inenvironmentclearance.nic.in/.../25052017utbko5l1kirthaiiitor2013.pdf · proposal was considered...

12
No.J-1 201 1 I 612012 -lA-l Ministry of Environment & Forests Government of lndia (lA-l Division) Paryavan Bhavan CGO.Complex, Lodi Road New Dethi - 110 003 Date: 5th June, 2013 To, The Chief Engineer Cl &DWing,Jammu J&D Power development Corporation Khuttar Market Sec'3 Extion Trikuta Nagar Jammu - 180 012 Subject: Kirthai Stage-ll HEP (930 MW) Project in Kishtwar District of Jammu & Kashmir U/ttls. J&K Power Development Corporation - for Scoping/TOR - regarding. Sir, This is with reference to your letter no. Cl&D/571-1117165'79 dated 6.2.2012 and 9.1.2013 on the above mentioned subject. Z. The proposal was eartier submitted for scoping ctearance for 990 MW. The ftow series have been approved by CWC on 1.9.2011. The flow series corresponding to monsoon flow in 90/. dependab[e year ranged from 673.7 to 1038.8 m3/sec, and a design discharge of 512 m3/sec'with bifuication of 413.47 m3/sec for 840 MW (6x140 MW) main undergiound powerhouse and 99.17 m3/sec for 90 MW dam'toe powerhouse has been adopt6d. 20% retease in lean season ftow ranging from 50 to 70 cumec was reported adequate to meet the downstream retease. As a resutt of downward revision of capacity from 990 MW to 930 MW, there witt be no submergence of Paddar Vattey. The project proposal was considered by Environment Appraisat Committee (EAC) for,River Vattey and hydroetectric Projects in iis meetings hetd on 30-31't March, 2012 &.1-2nd February, 2013- The comments ani observations of EAC on the proposal may be seen in the minutes of the meetings, which are avaitabte on the web-site of this Ministry. 3. tt is noted that the project envisages construction of a 121 m high concrete gravity dam across river (165 m from the deepest foundation levet) Chenab to generate 930 MW of hydropower. The catchment area of the project is 9987 Sq. Km. Totat tand requirement is about'416.25 ha, out of which 227.25 ha is forest [and, 40 ha is government land and 149 ha is private tand. Totat submergence area is about 331 ha. (Of which 155 ha isforest tand). An unflerground powerhouse is proposed with 6 units of 140 MW each + 90 MW (2$b MW ; 1x10 MW) auxitiary dam-toe powerhouse facititate to release of environmental ftows is atso proposed. About 15 famities witl be futty affected due to this project. Tota[ cost of the project is about Rs. 6087.48 Crores.

Upload: nguyencong

Post on 20-Mar-2019

214 views

Category:

Documents


0 download

TRANSCRIPT

No.J-1 201 1 I 612012 -lA-lMinistry of Environment & Forests

Government of lndia(lA-l Division)

Paryavan Bhavan

CGO.Complex, Lodi RoadNew Dethi - 110 003

Date: 5th June, 2013

To,

The Chief EngineerCl &DWing,JammuJ&D Power development CorporationKhuttar Market Sec'3 ExtionTrikuta NagarJammu - 180 012

Subject: Kirthai Stage-ll HEP (930 MW) Project in Kishtwar District of Jammu &

Kashmir U/ttls. J&K Power Development Corporation - for Scoping/TOR -

regarding.Sir,

This is with reference to your letter no. Cl&D/571-1117165'79 dated 6.2.2012 and

9.1.2013 on the above mentioned subject.

Z. The proposal was eartier submitted for scoping ctearance for 990 MW. The ftow

series have been approved by CWC on 1.9.2011. The flow series corresponding tomonsoon flow in 90/. dependab[e year ranged from 673.7 to 1038.8 m3/sec, and a design

discharge of 512 m3/sec'with bifuication of 413.47 m3/sec for 840 MW (6x140 MW) main

undergiound powerhouse and 99.17 m3/sec for 90 MW dam'toe powerhouse has been

adopt6d. 20% retease in lean season ftow ranging from 50 to 70 cumec was reported

adequate to meet the downstream retease. As a resutt of downward revision of capacity

from 990 MW to 930 MW, there witt be no submergence of Paddar Vattey. The projectproposal was considered by Environment Appraisat Committee (EAC) for,River Vattey and

hydroetectric Projects in iis meetings hetd on 30-31't March, 2012 &.1-2nd February, 2013-

The comments ani observations of EAC on the proposal may be seen in the minutes of the

meetings, which are avaitabte on the web-site of this Ministry.

3. tt is noted that the project envisages construction of a 121 m high concrete gravity

dam across river (165 m from the deepest foundation levet) Chenab to generate 930 MW

of hydropower. The catchment area of the project is 9987 Sq. Km. Totat tand requirementis about'416.25 ha, out of which 227.25 ha is forest [and, 40 ha is government land and

149 ha is private tand. Totat submergence area is about 331 ha. (Of which 155 ha isforesttand). An unflerground powerhouse is proposed with 6 units of 140 MW each + 90 MW

(2$b MW ; 1x10 MW) auxitiary dam-toe powerhouse facititate to release ofenvironmental ftows is atso proposed. About 15 famities witl be futty affected due to thisproject. Tota[ cost of the project is about Rs. 6087.48 Crores.

4. Based on recommendations of the EAC, the Ministry of Environment & Forestshereby accords ctearance for pre-construction activities at the proposed site as per theprovisions of 'the Environmental lmpact Assessment Notification, 2006 and subsequentamendment, 2009 atong with the fottowing Terms of Reference {TOR) for preparation ofEIA/EMP report. The EIA/EMP report shoutd contain the information in accordance withprovisions & stiputations as given in the Annexure-1. White preparing the EIA/EMP reportprevaiting norms shoutd be foltowed with respect to environmentat ftows, muck disposalsites and other parameters.

The Committee expressed its satisfaction over reduction in capacity from 990 MWto 930 MW as with this; land requirements and submergence area have come down,thereby saving Peddar vatley. The committee thus, agreed to the downward revision ofthe capacity of project to 930 MW subject to the fottowing conditions/additionat TORs:

. Keeping in view the proximity of protected forest [and, the Environmental Sensitivityis to be properly assessed and reftected in the EIA

o The EIA/EMP shoutd atso inctude the foltowing:

(i) Enumeration of atl ptant species betonging to atl groups, especiatty trees - number oftrees of eacli species and their volume in the submergence area; (ii) Studies onEconomic vatuation and Ecosystem Services will be carried out on the forest tost (iii)EMP: For Compensatory afforestation tree species affected in the forest witt be utitizedfor ptanting.

. Land cover and land-use pattern shoutd be given with Fatse Cotour Composition (FCC)o Flora of the Project Area: "29 taxa of flowering plants" appears to very [ow. Detaits

about Gymnosperms, Pteridophytes, shrubs and herbs are-to be presented in the EIAreport.

o The sampting locations are to be given.. Sampting tocations for ftorat/faunal studies appeared to be inadequate. Champion &

Seth (1968) shoutd be fottowed for forest typeso Environmental Evaluation: detaits of the environmentat evatuation should be given

and detaits of forest land/flora and fauna have to be presented in the EIA reporto Proposed Engineering and Biotogical measures: Use Coir mats - geotextiles on stopes

to prevent soil erosion and for raising plantations.. A study on environmentat ftow retease needs to be inctuded. Draw a separate cotumn

giving environmental ftow, spitt ftow, turbine ftow and ftow through the dam-toepowerhouse. Check the total retease d/s dam as per the prescribed norms. ln anycase retease of minimum environmental ftow must mimic the pre-dam flow patternof the river for sustaining the aquatic bio-diversity together with downstream userneed and accordingty, water withdrawal for power generation is to be regutated.Minimum environmental ftow retease would be 20Yo of average of four tean months oflean period and 20-30% of flows during non-tean and non-monsoon periodcorresponding to 90% dependabte year. The cumulative environmental ftow reteasesinctuding spittage during the monsoon period shoutd be about 30% of the cumulativeinflow during the monsoon periods corresponding to90/o dependabte year.

. The estimated PMF shown as 8140 cumec, whereas, the peak ftood hydrograph shows7440 cumce. This needs to be exptained/ reconciled in the EIA report.

5. The Consuttant engaged for preparation of EIA/EMP report has to be registeredwith Quatity Councit of lndia (QCI)/NABET under the scheme of Accreditation &Registration of MoEF. This is a pre'requisite.

6. Consultants shatt inctude a "Certificate" in EIA/EMP report regarding portion ofEIA/EMP prepared by them and data provided by other organization(s)/ laboratoriesinctuding status of approval of such laboratories.

7. The draft EIA/EMP report prepared as per the above Terms of References shoutdbe submitted to the State Potlution Control Board / Committee concerned forconducting Pubtic Hearing /Consuttation as per the provisions stiputated in EIA

Notification of 2006.

8. Att issues discussed in the Pubtic Hearing/Consuttations shoutd be addressed and

incorporated in the EIA/EMP Report. Final EIA/EMP report shoutd be submitted to theMinistry for Environmental Ctearance onty after incorporating these issues.

9. The TOR wi[[ remain vatid for a period of 2 years from the date of issue of thistetter for submission of EIA/EMP report atong with pubtic consuttation.

10. ln casq of any change in the Scope of the Project such as capacity enhancement,shifting of dam site/powerhouse and change in submergence etc., fresh scoping

ctearance has to be obtained by the project proponent.

11. lnformation pertaining to Corporate Environmental Responsibitity and

Environmentat Poticy shatt be provided in the EIA/EMP Report as per this Ministry'scircutar dated 19.5.2012.

12. This has approval of the Competent Authority.

(B. B. Barman)Director

Copy to:1. The Secretary. Ministry of Power, Shram Shakti, Bhawan, Rafi Marg, New Dethi-12. The Adviser (Fower), Ptanning Commission, Yojna Bhawan, New Dethi'110 001.3. The Principal Secretary (MPP & Power), Government of Jammu & Kashmir, Srinagar.4. The Secretary, Department bf Environment, Government of Jammu & Kashmir, Srinagar.5. Chief Engineer, Project Appraisat Directorate, Central Etectricityr Authority, Sewa

Bhawan, R.K. Puram, New Dethi- 110 066.6. The Regional Office, Ministry of Environment & Forest, Chandigarh.7. The Member Secretary, Jammu & Kashmir State Poltution Control Board, Parivesh

Bhavan, Gtadni, Transport Nagar, Narwat, Jammu'180 006.NIC Cett - with a request to uptoad in MoEF's websitePS to JS (AT)/Director (lA-l)/PVSRaoGuard fite.

(8. B.Barman)Director

8.9.10

n,I

(1)

Q)

' Annexure-l:

TERMS OT REI'ERENCE FOR CONDUCTING EIYVIRONMENT IMPACTASSESSMENT STUDY tr'OR 6A' CATEGORY HYDRO POWER PROJECTS AND

TNTORMAiTON TO BE INCLUDED IN EIA/EMP REPORT

Scoue of EIA Studies

-

The EIA Report should identi$/ the relevant environmental concerns and focus on potential --

impacts that may change due to the construction of proposed project. Based on the baseline ---

data collected for tluee (3) seasons (Pre-monsoon, Monsoon and Winter seasons), the status

of the existing environment in the area and capacity to bear the impact'on this should be

analysed. Based on this analysis, the mitigation measures for minimizing the impact shall be

suggested in the EIA/EMP study.

Details of the ProiecJ and Site

General introduction about the proposed project.

Details of project and site giving L-sections of all U/S and D/S projects of Chenab Riverwith atl relevant maps and figures. Connect such information as to establish the total

length of interferenci of Natural River, the total length of tunneling of the river and the

committed unresfricted release from the site of diversion into the main river.

A map of boundary of the project site'giving details of protected areas in the vicinity.ofproject location.Looation details on a map of the project area with contours indicating main project

features. The project layout shall be superimposed on a. contour map of ground

elevation showing main project features (viz. location of dam, Head works, main cana1,

branch canals, quarrying etc.) shall be depicted in a scaled map.

Layout details and map of the project along with contours with projgct components

clearly marked with proper scale maps of at least a l:50,000 scale and printed at least onA3 scale for clarity.Existence of National Park, Sanctuary, Biosphere Reserve etc. in the study area, if any,

should be detailed and presented on a map with distinct distances from the projectcomponents.j' Drainage pattern and map of the river catchment up to the proposed project site.

o Delineation of critically degraded areas inthe directly draining catchment on the basis ofsilt Yield lndex as per the methodology of All India Soil and Land Use Survey of India.

o Soil characteristics and map of the project area.

o Geological and seismo-tectonic details and maps of the area swounding the proposed

project site showing location of dam site and powerhouse site.. Rernote Sensing studies, interpretation of *t ttit imagery, topographic sheets along

with ground verification shall be used to develop the land use/land cover pattem of the

study,*ing overlaying mapping techniques viz. Geographic Information System (GIS),False Color composite (FCC) generated from satellite data of project area.

o Land details including forests, private and other land.o Demarcation of snow fed and rain fed areas for a realistic estimate of *re water

availability

?a

o Different riverine habitats like rapids,substaturn - bedrocks, rocks, boulbers,the study.

poolsn side pools and, variations in the riversand/silt or clay etc. need to be covered under

To know the present status of environment in the area" baseline data with respect toenvironmental components air, water, noise, soil, land;qiiJ"gy-iaii"ai".*it-ifi;;;Ifaqna), wildlife, socio-economic status etc.-should be collected-witl, io f* radius of the*Tn components of the project/site i.e. dam site ani d*"iirr;;;r. The air quality andnoise are to be monitored at such locations which are

^r"rir"r*r"iJr-v-& ecologically more

::*itive in the study area. The baseline studies should be,collected for 3 sgasons (pre-Monsoon, Monsoon and Post Monsoon seasons). rrr" stoay;;;-;ff;,"*r?rr".i,r*o Catchment area up-to the dam site.o Submergence Area

'Project area 91th" direct impryt-area should comprise of area falling within l0 km radiusfrom the periphery of rmr*oir, land coming *d;; submergence and *;;.;;;#;;dam upto the point where Tail Race Tunnel (rnD meets th;;.'-:-- '

o Downstream upto.10 km from tip of Tail Race Tunner (TRT).

(4) Details of the Methodolow

The methodology followed for collection of base line data along with details of number ofsamples and their locations in the map should be included, Study-area rfroufO be demarcatedproperly on tlie appropriate scale map. sampling sites shoula u. aepi.teiJoffiffi;;;parameter d,l,

ry9qer -legends. For forest classification, ctrarriion and S"A frq6s)classification should be followed.

(5) Methodolow for collection of Biodiversitv Data

- The number of sampling locations should be adequate to get a reasonable idea of thediversity and other attributes of flora and fauna. ftre'guiOing rd".6ffii;il1;;,,2*;tt tqav area (larger area should have larger numbEr of sampling tocatioiJ) i,irjT#r;;idiversity at the location, as known from sec,6ndury ro*".s (b"g. ealtern ii*auy* and lowaltitude sites should have a larger number of sampiing roruui"i-"*ine-il-tieilriaiilri,U;t'

- The entire area should be divided in grids of 5km X 5km preferuuty on a GIS domain.There afrei zsw of the grids should be iandornly selected zu r'*rpfinetri^]rr"rr -nafii;;;

be in the directly affected area (gnds- including-project components r"or, * i.re*uii]rrrr;powerhouse, tunnel, canal etc.) arra ure remuinlng fi tilr.j;i;;;;;Gr* of influencein 10 km radius form project components). At srich chosen location, th";;il;r#;;;sampling units (e.g. quadrats in case of flora/ransects in;;;i6;tffi;;;;;id;;;species area curves and the details of

!re.sag9 @raphs and ru*rruti* nu*Ler of species ina tabulated form) should be provided i.n the ereieiort. S;;;fth; ;;;;; ,lr;;-ds*;;;not be completely.overlapping with the study *.u uo*a*i"r. E;;;r-A;;;;ffiJEcounted and consid:t

9 tol seiecting 25Yo of ihegrids. rrr. r-*u., "i'-*iOr;;6, "rirv.jmay oome out as a decimal_number (i.e. it has an integral and a fractionjprrtl *fri;f,,h;"J;

be rounded to the next whole numbei.

- The conventional sampling is likely to miss-the presence of rare, enoangered and threatened(R.E'T.) species since they often occur in low densities and d d; ;if.*ri-rp;;;;

(

dr

usually secretive in behaviour. Rgaching the conclusion abggt the _absence

of such species

in the stgdy area based on such *"thodology is misleading. trt is very important to

Jb.ir**t tfr" rt"t6 of such species owing to tireir high conservation value. Hence likely

pid;oiiort, species shor,rl'rl be ascertained fr_om seoondarv sources by a p1op9r literature'r*ry for the said area including referring to field guidgs which are.now available for many

t*ona*i. grorpr in India. Bven titerattne tom studies/surveys h,9. larger landscapes

which include the study area for the concemed project must be relferred to siRce most

species from adjoining iatchments is likely to be present in the catchments in qu9{i9na $6ct suctr literature fofo the entire state can be referred to. Onoe a listing of possible R.E.T. rrp*i6 iorm the said area is developed, species specific methodologies should be adopted to

t.-'

;;.d; flr;ir'pr.rro.. in the study area wtrictr iould be far more conclusive as.compared

to the conventional sampling. If the need be, modern methods like camera ilapping can b9

resorted to, particulanf foi areas in the eastern Himalayas and fo1 secretive/noctumal

species. A ietraited listiiry of the literature referred to, for developing lists of R.E.T. species

,i.ofA be providea in ttrJgtA reports..

. The R.E.T. species rdferred to in this point should include species listed in Schedule I and III ;iyiiAi.fe furotection) Act, 1972 and those listed in the red data books (BSI, ZSI and

IUCN). '

(6) Comnonents of the EIA Stirdv

Various aspects to be studied and provided in the EIAIEMP report are zls follows:

A. Physical and Chemical Environment.'Geological&GeophysicalAspectsandSeismo-Tectonics:

o Physipal geography, Topography, Regional Geological aspects and structure of the

Catchment.o Tectonics, seismicrry and history of past earttrquakes in the area. A site specific

earthquake design shall be sent for approval of the NCSDP (N{ional csmmittee ofSeismic Design Parameters, Cental water commission, New Delhi for large dams.

o Landslide zone or area prone to landslide existing in the study area should be

examined. :

. Presence of important economic mineral deposit, if any.

Justification for location & execution of the project in relation to structural

components (dam height)..

fmpact of project on geological environment.

Meteorolory; Air and Noise!

o Meteorology (viz. Temperature, Relative humidity, wind speed/direction etc.) to be

collected fio* o"*"st IMD station... Ambient Air Quality with parameters viz. Suspended Particulate Matter (SPM),

Respirable Suspinded Particul4te Matter (RSPM) i.e. suspended particulate materials

<10 microns, Sulphur Dioxide (SO, and Oxides of Nitogen (NOx) in the study area

at 6locatiqns.. f*irting

"oir. levels and traffic deniity in the study arca at6 locations

Soil Characteristics

o soil classification, physic4 p.*qr.t:rs (viz., texture, porosity, bulk densiry and

::g^P.tgng capacity) and chemi.d la'#t '' (yi;.'ii,;il;hfi'.onductivity,magnesiumr calcium, total alkalinity, chlorides, ro&ror, potassium,

"rgr*ir r*U"i,

available potassium, available phosphorur, aAR, -nfid;;;;ijiiiry,

etc.) i6

Remofe sensing and GIS Studies

t Generation of thematic mlps viz., slope map, drainage frop, soil map, land use andap, eto. Based on these, trro*uti, *up;;;.*;i;r"t iriiv *+-ri""ri

De prepaxed

Water Quatity

o w-ater quality for both surface water.and ground ;;t"r "i iU physical parameters

(pH, temperature, erectricar conductivity, I5s)l (ii) chemic.l pararriil;(Afifit,Hardness, BOD, COD, NO2, pOa,_.CI,'3O+, iii K Ca, Mg, Sifioa, Oif'[Gre;1,phe.aolic corirpounds, residual sojium r*ug*irl Gtii

-Bril;;lU; ;.;;;,- g"rPI: Tgf cotifoun) and (1v) Heavy Metals (pb, is,'n& ca, Crfitotur cq cu,

o Delineation of sub and micro-watersheds, their locations and extent based on the AlllIndia Soil *t!q9 Uje S,rvey o.f rn&a telSrUSl O"p"*.i;;sffiffi;Govemment of India. Erosion levels in eacir *ioo-#atersii"o*Jft;tild;imicro-watershed through silt yield ford;(su) *.rrr.a

"f Alsius:

r-'v"'!r*EYu vr

Water Enyironment & Hydrolory

' Hy'dro-Meteorology ofge project viz..precipitation (snowfall, rainfaU), temperature,relative humidity, etc. Hydro-meteoroligi.ur rtuo.r'tr il;;i;#;'areu sr,oura ue

fgl}-Pd along-with real time telemetry and data *dritio" il,.* l"r inflows :

' [ff:f,il?*n*o water availability for the project, sedimentationrate, etc.o Basin characteristics - :

o CatasJrophic events like cloud bursts and flash floods, if any, should be documented.o For estimation of Sedimentation Rate, direct sampling of iu.r no;is-rfir'd.;;{d"q the_EIA studv, The study.rlorld b";;;;tJ il*#t;;;ffi:

o let up a G&D monitoring station and a few rain i.g. r",ions in the catchment areaforcol1ectingdata.dtrringtheinvestigation.o-'o-,--,-_-.-o Flow series, l'0 daily withgoyo,T5% and50% dependabre years dischargeso Information on the lO-daily flow basis for th9 ed per cent dependable i** a" no*iniercepted at the dam, theho* ai*rte;i; til;H;; ior* and the ,pr11 #ffii;;

the environmental flow and additional flow towards downstream of6;-d*, ilth;o The minimum pnvironmental flow shall be2}Yoof the flow of four conseoutive lean l

months of 90Yo -dependabre

yeag 30yo "ith; ;r;-rrg, monsoon flow. The fl;; fb,remaining months shall be in between 2o-30yo, i.p."a"g ;;- th. ;;;;;;;11il

yelireaents. A site specific study shall be currieJ orffi;;;pr* Jr**i'*ior.' Pdplogical studies/data asi approved by cwc shall be utlir.j in iii.-inrpu*tion of ,

EIA/EMp reporr. Actuar hydrological annual yi;il;;), d; b, ;i;;ii rriiliii."'

.it.li/a1 \." rlttrl +,,i .1

!.'i

.l

o Sedimentaiion data available with CWC may be used to find out the loss in storageover the years.

o A minimum'of I km distance from the tip of the reservoir to the tail race tunnelshould be maintained between upsteam and downsteam projects.

C Biological Environment

Besides primqfy studies, review of secondary datalliterature published for project area onflora & fauna including RET species shall be reported in EIA/EMP repofi.

Flora

o Characterization of forest types (as per Champion and Seth method) in the study areaand extent of each forest lype as per the Forest Working Plan.

o Dooumentation of all plant species i.e. Angiosperm, Gymnospbrm, Pteriodophytes,Bryophytes (all groups). ,

. General u.g.tutitn profile and floral diversity oovering all groups of flora includinglichens and orchids. A species wise list may be provided.

o Assessment of plant species with respect to dominance, densrty; frequency,abundance, diversity index, similarity index, importance value index (IVI) , ShannonWeiner index etc. of the species to be provided. Methodology used for ealculatingvanous diversity indices along with details of locations if quadrates, size oiquadrates etc. to be reported within the study area in different ecosystems.

. Existence of National park, Sanctuary, Biosphere Reserve etc in the study area, ifany, should be detailed

o F.conomically important species like medicinal plants, timber, fuel wood etc.. Details of endemic species found in the project area.. Flora under RET categories should be documented using Intemational Union for the

Conservation of Nature and Natural Resources (IUCN) criteria and Botanioal Surveyof India's Red Data list along-with economic significance. Species diversity

"r*Lfor RET species should be given;. Cropping pattern and Horticultural Practices in the study area.

i

Fauna:

o Fauna study and inventorisation should be carried out for all groups of animals in thestudy area. Their pre:sent status atongwith Schedule'of the species.

'1 . Documentation of fauna plankton (phyto and zooplankton), periphyton, benthos and

o lnformation (authenticated) on Avi-fauna and wildlife in the study area.o status'of avifauna their residenu migratory/ passage migrants etc.o Documentation of butterflies, if any, found in the area.o Details of endemic species found in the project area.o RET species-voucher specimens should be collected along-with GPS readings to

facilitate rehabilitation. RET faunal species to be classified as per IUCN Redbatalist and as per different schedule of Indian Wildlife (Protection) Act,1972.

o Existence of barriers and corridors, iiany, for wild.animals.o Compensatory afforestation to'compenrut. tlr" green belt area that will be removed,' ifany, as part of the proposed project development and loss of biodiversity.. Ciillection of primary data on agricultural activity, crop and their productivity and

inigation facilities components.

o For categoization of sub-catchment into various erosion ,classes and for theoonsequent CAT plan, the entire catchment (Indiarr Portion) is to be considered andnot only the directly the draining catchment

Aquatic Ecolory

.invertebrates, zooplankton,

o Fish and fisheries, their migration and breeding grounds.o Fish diversrty composition and maximum length & *eight of' the measured

populations to be studies for estimation of environmental flow; ,

o Conservation status of aquatic fauna.o Sampling for aquatic ecology and fisheries and fisheries must be conducted duringthree seasons - Pre-monsoon (summer), monsoon and winter. Sizes (engh &weight) of important fish species need'io be collected and Ur.rOiog=*i ffiir;

E Socio-Economic

-' Collection of baseline data on human settlements, health status of the community: and existing infrastructtue facilities for social welfare includin!. rorir6g df

population. -t ^Cotte"tion

of information with respgct to social awareness about the developmentalactivity in the area and social welfare measures existing and proposed byprojectproponent.

r Colleciion of information on sensitive habitat of historical;.uft*f and religious andecological importance.

' The socio-economic survey/ profile within 10 km of the study area for demographicprofile; Economic Stucture; . Developmental Profile; Agricultural prttices;Infrastructure, education facilities; health and sanitation facilities; availablecommunication network etc.

o Documentation of demographic, Ethnographic, Economic Structure anddevelopment profile of the area.

o Information on Agricultural Practices, Cultural and aesttretic sites, lnfrastructurefacilities etc. e

o Informatio.n on the dgpendence of the local people on minor forest produce and theircattle gazingrights in ttre forest land.

' List o1 all -th;

Project Affected Families with their name, og€, educationalqualification, family size, sex, religion, caste, sources of incomelf*a & house

loldings, other properties, occupation, source of income, house/lanil to be acquiredfor the project and house/land left with the family, any other property, possession of

o Special attention has to be given to vulnerable groups li.ke women, aged persons etc.

(7) Impact Prediction and Mitisation Measures

The adverse impact.due to the propose,cl p*jrrl should be assessed and effective mitigationsteps to abate these impacts should be described.

Air Environment

o Positive and negative impacts likely to.be accrued due to the project are listed.(S) Environmental Management plans j

l' catchment Area Treatment (cef) -r{an should be prepared micro-watershed wise.Identification,o{ free arainine/ oif:1r., d;;irirg;;i,-ent-.based upon :Remore sensing andGeographical Information svstlm rcrsi*.tt"a"i"gi"iia suaiil"tyfiki'Inde{ (syl) method ofAISLUS' Deptt' of Agriculture, Govt. "r

mJiu .oriiJ*ith ground,survey. Areas or watershedsfalling under 'very severe' and''ssvrr4 .r;ri.r;;grries should be provided and rgquired to betreated' Both biological as well as engineering *"d;"s should be proposed in consultation withstate Forest Depar[nent for ** rrqiiring ddrr;;-iear-wise ,riirdureorwork and monelaryallocation'strouta be prwided. rvritigation ;.d;;; ctrect s.hifting cultivation in the oatclrmentarea with provision for alternative ui'a u.ttrr rg'i.uitu*ipr"*lres should be included. .2' compensatory Afforestation shall be prepare! by ttre srate Forest "*;;;;

t ,r", of theforest land proposed to be diverted or conrtu"iion;f tilr projecl * p", ii', ilrest (conservation)Act' 1980' choice of plants for afforestation should-inciri; ili,l"ff iiC ,pgoirs,, if any. Thiswill be a part of the foiest clearance proposal.

' 3' Biodiversif and wildlife conservati* "14 .IUaygement

plan for the conservation andproservation ol.t*t endangered or endemio- flo'iaufaunal species or some National ,Pa'lc/sanctuarvl Biosphere Reslrve "r;td;;;;iL; ir. s"iriirlu. ur"*ua directry orindireotly by construciion ofthe prqiect, tr,* riit"6r" cinservatioiiaJrruriirrrould be prepared inconsultation with the state Foresi Drp"iliilil;d*;;ffiffiH?l"ri|6, detals. suitabreconservation techniques (in*itu/ex-situ) *ilii;;"p"*i und* the plan and the areas where suchconservation is proposed will be marked on u prgj"riLyort *up.

4' Fisheries conseryation and Managemer, Pl;-; rr".* fisheries nianagernent measuresshould be prepared for river *o ,.r""*oii. ir tt r .""rlrrtio.n or fish ladder/ fish-way etc. is notfeasible then measures for reservoir nrt rri.r *iiiuu"ffirca. The plan will detail out tho numberof hatchtiries' nurseriest' rearilg ponds .rc. propgrcd"qn'd9r the plan with proper drawings. trf anymigratory fish species is gettifu'atrertrg tfi fi1ii,ilfo routes,.time/season of upstream anddownstream migration, spiwnin-g grounds etc will ur al.uriua in aetaits. -----

5' Resettlement and Rehabilitation Ptan needed to be prepared on the basis of findings of thesocio-economic survey coupled withtheoutcomr-"t*[it;.ooruituti"n r,riil rr* nan:packageshall be prepared afteiconsrttationi"itr, the reprrs;diies orure project affected families and ttreState Government. Detailed budgetary estimates are to ue provided. Resettlements site should beidentified. rhe pran wlr arso il;rpd;;ffirililulior*"* strategies;6' Green Belt Devetopment Plan along tho periphery of the reservoiq uppr*rt ioads around ttrecolonies and other project.o*ponrnL,

loca pr*i"p*bs^m1st be suggested with physical andfinancial details' A iayout -up tt o*iog the propos"J'rito ro, developing the green belt should beprepared - :7 ' Reservoir Rim Treatment Ptan for stabilization of land sride / land- slip zones, if any, around thereservoir pe.pheY is to.be-prepared based onE;td ;riry of golory of the reservoirrim area. ,suitable engineering and biotogicut ,r*rr. f#;;rr;;;; ofidentified slip zones to bo:suggestedwith phvsical and financial scf,edule. a"t;;"p ;hffig the landstide/landslip zones shalt beprepared and appended in the chapter. ' r, qrv

lqrvouue'r'urfrD"r @'vr eucu us

8' Muck Qisposat PIan suitable sites for -dlqning of excavated materials should be identified, in l

consultation with state Pollution contror Boi';;J atrtr'F";J6rd;;lin *u.t disposalsites should be minimum 30;-;*"v;;irrTriri'"ffi The quantiry of,muck to bo generatedand the quantity of muck ry"potta?o te utilized rh"ll b; c-arcutatea in "orJt tion with the projectauthorities. Detairs of each dumping ,itu "ir. _i;;;""b. dl;ffiil;tu.r that can bedumped etc' should be worked'ouiana discussed ioidii*. pr"ii i"rirr,uuilitation of muckdisposal- sites should also be given. rh' i-ili;rl;;;'filr#;il;;'iTisposal sites,and

'1

lnI .i- - 11:. (' \.; -l:i

l:1 approach roads should be given. Th" pl* *r.at fye npsfcal and financial details of the medsures

proposed. Layout map showing the dumping sites'vis-d-vis other project components will be

prepared and appended in the chapter.

g. Restoration plan for Quarry Sites and landscaping of colony areas, working areas, roads. etc'-ffii[ ;i *ru

"oarreltii, e aggregate/clay etc. t"ifuir"a for construction of the projeot *9 +"

,o"p"tuy qo*i"rhir"r;houi-ri6 identified for the project should be.discussed along'with the

Engineering and Biological measures proposed. for.ttreii restoration with physical-and financial-d&"i-;y"";i ilp sho"wing quarry sites vis-d-vis other project oomponents, should be prepared.

10. Study of Design Earthquake Parameters: A site specific study of earthquake parameters shou! *

be dorre. Results of the site specific earthquake design parameters should be approved by National

Committee.of Seismic Design Parameters, Central Water Commission (NCSDP), New Delhi'

ll. Dam Break Analysis and Disaster Management Plan The outputs oldT break model should^ -

il;il;;J*itf, upp-priate graphs and-maps clearly bringing oq the impact of Dam Break

;il;t,r il iAentid,'ininautioi *r^, population and structues likely to be affected d}e t9

catastrophic floods in the event of dam irifrr., DMPwill be prepared lith the help of Dam B**;;rr[:-Mr.imurq water level that would be attained at various points on the downstream in

ou* tf du,n Ureat witt be marked on a detailed contour map of the downsteam area, to show the

extent of inundation. The action plan will include Emergency Action and Management plan

inolud-ing measures like preventive action notification, warning procedure and action plan for co-

ordination with various authorities

12. Water, Air and Noise Management Plans to be implemented during construction and post-

construction periods.

13. Public Eealth Delivery Plan including the provisions of drinking y1eT-.:upqly.for local-t p"prLtiqorhdf be in thi EIA/EMP Report. Status of the gxisting medicalfacilities in the project

ird" shail be discussed. possibilities of itrengthening of existing medical facilities, construction offfi *rAi"A infr*troeture etc. will be

"*plo..d after assessing the need of the labour force and

' local populace.

14-. Labour Management Plan for their Health and Safety.

'15. Sanitatign and Solid waste management plan for domestic waste from colonies and labour oamps

re. il."r Area Development plan to be formulated in consultation with the Reyepug offrcials.and

Village Pancatrayats. Appropriate schemes shall be prepared under EMP for the Local Area

Development Plan with sufficient financial provisions.

17. Environmental safeguards during construction activities including Road Construction.

18. Energr Conservation Measures for the w-o$ f9rc9 -during construction with physical

-a1dfrnaniial daails. Alternatives will be proposed for the labour force so that the exploitation of the

natural resource (wood) for the domestic and commercial use is curbed.

19. Environmental Monitoring Programme tp monitol thg mitigatory measures implemerrkd T.!htproject site is required will be pripared. Provision for Environment Management Cell should be

ir"a,". The plah wiil spef out the aspects, required to be .-qoolitored, monitoring

indicatorypararmeters with respect to each aspect and the agenoy responsible for the mo:ritoring ofthat particular aspeot throlghout the project implementation.

20. A summary of Cost Estimates for all the plans, cost for implementing all the Environmental

Management Plans.