemented
the infrastructure exemption measure by denying the NEL interconnector an
exemption from the relevant provisions of the Directive, while granting
exemptions for the Gazelle and TAP pipelines based on an inconsistent
interpretation of Article 36 (and Article 22)”.327
305. The European Union questions whether the infrastructure exemption measure falls
within the scope of application of Article I:1 of the GATT 1994. Russia has failed
to demonstrate how a measure encouraging the construction of new infrastructure,
which is designed to create new opportunities for gas of all sources to compete on
326 Russia’s first written submission, section XIX.B.
327 Russia’s responses to written questions from the Panel to the parties following the first substantive
meeting, para. 47.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 97 -
the EU market, restricts the competitive opportunities for Russian gas as compared
to foreign gas of other sources.328
306. In its first written submission, the European Union has underlined that whereas the
infrastructure exemption measure preserves equality of competitive opportunities
for gas of all sources, including gas imported from Russia or from other third-
countries, it does not guarantee, by contrast, that shares of participants in the EU
market will remain unchanged. In other words, all present and future market
participants must face the enhanced competition brought about by the expansion of
gas infrastructure.329
307. As regards comparisons between the decision denying NEL an exemption and
decisions exempting other pipelines, the European Union has explained why they
are unsuitable to prove that Russian gas was de facto afforded less favourable
treatment. All exemption requests are decided on a case-by-case basis and must
take account of the factual circumstances of each major infrastructure project,
including their physical characteristics in the light of the requirements of Article
36. 330
308. In so far as NEL is concerned, the European Union clarified, in its response to
question 21 posed by the Panel, that BNetzA's decision to deny an exemption to
the NEL pipeline was based on the ground that the NEL pipeline did not meet the
definition of “interconnector” provided in Article 2(17) of Directive 2003/55/EC.
This definition requires the transmission line to cross or span a border between
Member States. Section 2.1.2 of the Ruling provided to the Panel as Exhibit RUS-
61 explains the reasoning followed by BNetzA in this regard.331
309. The NEL pipeline did not reach the border and thus did not qualify as an
“interconnector”. In order for NEL to reach the border, a pre-existing stretch of
pipeline would have to be used. This pre-existing stretch was more than five times
as long as the new pipeline, belonged to another transmission system operator and
was not fully integrated into the NEL project. On the other hand, if that pre-
328 EU’s first written submission, paras. 719-721.
329 EU’s first written submission, para. 723.
330 EU’s first written submission, paras. 697-698.
331 European Union’s responses to the Panel’s questions after the first hearing, para. 44.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 98 -
existing stretch had been integrated into the NEL pipeline, it would preclude the
qualification of NEL as “new” gas infrastructure.
310. By contrast, Gazelle crosses the Czech/German border at the Rozvadoc/Waidhaus
border station. In paragraphs 19 to 26 of its decision on the exemption of
Gazelle,332
the Commission states the reasons for finding that this pipeline
qualified both as an “interconnector” and as “new” infrastructure within the
meaning of Article 36 of Directive 2009/73/EC. It examined whether the use of 20
km of an existing pipeline between Primda and the German border station of
Rozvadoc/Waidhaus prevented Gazelle from being considered a “new”
interconnector. The Commission concluded that Gazelle qualified as new gas
infrastructure because “[t]he predominant part of the 160 km Gazelle pipeline will
be newly constructed, while only a 20 km stretch will be achieved through the
transfer of an existing pipeline into the exclusive ownership and use by the Gazelle
owner, Brawa” and that building a parallel pipeline next to the existing system
would be uneconomical and also problematic for environmental reasons.333
311. The European Union has also explained that the alleged different treatment of the
NEL and Gazelle pipelines does not restrict the opportunities for Russian gas to
compete on the EU markets. Russia itself recognizes in footnote 942 of its first
written submission that the Gazelle pipeline is intended to transport Russian
natural gas imported via Nordstream and OPAL. Russia clarifies in the same
footnote that “it does not contend that the Commission’s differential treatment of
Gazelle compared to NEL modified the conditions of competition to the detriment
of Russian gas”.334
312. Similarly, there are objective reasons for considering TAP an “interconnector” as
defined in Article 2(17) of Directive 2009/73/EC. TAP is planned to stretch over
three countries: two Member States (Italy and Greece) and one Contracting Party
to the Energy Community (Albania). TAP therefore connects the transmission
systems of two Member States and is not deprived of that quality by the fact that it
crosses a third country, i.e. Albania.
332 Commission’s decision on Gazelle I (Exhibit RUS-81).
333 Commission’s decision on Gazelle I (Exhibit RUS-81), para. 25.
334 EU’s first written submission, paras. 728-729.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 99 -
313. Furthermore, as the European Union pointed out in its first written submission,
TAP is not reserved for exclusive use by Azeri gas from the Shah Deniz II gas
field.335
In its decision on the TAP exemption, the Commission explicitly verified
that the exemption “provides sufficient guarantees that gas from non-SD II sources
is provided access to TAP. These guarantees apply to gas that may be transported
through TAP by the Expansion Capacity through existing entry and exit points as
well as gas that may be transported through TAP via pipelines connecting to TAP
via new entry and exit points”.336
314. The European Union concludes that its interpretation of the term “interconnector”
in the cases of NEL, Gazelle and TAP were consistent with the requirements of
Article 22 of Directive 2003/55/EC and Article 36 of Directive 2009/73/EC. In any
event, the exemptions granted to Gazelle and TAP do not accord to gas from other
Members an advantage that is not immediately and unconditionally extended to
Russian gas transported via NEL. Russia’s Claim 22 must therefore be rejected.
4.5. CLAIM XIX: RUSSIA’S CLAIM UNDER ARTICLE I:1 OF THE GATT 1994 (RUSSIA’S CLAIM
23)
315. According to Russia’s responses to the Panel’s questions, its “Claim 23 challenges
the manner in which the EU applied or implemented the measure by imposing on
the exemption granted for the OPAL interconnector more restrictive conditions
than on the exemptions for Gazelle and TAP, as well as on exemptions for the
Nabucco and Poseidon pipelines”. 337
316. The European Union has already demonstrated in section 4.3 above, at paragraphs
288 to 294, that the conditions attached to the OPAL exemption are perfectly in
line with previous Commission practice, in particular the exemption decisions
concerning different sections of the Nabucco pipeline. They are also in line with
and very similar to the conditions subsequently attached to the TAP exemptions.
317. Further, the European Union will recall that in its first written submission it
contested the inferences drawn by Russia from comparisons between the OPAL
335 EU’s first written submission, para. 730.
336 Commission’s decision on TAP, para. 224 (Exhibit RUS-10).
337 Russia’s responses to written questions from the Panel to the parties following the first substantive
meeting, para. 47.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 100 -
and Gazelle exemption decisions, on the one hand, and between the OPAL and
Poseidon exemption decisions, on the other hand.338
318. As regards conditions attached to the Gazelle exemption, although it is true that no
capacity cap was imposed, it should be noted that Gazelle does not benefit from a
full exemption. Gazelle has a technical capacity of approximately 33bcm and
capacities above 30bcm are subject to regulation.339
The volume of Gazelle’s
regulated capacities is therefore similar to the 3bcm gas release program foreseen
for OPAL. The absence of a capacity cap among the conditions imposed on
Gazelle is justified by the fact that the physical end point of Gazelle is in
Germany, which is regarded as a competitive market. By contrast, OPAL ends in
the Czech Republic, a market where there is little competition among gas
suppliers.340
319. Moreover, as already noted at paragraph 311 above, Gazelle is used to transport
almost exclusively gas of Russian origin. If, as Russia claims, exemptions created
an advantage for the sale of gas transported through the exempted infrastructure
(quod non), the Gazelle exemption would essentially benefit the sale of Russian
gas.
320. The comparison between the OPAL exemption and the Poseidon exemption is also
unsuitable to prove a violation of Article I:1 of the GATT 1994. Since the
Poseidon pipeline was not built and put into operation by 2012, the exemption
granted to this infrastructure project expired long ago. For this reason, it cannot be
argued that the Poseidon exemption had any effects on the market and provided
more favourable treatment to gas of other origins than that afforded to Russian gas.
In any event, the Commission added stricter conditions to those that had been
imposed by the Italian and Greek regulatory authorities, namely to make available
to third-parties incremental transport capacity.341
321. Russia’s Claim 23 must therefore also fail.
338 EU’s first written submission, paras. 708-710, 728-729 and 732.
339 Commission’s decision on Gazelle I, para. 16 (Exhibit RUS-81).
340 Commission’s decision on Gazelle I, para. 40 (Exhibit RUS-81); Commission’s decision on OPAL,
paras. 45-48 (Exhibit RUS-82).
341 Commission’s decision on Poseidon (Exhibit RUS-86).
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 101 -
4.6. CLAIM XIX: RUSSIA’S CLAIM UNDER ARTICLE I:1 OF THE GATT 1994 (RUSSIA’S CLAIM
24)
322. In its responses to the Panel’s questions, Russia describes its Claim 24 as
challenging “the manner in which the EU applied or implemented the measure by
denying the NEL exemption and imposing restrictive conditions on the OPAL
exemption, while granting exemptions to various LNG facilities without imposing
any conditions in the case of Dragon and South Hook in the UK”.342
323. The European Union will recall, first, that it disputes that LNG is “like” natural
gas. In its opinion, any supposed advantage accorded to LNG by decisions
granting an exemption to LNG facilities does not discriminate against natural gas
within the meaning of Article I:1 of the GATT 1994.343
324. Second, pursuant to Article 22 of Directive 2003/55/EC and Article 36 of
Directive 2009/73/EC, the exemption of LNG facilities is subject to the same
criteria and conditions applicable to interconnectors and to storage facilities. The
fact that the Directive provides in Article 2(11) for a specific definition of “LNG
facility” does not mean that such facilities are treated differently in this respect
than other major gas infrastructure. Moreover, the origin of the LNG using a
particular facility plays no role in the Directive and in individual exemption
decisions.
325. Third, Russia has not demonstrated how the exemptions granted to the Dragon and
South Hook LNG facilities have conferred an advantage to “like” gas of certain
origins that were not extended immediately and unconditionally to Russian natural
gas flown through NEL and OPAL.
326. Russia’s Claim 24 must therefore be rejected.
4.7. CLAIM XX: RUSSIA’S CLAIM UNDER ARTICLE II:1 OF THE GATS (RUSSIA’S CLAIM 25)
327. Russia’s Claim 25 “challenges the manner in which the EU applied or
implemented the measure by denying the NEL exemption and imposing restrictive
conditions on the OPAL exemption, while granting exemptions to other pipelines
342 Russia’s responses to written questions from the Panel to the parties following the first substantive
meeting, para. 47.
343 EU’s first written submission, para. 734.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 102 -
and various LNG facilities, without imposing similarly restrictive conditions and
no conditions in the case of Dragon and South Hook in the UK. In Russia’s view,
the EU’s implementation of the measure, as applied in each of the exemption
decisions to date, including both those for interconnectors and LNG facilities,
demonstrates de facto discrimination and resulted in less favourable treatment
being provided to Russian services and service suppliers than like services and
service suppliers of other Members”.344
328. The European Union has rebutted this claim in paragraphs 743 to 751 of its first
written submission. Although the European Union does not dispute that the
infrastructure exemption measure falls within the scope of the GATS and that
Russian and other third-country suppliers of pipeline transport services are “like”
suppliers and supply “like” services, it contests that LNG services and service
suppliers are “like “ pipeline transport services and service suppliers. The
European Union refers to the explanations given in paragraphs 283 to 287 of its
first written submission and recalled in paragraphs 147 to 149, above.
329. As regards the exemptions granted to LNG facilities, the European Union will
nonetheless point out that Russia has not demonstrated that those facilities did not
meet the relevant criteria laid down in the EU Directive for being granted full
exemptions from third-party access requirements. The fact that Gazprom does not
operate LNG facilities and that Dragon and South Hook are partly owned by gas
suppliers of other Members does not suffice to show that LNG services and service
suppliers have been treated de facto more favourably than Russian pipeline
transport services and service suppliers.
330. Neither Article 36 of Directive 2009/73/EC, nor Article 22 of Directive
2003/55/EC before it, draw any distinctions based on the origin of the supplier of
pipeline transport services. The individual decisions implementing those
provisions do not distinguish either between Russian suppliers of pipeline
transport services or “like” service suppliers of any other origin. Russia has not
alleged, let alone proven, otherwise.
344 Russia's responses to written questions from the Panel to the parties following the first substantive
meeting, para. 47.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 103 -
331. The claim of de facto discrimination is not supported by the facts. It has been
demonstrated in the sections above that the terms of each individual exemption
decision that was adopted under the EU Directive is justified by the specificities of
each infrastructure project and of the gas markets concerned in each case. Because
the Directive requires the competent national authorities and the Commission to
examine the structure and conditions of competition on the relevant gas markets
prior to granting an exemption, they must take account of the identity of the
undertaking supplying pipeline transport services to the extent necessary for
determining the position they hold on those markets. However, the origin of the
undertaking supplying pipeline transport services has no bearing whatsoever on
the analysis that must be conducted for granting an exemption and for deciding to
impose any conditions.
332. The refusal of the exemption requested for NEL was warranted because the project
did not meet the requirements set out in Article 22 of Directive 2003/55/EC. The
conditions imposed on OPAL were necessary to ensure that the exemption would
not have a detrimental effect on competition in the Czech gas markets. Besides,
conditions such as capacity caps and gas release programs are in line with
Commission policy and have been attached to other exemptions, namely to those
granted to Nabucco and TAP, as appropriate in each case.
333. For all these reasons, the European Union submits that Russia failed to prove that
the infrastructure exemption measure discriminates against Russian pipeline
transport services supplied via NEL and OPAL and against Russian service
suppliers.
4.8. CLAIM XXI: RUSSIA’S CLAIM UNDER ARTICLE I:1 OF THE GATT 1994 IN RESPECT OF
UPSTREAM PIPELINE NETWORKS (RUSSIA’S CLAIM 26)
334. Through its Claim 26, Russia challenges “the implementation of the infrastructure
exemption measure to deny the NEL exemption and impose restrictive conditions
on the OPAL exemption, while the Directive automatically exempts UPNs from
the unbundling, TPA and tariff regulation requirements. In Russia’s view, the
EU’s implementation of the infrastructure exemption demonstrates de facto
discrimination. It results in less favourable treatment being provided to Russian
gas transported and sold on the EU market through NEL and OPAL, compared to
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 104 -
like gas primarily from Norway transported and sold through UPNs, in violation of
GATS Article I:1”.345
335. The European Union contests the basis for this claim, which is Russia’s erroneous
assertion that the Directive provides an “as such” exemption to upstream pipeline
networks.346
336. In addition, the European Union disputes the allegation that the EU Directive
discriminates against gas of a certain origin. The rules in respect of upstream
pipeline networks apply regardless of the origin of the gas. Not all gas flown
through upstream pipeline networks owned or operated by Norwegian gas
suppliers is necessarily gas of Norwegian origin. This may not be the case if other
undertakings are in a position to access those upstream pipeline networks and are
granted that access pursuant to the obligation in Article 34 of Directive
2009/73/EC.
337. In sum, the specific rules in the EU Directive applying to upstream pipeline
networks do not grant to natural gas of other Members, imported through upstream
pipeline networks, an advantage not extended immediately and unconditionally to
like Russian gas sold on the EU market through NEL and OPAL. Russia has not
demonstrated how the rules on upstream pipeline networks grant a competitive
advantage to gas of Norwegian origin to the detriment of Russian gas.
4.9. CLAIM XXII: RUSSIA’S CLAIM UNDER ARTICLE II:1 OF THE GATS IN RESPECT OF
UPSTREAM PIPELINE NETWORKS (RUSSIA’S 27)
338. At paragraph 2.2 of the conclusions of its preliminary ruling of 10 November
2016, the Panel has specifically found that Russia’s Claim 27 falls outside its
terms reference.
4.10. CLAIM XXIII: RUSSIA’S CLAIM UNDER ARTICLE XI:1 OF THE GATT 1994 (RUSSIA’S
CLAIM 28)
345 Russia's responses to written questions from the Panel to the parties following the first substantive
meeting, para. 50.
346 EU’s first written submission, paras. 674-675, 755. See also paragraphs 142-143 and 274-278,
above.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 105 -
339. Russia maintains that the capacity cap and gas release conditions imposed by the
Commission on OPAL constitute quantitative restrictions in violation of Article
XI:1 of the GATT 1994. It considers that its Claim 28 is an “as applied” claim
challenging the restrictive conditions attached to the OPAL exemption that, in its
view, instituted two quantitative restrictions on the volume of Russian gas
imported into the EU.
340. In its responses to the Panel’s questions,347
Russia stresses the fact, already
mentioned in paragraphs 743 and 744 of its first written submission, that the
OPAL exemption “applies exclusively for connection capacities on the OPAL with
entry in German territory and exit in Brandov”, adding that these are capacities
offered in bundled form. Russia further explains the OPAL exemption applies
equally to the capacity at the Griefswald entry point as it does the exit capacity at
Brandov, in that the “entry and exit capacities…are only offered in bundled form.”
341. The European Union understands that, in Russia’s conception, the Russian gas that
enters OPAL at Griefswald can only proceed from the Nordstream pipeline and
must inevitably continue to be transported on OPAL by Gazprom itself, or by
related companies. Thus, according to Russia, the condition preventing Gazprom
and related companies from booking more than 50% of OPAL’s exit capacities at
the Czech border in any given year would necessarily restrict the volume of
Russian gas that can be imported into the EU market.
342. However, Russia’s insistence on the link between the use of OPAL by Gazprom
and the importation of Russian gas proceeding from Nordstream is fundamentally
flawed.
343. In its responses to the Panel's questions, 348
the European Union has explained that
the capacity cap imposed by the European Commission has a very limited scope. It
does not restrict, and is not intended to restrict, the importation of Russian gas
exceeding the allowed 50% of OPAL’s capacities, provided that the gas is not
transported by Gazprom or to the Brandov exit point giving access to the Czech
market. The capacity cap seeks only to prevent Gazprom and RWE Transgas from
347 Russia's responses to written questions from the Panel to the parties following the first substantive
meeting, paras. 531-533.
348 European Union’s responses to the Panel’s questions after the first hearing, paras. 316-323.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 106 -
entrenching their dominant position on the Czech gas markets through their
activities as suppliers of pipeline transmission services on OPAL.
344. Consequently, there are various possibilities, also described by the European
Union in its responses to the Panel’s questions, for natural gas from Russia to be
imported into the EU using the remaining 50% capacities of OPAL. These
possibilities include the sale by Gazprom of Russian gas already at Griefswald or
on the Gaspool virtual trading point, allowing the gas to be transported onwards by
the client. If Gazprom supplies the pipeline transmission services on OPAL itself,
volumes of gas exceeding the 50% allowed capacities must be intended for the exit
point near Berlin, at Gross Köris, or they must be sold on the Czech market in a
regulated and non-discriminatory manner, implementing the 3bcm gas release
program provided for in the second condition imposed by the Commission.
345. Importantly, bookings of OPAL capacities by undertakings unrelated to Gazprom
are not restricted in any way. Such undertakings may perfectly use OPAL to
transport Russian gas produced by Gazprom, including gas intended for resale on
the Czech market. In fact, as is clear from its wording, the contested condition
imposing a capacity cap only restricts the supply of pipeline transmission services
by those undertakings found to be dominant on the Czech gas markets. It does not
restrict the quantities or volume of gas that may be imported from Russia.349
346. The European Union therefore fails to see how the fact that the OPAL exemption
applies to bundled entry and exit capacities advances Russia’s claim that the
capacity cap institutes a quantitative restriction on the importation of Russian
natural gas. Again, the origin of the gas is irrelevant for the purpose of applying
the 50% cap on the booking of OPAL capacities by undertakings dominant on the
Czech gas markets. Nothing in the exemption decision prevents Gazprom from
allowing unrelated undertakings to book the remaining OPAL capacities, thereby
increasing the overall volumes of Russian natural gas imported into the EU via
Nordstream and OPAL.
347. Contrary to Russia’s contention, the fact that the capacity release condition in the
OPAL infrastructure exemption has not been used does not confirm the existence
349 European Union’s responses to the Panel’s questions after the first hearing, paras. 323 -328.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 107 -
of the alleged quantitative restrictions on imports of Russian gas. It only confirms
Gazprom’s deliberate choice to refuse the use of OPAL by third parties, even if
this implies that 16bcm/year of the capacity of that pipeline is left idle. The
underuse of OPAL is thus a consequence of decisions taken by Gazprom, not of
the conditions imposed by the Commission. Russia admits that Gazprom has been
unwilling to forego the right to transport 3bcm/year of imported Russian gas over
OPAL.350
348. Russia plainly dismisses the possibility that Russian gas may be imported via
Nordstream for transport over OPAL by undertakings unrelated to Gazprom and
argues that imports are restricted by the amount of OPAL capacities – 16 bcm/year
– that Gazprom is prevented from booking under the contested capacity cap.351
349. This line of argument shows that Russia persists in ignoring not only the wording
of the contested conditions but also the reasons why the European Union
legislation requires that gas infrastructure is not sealed off for competitors by
virtue of exclusive or predominant use by dominant undertakings. An exemption
from the generally applicable obligations of third-party access and regulated tariffs
laid down in the EU Directive must be regarded as an advantage for vertically
integrated undertakings owning or operating a pipeline, since the exemption allows
them to freely allocate capacities and charge discriminatory tariffs on competitors
seeking access to the pipeline. The conditions challenged by Russia only restrict to
a limited extent the scope of the advantage that was granted to OPAL at the
request of its planned operator, OPAL NEL Transport GmbH.
350. By arguing that the conditions attached to the OPAL exemption constitute
quantitative restrictions prohibited by Article XI:1 of the GATT 1994, Russia is
implicitly arguing that the absence of an exemption from those obligations would
constitute a quantitative restriction on imports as well. That conclusion is surely
unwarranted. Article XI:1 forbids measures that restrict imports of foreign
350 Russia’s responses to written questions from the Panel to the parties following the first substantive
meeting, para. 540.
351 Russia’s first written submission, paras. 745-752 and responses to written questions from the Panel
to the parties following the first substantive meeting, para. 539.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 108 -
products. It does not forbid measures that allow imports of products from various
sources and foster competition on the market of the importing Member.
351. Moreover, the conditions attached to the OPAL exemption do not have either an
indirect limiting effect on imports arriving from Russia. The test devised by the
panel in Colombia – Ports of Entry refers to measures that create uncertainties and
affect investment plans, restrict market access or make importation prohibitively
costly.352
352. As the European Union pointed out in its responses to the Panel’s questions, the
conditions at issue do not give rise to uncertainties and are not designed to increase
costs affecting the price of Russian gas. In any event, Russia has not demonstrated
such effects.353
353. In sum, Russia’s claim under Article XI:1 of the GATT 1994 is unfounded and
must be rejected.
5. PROJECTS OF COMMON INTEREST
5.1. MEANING OF "RUSSIAN PROJECT"
354. Russia's various claims against the TEN – E measure are premised on the
allegation that the TEN – E discriminates against what Russia calls "Russian
projects". In its first written submission Russia failed to specify what it meant by
"Russian projects". In response to Panel Question 49, Russia has provided various
definitions of that concept.
355. According to a first definition, "Russian projects" are "projects that would
maintain the presence of Russian natural gas, Russian services, and Russian
service suppliers on the EU market".354
356. According to another definition,
352 Panel Report, Colombia – Ports of Entry, para. 7.240.
353 European Union’s responses to the Panel’s questions after the first hearing, paras. 346 -347.
354 Russia's response to Panel Question 49 a), para. 246 (Underlining added). See also e.g. Russia's
response to Panel Question 49 d), para. 254; and Panel Question 49 e), para. 255 ("for the purposes
of the GATT 1994 claims, 'Russian projects' are to be understood as projects that are likely to
maintain the level of the Russian natural gas imports in the EU").
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 109 -
[…] the adjective 'Russian' should […] be understood as referring
to projects that as they would not contribute to [the overall
objective of enhancing the diversification and security of gas
supply] (for the simple fact that they would benefit the position of
the largest supplier, Russia) would not be eligible for the more
favourable regulatory treatment that is associated with PCI
designation.
357. According to a yet another definition, "Russian projects" would be projects that are
"designed to facilitate or promote the transmission or storage of Russian natural
gas".355
358. The European Union considers that the various definitions of Russian projects
submitted by Russia are flawed and, ultimately, irrelevant for the purposes of this
dispute.
359. Russia's first definition appears to reflect, once again, Russia's fundamental
misconception that the GATT and GATS provisions which it has invoked
guarantee Russia's pre-existing import shares in the EU market. As recalled by the
European Union356
, however, those provisions are not aimed at ensuring that each
Member will "maintain" its previous "level of imports" into another Member, but
instead at ensuring equality of competitive opportunities. Furthermore, even if
Russia's definition had to be understood as referring to such competitive
opportunities (rather than to pre-existing import shares), it would be anticipating
and prejudging the very outcome of the examination to be conducted by the Panel
i.e. whether or not such competitive opportunities are affected by the challenged
measure to the detriment of Russia's goods, services or service suppliers.
360. Similarly, Russia's second definition is circular and self-fulfilling. In essence,
according to Russia, a "Russian project" is a project excluded a priori from
designation as a PCI under the TEN – E measure. It is no wonder that Russia then
comes to the conclusion that no "Russian project" has ever been designated, or
indeed can be designated, as a PCI.357
355 Russia's response to Panel Question 49 b), para. 250. ("In practical terms, [Russian projects] are
designed to facilitate or promote the transmission or storage of Russian gas").
356 EU's first written submission, para. 823.
357 See Russia's response to Panel Question No 75.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 110 -
361. Lastly, the third definition is unduly narrow because it appears to exclude from the
concept of "Russian project" any project that is either designed or has the effect in
practice of facilitating or promoting also the transmission or storage of gas from
any other source, in addition to Russian gas.358
362. The European Union considers that, ultimately, it is unnecessary to define the
concept of "Russian project". The provisions of the GATS and the GATT invoked
by Russia are not concerned with discrimination between "projects", but instead
with discrimination between goods, services and service suppliers. Russia bears
the burden of proving such discrimination. Russia cannot escape that burden
through the simple expedient of labelling a priori certain projects as "Russian
projects" according to contrived criteria of Russia's own device, such as those used
in the definitions discussed above.
5.2. CLAIM XXIV: ARTICLE II:1 GATS (RUSSIA'S CLAIM 29)
5.2.1. De iure claim
363. As shown in the EU's first written submission359
, Russia's claim that the TEN – E
measure discriminates de iure against Russian services and service suppliers is
unfounded. The origin of the promoter of a project is not among the selection
criteria and plays no role whatsoever in the designation of PCIs. There is nothing
in the TEN – E measure that excludes, either directly or indirectly, the projects
promoted by Russian suppliers of transmission services from being designated as a
PCI.
364. That the TEN – E measure does not discriminate de iure against Russian suppliers
of services is evidenced beyond doubt by the fact that, in practice, many
designated PCIs have been promoted by Russian service suppliers. This includes
also PCIs in the BEMIP Gas corridor.360
More precisely, the European Union has
estimated that, out of the 15 designated PCIs for the BEMIP Gas corridor included
358 See EU's first written submission, para. 816 and paras. 827-828.
359 European Union's first written submission, paras. 782-793, 800 and 808.
360 See EU's response to Panel Question 77.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 111 -
in the first Union list, 9 were applied for by entities of third countries, including 7
projects applied for by Russian entities.361
365. In response to Panel Question 48, Russia is able to cite just one single element of a
single provision of the TEN – E Regulation in support of its claim of de iure
discrimination, namely the reference in the legal definition of the BEMIP Gas
corridor to the objective of ending the dependency on a "single supplier".362
However, the "supplier" referred to in that definition is not a supplier of
transmission services, but instead a supplier of gas. Even if the definition of the
BEMIP Gas corridor invoked by Russia discriminated de iure against imports of
Russian gas (quod non – see below section 5.3), this would not translate into de
iure discrimination against Russian suppliers of services or Russian services,
because there is no legal requirement to the effect that Russian gas must be
transported by Russian service suppliers or that Russian service suppliers cannot
transport gas of other origins.
5.2.2. De facto claim
366. The European Union has also shown that the TEN – E measure does not
discriminate de facto against Russian service suppliers or services.363
367. Like its de iure claim, Russia's de facto claim under Article II:1 GATS is based on
the premise that the TEN – E measure discriminates against imports of Russian
gas. As explained below in section 5.3, however, that premise is unfounded. But,
even assuming ad arguendo that Russia's premise were correct, it would not
follow that the TEN – E measure discriminates de facto against Russian service
suppliers or services.
368. As explained in the EU's first written submission364
, in practice most TSOs are
controlled by EU nationals, whereas the large majority of gas consumed in the
European Union (66 %) is imported. As a result, the TSOs controlled by EU
persons very often operate infrastructures that are used exclusively or mainly to
361 See EU's Response to Panel Question 77, para. 186.
362 Russia's response to Panel Question 48, paras. 238-240.
363 EU's first written submission, paras. 809-811.
364 EU's first written submission, paras.810 and 620-624.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 112 -
transmit imported gas, including to a large extent Russian gas. The European
Union has provided many examples of such infrastructures.365
Conversely, TSOs
controlled by persons of third countries, such as Singapore's TIGF or Russia's
GASCADE, operate infrastructure used in part to transmit EU gas366
. Russia has
nowhere addressed this argument and evidence.
369. Furthermore, as recalled above, in practice many designated PCIs have been
promoted by entities of third countries, including Russian entities.367
5.2.3. The [[ ]] project
370. In response to Panel Question 48, Russia contends that "de jure discrimination of
Russian natural gas and Russian services and service suppliers is evidenced by the
[[ ]] project".368
However, as part of the same response and within just a few
paragraphs, Russia also advances the argument that the non-inclusion of the [[ ]] in
the first Union list of PCIs would rather constitute evidence of de facto
discrimination.369
Thus, the precise relevance of the [[ ]] project to Russia's claims
remains unclear.
371. At any rate, as explained below, Russia's claims of discrimination reflect a
fundamental misunderstanding of the relevant facts and are wholly unfounded. The
non-designation of [[ ]] was the result of the impartial application of objective
selection criteria and did not involve either de iure or de facto discrimination
against Russian gas or against Russian service suppliers or services.
372. As explained in the EU's first written submission370
, the [[ ]] project was
considered eligible according to the "general" criteria in Article 4(1) of the TEN –
E Regulation. Eventually, however, the project was not included in the first Union
list because other projects were ranked higher on the basis of an overall assessment
of the criteria in Article 4(2)(b) and 4(4) of the TEN-E Regulation.
365 EU's first written submission, paras. 622-623.
366 EU's first written submission, para.624.
367 See EU's response to Panel Question 47.
368 Russia's response to Panel Question 48, para. 240.
369 Russia's response to Panel Question 48, para. 242 in fine.
370 EU's first written submission, para. 831.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 113 -
373. As noted by Russia371
, all the candidate projects were assessed according to the
criteria specified in Annex IV to the Terms of Reference of the Regional Group for
the NSI East Gas Corridor. Those criteria are analogous to those eventually
included in Article 4(2)(b) and Annex IV to the TEN – E Regulation (which at the
time was still being debated by the EU Council and the European Parliament) and
do not discriminate against Russian gas or a fortiori against Russian service
suppliers or services.372
More specifically, the sub-criterion "diversification of
sources of supply" applies indistinctly, regardless of the origin of the gas.
Moreover, that sub-criterion does not distort market opportunities in favour of
domestic gas (or of gas from other third countries) and to the detriment of Russian
gas. Rather, it contributes to achieve greater equality of competitive opportunities
for gas from all potential sources, including Russia.
374. Contrary to Russia's assertions373
, the PCI candidate projects were not assessed
according to the criteria and weights mentioned in the document provided by
Russia as Exhibit RUS – 147. That document was used as supporting material for a
presentation given by officials of the Commission on 15 February 2002, i.e.
several months before the candidate projects were even submitted. The slide relied
upon by Russia is but a fictional example used to illustrate how the evaluation
could work in practice. The criteria and the weights shown in that slide are not
those eventually used by the Regional Group in its assessment of projects. Instead,
the criteria and weights actually used by the Regional Group are those shown in
the table below:
[[ ]]
375. It will be noted that the above table does not include the sub-criteria
"diversification of external supply" and "lower import dependency" mentioned by
Russia , but instead the sub-criteria "route", "source", "counterpart" and "impact on
capacity HHI", all of which are mentioned in in Article 4(2)(b) and in Annex IV to
371 Russia's response to Panel Question 48, para. 241. The terms of reference of the Regional Group for
the NSI East Gas Corridor have been provided by Russia as Exhibit RUS – 145.
372 EU's first written submission, paras. 819-825.
373 Russia's response to Panel Question 48, para. 242.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 114 -
the TEN – E Regulation. It will also be noted that the sub-criteria "diversification
of sources of supply" is given a weight of just 9 per cent.
376. Contrary to Russia's contention, it is not true that, with a score of 0.19, [[ ]]
"received - by far – the lowest score of all projects"374
. In fact, as shown by the
table below, out of a total of 53 candidate projects, 10 other projects scored lower
according to the quantitative criteria in Article 4(2)(b) of the TEN-E Regulation,
whereas two other projects achieved the same score.
[[ ]]
377. Last, also contrary to Russia's assertions375
, [[ ]] scored low not only on the sub-
criterion "diversification of source of supply", but also on most other quantitative
criteria, as shown by the table below:
[[ ]]
378. Russia further contends that the response given by EU Commissioner Oettinger to
a question from a member of the European Parliament would confirm that "[[ ]]
would never be able to obtain PCI status".376
However, in essence Commissioner
Oettinger limited himself to recall that, unlike NABUCCO, the [[ ]] project did not
fit within the legal definition of the Southern Gas Corridor (SGC). This is
uncontroversial since [[ ]] was not designed to transmit gas "from the Caspian
Basin, Central Asia, the Middle East and the Eastern Mediterranean", but instead
from Russian Siberia. But this does not imply that [[ ]] "would never be able to
obtain PCI status" within a different corridor. Indeed, this was understood by the
promoters of the [[ ]] project, who applied for designation as PCI within the NSI
374 Russia's response to Panel Question 48, para. 243. In support of this assertion Russia cites a table
included in a presentation prepared by the consultant Booz & Co and provided by Russia as Exhibit
RUS – 146. That table is incomplete in two respects: first it includes only pipelines, to the
exclusion of other types of infrastructure; and second, it does not include projects which were
assessed according to the quantitative criteria of Article 4(2)(b) of the TEN – E Regulation, but
were eventually considered ineligible under the criteria of Article 4(1)(c), or projects that were
eventually "clustered" with other projects.
375 Russia's response to Panel Question 48, para. 244.
376 Russia's response to Panel Question 48, para. 243, referring to Exhibit RUS – 165.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 115 -
East Gas corridor and not within the SGC. To repeat, the [[ ]] project was deemed
eligible for the NSI East Gas corridor, but was not selected only because it
obtained a relatively low score as compared to other projects.
379. In response to Panel Question 74, Russia alleges, without providing any evidence,
that the decision to cancel the [[ ]] project "was a direct consequence of the EU's
decision to score the project so low as to make it unable to ever obtain PCI
designation".377
The European Union does not wish to speculate about the real
reasons for the cancellation of the [[ ]] project. It would note, however, that
Russia's assertion seems implausible in view of the fact that the Commission
Regulation adopting the first list of PCIs had been adopted already on 14 October
2013378
, whereas the decision to cancel the [[ ]] project was not announced until
more than one year later, on 1 December 2014.379
[[ ]] decision to cancel [[ ]]
forced ENTSO-Gas to make an additional call for projects in April 2015 in order
to mitigate the withdrawal of [[ ]]. 380
5.3. CLAIMS XXV AND XXVI: ARTICLE III:4 GATT AND ARTICLE I:1 GATT (RUSSIA'S
CLAIMS 30 AND 31)
380. Russia's claims against the TEN – E measure under both Article III:4 GATT and
Article I:1 GATT raise similar issues and will be addressed together in this
section.
5.3.1. De iure claims
381. For the reasons set out in the EU's first written submission381
, the TEN –E measure
does not discriminate de iure between Russian gas and EU gas or between Russian
gas and gas from any third country.
377 Russia's response to Panel Question 74, para. 327
378 Commission Delegated Regulation (EU) No 1391/2013 (Exhibit EU - 3).
379 Russia's response to Panel Question 74, para. 327.
380 Press release: European Network of Transmission System Operators for Gas (ENTSOG) publishes
an addendum to the Annex A of the Ten Year Network Development Plan 2015, 29 June 2015,
http://www.entsog.eu/public/uploads/files/publications/Press%20Releases/2015/PR0090-
15_150629_Press%20Release_TYNDP2015_Addendum.pdf (Exhibit EU-133).
381 EU's first written submission, paras. 815-825.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 116 -
382. The Panel has asked Russia to identify any language in the TEN –E measure that
would support a finding of de iure inconsistency with either Article I:1 or Article
III:4 GATT.382
In response to this question, Russia limits itself to cite, once again,
the reference in the definition of the BEMIP Gas corridor to the objective of
ending the dependency on a "single supplier".383
As discussed below, however,
this objective does not lead to de iure discrimination against Russian gas.
383. The various priority corridors have been defined so as to cover in a balanced
manner all the main potential sources of supply of gas within and around the
European Union, as well as the supply needs of all EU Member States. For
geographical reasons, it is inevitable that not each corridor (and not each
infrastructure within each corridor) will contribute to facilitate the transmission or
storage of gas from each and every potential source to an identical extent. For that
reason, the existence of discrimination cannot be assessed by considering in
isolation just one of the priority corridors, such as BEMIP Gas. Instead, it is
necessary to make an overall assessment of all corridors, as well as of the already
existing infrastructures outside the current priority corridors. As explained in the
EU's first written submission384
, looking at each corridor or infrastructure in
isolation would lead to manifestly absurd and unacceptable results, as Russia has
been forced to concede in response to Panel Question 51.
384. Until 1991 Estonia, Latvia and Lithuania were part of the Soviet Union. As a
consequence, those three EU Member States are already adequately connected to
sources of gas supply in Russia by infrastructure built or supported by the Russian
authorities and their predecessors. For the same historical reasons, those EU
Member States were, until recently, totally isolated from other EU Member States
and sources of gas supply. One of the objectives of the BEMIP Gas corridor
priority corridor is to remedy this deficiency, by ensuring adequate connections
also between the Baltic States and Finland and other EU Member States. As
already explained by the European Union, those connections will not distort
market opportunities in favour of domestic gas (or of gas from other third
382 Panel Question 48.
383 Russia's response to Panel Question 48, paras. 238-240.
384 EU's first written submission, para. 825.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 117 -
countries) and to the detriment of Russian gas. Rather, they will contribute to
achieve greater equality of competitive opportunities for gas from all potential
sources.385
385. Moreover, while the BEMIP Gas corridor priority is not aimed at improving the
connections between Russia and each of the four EU Member States concerned,
this does not mean that the infrastructures within the scope of the BEMIP Gas
corridor will not benefit also Russian gas. For example, as already explained by
the European Union, both the first and the second Union lists include a project for
enhancing the Underground Gas Storage (UGS) facility in Inčukalns, Latvia (PCI
8.2.4), which is likely to continue to be used to store mainly Russian gas with a
view to supplying users in Latvia, Lithuania and Estonia, as well as in Russia (the
area of Saint Petersburg)386
. Similarly, other BEMIP Gas projects such as PCI 8.5
(gas interconnector Poland – Lithuania GIPL) and PCI 8.1.1 (gas interconnector
Estonia – Finland, Balticonnector) can be used not only to transmit gas into the
Baltic States or Finland from other sources of supply, but also to transmit Russian
gas to other EU markets after transiting through the territory of those EU Member
States.
5.3.2. De facto claims
386. The European Union has also shown that the TEN – E measure does not
discriminate de facto either between Russian gas and EU gas or between Russian
gas and gas from any third country.387
387. As explained by the European Union, all PCIs can be used for gas of all sources,
including Russian gas, and in practice many PCIs are likely to be used for Russian
gas, sometimes to a large extent. The European Union has provided specific
examples of those PCIs.388
The Panel has asked Russia to comment on those
examples.389
In its response, Russia does not dispute that the examples of PCIs
provided by the European Union will facilitate the transmission or storage of
385 EU's first written submission, paras. 821-825.
386 EU's first written submission, para. 828.
387 EU's first written submission, paras. 826-837.
388 EU's first written submission, paras. 828-829.
389 Panel Question 126.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 118 -
Russian gas. Instead, Russia now claims, for the first time, that those PCIs "are
eligible for only a fraction of the financial support that is provided to the PCIs not
involving the transmission or storage of Russian natural gas"390
. As discussed
below, this allegation has no basis whatsoever on the TEN – E Regulation or in the
co-funding decisions implementing that regulation.
388. In accordance with Article 14(1) of the TEN – E Regulation, all designated PCIs
falling within one of the gas priority corridors are eligible for financial assistance
in the form of grants for studies and financial instruments, irrespective of the
origin of the promoter of the project or the origin of the gas.
389. In turn, Article 14(2) of the TEN – E Regulation provides that all PCIs falling
within one of the gas priority corridors are eligible for EU financial assistance in
the form of grant for works if they fulfil the criteria specified in Article 14(2) of
the TEN – E Regulation. Those criteria do not include, either directly or indirectly,
the origin of the promoter or the origin of the gas to be transmitted or stored.
390. As explained in the EU's first written submission391
, in practice only a few among
the eligible PCIs receive financial support from the European Union. The decision
whether to co-fund an eligible PCI is taken according to objective evaluation
criteria, which do not include, either directly or indirectly, the origin of the
project's proponent or the origin of the gas.392
391. The comparison drawn by Russia between the financial contributions made to the
six PCIs mentioned by the European Union and those made to PCIs 8.2.3 and
8.5393
is meaningless because it fails to take into account that not all the projects
concerned were at the same stage of maturity in 2014, when the grants were
applied for, and that the grants being compared cover very different types of costs.
390 Russia's response to Panel Question 126, para. 522.
391 EU's first written submission, para. 780.
392 The criteria and procedures used for evaluating applications under the Connecting Europe Facility
programme, including those made in respect of gas PCIs, are described in the Guide for Applicants
issued by the Innovations and Networks Executive Agency: Guide for Applicants issued by the
Innovations and Networks Executive Agency. Call for proposals CEF-Eenergy-2016-2. June 2016
(Exhibit EU-134).
393 Russia's response to Panel Question 126, para. 523.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 119 -
392. The contributions received by PCI 8.2.3 and PCI 8.5 in 2014 consisted of grants
for works made in accordance with Article 14(2) of the TEN-E Regulation. In
contrast, the contributions received by PCI 6.8.2, PCI 6.20.2, PCI 6.1.1 and PCI
6.4 consist of grants for studies pursuant to Article 14(1) of the TEN-E
Regulation394
. Since the contributions consist of a percentage of the eligible costs,
it is only logical if the grants for studies received by PCI 6.8.2, PCI 6.20.2, PCI
6.1.1 and PCI 6.4 were lower than the grants for works received by PCI 8.2.3 and
PCI 8.5. Indeed, the costs of studies are typically within the range of a few million
Euros, whereas the eligible costs of works can reach several hundred millions.
393. Russia's allegations are further refuted by the fact that in 2015 the promoters of
PCI 6.1.1 (one of the two projects which, according to Russia, would have
received less favourable treatment because they facilitate the transmission of
Russian gas) received a grant for works of € 62.659.000395
, which is almost twice
the amount of support provided to PCI 8.2.3.
5.3.3. In the alternative, the TEN – E measure is justified under
Article XX j) GATT
5.3.3.1 Introduction
394. The European Union submits in the alternative that, in the event that the Panel
were to find that the TEN – E measure accords less favourable treatment to gas
imported from Russia than to domestic gas or to gas imported from any other
country in a manner inconsistent with Article III:4 GATT and/or with Article I:1
GATT, respectively, the TEN - E measure would, nevertheless, be justified under
the exception provided for in Article XX (j) GATT.
395. The European Union will first set out the legal standard for the application of
Article XX (j) GATT. The European Union will then apply that standard to the
relevant facts and show that:
gas is a product in "short supply" in the European Union;
394 [[ ]] did not apply for any grants in 2014. [[ ]] applied in 2014 for a grant for works. The application
was not granted because the project failed to obtain the required minimum score in respect of one
of the evaluation criteria.
395 List of actions selected for receiving assistance under the first CEF Energy 2015 call for proposals.
(Exhibit EU-135).
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 120 -
the TEN - E measure is "essential" for the "acquisition and distribution" of gas;
the TEN – E measure is "consistent with the principle that all Members are
entitled to an equitable share of the international supply" of gas; and
the aspects of the TEN – E measure challenged by Russia are temporary in
nature.
5.3.3.2 Legal standard
396. Article XX(j) GATT provides, in relevant part, that nothing in the GATT shall be
construed to prevent the adoption or enforcement by any Member of measures:
essential to the acquisition or distribution of products in general
or local short supply; Provided that any such measures shall be
consistent with the principle that all Members are entitled to an
equitable share of the international supply of such products, and
that any such measures, which are inconsistent with the other
provisions of the Agreement shall be discontinued as soon as the
conditions giving rise to them have ceased to exist.
397. The Appellate Body has explained that the evaluation of a defence under Article
XX GATT involves a "two-tiered analysis":396
first, the panel must examine whether the measure at issue is provisionally
justified under at least one of the subparagraphs of Article XX; and
second, the panel must determine whether the measure is applied in a manner
that satisfies the requirements of the chapeau of Article XX.
The "first tier" 5.3.3.2.1
398. According to the Appellate Body, in order to justify provisionally a measure under
a paragraph of Article XX GATT, two elements must be shown: first, that the
challenged measure is "designed" to address the particular interest specified in that
paragraph397
; and, second, that there is a "sufficient nexus" between the measure
and the interest protected.398
396 See e.g. Appellate Body Report, US- Gasoline, p. 22, DSR 1996:I, 3, at 20; Appellate Body Report,
Dominican Republic – Import and Sale of Cigarettes, para. 64; Appellate Body Report, Brazil –
Retreaded Tyres, para. 139; Appellate Body Report, EC – Seal Products, para. 5.169; and Appellate
Body Report, India – Solar Cells, para. 5.57. 397 See e.g. Appellate Body Report, India – Solar Cells, para. 5.57 and the case-law cited therein.
398 See e.g. Appellate Body Report, India – Solar Cells, para 5.57 and the case-law cited therein.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 121 -
399. More specifically, in the case of Article XX(j) GATT it must be shown that:
the measure is designed to address the "acquisition or distribution of products
in general or local short supply"; and
the measure is "essential" to address that interest.
400. The provisional justification of a measure under Article XX(j) GATT is subject to
the following two additional requirements:
the measure "must be consistent with the principle that all Members are
entitled to an equitable share of the international supply of the products
concerned"; and
the measures must be "discontinued as soon as the conditions giving rise to [the
measure] have ceased to exist".
(a) Meaning of "products in general or local short
supply"
401. The Appellate Body has explained that the assessment of whether a product is in
"general or local short supply" requires "a case-by-case analysis of the relationship
between supply and demand based on a holistic consideration of all relevant
factors." 399
402. In particular, according to the Appellate Body, a panel should examine
The extent to which a particular product is 'available' for purchase
in a particular geographical area or market, and whether this is
sufficient to meet demand in the relevant area or market.400
403. The terms "general" or "local", together with the disjunctive "or", indicate that the
relevant area or market must include all or part of the territory of the Member
invoking the defence.401
As regards the relevant factors for assessing the existence
of a shortage in that area or market, the Appellate Body has specified that the
analysis may, in appropriate cases, take into account
399 Appellate Body Report, India – Solar Cells, para. 5.74.
400 Appellate Body Report, India – Solar Cells, para. 5.71
401 Appellate Body Report, India – Solar Cells, para. 5.67
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 122 -
… not only the level of domestic production of a particular
product and the nature of the product that is alleged to be "in
general or local short supply"235, but also such factors as the
relevant product and geographic market236, potential price
fluctuations in the relevant market, the purchasing power of
foreign and domestic consumers, and the role that foreign and
domestic producers play in a particular market, including the
extent to which domestic producers sell their production abroad.
Due regard should be given to the total quantity of imports that
may be "available" to meet demand in a particular geographical
area or market. It may thus be relevant to consider the extent to
which international supply of a product is stable and accessible,
including by examining factors such as the distance between a
particular geographical area or market and production sites, as
well as the reliability of local or transnational supply chains.
Whether and which factors are relevant will necessarily depend
on the particularities of each case.402
404. The Appellate Body has further clarified that "a consideration of potential risks of
disruption in supply of a given product may inform the question of whether a
situation of short supply exists".403
(b) The meaning of "essential"
405. The Appellate Body has explained that the "necessity" of a measure under the
various paragraphs of Article XX GATT which use that term must be assessed
through a "process of weighing and balancing of a series of factors".404
In India –
Solar Cells, the Appellate Body confirmed that the same process of weighing and
balancing also is relevant in assessing whether a measure is "essential" within the
meaning of Article XX(j) GATT.
405
406. According to the Appellate Body, the relevant factors to be weighed and balanced
include, in particular, the following:406
the relative importance of the objective pursued by the measure;
the contribution of the measure to that objective; and
402 Appellate Body Report, India – Solar Cells, para. 5.71. Underlining added.
403 Appellate Body Report, India – Solar Cells, para. 5.76.
404 Appellate Body Report, Korea – Various Measures on Beef, para. 164; and Appellate Body Report,
EC – Seal Products, para. 5.169. 405 Appellate Body Report, India – Solar Cells, para. 5.63.
406 See e.g. Appellate Body Report, Korea – Various Measures on Beef, para. 164; Appellate Body
Report, Brazil- Retreaded Tyres, paras. 156 and 178; Appellate Body Report, China – Publications
and Audiovisual Products, paras. 237-249; Appellate Body Report, EC – Seals products, para.
5.169; Appellate Body Report, India – Solar Cells, para. 5.63.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 123 -
the restrictive effect of the measure on international commerce.
407. The Appellate Body has stated that panels enjoy certain latitude in setting out their
approach to determine the contribution of a measure to its objective. That approach
may be performed in qualitative or quantitative terms. Ultimately, the choice of the
approach to be followed "depends on the nature, quantity and quality of the
evidence existing at the time the analysis is made".407
408. Following the above analysis, the challenged measure should, in most cases, be
compared with alternative measures that are less trade restrictive, while making an
equivalent contribution to achieving the desired level of protection of the relevant
objective.408
409. The alternative measure must be "reasonably available".409
A measure is not
reasonably available "if it is merely theoretical in nature, for instance where the
responding member is incapable of taking it"410
, or "where the measure imposes an
undue burden […], such as prohibitive costs or substantial technical difficulties"
on either the responding Member411
or the industry concerned.412
The "second tier" 5.3.3.2.2
410. Under the "second tier" the Panel must consider whether the measure is "applied"
in a manner that would constitute
"a means of arbitrary or unjustifiable discrimination between countries where
the same conditions prevail"; or
"a disguised restriction on international trade".
407 Appellate Body Report, Brazil – Retreaded Tyres, paras 145 and 146. Appellate Body Report, EC –
Seals Products, para. 5.221.
408 See e.g. Appellate Body Report, Brazil – Retreaded Tyres, para. 156; and Appellate Body Report,
EC – Seal Products, paras. 5.169 and 5.261. 409 Appellate Body Report, EC – Seal Products, para. 5.258.
410 Appellate Body Report, EC – Seal Products, para. 5.258.
411 Appellate Body Report, EC – Seal Products, para. 5.258.
412 See e.g. Appellate Body Report, EC – Seal Products, para. 5.277.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 124 -
411. The European Union refers to the legal standard for the application of these two
requirements which it has described in its first written submission.413
Burden of proof 5.3.3.2.3
412. A responding party invoking an affirmative defence bears the burden of
demonstrating that its measure satisfies the requirements of that defence.414
However, the Appellate Body has clarified that, in establishing the requisite nexus
between the measure and the relevant interest, the responding party does not have
to "show, in the first instance, that there are no reasonably available alternatives to
achieve its objectives".415
Rather, it is for the complaining Member "to identify
possible alternatives to the measures at issue that the responding Member could
have taken".416
If the complaining Member has put forward a possible alternative,
the responding Member may seek to show that the measure in question is not, in
fact, "reasonably available" or that it is not a genuine alternative because it would
fail to achieve the desired level of protection.417
5.3.3.3 Gas is a product in "short supply" in the European
Union
413. As will be explained below, a number of factors coalesce to create a situation of
"shortage" of supply of gas in the European Union within the meaning of Article
XX(j) GATT. Some of those factors reflect the unique characteristics of gas and
are common to all gas markets, whereas others are specific to the EU market for
gas.
414. The supply of gas from any given source, or through any given route, may be
disrupted by events such as infrastructure breakdowns, commercial disputes,
natural disasters, social unrest, political actions or terrorism. As described in the
EU's first written submission418
, major disruptions of gas supply as a result of
413 EU's first written submission, 167-174.
414 See e.g. Appellate Body Report, EC – Seal Products, para 5.169. 415 Appellate Body Report, Brazil - Retreaded Tyres, para. 156. 416 Appellate Body Report, Brazil – Retreaded Tyres, para. 156. 417 Appellate Body Report, Brazil – Retreaded Tyres, para. 156. 418 EU's first written submission, para. 487.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 125 -
those events are by no means uncommon occurrences, either in the European
Union or in other countries.
415. As further explained in the EU's first written submission419
, gas is far less fungible
than other sources of energy, such as oil or coal. The transmission of gas
necessitates especially dedicated fixed infrastructure which is both very costly and
time-consuming to build. For that reason, in the event of a disruption affecting a
source of supply of gas or a route of supply of gas, it is not possible to resort to an
alternative source or route of supply unless the required infrastructure is already in
place.
416. In the European Union two additional factors aggravate further the risks of
disruptions of supply of gas:
417. First, the European Union is largely dependent on a relatively limited number of
sources of supply. The European Union imports 66 % of the natural gas that it
consumes. Several EU Member States import all420
or almost all421
their gas needs
from one single external source of supply. As a consequence, the European Union
is vulnerable to disruptions of supply of gas resulting not only from events in its
own territory, but also from events which may take place in the country of origin
of the gas or in the territory of any of the countries through which the gas must
transit before reaching EU territory and over which the EU authorities have no
control whatsoever.
418. Second, for historical reasons, the infrastructure interconnecting the transmission
networks of the various EU Member States is often inadequate, which leads to the
fragmentation of the EU market along national lines.
419. The above factors expose the European Union to genuine and serious risks of
disruption of supply of gas. Those risks have in the past materialised from time to
time. In particular, as explained in the EU's first written submission422
, in 2006423
419 EU's first written submission, para. 486.
420 Bulgaria, Finland and Slovakia.
421 Estonia, Latvia and Lithuania.
422 EU's first written submission, para. 487.
423 Following a dispute between the Ukrainian oil and gas company Naftogaz Ukrainy and Gazprom,
Gazprom cut off its deliveries of gas to Ukraine on 1 January 2006. The situation deescalated after
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 126 -
and again in 2009424
some EU Member States were affected by major disruptions
of supply, with dire social and economic consequences, following the interruption
of the transit of Russian gas through Ukrainian territory. Further disruptions have
occurred since 2009, though on a smaller scale than in 2006 and 2009.
420. As recalled above, the Appellate Body has clarified that the "potential risks of
disruption in supply" of a given product are relevant in assessing whether a
situation of "short supply "exists. The Appellate Body has further clarified that, in
assessing whether a situation of short supply exists, it may be relevant to examine
4 January 2006, as a preliminary agreement was found. In these four days, Austria, France,
Germany, Hungary, Italy and Poland reported a reduction of gas pressure in their own pipelines of
as much as 30%. (See Jon Henley, "Is Europe's gas supply threatened by the Ukraine crisis?" in The
Guardian, 03.03.2014. Available at: https://www.theguardian.com/world/2014/mar/03/europes-gas-
supply-ukraine-crisis-russsia-pipelin) (Exhibit EU-136).)
While no EU Member States had to interrupt supplies to customers, the EU Member States in
Eastern and South-Eastern Europe relying heavily on Russian gas saw their supplies fall drastically.
The volumes delivered from Russia were down by 40 % in Hungary, by 14 % in Poland, by 25% in
France, and by almost a third in Austria, Slovakia and Romania (See Jonathan Stern, The Russian-
Ukrainian gas crisis of January 2006, Oxford Institute for Energy Studies, 16.01.2006, p. 9.
Available at: https://www.oxfordenergy.org/wpcms/wp-content/uploads/2011/01/Jan2006-
RussiaUkraineGasCrisis-JonathanStern.pdf )(Exhibit EU-137).)
424 The gas crisis of 2009 began as a result of a similar dispute between Ukraine and Gazprom over the
gas prices and supplies for that year. On 2 January 2009, Poland, Romania, Bulgaria and Hungary
reported a reduction of gas pressure in their own pipelines. From 7 to 20 January 2009, Gazprom
stopped its gas delivery to Ukraine, affecting the supplies to the European Union transiting through
the country (See "Russia vows to end gas shortage" in BBC News, 02.01.2006. Available at:
http://news.bbc.co.uk/2/hi/europe/4574630.stm.) (Exhibit EU-138).)
The most serious effects of the disruption of Russian gas supply were felt in South-Eastern Europe,
which was cut off completely. (Simon Pirani, Jonathan Stern and Katja Yafimava, The Russo-
Ukrainian gas dispute of January 2009: a comprehensive assessment, Oxford Institute for Energy
Studies, February 2009, p. 22. Available at:
http://citeseerx.ist.psu.edu/viewdoc/download?doi=10.1.1.443.8094&rep=rep1&type=pdf.) (Exhibit
EU-139).)
Russian gas supply to Bulgaria was cut by up to 100 % during the crisis, which caused a loss of
around 9% of Bulgarian GDP. As the country relied exclusively on Russian gas, most major gas
consumers, such as the fertilizer industry, were disconnected. Slovakia saw its imports of Russian
gas cut by 97 %, Austria by 66 %, the Czech Republic by 71 %, Slovenia by 50%, Hungary by 45%
and Poland by 33%. (Press Release: "Member State general situation according the significance of
impact", European Commission, 09.01.2009.) (Exhibit EU-140).)
In Croatia, where the Russian gas supply was reduced by 40 %, the government immediately
declared a state of emergency. District heating companies and electric utilities had to shift to
alternative fuels while gas supplies to industry were disconnected. In Romania a third of the
Russian gas supply was cut, with the consequence that effective supply had to be restricted to some
industrial consumers. (Aleksandar Kovacevic, The Impact of the Russia–Ukraine Gas Crisis in
South Eastern Europe, Oxford Institute for Energy Studies, March 2009, pp. 11-12. Available at:
https://www.oxfordenergy.org/wpcms/wp-content/uploads/2010/11/NG29-
TheImpactoftheRussiaUkrainianCrisisinSouthEasternEurope-AleksandarKovacevic-2009.pdf),
(Exhibit EU-141).)
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 127 -
"the extent to which international supply of a product is stable and accessible",
including by examining factors such as "the reliability of local or transnational
supply chains".
421. For the reasons explained above, the existing "local and transnational chains" for
the supply of gas into, and within, the European Union can be affected by events
which are largely beyond the control of the EU's authorities and which may
seriously compromise the "stability" and "reliability" of those supply chains. In the
absence of adequate alternatives to the existing supply chains, the risks of a major
disruption of supply of gas in the European Union remain significant. As long as
those risks subsist, gas will be in "short supply" in the European Union within the
meaning of Article XX (j) GATT.
5.3.3.4 The TEN-E measure is essential for the acquisition and
distribution of gas
Relative importance of the objective 5.3.3.4.1
422. The aspects of the TEN- E measure challenged by Russia are designed to ensure
SoS of gas in the European Union. For the reasons explained in section 4.2.3.1 of
the EU's first written submission, SoS is considered a matter of fundamental
importance by the European Union.
Contribution to the objective 5.3.3.4.2
423. The TEN – E measure seeks to facilitate the timely implementation of PCIs with a
view to achieving the various energy policy objectives of the European Union
defined in the TFEU425
, including the objective to ensure SoS of gas.
424. In order to achieve those objectives, the TEN – E measure aims at developing and
improving the connections between European Union and the main potential
sources of supply of gas within and around the European Union, as well as the
interconnections among the traditionally isolated markets of the various EU
Member States. The ultimate goal is "to build infrastructure needed to allow gas
from any source to be bought and sold anywhere in the EU, regardless of national
425 EU's first written submission, paras. 774-776.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 128 -
boundaries".426
By contributing to that goal, the TEN – E measure contributes to
the "acquisition and distribution" of gas in the European Union within the meaning
of Article XX(j) GATT and, thereby, to ensure SoS of gas.
425. As explained above, the transmission of gas necessitates especially dedicated fixed
infrastructure, which is both very costly and time-consuming to build. For this
reason, in the event of a disruption affecting a source of supply of gas or a route of
supply of gas, it is impossible to resort to an alternative source of supply or route
of supply, respectively, unless the required infrastructure is already in place. The
TEN – E measure facilitates the building of such infrastructure, so that, in case of
disruption of a source or route of supply, it may be possible to switch promptly to
alternative sources or routes of supply of gas, thereby ensuring the continued
"acquisition and distribution" of gas and hence the SoS of gas.
426. More precisely, the priorities and selection criteria challenged by Russia are
necessary in order to ensure that the resources made available under the TEN –E
measure are used to fill infrastructure gaps, rather than in order to promote
infrastructures which would merely duplicate already existing infrastructure. Such
a duplication of transmission capacities would not be "essential" to ensure the
continued "acquisition and distribution" of gas and to achieve SoS.
Trade - restrictiveness of the measure 5.3.3.4.3
427. The TEN – E measure places no restriction on the importation or sale of gas from
Russia or from any other country. On the contrary, by developing and improving
the connections with the main sources of potential supply of gas around the
European Union, as well as the interconnections between the EU Member States,
the TEN – E measure contributes to facilitate and promote trade in gas.
428. As explained above, the ultimate goal of the TEN – E measure is to build the
infrastructure needed to allow gas from any source to be bought and sold anywhere
in the European Union. In order to approach that goal, the TEN – E measure
provides certain regulatory and financial incentives for building missing
infrastructures or improving inadequate ones. But the TEN – E measure neither
prescribes nor prohibits the use of any particular infrastructure. The choice
426 EU's first written submission, para. 824.
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 129 -
between the various sources and routes of supplies is left entirely to the market
operators.
429. To the extent that, as alleged by Russia, the benefits provided under the TEN – E
measure to certain infrastructures distorted competition between gas from different
sources, such distortion would be, having regard to the nature of the benefits
involved, minimal and temporary.
Alternative measures 5.3.3.4.4
430. In accordance with well-established case-law, it is for Russia to identify possible
alternatives.
5.3.3.5 The TEN – E measure is consistent with the principle
that all Members are entitled to an equitable share of the
international supply of gas
431. The TEN – E measure does not seek to replace the current suppliers of gas to the
EU market with new suppliers. Nor does it place any limit on the share which each
supplier of gas may achieve in the EU market. Quite to the contrary, the TEN – E
measure aims at ensuring that gas from all potential sources enjoy equal
competitive opportunities in the EU market.
432. As mentioned above, to the extent that, as alleged by Russia, the benefits provided
under the TEN – E measure to certain infrastructures distorted competition
between gas from different sources, such distortion would be minimal and
temporary and, therefore, would not prevent each Member from achieving an
"equitable" share of the EU market. Thus, Russia's share of imports of gas into the
European Union has remained at the same level, despite some fluctuations,
between 2005, the year preceding the adoption of Decision 1364/2006/EC (the
predecessor of the TEN – E Regulation) and 2015.427
5.3.3.6 The aspects of the TEN – E measure challenged by
Russia are temporary in nature
433. The TEN –E measure seeks to facilitate the timely implementation of PCIs. For
that reason, the Union list of PCIs is established every two years with an
427 See Import statistics for the period 2005-2015 in (Exhibit EU-142).
EU and its Member States – Certain measures relating to the energy sector Second Written Submission
(DS476) by the European Union
________________________________________________________________________________________
- 130 -
amendment of the TEN – E Regulation. Those PCIs which have reached sufficient
maturity cannot reapply and do not appear on the list anymore.428
434. Moreover, the PCIs being implemented in a given priority corridor must contribute
to the priorities defined in Annex I of the TEN – E Regulation for that corridor.
These priorities have been defined in view of the needs identified at the moment
when the TEN – E Regulation was enacted. Accordingly, at some point, the
priorities will be reassessed. Once a given priority is achieved, it will be redefined
or replaced as necessary.
5.3.3.7 The TEN – E measure is applied consistently with the
chapeau of Article XX GATT
435. The priorities and selection criteria challenged by Russia apply indistinctly,
regardless of the origin of the gas. In any event, those criteria are fully consistent
with the TEN – E measure's policy objective of ensuring SoS and do make a
genuine contribution to that objective. Any difference in treatment between
Russian gas and gas from other origin which might result from the application of
those criteria would thus not amount to "unjustified" or "arbitrary" discrimination.
436. In addition, as shown in the EU's first written submission, the selection of PCIs is
carried out in accordance with pre-established criteria stipulated in the TEN – E
Regulation, and in an open and transparent manner.
6. CONCLUSION
437. For all the above reasons, the European Union respectfully requests the Panel to
reject all of Russia's claims.
***
428 Article 3(4) and recital (24) of Regulation 347/20131.