in association with the kent & east sussex railway...
TRANSCRIPT
IN ASSOCIATION WITH THE KENT & EAST SUSSEX RAILWAY
Patrons: Gregory Barker MP, Chris Green MA FCIT
ROBERTSBRIDGE (RVR) STATION, STATION ROAD,
ROBERTSBRIDGE, EAST SUSSEX. TN32 5DG Tel: 01580 881833 Fax: 0870 916 6976
Registration Number: 2613553
John Henderson, NDD SE Assistant Asset Manager Highways Agency Federated House London Road Dorking RH4 1SZ
11
th February 2013
Dear Mr Henderson.
Rother Valley Railway – A21 Level Crossing Scheme
Consultation Response We are please to enclose our consultation response compiled on our behalf by Mott MacDonald. That in reply to Glen Thompson’s letter of 4
th May 2012 and your
subsequent comments received by email on 14th
September 2012. Our response to your points follows the consultation procedure laid down by the lead Government Authority The Office of the Rail Regulator (ORR). That process for consultation when seeking Powers to Construct and Operate a railway level crossing is detailed in Office of the Rail Regulator document: ‘Level Crossings: A guide for managers, designers and operators. Railway Safety Publication No. 7. December 2011’. In addition to the points you have raised, and that we have covered in the Mott MacDonald response report attached, you also sought clarification in two further matters:
Supply information on what protection the Highways Agency would have in the event that Rother Valley Railway ceased trading, particularly in respect of the ongoing maintenance or eventual removal of the proposed level crossing.
Response: RVR could arrange in consultation with the Office of the Rail Regulator for a provision to require the railway operator to have in place such protection by way of such as a charge of the railway assets to the estimated cost of removing the rails etc from the crossing and resurfacing the road as a normal carriageway. In any event those works would be a relatively straightforward task and not envisaged to be significantly expensive.
Supply information on the proposed public liability insurance of Rother Valley Railway.
Response: As part of any TWA/Level Crossing Order granted to operate the railway and level crossing the railway operator is required to maintain a minimum level of Public Liability Insurance. The current minimum level of insurance required by the ORR is £5m. We hope the enclosed is of assistance as we moved forward toward making formal application for Powers to construct and operate the railway Yours sincerely Mike Hart OBE Trustee: Rother Valley Railway Heritage Trust Director: Rother Valley Railway Ltd Office Tel: 01709 542907 Cell Phone: 07768 536100
Rother Valley Railway A21 Robertsbridge
Highways & Traffic Assessment Report (Response to HA Comments on A21 Crossing)
January 2013
Rother Valley Railway Ltd
313090 ITD ITQ 006 D
25 January 2013
Rother Valley Railway A21 Robertsbridge
Highways & Traffic Assessment Report (Response to HA Comments on A21 Crossing) January 2013
Rother Valley Railway Ltd
Mott MacDonald, Stoneham Place, Stoneham Lane, Southampton, SO50 9NW, United Kingdom
t +44 (0)23 8062 8800 f +44 (0)23 8062 8801, W www.mottmac.com
Robertsbridge Junction (RVR) Station, Station Road, Robertsbridge, Sussex TN32 5DG
Rother Valley Railway A21 Robertsbridge
Mott MacDonald, Stoneham Place, Stoneham Lane, Southampton, SO50 9NW, United Kingdom
t +44 (0)23 8062 8800 f +44 (0)23 8062 8801, W www.mottmac.com
Revision Date Originator Checker Approver Description
A 16.11.12 M D Lewis M Price M D Lewis First Issue
B 13.12.12 M D Lewis M Price M D Lewis Second Issue
C 17.01.13 M D Lewis R E Murdock R E Murdock Third Issue
D 25.01.13 M D Lewis R E Murdock R E Murdock Fourth Issue
Issue and revision record
This document is issued for the party which commissioned it
and for specific purposes connected with the above-captioned
project only. It should not be relied upon by any other party or
used for any other purpose.
We accept no responsibility for the consequences of this
document being relied upon by any other party, or being used
for any other purpose, or containing any error or omission
which is due to an error or omission in data supplied to us by
other parties
This document contains confidential information and proprietary
intellectual property. It should not be shown to other parties
without consent from us and from the party which
commissioned it.
313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
Chapter Title Page
Executive Summary i
1. Introduction 1
1.1 Background _______________________________________________________________________ 1 1.2 Project Chronology __________________________________________________________________ 2 1.3 Report Structure ____________________________________________________________________ 3
2. Location and Scheme Description 5
2.1 Location __________________________________________________________________________ 5 2.2 Scheme Description _________________________________________________________________ 6
3. Scheme Options 7
3.1 Overview _________________________________________________________________________ 7 3.2 Level Crossing _____________________________________________________________________ 8
4. Comparison of Scheme Options 9
4.1 Road Safety (Road Users) ____________________________________________________________ 9 4.2 Maintenance/Durability ______________________________________________________________ 10 4.3 Environmental ____________________________________________________________________ 10 4.4 Network Availability ________________________________________________________________ 10 4.5 Traffic Assessment _________________________________________________________________ 10
5. Traffic Assessment 11
5.1 Overview ________________________________________________________________________ 11 5.2 Highways Agency comments on Traffic Impact Study ______________________________________ 11 5.2.1.1 Flow Data ________________________________________________________________________ 11 5.2.1.2 Traffic Growth _____________________________________________________________________ 12 5.2.1.3 Queuing Analysis __________________________________________________________________ 12 5.2.1.4 Road Safety ______________________________________________________________________ 14
6. Road Safety Assessment 16
6.1 Background ______________________________________________________________________ 16 6.2 A21 near site of proposed crossing ____________________________________________________ 16 6.3 Comparative analysis of other sites ____________________________________________________ 16
7. Journey Time Assessment 18
7.1 Overview ________________________________________________________________________ 18 7.2 Journey Time Survey Findings ________________________________________________________ 18
8. Conclusions 20
Content
313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
8.1 Tourist Heritage Railway Transport ____________________________________________________ 20 8.2 Engineering ______________________________________________________________________ 20 8.3 Traffic Assessment _________________________________________________________________ 20 8.4 Road Safety ______________________________________________________________________ 21
Appendices 22
Appendix A. Non-Motorised User (NMU) Audit - Context Report ________________________________________ 23 Appendix B. Non-Motorised User (NMU) Audit Report ________________________________________________ 24 Appendix C. Traffic Impact Study ________________________________________________________________ 25 Appendix D. Traffic Impact Study – Supplementary Technical Note ______________________________________ 26 Appendix E. Personal Injury Accident Analysis Technical Note _________________________________________ 27 Appendix F. Journey Time Analysis Technical Note __________________________________________________ 28
i 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
Rother Valley Railway (RVR) Limited is seeking to reconstruct a section of railway between Bodiam
and Robertsbridge in East Sussex. This section is the final missing link in the Kent and East Sussex
Railway (KESR).
The reconstructed railway line will enable the direct interchange of passengers between KESR and the
mainline railway network at the new Robertsbridge Junction Station. Once complete this will enable
visitors to use the country’s public transport system to access the KESR and to use the line as a leisure
transport corridor serving popular attractions such as the National Trust’s Bodiam Castle and the historic
town of Tenterden.
In order to complete the restoration, RVR is proposing to construct a level crossing on the A21
Robertsbridge Bypass.
The Level Crossing Approval Process
The proposed restoration of the railway, and the construction of the associated level crossings, is
proposed to be enacted under the Transport & Works Act (TWA) and/or Level Crossings Act (LCA),
1983.
The lead Government Authority in the making of an Order to construct and operate a Level Crossing is
the Office of the Rail Regulator (ORR).
The process for seeking Powers to Construct and Operate a railway level crossing is detailed in Office of
the Rail Regulator document: ‘Level Crossings: A guide for managers, designers and operators. Railway
Safety Publication No. 7. December 2011’. That can be found at:
http://www.rail-reg.gov.uk/upload/pdf/level_crossings_guidance.pdf
As the first stage in this procedure, RVR has developed and refined designs and specifications for
the proposed crossing that have been considered at length by the overseeing organisation, the Office of
Rail Regulation (ORR).
Following completion of the initial stage of the level crossing approval process 20th January 2012 the
ORR issued a Letter of No Objection in Principle to the proposed level crossings.
As detailed in the procedural guidelines for such an application, RVR now seeks to consult with the
Local Highway Authority(s) as consultees in the level crossing approval process. This process of
consultation began in early 2012.
This further report presents technical work done in response to questions raised by the Highways Agency (HA) in particular in connection with the A21 level crossing.
Executive Summary
ii 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
As one part of that process the Highways Agency has suggested a formal ‘Application for a Departure
from Standard’ be submitted to HA by RVR. The RVR does not consider a response in such format is
appropriate to the application process outlined in the Office of the Rail Regulator document: ‘Level
Crossings: A guide for managers, designers and operators Crossing Order’. Instead RVR has sought to
cover such issues in this report and response.
1 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
1.1 Background
The Kent and East Sussex Railway (KESR) has progressively
reopened the old railway line between Tenterden and Bodiam Castle,
which became the current terminus of the line in 2000.
Rother Valley Railway (RVR) is a heritage railway charity aiming to
restore the final missing link for the KESR by recreating the link
between Robertsbridge and Bodiam, a distance of approximately 3
miles.
Completion of this link will restore the original line to Robertsbridge
Junction Station and so provide a direct public leisure transport
connection between mainline railway passenger services and the
KESR.
RVR began work on restoring the railway in 2010 and are following the
original rail alignment. To date: -
• About 1 mile of the new railway has been built from
Bodiam as far as Junction Road.
• At the western end the line has recently been rebuilt from
Robertsbridge Junction Station to the outskirts of the
village.
• RVR has now commissioned the construction of the new
Robertsbridge Junction Interchange Station.
To date RVR has committed about £1.5 million to these first phases of
the works and has available funding to complete the remaining ‘central’
section of the line once Powers have been secured.
To complete the link, RVR needs to cross the A21 Robertsbridge
Bypass and this represents the last major hurdle to the ultimate
restoration of some 13 ½ miles of heritage railway.
The proposed route follows that of the original railway and crosses the
A21 to the south of the Northbridge Street roundabout. The proposed
design will use a full barrier locally monitored and controlled level
crossing to provide a safe at grade intersection between the A21 and
the railway.
1. Introduction
2 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
1.2 Project Chronology
The following table sets out the approximate chronology and / or
timeframe of the scheme development to date: -
Milestone Timeline Key Outcomes
Rother Valley Railway
(RVR) Discussions with
Office of Rail Regulator
(ORR)
Early 2011 Initial discussions
and ORR visits to
proposed level
crossing sites
RVR letter to ORR 19th July 2011 Sets out proposed
level crossing details
and submission of
Mott MacDonald
(MM) Level Crossing
Impact study Issue
Revision ‘D’
ORR letter to RVR 24th August 2011 Response and
Report comments.
RVR email to ORR 6th November
2011
Submitted updated
MM Level Crossing
Impact study Issue
Revision ‘E’
ORR letter to RVR 20th January
2012
Summary Response
with no objection in
principle
RVR letter to Highways
Agency (HA)
23rd
May 2012 Submitted ORR
letter dated 23rd
March 2012 and MM
Level Crossing
Impact study Issue
Revision ‘E’
3 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
Meeting between Rother
Valley Railway and
Highways Agency
19th April 2012 Initial consultation
regarding process
and next steps
HA letter to RVR 4th May 2012 Set out next steps
for RVR to address
with respect to
traffic, safety and
consultation.
Meeting between RVR and
HA
7th September
2012
Discussed revised
position between HA
and RVR as part of
the consultation
agreement.
Table 1-1: Chronology of events regarding RVR and the scheme development
1.3 Report Structure
The sections of the report consider the following headings: -
Section 1 – Location and Scheme Description;
Section 2 – Scheme Options;
Section 3 – Comparison of Scheme Options;
Section 4 – Traffic Assessment;
Section 5 – Road Safety Assessment; and
Section 6 – Journey Time Assessment.
In addition, several appendices are included within this report which
provided supplementary evidence in support of the respective headline
findings of Sections 4 to 6 outlined above.
4 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
The accompanying appendices are as follow: -
Appendix Title Document
Reference
Revision
A
Non-Motorised
User (NMU)
Context
Report;
313090/ITD/ITQ/001 D
B NMU Audit
Report; 264223/ITD/ITQ/126 D
C
Traffic Impact
Study (this is
an earlier
report that we
are providing
additional
information on;
288755/ITD/ITW/001 E
D
Traffic Impact
Study –
Supplementary
Technical Note
(following HA
comments
dated 14th
September
2012);
313090/ITD/ITQ/003 D
E
Personal Injury
Accident
Analysis
Technical Note
313090/ITD/ITQ/004 D
F
Journey Time
Analysis
Technical Note
313090/ITD/ITQ/007 C
5 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
2.1 Location
The proposed level crossing is located on the A21 Robertsbridge
Bypass in East Sussex at a position approximately 135m south of the
Northbridge Street Roundabout.
Robertsbridge itself is a small village located approximately 10 miles
north of Hastings and 13 miles south east of Royal Tunbridge Wells.
The Section ID for the crossing location is 1400A21/841.
Figure 2-1: A21 Robertsbridge bypass, Northbridge Street roundabout and the proposed level crossing location.
i.
Source: Imagery ©2012 DigitalGlobe, GeoEye, Getmapping plc, Infoterra Ltd & Bluesky, Map data ©2012 Google
2. Location and Scheme Description
Proposed Level Crossing
site
Approximate alignment of
Railway Route
6 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
2.2 Scheme Description
The proposed scheme comprises the construction of an at-grade level
crossing of the A21. The crossing would comprise full carriageway
width locally monitored and controlled barriers in order to prevent
vehicle and NMU incursion onto the crossing in accordance with the
requirements of the Level Crossing Guidelines As Above. The proposal
also comprises the extension of the existing 40mph speed limit south of
the A21 roundabout junction with the C18 Northbridge Street, provision
of new signs and road markings in accordance with the requirements of
the Traffic Signs Regulations and General Directions (TSR&GD) and
the Traffic Signs Manual standards and/or the guidance document
“Level Crossings: a Guide for Managers, Designers and Operators –
Rail Publication 7 (December 2011)”, all as appropriate.
7 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
3.1 Overview
RVR has considered options for grade separation at the A21; with both
an underbridge and overbridge being investigated. It is understood that
both of these options would be preferable to a level crossing according
to ORR policy; however it was found that a level crossing represents
the most practical solution for a range of technical reasons.
In its submission to ORR a study by consultants Halcrow (Technical
Note: RVR-EW-001 15th May 2011) confirmed that the short distance
between the river bridge adjacent to Northbridge Street and the A21
would result in an unacceptably steep gradient up or down resulting in
safety issues and that an under bridge would put the railway track
under the A21 much lower than the adjacent river. In addition flooding
of the underbridge option would be inevitable and is anticipated to occur
several times during the course of a year. These events would lead to a
deposit of silt and collection of debris along the railway line which would
require removal prior to the line re-opening and cause train safety
adhesion risks. The level crossing option would have a significantly
reduced environmental impact in comparison to any other option.
Furthermore the flood assessment model work recently undertaken by
consultants Capita Symonds for RVR has considered flooding in the
area near the A21 at Northbridge Street and in particular its effect on
the adjacent bunded and protected housings area. The River Rother
immediately adjacent to the proposed Northbridge level crossing is a
‘pinch point’ in the flow of the river at times of significant flood flow. The
model used when the flood protection scheme was built some years
ago assumes that the river can overtop its banks into the field between
Northbridge Street and the A21 level crossings, so in effect increasing
the rivers flow capacity in that area. Remodelling that scheme with the
level crossings requires the reconstructed railway embankment joining
those two level crossings to have a number of flood culverts openings
under the railway line to enable that flood flow to continue to run
southwards under the railway at that location. A cutting built for an A21
underbridge would therefore require that flood flow to continue to be
able to pass across the railway in volume at times of significant flood
flow so completely filling such cutting with water, mud and detritus and
so make such a cutting impractical.
3. Scheme Options
8 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
3.2 Level Crossing
The proposed level crossing would be constructed from a monolithic
precast concrete slab with embedded rail, such as the EDILON LC-H
system or similar. This system offers minimal settlement and rapid
installation; typically requiring a short weekend closure to install.
EDILON LC-H systems have also been shown to require very little
maintenance over their operational life and would allow a seamless
connection to the adjacent road surface. The slabs can be
manufactured to provide high skid resistance values using special
concrete mixtures on the top surface. The railway embankment
required for construction of a level crossing would have an average
height of 1.66m.
9 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
4.1 Road Safety (Road Users)
It has been agreed with HA that any necessary detailed road safety
audit is premature at this stage, however, the HA has requested that
the needs of non-motorised users (NMUs) be considered. To that end,
an NMU Context report (313090/ITD-ITQ-001) and an NMU Audit report
(264223FD-ITD-ITQ-126) have been prepared.
These are shown at Appendix A and B respectively.
Potential road safety impacts include the following:
Traffic queuing back towards the Northbridge Street
roundabout north of the crossing.
Possibility of northbound traffic tailing back from Northbridge
Street roundabout and blocking the crossing.
Risk of unreliability associated with theft, vandalism or failure of
the crossing equipment.
It is considered that the provision of a level crossing at this location
would be even safer than a full barrier locally monitored signalman
controlled level crossing on the national rail network all as in Appendix
E. This is due to the following reasons:
As a tourist line, it will have fewer days of operation;
A limited proportion of journeys will take place under
dusk/night conditions;
Trains will be limited to speeds set by agreement with the
ORR but typically +/- 15mph at the crossing location; and
Few trains are timetabled to run during the weekday rush hours
when traffic density on the A21 will be at its peak.
4. Comparison of Scheme Options
10 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
4.2 Maintenance/Durability
As detailed above, the proposed level crossing construction will limit
maintenance to a negligible level.
4.3 Environmental
Rother District Council’s (RDC) Local Plan (Adopted: July 2006, Section
9.25) offers support to the extension of the KESR between Bodiam and
Robertsbridge on the basis that it does not compromise the integrity of
the floodplain or flood protection measures surrounding Robertsbridge.
RVR has commissioned consultants Capita Symonds to review the
impact of the reconstruction of the railway which work is currently
moving toward satisfactory completion.
RVR has also consulted with the High Weald area of outstanding
natural beauty (AONB) unit which has not presented any objection in
principle to the reinstatement of the line on its original alignment.
4.4 Network Availability
The construction of a level crossing would require a short weekend
closure of the A21 during the quietest part of the year.
4.5 Traffic Assessment
A traffic impact study produced by Mott MacDonald in September 2011
reported forecast impacts on the A21 as a result of the proposals.
These are amplified as a result of HA’s initial comments and are
detailed further in Section 5 of this report.
11 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
5.1 Overview
Mott MacDonald produced a Traffic Impact Study in September 2011
(Doc. Ref. 288755/ITD/ITQ/001/D) which sets out the assessment of
the proposed crossing and the forecast impacts as a result of its
operation.
The Traffic Impact Study sets out to report forecast maximum and
average northbound and southbound A21 queue lengths for the
following scenarios based on the timetabled operation of the proposed
crossing: -
Traffic flows for the ‘current year’ (2010);
Traffic flows for the ‘design year’ (five years hence): 2016; and
Traffic flows for the ‘design year’ (ten years hence) 2021.
It is recognised that significant queuing is forecast for the design year,
2021. On occasions, for example Bank Holidays, queues are forecast
to exceed 1km.
The Traffic Impact Study (Doc. Ref. 288755/ITD/ITQ/001/E, October
2011) is referenced at Appendix C.
5.2 Highways Agency comments on Traffic Impact Study
Comments on elements of this study were received by Mott
MacDonald, from the Highways Agency (via email dated 14th
September 2012).
These comments are summarised as follows: -
5.2.1.1 Flow Data
The HA’s consultants, Parsons Brinckerhoff (PB), have noted that whilst
acceptable for the purposes of this assessment: -
“it should be noted that hourly vehicular arrivals are unlikely to be
uniform particularly around the peak hours and further work may
therefore be necessary.”
5. Traffic Assessment
12 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
Furthermore: -
“The use of averages to determine weekday and weekend flows
for spring, summer and autumn will result in profiles that do not
represent peak flow conditions. A more robust and
recommended approach would be to assess the worst case
weekday and weekend profiles and also look at the upper
quartile of weekend and weekday flow data.”
Response - This has been considered and is shown in Section 5.2 of
the Technical Note referenced at Appendix D.
5.2.1.2 Traffic Growth
“TEMPRO has been used to growth the 2010 TRADS flows to
2016 and 2021 to represent five and ten year opening date
scenarios. The use of dataset 62 and NTM factors is accepted
together with the associated growth factors.”
Response - Hence, there are no actions arising in this regard.
5.2.1.3 Queuing Analysis
The HA’s consultants, PB, also note that: -
“The proposed level crossing is situated approximately 140m
south of the Northbridge Street roundabout. Therefore, assuming
a length of 5.75m per vehicle, a queue of 24 vehicles or more,
associated with the crossing in the southbound direction, would
result in queue interaction with the junction and represent an
unacceptable risk to road safety. Notwithstanding the above
recommended changes to the flow data and closure times, the
spreadsheet model indicates that queues of 24 vehicles or more
could occur during extreme flow days such as bank holidays.”
13 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
Furthermore: -
“Chapter 5 states that on extreme flow days the A21 is already
congested and therefore the introduction of the level crossing
would not have a discernable impact on traffic as it would already
be queuing. This conclusion is not supported as the level of
queuing associated with the congestion is not quantified and is
likely to vary on an annual basis. As such, the introduction of the
level crossing is likely to exacerbate the queuing conditions
which could cause queuing back to the Northbridge Street
roundabout.
There is also an additional danger that if traffic is queuing the
barriers could close on a vehicle which has not made it fully
across the level crossing due to the slow moving traffic. This
could however, be mitigated in the design if the crossing is
controlled by a signalman with CCTV coverage of the crossing in
addition to the yellow box markings.”
Response – With regard to the HA’s consultants concerns regarding
vehicles queuing and the operation of the barrier, there is no danger
to queuing traffic that the barriers could close on a vehicle. This is
due to the proposed level crossing being of the Full barrier Local
Monitored and signalman controlled type. This will not be an
‘automatic’, or unmanned / unmonitored level crossings.
Furthermore, the operational sequence for closing the level
crossing by the signalman being: -
Turn on road stop lights plus warblers.
Once the level crossing site is seen to be clear the
signalman will lower half only of barriers (diagonally
opposite and immediately facing the oncoming direction of
road traffic).
Then, when ready, and after ensuring no road traffic
remains within the level crossing envelope, the signalman
will lower the other pair of diagonally opposite barriers – so
completely isolating the road from the railway.
Then turn the railway signals to ‘clear’ for the passage of
the railway train – the maximum speed of which is set in
discussion with the overseeing body the Office of the Rail
Regulator but anticipated to be set in the region of +/-15
mph.
14 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
With respect to queuing capacity, the theoretical capacity of a link is
taken from the Highways Agency advice note TA46/97. Annex D of
TA46/97 refers to the Congestion Reference Flow (CRF). The CRF is
an estimate of the capacity of a link when it is considered to be
congested (i.e. the hourly traffic demand exceeds the maximum
sustainable hourly throughput of the link. The CRF for the maximum
sustainable hourly lane throughput is defined as: -
CAPACITY = [A – B * Pk%H]
Where, Pk%H is the percentage of ‘Heavy Vehicles’. A and B parameters are dependant on road standard; A B Single Carriageway 1380 15.0 Dual Carriageway 2100 20.0 Motorway 2300 25.0
Figure 3.2 (page 16) of the Traffic Impact Study (Doc. Ref.
288755/ITD/ITQ/001/D) indicates that the southbound flows for the
Spring / Autumn profile exceed the CRF in 2010.
Furthermore, it is considered that from a traffic operation perspective,
the interruption of vehicle flow on bank holidays at the proposed RVR
level crossing will be of much the same effect as at the various
pedestrian crossings and traffic light controlled junctions already
existing on the A21 between Tonbridge and Hastings.
5.2.1.4 Road Safety
At present there is not considered to be an accident problem at the
location of the proposed crossing. The HA’s consultants have raised
the concern that the introduction of a new level crossing and the
associated reduction in speed limit from 70mph to 40mph would inhibit
the free flow of traffic and increase the road safety risk. It is also
unclear how the speed reduction will be enforced.
It is also asserted by the HA’s consultants, PB, that: -
15 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
“the risk is further increased if the queue interacts with the
Northbridge Street roundabout which it is forecast to do during
peak flow days. Given that the above changes to the
spreadsheet model are likely to result in greater forecast levels of
queuing and the frequency of queue interaction with the
roundabout the road safety risk is likely to increase.”
Response – The speed limit at the crossing location is already 40mph.
The extension of the road speed restriction would form a part of the
level crossing powers contained within the TWA Order / Level Crossing
Order application. If the Order is made, the additional short section of
40mph road will become subject to the normal speed restriction
enforcement procedures already in place on the A21.
16 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
6.1 Background
In the HA’s correspondence (letter dated 4th May 2012), it was
requested that: -
“To demonstrate what the impact would be on road safety (an
entirely additional issue from rail safety). As discussed there is
already a collision record of Killed, seriously injured and slight
collisions that highway authorities are challenged with and the
HA seek developer mitigation to ensure that the collision record
does not worsen.”
And;
“To include an assessment of what impact the development
would have on changing behaviours of traffic diverting through
Robertsbridge. This should include consideration of the impact
on collision record at the A21 junction with George Hill.”
6.2 A21 near site of proposed crossing
With respect to the A21 itself, the data shows that there are three
Personal Injury Accidents (PIA) within a 250m search radius of the site.
Of these, only one (Sussex Police Ref. 0805073) is considered to be
relevant to the site. This involved a motor vehicle overtaking another
vehicle and was classified as slight in severity.
6.3 Comparative analysis of other sites
In order to make an informed decision on the possible impacts of a full
barrier controlled level crossing, six sites have been reviewed with
respect to their historical collision data.
The full details of the road safety (comparative analysis) are shown at
Appendix E.
The choice of these sites has been directed by RVR, who considered
that they have representative characteristics similar to those exhibited
by the proposed crossing site on the A21 at Robertsbridge.
6. Road Safety Assessment
17 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
The perceived generalised dangers associated with railway level
crossings come primarily from accidents at 'open' level crossings, half
barrier level crossings, automatically operated (unmonitored) level
crossings and user worked crossings.
The type of level crossings proposed by RVR are of the Full Barrier
type, local monitored & controlled by a railway signalman. These are
also classified as MCG, MOB & MOB-CACTV crossings in the reports
referred to below.
Two learned reports provide a useful detailed overview of railway
level crossing data:
• Railway Accident Investigation Branch (RAIB) (a UK
Government Agency). Study of 'Open' crossings – but that
contains detailed comparative performance data for ‘Full
Barrier’ crossings – as the type proposed by RVR.
Source:
http://www.raib.gov.uk/cms_resources.cfm?file=/110728_R122011_AOCLs_Class_Inv.
• Centre for Transport Studies: Andrew W Evans Imperial
College London. This paper investigates level crossing
performance over the period 1946 to 2009.
Source: http://www.cts.cv.ic.ac.uk/html/ResearchActivities/publicationDetails.asp?PublicationID=1432
It is therefore considered that full barrier level crossings are regarded
as having a good safety record as demonstrated both in this report
and the learned studies referred to above.
18 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
7.1 Overview
This section considers an assessment of the use by drivers of the route
via Robertsbridge village (C18) as an alternative to the A21.
As part of the overall assessment, journey time surveys have been
conducted along the A21 and Northbridge Street (the C18 through
Robertsbridge). That in response to a question from HA as to if the
route through Robertsbridge might provide an alternative to traffic
seeking to avoid a level crossing closure on the A21.
The surveys were undertaken on Tuesday 23rd
October for the following
periods: -
AM peak (0630 – 0830);
Inter-peak (0930 - 1130); and
PM peak (1630 – 1830).
The routes surveyed are as follows: -
A - A21(T) mainline, southbound (through the site of the
proposed level crossing).
B – C18 via Robertsbridge village, southbound (avoiding the
site of the proposed level crossing).
C - A21(T) mainline, northbound (through the site of the
proposed level crossing).
D – C18 via Robertsbridge village, northbound (avoiding the
site of the proposed level crossing).
7.2 Journey Time Survey Findings
Unsurprisingly, the journey time via the C18 Northbridge Street, through
Robertsbridge is longer than the direct route via the A21 Robertsbridge
Bypass.
The journey times along the A21 between the reference points takes
approximately 3 minutes 30 seconds, whilst journey times via the C18
Northbridge Street take approximately 5 minutes.
7. Journey Time Assessment
19 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
The standard deviation for the journey times has been calculated and
the variance from the mean has been determined. There is a high
confidence that journey times on this route fall within +/- 1 standard
deviation of the mean journey time.
It is considered unlikely that traffic would divert from the A21 at
Robertsbridge, along the C18 in order to avoid any queuing that may
occur as a result of the proposed level crossing being in operation. The
full results of the journey time surveys are shown at Appendix F.
20 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
8.1 Tourist Heritage Railway Transport
Completion of the railway line between Bodiam and Robertsbridge
Junction Station will enable the direct interchange of passengers
between KESR and the mainline railway network. Once complete this
will enable visitors to use the countries public transport system to
access the KESR, rather than at present largely by private car or coach.
With proper access to the mainline railway system at Robertsbridge
Junction the line will be able to operate as a public leisure transport
corridor serving popular attractions such as the National Trust’s busy
Bodiam Castle and the historic town of Tenterden.
This will create a heritage railway transport link that will provide tangible
public transport benefits as well as benefit the local economy as a result
of an increase in tourism. The railway will also serve to reduce traffic
movements on local rural roads by encouraging tourist to use the UK’s
public transport network to visit the KESR and the local attractions such
as Bodiam caste and Tenterden that the line serves. The level crossing
is considered to represent the only real feasible solution for crossing the
A21.
8.2 Engineering
With respect to design of the Level crossing, such works are not
covered by existing Design Manual for Roads and Bridges (DMRB) /
Manual of Contract Documents for Highway Works (MCHW). Therefore
those aspects which can be applied, such as the Stopping Sight
Distance (SSD), road markings, position of signage etc, will be done so
in accordance with the above standards and/or the guidance document
“Level Crossings: a Guide for Managers, Designers and Operators –
Rail Publication 7 (December 2011)”, all as appropriate.
8.3 Traffic Assessment
The traffic impact study indicates that a level crossing operating under
the sample timetable will cause only marginal delays to traffic on the
A21.
Queuing is forecast to occur on occasions, however, the A21 currently
experiences significant congestion, queuing and delay on Bank
Holidays. In fact analysis of traffic flow data shows that the A21
experiences congestion reference flows (CRF) which suggest that the
maximum sustainable hourly throughput of the link is exceeded.
Installation of the proposed level crossings will barely effect overall
journey times.
8. Conclusions
21 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
8.4 Road Safety
The provision of a full width barrier controlled level crossing does
introduce some potential road safety impacts. The proposal has been
the subject of a NMU Audit report (Appendices A and B) as requested
by HA. The conclusions of this are that there is little current NMU
activity along this section of the A21 (be it pedestrian, cyclists or
equestrian activity).
22 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
Appendix A. NMU Context Report _________________________________________ Error! Bookmark not defined. Appendix B. NMU Audit Report __________________________________________________________________ 24 Appendix C. Traffic Impact Study ________________________________________________________________ 25 Appendix D. Traffic Impact Technical Note _________________________________________________________ 26 Appendix E. Personal Injury Accident Report _______________________________________________________ 27 Appendix F. Journey Time Assessment ___________________________________________________________ 28
Appendices
23 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
Appendix A. Non-Motorised User (NMU) Audit - Context Report
24 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
Appendix B. Non-Motorised User (NMU) Audit Report
25 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
Appendix C. Traffic Impact Study
26 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
Appendix D. Traffic Impact Study – Supplementary Technical Note
27 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
Appendix E. Personal Injury Accident Analysis Technical Note
28 313090/ITD/ITQ/006/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
Appendix F. Journey Time Analysis Technical Note
Rother Valley Railway A21 Robertsbridge
Non-Motorised User (NMU) Audit - Context Report
January 2013
Rother Valley Railway Limited
313090 ITD ITQ 001 D
25 January 2013
Rother Valley Railway A21 Robertsbridge
Non-Motorised User (NMU) Audit - Context Report
January 2013
Rother Valley Railway Limited
Mott MacDonald, Stoneham Place, Stoneham Lane, Southampton, SO50 9NW, United Kingdom
t +44 (0)23 8062 8800 f +44 (0)23 8062 8801, W www.mottmac.com
Robertsbridge Junction (RVR) Station, Station Road, Robertsbridge, Sussex, TN32 5DG
Rother Valley Railway A21 Robertsbridge
Mott MacDonald, Stoneham Place, Stoneham Lane, Southampton, SO50 9NW, United Kingdom
t +44 (0)23 8062 8800 f +44 (0)23 8062 8801, W www.mottmac.com
Revision Date Originator Checker Approver Description
A 15
th November 2012
B Pledge M Lewis R Murdock First Issue
B 13
th December 2012
B Pledge M Lewis R Murdock Second Issue
C 17th January 2013 M Lewis R Murdock R Murdock Third Issue
D 25th January 2013 M Lewis R Murdock R Murdock Fourth Issue
Issue and revision record
This document is issued for the party which commissioned it
and for specific purposes connected with the above-captioned
project only. It should not be relied upon by any other party or
used for any other purpose.
We accept no responsibility for the consequences of this
document being relied upon by any other party, or being used
for any other purpose, or containing any error or omission
which is due to an error or omission in data supplied to us by
other parties
This document contains confidential information and proprietary
intellectual property. It should not be shown to other parties
without consent from us and from the party which
commissioned it.
313090/ITD/ITQ/001/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
Chapter Title Page
Executive Summary i
1. Introduction 1
1.1 Background _______________________________________________________________________ 1
2. Scheme Description 2
2.1 Overview _________________________________________________________________________ 2
3. Policy Context 4
3.1 Planning and the Strategic Road Network ________________________________________________ 4
4. NMU Activity 6
4.1 NMU Flows ________________________________________________________________________ 6 4.1.1 Pedestrians and pedestrian routes ______________________________________________________ 6 4.1.2 Cyclists and cycle routes _____________________________________________________________ 7 4.1.3 Equestrians and equestrian routes ______________________________________________________ 8 4.1.4 Flows and speed of motorised traffic ____________________________________________________ 8 4.1.5 Accident Data ______________________________________________________________________ 9 4.2 Potential and Actual Impacts _________________________________________________________ 10 4.3 Existing Assessment _______________________________________________________________ 10 4.4 NMU Objectives ___________________________________________________________________ 10 4.5 NMU Audit _______________________________________________________________________ 11
Appendices 12
Appendix A. Results of NMU Survey (Sunday 13th January 2013) ________________ Error! Bookmark not defined.
Content
i 313090/ITD/ITQ/001/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
The Kent and East Sussex Railway (KESR) operates between Tenterden in Kent and Bodiam Castle in
East Sussex. The line is currently difficult to access by public transport.
The Rother Valley Railway (RVR) Heritage Trust is currently reconstructing the railway line between the
line’s current terminus at Bodiam and Robertsbridge Junction Station to enable the direct interchange of
passengers between KESR and the mainline railway network. Once complete that will enable visitors to
use the country’s public transport system to access the KESR and to use the line as a leisure transport
corridor serving popular attractions such as the National Trust’s Bodiam Castle and the historic town of
Tenterden.
This report sets out the Non-Motorised User (NMU) Context Report requirements as defined in the
Highways Agency standard HD42/05 ‘Non-Motorised User Audits’. The NMU Context Report provides a
summary of all available information relevant to existing and potential patterns of use by NMUs within the
design life of the scheme.
This NMU Context Report sets out the opportunities and objectives to improve conditions for NMUs in
relation to the proposed scheme.
Executive Summary
1 313090/ITD/ITQ/001/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
1.1 Background
This NMU Context Report has been prepared at the outset of the
preliminary design and relates to footways, footpaths, public rights of
way (PROW), permissive paths, cycleways and other local routes
potentially impacted upon by the proposed A21 Rother Valley Railway
level crossing proposal. It has been prepared following the guidance
given in the Highways Agency’s standard HD42/05 – Non-Motorised
User Audits.
The report takes into account work to date with respect to NMUs,
primarily in relation to the existing route and also to adjacent
communities and suggests mitigation measures (where appropriate).
It is understood that as part of the scheme development, an
Environmental Statement has not yet been prepared. It is envisaged
that this statement will be prepared at a later date as part of the
Transport & Works Act / Level Crossing Order application process.
1. Introduction
2 313090/ITD/ITQ/001/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
2.1 Overview
The proposal comprises the construction of a new full-barrier controlled
railway level crossing across the A21(T) Robertsbridge Bypass, some
135m south of the existing roundabout with the C18 (Northbridge
Street).
View of A21 looking south towards proposed level crossing site
Source: Mott MacDonald
The A21 at this location is a two-lane, two-way all purpose trunk road
(APTR). The carriageway cross-section at this location is 7.3m wide
with 1.0m wide hardstrips. For the purposes of this assessment, it is
considered as being of ‘S2’ standard.
The location of the proposed level crossing site is shown overleaf in
Figure 2-1.
2. Scheme Description
3 313090/ITD/ITQ/001/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
Figure 2-1 Proposed level crossing location (Robertsbridge)
Source: Background Mapping - Ordnance Survey data © Crown copyright and database
copyright 2010
Proposed
Crossing Site
4 313090/ITD/ITQ/001/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
3.1 Planning and the Strategic Road Network
The policy context in which this process is being developed is twofold,
and is outlined as follows: -
The Level Crossing Approval Process
The proposed restoration of the railway, and the construction of the
associated level crossings, is proposed to be enacted under the
Transport & Works Act (TWA) and/or Level Crossings Act (LCA), 1983.
The lead Government Authority in the making of an Order to construct
and operate a Level Crossing is the Office of the Rail Regulator (ORR).
The process for seeking Powers to Construct and Operate a railway
level crossing is detailed in Office of the Rail Regulator document:
‘Level Crossings: A guide for managers, designers and operators.
Railway Safety Publication No. 7. December 2011’. That can be found
at:
http://www.rail-reg.gov.uk/upload/pdf/level_crossings_guidance.pdf
RVR has developed and refined designs and specifications for the
proposed crossing that have been considered at length by the
overseeing organisation, the ORR.
Following completion of the initial stage of the level crossing approval
process 20th January 2012 the ORR issued a Letter of No Objection in
Principle to the proposed level crossings.
As detailed in the procedural guidelines for such an application, RVR
now seeks to consult with the Local Highway Authority(s) as consultees
in the level crossing approval process. This process of consultation
began in early 2012.
Department for Transport / Highways Agency Development Protocols
The Department for Transport (DfT) Circular 02/2007 March 2007 sets
out the parameters for development on the Highways Agency (HA)
network.
3. Policy Context
5 313090/ITD/ITQ/001/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
This states that: -
42. The Agency will adopt a graduated and less restrictive
approach to accesses on the remainder of the strategic road
network, but there will still be a presumption in favour of using
existing accesses and junctions. Any additional junctions or
increased junction capacity should be identified in the LDD
and/or RTS and will be considered within the context of the
Agency’s forward programme of works.
43. Regardless of the status of the road, developers will be
required to ensure that their proposals comply in all respects with
design standards and other requirements. Where there would be
physical changes to the network, schemes must be submitted to
road safety and non-motorised user audit procedures. The
Design Manual for Roads and Bridges sets out details of the
Secretary of State’s requirements for access design and audit. If
necessary, further advice is available from the Agency. The
Secretary of State may direct that planning permission not be
granted for any planning application which fails to meet these
requirements or which, for any other reason, raises significant
safety concerns.
44. The Agency should be consulted on any development
proposals where a new access onto a local road is required,
which in turn feeds a strategic road and has the potential for a
material effect.
45. LPAs will need to consult the Agency over any development
which may affect the users of a strategic road, even though it
may not lead to an increase in traffic. Examples of such
development would include earth mounds, wind farms and golf
courses. The Agency should also be consulted on applications
for signs or advertisements visible from the strategic road
network.”
6 313090/ITD/ITQ/001/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
4.1 NMU Flows
Mott MacDonald has been unable to directly source data from any
public authority relating to pedestrian, cycle and equestrian activity
along the A21 at Robertsbridge (between the roundabout with the C18
to the north and the roundabout with the A2100 to the south).
However, as part of the scheme development proposals, RVR has
undertaken a number of surveys to conduct counts of NMU movement
along the A21 at the location of the proposed level crossing in order to
quantify the level of activity that does occur.
Initial surveys conducted by RVR on Wednesday 14th November 2012
for the 12-hour period 0700-1900 showed that no pedestrians, cyclists
or horses were recorded as passing the site.
Further surveys conducted at the site of the proposed A21 level
crossing on Sunday 13th January 2013 for the 12-hour period 0700-
1900 again showed that no pedestrians, cyclists or horses were
recorded as passing the site. The results of both surveys are provided
at Appendix A.
Furthermore, Mott MacDonald considers that there is likely to be no, or
little, NMU activity along this section of the A21. This is based on the
premise that the A21 at this location acts as a bypass to the east of
Robertsbridge and its primary function is the efficient and expeditious
movement of traffic, north–south along the A21 corridor.
Nevertheless, the use of the A21 at this location does permit the
passage of NMU traffic and so this report considers the pedestrian,
cycle and equestrian usage even though those flows are clearly
extremely low.
4.1.1 Pedestrians and pedestrian routes
There is no pedestrian provision along the A21(T) Robertsbridge
Bypass.
Signed pedestrian routes run perpendicular to the A21 near the location
of the proposed level crossing. However, these are situated in adjacent
fields and grazing land and do not necessitate the crossing of the A21.
There is also an overbridge for east-west movements located
approximately 200 metres south of the location of the proposed level
crossing, near Redlands Lane.
4. NMU Activity
7 313090/ITD/ITQ/001/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
The location of adjoining footpaths, bridleways and cycleways are
shown in Figure 4.1 overleaf.
4.1.2 Cyclists and cycle routes
According to the SUSTRANS website (www.sustrans.org) the A21 does
not form part of the National Cycle Network at this location.
There are 1.0m wide hardstrips along which cyclists can potentially
travel and at the time of a site visit in October 2012 are considered to
be relatively free of detritus.
Figure 4-1 shows the location of current footpaths, cycleways and
bridleways in the Robertsbridge area.
Figure 4-1:Location of footpaths, bridleways, cycleways etc
Source: East Sussex County Council website (www.eastsussex.gov.uk)
Key:-
Footpaths
Bridleways
8 313090/ITD/ITQ/001/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
Licensed Cycleway
It can be seen, that the A21 does not form part of any other function for
cyclists, pedestrians or equestrians.
There is one footpath that passes beneath the A21 close to the site of
the proposed level crossing.
4.1.3 Equestrians and equestrian routes
Figure 4-1 above shows the location of existing bridleways. None of
these are affected by the scheme proposal.
4.1.4 Flows and speed of motorised traffic
The Highways Agency publishes traffic data collected from Automatic
Traffic Counters (ATCs) at various locations on the motorway and trunk
road network on their TRADS2 website (http://trads.hatris.co.uk/). Data
for the whole of 2011 is available and hourly traffic flows have been
downloaded for use in this study from two sites on the A21:
Site No. T/04/215 – southbound on the A21 Robertsbridge
Bypass southern section (Grid reference E574125, N124015)
Site No. T/04216 – northbound on the A21 Robertsbridge
Bypass southern section (Grid reference E574128, N123929)
Traffic data has been summarised as annual average daily traffic
(AADT) for the purposes of this NMU Context Report.
Figure 4-2 2011 AADT on A21 near Robertsbridge
Table Heading Left Southbound Northbound Total
AM Peak 541 565
PM Peak 711 551
AADT Total 7,472 7,427 14,899
Source: TRADS2 website: Online Reporting (Period report 01/01/2011 to 31/12/2011)
9 313090/ITD/ITQ/001/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
Figure 4-3 2011 AADT Flow Profile on A21(T) near Robertsbridge
0
100
200
300
400
500
600
700
800
900
1000
01:0
0
02:0
0
03:0
0
04:0
0
05:0
0
06:0
0
07:0
0
08:0
0
09:0
0
10:0
0
11:0
0
12:0
0
13:0
0
14:0
0
15:0
0
16:0
0
17:0
0
18:0
0
19:0
0
20:0
0
21:0
0
22:0
0
23:0
0
00:0
0
Hour
Tra
ffic
vo
lum
e (
veh
icle
s)
A21 Southbound (ATC site 215)
A21 Northbound (ATC site 216)
Source: TRADS2 website: Online Reporting (Period report 01/01/2011 to 31/12/2011)
4.1.5 Accident Data
Personal Injury Accident (PIA) data has been obtained from Sussex
Police. Data for the most recent five-year period has been requested
and data supplied covered the period 1st November 2005 to the 30
th
November 2010.
10 313090/ITD/ITQ/001/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
The purpose of obtaining historic accident data is to review the current
road safety record in the vicinity of each of the proposed level crossing
sites. The road safety record will inform the assessment of the physical
extent of any necessary changes to speed limits required on the
approaches to the crossings. An assessment has also been made of
the potential impact of the introduction on the road safety record, either
positive or negative.
According to the records of Sussex Police, there has been only one PIA
recorded near the vicinity of the site, which involved a vehicle travelling
southbound overtaking another vehicle near Redlands Lane.
For full details on the road safety record of the A21 at this location, refer
to MM Report on A21 PIA Analysis (Doc. Ref. 313090-ITD-ITQ-004).
4.2 Potential and Actual Impacts
It is considered that the construction of a proposed full barrier-controlled
level crossing in itself would not have an adverse affect on the
movements of NMUs in this area.
Furthermore, it is considered that there are no immediately identifiable
conflict points that would impact NMUs.
4.3 Existing Assessment
Mott MacDonald understands that there has been no previous
assessment of the effects on the NMU routes as part of the proposed
works.
4.4 NMU Objectives
Based on the above, the objectives of the NMU assessment are to:
where applicable;
Maintain safety for vulnerable NMU users on the A21 and
where it intersects with the existing highway network; and
the design of the proposal is cogniscent of NMU
requirements.
11 313090/ITD/ITQ/001/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
4.5 NMU Audit
The NMU Audit is a separate document prepared by Mott MacDonald
which examines the potential impacts on non-motorised users as a
result of the proposals.
Please refer to the Mott MacDonald report ‘A21 Non-Motorised User
Audit Report – Rother Valley Railway’ (Doc. Ref. 264223FD-ITD-ITQ-
126-C).
12 313090/ITD/ITQ/001/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
Appendix A. Results of NMU Surveys (Wednesday 12th November 2012 and Sunday 13th January 2013) _______ 13
Appendices
13 313090/ITD/ITQ/001/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
Appendix A. Results of NMU Surveys (Wednesday 12th November 2012 and Sunday 13th January 2013)
Non-Motorised User Audit
A21 Rother Valley Railway Non-Motorised User (NMU) Audit Report
January 2013
Rother Valley Railway Limited
€
264223FD ITD ITQ 126 D
25 January 2013
Non-Motorised User Audit
A21 Rother Valley Railway Non-Motorised User (NMU) Audit Report
January 2013
Rother Valley Railway Limited
Mott MacDonald, Stoneham Place, Stoneham Lane, Southampton, SO50 9NW, United Kingdom
t +44 (0)23 8062 8800 f +44 (0)23 8062 8801, W www.mottmac.com
Robertsbridge Junction (RVR) Station, Station Road, Robertsbridge, Sussex TN32 5DG
Non-Motorised User Audit
Mott MacDonald, Stoneham Place, Stoneham Lane, Southampton, SO50 9NW, United Kingdom
t +44 (0)23 8062 8800 f +44 (0)23 8062 8801, W www.mottmac.com
Revision Date Originator Checker Approver Description
A 15/11/12 M D Lewis B A Pledge R E Murdock First Issue
B 12/12/12 M D Lewis B A Pledge R E Murdock Second Issue
C 17/01/13 M D Lewis R E Murdock R E Murdock Third Issue
D 25/01/13 M D Lewis R E Murdock R E Murdock Fourth Issue
Issue and revision record
This document is issued for the party which commissioned it
and for specific purposes connected with the above-captioned
project only. It should not be relied upon by any other party or
used for any other purpose.
We accept no responsibility for the consequences of this
document being relied upon by any other party, or being used
for any other purpose, or containing any error or omission
which is due to an error or omission in data supplied to us by
other parties
This document contains confidential information and proprietary
intellectual property. It should not be shown to other parties
without consent from us and from the party which
commissioned it.
264223FD/ITD/ITQ/126/D 25 January 2013
Non-Motorised User Audit
Chapter Title Page
1. Introduction 1
2. Background 2
3. Items Raised in this Audit 4
4. Audit Team Statement 6
Appendices 7
Appendix A. List of Documents / Drawings Reviewed _________________________________________________ 8
Content
1 264223FD/ITD/ITQ/126/D 25 January 2013
Non-Motorised User Audit
This report describes a Non-Motorised User (NMU) audit carried out for a proposed full barriered
locally controlled and monitored, railway level crossing of the A21 near Robertsbridge, East
Sussex. The proposals comprise the construction of a new at-grade embedded rail on a pre-cast
concrete slab, lifting gated barriers which extend the full width of the carriageway and associated
road markings and signs.
The audit was carried out for the Design Team in October 2012 in
accordance with Highways Agency standard, HD42/05 ‘Non Motorised
User Audits’.
The report has been prepared as a stand-alone Preliminary Design
Stage NMU audit. The audit team has prepared the ‘Rother Valley
Railway Non-Motorised User Audit Context report (dated November
2012), prepared by Mott MacDonald’s Integrated Transport Division
(Southampton).
The Audit Team comprised:
M Lewis (NMU Audit Leader) BEng, C.Eng, MICE
B Pledge(NMU Audit Team Member) AMCIHT, AMIHE
The audit comprised of: -
An examination of the scheme preliminary design drawings
A site visit on Tuesday 23rd
October 2012; and
A review of the Context Report, dated November 2012.
1. Introduction
2 264223FD/ITD/ITQ/126/D 25 January 2013
Non-Motorised User Audit
The following reports and data were reviewed during the Audit process:-
2.1 Context Report
The Context Report identifies three main objectives for the A21
proposed level crossing. These, and the design features that have
been incorporated to satisfy them, have been included in the
Preliminary Design as described below.
Table 2-1: Summary of Design Objectives and Design Feature
Objective Design Feature
Ensure continuity of existing NMU routes where applicable
The alignment of the proposed railway corridor runs perpendicular to the A21. this route is used as a footpath link. East-west pedestrian route, grade-separated from the A21 to be secured.
Maintain safety for vulnerable NMU users on the A21and where it intersects with the existing highway network
No (or little NMU) activity expected – and largely unaffected by the proposed A21 crossing.
Ensure a design of NMU measures compliant with user requirements.
The design has been undertaken with the needs of NMU taken into account.
2.2 Road Safety Audit
At the time of writing, it is understood that no road safety audits have
been prepared in association with the proposed scheme. It is
envisaged that road safety audit(s) will be carried out at a later date as
part of the Transport & Works Act / Level Crossing Order application
process.
2.3 Summary of Pedestrian Movements
Mott MacDonald has been unable to directly source data from any
public authority relating to pedestrian, cycle and equestrian activity
along the A21 at Robertsbridge (between the roundabout with the C18
to the north and the roundabout with the A2100 to the south).
2. Background
3 264223FD/ITD/ITQ/126/D 25 January 2013
Non-Motorised User Audit
However, recent surveys of NMU movements at the site of the
proposed A21 level crossing were undertaken on Sunday 13th
November 2013 for the 12-hour period 0700-1200. These show that no
pedestrians, cyclists or horses were recorded as passing the site.
4 264223FD/ITD/ITQ/126/D 25 January 2013
Non-Motorised User Audit
3.1 Issue 1
Location: Existing pedestrian footpath
The alignment of the proposed extension of the railway between
Bodiam (to the east) and Robertsbridge (to the west) bisects the A21 at
a distance approximately 140 metres south of the A21 roundabout
junction with the C18.
This railway route, crosses adjoining fields and grazing meadows,
which are signposted as pedestrian footpaths / rights of way. As the
scheme develops, it is important that the pedestrian footpath routes are
maintained.
This may necessitate the fencing of the RVR railway line to prevent
unauthorised intrusion along the corridor.
Figure: 3-1: View looking south along A21 and view of adjoining grazing
meadows with RoW.
Source: Mott MacDonald
Action Taken
The existing pedestrian footpath routes will be retained and not
interfered with resultant from the new railway and the A21 level
crossing.
The RVR railway line will be fenced to normal railway standards to
prevent unauthorised intrusion along the corridor.
3. Items Raised in this Audit
5 264223FD/ITD/ITQ/126/D 25 January 2013
Non-Motorised User Audit
3.2 Issue 2
Location: at site of proposed at-grade crossing
Drawings prepared by Rother Valley Railway (Drwg. No. A21-LC-01)
show the proposed layout for the level crossing.
These feature a full (carriageway) width barrier to prevent vehicular
traffic and NMUs incurring into the level crossing.
Cyclist activity on the A21 is considered to be low.
Action Taken
Cyclists who do travel along the A21 will be held at the stop line with
other traffic when the level crossing barriers are lowered, closing the
road and preventing access to all, including NMUs. The barriers would
be incorporated into the railway corridor fence line. No supplementary
NMU access across the railway would be provided at the level crossing.
6 264223FD/ITD/ITQ/126/D 25 January 2013
Non-Motorised User Audit
I certify that this audit has been carried out in accordance with HD 42/05.
NMU Audit Leader
M D Lewis BEng (Hons), CEng, MICE
Signed:
Date: 25th January 2013
Senior Road Safety Engineer
Mott MacDonald
Stoneham Place
Stoneham Lane
Southampton
SO50 9NW
NMU Audit Team Member
B A Pledge, AMCIHT, AMIHE
Signed:
Date: 25th January 2013
Senior Road Safety Engineer
Mott MacDonald
Stoneham Place
Stoneham Lane
Southampton
SO50 9NW
4. Audit Team Statement
7 264223FD/ITD/ITQ/126/D 25 January 2013
Non-Motorised User Audit
Appendix A. List of Documents / Drawings Reviewed __________________________________________________ 8
Appendices
8 264223FD/ITD/ITQ/126/D 25 January 2013
Non-Motorised User Audit
A.1. Documents / Drawings
Drawings / Documents reviewed by the Audit Team
Document Number. Rev Title
288755/ITD/ITW/001 D Rother Valley Railway (Proposed Level Crossings) Traffic Impact Study
313090/ITD/ITQ/001 D A21 Rother Valley Railway Non-Motorised User (NMU) Audit – Context report
Source: Mott MacDonald
Appendix A. List of Documents / Drawings Reviewed
Rother Valley RailwayProposed Level Crossings
Traffic Impact Study
October 2011
Rother Valley Railway Limited
Appendix C
Traffic Impact Study Revision E dated October 2011
Please see copy of this report previously submitted.
Rother Valley Railway A21 Robertsbridge
Traffic Impact Study - Supplementary Technical Note
January 2012
Rother Valley Railway Limited
313090 ITD ITQ 003 D
PiMS
17 January 2013
Rother Valley Railway A21 Robertsbridge
Traffic Impact Study - Supplementary Technical Note
January 2012
Rother Valley Railway Limited
Mott MacDonald, Stoneham Place, Stoneham Lane, Southampton, SO50 9NW, United Kingdom
t +44 (0)23 8062 8800 f +44 (0)23 8062 8801, www.mottmac.com
Robertsbridge Junction (RVR) Station, Station Road, Robertsbridge, Sussex TN32 5DG
313090/ITD/ITQ/003/D 17 January 2013 PiMS
Rother Valley Railway A21 Robertsbridge
Revision Date Originator Checker Approver Description Standard
A 19 October 2012 SLA MDL MDL First Issue
B 15 November 2012 SLA MDL MDL Second Issue
C 12 December 2012 SLA MDL MDL Third Issue
D 17 January 2013 SLA MDL REM Fourth Issue
Issue and revision record
This document is issued for the party which commissioned it
and for specific purposes connected with the above-captioned
project only. It should not be relied upon by any other party or
used for any other purpose.
We accept no responsibility for the consequences of this
document being relied upon by any other party, or being used
for any other purpose, or containing any error or omission which
is due to an error or omission in data supplied to us by other
parties.
This document contains confidential information and proprietary
intellectual property. It should not be shown to other parties
without consent from us and from the party which
commissioned it.
313090/ITD/ITQ/003/D 17 January 2013 PiMS
Rother Valley Railway A21 Robertsbridge
Chapter Title Page
1. Introduction 1
1.1 Introduction ________________________________________________________________________ 1 1.2 Review of methodology _______________________________________________________________ 2
2. Comparison of 2009 and 2011 data 3
2.1 Introduction ________________________________________________________________________ 3 2.2 T/04/215 – southbound _______________________________________________________________ 3 2.3 T/04/216 – northbound _______________________________________________________________ 4
3. Sensitivity test: weekday and weekend – 2010 6
3.1 Introduction ________________________________________________________________________ 6 3.2 T/04/216 – southbound _______________________________________________________________ 6 3.3 T/04/216 – northbound _______________________________________________________________ 7 3.4 T/04/2016 – northbound (non bank holiday weekday) _______________________________________ 7
4. Assessment of upper quartile 2010 9
4.1 Introduction ________________________________________________________________________ 9
5. Revised queue model 10
5.1 Introduction _______________________________________________________________________ 10 5.2 Traffic profile ______________________________________________________________________ 10 5.3 Closure period and assessment year ___________________________________________________ 10 5.4 Results __________________________________________________________________________ 10
6. Summary 13
6.1 General __________________________________________________________________________ 13 6.2 Queuing _________________________________________________________________________ 13
Appendices 14
Appendix A. Correspondence ___________________________________________________________________ 15
Content
313090/ITD/ITQ/003/D 17 January 2013 PiMS
1
Rother Valley Railway A21 Robertsbridge
1.1 Introduction
In October 2011, Mott MacDonald produced a Traffic Impact Study (Document Reference:
288755/ITD/ITW/001/E) on the behalf of Rother Valley Railway Limited. As set out in the 2011 report, the
Rother Valley Railway Heritage Trust is proposing to reconstruct part of the historical railway line, between
Tenterden in Kent and Bodiam in East Sussex, with three proposed level crossings along the route.
Part of this previous work looked at traffic flows on the A21, assessing the likely traffic impact from the
proposed level crossing on this trunk road.
As described in Section 2.2.1 of the Mott MacDonald report: -
“The Highways Agency publishes traffic data collected from ATCs at various locations on the trunk
road and motorway network on their TRADS2 website (http://trads.hatris.co.uk/). Data for the whole
of 2010 is available and hourly traffic flows have been downloaded for use in this study from two
sites on the A21:”
These being: -
Site no T/04/215 – southbound on the A21 Robertsbridge Bypass southern section (Grid reference
E574125, N124015); and
Site no T/04216 – northbound on the A21 Robertsbridge Bypass southern section (Grid reference
574128, N123929).
The initial work assessed ‘typical days’ in 2010 for:
Spring/Autumn – Average weekday (Monday to Friday);
Spring/Autumn – Average Saturday;
Spring/Autumn – Average Sunday;
Summer – Average weekday (Monday to Friday);
Summer – Average Saturday; and
Summer – Average Sunday.
The initial work also looked at a ‘non typical’ day in 2010 for:
May Day Bank Holiday Monday; and
August Bank Holiday Monday.
Further to the interrogation of the TRADS database, a spreadsheet model was built to forecast the
maximum queuing resulting from barrier closures at the level crossings. Inputs to the model included:
Times of closure of the barrier based on the draft Rother Valley Railway (RVR) timetable;
Duration of each closure – assumed to be 51 seconds based on the information provided by ORR/HMIR
(refer to Appendix B of the October 2011 report);
Hourly flows for 2010, in vehicles per minute, at times of barrier closure for each of the average day
types and Bank Holidays referred to above for the spring/autumn and summer periods;
1. Introduction
313090/ITD/ITQ/003/D 17 January 2013 PiMS
2
Rother Valley Railway A21 Robertsbridge
An assumed rate of flow over the crossing after the barrier has been raised. This was assumed to be
one vehicle every 2 seconds or 30 vehicles per minute, based on previous experience; and
Traffic growth rates derived from TEMPRO for 2010 to 2016 and 2010 to 2021.
The model outputs the maximum and average queue lengths in vehicles at the time when the barrier opens
to traffic.
1.2 Review of methodology
The Highways Agency (HA) reviewed the methodology adopted, as outlined in Section 1.1, appraising the
suitability of this approach. In a letter dated 4th May 2012, the HA requested that the assessments should
also consider 2009 and 2011 traffic data.
In addition to examining the 2009 and 2011 data, Parsons Brinckerhoff (PB), acting as consultants to the
HA, were asked to review the Traffic Impact Study, providing comments on the methodology. An email
from the HA to Mott MacDonald dated 14th September set out PB’s comments, as per Appendix A of this
Supplementary Technical Note. In broad terms, PB’s comments comprised the following:
Assess the worst case weekday and weekend profiles for 2010;
Examine at the upper quartile of weekday and weekend flow data for 2010; and
Apply 112 second closure time to weekday and weekend flows for 2010.
Also of relevance is the distance between the site of the proposed crossing and the proximity of the
Northbridge Street roundabout to the north, which is approximately 140m and also the view “that barrier
closures of 51 and 112 seconds would have no discernible effect on overall journey times in most cases as
drivers would be in a queue anyway” (Section 5.4.2, Rother Valley Railway Proposed Level Crossing
Traffic Impact Assessment, 2011).
These elements will be looked at in turn in the following sections of this report.
313090/ITD/ITQ/003/D 17 January 2013 PiMS
3
Rother Valley Railway A21 Robertsbridge
2.1 Introduction
TRADS data has been downloaded for the following sites:
T/04/215 – southbound on the A21 Robertsbridge Bypass southern section (Grid reference E574125,
N124015); and
T/04/216 – northbound on the A21 Robertsbridge Bypass southern section (Grid reference E574128,
N123929).
At the request of the HA, 2009 and 2011 data has been compared with that of 2010. Monthly data, by
hour, has been compared to assess the variability of traffic flow. It should be noted that Bank Holidays
have been excluded from this exercise, as they can skew results, particularly as there were more Bank
Holidays in 2011.
Traffic data, by month, for each of the three years has been downloaded from TRADS. The average hourly
flow across 24 hours (per month) have been calculated, and it is this that has been compared. Weekdays
and weekends have been compared separately, and all months have been compared.
Sections 2.2 and 2.3 summarise the findings by direction of travel.
2.2 T/04/215 – southbound
Comparing weekdays in 2009 with weekdays in 2010, across the year, there was a 3% decrease in traffic
flow, although traffic flows in the months of February, March, April, June July and October 2010 exhibited
higher flows than in the comparative 2009 months.
Comparing weekends in 2009 with weekends in 2010, traffic flows were 5% higher in 2009.
Comparing weekdays in 2010 with weekdays in 2011, there was a 2% increase.
Comparing weekends in 2010 with weekends in 2011, traffic was 4% higher in 2011.
2. Comparison of 2009 and 2011 data
313090/ITD/ITQ/003/D 17 January 2013 PiMS
4
Rother Valley Railway A21 Robertsbridge
Table 2.1: Comparison of 2009 and 2010 flows - SB
% difference weekdays % difference weekends
Jan -12% -12%
Feb 1% -2%
Mar 1% -2%
Apr 2% 1%
May -1% -4%
Jun 2% -2%
Jul 0% 5%
Aug -3% -8%
Sep -10% -13%
Oct 1% 2%
Nov -2% 0%
Dec -17% -21%
Average -3% -5%
The red highlight denotes months where 2010 had lower flows than 2009 or 2011. Blue denotes months where 2010 had higher flows
than 2009 or 2011. Green denotes no change.
Table 2.2: Comparison of 2010 and 2011 flows - SB
% difference weekdays % difference weekends
Jan 11% 12%
Feb 7% 3%
Mar -2% 0%
Apr -1% 11%
May -5% -6%
Jun -3% -2%
Jul 0% -4%
Aug -1% -1%
Sep 0% -3%
Oct -2% 2%
Nov -1% 3%
Dec 24% 29%
Average 2% 4%
The red highlight denotes months where 2010 had lower flows than 2009 or 2011. Blue denotes months where 2010 had higher flows
than 2009 or 2011. Green denotes no change.
2.3 T/04/216 – northbound
Comparing weekdays in 2009 with weekdays in 2010, across the year, there was a 5% decrease in traffic
flow. The TRADS data shows that 2009 had slightly higher values than 2010.
Comparing weekends in 2009 with weekends in 2010, traffic flows in 2009 were 7% higher.
Comparing weekdays in 2010 with weekdays in 2011, there was a 1% variation in traffic flow, with 2010
having slightly lower flows.
313090/ITD/ITQ/003/D 17 January 2013 PiMS
5
Rother Valley Railway A21 Robertsbridge
Comparing weekends in 2010 with weekends in 2011, there was a 2% increase in traffic flow, with 2011
having slightly higher values.
Table 2.3: Percentage difference between 2009 and 2010 flows - NB
% difference weekdays % difference weekends
Jan -11% -16%
Feb -2% -5%
Mar 0% -6%
Apr -2% -2%
May -4% -11%
Jun 1% -3%
Jul 1% 2%
Aug -6% -6%
Sep -11% -15%
Oct -1% 1%
Nov -3% -1%
Dec -17% -23%
Average -5% -7%
The red highlight denotes months where 2010 had lower flows than 2009 or 2011. Blue denotes months where 2010 had higher flows
than 2009 or 2011. Green denotes no change.
Table 2.4: Percentage difference between 2011 and 2010 flows - NB
% difference weekdays % difference weekends
Jan 11% 12%
Feb 7% -1%
Mar -4% -1%
Apr -2% 3%
May -5% -3%
Jun -4% -5%
Jul -4% -7%
Aug -2% -4%
Sep -2% -2%
Oct -1% 2%
Nov 0% 2%
Dec 23% 28%
Average 1% 2%
The red highlight denotes months where 2010 had lower flows than 2009 or 2011. Blue denotes months where 2010 had higher flows
than 2009 or 2011. Green denotes no change.
313090/ITD/ITQ/003/D 17 January 2013 PiMS
6
Rother Valley Railway A21 Robertsbridge
3.1 Introduction
At the request of PB, the TRADS database has been interrogated to determine the busiest weekday and
weekend for 2010.
A ‘yearly tabular report’ for each of the two sites has been sourced from TRADS. This produces
information by month for each day (24 hours). Weekdays have been isolated from weekend days. Flows
have been ranked by busiest weekday and busiest weekend day, so the highest 24 hour flow could be
identified.
In order to assess a worst case scenario, the highest flows for the northbound and highest flows for the
southbound were identified. The days may not be the same, but in terms of completeness, it was
considered appropriate to determine the worst day for each TRADS site.
The original assessment carried out in October 2011 looked at seasonality and ‘typical’ and ‘non typical’
days, i.e. Bank Holidays were classed as ‘non typical’. PB has requested that the busiest day should be
identified, and for the purpose of this assessment, Bank Holidays have been included.
3.2 T/04/216 – southbound
The busiest weekday for southbound traffic has been determined as Friday 4th June. The busiest
weekend day has been determined as Saturday 28th August. A profile for each day is shown in Figures
3.1 and 3.2.
Figure 3.1: Friday 4th June 2010 – 24 hour profile
Figure 3.2: Saturday 28th
August 2010 – 24 hour profile
0
100
200
300
400
500
600
700
800
900
1000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time
Nu
mb
er
of
ve
hic
les
i.
0
100
200
300
400
500
600
700
800
900
1000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time
Nu
mb
er
of
veh
icle
s
3. Sensitivity test: weekday and weekend – 2010
313090/ITD/ITQ/003/D 17 January 2013 PiMS
7
Rother Valley Railway A21 Robertsbridge
For northbound traffic, the worst weekday was identified as being a Bank Holiday. Therefore, in order to
provide a robust assessment, the second busiest weekday has been identified and assessed.
However, for southbound traffic, the busiest weekday has been identified as being a non Bank Holiday. In
light of this no additional weekday analysis has been undertaken. Section 5 of this report, which examines
the resultant queues from the sensitivity test (e.g worst weekday), does not report on southbound Bank
Holiday queues.
3.3 T/04/216 – northbound
The busiest weekday for northbound traffic has been determined as Monday 3rd
May. The busiest
weekend day has been determined as Sunday 4th July. A profile for each day is shown in Figures 3.3 and
3.4.
Figure 3.3: Monday 3rd
May 2010 – 24 hour profile
Figure 3.4: Sunday 4th July 2010 – 24 hour profile
0
200
400
600
800
1000
1200
1400
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24Time
Nu
mb
er
of
ve
hic
les
ii.
0
200
400
600
800
1000
1200
1400
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24Time
Nu
mb
er
of
ve
hic
les
3.4 T/04/2016 – northbound (non bank holiday weekday)
Where the busiest day has been identified as a Bank Holiday, a second day (non Bank Holiday) has been
identified. For northbound traffic, Monday 3rd
May 2010 has the highest flows, but this happens to be a
Bank Holiday. The TRADS data shows that Friday 4th June was the second busiest day in 2010 in terms of
total 24 hour traffic flow. Figure 3.5 shows the daily profile for this data.
313090/ITD/ITQ/003/D 17 January 2013 PiMS
8
Rother Valley Railway A21 Robertsbridge
Figure 3.5: Friday 4th June 2010 – 24 hour profile
0
100
200
300
400
500
600
700
800
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Time
Nu
mb
er
of
ve
hic
les
The traffic flows for these identified weekdays and weekend days have been used in the Queue Model,
which was developed during the initial RVR traffic impact assessment work.
313090/ITD/ITQ/003/D 17 January 2013 PiMS
9
Rother Valley Railway A21 Robertsbridge
4.1 Introduction
Further to determining the busiest day and weekend day for both northbound and southbound traffic on the
A21, PB has requested that Mott MacDonald,
“look at the upper quartile of weekend and weekday flow data” (email dated 14 September 2012).
The TRADS data which has been generated in Section 3 has also been used for this exercise. The 24
hour traffic flows have been ranked into ascending order, so that the 75th percentile value can be
determined. From this, the upper quartile can be identified.
The results are shown in Table 4.1
Table 4.1: Upper quartile for 2010
Direction/day 75th percentile flow Busiest 24 hour flow
NB weekday 8,167 10,866
NB weekend b/h 7,886 9,476
NB weekend non b/h 8,167 9,953
SB weekday 8,238 10,246
SB weekend 7,612 9,060
It can be seen that the busiest flows assessed are significantly higher than the 75th percentile.
4. Assessment of upper quartile 2010
313090/ITD/ITQ/003/D 17 January 2013 PiMS
10
Rother Valley Railway A21 Robertsbridge
5.1 Introduction
The Queue Model designed as part of 2011 Mott MacDonald report has been used to assess queue
lengths for the busiest weekday (for northbound this will be for the Bank Holiday and non-Bank Holiday)
and busiest weekend day.
As per Section 4.3 of the October 2011 report,
“Using the 2010 traffic flow data and the traffic growth factors from TEMPRO, a set of forecasts of
traffic queue propagations has been produced…the analysis for the A21 has identified where a traffic
queue at the closed level crossing has the potential to block the upstream roundabout, 140m to the
north of the crossing. For each barrier closure throughout the day, derived from the preliminary
timetable, calculations have been undertaken for each day type…”
The previous work assumed that the traffic volume in a given hour would arrive at the level crossing at a
uniform rate, and a barrier closure period of 51 seconds (0.85 minutes applied). PB has recommended that
a flat or uniform profile should not be used, and that “a worst case scenario of 112 seconds closure time is
applied to the weekday and weekend flows to assess the impact” (email dated 14 September 2012).
5.2 Traffic profile
In order to generate an arrival profile which is not uniform, the peak segment within an hour, e.g. 1045-
1100 in the hour 1000-1100, has been determined. TRADS data is hourly and not by minute; calculating
traffic flows for a non-uniform arrival rate is therefore not possible.
Therefore, to account for the varying arrival time of vehicles, traffic flow per minute for a given hour has
been factored by 20% and 40% in order to model a peaking effect.
5.3 Closure period and assessment year
At the request of PB, a 112 second (1.87 minutes) closure time has been applied to the model.
For the purposes of this assessment, the Queue Model has been run for 2021.
Growth rates have been applied to the 2010 TRADS data. The rates used in the previous work have been
applied to the revised queue model; PB has confirmed that “the use of dataset 62 and NTM factors [are]
acceptable together with associated growth factors” (email dated 14 September 2012).
5.4 Results
Tables 5.1 to 5.3 show the results for three scenarios:
Hourly uniform profile;
Hourly profile with 20% factor; and
Hourly profile with 40% factor.
5. Revised queue model
313090/ITD/ITQ/003/D 17 January 2013 PiMS
11
Rother Valley Railway A21 Robertsbridge
Each of the three scenarios has results for the busiest weekday and busiest weekend day. Furthermore,
the northbound direction has results for a Bank Holiday. This is because the Bank Holiday represents the
busiest weekday.
As discussed in Section 3.2, southbound Bank Holiday queues are not reported.
Table 5.1 shows that for a uniform profile, the maximum queue length predicted by the model is 265m.
When looking at the likely average queue length, southbound traffic for both weekdays and weekends have
an average of queue of 162m, with northbound traffic having an average queue of 149m on weekdays and
152m on weekends.
Table 5.1: Modelling results for 2021 – uniform profile
Day type Northbound Southbound
Maximum queue (m) Average queue (m) Maximum queue (m) Average queue (m)
Weekday (not Bank Holiday)
155 137 177 154
Weekend 198 147 183 148
Bank Holiday 265 205 n/a n/a
Note: All queue lengths are in metres (rounded up to the nearest whole metre)
Table 5.2 shows the results of the plus 20% profile. It can be seen that the maximum queue length on the
busiest day (a Bank Holiday) is predicted to be 383m in 2021; with an average queue length of 247m.
The model shows that on the busiest day (non Bank Holiday), the maximum forecast queue length is 265m
for both northbound and southbound traffic on weekdays and weekends. The model shows average queue
lengths as between 172m and 185m. Weekdays and weekends show very similar results in terms of
forecast traffic queues.
Table 5.2: Modelling results for 2021 – profile plus 20%
Day type Northbound Southbound
Maximum queue (m) Average queue (m) Maximum queue (m) Average queue (m)
Weekday(not Bank Holiday)
265 172 265 185
Weekend 265 172 265 184
Bank holiday 383 247 n/a n/a
Note: All queue lengths are in metres (rounded up to the nearest whole metre)
Table 5.3 shows the results for 2021 with a plus 40% profile.
Table 5.3: Modelling results for 2021 – profile plus 40%
Day type Northbound Southbound
Maximum queue (m) Average queue (m) Maximum queue (m) Average queue (m)
Weekday(not Bank Holiday)
265 195 265 209
Weekend 277 193 265 208
Bank Holiday 2971 648 n/a n/a
Note: All queue lengths are in metres (rounded up to the nearest whole metre)
313090/ITD/ITQ/003/D 17 January 2013 PiMS
12
Rother Valley Railway A21 Robertsbridge
The model results indicate a significant increase in Bank Holiday queuing in 2021; with a maximum queue
of 2,971m and an average queue of 648m. The weekday (non-Bank Holiday) and weekend show a slight
increase in queuing when compared to the plus 20% profile.
For the busiest weekday, the model indicates that northbound traffic would have an average queue length
of 195m and southbound traffic would have an average queue length of 209m.
For the busiest weekend day, the model indicates that northbound traffic would have an average queue
length of 193m and southbound traffic would have an average queue length of 208m.
In summation, applying the busiest weekday and weekend day to the queue model, queues would extend
north beyond the Northbridge Street roundabout for southbound traffic. Furthermore, as stated in Section
4.4 of the previous Mott MacDonald report: -
“It should be borne in mind that although the proposed level crossings would impact on the free flow
of traffic level crossing this would not occur every day. The 2011 schedule of days of operation of
the KESR indicates that trains will run on 181 days of the year, i.e. approximately 50%. As noted
previously the RVR would run to a similar schedule”. Further details of this can be found in the
October 2011 report.
A second important point noted by the previous work stated that: -
“the presence of the [level] crossing would have little noticeable effect on overall journey times,
given the signification congestion that currently occurs on the A21”.
It is also noted that at the busiest bank holiday periods, vehicles held at the level crossing released to
proceed in effect move forward to rejoin the rear of the traffic queue they were already following –
excepting that a number of cars will have been assisted in joining the A21 traffic flow from side road
connections to the A21 using any queue gap that is created for a distance either side of the level crossing.
313090/ITD/ITQ/003/D 17 January 2013 PiMS
13
Rother Valley Railway A21 Robertsbridge
This Technical Note (TN) has been completed to address the comments provided by the Highways Agency
(HA) and Parsons Brinckerhoff (PB), based on the Mott MacDonald report issued in October 2011. The
following sets out the key findings of this TN:
6.1 General
Comparing 2010 TRADS data with 2009 and 2011 data, the variation across the years is between +/-
2% and +/- 7%.
The busiest weekday for southbound traffic is determined as Friday 4th June and the busiest weekend
day is determined as Saturday 28th July.
The busiest weekday for northbound traffic is determined as Monday 3rd
May and the busiest weekend
day is determined as Sunday 4th July. Monday 3
rd May was a Bank Holiday, hence this could be
classed as ‘non typical’. The second busiest weekday was Friday 4th June.
Trains would normally run on about 50% of the days of the year with typically seven trains operating per
day in both directions during the summer months. Trains would not generally start running until after
10:00 and would continue throughout the day at around hourly intervals until approximately 18:00.
In 2010, the busiest average hour for weekday traffic in a southbound direction was 1700-1800. The
busiest average hour for weekend traffic in a southbound direction was 1200-1300.
In 2010, the busiest average hour for weekday traffic in a northbound direction was 0700-0800. The
busiest average hour for weekend traffic in a northbound direction was 1000-1100.
All modelling results are for the year 2021, using the approved growth rates.
Based on comments from PB, the level crossing barrier has been assessed for closure period of 112
seconds (1.87 minutes).
Traffic is forecast to grow by between 8-11% from 2010 up to 2021 (as detailed in the Mott MacDonald
October 2011 report).
6.2 Queuing
It is important to note from Section 5.4.2, Rother Valley Railway Proposed Level Crossing Traffic Impact
Assessment, 2011, that despite the queue model showing traffic exceeding 140m north of the crossing: -
“long queues currently occur on occasions on the A21, particularly at Bank Holidays, and this would
occur in the future irrespective of whether or not a level crossing was present”
Key findings from this TN show that:
The longest forecast traffic queue, on a typical day, is estimated to be on a weekday in the southbound
direction (with a 40% profile uplift), with average forecast queue lengths of 209m.
The busiest weekday, with a 20% profile uplift, was in the southbound direction, with a predicted
average queue of 185m (maximum queue of 265m).
The busiest weekend day, with a 20% profile applied was in the southbound direction, with a predicted
average queue of 184m (maximum queue of 265m).
In light of these key findings, the capacity of the A21 was exceeded in 2010 and a flow of 1,649 vph would
have caused notable congestion anyway on the A21. “Barrier closures of 51 and 112 seconds would have
no discernible effect on overall journey times in most cases as drivers would be in a queue anyway”
(Section 5.4.2, Rother Valley Railway Proposed Level Crossing Traffic Impact Assessment, 2011).
6. Summary
313090/ITD/ITQ/003/D 17 January 2013 PiMS
14
Rother Valley Railway A21 Robertsbridge
Appendix A. Correspondence ___________________________________________________________________ 15
Appendices
313090/ITD/ITQ/003/D 17 January 2013 PiMS
15
Rother Valley Railway A21 Robertsbridge
Appendix A. Correspondence
Rother Valley Railway A21 Robertsbridge
Personal Injury Accident Analysis Technical Note
January 2013
Rother Valley Railway Limited
313090 ITD ITQ 004 D
25 January 2013
Rother Valley Railway A21 Robertsbridge
Personal Injury Accident Analysis Technical Note
January 2013
Rother Valley Railway Limited
Mott MacDonald, Stoneham Place, Stoneham Lane, Southampton, SO50 9NW, United Kingdom
t +44 (0)23 8062 8800 f +44 (0)23 8062 8801, W www.mottmac.com
Robertsbridge Junction (RVR) Station, Station Road, Robertsbridge, Sussex TN32 5DG
Rother Valley Railway A21 Robertsbridge
Mott MacDonald, Stoneham Place, Stoneham Lane, Southampton, SO50 9NW, United Kingdom
t +44 (0)23 8062 8800 f +44 (0)23 8062 8801, W www.mottmac.com
Revision Date Originator Checker Approver Description
A 15.11.12 B A Pledge M D Lewis M D Lewis First Issue
B 11.12.12 B A Pledge M D Lewis M D Lewis Second Issue
C 17.01.13 B A Pledge M D Lewis R E Murdock Third Issue
D 25.01.13 B A Pledge M D Lewis R E Murdock Fourth Issue
Issue and revision record
This document is issued for the party which commissioned it
and for specific purposes connected with the above-captioned
project only. It should not be relied upon by any other party or
used for any other purpose.
We accept no responsibility for the consequences of this
document being relied upon by any other party, or being used
for any other purpose, or containing any error or omission which
is due to an error or omission in data supplied to us by other
parties
This document contains confidential information and proprietary
intellectual property. It should not be shown to other parties
without consent from us and from the party which
commissioned it.
313090/ITD/ITQ/004/D 25 January 2013
Rother Valley Railway A21 Robertsbridge
Chapter Title Page
1. Introduction 1
1.1 Overview __________________________________________________________________________ 1
2. Analysis of PIA Data 2
2.1 Overview __________________________________________________________________________ 2 2.1.1 Site 1: Rail level crossing at Cooksbridge _________________________________________________ 2 2.1.2 Site 2: Rail level crossing at Etchingham _________________________________________________ 2 2.1.3 Site 3: Rail level crossing at Lyminster ___________________________________________________ 3 2.1.4 Site 4: Rail level crossing at Robertsbridge________________________________________________ 3 2.1.5 Site 5: Rail level crossing at Woodgate ___________________________________________________ 3 2.1.6 Site 6: Rail level crossing at Drayton Lane ________________________________________________ 3 2.1.7 Site 7: Proposed Rail level crossing site at Robertsbridge ____________________________________ 4 2.2 Proposed investigation of Rail level crossing site at A487 Porthmadog __________________________ 4
3. Level Crossing Safety Reports 5
4. Conclusions and Recommendations 7
Content
313090/ITD/ITQ/004/D 25 January 2013
1
Rother Valley Railway A21 Robertsbridge
1.1 Overview
Mott MacDonald has been commissioned by Rother Valley Railway Limited (RVRL) to undertake a number
of highway, traffic and road safety analyses in support of a proposed railway level crossing of the A21 at
Robertsbridge, East Sussex.
This Technical Note examines the personal injury accident (PIA) data for a range of sites which exhibit
similar characteristics to the proposed site at Robertsbridge. The purpose of this is to see to what extent, if
any, the presence of the level crossing, is considered to be a contributory factor.
In addition, reference is also made within this report to railway industry reports concerning railway level
crossing safety performance.
Seven sites have been identified in collaboration with RVR and these are outlined in the following table: -
Site
No. Site Name Road Location / Town Site OSGR
PIA Search Criteria
(5 years data 01/01/2007 to
31/12/2011)
1 Rail level crossing at Cooksbridge
A275 Cooksbridge Nr Lewes
540093; 113435
A275 only – 250m radius search of level crossing
2 Rail level crossing at Etchingham
A265 Haremere Hill, Etchingham
571517; 126263
A265 only – 250m radius search of level crossing
3 Rail level crossing at Lyminster
A284 Lyminster, Nr Littlehampton
502722; 103881
A284 only – 250m radius search of level crossing
4 Rail level crossing at Robertsbridge
Brightling Road/Station Road
Station Road, Robertsbridge
573313; 123213
Brightling Rd/Station Rd only – 250m radius search
of level crossing
5 Rail level crossing at Woodgate
A29 Lidsey Road, Chichester
493797; 104325
A29 only – 250m radius search of level crossing
6 Rail level crossing at Drayton
B2144 Drayton Lane, Chichester
489049; 104414
B2144 only – 250m radius search of level crossing
7 Proposed rail level crossing A21, near Robertsbridge
A21(T) North of Robertsbridge
574118; 124080
A21 only – 250m radius search of OSGR co-
ordinates
Table 1-1: List of sites featuring PIA analysis
1. Introduction
313090/ITD/ITQ/004/D 25 January 2013
2
Rother Valley Railway A21 Robertsbridge
2.1 Overview
PIA data has been obtained from the Road Policing Unit, Sussex Police. At each site, detailed in the table
above, a search for PIA records occurring between 01/01/2007 to 31/12/2011 (latest five years’ of data
available) has been requested.
Where there are sites with an existing rail level crossing (Sites 1 to 5) a circle search radius of 250 metres
has been used and a full narrative report was provided. From these narrative reports, PIAs involving the
operation of the rail level crossing have been analysed further, to determine weather it was a contributory
factor in the accident.
At the proposed rail level crossing site on the A21 near Robertsbridge (Site 7), a search radius of 250
metres has also been used. All accidents occurring with the five-year period are described within this
Technical Note.
All accidents occurring with the five year period are described within this section of this Technical Note.
2.1.1 Site 1: Rail level crossing at Cooksbridge
Location: A275 Cooksbridge, Nr Lewes (E540093; N113435). Total PIAs in five-year search: 4 (0 Fatal, 1
Serious, 3 Slight).
Two of the PIAs (both Slight) involved stationary traffic due the level crossing being in operation.
One was side impact accident, occurring after being beckoned out from a side road (in traffic).
The other was on approach to the level crossing, travelling too fast, and colliding with a stationary
queuing vehicle.
2.1.2 Site 2: Rail level crossing at Etchingham
Location: A265 Haremere Hill, Etchingham (E571517; N126263). Total PIAs in five-year search: 0 (0 Fatal,
0 Serious, 0 Slight).
No PIAs recorded.
2. Analysis of PIA Data
313090/ITD/ITQ/004/D 25 January 2013
3
Rother Valley Railway A21 Robertsbridge
2.1.3 Site 3: Rail level crossing at Lyminster
Location: A284 Lyminster, Nr Littlehampton (E502722; N103881). Total PIAs in five-year search: 5 (0 Fatal,
0 Serious, 5 Slight).
None of the PIAs were considered to be related to the operation of the Level Crossing.
2.1.4 Site 4: Rail level crossing at Robertsbridge
Location: adjacent to Network Rail Station, Station Road, Robertsbridge (E573313; N123213). Total PIAs
in five-year search: 1 (1 Fatal, 1 Serious, 0 Slight).
One PIA was recorded and this is deemed to be in relation to the Level Crossing.
Fatal accident involving a car passing through the Level Crossing at excessive speed. The vehicle
was travelling east when it grounded on the railway section and lost control. This resulted in a
collision with seven parked cars, and the fatality of one pedestrian and slight injury to another.
2.1.5 Site 5: Rail level crossing at Woodgate
Location: A29 Lidsey Road, Chichester (E493797; N104325). Total PIAs in five-year search: 5 (0 Fatal, 2
Serious, 3 Slight).
None of the PIAs were considered to be related to the operation of the Level Crossing.
2.1.6 Site 6: Rail level crossing at Drayton Lane
Location: B2144 Drayton Lane, Chichester (E489049; N104414). Total PIAs in five-year search: 5 (0 Fatal,
1 Serious, 4 Slight).
One PIA (Slight) involved stationary traffic due the level crossing being in operation.
Rear end shunt type accident in northbound traffic queue at the level crossing.
313090/ITD/ITQ/004/D 25 January 2013
4
Rother Valley Railway A21 Robertsbridge
2.1.7 Site 7: Proposed Rail level crossing site at Robertsbridge
Location: A21 North of Robertsbridge (E574118; N124080). Total PIAs in five-year search: 3 (0 Fatal, 2
Serious, 1 Slight).
The details for all three PIAs that occurred near the proposed rail level site are as follows:
Occurring on the A21 southbound, approx 170m north of the junction with Redlands Lane. Slight
injuries were sustained to both car drivers a vehicle (V1) overtook another (V2) on the hatched
separation markings. V2 pulled nearside, causing it to swerve and collide with V1. V1 overturns
and V2 strikes the nearside barrier.
Occurring on the A21 southbound, north of the Northbridge Street Roundabout. Serious accident
after a motorcyclist (V1) attempted to overtake a car (V2) prior to roundabout. V2 turned right to
access the offside (northbound) lay-by, causing V1 to collide in its side. Rider of V1 received
serious injuries.
Occurring on the A21 northbound, just north of the Northbridge Street Roundabout. Serious injuries
caused to a solo motorcyclist when re-starting after stalling. Due to vehicle defect (throttle stuck
open) the motorcycle collided with pedestrian guard rail.
2.2 Proposed investigation of Rail level crossing site at A487
Porthmadog
It was suggested in the Highways Agency letter dated 4th May 2012 that the A487 Porthmadog Heritage
Railway level crossing might provide a suitable comparison for the RVR proposals. The A487 level
crossing is built tramway style whereby the railway runs along the centre of the highway, in the same
direction as the road traffic, rather than across the highway at an acute angle as is more normal and as the
RVR proposals. The Porthmadog level crossing brings with it entirely different safety considerations such
as cyclists running along the line of the railway if they do not follow the alternative safe signposted route. In
addition, the Porthmadog crossing does not have any form of barriers / gates to close off the highway and
footways while the road is being crossed by a train.
The level crossings proposed for RVR are modern crossings where the railway crosses over the road at an
acute angle and incorporate full barriers. There is no commonality between the A487 Porthmadog crossing
and those proposed for RVR.
313090/ITD/ITQ/004/D 25 January 2013
5
Rother Valley Railway A21 Robertsbridge
The type of level crossings proposed by RVR are of the Full Barrier type, locally monitored and controlled
by a railway signalman. These are also classified as MCG, MOB and MOB-CACTV crossing in the reports
referred to below.
The perceived generalised dangers associated with railway level crossings come primarily from accidents
at ‘open’ level crossings, half-barrier level crossings, automatically operated (unmonitored) level crossing
and user worked crossings.
Full Barrier level crossings are used extensively, including such as the East Coast mainline with trains
operating at 125 mph.
3-1: Example of typical East Coast Main Line Level Crossing
Source: Rother Valley Railway Limited
Two learned reports provide a useful detailed overview of railway level crossing data: -
• Railway Accident Investigation Branch (RAIB) (a UK Government Agency). Study of 'Open' crossings – but that contains detailed comparative performance data for full barrier crossings – as the type proposed by RVR. That report is at:
http://www.raib.gov.uk/cms_resources.cfm?file=/110728_R122011_AOCLs_Class_Inv.pdf
The RAIB general website is at: http://www.raib.gov.uk/home/index.cfm
3. Level Crossing Safety Reports
313090/ITD/ITQ/004/D 25 January 2013
6
Rother Valley Railway A21 Robertsbridge
• Centre for Transport Studies : Andrew W Evans Imperial College London
This paper investigates level crossing performance over the period 1946 to 2009. That report is at:
http://www.cts.cv.ic.ac.uk/html/ResearchActivities/publicationDetails.asp?Publ icationID=1432
As in both the above studies, locally monitored Full Barrier Level Crossings (also classified as MCG, MOB
& MOB-CACTV crossings in these reports) have and excellent safety performance record.
There do not appear to be any full barrier level crossings currently installed on heritage railways. Heritage
railways operate at maximum speeds of 25mph, being very much lower than generally seen on mainline
Network Rail level crossings. That lower speed must by nature mean that a heritage railway full barrier
crossing will perform even better, because of reduced train stopping distances than those studied in the
above learned reports.
The proposed Rother Valley Railway level crossings will operate with maximum train speeds set by
agreement with the Office of the Rail Regulator (ORR). Train speed on the whole line is a maximum speed
of 25mph, and are anticipated to be set in the region of +/- 15mph at the level crossings, assisting trains to
stop on sight of the crossing being blocked for any reason.
The Kent & East Sussex Railway operates the existing railway from Tenterden to Bodiam (where it will join
the Rother Valley Railway). It has several level crossings, including over two ‘A’ roads that all use
traditional hand worked level crossing gates to close off the highway and footpath.
313090/ITD/ITQ/004/D 25 January 2013
7
Rother Valley Railway A21 Robertsbridge
The broad conclusions of this Technical Note are as follows: -
1. The choice of those level crossing sites reviewed in detail above, has been directed by RVR, who
considered that they have representative characteristics similar to those exhibited by the proposed
RVR level crossing site on the A21 at Robertsbridge.
2. Full barrier level crossings are demonstrated in the report and associated learned studies as
having a good accident record.
4. Conclusions and Recommendations
Rother Valley Railway A21 Robertsbridge
Journey Time Analysis Technical Note
January 2013
Rother Valley Railway Limited
313090 ITD ITQ 007 C
17 January 2013
Rother Valley Railway A21 Robertsbridge
Journey Time Analysis Technical Note
January 2013
Rother Valley Railway Limited
Mott MacDonald, Stoneham Place, Stoneham Lane, Southampton, SO50 9NW, United Kingdom
t +44 (0)23 8062 8800 f +44 (0)23 8062 8801, W www.mottmac.com
Robertsbridge Junction (RVR) Station, Station Road, Robertsbridge, Sussex TN32 5DG
Rother Valley Railway A21 Robertsbridge
Mott MacDonald, Stoneham Place, Stoneham Lane, Southampton, SO50 9NW, United Kingdom
t +44 (0)23 8062 8800 f +44 (0)23 8062 8801, W www.mottmac.com
Revision Date Originator Checker Approver Description
A 15.11.12 B A Pledge M D Lewis M D Lewis First Issue
B 12.12.12 B A Pledge M D Lewis M D Lewis Second Issue
C 17.01.13 B A Pledge M D Lewis R E Murdock Third Issue
Issue and revision record
This document is issued for the party which commissioned it
and for specific purposes connected with the above-captioned
project only. It should not be relied upon by any other party or
used for any other purpose.
We accept no responsibility for the consequences of this
document being relied upon by any other party, or being used
for any other purpose, or containing any error or omission which
is due to an error or omission in data supplied to us by other
parties
This document contains confidential information and proprietary
intellectual property. It should not be shown to other parties
without consent from us and from the party which
commissioned it.
313090/ITD/ITQ/007/C 17 January 2013
Rother Valley Railway A21 Robertsbridge
Chapter Title Page
1. Introduction 1
1.1 Overview __________________________________________________________________________ 1
2. Analysis of Journey Time Data 2
2.1 Overview __________________________________________________________________________ 2
3. Conclusions 3
Content
313090/ITD/ITQ/007/C 17 January 2013
1
Rother Valley Railway A21 Robertsbridge
1.1 Overview
Mott MacDonald has been commissioned by Rother Valley Railway (RVR) to undertake a number of
highway, traffic and road safety analyses in support of a proposed railway level crossing of the A21 at
Robertsbridge, East Sussex.
This Technical Note displays and examines the Journey Time data undertaken on a series of surveys that
were completed on Tuesday 23 October 2012. The purpose of this is to see how journey times could be
affected, should vehicles use the alternative route via Robertsbridge village, to avoid the proposed level
crossing.
Four routes were surveyed (two northbound and two southbound). These are outlined in the following
table:-
Route Route Description Start point End point
A A21(T) mainline, from north to south (through the proposed level crossing).
Passing the A21 north lay-by entrance
A21 southbound exit at A2100/A21 Vinehall Road
Roundabout
B Via Robertsbridge village, from north to south (avoiding the proposed level crossing)
Passing A21 north lay-by entrance
A21 southbound exit at A2100/A21 Vinehall Road
Roundabout
C A21(T) mainline, from south to north (through the proposed level crossing).
A21 southbound exit at A2100/A21 Vinehall Road Roundabout
Passing the A21 north lay-by entrance
D Via Robertsbridge village, from south to north (avoiding the proposed level crossing)
A21 southbound exit at A2100/A21 Vinehall Road Roundabout
Passing A21 north lay-by entrance
Table 1-1: List of journey time survey routes
The routes are shown in Figure 1.2 below: -
1. Introduction
313090/ITD/ITQ/007/C 17 January 2013
2
Rother Valley Railway A21 Robertsbridge
2.1 Overview
After examining the historic tidal traffic flow from TRADS database, three separate time periods were
determined to record journey time data. They were as follows;
Morning traffic peak (07:00 – 08:00hrs);
Off peak (10:00 – 11:00hrs), and;
Evening traffic peak (17:00 – 18:00hrs).
For each route surveyed (A, B C and D) several ‘runs’ were completed within the different time periods, to record journey times in varying traffic conditions. The table below displays the average time to complete each route:
Average time to complete route (mins:secs)
Route Morning peak Off peak Evening peak
A 03:51 03:41 03:57
B 06:12 04:27 05:51
C 03:21 03:13 03.13
D 04:43 04:48 04:44
*Green denotes the longest time taken to complete route.
The standard deviation for the journey times has been calculated and the variance from the mean has been
determined. There is a high confidence that journey times on this route fall within +/- 1 standard deviation
of the mean journey time. This suggest that the reliability of the journey along the A21 is not significantly
variable, based in the data recorded.
2. Analysis of Journey Time Data
313090/ITD/ITQ/007/C 17 January 2013
3
Rother Valley Railway A21 Robertsbridge
The journey time surveys were conducted on a single day and comprised four runs northbound and
southbound on Routes A, B, C and D respectively during the AM peak.
A further two runs, northbound and southbound, were conducted in the inter-peak, per direction on routes A
- D (inclusive).
Finally, a further four runs were conducted, northbound and southbound, on routes A – D (inclusive for the
PM peak.
The broad conclusions that can be drawn are that, the sample sizes, whilst not numerous, indicate, not
unsurprisingly, that the route along the A21 Robertsbridge Bypass, is significantly quicker than that via the
C18 Northbridge Street.
The increase in journey time is similar to the period the crossing is closed to road traffic, leaving aside the
fact that a west-bound train will also cause the C18 Northbridge Street crossing to be closed. Furthermore,
traffic attempting this would encounter the lead vehicle of the platoon of traffic released from the A21
crossing leading to delays re-entering the A21.
Therefore, it is considered that there is no time advantage for A21 traffic diverting via the C18 through
Robertsbridge when the proposed level crossing barriers are closed.
3. Conclusions