implementing safe working practices during shaft construction__tunnels__bts

44
7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 1/44  Implementing safe working practices during shaft construction  A London Underground guidance document produced in conjunction with: BAM, Bechtel, Costain, Dragados, Ferrovial, Laing O’Rourke, and Taylor Woodrow

Upload: heidyhelmy

Post on 13-Apr-2018

227 views

Category:

Documents


0 download

TRANSCRIPT

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 1/44

 

Implementing safe working

practices during shaft construction

 A London Underground guidance document produced in

conjunction with:

BAM, Bechtel, Costain, Dragados, Ferrovial, Laing O’Rourke, and Taylor Woodrow

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 2/44

2 | P a g e  

Shaft Safety Guidance ForewordThis shaft safety guidance document is a ‘must read’ for all teams involved

with constructing shafts; for design teams in the early phases of the project

right through to foremen operating the logistics on a daily basis above and

within the shaft.

Here’s why London Underground wants you to read and use this guide:

TfL Vision and Values

Transport for London (TfL) is committed to a vision of:

‘Everyone home safe and healthy every day’.

In the Capital Programmes Directorate (CPD), we will

contribute to this achievement by safely delivering one ofEurope’s largest capital programmes, while continuing to reliably and safely keep

four million passengers a day moving.

The focus of our first three-year strategy is establishing the systems and behaviours

that we need to effectively manage the health, safety and environmental (HSE)

aspects of project delivery, the day- to-day health and safety of our staff and our

impact on the environment.

David Waboso

Director of Capital Programmes

Improving Shaft Safety

The Stations Capacity Programme encompasses the major

projects to add additional capacity to key stations in the centre of

London.

Tunnelling and therefore shafts are a critical part of the work at

each station and there are often significant constraints on the

shaft location, size and logistics due to neighbouring properties and the roadnetwork.

It is important that each project considers these constraints, from the early feasibility

stages, to ensure that TWA powers and property strategies provide adequate space

and access to create a safe working site focussed around the shafts.

Please take time to read these guidelines to make working in and near shafts even

safer in the future.

Ralph Freeston

Head of Stations Capacity Programme

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 3/44

3 | P a g e  

Contents

Shaft Safety Guidance Foreword ............................................................................... 2 

TfL Vision and Values .......................................................................................... 2 

Improving Shaft Safety ........................................................................................ 2 

Document aims ....................................................................................................... 4 

Section 1 - Planning for shaft safety ....................................................................... 5 

Section 2 - People and their behaviours ................................................................. 8  

Section 3 - Processes and procedures ................................................................. 11 

Section 4 – Plant, services and materials ............................................................. 13 

Conclusion ............................................................................................................ 18 

 Acknowledgements ............................................................................................... 18 

 Appendix A – Examples of above ground layout for shaft sites ............................ 19 

 Appendix B – Examples of internal shaft layout and environments ....................... 27 

 Appendix C - List of other useful documentation and guidance ............................ 36 

 Appendix D - List of considerations with existing guidance and standards ........... 37 

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 4/44

4 | P a g e  

Document aims

The following guidance document has been produced by London Underground in

response to a number of incidents in and around shafts. All health and safety

incidents on construction projects are unacceptable and preventable. This document

captures and promotes construction best practice found on major construction sites

to improve the industry’s health and safety performance.

This document does not replace existing regulations and standards, nor is it an

exhaustive reference. Rather, it aims to complement the existing regulations and

offer guidance and support where applicable. The document was produced through

a number of working group meetings, utilising shaft sinking and tunnelling expertise

from BAM, Bechtel, Costain, Dragados, Ferrovial, Laing O’Rourke, and Taylor

Woodrow.

The report has been split into 4 key sections:

  Planning

  People

  Processes

  Plant

Each section is written based on the working group outputs and recommendations.

Examples of various site and shaft conditions/layouts as well as a detailed checklist

can be found in the appendix.

This document aims to promote the health and wellbeing of all construction related

activities and workers through knowledge sharing and collaboration.

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 5/44

5 | P a g e  

Section 1 - Planning for shaft safety

The following section relates to the planning of any shaft or tunnel related works. It

specifically identifies factors that can influence and affect the entire works early in

the project lifecycle. Collaboration with all the involved parties is essential.

Design

During the design of a project it is vital that all parties are engaged and consulted as

much as possible. Some key considerations during the design phase are:

  Consider buildability – especially for lifting, access and temporary works

  Select shaft locations carefully – involve the construction team

  Maximise your space

  Shafts must be sized appropriately from top to bottom, including above

ground structures  Capture any learning before people leave a project

  Design for all stages of the shaft lifecycle

Procurement

Using the supply chain offers essential, in-depth expertise in a variety of areas. We

recommend the following:

  Minimise interfaces where possible

  Choose and involve suppliers early, selecting on the quality of past

performance and their approach to the project, not price

  Involve the supply chain when producing tender documentation

Construction

Planning for construction is as important as planning for the final operations and the

following considerations should be assessed:

  A robust list of construction requirements should be produced

  Size shafts based on the greater of the permanent and temporaryconstruction scenarios

  Size the shaft in its construction phase based on maximum lift size, temporary

services and access requirements

  Engage with specialists, suppliers and stakeholders early

Space/Layout

Ensuring the site layout around the shaft is planned early and effectively can be the

difference between a productive or a dangerous workplace. How you use the space

is more important than how much you have. The following should be considered:

  Use 4D modelling to visualise site requirements, size and layout

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 6/44

6 | P a g e  

  Key operations that drive layout are:

- Removal of excavated material

- Location and type of any lifting and lifting equipment

- Excavated material skip and bin size

- Providing 2 means of personnel access/egress

  Storage and laydown requirements for materials and associated equipment

Logistics and access

Take time to review the logistics of the site, especially the removal of excavated

material. Consider the following:

  Which delivery and removal option for excavated material impacts the local

transport system the least

  The type of shaft construction dictates the logistics (pre-cast rings, SCL, piled

or D-wall)

  Segregation of pedestrian and vehicular access is essential, including internal

shaft vertical segregation

  Access road design for number of vehicle movements per hour

  Consider urban vs. rural environmental differences

Temporary Works

Temporary works should be planned early to reduce spatial and time impacts:

  Carefully schedule temporary works on a register and keep updated

  Planning of temporary works is as important as the permanent works  Allow enough time to plan and check temporary works thoroughly

  Which temporary works designs need to be checked independently

  Involve the operations team in the selection of temporary works

Ground conditions

The site ground conditions will determine a number of factors on site, including sizing

plant, shaft construction technique etc. Consider the following:

  Complete a thorough ground investigation of the site area and review how the

findings could affect the build sequence

Duration

Factors affected by the duration of the project, or that could directly impact the

duration are:

  The more planning time the better

  Consider duration of temporary state elements, i.e. how long does the shaft

rely on just the primary lining

  Ground movements (settlement) vs. time, may dictate overall durations

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 7/44

7 | P a g e  

Environment

The environmental impact of a project can be reduced if it is planned for correctly.

Consider the following:

  Noise, dust and light considerations and the use of a shaft top building

  Conduct local flood risk analysis and mitigation measures

  Consider neighbours and residents

  Engage with Local Authorities early, build up trust and relationships

Risk assessment

Risk assessments are a legal requirement and should not be rushed. They require

input at every stage:

  Planning stage requires high level RA to include construction period

  Buildability checks to be completed by contractor and end user  Consider a Hazard and Operability study (HAZOP)

  Need to consider and plan for catastrophic failures, such as the bow-tie

model

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 8/44

8 | P a g e  

Section 2 - People and their behaviours

This section will review the people selected for projects and how their behaviours

can affect a site positively. People are a project’s most important and valuable

resource and need to be selected and trained carefully. Behaviours are often led

from the top down, so the behaviours of the project’s leadership team should be very

carefully considered. This includes the behaviours of the client.

Behaviours

There are more incidents of items falling down a shaft than there are from a

structure. Working in and around a shaft always involves working at height.

However, the workforce does not always realise this. Recognising this is key to

maintaining a safe worksite.

We can help deter negative behaviours on site by:

  Setting site expectations early and consistently

  Repetitive work causes normalisation and a reduced awareness of hazards

  Positively reinforce desired behaviours and apply consequences to negative

behaviours

  Frequently asking the operatives on site to provide solutions to problems will

gain buy-in, particularly if they receive feedback on their contributions

Other factors that may drive behaviours on site include:

  Very low chances of incidents occurring cause reduced vigilance

  Inadequate supervision on site causes a slippery slope

  Investigate near-miss trends on other projects to identify negative behaviours

When selecting staff, it is important to understand what motivates that particular

group of people and the associated leader. People from different geographical

backgrounds may have experienced different standards of construction

Leadership and Management

The management and leadership teams maintain the safe work culture. Thefollowing points note key leadership styles that should be adopted:

  Strong, experienced, visible leadership and management team

  Use simple and effective communication

  Plan the site behaviour through systems and manager buy-in

  Monitor workforce and production regularly

  Delegate responsibility e.g. allocate owners of site areas

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 9/44

9 | P a g e  

Clients

It is not just the main contractor and suppliers which can have an effect on the

behaviours on site. Client buy-in and monitoring will also help drive these

behaviours:

  Clients need to show buy-in to health and safety

  Clients need to collaborate and monitor performance

  Client to set high standards

  Client setting and monitoring of KPI’s and safety standards

Fatigue

Working on a construction project can be tiring, especially where shift working is

required. The following recommendations have been made based on data around

shift patterns:

  Shift patterns should be carefully selected with the aim of minimising fatigue

  The workforce may request tiring shift patterns to earn more money

  Monitor the fatigue of the workforce through productivity and near misses

  Prepare a fatigue management report prior to shift works being implemented

Visitors

Visitors on site are a hazard. They are new to the worksite, and sometimes come

from backgrounds that are predominantly off-site. However, visiting sites is a good

way to share knowledge and pass on learning. Consider:

  Limit the number of non-essential visitors

  Eliminate visitors from dangerous situations by timing visits around activities

  Have separate rules for visitors

Training and experience

It is crucial that the roles and responsibilities for the various positions on site are

established early and that staff meet these criteria with their experience. The

following points give guidance when taking on new personnel:

  Set training and experienced standards early and verify staff have them

  Use a probation period for new staff

  Provide on-site training

  Plan for the fact that there may be resource shortages

  New team members can affect the performance of existing team members

When hiring for educated roles, such as Engineers or Surveyors, a specific set of

educational and experience requirements should be set out prior to hiring.

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 10/44

10 | P a g e  

Complacency

One of the main causes of behaviour types or changes to a particular behaviour is

complacency. People will inherently change to an easier approach to a job. Predict

and plan for this behaviour

TeamsTeams are the driving force behind any project. It is teams, that will complete the

works on site, and management teams that will monitor performance and finance:

  Good teams require a number of different personality types and take time to

form

  Good leaders are essential

  Link bonus to whole team performance, including safety and quality

  Provide regular feedback to teams 

Continuous improvement

People resist change, especially in construction. Ways to help minimise the time

required to change a behaviour or work pattern are:

  Keep new procedures simple

  Tell the workforce how new methods will benefit them

  Use regular reinforcement after a change is implemented

  Involve the workers when coming up with new working patterns

  Document and scrutinise changes to the same level of as the original plan

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 11/44

11 | P a g e  

Section 3 - Processes and procedures

This section is not in itself a procedure, nor does it stipulate procedures that should

be followed. It aims to support information, applicable standards and other guidance

documents, procedures and processes which already exist for the safe planning and

delivery of shafts.

 Any processes and procedures that are in place should aid the works and should not

be there for the sake of it.

Development of Procedures and Policies

 A wide variety of procedures and processes will need to be followed to ensure shafts

are designed, constructed and operated safely. These documents should be written

in clear, unambiguous and easily understood language which describes:

  Who - the definition of roles and responsibilities 

  What - the requirements to be met and forms and processes to be used 

  When - timescales and/or order in which actions need to happen 

  Where - location specific requirements 

  Why - establish the required outcome 

 Adherence to procedures will assist in delivering a safe and functional design with

appropriate safe systems of work developed in a controlled, methodical and

considered manner:

  Consider the design and construction standards that are applicable to widerconstruction activities (lifting, working at height, fire evacuation, etc.)

  Review these standards to reflect unique requirements within shafts

  Develop bespoke standards, where necessary, specifically for works

associated with shafts

Existing Guidance

When developing processes and procedures for the safe design and construction of

shafts, the existing guidance documents should be reviewed first. See appendix C.

Optioneering and Technique selection Consideration should to be given to the nature of the shaft, its intended final use

(e.g. ventilation, permanent (lift) access, supply riser etc.) and its proposed method

of construction.

Shaft Types 

 A number of shaft types and construction methodologies exist which will require

different procedures. These include but are not limited to:

  SCL shafts

  Segmental lined – underpinned

  Segmental lined – jacked

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 12/44

12 | P a g e  

  Sheet piled

  Diaphragm wall

  Secant piled

  Contiguous pile

  Drill and blast, rock faced

People

Roles and responsibilities for the various positions as defined by procedures are

established early, allowing sufficient time to ensure that staff meet the required

competencies. The following points give guidance on criteria to look for when

assigning responsibilities and taking on new personnel:

  Competence of personnel, verified

  Provide on the job training

  Clear definition of roles and responsibilities  Organisational structure and lines of reporting

Other procedures

Logistics:

Multiple operations and site constraints may include:

  Shafts close to infrastructure

  Site constraints – used to create diagrams, plans and photos etc.

  Site conditions – ground conditions, ground water, weather, ground conditions

  Multiple operations

The below table details a number of final considerations and project chronologies as

an aide memoir:

Chronology

Design/planning and space-proofing

Ground investigation

3rd party considerationsTW’s requirements Logistics/deliveries/ access routes and vehicles falling down shaft

LiftingPeople, access and emergency preparednessBackfill and removalFit-outEdge protection

Maintenance and monitoring

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 13/44

13 | P a g e  

Section 4 – Plant, services and materials

 As a matter of course, a great deal of consideration is given to the selection of

specialist plant items and safety systems in order to construct and use tunnels.

However, the same level of consideration is not always applied when a shaft is to be

constructed and used. This apparent discrepancy is largely without justification, as

many of the conditions encountered in shafts and tunnels are fundamentally similar.

This section of the document is intended to assist those persons tasked with

selection of plant and equipment that will be used during the construction and

operation of shafts.

Pre-construction planning

 A number of factors should be considered when selecting plant and equipment that

will be used to construct and operate a shaft. These factors should include, but not

be limited to:

  The method of construction to be used

  The size of the shaft

  Ground conditions

  Shaft use throughout its lifecycle

Each shaft should be treated as largely unique. As such, the plant and equipment

used to construct and operate each shaft should be comprehensively and carefully

considered – selecting plant and equipment based on its availability should be

avoided. Similarly, experience or knowledge of plant and equipment being used

under similar circumstances should not entirely negate the requirement for a

thorough process of selection.

Power supply

Most shafts will require lighting and ventilation and some will require pumping to

remove ground water. Additionally a number of modern plant items used in shaft and

tunnel construction are electrically powered. The provision of sufficient electrical

power to a shaft site should consider:

  Identify all power requirements plus emergency contingency 

  The cable route and voltage drop 

  Prevention of cable damage

  Accessibility for maintenance and commissioning

Ventilation

Shafts are generally considered ‘confined spaces’ when their depth is equal to or

exceeds their diameter, and so ventilation should be provided at an early stage

during construction. When selecting an appropriate sized ventilation system,

consider:

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 14/44

14 | P a g e  

  The minimum volume of fresh air for both gases and dust (see BS 6164) 

  Selecting the most efficient system on a whole life basis 

  Ventilation duct restraints and support structure

  SCL methods produce high quantities of dust

  Other dust suppression methods, including wetting down

  Efficient ventilation must be designed, it doesn’t just happen 

Other services – Water-lines, pump-lines, concrete / grout lines

 As with ventilation duct, similar considerations should be made, including:

  Service requirements including back-up and fixings

  Procure pipelines from a single-source to ensure joints fit 

  Consider pressure build-up, including that caused by blockages 

  Specialist dewater pumps to cope with high head pressures 

  Periodic maintenance, especially to concrete lines which wear out   Maintenance access 

Access

There are no hard-and-fast rules when selecting access and egress arrangements

for shaft construction and use. BS6164 advises that two means of access and

egress should be provided for shaft work, but then these means may be selected

from any combination of systems.

Options for man access include:

  Fixed stairs (purpose made Haki or similar)

  Hoists (Alimak or similar)

  Ladder bay

  Crane basket (purpose made)

  Davit arm (usually a last resort)

The following considerations have been made:

  How much space is available? 

  Fixed access systems take up considerable room

  Fixed elevator systems are less practical during shaft construction 

Crane attached man-riding systems are considered a reasonable compromise

between versatility and suitability. However, a smaller stand-by crane should be kept

on site for use in an emergency evacuation situation. 6-monthly LOLER checks will

be required on any equipment used to lift people.

Other factors to consider include:

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 15/44

15 | P a g e  

  The depth of the shaft

  Access or egress provision for emergency escape 

  The worst case scenario must be adequately planned for

Whatever combination of access arrangements are adopted, it is essential that

provision for accessing the shaft base with a stretcher is made, should the

evacuation of a stricken individual be required.

Crane selection and lifting

Shaft sinking, irrespective of method, is crane intensive. Materials must be frequently

lowered into the shaft, and arising must be removed. Additionally, plant used during

the construction process may be subject to many cycles of lowering in and raising

out of the shaft.

Of the available options of mobile, crawler, tower or gantry cranes, no one choice is

particularly better than any other, although it should be noted that, because of the

repetitive nature of servicing a shaft, a fixed gantry system is often most efficient.

Gantry cranes can run on ground level rails (Goliath), high level rails (overhead) or a

combination of the two (semi-Goliath). 

Crane selection for shaft sinking should be subject to the same process as when

cranes are selected for any other lifting operations. Agree this early and factor this

into construction:

  Consider the full range of lifts to be performed 

  How much space is available on site

  What are the ground conditions of the site

  Are there ‘proximity hazards’, such as buried services, overhead power lines

or adjacent tall buildings in the local area

  Consider the accessibility of the site and the logistics involved in crane

delivery

Lifting is one of the most frequent activities during shaft construction and use, and

yet comes with high inherent risk. The selection of an appropriate crane should bepart of the process of developing a comprehensive Lifting Plan. Whilst a large

number of the lifts associated with shaft construction and use will be repetitive or

similar, the Lifting plan should, where possible, avoid generalisations and all

eventualities should be accounted for.

 Activities that are often overlooked during the production of Lift Plans include the

unloading of equipment or materials from trailers. Consideration of the lifting

accessories used during shaft construction should include:

  Specialist and standard lifting equipment

  Inspections

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 16/44

16 | P a g e  

  Additional training requirements

  The design and manufacture of any bespoke lifting equipment

  Creating and maintaining a register of lifts

Communication between the lift team and personnel within the shaft is essential to

ensure the safety of lifting operations. Typically the crane operator cannot see into

the shaft. Two way radio communications should be assigned to a dedicated lifting

channel to avoid interference. Clear instructions should be established prior to lifts

taking place using a standard set of terms to avoid confusion. CCTV systems may

also be employed but can sometimes be a source of distraction to the crane

operator.

When working in smaller shafts, consider:

  Some lifting operations will be carried out whilst personnel are within the shaft

  Exclusion zones may not be available  Securing of loose loads must be taken more seriously

  Muck skips should not be over-filled

When lifting small tools to the shaft, blue rope is not suitable. The provision of a

small winch at the pit-top, either manually operated or powered, should be

considered. Remember that using blue rope to lower a gas monitor into a shaft is an

invitation to use it for other, potentially disastrous, objects.

Atmospheric monitoring and fire safety equipment

 Atmosphere monitoring and fire safety equipment in shafts should be provided at a

similar point in time as ventilation. The type of systems utilised will be dependent

once again on the whole-life cycle of the shaft:

  Consider monitoring the atmosphere during the shaft construction phase and

how it will be protected 

  Fixed systems can be installed once the shaft has reached its full depth

  SCADA systems can provide continuous recording of data which can be

useful for analysing the presence of semi-toxic atmospheres

  Installing multiple systems at set distances 

During shaft construction the minimum fire safety equipment that should be provided

is:

  A selection of fire extinguishers, suitable for the types of fire that may occur,

at the base of the shaft whilst personnel are working within.

  A portable structure to contain the extinguishers that can be raised or lowered

by the crane 

 A fixed sprinkler or inundation system may also be appropriate in some situations,and their suitability should be assessed on an individual basis.

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 17/44

17 | P a g e  

Plant and equipment that is to be used for tunnelling work is, generally, without

exception required to be fitted with fire safety features. These features include:

  Automatic fire suppression in engine bays 

  Non-flammable oils and fluids 

  Incombustible tyres and other parts that are exposed to heat 

  Anti-static protection 

We also note that excavators commonly used to excavate shafts are usually

machines that are equipped for carrying out work on surface. Consideration must be

given to fire safety features for both shaft and tunnel plant.

Excavation and support equipment selection

The list of equipment that may be used in shaft construction is extensive. Certain

methods require specialist items, such as the SCL method, and all shaft

constructions require a means to excavate, shift and remove muck. When selecting

plant consider sizes, weights, performance capabilities and experience or user

preference.

 All plant items should be selected from the available range by a process of careful

appraisal, with the following being amongst the considerations being made:

  The size of the plant item relative to the shaft

  Room to manoeuvre and operate, and will not present a risk to personnel

  The weight of the plant item and associated craneage requirements

  Lifting points on plant items

Plant and Personnel Separation

Wherever possible, plant and construction personnel should be separated by a

physical barrier. Where this is not possible consideration must be given to fitting

devices which make the plant operator aware of people around the machine. Rear

view mirrors are essential but rear facing CCTV and proximity sensors are also

available. This is always an important consideration but even more so in the confinesof a shaft.

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 18/44

18 | P a g e  

Conclusion

This guidance document is intended to highlight key considerations that should be

taken into account when working in and around shafts. It does not aim to be an

exhaustive list or an instruction manual, but rather to complement the existing

regulations in place. The document has focussed on 4 key areas: Planning, People,

Processes and Plant.

It should be stressed that every shaft environment is different, with an array of

methodologies, equipment, locations and people working on them. Care must be

taken to ascertain the risks inherent to each individual shaft and the associated

mitigation measures.

Further information and guidance can be found in:

-  Appendix A, Examples of site layouts with shafts

-  Appendix B, Examples of confined shaft layouts

-  Appendix C, List of other useful documentation and guidance

-  Appendix D, List of considerations with existing guidance and standards

Acknowledgements

London Underground would like to thank the following companies for helping to

create this guidance document:

  BAM

  Bechtel

  Costain

  Dragados

  Ferrovial

  Laing O’Rourke 

  Taylor Woodrow

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 19/44

19 | P a g e  

Appendix A – Examples of above ground layout for shaft sites

Figure 1 - Victoria Station Upgrade site layout

Figure 2 - Victoria Station Upgrade site layout alternate time-lapse view

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 20/44

20 | P a g e  

Figure 3 - Victoria Station Upgrade site layout and prop requirements

Figure 4 - Landsec Nove site layout, adjacent to Victoria Station Upgrade project

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 21/44

21 | P a g e  

Figure 5 – Crossrail/LUL Tottenham Court road site layout

Figure 6 – Crossrail/LUL Tottenham Court road site layout alternate time-lapse view

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 22/44

22 | P a g e  

Figure 7 - Crossrail Farringdon site layout and surrounding buildings in close proximity

Figure 8 - C360 Mile End site layout during shaft works

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 23/44

23 | P a g e  

Figure 9 - C360 Mile End site layout during shaft works, alternate view

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 24/44

 24 | P a g e  

Figure 10 - C360 Mile End site layout prior to shaft works commencing  Figure 11 - Limmo Peninsular shaft 1 site layout 

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 25/44

25 | P a g e  

Figure 12 - Limmo peninsular shaft site layout alternate view

Figure 13 - C360 Mile End site layout, alternate view, prior to shaft works commencing

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 26/44

26 | P a g e  

Figure 14 - Stepney Green shaft site layout

Figure 15 - Stepney Green shaft site layout alternate view

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 27/44

27 | P a g e  

Appendix B – Examples of internal shaft layout and environments

Figure 16 - Fisher Street shaft showing excavation for underpinning of segmental lining

Figure 17 - C360 Eleanor Street second shaft with secondary lining applied

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 28/44

28 | P a g e  

Figure 18 - Crossrail Tottenham Court Road shaft internal layout, SCL adit

Figure 19 - Stepney Green shaft base slab works

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 29/44

29 | P a g e  

Figure 20 - Bond Street Station Upgrade shaft top prior to OSD construction

Figure 21 - Crossrail Tottenham Court Road shaft internal layout, during SCL works

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 30/44

 30 | P a g e  

Figure 23 - Limmo peninsular shaft 2 manrider accessFigure 22 - Crossrail Tottenham Court Road shaft internal layout, during SCLworks alternate view

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 31/44

31 | P a g e  

Figure 24 - Crossrail Tottenham Court Road shaft internal layout, duringRC works 

Figure 25 - Crossrail Tottenham Court Road shaft internal layout,post RC works 

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 32/44

32 | P a g e  

Figure 26- Bond Street Station Upgrade early shaft excavation

Figure 27 - Bond Street Station Upgrade shaft base concrete works

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 33/44

33 | P a g e  

Figure 28 - Bond Street Station Upgrade waterproof TAM injection

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 34/44

34 | P a g e  

Figure 29 - Bond Street Station Upgrade SCL works with Oruga SCL spraying robot

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 35/44

35 | P a g e  

Figure 30 - Bond Street Station Upgrade man-rider access

Figure 31 - C360 Eleanor Street temporary SCL shaft

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 36/44

36 | P a g e  

Appendix C - List of other useful documentation and guidance

  Construction (Design and Management) Regulations 2007/2015 (CDM)

  Occupation Health and Safety standard (OHSAS) 18001:2007

  Lifting Operations and Lifting Equipment Regulations (LOLER) 1998

  Provision and Use of Work Equipment Regulations (PUWER) 1998

  BS7121 - British Standard Code of Practice for the Safe Use of Cranes

  LU Manual of Good Practice G050

  CITIA C703

  BS 6164:2011 - Code of practice for health and safety in tunnelling in the

construction industry

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 37/44

37 | P a g e  

Appendix D - List of considerations with existing guidance and

standards

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 38/44

38 | P a g e  

Planning Design the build methodology and requirements? □

the location of the shaft and local environment? □

tried to maximise the space within the shaft and at ground level? □

sought out experience personnel to capture knowledge and experience? □

allowed sufficient time in the programme for planning? □

Procurement utilised the supply chain in the design? □

using only one contractor per area? □

chosen the suppliers early? □allowed plenty of lead time to procure the supply chain? □

all the procurement routes available? □

Construction all the construction requriements? □

all the activities and resource requirements? □

lifting, services and access requirements? □

tried to ensure shafts are bigger than 10m diameter? □

engaged with Specialist Suppliers? □

considered involving the site teams? □

space/layout involved the right people in the planning stage? □

made the best use of space provided? □

that less Space actually sharpens the mind? □

used 4D BIM for requirements? □

checked the shaft base layout for activities? □

that too much space at shaft top level can make things harder? □

that the layout on site is driven by: muck, plant and lifting? □conveyors do not generally suit SCL works? □

guide rai ls on shaft wall? □

muck skips versus conveyor methods? □

storage of materials? □

logistics that conveyor belts are suitable for long straight tunnels? □

that you could apply and push for full road closures? □

muck away and deliveries? □

using lorry holding areas? □

precast delivery vs. SCL? □

using one way traffic systems? □

reducing lorry movements through alternatives - such as boat or train? □

both day-to-day and emergency access and egress? □

that the type of shaft construction dictates the logistical requirements? □

planning for two types of site (SCL and segmental lining) in order to compare? □

 Access involved the health and safety team? □

segregated vehicles and pedestrians? □

urban vs. rural environments? □

pushed councils for more land take? □

a one way system? □

tried to minimise lorry movements on busy roads? □

Shaft construction what materials will be used? □

that changing from segmental to SCL part way through construction requires a new si te layout? □

planned for multiple shaft setups? □

that the speed of construction can reduce spatial requirements? □

that 24/7 or night shift works may require more storage capacity? □

ground conditions? □

confirming design details early? □

that the speed of construction is affected by material choice? □

that the crane selection is key and agreed this early? □Temporary works checked all elements of TW required? □

created a schedule of TW’s and kept it up to date? □

that stronger shafts without permanent props open more space? □

that the planning of TW's is as important as the permanent works? □

kept a register of all temporary operations? □

that clear space is required to allow time for thorough checking? □

that anything that is hanging or lowered requires TW's checks? □

involved the operations team? □

Lift plan and schedule that the crane choice affects shaft construction? □

created a register and plan for all lift types? □

Ground conditions ensured a ground investigation has been/will be completed? □

tha the client/developer should invest the time in the GI? □

reviewed the ground conditions? □

spent time understanding the GI reports? □

Duration the duration of the shaft temporary state? □

settlement vs. time? □

how long ground monitoring will be required for? □

that the number of vehicles per hour within the road design? □

rivers or rail for muck away and deliveries ? □

Check when

completeHave you/have you considered…..Topic

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 39/44

39 | P a g e  

Weather conditions snow, wind, rain etc? □

ground water and pumps? □

using covers vs. OSD and produced cost analysis? □

Lead in time using ECI procurement where possible? □

Environment noise, dust, light considerations? □

using covers to reduce dust and noise pollution? □

dust control? □

influential neighbours and residents? □

the option to place a lid on the shaft? □

engaged with local authorities early? □

Services  Alimak lifts vs. depth? □

the no. of people in shaft? □

the speed of escape and rescue? □

ventilation and extraction for all adits? □

that everything needs to be designed to fit the shaft? □

that a barrier between Alimak and crane is required? □

a man rider on its own needs to have 2 cranes to evacuate? □

ventilation is a minimum of 2 ducts (air in and out)? □

that clear space down a shaft is essential? □

early planning including specialists for services? □

Risk assesment that the planning stage requires a high level RA? □

buildability checks need to be completed by contractor and end user? □

produced a HAZOP? □

planned for catastrophic failure? □

 that the designer needs to carry out the shaft construction method and catastrophic risk assessment? □

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 40/44

40 | P a g e  

People Behaviours setting site expectations early? □

that repetitive work causes “normalising”? □

staggered and varied shift patterns? □

using reinforcement and punishment style consequences? □

agreed the consequences early in the management system? □

asked the operatives on site to provide solutions to gain buy-in? □

that reduced visibility of works causes complacency? □

that very low chances of incidents causes reduced vigilance? □that a lack of supervision on site causes a slippery slope? □

satellite sites typically have less supervision? □

used red/green light systems? □

that people are more aware in new environments? □

using stillages for lifting small items to prevent shortcuts? □

colour-coding lifts to determine final lay-down location? □

investigated any current near-miss trends on other projects? □

that strong, experienced leaders are required? □

gained the agreement needed from management team? □

that fewer rules but with better reinforcement is better? □

colour coding safe zones in the shaft bottom? □

taken time to educate the workforce fully of the rules and risks? □

simple, effective, well presented RAMS? □

measured performance regularly? □

predicting behaviours in advance and planning pre-emptive action to reinforce? □

that visibility of buy-in from senior management is important? □

that supervisors must remain visible to reduce behaviours? □

rotating managers through teams to keep things fresh? □

rotating banks-person positions (top and bottom)? □

using voting cards to check the knowledge of workforce? □

changing strategies to keep things fresh and prevent normalising? □

that the management should attend workforce briefings regularly, not just after a problem? □

allocated owners of dangerous areas? □

allocated deputies to cover holidays etc? □

that a lot of good workers are with companies. Agency staff are unknown? □

that in-house company staff are better than agency staff? □

set up regular leadership meetings to discuss safety issues and improvements? □

used independent assessors to check the quality, performance and experience of teams? □

Clients that clients should show buy-in by attending briefings and managerial meetings? □monitoring the contractor’s performance and ensuring all staff are trained to the correct level? □

that the contractor should own safety on site and the client should show buy-in as a minimum? □

that by collaborating and monitoring each other’s performance, a positive, reinforcing cycle can be created? □

set high standards for roles and responsibilities of personnel? □

Incentives that client focus and setting KPI’s can drive behaviours? □

that a lack of monitoring reduces effort? □

asked the client to be vigorous with monitoring? □

that monitoring drives behaviour? □

Fatigue that shift patterns should be selected based on the activities and location of the workforce? □

that the workforce may prefer tiring shift patterns as this offers financial bonus despite causing fatigue? □

fatigue monitoring? □

monitoring productivity levels and the number of near misses as these can indicate fatigue? □

explained monitoring activities to the workforce as they may assume it is about productivity? □

No change culture that people will embrace change provided that you can gain their buy-in? □

shown the workforce how new ways of work will benefit them? □

used regular reinforcement to ensure a new behaviour is adopted quickly? □

involved the workers when coming up with new working patterns to gain their buy-in? □

kept new procedures simple and not overcomplicate with lots of new rules? □

Visitors that too many untrained, non-essential visitors are bad? □

eliminating people from dangerous situations? □

having separate rules for visitors? □

timing visits around work activities? □

that all experience cards (CSCS) need to be checked; cards can be bought on the black market? □

that the experience of staff must be relevant? □

that there may be resource shortages? □

applied a normalising, or probation, period to all new workers on site? □

tha new graduates and apprentices should work with a more experienced supervisor? □

you may need to train people who lack experience? □

providing on-the-job training for skills gaps?□giving new starters on-site experience before being allowed to use equipment? □

introducing a new person may affect current team? □

that a change of management or new supervisors may reduce team performance? □

ensured that ongoing training, education and experience is provided for the workforce? □

 

Leadership and

management

Training and

experience

Topic Have you/have you considered…..Check when

complete

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 41/44

41 | P a g e  

Geographical that everyone will have different experiences and hence different standards of construction? □

Education that when hiring for educated roles, set out educational and experience requirements before hiring? □

Complacency predicted and planned for complacent behaviour? □

taken time to plan the culture of the site before works commence? □

Teams that good teams take time to form and require a number of different personality types? □

that good people can be affected by one bad person in a team? □

that leaders that own, lead and take feedback are crucial? □

allowed time to form teams and plan for this? □

linked bonus to whole team performance? □

provided regular feedback to teams? □

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 42/44

42 | P a g e  

Processes Developing procedures Who – is it for? □

What - is required? □

Where - is its location? □

When – will it happen? □

Why – is it happening? □

generic standards that are applicable to wider construction activities? □

reviewed standards in lieu of unique requirements within shafts? □developed bespoke procedures,specifically for works associated with shafts? □

Existing guidance reviewed existing guidance documents for shafts first? □

Optioneering and method the purpose of the shaft and method of construction? □

Shaft types SCL shafts? □

segmental lined – underpinned? □

segmental lined – jacked? □

sheet piled? □

diaphragm wall? □

secant piled? □

contiguous pile? □

drill and blast, rock faced? □

People operative competence? □

management competence? □

competence to be considered as training, experience, knowledge and behaviours? □

that the experience of staff must be relevant? □

that you may need to train people who lack experience? □

that all CSCS and other experience cards need to be checked and validated? □

provided on-the-job training for skills gaps? □

probationary on-site experience before being allowed to use equipment? □

produced a clear definition of the organisation and the roles and responsibilities? □

organisational structure and lines of reporting? □

Other procedures shafts close to LU infrastructure? □

shafts working in and around other infrastructure (live roads)? □

any site constraints and created diagrams, plans and photos etc from these? □

site conditions – ground conditions, ground water, weather, ground conditions? □multiple operations and constrained sites? □

Topic Have you/have you considered…..Check when

complete

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 43/44

43 | P a g e  

Plant Pre-construction planning the method of construction and ground support system? □

any plant requirements for methodology? □

that underpinning is crane-intensive, whereas SCL methods require specialist equipment? □

that shafts in hard rock may be excavated by drill and blast? □

that the diameter or size of the shaft, including equipment fit and safety of personnel? □

the depth of the shaft? □

any known or anticipated ground conditions? □

contingency for unexpected ground conditions including water ingress? □

the whole life cycle of the shaft? □

the number of activities required to develop a shaft? □

the shaft’s intended use? □

constructing permanent or secondary linings? □

any post-construction fit-out requirements? □

that every site is unique, and that cutting and pasting from other projects will not necessarily work? □

Power supply lighting and ventilation? □

any contingency for items that may be required during un-planned events? □

the effects of voltage drop over long distances? □

prevention of cable damage? □

cable routes, including the use of buried cables (preferred) or goal posts (not preferred)? □

cable tray systems ? □

routing cables near to fixed access installations? □

a back-up power supply? □

that back-up equipment should allow safety critical equipment to run simultaneously? □

the exposure rating to potential damage? □

regular testing of power supplies? □

Ventilation that big fans can be run at a low frequency when less ventilation is required, not possible with small fans? □

unavoidable losses of ventilation performance over long distances? □

the combined effects of dust, diesel engine power and number of personnel working? □

the minimum volume of fresh air and air flow (see BS 6164)? □

the location of a forced ventilation fan to ensure the cleanest air possible? □

that high quality ventilation ducts will last longer? □

maintenance of ventilation - note: higher quality ducts require less maintenance? □

pressure loss on duct routes caused by curves and bends? □

ventilation restraint and support structure including the start-up pressure surge of the fan? □

the risk of carrying out repairs to ventilation duct at height? □

the risk of the ventilation support system failing? □

the provision of de-dusting capability in the ventilation design? □

that SCL methods produce high quantities of dust? □

that dust presents health risks to the workforce, and may breach environmental legislation? □

water based dust-suppression systems (can make for very wet working conditions)? □

extraction based de-dusting systems (require sufficient space)? □

that filter units will also require regular and intensive maintenance? □

Other services temporary works for fixings and fittings? □

maintenance and inspection? □

procuring pipelines from a single-source to ensure joints fit? □

nominal pressure, as well as build-up caused by blockages? □

safe pressure relief valves? □

cleaning of pipelines? □

monitoring pipe thickness over time, caused by material friction? □

specialist dewater pumps to cope with high head pressures? □

checked pumping equipment is fit for purpose? □

standby pumps in higher risk areas? □

 Access 2 means of access? □

how much space is available? □

that fixed access systems take up considerable room? □

that fixed elevator systems are less practical during shaft construction? □

that man-riding systems require a standby crane and 6 month LOLER checks? □

the depth of the shaft? □

access or egress provision for emergency escape? □

that the worst case scenario must be adequately planned for? □

access for stretcher? □

 

Topic Have you/have you considered…..Check when

complete

7/25/2019 Implementing Safe Working Practices During Shaft Construction__Tunnels__BTS

http://slidepdf.com/reader/full/implementing-safe-working-practices-during-shaft-constructiontunnelsbts 44/44

Crane selection the length of rope required, how many falls and the additional weight of the rope when sizing the crane? □

how much space is available on site, and is there time to design a bespoke gantry crane? □

the ground conditions of the site? □

if there are there buried services, overhead power lines, adjacent tall buildings in the local area etc? □

the accessibility of the site and the logistics involved in crane delivery? □

developed a comprehensive lift plan? □

unloading of deliveries? □

any specialist and standard lifting equipment? □

inspections? □

any additional training requirements? □

spreader beams for the lifting of plant and equipment? □

the design and manufacture of any bespoke lifting equipment? □

communications within lift team? □

that some lifting operations will be carried out whilst personnel are within the shaft? □

that exclusion zones may not be available (e.g. small shafts)? □

that the securing of loose loads must be taken more seriously in small shafts? □

that muck skips should not be over-filled? □

using winches for lowering small tools? □

 Atmosphere he whole life cycle of shaft? □

gas monitoring during the shaft construction phase and how the monitors will be protected? □

that fixed systems can be installed once the shaft has reached its full depth? □

SCADA systems record data which can be used to analyse the presence of semi-toxic gas? □

installing multiple systems at set distances? □

a selection of relevant fire extinguishers at the base of the shaft is minimum? □

that a portable structure to contain the extinguishers can be raised or lowered by the crane? □

sprinkler systems? □

that surface excavators are not typically fitted with fire safety features? □

automatic fire suppression in engine bays? □

using non-flammable oils and fluids? □

incombustible tyres and other parts that are exposed to heat? □

Excavation equipment the size of the plant item relative to the shaft? □

room to manoeuvre and operate, and will not present a risk to personnel? □

the weight of the plant item and associated craneage requirements? □

lifting points on plant items? □