implementing abc on bridge replacement and rehabilitation

70
Implementing ABC on Bridge Replacement and Rehabilitation Projects Bala Sivakumar T.H.E. Conference 2016

Upload: others

Post on 10-Jun-2022

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Implementing ABC on Bridge Replacement and Rehabilitation

Implementing ABC on Bridge Replacement andRehabilitation Projects Bala Sivakumar

T.H.E. Conference 2016

Page 2: Implementing ABC on Bridge Replacement and Rehabilitation

Outline

Introduction to ABC

ABC Technologies & Methods

Implementing Bridge Moves

ABC Rehab Projects

ABC Replacement

Projects

Implementing Prefab

Systems

Page 3: Implementing ABC on Bridge Replacement and Rehabilitation

What is ABC?

Page 4: Implementing ABC on Bridge Replacement and Rehabilitation

What is ABC?

Accelerated Bridge Construction (ABC)

ABC is bridge construction that uses innovative methods to

reduce mobility impacts when replacing/rehabilitating existing bridges.

ABC is a platform for innovation

Page 5: Implementing ABC on Bridge Replacement and Rehabilitation

Reasons for considering ABC include:• Heavily traveled route (high ADT)• Long or non-existent detours • Part-width construction is not a

preferred option

Reasons for ABC?

Cast-in-place construction is a sequential processABC allows work to be done in parallel – reduce schedule

Page 6: Implementing ABC on Bridge Replacement and Rehabilitation

Reduces disruption to

traffic

ABC Advantages

Safer; reduces exposure of workers and public

Better quality control due to prefabricated

elements

Reduced environmental

impacts

Page 7: Implementing ABC on Bridge Replacement and Rehabilitation

ABC Elements and Methods

ACCELERATED BRIDGE CONSTRUCTION

Prefabricated Elements &

Systems (PBES)

Accelerated Geo-tech Work

Rapid Demolition

Bridge Movement Technologies (SIBC /

SPMT)

Innovative Contracting

Page 8: Implementing ABC on Bridge Replacement and Rehabilitation

Time Metrics for ABC – Mobility Impact Time

TRAFFIC IMPACTS WITHIN

Tier 1 24 hours

Tier 2 3 days

Tier 3 2 weeks

Page 9: Implementing ABC on Bridge Replacement and Rehabilitation

ABC – National Perspective

• 2200 + ABC projects to date (2014)

• 43 states have used ABC (2014)

• Several states have ABC programs for statewide implementation

• ABC candidates are selected using a screening process

Page 10: Implementing ABC on Bridge Replacement and Rehabilitation

ABC Technologies

Page 11: Implementing ABC on Bridge Replacement and Rehabilitation

Full Depth Precast Deck Panels

Casting and curing decks is a slow process

Page 12: Implementing ABC on Bridge Replacement and Rehabilitation

Pre-decked beams• Concrete deck bulb tees• Concrete Deck double

tees

MODULAR CONCRETE SUPERSTRUCTURE SYSTEMS

Page 13: Implementing ABC on Bridge Replacement and Rehabilitation

Prestressed Deck Bulb Tee — NY Route 31

Page 14: Implementing ABC on Bridge Replacement and Rehabilitation

NJDOT Route 18 Bridge Over Route 1Weekend Replacement

MODULAR STEEL SUPERSTRUCTURE SYSTEMS

Page 15: Implementing ABC on Bridge Replacement and Rehabilitation

Prefabricated Abutment & Wingwalls

Page 16: Implementing ABC on Bridge Replacement and Rehabilitation

• Build the entire bridge superstructure and then move it into place in a few hours.

• Bridge movement technologies:– Slide-In Bridge Construction (SIBC)– Self-Propelled Modular Transporters (SPMT)– Float-In– Launching / Skidding

Bridge Movement Technologies

Page 17: Implementing ABC on Bridge Replacement and Rehabilitation

3 June 2008 17

Roll-Out l Roll-In Hood Canal Bridge, WSDOT

Before During After

Page 18: Implementing ABC on Bridge Replacement and Rehabilitation

Roll-Out/Roll-In New York City Van Wyck Expressway

Page 19: Implementing ABC on Bridge Replacement and Rehabilitation

Push/pull hydraulic jacks

Pulling with• strand jacks• power winch

Bridge Slide Systems

Page 20: Implementing ABC on Bridge Replacement and Rehabilitation

Roller BearingsCoefficient of Friction: 5% of Vertical Load

Teflon-Coated Neoprene Bearing PadsCoefficient of Friction: 10% of Vertical Load

Slide Bearings

Page 21: Implementing ABC on Bridge Replacement and Rehabilitation

Bridge Movement – Float-In

Page 22: Implementing ABC on Bridge Replacement and Rehabilitation

Self Propelled Modular Transporter (SPMT)

What is an SPMT?• Multi-axle platform• Each axle pivots 360 degrees• Lifts, carries, sets large/heavy loads• Each axle moves independently

Page 23: Implementing ABC on Bridge Replacement and Rehabilitation

Bridge Movement with SPMTs

Page 24: Implementing ABC on Bridge Replacement and Rehabilitation

MassDOT Study• 2 similar parallel bridges: One conventional one ABC using PBES• Conventional = $ 224 / SF• ABC = $284 / SF• 27% cost differential; These are NE prices

FIU Study

• FIU compared costs using 53 ABC projects in the FHWA ABC database with similar conventional projects

• ABC costs were 20% higher on average

ABC COSTS

Page 25: Implementing ABC on Bridge Replacement and Rehabilitation

• Design-Bid-Build• Design-Build• Construction Manager / General Contractor

ABC Contracting• Incentive / Disincentive based on user delay costs• A+B Bidding

ABC DELIVERY

Page 26: Implementing ABC on Bridge Replacement and Rehabilitation

ABC Resources SHRP2 ABC Toolkit

• Sample ABC plans

• Sample ABC design calcs.

• ABC Specs / Special provisions

• ABC erection concepts

Page 27: Implementing ABC on Bridge Replacement and Rehabilitation

Implementing PBES

Page 28: Implementing ABC on Bridge Replacement and Rehabilitation

14 Day Bridge Replacement – Keg Creek Bridge, Council Bluffs, Iowa

• Total prefabricated bridge• 3 Spans• 14 day closure• 14 day ABC period• Opened November 1, 2011

Page 29: Implementing ABC on Bridge Replacement and Rehabilitation

Oct 17, 2011

Nov 1, 2011

Page 30: Implementing ABC on Bridge Replacement and Rehabilitation

Cross-Sections/Plan

UHPC Joints

Page 31: Implementing ABC on Bridge Replacement and Rehabilitation

Prefabrication Yard Adjacent to Bridge – Iowa Bridge Farm

Page 32: Implementing ABC on Bridge Replacement and Rehabilitation

93 K

168 K

Prefabrication of Abutments and Piers

52 K

Page 33: Implementing ABC on Bridge Replacement and Rehabilitation

Precast Abutment Assembly – Days 3 and 4

Page 34: Implementing ABC on Bridge Replacement and Rehabilitation

• Pier caps: 168 kips• Required two 110 ton cranes to lift into place

168 K

Precast Pier Assembly – Day 5

Page 35: Implementing ABC on Bridge Replacement and Rehabilitation

112 K

Span – 70 ft

Erection of Superstructure Elements – Days 7 and 8

Page 36: Implementing ABC on Bridge Replacement and Rehabilitation

Erection of the Superstructure Elements – Days 7 and 8

Page 37: Implementing ABC on Bridge Replacement and Rehabilitation

• Full moment transfer

• No post-tensioning required

• Only 6 in. wide; low-permeability

• 25,000 psi strength• Steel fiber

reinforcement

Ultra High Performance Concrete Deck Closure Pours – Day 10

Page 38: Implementing ABC on Bridge Replacement and Rehabilitation

Precast Approach Slab — Day 10

Precast SleeperSlab

Page 39: Implementing ABC on Bridge Replacement and Rehabilitation

Time Lapse – 14 Day Replacement

Page 40: Implementing ABC on Bridge Replacement and Rehabilitation

Implementing Slide-In Bridge Construction

Page 41: Implementing ABC on Bridge Replacement and Rehabilitation

• Weekend Replacement• 20 Hr Closure

I-84 Bridges Slide-In Replacement — New York 2013

Page 42: Implementing ABC on Bridge Replacement and Rehabilitation

• Over 75,000 ADT• 16% trucks• Existing bridges are too narrow for cross-overs• 3 Span bridge replaced with single span• One Saturday night closure per bridge

NY I-84 Bridges

Page 43: Implementing ABC on Bridge Replacement and Rehabilitation

• NEXT beams• Precast approach slabs• UHPC closure pour

Superstructure Sections

Page 44: Implementing ABC on Bridge Replacement and Rehabilitation

New Superstructures on Falsework

Page 45: Implementing ABC on Bridge Replacement and Rehabilitation

New Abutment Construction

Page 46: Implementing ABC on Bridge Replacement and Rehabilitation

Slide-In Replacement Concept

Slide SurfaceTemporary end span

Modular walls

During Slide

Page 47: Implementing ABC on Bridge Replacement and Rehabilitation

End Diaphragm and Slide Shoe

Page 48: Implementing ABC on Bridge Replacement and Rehabilitation

Bridge Slide – October 21, 2013

7 hours to demolish existing bridge and slide in new bridge

Page 49: Implementing ABC on Bridge Replacement and Rehabilitation

Both Bridge Slides Completed 10 Months After NTP

Page 50: Implementing ABC on Bridge Replacement and Rehabilitation

Time Lapse

Page 51: Implementing ABC on Bridge Replacement and Rehabilitation

ABC Rehab Projects

• PBES• SPMT

Page 52: Implementing ABC on Bridge Replacement and Rehabilitation

Minneapolis Franklin Avenue Bridge Rehabilitation

New deck, cap beams and columns using precast members

Page 53: Implementing ABC on Bridge Replacement and Rehabilitation

Minneapolis Franklin Avenue Bridge Rehabilitation

• Part-width construction is not cost-effective

• Cast-in-Place Construction: Requires full closure for two years

• ABC alternate: Full closure for 3 months• Adjacent to Univ. of Minnesota campus• Closure can be timed to occur in summer months• On-site pre-casting by contractor

Page 54: Implementing ABC on Bridge Replacement and Rehabilitation

On Site Pre-casting --- Franklin Ave. Bridge MN

Page 55: Implementing ABC on Bridge Replacement and Rehabilitation

Steam Curing / Wet Curing of Slab Panels

Page 56: Implementing ABC on Bridge Replacement and Rehabilitation

PennDOT State Route 30 Bridge – Weekend Replacement Replacement • 54 Hour closure (Friday night – Monday Morning)

• Busy State Route (ADT 30,000) over local road in East Pittsburgh, PA• Full superstructure and partial substructure replacement

Page 57: Implementing ABC on Bridge Replacement and Rehabilitation

Partial Demolition of Abutments / New Preacst Caps

Page 58: Implementing ABC on Bridge Replacement and Rehabilitation

Steel Superstructure Modules -- Assembly

Page 59: Implementing ABC on Bridge Replacement and Rehabilitation

Bridge Model

Page 60: Implementing ABC on Bridge Replacement and Rehabilitation

Weekend Superstructure Replacement Using SPMTsBridge Over Route 9 ; Massachusetts

Substructure Rehab

Page 61: Implementing ABC on Bridge Replacement and Rehabilitation

STAGING AREA

ROUTE 9

Bridge Over Route 9; Site-Layout

Page 62: Implementing ABC on Bridge Replacement and Rehabilitation

Substructure Rehabilitation with Precast Caps

Page 63: Implementing ABC on Bridge Replacement and Rehabilitation

New Two-span Steel Superstructure on False-work

Page 64: Implementing ABC on Bridge Replacement and Rehabilitation

SPMT Move

Page 65: Implementing ABC on Bridge Replacement and Rehabilitation

New Superstructure on Rehabilitated Substructure

Page 66: Implementing ABC on Bridge Replacement and Rehabilitation

NJ Transit Bridge Replacement – Plainfield, NJ• Weekend Superstructure Replacement with SPMT– October 2015• Rehab Substructure

Page 67: Implementing ABC on Bridge Replacement and Rehabilitation

Substructure Rehab -- Saturday

New bridge assembled in station parking lot

Page 68: Implementing ABC on Bridge Replacement and Rehabilitation

Bridge Move – Saturday Night

Page 69: Implementing ABC on Bridge Replacement and Rehabilitation

Track Work -Sunday

Page 70: Implementing ABC on Bridge Replacement and Rehabilitation

Thank You