Immissionsprognose Luft Gutachtenprüfung. Wolfgang J.Müller. Bucharest February 2006. Diese Anforderungen an ein Gutachten gelten für jedes Immissionsprognose Modell !. Gliederung. 1.Einleitung 2.Anforderungen an gutachterliche Stellungnahmen 3.Prüfung von Gutachten 4.Fazit. - PowerPoint PPT PresentationTRANSCRIPT
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 1
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Immissionsprognose Luft
GutachtenprüfungWolfgang J.Müller
Bucharest February 2006
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 2
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Diese Anforderungen an ein Gutachten gelten für
jedes
Immissionsprognose
Modell !
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 3
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Gliederung
1. Einleitung
2. Anforderungen an gutachterliche Stellungnahmen
3. Prüfung von Gutachten
4. Fazit
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 4
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
1. Einleitung
• Grundlage zur Feststellung und Beurteilung von
Luftschadstoffen bei Anlagen ist die TALuft
• Für die Immissionsprognose Anhang 3 der TALuft
• Und …..
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 5
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
2. Anforderungen an gutachterliche Stellungnahmen
Grundlagen
• TALuft
• Anforderungen des LAI an Messstellen (Gutachter)
für Emissionsmessungen
• VDI / DIN Richtlinien
Es ist nicht ausreichend diese nur aufzuzählen!
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 6
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
• Beschreibung der Aufgabenstellung
• Vollständige Messplanung
• Beschreibung des tatsächlichen Ablaufs der Messung
• Bei Abweichung von anerkannten Messverfahren oder
Verwaltungsvorschriften detaillierte Begründung erforderlich
• Messwertauflistung
2. Anforderungen an gutachterliche Stellungnahmen
Allgemeine Anforderungen
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 7
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
• Darstellung der Auswerteverfahren
• Qualitätssicherungsmaßnahmen
• Namentliche Benennung des Berichterstatters und der
beteiligten Personen
• Aufgabenstellung und Bewertung der Ergebnisse müssen
aufeinander abgestimmt sein
• Verwaltungsrechtliche Bewertung obliegt der Behörde
2. Anforderungen an gutachterliche Stellungnahmen
Allgemeine Anforderungen
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 8
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
• Emissionsgutachten (E-Messberichte)
• Immissionsgutachten (I-Messberichte)
• Immissionsprognosegutachten (I-Prognose)
3. Prüfung von Gutachten
3 verschiedene Gutachten bilden das „Team“ der
Immissionsprognose
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 9
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Prüfung von Emissionsgutachten
Formulierung der Messaufgabe
- Vollständige Beschreibung der Aufgabenstellung
- Darstellung der aufgabenbezogenen Sachprobleme
Die Aufgabe muss mit den im Gutachten beschriebenen Mitteln von Dritten nachvollzogen werden können.
Anlagenbeschreibung- Beschreibung der relevanten Anlagenteile inkl. Emissions-
quellen und Einrichtungen zur Erfassung und Minderung der Emissionen
- Betriebs- bzw. Emissionszeiten der Anlage
- Betriebszustand der Anlage während der Messung
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 10
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Messergebnisse
- Plausibilitätsprüfung der Messergebnisse
- Ergebnisse vergleichbarer Anlagen vorhanden?
- Liegen die Ergebnisse im erwarteten Bereich?
- Weisen die Abluftrandparameter Unplausibilitäten auf?
Prüfung von Emissionsgutachten
Unter Berücksichtigung der genannten Prüf- und Beurteilungspunkte ist dann zu entscheiden, ob das Gutachten bzw. der Messbericht plausibel ist.
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 11
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Immissionsgutachten
Als Grundlage der Vorbelastung der Immission
Als Bestimmung der Emissionsquellstärke bei diffusen Emissionsquellen
Als Prüfung der Zusatzbelastung durch die neue Quelle
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 12
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Prüfung von Immissionsprognosegutachten
Einsatzgebiete:
- beliebige Entfernungsbereiche
- einzelne Quellen oder Viel-Quellensysteme
- ebenes oder komplexes Gelände
Ziel:
Prognose der vorhandenen und/oder zu erwartendenSchadstoffbelastung
Immissionsprognosen
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 13
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Schematischer Ablauf einer Immissionsprognose:
Aufbereitung für die
Ausbreitungs-rechnung
Ausbreitungs-rechnung
Transmission
Bewertung der
Ergebnisse
Ergebnis Ausbreitungs
-rechnung Immission
Daten-sammlung Emission
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 14
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Prüfung von Immissionsprognosegutachten
Die bisher genannten Anforderungen an gutachterliche
Stellungnahmen sind auch hier zu berücksichtigen.
- Vollständige Beschreibung der Aufgabenstellung
- Darstellung der aufgabenbezogenen Sachprobleme
Die Aufgabe muss mit den im Gutachten beschriebenen Mitteln von Dritten nachvollzogen werden können.
Notwendige Basisinformationen
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 15
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
- Emissionsdaten aus zitierten Messberichten oder einschlägiger
Literatur
- Bewertung der verwendeten Daten
- Rückschlüsse auf andere Anlagen belegen
- Entsprechen die Quellen den Anforderungen der TA Luft?
Emissionsbegrenzungen, Schornsteinhöhe, Ableitung Über
Dach
- Frühere Gutachten zur betrachteten Anlage sind zu benennen
Datensammlung
Die im Gutachten verwendeten Daten sind eindeutig ihrer Herkunft nach zu kennzeichnen und ihrer Auswahl nach zu bewerten.
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 16
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Eingangsdaten für die Ausbreitungsrechnung
• Die korrekte Überführung der gesammelten Daten in die
Eingangsdatei der Ausbreitungsrechnung ist von
entscheidender Bedeutung!
• Eine detaillierte sachgerechte Prüfung der Eingangsdaten
zur Immissionsprognose ist nur mit ausreichender
Fachkenntnis über das verwendete Ausbreitungsmodell
möglich. Aber die notwendige Vorprüfung kann auch die
Genehmigungsbehörde durchführen !
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 17
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
• Emissionsdaten/-faktoren
• Emissionsmassenstrom
• Abgasvolumen inkl. Bezugsangabe
(feucht/trocken)
• Abgasgeschwindigkeit
• Wärmestrom / Abgastemperatur
• Quellhöhe und räumliche Ausdehnung der Quelle
• Lage der Emissionsquellen (Lageplan)
Eingangsdaten für die Ausbreitungsrechnung
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 18
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Eingangsdaten Meteorologie
Herkunft des Datensatzes
• Standort (Koordinaten)
• Anemometerhöhe
• Umgebung Einflußfaktoren
Zeitliche Repräsentativität des Datensatzes
Räumliche Repräsentativität
Übertragbarkeit auf Anlagenstandort geprüft ?
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 19
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
1. Ist die Station für die Ausbreitungsverhältnisse im Rechengebiet repräsentativ ?
2. Werden die lokalen Windsysteme von der Station ausreichend berücksichtigt ?
3. Werden die zu erwartenden Hauptwindrichtungen von der Station genügend genau wiedergegeben ?
4. Welche Methode wurde zur Übertragung der meteorologischen Daten einer Station auf das Rechengebiet verwendet? z. B. nach Kolb, FITNAH, METRAS
Eingangsdaten Meteorologie
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 20
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Quelle:argusoft
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 21
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Z0 Rauigkeitslänge
Die Datenbankinternen (CORINAIR)
örtlichen Zuweisungen sind mit der Realität zu vergleichen
und ihre sachgerechte Anwendung ist zu prüfen
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 22
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Die Turbulenzerzeugung aufgrund der Bodenrauigkeitwird durch die Rauigkeitslänge z0 beschrieben.
Die Rauigkeitslänge liegt etwazwischen 1/10 und 1/20 der Hindernishöhe.
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 23
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”Klasse
z0 in
mNutzung nach CORINE–Kataster
1 0,01 Strände, Dünen und Sandflächen; Wasserflächen
2 0,02 Deponien und Abraumhalden; Wiesen und Weiden ; Natürliches Grünland; Flächen mit spärlicher Vegetation; Salzwiesen; Gewässerläufe; Mündungsgebiete
3 0,05 Abbauflächen; Sport– und Freizeitanlagen; Nicht bewässertes Ackerland; Gletscher und Dauerschneegebiete
4 0,10 Flughäfen; Sümpfe; Torfmoore; Meere und Ozeane
5 0,20 Straßen, Eisenbahn; Städtische Grünflächen; Weinbauflächen; Komplexe Parzellenstrukturen; Landwirtschaft und natürliche Bodenbedeckung; Heiden und Moorheiden; Felsflächen ohne Vegetation
6 0,50 Hafengebiete; Obst– und Beerenobstbestände; Wald–Strauch–Übergangsstadien
7 1,00 Nicht durchgängig städtische Prägung; Industrie– und Gewerbeflächen; Baustellen; Nadelwälder
8 1,50 Laubwälder; Mischwälder
9 2,00 Durchgängig städtische Prägung
Rauigkeitsklassierung nach TALuft
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 24
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
z0 Verteilung, Beispiel
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 25
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
• InputDatei Austal2000
• Meteorologie
• Aufpunktraster
• Rauigkeitslänge (CORINE-Kataster)
• Qualitätsstufe
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 26
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
• Ausbreitungsprogramm mit Versionsnummer (AUSTAL2000)
• Aussagen zum Anwendungsbereich des Modells (z.B.
Gebäudeumströmung)
• Den Einsatz des Ausbreitungsmodells begleitende, qualitätssichernde Maßnahmen
Ausbreitungsrechnung
Zur der Ausbreitungsrechnung sind u.a. folgende Angaben
erforderlich:
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 27
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Ergebnisse der Ausbreitungsrechnung
Ergebnisdarstellung:
• Darstellung der Berechnungsergebnisse in tabellarischer
Form (Beurteilungsflächen, Monitorpunkte)
• Graphische Darstellung der Berechnungsergebnisse mit
Beurteilungsflächen
Einfache, erste Plausibilitätsprüfung mit der
Windrichtungsverteilung der verwendeten Meteorologie
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 28
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Bewertung der Ergebnisse der
Ausbreitungsrechnung
• Sind die allgemeinen Anforderungen an Gutachten erfüllt?
• Sind alle genannten Punkte vom Gutachter zufriedenstellend
abgearbeitet worden?
• Erscheinen die ermittelten Ergebnisse plausibel?
Nach Abarbeitung der genannten Prüf- und Beurteilungspunkte
ist dann zu entscheiden, ob das Gutachten plausibel ist.
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 29
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Immissionsprognosegutachten
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 30
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
4. Fazit
• Auf die Einhaltung der allgemeinen Anforderungen an
Gutachten ist zu achten!
• Die Prüfung von Immissionsprognosegutachten erfordert
Sach- und Fachkenntnis.
• Die Dokumentation der angewendeten Vorgehensweise
als auch einzelner Arbeitsschritte ist im Rahmen der
Qualitätssicherung unbedingt notwendig.
Die vom Gutachter erzeugten Ergebnisse
müssen durch Dritte reproduzierbar sein.
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 31
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Austal2000Thanks for your attention
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 32
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Air Pollution
Dispersion Calculation
Industry
Wolfgang J. Müller
Former Lower Saxony State Agency for Ecology
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 33
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Overview• Basic• Stack height• Gauss vs. Lagrange model • TA Luft – AUSTAL2000• Meteorology• Example Preassessment• Remarks
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 34
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
First General Administrative Regulation Pertaining the
Federal Immission Control Act
Technical Instructions on Air Quality Control – TA Luft1. October 2002
Basic:Basic:TA LuftTA Luftnew Licensing procedure guidelinenew Licensing procedure guidelinefor fullfillingfor fullfillingEU Guidelines Air QualityEU Guidelines Air Quality
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 35
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
First step:Checkstack height
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 36
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Source strength Exhaust volume
= f ( Mieteneigenschaften,... Betreiber (Management),.... Meteorologie...)
EM
ISS
ION
Point source or diffusive source ?
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 37
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Low stack height
High stack
TR
AN
SM
ISS
ION
Distance from Source
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 38
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Abbildung 1: Nomogramm zur Ermittlung der Schornsteinhöhe
D= 1.5 m
T= 80 Grad C
R= 60000m3/h
Q/S (kg/h)
24 kg /h
0.08= 300
H = 55 m plus x m for developed areas
Stack height –Nomogram TA Luft /
Q/S =
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 39
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
PM
SO2
TALuft,Annex 7,Tab. 22
Adjust !?
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 40
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Gauß Model
TALuft 1986
AUSTAL86
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 41
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Restrictions of GAUSS Model• Wind- and Turbulence fields are homogeneous in space and time• Flat, homogeneous terrain• Constant source strength• invalid by calm, low windspeed• Statistic of Dispersion Classes
• Dispersion parameters by experiments• Dispersion coefficients valid in the range approx. 100 m ----------------------10 km
• Results:Annual Mean Value, 98% Percentile
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 42
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Lagrange Partikelmodell VDI 3945 Blatt 3 includePhysical processes :
• Transport by the mean wind
• Dispersion in the Atmosphäre
• Dry Deposition • Chemical process of 1. Order
• thermal & mechanical impuls (plume rise)
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 43
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Lagrange Modelsystem
„new model system“
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 44
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
0…….80 s.................... 240 s later
Emission1000 Particlesin H=100 m
Calculation of Concentration by mass of particleof each cell volume
Distance from source (m)
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 45
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Transformation of EU Guideline Air Quality in
National law and TALuft• Components:
NO2, SO2, Benzene, PM10, Tetrachlorethen, Hydrogenfluoride, Ammonia
Heavy metals …• Ambient air concentration and deposition• Timescales:
annual mean, daily mean, and hourly mean with exceedence frequencies per year
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 46
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Check of Dispersion Calculation ReportProcess flow
Preparation for Calculation
Dispersion Calculation
Transmission
Evaluation of results
Results of Calculation
Ambient air
Data-Collection Inputdata Emission,
Meteo
Orography
Buildings
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 47
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
AUSTAL2000
• Next generation dispersion model
Most flexibel approach with respect to • Meteorology• Terrain, Orography• Wind flow around buildings• Use of meteorological time series• Proved in practice since 16 years
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 48
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Advantage vs. Gauss model concept
• Timeseries of emission • Timeseries of Meteorology• Profile of winddirection, velocity depending
of height• Roughness length • Terrain, orography • Chemical transformation 1. Order
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 49
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
• Instationary dispersion situation• Timeseries and statistics of meteo data• all kinds of Point- , line-, area- and volume-
sources• Calculation of shorttime and longterm
concentrations • Monitoring of hourly values at monitoring sites
Advantages of AUSTAL2000
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 50
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
AUSTAL2000
• Free software (GNU license) • Programm and software source code
• Based on System LASAT, Janicke• commercial software package
www.austal2000.de
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 51
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Odour Dispersion Calculation included !
Model system
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 52
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Meteo Input data• Winddirection in the height of anemometer
• Windvelocity in the height of anemometer
Turbulence describing parameters:• Monin- Obukhov Length• Boundary layer height
• Roughness length describing the turbulence production by soil roughness
• Displacement height• Dispersion Class as used before.
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 53
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Mean Roughness LengthSubject to the Land CoverIndicated in theCORINE Land CoverInventoryTab. 14 Annex 3 TALuft
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 54
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Z0 Roughness length
DisplacementHeight d
Forest: z0 = 1,5 mDisplacement Height d= 6*z0 = 9, 0 m
Windprofile u~ ln (z)
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 55
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Corine Land Cover
http://www.corine.dfd.dlr.de
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 56
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Z0= 0.77m R=2 km
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 57
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Meteo Data File StructureTimeseries *.akt
• * AKTERM-Zeitreihe, Deutscher Wetterdienst, Offenbach (KB1A) • * Zeitraum 01/1999 bis 12/1999 • * anonymisierte Daten, Stand: 11.04.2002 • + Anemometerhoehen (0.1 m): 32 41 57 74 98 144 200 244 283
• Station Direction• Year Velocity n/10 (m/s)
• Month Dispersion Class• Day Mixing Height • Time• AK 10999 1999 01 01 00 00 1 1 150 29 1 2 1 -999 9• AK 10999 1999 01 01 01 00 1 1 130 31 1 2 1 -999 9• AK 10999 1999 01 01 02 00 1 1 130 33 1 2 1 -999 9• AK 10999 1999 01 01 03 00 1 1 130 35 1 3 1 -999 9• AK 10999 1999 01 01 04 00 1 1 140 30 1 2 1 -999 9
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 58
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects” T
RA
NS
MIS
SIO
N
Wind Direction Distribution (1 year in %)
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 59
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
R= 50 * H,xi,yi c> 3% Limit Value Year
? X,Y max. concentrationadditional loadselection of 2 measuring sites
area of calculation
AUSTAL2000
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 60
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Monitor point hourly timeseries gas
Imm
issi
on
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 61
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Nesting of grid cell
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 62
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
ti „ Project1-2006“qs -2az anno96.aktermhq 60z0 0.5so2 2.2no2 4.5no 3.4pm-1 4.7pm-2 4.7
TitleQuality stageData file meteoQuellhöhe (m)Roughness lengthSO2-emission in g/sNO2-emission in g/sNO-emission in g/sDust emission(d < 2.5 µ)Dust emi (2.5 < d < 10 µ)
Input data
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 63
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Log data file/ data file of Results AUSTAL2000
2004-04-22 17:39:02 START…..
=========================== Beginn der Eingabe ==========================> ti "0305 Tierhaltung Ohne" 'Projekt-Titel Title> gx 3384360.00 'X-Koordinate des Bezugspunktes Reference Coordinate> gy 5794920.00 'Y-Koordinate des Bezugspunktes Reference Coordinate> z0 0.50 'Rauhigkeitslänge roughnesslength> qs 0 'Qualitätsstufe quality stage> as "E:\Meteorology\Austal2000\osnabrueck_91-00.aks" 'AKS-Datei meteodatafile> ha 10.00 'Anemometerhöhe (m)> dd 30 'Zellengröße (m) cellgrid> x0 -413.8 'X-Koordinate der l.u. Ecke des Gitters (coordinate 0,0)> nx 30 'Anzahl Gitterzellen in X-Richtung number of grid cells> y0 -319.0 'Y-Koordinate der l.u. Ecke des Gitters (coordinate 0,0)ny 26 'Anzahl Gitterzellen in Y-Richtung number of grid cells……….
Check in detail is possible !!
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 64
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
• Particle size depending calculation of PM: ambient air concentration and deposition
• Calculation of deposition of Ammonia (Nitrogen)
• Chemical transformation of NO to NO2
• Calculation of 3- dimension Windfield in the case of terrain and building
Advantages of AUSTAL2000
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 65
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Next steps in Romania:
• Use of AUSTAL2000, source code available, free of charge
• Data format transformation of meteo data for AUSTAL2000
• Automatic roughness length calculation adoption• training
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 66
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Example – Screening methods preassessment air quality
• Collect, summerize emissions• Compare with National, EMEP Inventory….• What stack height is needed ?• Are emission data reliable?• Calculate air conconcentration by AUSTA2000 model, • Compare with passive sampler and…
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 67
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
1. Simulation of annual mean Concentration
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 68
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Calculated Time series (hourly) at Monitoring Point 1
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 69
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Remarks
1. You need persons, who are mainly involved in dispersion calculation !
2. You have to reinforce these persons for checking dispersion calculation reports !
3. These persons have to build up a knowledge center for all kinds of dispersion calculation questions in accordance to the EU Guideline of Air Quality
Wolfgang J.MüllerSTE; former Lower Saxony State Agency for Ecology
Bucharest, 21st to 23rd of February 2006
Component 4: “Operational Duties, Integrated Permitting Procedure”Activity 4.3: “Establishment of an Integrated Permitting Procedure, Application of BAT”Mission 41-1: Workshop – “Presentation of the “Manual on Integrated Permitting Procedure” 70
EU-Twinning Project RO2004/IB/EN-09 “Implementation and Enforcement of the Environmental Acquis
at National Level and Coordination of 8 Regional Twinning Projects”
Thanks for your attention ! …