implementation and deployment - best practices for managing change
TRANSCRIPT
Implementation and Deployment
The Challenges of Managing Major Change
Peter QuintanaProgramme DirectorStandard Chartered BankMarch 2002
– A statement of the obvious
– Some worrying statistics
– Reasons for failure
– A programme approach to change
– What can we do to improve?
– Tactics for success
Excellence in execution….
….Requires flexibility and discipline
Organisations face increasingly complex & demanding change programmes….
Multi-Site
Large Scale
Complex
ResourceIntensive
High Cost
High Risk
MultipleStakeholders
Global
Multi-Cultural
Multi-Functional
Majorstrategicchange
…impacting on every aspect of their business
Some worrying statistics
100 Change Projects50% (50 Projects)
Deliver the Solution
• 30% are cancelled• 20% have serious delivery problems
50% (50 Projects) Fail
50 Change Projects70% (35 Projects)Are accepted by
business users
• 30% fail to be accepted by business users
30% (15 Projects) Fail
Some worrying statistics
35 Change Projects40% (15 Projects)Deliver Expected Business Benefits
• 60% fail to deliver expected business benefits
60% (20 Projects) Fail
Some worrying statistics
Reasons for failure 1 - Delivering the solution
55 1010 1515
Technology IlliteracyLack of IT managementDidn’t need it any longer
Lack of planningChanging requirements
Unrealistic expectationsLack of resourcesLack of user involvementIncomplete requirements
Percentage of failed projects
Lack of executive support
Lack of planning for the changes
No short-term successes
Under- involvement of affected staff
No clear vision of the change
Poor communications
Fear of failure
Resistance
Inertia
Reasons for failure 2 - Readiness for change
Projects not aligned to strategy
Company strategy changed
The marketplace changed
Reasons for failure 3 - Delivery of benefits
Strategy
Objectives
Critical Success Factors
The business case was wrong
The desired benefits were not known
Projects not prioritised against organisational CSFs
Projects do not contribute to shareholder value
– Prioritise investment by contribution to the business
– Select the ‘right’ set of projects
– Set a baseline so we can measure business benefits
– Combine strong project management with skill in managing the human elements
– Be able to change as the outside world changes
Flexibility and discipline….
….A programme approach to change
Programme management….
….Managing risk in multiple dimensions
The identification, prioritisation and execution of a portfolio of change initiatives in an open
environment to achieve real business benefits and enhance shareholder value
….Gated approval to allow reaction to change
Initiation Operations
Planning
Impl
emen
t
benefitsbenefits
benefits
Planning
Review
Review
3. Business Plan approved,funding for detailed planning in place
5. Additional funding approved at milestoneevents
An open lifecycle….
Definition
1. Strategic alignment and prioritisation of change initiatives to achieve business benefit
2. Approval to establish overall funding, resources and infrastructure
7. Progressive delivery of benefits
8. Controlled transfer of responsibility to operations
4. Identification of detailed tasks, interdependencies, timeframes, resources and benefits
6. Managing achievement, delivery of benefits, issues and variations
What can we do to improve - Delivering the Solution
Providing Support
Developing the Capabilities of
the PM Community
Establishing Project
Management Standards
Developing Capabilities to Deliver Projects
–Advice and coaching for project managers and teams
–Assurance reviews
–Establishing corporate processes
–Benchmarking
–Helping strategic sponsors fulfil their roles
–Career structure with competencies for project managers
–Training curriculum
–Group Project Management Guide
–Project Management Library
–Tools and techniques
Skills and disciplines for project management
–The Group Project Management Guide
–Assessing project risk–Project approvals–Roles and responsibilities–Managing projects by a number of processes
–The Project Management Library
–Templates–Best practice examples–Advice and guidance–Tools & techniques
Group projectmanagement guide V2.0
The projectmanagement library
First release - April 1999
Focus on time, cost and quality
Helps to determine:– the required project
approvals– the “management
environment”– PM experience– project organisation– formality of
approach– level of external
review
Assessing project risk
Risk Score (max score 15) 12Risk Classification (High Medium Low) HIs this a Critical Project? (Yes, No) Yes
High Risk = score of 12-15Medium Risk = score of 7 - 11Low Risk = score of <7
Risk Category Risk Factor Notes FactorScore
Categorytotal
RoundedAverage
Project Size Cost Project is >10M USD 3
P & L impact P&L is > 4M USD (2001) 3Project duration (incl.Feasibility)
9 – 12 months 3 9 3
Complexity Project objectives High level scope clear & agreed 2SCB areas impacted Single business units, but
multiple geography2
External parties 2 external suppliers 2Degree of change Minor operational changes 2Dependence on otherprojects
Partial dependence on CS&Sfor channel capability; andMBP for direction on hubbing
2 10 2
Time-scale Ability to achieve Very demanding timescale –very tight and no contingency
3
End-date Imposed internally 2 5 3BusinessImpact
Impact on GroupAnnual Results
>0.1% and <0.5% 2
Strategic significance Moderate 2Customer impact Significant 3Regulatory impact Some negotiations required
with one or more regulator2
Market impact No + or – impact on share price 1Reputation Moderate 2Stability of localenvironment in whichthe project isoperating
Stable 1 13 2
Organisation Group experience Done before 1Team experience Project management and team
skills available within Group2
Technology risk Technology new to businessunit or geography
2
Business risk Some business process/productnew to business unit orgeography
2 7 2
TOTAL 44 12
Par for Detailed Planning Phase
Detailed Planning Phase
Par for Implementation
Implementation
Feasibility
Project approvals - managing risk levelsU
nce
rtai
nty
+
-
Time
PAR1 PAR2
What can we do to improve - Readiness for ChangeDefine The
Change
Assess The Climate
Identify Change Approach
Generate Sponsorship
Develop Target Readiness
Create Cultural Fit
Build Agent Capacity
Motivation Planning
Communication Planning
Integrate Planning
Plan
ImplementMonitor
Skills and tools to understand and manage the human elements of changeAccelerating ImplementationManagement(IMA)
5
Sponsor Capacity
Employee Readiness
Cultural Fit
Agent Capacity
Organizational Stress
History of
Implementation
Focus on implementation history and organisational capabilities
Strategies to surface and overcome resistance to change
Assessing sponsor capacity
– Changes are lost in the management ‘black hole’
– Impact on power & control– Impact on job characteristics– Work pressure, stress & worklife
disruption
– Treat all layers of the organisation as change ‘targets’– Define terms of reference for Steering Committee
– Objectives – Responsibilities– Outputs
– Implement a face to face communications programme– Implement regular written communications
– Bi-weekly bulletin– Monthly executive update– Vendor position statement – Ad hoc information packs
– Define measurement of effective implementation success– Ensure clear links between jobs, strategy and changes– Ensure careful prioritisation and allocation of resources
Building reinforcing sponsorship
ObjectivesRepresent the interests of all stakeholders
to the programme and provide direction to the programme director
Regularly review the business case and recommend corrective action for any changes in the business case
Provide policy guidance to, and resolve any issues that cannot be resolved by, the programme director
Ensure adequate resources are available and allocated to the programme
Provide assurance on overall programme performance through the monitoring of significant risks and progress against targets for quality, time scales and costs
Principle ResponsibilitiesDefine Programme Director’s responsibilities
and objectives
Provide overall guidance and direction to the programme
Review and approve the Programme Terms of Reference and Plan
Review progress against the plan and budget, and any exceptions
Authorise items of expenditure above Programme Director’s delegated authority
Ensure that regular programme assessments are undertaken
Sign off each completed stage and approve progress to the next stage
Ensure that all deliverables are satisfactorily completed and delivered
Approve the impact of agreed scope changes
Steering Committee Terms of Reference
Global Unsecured Lending Processing Solution
A fixed term contract with a third party, governed by a series of service level agreements, for continuous management responsibility for the
provision of a single Cards and Loans processing Application, plus data centre processing support and software development services for that
Application, supporting all Unsecured Lending products and services - for credit cards and personal loans, globally. Headlines @ 8/2/2002 :Programme approved for Functional Solution Definition (FSD) PhasePre-FSD will be conducted with both vendors - SLBS and CertegyFSD will be conducted with a single choice vendorProgress in the last two weeks:
Heads of Agreement (HoA) and Commercial negotiations nearing completionCommenced audit of the evaluation framework and vendor selection processPresented Due Diligence findings to Programme Steering Committee (4/2/02)Issued Vendor Position Statement on 5/2/2002Investment Proposal for FSD Phase approved by CBPIC (6/2/02)Preparation for Pre-FSD and FSD Phase
What's Next:Obtain further transparency on vendor customisation and conversion costsExplore potential opportunities for business process outsourcing within GULPSExplore potential to include Collections within GULPSAnalyse existing IS / IT costs allocated to Unsecured LendingCommence working with Compliance to understand regulatory position
COSTSRFP : budget US$325k, spent US$342kDD : revised budget US$1.9m, spent/committed to date US$1.45m
KEY ISSUES & RISKSLack of available SCB business resource to join the programme team.Lack of in-country resource to support programme during FSD and subsequent roll-out.Regulatory restrictions may prevent a single service centre.Both MESA and Africa have reported urgent needs for unsecured lending systems solutions. The GULPStimetable cannot hold these up, but it is recommended the solutions adopted are either short-term fixes, orallow SCB to exit with minimum cost.
COMMUNICATIONSMeetingsProgramme Steering Committee : Next PSC date - To Be AdvisedCore Programme Team : Weekly, every Monday at 5pm SG
ReportsMonthly Project Status & Financial Report: Due on 12th Feb 2001Quarterly Project Status & Financial Scorecard: Due in Mar 2002
PublicationsBi-Weekly Bulletin Board: If you wish to be taken off the distribution list / would like to see more info. - pleasecontact Cecilia Teoh (Tel: +65 3312833 Email: Gulps Programme/APRS/SCB)Document Store: A GULPS document database has been established in Lotus Notes
Bi-weekly bulletin
Global Unsecured Lending Processing SolutionExecutive Update
Issued By : Peter Quintana Overall StatusFebruary 2002
Objective To source a managed service, comprising integrated, consolidated, standardised software
solutions and data processing, to support unsecured lending products and services – i.e. creditcards and personal loans – offered in segmented APR, MESA and Africa
Scope A fixed term contract with a third party, governed by a series of service level agreements, for
continuous management responsibility for: the provision of a single Cards & Loans processing Application data centre processing support and software development services for that Application parameter management and migration of parameter changes to production
The Application will support all unsecured lending products and services - for credit cards andpersonal loans - globally
Business Case Programme Costs : US$65M; IS/IT Savings EP @ Stake (2007) : US$12-17MBenefits Removes the restrictions inherent in the current systems Delivers worldclass functionality for competitive advantage (profitability & service levels) Benchmarks to best in market on cost for performanceBudget RFP phase - budget US$325k; spent US$342k DD phase – revised budget US$1.9M; spent/committed to date US$1.45M
ResourcesProgramme Steering Committee John Lorimer, Mike Grime, Mike Hart, Subroto Som,
Roland Teo, CY LingProgramme Director Peter QuintanaProgramme Office Cecilia TeohCore Programme Team Keyka Pourkarimi, Raymond Yip, John Carr, Ericson
Chan, David FleetFinance Tan Sok Hong
Achievements to w/e 8/2/2002• RFP phase
• completed end September• five vendors responded
• Due Diligence phase• Findings presented to PSC 4/2/02• Heads of Agreement/Commercial Negotiations (on service fees) nearing completion
• Functional Solution Definition (FSD) Phase• Approval for budget to proceed to FSD gained from CBPIC 6/2/02• A ‘Pre-FSD’ phase has been agreed to explore BPO options, clarify vendor
customisation/conversion costs, and analyse internal IS/IT costs• Heads of Agreement will not be signed until Pre-FSD is concluded• FSD is now expected to start by 1st April latest
Key Milestones – Functional Solution Definition Phase
Issues
• The Pre-FSD phase may delay the start of FSD to 1st April, and therefore the projected datefor first country roll-out to Q2 2003, as the vendor will potentially not be able to start sourcingand deploying their team until 1st March (once Heads of Agreement have been signed)
• The start of FSD is dependent on sufficient resources being recruited into the BusinessStream. HR have been contacted and are preparing job watches for publication on 18/2, andsome potential candidates have already been identified
• The FSD budget presented provided for 3 FSD workshops. To manage costs more effectively,this approach will be revised. However, the outcome of FSD will be a fixed vendor cost andschedule for customisation and conversion that will be included in the final contract. ThereforeFSD must result in a sufficiently detailed understanding of each country’s specific needs, tohave confidence in the final price and timeline.
Present Due Diligence findings/FSD budget to PSC 04/02/02
Present FSD funding proposal to CBPIC 06/02/02
Achieve transparancy in vendor conversion costs 22/02/02
Review and sign-off data centre location 28/02/02
Analyse current & residual IS/IT costs 28/02/02
Review inclusion of Collections in scope 22/02/02
Scope BPO options 28/02/02
Finalise and sign-off GWAN costs 22/02/02
Confirm funding & scope of ISIS 22/02/02
Review financial treatment of programme costs 28/02/02
Finalise Heads of Agreement 22/02/02
Finalise Commercial Terms 28/02/02
Re-work FSD approach 15/02/02
Define Process Stream 28/02/02
Present Pre-FSD findings and recommendations to PSC 01/03/02
Present Pre-FSD findings and recommendations to EXCO 13/03/02
Mobilise for FSD 31/03/02 Date tbc
Complete FSD 30/06/02 Date tbc
Sign-off Customisation scope & costs 30/06/02 Date tbc
Sign-off Conversion Schedule 30/06/02 Date tbc
Present FSD results/Implementation budget to PSC 30/06/02 Date tbc
Present Implementation funding to CBPIC 30/06/02 Date tbc
Present overall programme for approval to Board 30/06/02 Date tbc
Sign Contract 30/06/02 Date tbc
Monthly executive update
What can we do to improve - Delivery of Benefits
Initiation
Planning
ReviewImplementation
1. Analysis & Identification of improvements
2. Benefits Identification & Quantification
5. Benefits Tracking & Reporting
3. Benefits Optimisation
4. Refine & Develop Business Cases
6. Benefits Review
Close
Skills and disciplines for benefits management
Project A
Project B
Project c
Project D
Project E
Project D
Tranche 1 Benefits realised
Tranche 2 Benefits realised
Project F
Project H
Project E
Project IProject G
TRANCHE ONE TRANCHE TWO
TRANCHE THREE
Tranche 3
PROGRAMME
CLOSE
Focus on progressive delivery of benefits
Analyse & Identify
Improvements Required
Define & Quantify Benefits
Optimise Benefits
Baseline Benefits &
Define Measurement
Criteria
Continuous Tracking &
Reporting of Benefits
Realisation
Review Achievement of Benefits
– What improvements are required or desired?
– What benefits are expected and on what scale? What type of benefit?
– Which benefits will provide best nett return on investment
– Chosen benefits must be baselined to provide a starting point for measurement
– What to measure and how to measure must be clearly defined including source of MIS
– Individual benefits must be tracked until fully realised (to ensure benefits case does not change)
– Review validity of benefit achievement when projects meet deliverables
The benefits management process
– Identify the initiatives needed to deliver the targeted benefits
– Understand the relationships and inter-dependencies between initiatives, benefits and programme outcomes i.e. the cause and effect dynamics of activities and results
– Evaluate initiatives in the context of risk, cost and time to payback vs contribution to high level programme benefits
– Classify initiatives as – Strategic choices– Winners– Tactical returns– Losers
– Prioritise and sequence the programme to maximise benefits in the short term
27
Optimising benefits - the road map
Shareholder Value
Enhanced
CustomerValue
Enhanced
EmployeeValue
Enhanced
Effective AcquisitionManagement
achieved
Effective 1 -to - 1or Customized
MarketingCapabilityachieved
Superior Customer
Managementcreated
EffectiveCampaign
Managementachieved
CustomerInformation
rules& standards
created
Staff are skilled
in QM andhave the
tools
EffectiveBusiness & Marketingplanningachieved
Brand Valuesdefined
QuantitativeMarketing
Implemented
EffectiveProduct
Managementachieved
CustomizedCommunication
CustomerSegmentsidentified
CustomerAnalysiscapabilityincreased
Understandingof Customer
needs,behavior,
value
Quality & amount
of CIincreased
Alliances&
Co-branding
Differentiated & consistent S&S
by customersegmentachieved
Sales & ServiceIntegrationachieved
Proactive Sales process
enhanced
People &Culture
aligned withS&S
Success Criteriameasured onMarketing Efficiency Dashboard
Sales and Retention
Informationupgraded
EffectiveCRM planning
achieved
ExternalSegmentation
frameworkcompleted
External &InternalResearchconducted
ULTIMATEOUTCOMES
Establish a InformationManagement process
Establish a DQManagement process
Define CRM strategy
CRMstrategydefined
SalesManagement
refined
Develop businessplan by country,product, segment
Built inBrandCornerstone
Develop CustomerManagementPlan
Customer Information & Marketing Summary Road Map
Tactics for success - Leading Change
– Local Line Leaders– accountability for results and authority to undertake changes
– who can also undertake meaningful organisational experiments
– Internal Networkers– through which new ideas and practices spread across the
organisation– ability to carry ideas, support and ‘stories’ – help make executive leaders aware of the support that changes need
‘Little significant change can occur if it is driven only from the top’ Therefore cultivate the ‘leadership communities’ at lower levels of the hierarchy who can play critical roles, e.g.
Tactics for success - Initiating Change
‘The fundamental problem is lack of time flexibility - the discretion to focus on what might be important in the long term’ Therefore ensure time invested is effective in order to generate willingness to commit, e.g.
– Integrate initiatives into programmes of change– Create capacity for coaching – Explicitly raise questions about relevance (and revisit regularly)– Make more information available– Keep training tightly linked to business
– Start small and build momentum– Avoid frontal assaults– Encourage participation by choice (not coercion)– Establish interim goals– Communicate the benefits– Avoid jargon – Act as mentors, interpreters and diplomats
Tactics for success - Sustaining Change
‘Harmony is often maintained through a façade - don’t rock the boat’ Therefore ‘lower the water level’ to reveal the rocks underneath and develop organisational confidence to raise issues and challenges e.g.
Tactics for success - Redesigning Change
‘Long term change programmes and ‘change du jour’ create significant potential for disillusionment’ Therefore encourage thinking and new ideas about strategy and purpose e.g.
– Keep articulating the case for change in terms of business results
– Engage network leaders as coaches and carriers of new ideas– Release information about new innovations early– Engage people continually in thinking about strategy and
purpose– Ensure process is open to new strategic influences in the
environment
– The risks of failure to deliver the solution can be mitigated by standards and discipline in project management
– The risks of failure due to lack of readiness for change can be mitigated by adopting tools and developing skills to understand and manage the human elements of change
– The risks of failure to deliver the benefits can be mitigated by standards and disciplines to optimise the programme and maximise returns
Summing up - flexibility means managing risk….
The organisational capability to react to change within an open ‘programme’ life cycle
Appendices
– Optimising Benefits : Initiative Evaluation
Contribution to benefitContribution to benefit
RiskRisk
HighHigh
HighHighLowLow
How risky is an initiative in comparison to its contribution to achieving the high level programme benefits?
Consider a risk status in terms of both the risks to implementing the initiatives successfully and the future operational risks to benefits delivery.
Risk Factors to consider:• the size of the initiative - cost, size of implementation team, duration of project implementation• complexity - dependencies between initiatives and between programmes, geographical spread,
participation of external parties, cross business impact• organisation - skills, experience, knowledge of new technology, scarce resources• business impact - customers, regulators • business risk - new product, new market, competitor activity• extent of business change • sensitivity to changes in markets, strategy, technology
LowLow
Optimising benefits - 1. Risk evaluation
Contribution to benefitContribution to benefit
CostCost
HighHigh
HighHighLowLow
How much does an initiative cost to implement in comparison to its contribution to achieving the high level programme benefits?
Cost should include all implementation costs.
Cost Factors to consider:• systems and hardware• staff cost of the implementation team and administrative costs of the initiative
e.g. travel etc• redundancy costs resultant from change and any associated recruitment cost
for new skills• marketing • training etc.
LowLow
Optimising benefits - 2. Cost evaluation
Contribution to benefitContribution to benefit
Speed Speed of of
returnreturn
Long Long termterm
HighHighLowLow
How long will it be until the investment in this initiative is paid back in comparison to its contribution to achieving the high level programme benefits?
Early in the programme lifecycle this evaluation will be on a best guess basis. Later with more accurate estimates available more sophisticated methods may be employed.
Financial evaluation methods:• simple payback duration • time taken to reach steady state
short short termterm
Optimising benefits - 3. Financial Return evaluation
Contribution to benefit
Attractiveness of initiative
Highly attractive
HighLow
Unattractive
Tactical Tactical ReturnReturn
StrategicStrategicChoicesChoices
LosersLosers
WinnersWinners
Optimising benefits - Classification of initiatives
1. Strategic Choices - essential to the programme, however they need to be planned and implemented with a great deal of caution. First actions on these initiatives are likely to be the commissioning of detailed planning work to establish true costs, risks and investigate alternative solutions. It is unlikely that these will be the first initiatives to be implemented. Action may include suspending implementation of existing initiatives.
2. Winners - the ‘obvious’ initiatives which make a big contribution. They are more likely to be included in the first tranche of programme activities and lay the foundations for future programme activity by establishing profile for the programme and potentially funding for further tranches of activity. They are not necessarily ‘quick wins’ but rather ‘quick starts’.
3. Tactical returns - These are not big contributors to the end result but are attractive as low in cost, low risk or payback quickly. These should be considered for inclusion in the programme only after the resource considerations of 1. & 2. have been allocated.
4. Losers - these are not worth pursuing in the current environment. Details retained for future reference.
Optimising benefits - Classification
Strategic High Potential
Key Operational Support
Projects delivering assets critical to
achieving the organisational
strategy
Projects delivering assets which may be crucial to the
future organisational
strategy
Projects delivering assets on which the organisation will be critically dependent
Projects delivering assets which are valuable but not
crucial to organisational
success
Strategic High Potential
Key Operational Support
Business Innovation and
Change
Business Process Structuring
Creating Opportunities for Business Change
Proving the potential benefits
Process rationalisation and
integration
Process elimination and cost reduction
Optimising benefits - Alternative classification methods
Classification by business contribution Classification by benefit drivers