important instructions for bidders - esic hospitals & …€¦ · · 2017-09-14tenderer...
TRANSCRIPT
Annexure-B
Important Instructions for Bidders
All bidders/contractors are required to procure Class-IIIB Digital Signature Certificate (DSC) with
Both DSC Components i.e. Signing & Encryption to participate in the E- Tenders.
Bidder should get Registered at https://esictenders.eproc.in.
Bidders can contact our Helpdesk at https://esictenders.eproc.in/html/Support.asp
Bidder needs to submit Bid Processing Fee charges of Rs. 2495/- (non-refundable) in the form of
Demand Draft from any scheduled bank in favour of M/s. C1 India Pvt. Ltd., payable at New Delhi
(or in any other form as acceptable by C1 India Pvt. Ltd.) for participating in the Tender.
Along with the Demand Draft, Bidder needs to send a covering Letter mentioning about the
Payment Details, Company Name, Address, User ID and Payment towards ESIC Bid Processing
Fees (Mention the Tender ID and Tender Title).
The payment should reach at the below mentioned address, at least one day before the due date
and time of Bid Submission:
Kind Attn: Mr. Mohit Chauhan C1 India
Pvt. Ltd.
301, Gulf Petro Chem Building, 1st Floor,
Udyog Vihar, Phase – 2,
Gurgaon, Haryana - 122015
Note: Bid Processing Fee will be Approved only after the receipt of payment.
Page 3 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
Annexure-C
ELIGIBILTY CONDITIONS
1. At least Three (3) years’ experience of providing round the clock mechanized
housekeeping and facility management services in Medical College or Hospital with bed
strength of 100 beds or more run by the central Government/State Government/public
or Private Sector companies/undertaking or Autonomous bodies.
2. Tenderer should have minimum Three years (experience certificate to be enclosed) in
mechanized housekeeping and facility management service and have successfully
completed:-
(a) One similar work of value equal to 3.2 crore or more in the last three years.
(b) Two similar works of value equal to 2.4 crore or more in the last three years.
(c) Three similar works of value equal to 1.6 Crore or more in the last three years.
3. Tenderer is required to submit copy of work order and satisfactory completion
certificates from the Clients/Employers in support of the above failing which the
information is liable to be treated as invalid.
4. The Tenderer must have an average annual turnover of 4 crores and should be profit
making during the last three years.
5. Copies of the following documents must be submitted along with the Technical Bid.
(a) Audited Balance Sheet, Audited Income and Expenditure statement, Audit report
and Audited Profit and Loss Account of last three financial years i.e.
2013-14, 2014-15 and 2015-16
(b) Income Tax return of last three Financial years i.e. 2013-14, 2014-15 and
2015-16
(c) GST Registration Certificate
b) ESI Registration Certificate
c) PF Registration Certificate
d) Labor license
e) PAN No.
6. The Tenderer should have at least 150 employees on its payroll specifically trained for
housekeeping work as on date. Full list of the employees along with details should be
attached with the technical Bid.
7. Tenderer should have a registered office/Branch office in Faridabad or Delhi/NCR.
Page 4 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
ANNEXURE-D
INSTRUCTIONS TO THE BIDDERS
1. COST OF BIDDING & BID DOCUMENT:
1.1 Tender document may be downloaded from the website www.esic.nic.in, www.esichospitals.gov.in, www.esicmcfbd.nic.in. (https://esictenders.eproc.in).
1.2 The bidder shall bear all costs associated with the preparation and submission of the bid.
The Dean, will not be responsible or liable for these costs, regardless of the conduct or
outcome of the bidding process.
2. EARNEST MONEY DEPOSIT:
2.1 A demand draft drawn on any nationalized bank in favor of “ESIC Fund A/C No. 1”,
payable at Faridabad for Rs. 800000 /- (Rupees Eight Lakh only) is to be enclosed towards
Earnest Money Deposit(EMD).
2.2 Bids received without EMD will not be considered and summarily rejected. The EMD of
the unsuccessful bidder will be refunded in due course without accrual of any interest.
3. DOCUMENTS COMPRISING BID:
The bid prepared by the bidder shall contain following documents & and scanned copy must
be submitted/uploaded online after duly filling, signing and stamping on all the pages of the
original bid document:-
3.1 Technical Bid :
The following documents should be enclosed forming the part of technical bid:
A. Notice Inviting Tender (NIT) -- (Annexure-A)
B. Important Instruction for e-tender (Annexure-B)
C. Eligibility Criteria- (Annexure-C)
D. Instruction to Bidders- (Annexure- D)
E. General Conditions of Contract- (Annexure E)
F. Scope of Work- (Annexure- F)
G. ADDITIONAL SCOPE OF WORK AND SPECIAL CONDITIONS (Annexure G)
H. Technical Bid Performa- (Annexure H)
I. Financial Bid Performa (Annexure -I,I(1),I(2))
Page 5 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
J. Declaration-- (Annexure- J)
K. Demand Draft for EMD of Rs. 800000/- (Rupees Eight Lakh only)
L. Income Tax returns for 2013-14, 2014-15 and 2015-16 along with Income
Tax Clearance Certificate.
M. ESI and EPF payment details for last two years up to July 2017
N. Copy of Audited Balance-Sheet, Audited Income and Expenditure Statement
Audited,
Profit & Loss A/c. & Audit Report for the financial year 2013-14, 2014-15 and 2015-
16.
O. Copies of all the registration certificates including ESI, EPF, Contract Labour
(Abolition & Regulation) Act 1970, Goods and Service Tax , Income Tax (PAN
Card) and Professional Tax, if applicable)
P. Satisfactory completion certificate and copy of work order as prescribed in
ELIGIBILITY CONDITIONS in Annexure-C.
3.2: Financial Bid:
The rates in Financial Bid shall be filled by the parties in figure and words both. The details of
work to be done are given in Annexure-D as ‘SCOPE OF WORK’. Notwithstanding, the parties
may visit the office premises before tendering the rate on any working day i.e. from Monday
to Friday from 10:00 AM to 4:00 PM for estimating the quantum of work.
Note: All the documents submitted along with the bid shall be self-attested and must be
legible and signed and stamped by authorized signatory, otherwise the bid is likely to be
rejected. Correction, if any should be attested with dated initials by the same person who is
signing the Tender Form. Overwriting will render tender liable to be rejected.
4. SUBMISSION:
4.1 Tender must be submitted through online portal only as per Annexure-B. The bid received
in physical mode only shall not be considered at all.
(a) In addition to submission through e-tender protal, physical copy of Sealed Tender
along with EMD should be delivered in the tender box kept in Conference Hall, ESIC
Medical College, NIT-3, Faridabad-121001. The responsibility for ensuring that the
tenders are delivered in time would rest with the bidder. Please note, that bid received
without EMD shall not be considered.
(b) The sealed envelope shall be addressed to the Dean at the following address:
To,
Dean
ESIC Medical College, NIT-3, Faridabad -121001 (Haryana)
Page 6 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
(c) The envelope should also indicate the name and address of the bidder.
(d) Tenders received after the fixed date and time of receipt will not be entertained in any
circumstance.
5. OPENING OF TENDER: The online tenders shall be opened on schedule date and time in
the presence of the tenderers who choose to be present. First, technical Bid will be
opened and schedule of opening financial bid of those tenders who are found technically
qualified in first stage will be informed telephonically or through e-mail. Financial bids of
those tenders found to be technically not qualified will be returned.
6. MISCELLENEOUS:
1. Any attempt to negotiate directly or indirectly on the part of the Tenderer with
authority competent to finally accept the Tender, or influence the acceptance of the
tender by any means will result his tender excluded from consideration.
2. The Dean of ESIC or any other authorized Officer of the Corporation reserves the right
to reject any or all the Tenders without assigning any reason thereof.
3. Conditional tender, illegible and ambiguous tender, partially filled tender, incomplete
tender and tender without enclosing aforementioned documents will summarily be
rejected.
Page 7 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
ANEXURE-E
GENERAL CONDITIONS OF CONTARACT (GCC) 1 The persons deployed by the Contractor should be properly trained, have requisite
experience and skills for carrying out a wide variety of housekeeping work using
appropriate materials and tool/equipments.
2 The Contractor should ensure the Health and safety measures of the employees. ESIC
may also conduct health check up of the staff deployed at regular intervals.
3 The Contractor will be responsible for supply/installation/refilling/maintenance of all
such items/equipments used in wash rooms and other areas for housekeeping
purposes.
4 The Contractor must deploy adult and skilled labour only. Employment of child labour
will lead to the termination of the contract. The Contractor shall engage only such
workers, whose antecedents have been thoroughly verified, including character and
police verification and submit police verification certificate in respect of each staff
before deployment. The Contractor shall be fully responsible for the conduct of his
staff.
5 In case of breach of any terms and conditions attached to the contract, the
Performance Security Deposit of the Contractor will be liable to be forfeited by ESIC
besides annulment of the contract.
6 The Contractor must provide standard liveries to its housekeeping
staff/supervisors/managers. The staff shall be in proper uniform and with their
identity properly displayed.
7 ESIC will provide space for setting up a control room of the Contractor in each premise.
The control room will have seating arrangements for the Manager and/or Supervisor.
The contractor will arrange for all other items, viz., biometric attendance machine,
computerized inventory of stores, computerized daily duty roster chart, etc. The
house keeping staff will first report to the Manager/Supervisor in the control room
and subsequently deployed for duty after having been checked for liveries, upkeep,
issue of material and equipments, etc. ESIC will provide space for a store room to the
Contractor in each of the premises. The storekeeper/supervisor deployed by the
contractor will store all their liveries, materials, equipments in the store room and
maintain a computerized record of the stores which shall be opened to inspection by
ESIC staff during working hours.
8. ESIC will depute a person in each of the premises to ensure that the office rooms,
committee rooms, hospital rooms etc. are open at designated hours for
cleaning/housekeeping work.
Page 8 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
9 (a). The contractor shall release monthly wages to the staff deployed in time from ESIC
through online payment only. Disbursement of salary shall have no linkage to clearance
of Bills by ESIC.
(b). Attested copies of ESIC Card/TIC with photograph wherever applicable should be
submitted to ESIC after deployment of manpower.
(c) ESIC/EPF compliance has to be made by the contractor every month & copies of
challans/RCs as proof to be submitted for preparing of bills.
10. The Contractor shall:
(a) Ensure Pest/Animal and Rodent free environment in the premises of ESIC.
(b) Provide tissue boxes and hand towels in Officers rooms.
(c) Provide toiletries, steel body liquid soap dispensers, jumbo toilet roll dispensers, etc.
in wash rooms, toiletries, C-Fold Towel dispensers, Jumbo Roll dispensers, Soap
dispensers, etc. in all designated washrooms, and garbage bins/bags, etc. in all work
station, wash rooms and pantries.
(d) Ensure that their managers/supervisors are equipped with mobile phones.
(e) Arrange for a garbage disposal vehicle, bins, and other material required for
segregation and disposal of waste in a professional manner.
(f) Provide Hospital Waste Management Services when applicable including all
equipment, disposables containers, trolleys etc. complete in all respects.
(g) Plan; manage collection, mechanized screening/segregation of dry and wet garbage in
the earmarked area and efficient transport and disposal of the garbage in the disposal
area. The work should be carried out in an eco friendly manner. The Contractor will
arrange for required resources, including manpower, machinery, disposal bags, bins,
van, etc. The contractor will also ensure that the garbage collection/disposal work
does not adversely affect the surroundings or personnel deputed for the work.
Protective gear including boots, gloves etc. shall be provided by the Contractor to the
housekeeping staff.
PERFORMANCE SECURITY:
The successful bidder shall furnish, a Performance security for an amount equal to 5%
(five percent) of successful bid amount in the form of Demand Draft from any scheduled
Bank in favour of the “ESIC Fund A/C No.- 1”, payable at Faridabad. EMD amount is
adjustable towards the performance security in case of successful bidder. No interest will
be paid on the security deposits. This amount will be refunded after satisfactory
fulfillment of the contract by him and all accounts thereafter are settled and after six
months from the date of last bill raised.
PAYMENT PROCEDURE
Page 9 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
1. The billing cycle will be calendar month and The Agency will have to submit the
bill in duplicate complete in all respects upto 3rd of each month. However, the
Agency shall be under obligation for making the payment to their workers
through Bank transactions (not through cash/cheque) on or before 7th of each
month and this payment should not be linked to the payment of the bills by ESIC.
However, endeavor shall be made to make the payment to the agency within
fifteen days from the date of submission of the bill completed in all aspect.
2. The bill is to be submitted with the following documents :-
(a) The details of payments along with bank account number for the previous month to
be uploaded by the agency on its website. if there is no website, it is to be sent by mail to
the appropriate authority.
(b) Location wise details of all employees deployed at this site only ESI, EPF contribution
paid for the previous month along with paid challans.
(c) Location wise Goods and Service tax and other statutory dues for the previous month
along with paid challans segregated for this institute.
(d) An Undertaking that all statutory Labour Laws including Minimum Wages Act is being
complied with.
(e) Computerized printout of Biometric Attendance Sheet duly verified by authorized
person of ESIC in respect of the persons deployed for the billing month, along with salary
sheet for the billing month.
3. If it is found that agency is delaying disbursement of salary regularly, strict action up
to extent of termination of contract may be taken.
4. The agencies which do not provide proof of payment of statutory dues, their contract
will be terminated by giving one month’s notice for termination of contract.
5. Payment of the bill will be based on computerized print outs in standardized proforma
approved by ESIC.
6. All the payment to the workers to be made by the agency through bank transactions
only. Cash payment is strictly prohibited. Such payments are to be treated at par with non-
payment of wages. There must be no deviation whatsoever in this regard. If agency fails
to make payment to its workers through Bank, contract is liable to be terminated and
fresh tender process will be initiated.
7. Agency shall record signature of each employee in wage register as a token of having
disbursed salary and having handed over salary slip for the month. Salary slip shall include
all wage component, deductions clearly mentioned.
Page 10 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
8. The contractor shall ensure the payment of Minimum Wages as per latest Central Govt. notification.
MAINTENANCE OF RECORDS
1. The contractor shall maintain such other records as per scope of work or prescribed
by ESIC from time to time.
2. The wage of workers for last month credited to their Bank Account and date of
credit and the details of payment along with bank Account No. are to be maintained and
submitted by the Agency to the appropriate authority alongwith details of deduction and
payment in respect of ESI /EPF /Service Tax/ other statutory dues in previous month and
date of such deposit. (Copy of challan to be enclosed).
MATERIAL, MACHINES AND EQUIPMENTS
1. The contractor shall provide all the necessary material for keeping the hygiene and
sanitation of the building.
2. The contractor shall provide necessary material, machines and equipment for
cleaning, dusting etc., to their workers including the wet and dry vacuum cleaners,
brooms, mops, brushes, scrubbing, auto scrubber, high pressure jet, ringer trolley, caddy
buckets, spider cranes etc.
3. Alternative arrangements of machines and equipments must be done by the
contractor in case of any breakdown or maintenance in the provided machines and
equipments.
4. The contractor shall provide the cleaning material vis-à-vis phenyl, acid, liquid
soap, phenolphthalein ball/cakes and other detergents/cleaning agents/liquids that are
required for aforesaid work.
5. Contractor shall provide room-fresheners, mosquito repellants and other
pest/rodent control chemicals/agents etc.
6. Contractor must provide all the necessary materials required for Biomedical Waste
collection, storage and transportation like polybags, Puncture proof containers, card
boards, heavy duty gloves, gum boots, masks etc. as per the norms of Pollution Control
Board.
7. The contractor shall provide the names/ brands of the material to be used for the
cleanliness and upkeep of the office.
8. The contractor shall handover a list of the inventory he is bringing in the ESIC
premises and shall also be responsible for their safety and security.
Page 11 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
STATUTORY COMPLIANCE
1. Contractor shall make compliance to the provisions of all Labour Laws applicable.
The Contractor at all times must indemnify ESIC against all claims, damages or
compensation under all statutory laws and rules prevailing time to time which, interalia,
include the provisions of Payment of Wages Act, 1936; Minimum Wages Act, 1948;
Employer's Liability Act, 1938; the Workmen Compensation Act, 1923; Industrial
Disputes Act, 1947; Maternity Benefit Act, 1961; Employees’ Insurance Act, 1948;
Employees Provident Fund and Miscellaneous Provisions Act, 1952;or any other law
relating thereto and rules made hereunder from time to time. Corporation will not own
any responsibility in this regard.
2. The contractor shall furnish copies of periodical returns as and when they are
submitted or due to the various Government Departments.
3. The contractor shall be responsible for the registration under the contract labor
(Regulation and Abolition) Act, 1970 in respect of employees/ workers engaged by them.
ACCIDENT OR INJURY TO WORKMEN
The ESIC will not be liable for any damage or compensation payable to any workmen for
death or injury resulting from any act or default by contractor. The contractor shall
indemnify ESIC for all such damages, compensation and expenses whatsoever in respect
thereof or in relation thereto.
DISPUTE JURISDICTION
1. In case of any dispute and differences of opinion arising out of this contract, the
decision of the Dean, ESIC Medical College, NIT-3, Faridabad will be final and binding
upon the Contractor.
2. All the disputes will be subject to the jurisdiction of Court situated at Faridabad only.
SUBLETTING NOT ALLOWED
The agency shall not sublet or subcontract this service/work to any other party in any
circumstances, after agreement of contract. If it comes to the notice of the ESIC Medical
College and Hospital, NIT-3, Faridabad the contract will be terminated and PGM will be
forfeited.
Variations The ESIC official in charge may order variations in the scope or quantum of work through
a written variation order. The payment for the variation shall be worked out on the basis
of contract rates for manpower and prorate for additional areas for equipment, toiletries
etc.
Page 12 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
Liquidated damages and Penalty: a. Whenever and wherever it is found that the cleanliness is not up to the mark, it will
be brought to the notice of the supervisory staff of the Contractor by ESIC and if no
action is taken within One hour, liquidated damages @ Rs.500/- per instance shall be
imposed. The decision of competent authority shall be final, in this regard.
b. In case, any person deployed under contract is absent, penalty equal to (double) the
wages of number of staff/supervisor absent on the particular shall be levied by the
Hospital and same shall be deducted from the contractor's bill.
c. In case any housekeeping staff/supervisor is found without proper uniform, identity
card, name badge etc, a penalty of Rs 500/- per instance shall be imposed and
deducted from the bill. Agency shall be under obligation to terminate the service of a
repetitive offender (more than three instance in a month for a particular staff) from
the services at the institute.
d. Any complaint of misbehavior to staff or visitors shall invite a penalty of Rs. 500 per
instance.
e. Any loss or damage to property or equipments of the institute by housekeeping staff
shall be recovered from the bill of agency along with suitable penalty.
f. If the image of the institute is tarnished by any of the activity of housekeeping agency
or its staff, contract may be terminated with the forfeiture of security deposit without
prior notice.
Manpower
a). Any misconduct/misbehavior on the part of the manpower deployed by the Contractor
will not be tolerated and such person will have to be replaced by the Contractor at his
own costs, risks and responsibilities immediately, with written intimation to ESIC.
b.) The Contractor should ensure to maintain adequate no. of manpower and also arrange
a pool of stand by housekeeping staff/supervisor. In case any housekeeping
staff/supervisor absences from the duty, the reliever of equal status shall be provided by
the Contractor from an existing pool of housekeeping worker/supervisor/manager.
Materials & Equipments
1. Any deviation in the material quality and quantity quoted will invoke penalty as
decided by the competent authority. For proper maintenance, suitable cleaning
material which are environment friendly, not harmful to humans and property
should be used.
2. If it is found that machines/ equipments are not in working condition at any time,
it will invoke penalty as decided by competent authority.
Page 13 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
Risk Clause The Contractor shall at all times will have standby arrangements for carrying out the work
under the Contract in case of any failure of the existing arrangement.
ESIC reserves the right for termination of the contract at any time by giving one month
written notice, if the services are found unsatisfactory and also has the right to award the
contract to any other selected tenderers.
All necessary reports and other information will be supplied on a mutually agreed basis
and regular meeting will be held with the ESIC on weekly basis.
• Contractor and its staff shall take proper and reasonable precautions to prevent
from loss, destructions, waste or misuse the areas of responsibility given to them by the
ESIC and shall not knowingly lend to any person or company any of the effects or assets
of the ESIC under its control.
• In the event of loss/damage of equipments etc. at the premises of the ESIC due to
negligence/ carelessness of Contractor staff, if established after a joint inquiry, then the
Contractor shall compensate the loss to ESIC.
• The Contractor or its representatives shall meet ESIC representatives regularly to
take feedback regarding the Housekeeping services. The Contractor will also maintain a
suggestion book for comments on the services rendered by it.
• The Contractor shall, in performing its part of this Agreement, ensure the safety of
the building and the persons working in or visiting the ESIC’s premises and shall
indemnify ESIC for any loss or damage caused by any act of the Contractor or its
employees of staff etc.
• The Contractor shall not assign or sublet, this Agreement or any part thereof to any
third party.
• In every case the Contractor shall make alternative arrangements for meeting his
contractual responsibilities.
• Measure of success will be based on the feedback from visitors, Clinicians and staff
which will be recorded and action report needs to be submitted every month by the
Contractor.
• Training on behavior aspects and ethics must be done regularly. ESIC’s way of
working should be communicated to all contract staff. Training report of the same must
be submitted once in a month.
• Licenses required for Housekeeping services at the site must be procured by the
Contractor within one month of resumption of work.
Page 14 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
ANNEUXURE ‘F’
SCOPE OF WORK
The aim and objective is to provide a high level of clean, hygienic and presentable look to the
entire area by deputing adequate number of un-skilled employees and pre-designated semi-
skilled Manager/Supervisors.
The designated area includes: The entire covered and uncover area within the premises of
the ESIC Medical College & Hospital, NH 3, Faridabad which includes
(a) Daily Services
Housekeeping/cleaning services should be done daily from Monday to Saturday at regular
intervals, so that the areas covered under the contract remain spic and span all the time.
Working hours should be adjusted in such a manner that cleaning work in the morning should
be completed well before 08:00 A.M.
1. Cleaning dusting, vacuuming and disinfecting of floors, walls and ceilings, removal of waste
and any other garbage from the entire area covered under the contract (such as halls,
conference rooms, committee rooms, office rooms, cabins, cubicles, etc.)
2. Sweeping, cleaning, mopping with disinfecting cleaner of area covered under the contract,
including all staircases, cabins, lobbies, reception, training rooms, office rooms, cabins,
meeting rooms, security office and other areas as covered in the contract.
3. Cleaning of baskets, wastepaper baskets, cob-webs, etc. and disposing off all the collected
refuse at designated site on daily basis.
4. Dusting of computer systems and their peripherals, all doors and windows, furniture,
fixtures, fans, equipment, accessories etc. and cleaning of all windows glasses and grills.
Cleaning and dusting of window panes/Venetian blinds.
5. Spraying Room Fresheners in all rooms, on a daily basis at regular intervals.
6. Scrubbing/cleaning of toilets, wash basins, sanitary fittings, glasses, toilets, floors, etc.
7. Cleaning and disinfecting all vitreous fixtures including toilet bowls, urinals, sinks, toilet
seats, containers etc. Brush thoroughly to include below water level and under rims
including areas at hinges and cistern handles. Re-stock toiletries, which include liquid hand
soap, toilet rolls, air fresheners, sanitary cubes, naphthalene balls in toilets, etc. after daily
check-ups in the morning, afternoons and on call basis during daytime.
Page 15 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
8. Cleaning and dusting of electrical switchboards, light fixtures, fans, air conditioner vents, overhead light fixtures, projectors, fire-fighting equipments, nameplates, plant boxes, doormats etc.
9. Placing garbage bags in all garbage bins to avoid stains and stinks and clear them on daily
basis.
10. Check and remove hairs, dust, dirt or any such object from anywhere in area
covered under the contract.
11. Cleaning, dusting, scrubbing of pantries, reception, security rooms, training halls,
committee rooms, computer labs etc.
12. Cleaning of all open areas between the building and boundary including sweeping
of roads, lawns, paths, cleaning open drains etc. as directed by the ESIC official in charge.
(b) Waste Disposal Management:
The contractor will ensure collection, mechanized screening/segregation of dry and wet garbage in the earmarked area. The contractor will also segregate bio degradable and non bio degradable garbage. Finally, the contractor will arrange to suitably transport and dispose garbage from the
earmarked area to the nearest Corporation bin outside each premises.
The Contractor shall keep suitable size and specification bins at the collection area. The Contractor will employ his staff for the collection/disposal work. The garbage will have to be disposed off at least twice a day. The contractor will also arrange for the garbage bags, prepare a flowchart indicating the method of collection/disposal, etc.
(c) Weekly Services:-
The deep cleaning of the entire area will be done by the Contractor once a week as under:- 1.
Dusting of entire area including windows/windowpanes/doors/ledges, etc.
2. Thorough cleaning/sweeping/washing/mopping with disinfectant cleaners of all floors, staircases and toilets. Scrubbing of all floors and ceramic tiles base. Cleaning of ceiling and high walls, removal of wash stains on walls, cleaning of roofs, porches etc.
3. Cleaning of sanitary fitting, toilet drain pipes etc. in the toilets with standard cleaning
material.
4. Cleaning of all windows glasses and grills with detergent/cleaning agents.
5. Washing of outside area with High Pressure Jet machine.
6. Clean all chrome fittings, glass frames, soap holders etc. to a shiny finish.
Page 16 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
7. The Tenderer will make a cleaning program and submit to ESIC for weekly cleaning so that ESIC’s concerned official/In charge for the particular area can be deputed on the day of cleaning to make the area available and supervise the cleaning work.
8. The Contractor will work in the specified area mentioned in the scope of work.
9. The Contractor will provide the duty register to ESIC as required.
(d) Pest and Rodent Control Services
1. The Contractor shall take effective measures for Rodent and Disinfection Services including
fogging etc. in the area under contract.
2. The Contractor shall use chemicals that are harmless to humans and machines and are of WHO specification. Further, the chemicals should not leave any spots in the treated area. MSDS report of these chemicals should also be attached.
3. The Contractor will be responsible for any damage to human/machinery by any chemicals used by him. Any damage caused to machinery/books due to rodent and disinfection services in the areas covered under contract shall be made good by the Contractor.
4. The Contractor will submit a detailed plan for carrying out the Pest and Rodent Control
Services for the approval of ESIC.
5. Agency is required to ensure rodent/pest free environment.
6. Area of operation will include area in/over false ceiling of hospital.
7. Agency will ensure odorless environment.
(e) Housekeeping Monitoring and Control
For better management and smooth services, the following monitoring mechanism will be adopted by the Contractor:- 1. Toilets Checklist This is to be attached on the back of the toilet door. It is to be filled up by the Contractor
supervising staff on duty daily.
2. Management/Housekeeping Services Requirements/Complaints Report
This is to be filled up by the management and administrative staff of the Contractor who receive/observe the complaints/requirements for any of the services. All suggestions, complaints related to services or staff deployed by the Contractor will be registered at site on the computer and report to Caretaker, ESIC. The Contractor will take immediate action to resolve the same failing which the Penalty Clause
will be invoked.
Page 17 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
3. Housekeeping Services Complaints Register
This register is to be completed on the basis of information received by the Housekeeping Supervisor from ESIC through the inspection of the site, material on site, attendance sheet of the staff, weekly report, client letter/fax/e-mail, verbal complaints from ESIC, etc. and necessary action is to be taken.
Annexure-G
ADDITIONAL SCOPE OF WORK AND SPECIAL CONDITIONS In case of any differences, these Particular Conditions of Contract will supersede the General Conditions of Contract. The services shall be provided round the clock on all days including holidays:-
The services include:
I. Cleaning of the whole premises including toilets and open areas through mechanized
equipment
II. Wet moping of covered areas.
III. Cleaning of window panes and door panels.
IV. Cleaning and dusting of furniture and fittings.
V. Any other work within the scope of the specialized services.
VI. Vacuum Cleaning of all carpets and upholstered furniture.
1. PATIENTS ROOM:
The Contractor shall be responsible for routine cleaning of the patient room ward everyday in the morning and evening. The Contractor shall also maintain cleanliness in the patient rooms/ward throughout the day and shall clean the room thoroughly on patient’s discharge and keep it ready for the next arrival. (a) THE ROUTINE CLEANING WILL INCLUDE
· Dusting of the furniture in the room including bed, chair, table TV, fridge etc.
· Sweeping and mopping the entire room with a disinfectant solution.
· Cleaning of Toilet and bathroom with a bathroom cleaning solution.
(b) CLEANING OF DISCHARGE OF AN INPATIENT WILL INCLUDE · Wiping of the
furniture and fixtures in the room with a soap solution.
· Sweeping and mopping the entire room with a disinfectant solution.
Page 18 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
· Cleaning of toilet and bathroom with a disinfectant/bathroom cleaning solution.
· Reporting any maintenance required in the room.
2. CLEANING THE PATIENT COMMON AREAS
o Dusting the walls, furniture and fixtures in the corridor and lobby.
o Sweeping and mopping the floor with a disinfectant.
o Cleaning public toilets with soap solution and keeping them odor free using deodorizer
cubes/Odonil.
o Cleaning doors and windows with soap solutions.
o Cleaning consulting room, dressing room, laboratory and other similar areas. The cleaning
pattern will be same as cleaning patient rooms.
3. OPERATION THEATRE
o All the dustbins washed and lined with colour-coded bags in the morning. The trash bag
shall be changed when it is full.
o Operation theater walls shall be thoroughly cleaned using a specialize soap/disinfectant
solution before and after every operation.
o Floor shall be washed thoroughly mopped with a specialized soap/disinfectant solution.
The entire operation theater floor area shall be scrubbed once a day.
o Toilets/bathrooms to be cleaned on checklist basis.
o All the dustbins washed and lined with colour-coded bags in the morning. The Trash bag shall be changed when it is full. Operation theatre walls shall be thoroughly cleaned using specialize soap/disinfect ant solution before and after every operation.
o Floor shall be washed thoroughly mopped with a specialized soap/disinfectant solution.
The entire operation theatre floor area shall be scrubbed once a day.
o Toilets/bathrooms will be cleaned with soap solution and kept odor free using deodorizer
cubes.
o The common areas, doctor’s lounge, nurses lounge, Change rooms, waiting lounge and inside operation theater shall be swept and mopped in the morning and at regular intervals to keep them clean.
Page 19 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
o The floor scrubbing will be done in the night or as and when asked for according to the
scheduled operations and movements in that area.
4. CLEANING OF OFFICE/CONSULTANT ROOMS
o The Contractor shall remove trash from office dustbin and change the trash liner every
evening before closing hours.
o The offices shall be dry dusted and swept after the closing hours.
o Vacuum cleaning shall be done on carpets and upholstery.
o The worktables shall be cleaned with soap solution in the morning.
o The office shall be mopped with soap solution in the morning.
o Office staff rest rooms/toilets shall be cleaned using soap solution and kept odor free
using deodorizer.
5. CLEANING OF LABORATORY and OTHER CRITICAL AREAS
o All the dustbins shall be washed and lined with colour coded bag in the morning. The
trash bag shall be changed when it is full.
o Walls shall be thoroughly cleaned using a specialized soap/disinfectant solution in the
morning.
o The floor shall be thoroughly mopped with a specialized soap solution.
o The entire laboratory area shall be scrubbed at less twice in a week.
o Toilets/bathrooms shall be cleaned with soap solution and kept odor free using
deodorizer cubes.
o The common area shall be swept and mopped in the morning and at regular intervals to
keep them clean.
6. GLASS WINDOWS and DOORS
Page 20 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
o The Contractor shall have his staff clean glass with appropriate soap solution on weekly
basis.
o Internal glasses shall be wiped with dry cloth to remove fingerprints at regular interval.
7. GARBAGE DISPOSAL
o The Contractor shall collect garbage in specified colour coded bags from all dustbins and garbage bins existing inside the premises and shall dispose the garbage at the designated area within the Hospital.
8. CLEANING OF ACADEMICS/ADMINISTRATIVE BLOCK
Basement and all floors with terrace including Class Rooms, Practical Rooms, halls, office rooms,
committee rooms, cabins, cubicles, staircases, lobbies, lawn, training hall, conference hall, reception,
staff canteen, gents and ladies toilet blocks, officers’ rooms, recreation hall, TOR, camp
accommodation, parking, open space and other areas remaining/proposed (after complete hand
over of new building).
9. CLEANING OF RESIDENTIAL AREA
Residential quarters consisting Number of Blocks located at ESIC including All rooms of Girls and Boys
hostels; Corridors; staircases; Toilets, All Terraces, , Mess, Corridors, staircases, terrace of all
residential hostel and staff quarters roads, parks, parking, open space, play-grounds inside the
boundary walls and other areas remaining/proposed (after complete hand over of building). 10. CLEANING OF OUTER AREA OF MEDICAL COLLEGE & HOSPITAL
Entire outer area including roads, parking, opens space, ETP/STP plant, DG Plant, Oxygen plant,
playground, Biomedical waste storage room, Air condition plant and other areas
remaining/proposed after complete hand over.
Page 21 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
CLEANING SCHEDULE
1. VERY HIGH RISK AREA (OT AREA LABOUR ROOM)
S.
No
Activity Frequency Agents Used Responsibility
1. Garbage removal After every case As per the BMW guidelines
Area supervisor
2. Feather brushing After every case Feather Brush
3. 1st mopping Before start 1st patient
and after every case Wizard
4. 2nd mopping Before start 1st patient
and after every case 1 % Sodium Hypochlorite
5. Garbage removal from the OT Corridor
After every case As per the BMW guidelines
6. Brushing in the OT corridor In continuation Flat Mop
7. Dusting of doors and windows in OT
Corridor After every 1 hr. X color Duster
8 Mopping with Wizard in OT corridor After every 1 hr. Wizard
9. Mopping with Sodium Hypochlorite in
OT corridor After every 4 hrs. 1 % Sodium Hypochlorite
2. ICU, CCU, ICCU, NICU, PICU
S.
No
Activity Frequency Agents Used Responsibility
1. Removal of Garbage Thrice in a day (7 a.m., 2.30
p.m and 7.30 p.m.) as and
when required
As per the BMW Guidelines
2. Brushing Thrice in a day 9.00 a.m., 3.00p.m., 9.00 p.m.
Feather Brush
Page 22 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
3. Dusting After every 1 hr. X color Duster
Area supervisor
4. Mopping with wizard After every 1 hr. Wizard
5. Mopping with Sodium Hypochlorite
After every 4 hrs. as and when
required 1 % Sodium Hypochlorite
6. Washroom cleaning with Wizard
Cleaning after every half an
hr. Wizard
7. Washroom cleaning with Sodium Hypochlorite
Cleaning After every 4 hrs. as
and when required 1 % Sodium Hypochlorite
3. HIGH RISK AREA (EMERGENCY)
S.
No
Activity Frequency Agents Used Responsibility
1. Removal of Garbage Thrice in a day (7 a.m., 2.30 p.m and
7.30 p.m.) as and when required
As per the BMW Guidelines
Area supervisor
2. Brushing Thrice in a day 9.00 a.m., 3.00p.m, 9.00 p.m.
Feather Brush
3. Dusting After every 2 hrs. as and when required Wizard
4. Mopping with wizard After every 2 hrs. as and when required Wizard
5. Mopping with Sodium Hypochlorite
After every hrs. as and when required 1% Sodium Hypochlorite
6. Washroom cleaning wizard
with Cleaning after every half an hr. Wizard
4. MODERATE RISK AREA (OPD ROOMS/WARDS)
S.
N
o
Activity Frequency Agents Used Responsibility
1. Removal of Garbage Thrice in a day (7 a.m., 2.30 p.m and
7.30 p.m.) as and when required
As per the BMW
Guidelines
2. Brushing Thrice in a day (7 a.m., 2.30 p.m and
7.30 p.m.) as and when required
Feather Brush
3. Dusting Thrice in a day (7 a.m., 2.30 p.m and
7.30 p.m.) as and when required
Z Color Duster
4. Mopping with wizard Thrice in a day (7 a.m., 2.30 p.m and
7.30 p.m.) as and when required
Wizard
Page 23 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
5. Mopping with Sodium
Hypochlorite
Thrice in a day (7 a.m., 2.30 p.m and
7.30 p.m.) as and when required
1 % Sodium
Hypochlorite
Area supervisor
6. Washroom (OPD) Four times in a day 1st start from
7.00 a.m.,
2nd from 11.00 a.m.,
3rd from 2.30 p.m.
4th from 1.30 p.m. As and when
required
Wizard and 1 %
Sodium
Hypochlorite
Washroom (WARDS) st Eight times in a day 1
start from
nd
6.00 a.m., 2 from 8.00 a.m., 3rd
th from 10.00 am; 4 from 1.00 p.m; 5th from 4.00 pm; 6th from 6.00pm;
7th from 8.00 pm; 8th from 12.00am
Wizard and 1 % Sodium
Hypochlorite
7. Brushing in the corridor in the
Moderate Area
In continuation Flat Mop
8. Dusting in the corridor area Twice in a day it starts From 7.00 a.m.
onwards
Z Color Duster
9. Mopping with wizard In continuation Wizard
10
.
Mopping with Sodium
Hypochlorite
After every 8 hrs. 1 % Sodium
Hypochlorite
5. PATHOLOGY LAB
S. No
Activity
Frequency Agents Used Responsibility
1. Removal of Garbage Thrice in a day (7 a.m., 2.30 p.m and 7.30
p.m.) as and when required
As per the BMW Guidelines
Area supervisor
2. Dusting/Brushing Twice in a day 8.00 a.m. and 5.00 p.m. as and when required
Y Color Duster
3. Mopping with wizard After every three hrs. as and when
required Wizard
4. Mopping with Sodium Hypochlorite
After every 8 hrs. as and when required 1% Sodium Hypochlorite
6. DIAGNOSTIC AREA
Page 24 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
S. No
Activity
Frequency Agents Used Responsibility
1. Removal of Garbage Thrice in a day (7 a.m., 2.30 p.m and
7.30 p.m.) as and when required
As per the BMW Guidelines
Area supervisor
2. Dusting Twice in a day 8.00 a.m. and 5.00 p.m. as and when required
Z Color Duster
3. Brushing Twice in a day 8.00 a.m. and 5.00 p.m. as and when required
Z Color Duster
4. Mopping with wizard After every 3 hrs. as and when required Wizard
5. Mopping with Sodium Hypochlorite
After every 8 hrs. as and when required 1 % Sodium Hypochlorite
7. PUBLIC AREA WASHROOM
S. No
Activity
Frequency Agents Used Responsibility
1. Cleaning with Wizard Cleaning will be done after half an hr. and boy will be stationed there
Wizard
2. Washroom Cleaning with Sodium Hypochlorite
Cleaning will be done after 8 hrs. as and when required
1% Sodium Hypochlorite
Area supervisor
8. CORRIDOR
S. No
Activity
Frequency Agents Used Responsibility
1. Mopping with dry mop In continuation Flat Mop
Area supervisor
2. Mopping with Wizard After every 3 hrs. as and when required Wizard
3. Mopping with Sodium Hypochlorite
After every 8 hrs. as and when required 1 % Sodium Hypochlorite
9. LOBBY
S. No
Activity
Frequency Agents Used Responsibility
1. Dusting In continuation Z Color Duster
Area supervisor
2. Brushing with Dry Mop In continuation Flat Map
3. Mopping with Wizard After every 3 hrs. as and when required Wizard
4. Mopping with Sodium Hypochlorite
After every 8 hrs. as and when required 1 % Sodium Hypochlorite
10. OPD AREA
Page 25 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
S. No
Activity
Frequency Agents Used Responsibility
1. Removal of Garbage Thrice in a day (8 a.m., 2.30 p.m and 7.30
p.m.) as and when required
As per the BMW Guidelines
Area supervisor
2. Brushing Twice in a day 7.30 a.m. and 8.00 p.m. as and
when required Feather Brush
3. Dusting Twice in a day 7.30 a.m. and 8.00 p.m. as and
when required Z Color Duster
4. Mopping with wizard Twice in a day 7.30 a.m. and 8.00 p.m. as and
when required Wizard
5. Mopping with Sodium Hypochlorite
After every 8 hrs. as and when required 1 % Sodium Hypochlorite
11. PHARMACY
S. No
Activity
Frequency Agents Used Responsibility
1. Removal of Garbage Thrice in a day (8 a.m., 2.30 p.m and
7.30 p.m.) as and when required
As per the BMW Guidelines
2. Brushing Twice in a day 8.00 a.m. and 8.00 p.m. as and when required
Feather Brush
Area supervisor
3. Dusting Twice in a day 8.00 a.m. and 8.00 p.m. as and when required
Z Color Duster
4. Mopping with wizard After every 3 hrs. as and when required Wizard 5. Mopping with Sodium
Hypochlorite After every 8 hrs. as and when required Sodium Hypochlorite
12. PROCEDURE/TREATMENT ROOM
S.
No Activity Frequency Agents Used Responsibility
1. Removal of Garbage Thrice in a day (7 a.m., 2.30 p.m
and 7.30 p.m.) as and when
required
As per the BMW Guidelines
Area supervisor
2. Brushing Thrice in a day starts from 7.00 a.m, 2.30 p.m. and 8.00 p.m. as and when
required
Feather Brush
3. Dusting Twice in a day 8.00 a.m. and 8.00 p.m. as and when required
Y Color Duster
4. Mopping with wizard After every 3 hrs. as and when required Wizard
5. Mopping with Sodium Hypochlorite
After every 6 hrs. as and when required 1% Sodium Hypochlorite
Page 26 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
13. MORTUARY
S. No
Activity
Frequency Agents Used Responsibility
1. Brushing In the morning in presence of Security as and when required
Feather Brush
Area supervisor
2. Mopping with wizard In the morning in presence of Security as and when required
Wizard
3. Mopping with Sodium Hypochlorite
After every 8 hrs. 1% Sodium Hypochlorite
14. MINIMAL RISK AREA
(ADMINISTRATION, RECORD ROOM/STORAGE ROOM ENGINEERING OFFICE)
S. No
Activity
Frequency Agents Used Responsibility
1. Brushing Once in a day it starts from 7.30 a.m. as and when
required Feather Brush
2. Mopping with wizard Once in a day it starts from 7.30 a.m. as and when
required Wizard Area supervisor
15. CAFETERIA/CANTEEN/MESS
S. No
Activity
Frequency Agents Used Responsibility
1. Removal Of Garbage
Thrice in a day starts from 10.00 a.m,
3.00 p.m. and 8.00 p.m. as and when required
Garbage Bag
Area supervisor
2. Brushing
Thrice in a day 8.00 am, 12.00 pm, 6.00 pm as and when
required Flat Mop and
feather brush
3 Dusting
Thrice in a day 8.00 am, 12.00 pm, 6.00 pm as and when
required Z colour duster
4 Mopping with wizard
After every three hours and after every meal as and when
required Wizard
Dilution of Wizard in all areas = 40 ml in 1 liter of water
Cleaning of spillage of Blood/Body fluids
1. Use disposable gloves.
2. Cover area with 1% Sodium Hypochlorite
3. Leave for 20 minutes
Page 27 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
4. Collect residue with disposable paper. Wipe and discard in bag.
5. Wash surface with detergent and dry.
6. All waste, gloves, wipe, discard, seal and dispose as clinical waste. Mopes cleaning- Detergent wash
and dry. Buckets- Detergent wash and dry (if contaminated 1% Sodium Hypochlorite overnight
rinse and dry).
DISPOSAL OF BIO-MEDICAL WASTE
1) All collection, storage, transportation and disposal of hospital waste shall be in accordance with
Bio- Medical Waste (management and Handling Rules of India, 1998 and any amendments
or other regulations, in this regard.
2) A detailed Hospital Waste Management Plan shall be prepared and got approved from ESIC
before start of work.
3) All infected, chemical, Radiation, Cytotoxic Health care Waste shall be segregated, collected,
stored, transported and disposed in accordance with set guidelines in safety, ensuring that it at
no stage gets mixed general waste. Unscientific burning shall not be permitted. Different
coloured bags/containers namely white, green, red, yellow, blue, black and transparent, puncture
proof or stainless steel, lead containers shall be used depending on the category of waste.
4) The waste shall be carefully secured or pretreated for transportation to a common facility for
disposal.
5) Waste shall not be transferred from one bag to another. Bags should be tied when three fourths
full and then placed in a bigger bag/container for transporting.
6) Covered Trolleys should be used for transportation. Before final disposal/treatment waste should
be kept in specified location and in specific liners and containers.
7) The scope includes segregation, collection, storage, transportation within Hospital.
METHOD AND PROCEDURE
• Anatomical waste will be collected in yellow bag and will be given to Centralized Waste
Management Contractor.
• Soiled waste (Solid Waste)- will be segregated and collected in red bag and will be given to
Centralized Waste Management Contractor.
• Plastic Waste will be collected in Blue Bag and will be autoclaved chemically disinfected and then
shredded.
• Sharps will be collected in puncture proof container and will be given to Centralized Waste
Management Contractor.
• Microbiology Waste will be autoclaved.
• Liquid Waste will be disinfected with hypochlorite solution before disposal.
• Expired Medicines will be sent to pharmacy for return.
• General Waste will be collected in Black Bag and will be disposal as normal waste.
Page 28 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
The following shall be followed:-
1) Segregation will be done at source.
2) Bins will have Bio-hazardous sign on them.
3) Housekeeping personnel will wear Gloves and Masks before collecting garbage.
4) Bags will be secured when they are ¾th full and will be clearly labeled with the date, time and
respective floor.
5) While handling the bag it must be held at the closed top and away from the body.
6) If a bag is found broken or not completely sealed then it should be double bagged into a
second bag.
7) Garbage will be transported in designated trolley to the storage area.
8) Cleared daily at designated time.
9) Access to waste storage area is limited to authorized persons.
10) Waste storage area must be inspected every week for spills and contained deterioration
and the inspection must be documented.
11) Before the collection by the outside vendor the garbage bag has to be weighed and the details
like date, time floor, weight, will be entered in the garbage register by the housekeeping boy
in the presence of security.
12) If for any reason, it becomes necessary to store the waste beyond such period, the authorized
person must take permission from the authorities and take measure to ensure that the waste
doesn’t adversely affect human health and environment.
RESOURCES(MANPOWER, MATERIAL AND MACHINES) MANAGEMENT
• The Contractor has to provide high standard fully mechanized housekeeping services with
latest cleaning equipments / machines and tools.
• The Contractor has to deploy sufficient number of manpower & machines/ equipments so
as to ensure high quality service. Computerized record of number of manpower deputed,
machines, equipments & materials used may be maintained and submitted to ESIC on
regular interval.
• Replacement/alternative arrangements of manpower & machines/ equipments must be
done by the contractor in case of any kind of breakdown, maintenance, or any other activity
held in ESIC Medical College & Hospital, Faridabad.
• Indicative description of equipment and machines requirement, materials and manpower
utilization is as under. However, the list is not exhaustive.
LIST OF EQUIPMENTS, TOOLS, & TACKELS
S.No. Description Minimum Number of machines
required
1. Scrubbing Machine 4
Page 29 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
2. Wet/Dry Vacuum Cleaner 6
3. Ride-on machine 2
4. Single Disk 2
5. Wringler Trolley 4
6. Jet Spray/High Pressure jet 2
7. Glass Cleaner Kit 2
8. Caddy Basket 16
9. Wet Floor Signage Board 20
MANPOWER MANAGMENT
OLD HOSPITAL BUILDING
S.N o.
Location Description No. of House keeping staff required
1 Ground
Floor
MS Office, Radiology,
PPCentre,IT Room G(4)
Operation Theatre M(1), E(1) =Total (2)
Skin & Psychiatry Ward, M(1), E(1), N(1) =Total (3)
Surgery Ward (M,F) M(3), E(2), N(2) =Total (7)
2 First Floor
Labor Room M(2), E(1), N(1) =Total (4)
Maternity Ward M(2), E(1), N(2) =Total (5)
Ortho Ward (M,F) M(2), E(1), N(1) =Total (4)
Paediatric Ward M(1), E(1), N(1) =Total (3)
3 Second Floor Medicine Ward (M,F) M(3), E(2), N(2) =Total (7)
Kitchen G(1)
Page 30 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
4 Outer &
Laundary Outer & Laundary G (4)
TOTAL 44
OPD Block
S.N o.
Location Description No. of House keeping staff required
1 Basement CSSD G(2 )
2 Ground Floor
MAY I help YOU counter, G(1 )
OPD Registration area Medicine G(3 )
Gynae & Paed OPD G( 2)
Pharmacy G(1 )
Radiology G(2)
Casualty & Minor OT M( 3), E( 3), N(3) =Total (9 )
Pharmacy Store G(1 )
Laundry G(1 )
Physiotherapy G(1)
3 First Floor
Ortho, Dental & Medicine OPD G( 4)
Laboratory G(3 )
Medical Record Department G(1)
Canteen G( 2)
4 Second Floor Eye , ENT & AYUSH, OPD G(4)
5 Third Floor Skin, Psychiatry & Surgery OPD G(4)
6 Outer Area + Basement G(3)
TOTAL 44
Academic Block
S.N o.
Location Description No. of House keeping staff required
Page 31 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
1 Ground Floor
Reception Area, Library, Reading Rooms, Dean Office,
BO Cabins, Admin Area, Conference Hall, foyer,
gymnasium, lift lobby
G(5)
Canteen & Examination Hall G(1 )
2 First Floor Anatomy Department, stairs and lift
lobby G(2)
Pathology Department, stairs and
lift lobby G(2)
3 Second Floor
Biochemistry Department, stairs
and lift lobby G( 2)
Microbiology Department, stairs
and lift lobby G(2 )
4 Third Floor
Physiology Department, stairs
and lift lobby G(2 )
Pharmacology Department, stairs
and lift lobby G(2 )
5 Fourth Floor
Preventive & Social Medicine
Department, stairs and lift lobby G(2 )
Forensic Medicine Department,
stairs and lift lobby G(2 )
6 Outer Area G(1)
T OTAL 23
Hostels and Residential Area
S.N o.
Location Description No. of House keeping staff required
1 Girls Hostel
(A) Ground + 6 Floors ( All Rooms) M(2 ) , E(4)= Total (6)
2 Boys Hostel (
B)
Ground + 6 Floors ( All Rooms) M(2 ) , E(4)= Total (6)
Student Mess M(3 ) , E(2)= Total (5)
3 Residential
Hostel ( C) Ground + 6 Floors G(2 )
4
5
Staff Quarter
A-1 Ground + 6 Floors G(2 )
Staff Quarter
C-1 Ground + 10 Floors G(3 )
Page 32 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
6 Staff Quarter
C-2 Ground + 6 Floors G(2 )
7 Staff Quarter D Ground + 5 Floors G(2 )
8 Outer Area G(1 )
TOTAL 29
Note :- The manpower of Housekeeping staff may be increased or decreased as per requirement.
M = Morning Shift
E = Evening Shift
N = Night Shift
G = General Shift
SUPERVISORS
S.N o.
Location No. of House keeping supervisors required
1 Old Building M( 1), G( 1)Female, E(1) =Total (3)
2 OPD Block +
Casualty G(1) , G(1)= Total (2)
3
Academic Block, Hostels,
Residential
Area
G(1)
5 Entire Premises(Night )
N(1)
TOTAL 7
Page 33 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
Annexure ‘H’ TECHNICAL BID PERFORMA
GENERAL INFORMATION
NAME OF THE AGENCY/FIRM ALONG
WITH ADDRESS AND TELEPHONE
/MOBILE NO/E-MAIL ADDRESS
NAME OF OWNER/ALL PARTNERS/ALL
DIRECTORS
TYPE OF FORMATION
(Proprietorship/ Partnership / Pvt.
Ltd/Ltd.)
BANK ACCOUNT NUMBER WITH
BANKER’S NAME AND ADDRESS
STATUTORY AND OTHER REQUIREMNTS:
1. REGISTRATION DETAILS : (Enclose Copy of registration certificate)
Statute Registration Number Copy Enclosed (Yes/No)
Contract
Labour(Abolition
And Regulation Act,
1970) Registration
E.S.I. Act, 1948
E.P.F.M.P. ACT, 1952
Goods and Service Tax
Registration
PAN NO. UNDER INCOME
TAX ACT
2. Copies of Income Tax Return for FY 2013-14, FY 2014-15 and FY 2015-16 along with
Income Tax Clearance Certificate :
Page 34 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
Financial
Year
Income Tax Return
Enclosed (Yes/No)
Income Tax Clearance Certificate
Enclosed (Yes/No)
2013-14
2014-15
2015-16
3. DETAILS OF BALANCE SHEET/P&L ACCOUNT DURING LAST THREE YEAR :
Financial Year Copy Enclosed
(Yes/No)
Income (Rs.) Expenditure(Rs.) Net Profit/LO
(Rs.)
2013-14
2014-15
2015-16
4. DETAILS OF SATISFACTORY PERFROMANCE CERTIFICATE FROM
PSUs/Govt./SemiGovt. / Pvt. Firm WHERE TENDERER HAS WORKED AS PER
ANNEXURE C:
Name of PSUs/Govt./Semi-Govt./Pvt
Firm
Period of Contract
5. DETAILS OF CONTRACT /WORK ORDER DURING LAST THREE YEAR
Sr. No. Name and
Address of
Organization
Value of
Contract (In Rs.)
Duration of Contract
From To
SIGNATURE OF THE AGENCY
WITH SEAL
Page 35 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
Annexure-I FINANCIAL BID PERFORMA
“Housekeeping Services at ESIC Medical College and Hospital, NIT-3, Faridabad”
A- MANPOWER
S. No .
Description No. of Manpo wer
Description of Wages & allowances (as
per latest central govt.
notification)
Rate per person per month
Annual amount (No.
of Manpower*Total
Monthly amount per
person X 12)
1. House-keeping Staff (unskilled)
140
1. Minimum Wage
2.PF @ 13.36%
3.ESIC @ 4.75%
4.Statutory Bonus
5.Uniform and washing Allowances
Total amount
2. Supervisor(semi-
skilled)
07
1.Minimum Wage
2. PF @ 13.61%
3.ESIC @ 4.75%
4.Statutory Bonus
5.Uniform and washing
charges
Total amount
Note:- Good and Service Tax applicable will be reimbursed on actual basis.
B-COST OF ALL CLEANING MATERIALS(As per Annexure-I(1) TO BE FILLED UP ONLINE)
S.No. Description Monthly Amount (In Rs.)
Annual Amount (In Rs.)
Cost of all cleaning material
(As per Annexure-I(1))
Page 36 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
C- RENT FOR MECHANISED EQUIPMENTS FOR HOUSEKEEPING SERVICES(As per Annexure-I(2) TO
BE FILLED ONLINE)
S.No. Description Monthly Amount(In Rs.) Annual Amount (In Rs.)
1 Rent for mechanized equipments
(As per Annexure-I(2))
D- SERVICE CHARGES
S. No. Monthly Service Charge in Percentage of A (i.e. Manpower)
Monthly Amount
(In Rs.)
Annual Amount (In Rs.)
1
E- TOTAL AMOUNT TO BE CONSIDERED FOR FINALIZATION OF SUCCESSFUL BIDDER
=A+B+C+ D
Note:
1. Payment shall be made for the actual man days of employment. Attendance will be verified by
Caretaker/authorized person. The contractor shall submit the cash memo of the material
purchase along with monthly bills for tender and non-tender items.
2. In case of absence of any of the above-mentioned workers without providing suitable
replacement, an amount of Rs.500 per day shall be recovered as liquidated damages per person
per day of absence. However, penalty can be waived off by competent authority in case of natural
calamities or situations beyond the control.
3. All the above workers must be qualified & experienced in their relevant field & capable to perform
their duties.
4. Wages should not be less than the prescribed minimum wages by the central Govt.
5. Uniform, Identity Cards, Name Plates have to be provided to each and every Staff. Bio-
Data of each staff should be maintained and whenever asked for must be shown/provided
immediately.
6. Increase in minimum wages of workers will be paid extra accordingly as per Minimum wages
Act & corresponding ESI/PF contribution.
Signature of Owner/Managing Partner/Director
Date: Name:
Place: Seal:
Page 37 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
Annexure-I (1) MATERIAL (Monthly-Approx.) (Sample)- To be filled online.
S.No. Materials Name Brand Unit Qnty Rate per
unit Amount
1. Hard Broom Rod(Big) As per
sample Pcs Y30 T
2. Parking Broom As per
sample Pcs 20
3. Napthalene Ball Trishul Pkt. 20
4. Air Freshner Odonil Pcs 160
5. Air Neutilizer(300 Ml) Air Wick Pcs 70
6. Brasso (500 Ml) Brasso Bottles 10
7. Duster Floor Big As per
sample Pcs 200
8. S
Dius
zet er (check)
Big
As per
sample Pcs 100
9. Duster (Check) Small As per
sample Pcs 100
10. Duster (Yellow) Big As per
sample Pcs 100
11. Duster (Yellow) Small As per
sample Pcs 100
12. Soft Broom As per
sample Pcs 100
13. Hard Broom As per
sample Pcs 40
14. Liq. Soap (5Ltr.Can) Fem Can 30
15. Acid (5 Ltr. Can) Trishul Can 60
16. Spray Bottle (Empty) As per
sample Nos. 15
17. Colin Dispenser (Empty) As per
sample Nos. 30
18. Detergent Bar Vim Pcs 15
19. Liquid Soap Pump 500
ml. As per
sample Pcs 120
20. Hand Soap Cake Dettol Pcs 100
21. 100Poli shGm (1. Kg
pack)
Mansion Kg. 1 Kg.
22. Hand Gloves As per
sample Pair 180
Page 38 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
23. Dust Pan National Pcs 40
24. Mosquito Spray Black Hit Pcs 80
25. P(500late fmorl.m)
Brush (Big Size)
As per
sample Nos. 15
26. Scrubber Big Scotch Pcs 160
Brite
27. Dust control set As per
sample Pcs 40
28. Washing Powder – Nirma Pkt. 80
29. 1M
-K
FG
o.l d Towel Daffodil Pkt. 300
30. STomilaeltl sRiozell (75
mtr.)
Daffodil Pcs 500
31. Urinal Cube A-One Pkt. 60
32. (400Wipe Gr Hmeas) vy National Set 20
33. DWuhtiyt e Phenyle 5 Thrissul Can 70
34. LRt-r2. C(5a nlt r. Can) Taski Can 32
35. R-3 (5 ltr. Can) Taski Can 05
36. R-4 (5 ltr. Can) Taski Can 10
37. D-7 (5 ltr. Can) Taski Can 05
38. R-5 (5 ltr. Can) Taski Can 30
39. R-6 (5 ltr. Can) Taski Can 36
40. Dust Bin (small size)
As per
sample Pcs 20
41. Vacuum Pump As per
sample Pcs 10
42. Glass Cleaner- Colin Bottles 60
43. 500Dust mBli.n (Big size)
As per
sample Pcs 10
44. Caddy Basket As per
sample Pcs 05
45. Wet Mops As per
sample Pcs 10
Page 39 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
46. Wet Mops (round) (for
Bath Room) As per
sample Pcs 10
47. Pest Control and
Rodents Control
treatment with material
& equipment
As per
sample Twice
Monthl y
01
48. Teepol ( 5 Ltr can) As per
sample Litre 10
49. Black phenyl(5 Litre
can) As per
sample Litre 20
50. T-20 Concentrate As per
sample Ltr. (05 ltr. 20
51. Harpic As per
sample Ltr. (05 ltr. 10
52. R-9 Taski As per
sample Ltr. (05 ltr. 10
53. Room freshener As per
sample Pcs. 70
54. Plastic Juna As per
sample Pcs. 50
55. Bleach Powder As per
sample Kg. 10
56. Finit (05 Ltr. Can) As per
sample Ltr. 15
57. Iron Patti As per
sample Pcs. 20
58. Bucket (15 Ltr.) As per
sample Nos. 10
59. Plastic Mug (1 Ltr.) As per
sample Nos. 15
60. Toilet Brush (Hokey) As per
sample Nos. 10
61. Toilet Brush (Round) As per
sample Nos. 20
62. Toilet Pump (Bouch) As per
sample Nos. 10
63. Garbage Bag (Big-Blue) As per
sample Kg. 100
64. Garbage Bag (SmallBlue) As per
sample Kg. 100
65. Garbage Bag
(BigYellow) As per
BMW rules
As per
sample Kg. 100
66. Garbage Bag
(SmallYellow) As per
BMW rules
As per
sample Kg. 100
Page 40 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
67. Garbage Bag (Big-Red) As
per BMW rules As per
sample Kg. 100
68. Garbage Bag (Small- Red) As per BMW rules
As per
sample Kg. 100
69. Garbage Bag (BigGreen) As per
sample Kg. 100
70. Garbage Bag
(SmallGreen) As per
sample Kg. 100
71 Gum Boots As per
sample Pairs 20
TOTAL AMOUNT
Rate of material shall be inclusive of GST, other taxes, duties, service charges, transportation, etc.
Signature of Owner/Managing Partner/Director
Date: Name:
Place: Seal:
Page 41 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
Annexure-I (2)
LIST OF EQUIPMENTS, TOOLS, & TACKELS
S.N o.
Description Minimum
Number of
machines
Rent per unit per
month Monthly Rent Annual Rent
1 Scrubbing Machine 4
. 2
Wet/Dry Vacuum Cleaner 6
.3 Ride-on machine 2
.4 Single Disk 2
.5 Wringler Trolley 4
6 Jet Spray/High Pressure jet 2
.7 Glass Cleaner Kit 2
.8 Caddy Basket 16
9.
. Wet Floor Signage Board 20
Total Amount
Rent shall be inclusive of GST, other taxes, duties, service charges, transportation, loading/unloading,
conveyance etc.
Signature of Owner/Managing Partner/Director
Date: Name:
Place: Seal:
Page 42 of 42
(Instructions read and complied/Terms and Conditions Accepted) (Sign and seal of Bidder)
Annexure-J
DECLARATION
1. I, ____________________________ Son Daughter of Shri_______________
Proprietor/Partner/Director / Authorized Signatory of _________________ am competent to
sign this declaration and execute this tender document;
2. I have carefully read and understood all the terms and conditions of the tender and hereby
convey my acceptance of the same.
3. The information / documents furnished along with the above application are true and
authentic to the best of my knowledge and belief. I / we, am / are well aware of the fact that
furnishing of any false information / fabricated document would lead to rejection of my
tender at any stage besides liabilities towards prosecution under appropriate law.
4. I have apprised myself fully about the job to be done during the currency of period of
agreement and also acknowledge to bear the consequences of non-performance or
deficiencies in services on my part.
5. Company/firm has done in past satisfactory/disciplined work and not blacklisted in past by
any client.
Signature of Owner/Managing Partner/Director
Date: Full Name:
Place: Company's Seal:
N.B.: The above declaration on the letter head of agency, duly signed and sealed, should be
enclosed with Technical Bid.