    Schedule of Quantities

    I No. Description of Item Qty Unit

    Sub. Head: - Earth work

    1

    4512.00 Cu.m.

    2

    2670.00 Cu.m.

    3

    (a) All kinds of soil. 3992.00 Cu.m.

    4

    2245.00 Cu.m.

    NAME OF WORK :- Widening of Dallupura Road, at Mayur Vihar Phase- III (FDallupura) and Strenthening /Improvement of riding quality and construction of storm

    Disposal and carriage of excavated malba, lime,moorum and earth etc by machenical transportincluding loading, unloading and stacking for all leadsand lifts (Beyond initial lead of 50 m , lift upto 1.5 mor as per direction of Engieer - in - Charge )

    Earth work in excavation by mechanical means(Hydraulic excavator) / mannual labour over areas(exceeding 30cm in depth, 1.5m in width as well as 10sq.m.on plan) i/c disposal of excavated earth lead upto50m and lift upto 1.5m, .disposed earth to be levelledand neatly dressed.

    Earth work in excavation by mechanical means(Hydraulic excavator) / mannual labour in foundationtrenches or drain (not exceeding 1.5 m in width or 10sqm.on plan) including dressing of sides and ramming

    of bottom lift up to 1.5 m including getting out theexcavated soil as directed with in a lead of 50m.

    Filling available excavated earth (excluding rock) intrenches, plinth sides of foundations etc. in layers notexeceding 20cm in depth: consolidating each

    deposited layer by ramming and watering lead upto50m and lift upto 1.5m.

  • 8/8/2019 IIIrd RA Bill Dallupura

    2/351

    5

    555 Cu.m.

    Sub. Head: - Concrete Work

    6

    (a)

    260.00 Cu.m.

    (b)

    32.00 Cu.m.

    Sub. Head: - Reinforced Cement Concrete Work

    Desilting of drains by getting out the manure/ sludgerubbish etc in or under water or liquid mud in foulposition in restricted working condition i/c disposal ofexcavated material by machenical transport includingloading, unloading and stacking for all leads and lifts(Beyond initial lead of 50m, lift upto 1.5m or as perdirection of Engieer - in - Charge)

    P/L in position cement concrete of specified gradeexcluding the cost of centering and shuttering all workupto plinth level.

    1:5:10 ( 1 cement : 5 coarse sand : 10 graded stoneaggregate 40 mm nominal size).

    1:2:4 ( 1 cement : 2 coarse sand : 4 graded stoneaggregate 20 mm nominal size).

  • 8/8/2019 IIIrd RA Bill Dallupura

    3/351

    7

    1340.00 Cu.m.

    8

    (a) TMT bars. 100486 Kg.

    9

    (a)

    1949.00 Sqm

    (b)

    250.00 Sqm

    (c)

    5130.00 Sqm

    Providing and laying in position ready mixed concretemanufactured in fully automatic batching plant andtransported to site of work in transit mixer for a leadup to 10kms having continuous agitated mixer, manuf-actured as per mix design of specified grade forreinforced cement concrete work including pumpingof R.M.C. from transit mixer to site of laying ,excluding the cost of centering, shuttering finishingand reinforcement including cost of admixtures inrecommended proportions as per IS : 9103 toaccelerate/ retard setting of concrete, improveworkability without impairing strength and durabilityas per direction of the Engineer - in - charge. M-25grade Reinforced cement concrete by using 410kg ofcement per cum of concrete.

    Reinforcement for RCC work including straightening,cutting, bending placing in position and binding allcomplete.

    Centring and shuttering including strutting, proppingetc. and removal of form for.

    Suspended floors, roofs, landings, balconies andaccess platform..

    Small lintels not exceeding 1.5m clear span, mouldingas in cornices, window sills, string courses, bands,copings, bed plates, anchor blocks and the like.

    Walls (any thickness) including attached pilasters,butteresses, plinth and string courses etc.

  • 8/8/2019 IIIrd RA Bill Dallupura

    4/351

    (d)

    4222.00 Sqm

    10

    771.00 Sqm

    Sub. Head: - Brick Work

    11

    (a) 1:6 (1 cement: 6 coarse sand). 145.00 Cu.m.

    Sub. Head: - Finishing

    12 12 mm cement plaster of mix.

    (a) 1:4 ( 1 cement : 4 coarse sand ) 773.00 Sqm

    13

    450.00 Sqm

    14

    (a)

    3360.00 Sqm

    Walls (any thickness) including attached pilasters,butteresses, plinth and string courses etc.( with shutterfinish surface for central verge kerbstones )

    Providing and fixing in position precast RCC draincover of approved manufacturere i.e. KK. S&S orequivalent make of size 1150 x 400 x 100mm(thickness) or required size with ten hole by using M-30 grade of concrete & reinforced of approvedmanufacture with two layers of 8 mm dia of steel withsix nos along the length & 14 Nos along the widtheach layer suitable distributed & manufactured byvibrator compaction process using joint less FRPmoulds to active shuttering finish on five faces as topface with have broom finish complete as per directionof Engineer-in-Charge.

    Brick work with FPS bricks of class designation 75 infoundation and plinth in cement mortar :-

    Neat cement punning with OP Cement of approvedmanufacture and grade

    Painting with synthetic enamel paint of approvedbrand and manufacture of required colour to give aneven shade.

    Two or more coats on new work over an under coat ofsuitable shade with ordinary paint of approved brandand manufacture

  • 8/8/2019 IIIrd RA Bill Dallupura

    5/351

    15

    116.00 Cu.m.

    Sub. Head: - Road Work

    16

    6375.00 Sqm

    17

    (a) 90mm to 45mm 772.00 Cu.m.

    (b) 63mm to 45mm 579.00 Cu.m.

    (c) 53mm to 22.4mm 1157.00 Cu.m.

    18

    2071.88 Cu.m.

    19

    (a) On bituminous surface @ 0.50 Kg / sqm.

    99774.00 Sqm

    (b) On W.B.M. @ 0.75 Kg / sqm. 6375.00 Sqm

    Demolishing RCC work including stacking of steelbars and disposal of unserviceable material within 50metres lead.

    Consolidation of subgrade with power road roller of 8to 12 tonne capacity including making good theundulations etc. with earth or quarry spoils etc. andrerolling the subgrade

    Supplying & Stacking of graded stone aggregate atsite of size range.

    Laying spreading and compacting stone aggregate ofspecified sizes to WBM specifications includingspreading in uniform thickness, hand picking, rollingwith 3 wheeled road / vibratory roller 8-10 tonne instages to proper grade and camber, applying and brooming requisite type of screening / bindingmaterial to fill up interstices of coarse aggregatewatering and compacting to the required density .

    Providing and applying tack coat using hot straightrun bitumen of grade 80/ 100 including heating the bitumen, spraying the bitumen with mechanicallyoperated spray unit fitted on bitumen boiler, cleaningand preparing the existing road surface as per

    specifications :

  • 8/8/2019 IIIrd RA Bill Dallupura

    6/351

    20

    (a)

    510.00 cum

    21

    (a)

    2110.00 Cu.m.

    Providing and laying Bituminous Macadam onprepared surface with specified graded crushed stoneaggregate for profile corrective base/ binder courseincluding loading of aggregate with F.E. loader , hotmixing of stone aggregates and bitumen in hot mixplant, transporting the mixed material by tippers topaver and laying the mixed material with paver finisher

    fitted with electronic sensing device to the requiredlevel and grade and rolling with road rollers, as perMORTH specification to achieve the desired densityand compaction but excluding the cost of primer/ tackcoat.

    80mm average compacted thickness with bitumen of60/70 grade @ 3.5% (Percentage by weight of total

    mix)

    Providing & laying dense bituminous macadam onprepared surface with specified graded crushed stoneaggregate for profile corrective base/binding courseincluding loading of aggregate with FE loader and hotmixing of stone aggregate, filler and bitumen in batchtype hot mix plant transporting the mixed material bytipper to paver and laying the mixed material withpaver finisher fitted with electronic sensing device tothe required level and grade and rolling by road rollersas per MORTH specifications to achieve the desired

    density, but excluding cost of primer/tack coat.

    50/75mm average compacted thickness with bitumenof 60/70 grade @ 5% (percentage by weight of totalmix) and lime filler @ 2% (percentage by weight of

    Aggregate).

  • 8/8/2019 IIIrd RA Bill Dallupura

    7/351

    22

    (a)

    1376.00 Cu.m.

    23

    754.00 Sqm

    Providing & laying dense bituminous concrete on prepared surface with specified graded stoneaggregate for wearing course including loading ofaggregate with FE loader, hot mixing of bitumen fillerand aggregates in batch type hot mix planttransporting the mixed material by tipper to paver andlaying the mixed material with mechanically paverfinisher fitted with electronic sensing device to therequired level and grade and rolling by road rollers as per MORTH specifications to achieve the desireddensity, but excluding cost of primer / tack coat.

    (a) 40/50 mm compacted thickness with bitumen ofgrade 60/70 @ 5.50% and lime @ 3% (percentage byweight of total mix ) and adding waste plastic additive@ 8% weight of bitumen used. The plastic waste powder shall be dust free and the partical size ofplastic waste powder should be less than 2 mm.

    Providing & applying 2.5mm thick road marking

    stripd (retro-reflective) of specified shades/coloursusisng hot tharmoplastic material by fully/semiautomatic thermo -plastic paint applicator machinefitted with profile shoe,glass beads dispenser, propanetank heater and profile shoe heater, driven byexperienced operator on road surface including cost ofmaterial, labour, T & P, cleaning the road surface ofall dirt, seals oil, grease and foreign materials etc.complete as per direction of Engineer-in-charge andaccoardance with applicable specifications.

  • 8/8/2019 IIIrd RA Bill Dallupura

    8/351

    24

    (a) 250 mm dia. R.C.C. pipe 48.00 Metre

    25

    2800.00 Metre

    26

    720.00 Sqm

    27

    600.00 Sqm

    28

    42.00 Each

    Providing and laying non-pressure NP2 class (lightduty) R.C.C. pipes with collars jointed with stiffmixture of cement mortar in the proportion of 1:2(1cement : 2 fine sand) including testing of joints etc.complete :

    Taking out existing / old kerb stone and disposal withall head and lift complete as per direction of Engineer-in-charge.

    Providing & making 30cm wide channel 50mm Thickof conc 1:3:6 (1 cement : 3 coarse sand : 6 gradedstone aggregate 20mm nominal size) over 75 mm bedof dry bbrick ballast 40 mm nominal size wellramamed and consolidated and grouted with fine sand

    including finishing the top smooth etc. complete andas per direction of Engineer-in-charge.

    Providing and laying 60mm thick factory madecement concrete interlocking paver block of M-30grade made by block making machine with strongvibratory compaction and of approved size and

    design/ shape laid in required colour and pattern overand including 50mm thick compacted bed of coursesand, filling the joints with coarse sand etc. allcomplete as per the direction of Engineer-in-charge.

    Providing and fixing post delineators (made of ABSroundbody fitted with 2 nos 100mm dia) reflective

    and reflectors and mounted on MS pipe of 65mm diadully powder coated anti-rust and anti theft steel to beinstalled as per direction of Engineer-in-charge.

  • 8/8/2019 IIIrd RA Bill Dallupura

    9/351

    29

    800.00 Each

    30

    756.00 cum

    Providing and fixing Glow studs of size 100x20 mmmade of heavy duty body shall be moulded ASA(Acrylic styrene Acryloretrite) or HIP (High impact polystyrene) or ABS having electronically weldedmicro- prismatic lens with abrasion resistant coatingas approved by Engineer in charge. The Glow studsshall support a load of 13635 kg tested in accordancewith ASTM D4280. The slope of retro- reflectivesurface shall be 35 +/-5 degress to base .The reflectivepanels on both sides with at least 12 cm of reflectivearea up each side. The luminance intensity should beas per the specification and shall be tested asdescribed in ASTM I: 809 as recommended in BS:873 part 4 : 1973. The studs shall be fixed to the Roadsurface using the adhesive conforming to IS, as per procedure recommended by the manufacturercomplete and as per direction of Engineer-in-charge.

    Supplying and stacking of good earth at site includingroyalty and carriage up to 1 km (earth measured in

    stacks will be reduced by 20% for payment).

  • 8/8/2019 IIIrd RA Bill Dallupura

    10/351

    31

    400.00 Metre

    32

    2900 Kg.

    Total Of All Sub. Heads.

    Providing and placing barricading 2.00 metre highconsisting of 2.50x2.00m panels made of 1.63mmthick M.S. sheet with frame of 40x40x6mm angleiron horizontal & vertical braces of M.S. flat30x5mm, 2 nos.MS Channel ISLC-75-500MM Longat base as per appoved drawing including applying apriming coat of approved steel primer and painting as per direction of Engineer-in-charge. This item shallalso include arrangement for traffic diversion such astraffic signals diversion signs, marking, flages etc. asdirected by the Engineer-in-charge. The barricading provided shall be retained in position at sitecontinuously during the execution of the entire worktill its completion including its maintenance fordamages & painting & shall not be removed at anystage prior approval of Engineer-in-charge., for theshifting to the next location & shall include allincidental, labour, material, equipment & worksrequired to execute the job.

    NOTE:- One time payment shall be made for each

    running meter of barricading, fabrication& providedfrom start of work i/c its shifting from place to placeas also its maintenance, the barricading providedshall remain to be property of the contractor oncompletion of work.

    Deduct on account of old C.T.D. bars received fromthe demolishing of RCC work at site.(Credit to Work)

    Assistant Engineer (P)PWD Zone M-2MSO Building New Delhi

    Executive Engineer (P)PWD Zone M-2

    MSO Building New Delhi

  • 8/8/2019 IIIrd RA Bill Dallupura

    11/351

  • 8/8/2019 IIIrd RA Bill Dallupura

    12/351

    Rate Amount

    50.66 228578

    101.85 271940

    103.40 412773

    45.70 102597

    om DDA Chilla Sports Complex towater drain at one side.

  • 8/8/2019 IIIrd RA Bill Dallupura

    13/351

    210.92 117061

    1132949

    2237.75 581815

    3257.45 104238

    686053

  • 8/8/2019 IIIrd RA Bill Dallupura

    14/351

    4263.58 5713197

    42.70 4290752

    187.35 365145

    119.25 29813

    180.40 925452

  • 8/8/2019 IIIrd RA Bill Dallupura

    15/351

    270.60 1142473

    3493.91 2693805

    15160637

    2121.75 307654

    307654

    82.55 63811

    21.40 9630

    51.30 172368

  • 8/8/2019 IIIrd RA Bill Dallupura

    16/351

    537.55 62356

    308165

    1.07 6821

    742.30 573056

    768.45 444933

    810.55 937806

    192.55 398940

    17.15 1711124

    23.90 152363

  • 8/8/2019 IIIrd RA Bill Dallupura

    17/351

    4,242.20 2163522

    5366.50 11323315

  • 8/8/2019 IIIrd RA Bill Dallupura

    18/351

    6213.90 8550326

    497.30 374964

  • 8/8/2019 IIIrd RA Bill Dallupura

    19/351

    258.20 12394

    9.42 26376

    198.80 143136

    0

    346.35 207810

    786.35 33027

  • 8/8/2019 IIIrd RA Bill Dallupura

    20/351

    536.60 429280

    144.05 108902

  • 8/8/2019 IIIrd RA Bill Dallupura

    21/351

    786.40 314560

    -20.55 -59595

    27853060

    45448518

  • 8/8/2019 IIIrd RA Bill Dallupura

    22/351

  • 8/8/2019 IIIrd RA Bill Dallupura

    23/351

    ABSTRACT OF COST- IInd R/A BILL

    SITUATION :- Mayur vihar Phase- III. Delhi

    AGENCY :- Sh. Mahavir Prasad Gupta

    AGGREMENT NO :- 32 / EE / PWD / M-212 / 2009- 2010

    DATE OF START :- 8/12/2009

    D.O.C. (Stipulated) 7/6/2010

    D. O. C.(Actual) :- Work in Progress

    DATE OF ABSTRACT :- 11/5/2010I. No. Description of Item Quantity Unit Rat

    Sub. Head: - Earth work FR

    1

    Qty B/F from EMB-27 / P-49 1316.63

    Qty B/F from TEMB / P-3 227.77

    Qty B/F from TEMB / P-9 265.13

    Qty B/F from TEMB / P-15 292.68

    2102.21 Cu.m. 50.66

    2

    Qty B/F from EMB-27 / P-49 1880.92

    Qty B/F from TEMB / P-5 7.92

    1888.84 Cu.m. 101.85

    NAME OF WORK :- Widening of Dallupura Road, at Mayur Vihar Phase- III (From DDDallupura) and Strenthening /Improvement of riding quality and construction of storm water drain

    Disposal and carriage of excavated malba,lime, moorum and earth etc by machenicaltransport including loading, unloading andstacking for all leads and lifts (Beyondinitial lead of 50 m , lift upto 1.5 m or as

    per direction of Engieer - in - Charge )

    Earth work in excavation by mechanicalmeans (Hydraulic excavator) / mannuallabour over areas (exceeding 30cm indepth, 1.5m in width as well as 10 sq.m.on

    plan) i/c disposal of excavated earth leadupto 50m and lift upto 1.5m, .disposedearth to be levelled and neatly dressed.

  • 8/8/2019 IIIrd RA Bill Dallupura

    24/351

    I. No. Description of Item Quantity Unit Rat

    3

    (a) All kinds of soil.

    Qty B/F from EMB-27 / P-50 956.71

    Qty B/F from TEMB / P-1 325.39

    Qty B/F from TEMB / P-5 378.76

    Qty B/F from TEMB / P-12 418.11

    2078.97 Cu.m. 103.40

    Sub. Head: - Concrete Work6

    (a)

    Qty B/F from EMB-27 / P-50 22.87

    Qty B/F from TEMB / P-2 1.36

    Qty B/F from TEMB / P-3 9.87Qty B/F from TEMB / P-10 14.70

    Qty B/F from TEMB / P-17 22.20

    71.00 Cu.m. 2237.75

    Earth work in excavation by mechanicalmeans (Hydraulic excavator) / mannuallabour in foundation trenches or drain (notexceeding 1.5 m in width or 10 sqm.on

    plan) including dressing of sides andramming of bottom lift up to 1.5 mincluding getting out the excavated soil asdirected with in a lead of 50m.

    P/L in position cement concrete ofspecified grade excluding the cost ofcentering and shuttering all work upto

    plinth level.

    1:5:10 ( 1 cement : 5 coarse sand : 10graded stone aggregate 40 mm nominalsize).

  • 8/8/2019 IIIrd RA Bill Dallupura

    25/351

    I. No. Description of Item Quantity Unit Rat

    7

    Qty B/F from EMB-27 / P-49 46.83

    Qty B/F from TEMB / P-11 38.92

    Qty B/F from TEMB / P-22 107.66

    Qty B/F from TEMB / P-37 64.13

    257.54 Cu.m. 4263.58

    8

    (a) TMT bars.

    Qty B/F from EMB-27 / P-51 10103.99

    Qty B/F from TEMB / P-3 298.22

    Qty B/F from TEMB / P-6 222.38

    Qty B/F from TEMB / P-7 1531.19

    Qty B/F from TEMB / P-13 3716.20

    Qty B/F from TEMB / P-16 3763.29

    Qty B/F from TEMB / P-19 1962.15

    Qty B/F from TEMB / P-21 4069.12Qty B/F from TEMB / P-22 3126.25

    Qty B/F from TEMB / P-27 1478 80

    Sub. Head: - Reinforced CementConcrete Work

    Providing and laying in position readymixed concrete manufactured in fullyautomatic batching plant and transported tosite of work in transit mixer for a lead up to10kms having continuous agitated mixer,manuf -actured as per mix design ofspecified grade for reinforced cementconcrete work including pumping ofR.M.C. from transit mixer to site of laying ,excluding the cost of centering, shutteringfinishing and reinforcement including costof admixtures in recommended proportionsas per IS : 9103 to accelerate/ retard settingof concrete, improve workability withoutimpairing strength and durability as perdirection of the Engineer - in - charge. M-25 grade Reinforced cement concrete byusing 410kg of cement per cum of

    concrete.

    Reinforcement for RCC work includingstraightening, cutting, bending placing in

    position and binding all complete.

  • 8/8/2019 IIIrd RA Bill Dallupura

    26/351

    I. No. Description of Item Quantity Unit Rat

    33304.50 Kg. 42.70

    9

    (b)

    Qty B/F from EMB-27 / P-52 89.03

    Qty B/F from TEMB / P-2 1.93

    Qty B/F from TEMB / P-4 5.08

    Qty B/F from TEMB / P-10 10.50

    Qty B/F from TEMB / P-14 18.64

    Qty B/F from TEMB / P-17 15.00

    Qty B/F from TEMB / P-20 15.75Qty B/F from TEMB / P-25 15.75

    Qty B/F from TEMB / P-34 4.50

    176.18 Sqm 119.25

    (c)

    Qty B/F from EMB-27 / P-52 199.68

    Qty B/F from TEMB / P-4 493.92

    Qty B/F from TEMB / P-9 136.80

    Qty B/F from TEMB / P-13 122.40

    Qty B/F from TEMB / P-16 250.20

    Qty B/F from TEMB / P-19 216.00

    Qty B/F from TEMB / P-21 108.00

    Qty B/F from TEMB / P-25 216.00

    Qty B/F from TEMB / P-34 162.00

    1905.00 Sqm 180.40

    Centring and shuttering including strutting,propping etc. and removal of form for.

    Small lintels not exceeding 1.5m clearspan, moulding as in cornices, windowsills, string courses, bands, copings, bed

    plates, anchor blocks and the like.

    Walls (any thickness) including attached pilasters, butteresses, plinth and stringcourses etc.

  • 8/8/2019 IIIrd RA Bill Dallupura

    27/351

    I. No. Description of Item Quantity Unit Rat

    10

    Qty B/F from TEMB / P-37 189.06

    189.06 Sqm 3493.91

    11

    (a) 1:6 (1 cement: 6 coarse sand).

    Qty B/F from TEMB / P-37 17.80

    17.80 Cu.m. 2121.75

    Sub. Head: - Road Work

    16

    Qty B/F from EMB-27 / P-52 4286.18

    Qty B/F from TEMB / P-8 18.09

    4304.27 Sqm 1.07

    17

    (a) 90mm to 45mm

    Qty B/F from EMB-27 / P-53 518.71

    Qty B/F from TEMB / P-9 192.15

    710.86 Cu.m. 742.30

    Providing and fixing in position precastRCC drain cover of approvedmanufacturere i.e. KK. S&S or equivalentmake of size 1150 x 400 x 100mm(thickness) or required size with ten hole

    by using M-30 grade of concrete &reinforced of approved manufacture withtwo layers of 8 mm dia of steel with six nos

    along the length & 14 Nos along the widtheach layer suitable distributed &manufactured by vibrator compaction

    process using joint less FRP moulds toactive shuttering finish on five faces as topface with have broom finish complete as

    per direction of Engineer-in-Charge.

    Brick work with FPS bricks of classdesignation 75 in foundation and plinth incement mortar :-

    Consolidation of subgrade with power roadroller of 8 to 12 tonne capacity includingmaking good the undulations etc. withearth or quarry spoils etc. and rerolling the

    subgrade

    Supplying & Stacking of graded stoneaggregate at site of size range.

  • 8/8/2019 IIIrd RA Bill Dallupura

    28/351

    I. No. Description of Item Quantity Unit Rat

    Qty B/F from TEMB / P-10 12.67

    402.76 Cu.m. 768.45

    (c) 53mm to 22.4mm

    Qty B/F from EMB-27 / P-53 777.82

    Qty B/F from TEMB / P-12 12.25

    790.07 Cu.m. 810.55

    18

    Qty B/F from EMB-27 / P-54 1314.46

    Qty B/F from TEMB / P-10 1.81

    Qty B/F from TEMB / P-12 1.36

    Qty B/F from TEMB / P-15 26.81

    Qty B/F from TEMB / P-18 26.81

    1371.25 Cu.m. 192.55

    19

    (a) On bituminous surface @ 0.50 Kg / sqm.

    Qty B/F from TEMB / P-28 2683.59

    Qty B/F from TEMB / P-29 3280.13

    Qty B/F from TEMB / P-30 3478.32

    Qty B/F from TEMB / P-32 2607.55

    Qty B/F from TEMB / P-33 3038.55

    Qty B/F from TEMB / P-34 2999.31

    Qty B/F from TEMB / P-35 2721.06

    Qty B/F from TEMB / P-36 3512.4524320.96 Sqm 17.15

    Laying spreading and compacting stoneaggregate of specified sizes to WBMspecifications including spreading inuniform thickness, hand picking, rollingwith 3 wheeled road / vibratory roller 8-10tonne in stages to proper grade and camber,applying and brooming requisite type ofscreening / binding material to fill upinterstices of coarse aggregate watering andcompacting to the required density .

    Providing and applying tack coat using hotstraight run bitumen of grade 80/ 100including heating the bitumen, spraying the

    bitumen with mechanically operated sprayunit fitted on bitumen boiler, cleaning and

    preparing the existing road surface as perspecifications :

  • 8/8/2019 IIIrd RA Bill Dallupura

    29/351

    I. No. Description of Item Quantity Unit Rat

    Qty B/F from TEMB / P-23 1114.43

    Qty B/F from TEMB / P-24 1469.42

    Qty B/F from TEMB / P-26 1465.43

    4049.28 Sqm 23.90

    20

    (a)

    Qty B/F from TEMB / P-38 307.75

    307.75 cum 4,242.20

    Providing and laying Bituminous Macadamon prepared surface with specified graded

    crushed stone aggregate for profilecorrective base/ binder course includingloading of aggregate with F.E. loader , hotmixing of stone aggregates and bitumen inhot mix plant, transporting the mixedmaterial by tippers to paver and laying themixed material with paver finisher fittedwith electronic sensing device to therequired level and grade and rolling withroad rollers, as per MORTH specificationto achieve the desired density andcompaction but excluding the cost of

    primer/ tack coat.

    80mm average compacted thickness with bitumen of 60/70 grade @ 3.5%(Percentage by weight of total mix)

  • 8/8/2019 IIIrd RA Bill Dallupura

    30/351

    I. No. Description of Item Quantity Unit Rat

    21

    (a)

    Qty B/F from TEMB / P-38 1732.871732.87 Cu.m. 5366.50

    Providing & laying dense bituminousmacadam on prepared surface withspecified graded crushed stone aggregatefor profile corrective base/binding courseincluding loading of aggregate with FEloader and hot mixing of stone aggregate,filler and bitumen in batch type hot mix

    plant transporting the mixed material by

    tipper to paver and laying the mixedmaterial with paver finisher fitted withelectronic sensing device to the requiredlevel and grade and rolling by road rollersas per MORTH specifications to achievethe desired density, but excluding cost of

    primer/tack coat.

    50/75mm average compacted thicknesswith bitumen of 60/70 grade @ 5%(percentage by weight of total mix) andlime filler @ 2% (percentage by weight ofAggregate).

  • 8/8/2019 IIIrd RA Bill Dallupura

    31/351

    I. No. Description of Item Quantity Unit Rat

    31

    Qty B/F from EMB-27 / P-55 37.50

    37.50 Metre 786.40

    Gross of Agmt. Items

    Less already paid vide Ist R/A Bill

    Net Gross of Agmt. Items

    Providing and placing barricading 2.00metre high consisting of 2.50x2.00m

    panels made of 1.63mm thick M.S. sheetwith frame of 40x40x6mm angle ironhorizontal & vertical braces of M.S. flat30x5mm, 2 nos.MS Channel ISLC-75-500MM Long at base as per appoveddrawing including applying a priming coat

    of approved steel primer and painting as per direction of Engineer-in-charge. Thisitem shall also include arrangement fortraffic diversion such as traffic signalsdiversion signs, marking, flages etc. asdirected by the Engineer-in-charge. The

    barricading provided shall be retained in position at site continuously during theexecution of the entire work till itscompletion including its maintenance fordamages & painting & shall not beremoved at any stage prior approval of

    Engineer-in-charge., for the shifting to thenext location & shall include all incidental,labour, material, equipment & worksrequired to execute the job.

    NOTE:- One time payment shall be madefor each running meter of barricading,fabrication& provided from start of worki/c its shifting from place to place as alsoits maintenance, the barricading providedshall remain to be property of thecontractor on completion of work.

    Add Contractors Enhancement @ 7.25 %above

  • 8/8/2019 IIIrd RA Bill Dallupura

    32/351

    I. No. Description of Item Quantity Unit Rat

    Secured Advance

    Quantity fresh brought at site NIL kg

    Qty. consumed at site -20000.00 "

    Quantity outstanding in this bill -20000.00 kg

    Amount of this Bill -20000.00 kg 37.00

    Total=RECOVERIES

    1 Security deposited @ 5 % on Rs 18118975

    Less already recovered as EMD

    Now recovered

    2 Income Tax @ 2% on Rs 18118975

    Less already recovered in Ist R/A Bill

    Now recovered

    3 Surcharge @ 10% on Rs 362380

    Less already recovered in Ist R/A Bill

    Now recovered

    4 Education Cess @ 3% on Rs 335367

    Less already recovered in Ist R/A Bill

    Now recovered

    5 Sale Tax / vat @ 3 % on Rs 18118975

    Less already recovered in Ist R/A Bill

    Now recovered

    6 Labour Cess @ 1% on Rs 18118975

    Less already recovered in Ist R/A Bill

    Now recovered

    7

    3 % on Rs 48743536

    Less already recovered in Ist R/A Bill

    Now recovered

    Total recoveries ,Marked as 'C' Rs.

    Net Payable A + B - C

    Net Payable 15243952 -620000 -1440724

    CERTIFIED THAT:-

    1.The work has been executed as per C.P.W.D. Specification.

    2.Necessary Recoveries has been made in this Bill.

    3.Contractor has made his own arrangement of water.

    4.No labour complaints have been received so far.

    5.Contractor has appointed Engineers as per Clause-36

    Marked as 'B'

    Amount Withheld for Not achieving Ist ,IInd & IIIrd milestone @ 3%

  • 8/8/2019 IIIrd RA Bill Dallupura

    33/351

  • 8/8/2019 IIIrd RA Bill Dallupura

    34/351

    Amount

    PR

    - 106498.06

    - 192377.90

    A Chilla Sports Complex toat one side.

  • 8/8/2019 IIIrd RA Bill Dallupura

    35/351

    Amount

    - 214965.50

    - 158880.25

  • 8/8/2019 IIIrd RA Bill Dallupura

    36/351

    Amount

    4100.00 1055914.00

  • 8/8/2019 IIIrd RA Bill Dallupura

    37/351

    Amount

    - 1422101.99

    - 21009.47

    - 343662.00

  • 8/8/2019 IIIrd RA Bill Dallupura

    38/351

    Amount

    3200.00 604992.00

    - 37767.15

    - 4605.57

    - 527674.58

  • 8/8/2019 IIIrd RA Bill Dallupura

    39/351

    Amount

    - 309502.27

    - 640394.80

    - 264033.56

    - 417104.46

  • 8/8/2019 IIIrd RA Bill Dallupura

    40/351

    Amount

    - 96777.79

    - 1305517.03

  • 8/8/2019 IIIrd RA Bill Dallupura

    41/351

    Amount

    5275.00 9140880.81

  • 8/8/2019 IIIrd RA Bill Dallupura

    42/351

    Amount

    - 29490.00

    16894149.19

    1224825.82

    18118975.01

    Say 18118975

    -2875023

    A 15243952

  • 8/8/2019 IIIrd RA Bill Dallupura

    43/351

    Amount

    31.00 -620000

    -620000

    905949

    -974871

    0

    362380

    -57500

    304880

    36238

    -5750

    30488

    10061

    -1898

    8163

    543569

    -86251

    457318

    181190

    -28750

    152440

    1462306

    -974871

    487435

    1440724

    13183228

  • 8/8/2019 IIIrd RA Bill Dallupura

    44/351

    Amount

  • 8/8/2019 IIIrd RA Bill Dallupura

    45/351

    I.No. Description No. L B D or

    18

    Noida Bound

    RD- 1215.00 to1225.00

    1 10.00 (3.70+3.60)/2 0.10

    Dallupura Bound

    Deduction for bus stand 1 9.40 0.35 0.10Deduction for chamber 1 3.00 1.20 0.10

    Deduction for bus stand 1 7.00 0.90 0.10

    Deduction for bus stand 1 6.90 0.60 0.10

    Deduction for trees 3 0.60 0.60 0.10

    Total=

    18

    Noida Bound

    RD- 1215.00 to1225.00

    1 10.00 (3.70+3.60)/2 0.07

    Dallupura Bound

    Deduction for bus stand 1 9.40 0.35 0.07

    Deduction for chamber 1 3.00 1.20 0.07

    Deduction for bus stand 1 7.00 0.90 0.07

    Deduction for bus stand 1 6.90 0.60 0.07

    Deduction for trees 3 0.60 0.60 0.07Total=

    18

    Noida Bound

    RD- 1215.00 to1225.00

    1 10.00 (3.70+3.60)/2 0.07

    1 15.00 (2.00+1.90)/2 0.07

    1 15.00 (1.90+1.65)/2 0.07

    1 15.00 (1.65+1.60)/2 0.07

    1 15.00 (1.60+1.60)/2 0.07

    1 15.00 (1.60+1.40)/2 0.07

    1 15.00 (1.40+1.55)/2 0.07

    1 15.00 (1.55+1.60)/2 0.07

    1 15.00 (1.60+1.90)/2 0.07

    1 15.00 (1.90+1.25)/2 0.07

    1 15.00 (1.25+1.45)/2 0.07

    1 15.00 (1.45+1.35)/2 0.07

    Laying spreading and compacting stone aggregate of specifiedsizes to WBM specifications including spreading in uniform

    Ist layer, 90- 45mm

    Laying spreading and compacting stone aggregate of specified

    sizes to WBM specifications including spreading in uniform

    IInd layer, 63-45mm

    Laying spreading and compacting stone aggregate of specifiedsizes to WBM specifications including spreading in uniform

    IIIrd layer, 53-22.50mm

    Budh Singh Marg,Vasundhara Enclave Bound

  • 8/8/2019 IIIrd RA Bill Dallupura

    46/351

    1 13.00 (1.35+1.34)/2 0.07

    Dallupura Bound

    Deduction for bus stand 1 9.40 0.35 0.07

    Deduction for chamber 1 3.00 1.20 0.07

    Deduction for bus stand 1 7.00 0.90 0.07

    Deduction for bus stand 1 6.90 0.60 0.07

    Deduction for trees 3 0.60 0.60 0.07

    Total=

    18

    Noida Bound

    RD- 1215.00 to1225.00

    1 10.00 (3.70+3.60)/2 0.07

    1 15.00 (2.00+1.90)/2 0.07

    1 15.00 (1.90+1.65)/2 0.07

    1 15.00 (1.65+1.60)/2 0.071 15.00 (1.60+1.60)/2 0.07

    1 15.00 (1.60+1.40)/2 0.07

    1 15.00 (1.40+1.55)/2 0.07

    1 15.00 (1.55+1.60)/2 0.07

    1 15.00 (1.60+1.90)/2 0.07

    1 15.00 (1.90+1.25)/2 0.07

    1 15.00 (1.25+1.45)/2 0.07

    1 15.00 (1.45+1.35)/2 0.07

    1 15.00 (1.35+1.30)/2 0.07

    1 15.00 (1.30+1.22)/2 0.071 15.00 (1.22+1.35)/2 0.07

    1 13.00 (1.35+1.34)/2 0.07

    Dallupura Bound

    Deduction for bus stand 1 9.40 0.35 0.07

    Deduction for chamber 1 3.00 1.20 0.07

    Deduction for bus stand 1 7.00 0.90 0.07

    Deduction for bus stand 1 6.90 0.60 0.07

    Deduction for trees 3 0.60 0.60 0.07

    Total=

    Laying spreading and compacting stone aggregate of specifiedsizes to WBM specifications including spreading in uniform

    VIth layer, 53-22.50mm

    Budh Singh Marg,Vasundhara Enclave Bound

  • 8/8/2019 IIIrd RA Bill Dallupura

    47/351

  • 8/8/2019 IIIrd RA Bill Dallupura

    48/351

    Quantity Unit

    3.65 Cum

    -0.33 "-0.36 "

    -0.63 "

    -0.41 "

    -0.11 "

    1.81 Cum

    2.74 Cum

    -0.25 "

    -0.27 "

    -0.47 "

    -0.31 "

    -0.08 "1.36 Cum

    2.74 Cum

    2.19 "

    2.00 "

    1.83 "

    1.80 "

    1.69 "

    1.66 "

    1.77 "

    1.97 "

    1.77 "

    1.52 "

    1.58 "

  • 8/8/2019 IIIrd RA Bill Dallupura

    49/351

    1.31 "

    -0.25 "

    -0.27 "

    -0.47 "

    -0.31 "

    -0.08 "

    26.81 Cum

    2.74 Cum

    2.19 "

    2.00 "

    1.83 "1.80 "

    1.69 "

    1.66 "

    1.77 "

    1.97 "

    1.77 "

    1.52 "

    1.58 "

    1.49 "

    1.42 "1.45 "

    1.31 "

    -0.25 "

    -0.27 "

    -0.47 "

    -0.31 "

    -0.08 "

    26.81 Cum

  • 8/8/2019 IIIrd RA Bill Dallupura

    50/351

  • 8/8/2019 IIIrd RA Bill Dallupura

    51/351

    DATE OF MEASUREMENTS :-

    I.No Description No L B

    2

    Noida Bound

    Near RD(-12.30) to Drain Edge RD199.50 1 12.30 (0.80+0.90)/2

    1 9.40 (3.40+2.80)/21 15.00 (2.80+1.60)/2

    1 15.00 (1.60+2.10)/2

    1 15.00 (2.10+1.60)/2

    1 15.00 (1.60+1.50)/2

    1 15.00 (1.50+1.40)/2

    1 15.00 (1.40+1.40)/2

    1 15.00 (1.40+1.25)/2

    1 15.00 (1.25+1.20)/2

    1 9.60 (1.20+1.10)/2

    1 13.50 (1.20+1.10)/2

    1 12.00 (4.08+4.55)/2

    1 15.00 (4.55+5.30)/2

    1 15.00 (5.30+4.25)/2

    1 5.00 (4.25+4.20)/2

    Deduction 1 13.50 (0.80+0.90)/2

    After BudhSingh Marg Cut RD-283.50 to 309.00

    1 15.00 (2.40+1.95)/2

    1 1.50 (1.95+2.00)/2

    1 1.30 (2.00+1.50)/2

    1 7.70 (4.35+4.90)/2

    Deduction for chamber Edge 1 1.70 (1.10+1.20)/2

    Noida Bound R.D 293.70 to R.D-350.00 1 6.30 (2.90+2.85)/2

    1 15.00 (2.85+3.45)/2

    1 15.00 (3.45+2.55)/2

    1 15.00 (2.55+3.10)/2

    1 5.00 (3.10+3.16)/2

    Noida Bound R.D 390.00 to R.D-480.00 1 15.00 (2.87+3.00)/2

    1 15.00 (3.00+2.60)/2

    1 15.00 (2.60+2.70)/2

    1 15.00 (2.70+2.95)/2

    1 15.00 (2.95+2.80)/2

    1 15.00 (2.80+3.00)/2

    Deduction For slab 1 1.15 2.85

    Noida Bound R.D 505.00 to R.D 780.00 1 5.00 (2.95+2.95)/2

    1 15.00 (2.95+2.65)/2

    Earth work in excavation by mechanical means(Hydraulic excavator) / mannual labour over areas

  • 8/8/2019 IIIrd RA Bill Dallupura

    52/351

    1 15.00 (2.65+2.80)/2

    1 15.00 (2.80+2.75)/2

    1 15.00 (2.75+2.50)/2

    1 15.00 (2.50+2.90)/2

    1 15.00 (2.90+3.40)/2

    1 15.00 (3.40+3.85)/2

    1 15.00 (3.85+4.60)/2

    1 15.00 (4.60+5.45)/21 15.00 (5.45+5.70)/2

    1 15.00 (5.70+5.93)/2

    1 15.00 (5.93+6.05)/2

    1 15.00 (6.05+6.00)/2

    1 15.00 (6.00+5.55)/2

    1 15.00 (5.55+5.05)/2

    1 15.00 (5.05+5.25)/2

    1 15.00 (5.25+5.40)/2

    1 15.00 (5.40+5.50)/2

    Deduction For M.H. 2 3.14./4 0.85

    Deduction For M.H. 1 1.50 1.70

    Noida Bound R.D 780.00 to R.D-905.50 1 15.00 (5.50+5.90)/2

    1 15.00 (5.90+6.20)/2

    1 15.00 (6.20+6.80)/2

    1 15.00 (6.80+7.15)/2

    1 15.00 (7.15+7.22)/2

    1 15.00 (7.22+7.45)/2

    1 15.00 (7.45+7.82)/2

    1 15.00 (7.82+7.90)/2

    1 5.50 (7.90+7.90)/2

    Noida Bound R.D 922.00 to R.D-1023.40 1 8.00 (4.95+4.75)/2

    1 15.00 (4.75+4.75)/2

    1 15.00 (4.75+4.90)/2

    1 15.00 (4.90+4.90)/2

    1 15.00 (4.90+5.00)/21 15.00 (5.00+5.35)/2

    1 13.20 (5.35+5.80)/2

    Flair 2./3 5.20 5.8

    Budhsingh Marg Cut C/v 1 10.55 (1.80+1.80)/2

    Noida Bound R.D.96.00 to R.D 117.00 1 15.00 (1.80+2.20)/2

    1 6.00 (2.20+2.50)/2

    BudhSingh Marg Vasundhara Bound 1 15.00 (2.30+2.50)/2

    1 9.10 (2.50+2.95)/2

    1 5.40 (2.95+3.20)/2

    1 22.00 (1.35+1.20)/2

  • 8/8/2019 IIIrd RA Bill Dallupura

    53/351

    C/V Budh singh Marg Cut 1 10.55 (1.80+1.80)/2

    Cutting By Jalboard 1 6.70 (2.00+2.00)/2

    1 9.45 (2.25+2.30)/2

    1 4.30 (2.65+2.62)/2

    1 5.10 (2.75+2.80)/2

    Vasundhara Cut 1 14.00 (3.55+3.50)/21 2.20 (1.20+1.20)/2

    Noida Bound R.D 350.00 to R.D-390.00 1 10.00 (3.16+3.22)/2

    1 15.00 (3.22+3.05)/2

    1 15.00 (3.05+2.87)/2

    Noida Bound R.D 480.00 to R.D-505.00 1 15.00 (3.00+3.00)/2

    1 10.00 (3.00+2.95)/2

    Noida Bound R.D 905.50 to R.D-922.00 1 9.50 (5.25+5.25)/2

    1 7.00 (5.25+4.95)/2

  • 8/8/2019 IIIrd RA Bill Dallupura

    54/351

    D or H Quantity Unit

    0.45 4.70 Cum.

    0.45 13.11 "0.45 14.85 "

    0.43 11.93 "

    0.43 11.93 "

    0.43 10.00 "

    0.43 9.35 "

    0.43 9.03 "

    0.43 8.55 "

    0.43 7.90 "

    0.43 4.75 "

    0.43 6.68 "

    0.43 22.27 "

    0.43 31.77 "

    0.43 30.80 "

    0.43 9.08 "

    0.43 -4.93 "

    0.43 14.03 "

    0.43 1.27 "

    0.43 0.98 "

    0.43 15.31 "

    0.43 -0.84 "

    232.52 Cum.

    0.43 7.79 Cum.

    0.43 20.32 "

    0.45 20.25 "

    0.45 19.07 "

    0.45 7.04 "

    0.45 19.81 "

    0.45 18.90 "

    0.45 17.89 "

    0.45 19.07 "

    0.45 19.41 "

    0.45 19.58 "

    0.45 -1.47 "

    187.66 Cum.

    0.46 6.79 Cum.

    0.46 19.32 "

  • 8/8/2019 IIIrd RA Bill Dallupura

    55/351

    0.46 18.80 "

    0.46 19.15 "

    0.46 18.11 "

    0.44 17.82 "

    0.41 19.37 "

    0.43 23.38 "

    0.45 28.52 "

    0.45 33.92 "0.45 37.63 "

    0.45 39.25 "

    0.45 40.43 "

    0.45 40.67 "

    0.45 38.98 "

    0.45 35.78 "

    0.45 34.76 "

    0.43 34.35 "

    0.43 35.15 "

    0.43 -0.57 "

    0.43 -1.10 "

    540.51 "

    0.40 34.20 "

    0.42 38.12 "

    0.44 42.90 "

    0.45 47.08 "

    0.43 46.34 "

    0.43 47.31 "

    0.43 49.25 "

    0.45 53.06 "

    0.45 19.55 "

    377.81 "

    0.42 16.80 "

    0.44 31.35 "

    0.45 32.57 "

    0.43 31.61 "

    0.43 31.93 "0.43 33.38 "

    0.45 33.12 "

    0.49 9.75 "

    0.50 9.50 "

    0.47 14.10 "

    0.45 6.35 "

    0.45 16.20 "

    0.42 10.41 "

    0.45 7.47 "

    0.45 12.62 "

  • 8/8/2019 IIIrd RA Bill Dallupura

    56/351

    0.45 8.55 "

    305.71 "

    0.43 5.76 Cum.

    0.44 9.46 "

    0.41 4.65 "

    0.43 6.09 "

    0.45 22.21 "0.45 1.19 "

    0.45 14.36 "

    0.45 21.16 "

    0.45 19.98 "

    0.45 20.25 "

    0.45 13.39 "

    0.45 22.44 "

    0.45 15.75 "

    176.69 "

  • 8/8/2019 IIIrd RA Bill Dallupura

    57/351

    I.No Description No L B

    Measurement on dated:-

    3

    (a) All kinds of soil.

    Noida Bound

    R.D 930.00 to 1019.20

    1 15.00 (2.05+2.10)/2

    1 15.00 (2.10+2.20)/21 15.00 (2.20+2.25)/2

    1 15.00 (2.25+2.25)/2

    1 15.00 (2.25+2.20)/2

    1 14.20 (2.20+2.15)/2

    Measurement on dated:-

    3

    (a) All kinds of soil.Noida Bound

    R.D 351.00 to 387.00 1 15.00 (2.40+2.30)/2

    1 15.00 (2.30+2.40)/2

    1 6.00 (2.40+2.40)/2

    Deduction, Pipe Line 1 36.00 1.20

    R.D 483.50 to 501.00 1 15.00 (2.10+2.10)/2

    1 2.50 (2.10+2.00)/2

    R.D 900.00 to 930.00 1 15.00 (1.85+1.95)/2

    1 15.00 (2.30+2.05)/2

    1 20.00 (2.10+2.05)/2

    1 16.90 (2.05+2.05)/2

    Earth work in excavation by mechanical means(Hydraulic excavator) / mannual labour in foundation

    Earth work in excavation by mechanical means(Hydraulic excavator) / mannual labour in foundation

    At Dallupura Road & Rd No. 102 T-Point, R.D1019.20 to 1039.20

    At Dallupura Road & Rd No. 102 T-Point, R.D1039.20 to 1056.10

  • 8/8/2019 IIIrd RA Bill Dallupura

    58/351

    D or H Quantity Unit

    2.20 68.48 Cum.

    2.20 70.95 "2.20 73.43 "

    2.20 74.25 "

    2.20 73.43 "

    2.20 67.95 "

    428.49 "

    1.48 52.17 "

    1.48 52.17 "

    1.48 21.31 "

    0.90 -38.88 "

    1.42 44.73 "

    1.42 7.28 "

    1.48 42.18 "

    1.48 48.29 "

    2.00 83.00 "

    2.00 70.14 "

  • 8/8/2019 IIIrd RA Bill Dallupura

    59/351

    I.No. Description No. L B D or

    18

    Noida Bound

    RD- 1215.00 to1225.00

    1 10.00 (3.70+3.60)/2 0.10

    Dallupura Bound

    Deduction for bus stand 1 9.40 0.35 0.10Deduction for chamber 1 3.00 1.20 0.10

    Deduction for bus stand 1 7.00 0.90 0.10

    Deduction for bus stand 1 6.90 0.60 0.10

    Deduction for trees 3 0.60 0.60 0.10

    Total=

    18

    Noida Bound

    RD- 1215.00 to1225.00

    1 10.00 (3.70+3.60)/2 0.07

    Dallupura Bound

    Deduction for bus stand 1 9.40 0.35 0.07

    Deduction for chamber 1 3.00 1.20 0.07

    Deduction for bus stand 1 7.00 0.90 0.07

    Deduction for bus stand 1 6.90 0.60 0.07

    Deduction for trees 3 0.60 0.60 0.07Total=

    18

    Noida Bound

    RD- 1215.00 to1225.00

    1 10.00 (3.70+3.60)/2 0.07

    1 15.00 (2.00+1.90)/2 0.07

    1 15.00 (1.90+1.65)/2 0.07

    1 15.00 (1.65+1.60)/2 0.07

    1 15.00 (1.60+1.60)/2 0.07

    1 15.00 (1.60+1.40)/2 0.07

    1 15.00 (1.40+1.55)/2 0.07

    1 15.00 (1.55+1.60)/2 0.07

    1 15.00 (1.60+1.90)/2 0.07

    1 15.00 (1.90+1.25)/2 0.07

    1 15.00 (1.25+1.45)/2 0.07

    1 15.00 (1.45+1.35)/2 0.07

    Laying spreading and compacting stone aggregate of specifiedsizes to WBM specifications including spreading in uniform

    Ist layer, 90- 45mm

    Laying spreading and compacting stone aggregate of specified

    sizes to WBM specifications including spreading in uniform

    IInd layer, 63-45mm

    Laying spreading and compacting stone aggregate of specifiedsizes to WBM specifications including spreading in uniform

    IIIrd layer, 53-22.50mm

    Budh Singh Marg,Vasundhara Enclave Bound

  • 8/8/2019 IIIrd RA Bill Dallupura

    60/351

    1 13.00 (1.35+1.34)/2 0.07

    Dallupura Bound

    Deduction for bus stand 1 9.40 0.35 0.07

    Deduction for chamber 1 3.00 1.20 0.07

    Deduction for bus stand 1 7.00 0.90 0.07

    Deduction for bus stand 1 6.90 0.60 0.07

    Deduction for trees 3 0.60 0.60 0.07

    Total=

    18

    Noida Bound

    RD- 1215.00 to1225.00

    1 10.00 (3.70+3.60)/2 0.07

    1 15.00 (2.00+1.90)/2 0.07

    1 15.00 (1.90+1.65)/2 0.07

    1 15.00 (1.65+1.60)/2 0.071 15.00 (1.60+1.60)/2 0.07

    1 15.00 (1.60+1.40)/2 0.07

    1 15.00 (1.40+1.55)/2 0.07

    1 15.00 (1.55+1.60)/2 0.07

    1 15.00 (1.60+1.90)/2 0.07

    1 15.00 (1.90+1.25)/2 0.07

    1 15.00 (1.25+1.45)/2 0.07

    1 15.00 (1.45+1.35)/2 0.07

    1 15.00 (1.35+1.30)/2 0.07

    1 15.00 (1.30+1.22)/2 0.071 15.00 (1.22+1.35)/2 0.07

    1 13.00 (1.35+1.34)/2 0.07

    Dallupura Bound

    Deduction for bus stand 1 9.40 0.35 0.07

    Deduction for chamber 1 3.00 1.20 0.07

    Deduction for bus stand 1 7.00 0.90 0.07

    Deduction for bus stand 1 6.90 0.60 0.07

    Deduction for trees 3 0.60 0.60 0.07

    Total=

    Laying spreading and compacting stone aggregate of specifiedsizes to WBM specifications including spreading in uniform

    VIth layer, 53-22.50mm

    Budh Singh Marg,Vasundhara Enclave Bound

  • 8/8/2019 IIIrd RA Bill Dallupura

    61/351

  • 8/8/2019 IIIrd RA Bill Dallupura

    62/351

    Quantity Unit

    3.65 Cum

    -0.33 "-0.36 "

    -0.63 "

    -0.41 "

    -0.11 "

    1.81 Cum

    2.74 Cum

    -0.25 "

    -0.27 "

    -0.47 "

    -0.31 "

    -0.08 "1.36 Cum

    2.74 Cum

    2.19 "

    2.00 "

    1.83 "

    1.80 "

    1.69 "

    1.66 "

    1.77 "

    1.97 "

    1.77 "

    1.52 "

    1.58 "

  • 8/8/2019 IIIrd RA Bill Dallupura

    63/351

    1.31 "

    -0.25 "

    -0.27 "

    -0.47 "

    -0.31 "

    -0.08 "

    26.81 Cum

    2.74 Cum

    2.19 "

    2.00 "

    1.83 "1.80 "

    1.69 "

    1.66 "

    1.77 "

    1.97 "

    1.77 "

    1.52 "

    1.58 "

    1.49 "

    1.42 "1.45 "

    1.31 "

    -0.25 "

    -0.27 "

    -0.47 "

    -0.31 "

    -0.08 "

    26.81 Cum

  • 8/8/2019 IIIrd RA Bill Dallupura

    64/351

  • 8/8/2019 IIIrd RA Bill Dallupura

    65/351

    I.No Description No. L B

    5

    Dallupura Bound, DDA Drain

    Start from R.D 607.50

    Ist cut, RD 607.50 to 683.00 2 30.00 2.40

    1 16.65 2.40IInd cut, RD- 1215.00 to1225.00 3 30.00 2.40

    1 7.60 2.40

    IIInd cut, RD- 1215.00 to1225.00 3 30.00 2.40

    1 12.85 2.40

    IVth cut, RD- 1215.00 to1225.00 4 30.00 2.40

    1 7.75 2.40

    Desilting of drains by getting out the manure/ sludgerubbish etc in or under water or liquid mud in foul positionin restricted working condition i/c disposal of excavatedmaterial by machenical transport including loading,unloadin and stackin for all leads and lifts Be ond initial

  • 8/8/2019 IIIrd RA Bill Dallupura

    66/351

    D or H Quantity Unit

    0.50 72.00 Cum.

    0.50 19.98 "0.50 108.00 "

    0.50 9.12 "

    0.50 108.00 "

    0.50 15.42 "

    0.50 144.00 "

    0.50 9.30 "

    485.82 "

  • 8/8/2019 IIIrd RA Bill Dallupura

    67/351

    I.No Description No L B

    6

    (a)

    Noida Bound, Box Drain

    R.D 930.00 to 1019.20 2 30.00 1.40

    1 29.20 1.40

    6

    (a)

    Noida Bound

    R.D 351.00 to 387.00 1 15.00 (1.40+1.25)/2

    1 15.00 (1.25+0.85)/2

    1 6.00 (0.85+1.40)/2

    R.D 483.50 to 501.00 1 15.00 1.40

    1 2.50 1.40

    R.D 900.00 to 930.00 1 15.00 1.40

    1 15.00 1.40

    1 20.00 1.70

    1 16.90 1.70

    6

    (a)

    Budh Singh Marg, Dallupura bound 1 15.00 (1.16+1.37)/2

    Ist Cut 1 15.00 (1.37+1.58)/2

    1 15.00 (1.58+2.04)/2

    1 10.20 (2.04+2.38)/2

    flair 1./3 0.60 2.38

    IIIrd Cut 2./3 1.57 2.50

    1 15.00 (2.50+2.65)/2

    1 4.25 (2.65+2.63)/2

    IVth Cut 1 5.00 (2.65+2.63)/2

    Budh Singh Marg, Vasundhara bound 1 15.00 (2.20+2.67)/2

    1 15.00 (2.67+2.45)/2

    1 15.00 (2.45+2.55)/2

    1 15.00 (2.55+2.45)/2

    1 15.00 (2.45+2.42)/2

    1 15.00 (2.68+2.58)/2

    1 6.65 (2.58+2.60)/2

    1 17.50 (2.55+2.45)/2

    Ramp Dustbin, (10.70+10.75+12.15/3=11.20)

    1 11.20 (3.45+4.00+4.65)/3

    1./3 10.70 0.40

    P/L in position cement concrete of specified gradeexcluding the cost of centering and shuttering all work

    1:5:10 ( 1 cement : 5 coarse sand : 10 graded stone

    P/L in position cement concrete of specified gradeexcluding the cost of centering and shuttering all work

    1:5:10 (1 cement : 5 coarse sand : 10 graded stone

    At Dallupura Road & Rd No. 102 T-Point, R.D1019.20 to 1039.20

    At Dallupura Road & Rd No. 102 T-Point, R.D1039.20 to 1056.10

    P/L in position cement concrete of specified gradeexcluding the cost of centering and shuttering all work

    1:5:10 ( 1 cement : 5 coarse sand : 10 graded stoneaggregate 40 mm nominal size).

  • 8/8/2019 IIIrd RA Bill Dallupura

    68/351

    D or H Quantity Unit

    0.10 8.40 Cum.

    0.10 4.09 "

    12.49 "

    0.10 1.99 Cum.

    0.10 1.58 "

    0.10 0.68 "

    0.10 2.10 "

    0.10 0.35 "

    0.10 2.10 "

    0.10 2.10 "

    0.10 4.15 "

    0.10 3.51 "

    0.08 1.42 Cum.

    0.08 1.66 "

    0.08 2.04 "

    0.08 1.69 "

    0.08 0.04 "

    0.08 0.2 "

    0.08 2.9 "

    0.08 0.84 "

    0.08 0.99 "

    0.08 2.74 "

    0.08 2.88 "

    0.08 2.81 "

    0.08 2.81 "

    0.08 2.74 "

    0.08 2.96 "

    0.08 1.29 "

    0.08 3.28 "

    0.08 3.39 "

    0.08 0.11 "

  • 8/8/2019 IIIrd RA Bill Dallupura

    69/351

    I.No Description No L B

    7

    Dallupura Bound, DDA Drain

    Start from R.D 607.50

    Top Slab, Panel No 1 1 5.20 2.88

    2 2.88 0.10

    Top Slab, Panel No 2 1 5.20 2.80

    2 2.80 0.10

    Top Slab, Panel No 3 1 5.20 2.83

    2 2.83 0.10

    Top Slab, Panel No 4 1 5.20 2.82

    2 2.82 0.10

    Top Slab, Panel No 5 1 5.20 2.832 2.83 0.10

    Top Slab, Panel No 6 1 5.20 2.82

    2 2.82 0.10

    Top Slab, Panel No 7 1 5.20 2.83

    2 2.83 0.10

    Top Slab, Panel No 8 1 5.20 2.83

    2 2.83 0.10

    Top Slab, Panel No 9 1 5.20 2.84

    2 2.84 0.10

    Top Slab, Panel No 10 1 5.20 2.84

    2 2.84 0.10

    Top Slab, Panel No 11 1 5.20 2.84

    2 2.84 0.10

    Top Slab, Panel No 12 1 5.20 2.85

    2 2.85 0.10

    Top Slab, Panel No 13, culvert

    (3.16+2.90)/2 1 0.95 3.03

    1 2.90 0.10

    Top Slab, Panel No 14 1 5.20 2.85

    2 2.85 0.10

    Providing and laying in position ready mixedconcrete manufactured in fully automatic batching

  • 8/8/2019 IIIrd RA Bill Dallupura

    70/351

    Top Slab, Panel No 16 1 5.20 2.83

    2 2.83 0.10

    Top Slab, Panel No 17 1 5.20 2.84

    2 2.84 0.10

    Top Slab, Panel No 18 1 5.20 2.83

    2 2.83 0.10

    Top Slab, Panel No 19 1 5.20 2.83

    2 2.83 0.10

    Top Slab, Panel No 20 1 5.20 2.87

    2 2.87 0.10

    Top Slab, Panel No 21 1 5.20 2.85

    2 2.85 0.10

    Top Slab, Panel No 22 1 5.20 2.832 2.83 0.10

    Top Slab, Panel No 23 1 5.20 2.82

    2 2.82 0.10

    Top Slab, Panel No 24 1 5.20 2.83

    2 2.83 0.10

    Top Slab, Panel No 25 1 5.20 2.842 2.84 0.10

    Top Slab, Panel No 26 1 5.20 2.82

    2 2.82 0.10

    Top Slab, Panel No 27 1 5.20 2.84

    2 2.84 0.10

    Top Slab, Panel No 28 1 3.08 2.842 2.84 0.10

    Top Slab, Panel No 29, culvert 1 3.08 2.90

    1 2.90 0.10

    Top Slab, Panel No 30 1 5.20 2.88

    2 2.88 0.10

    Top Slab, Panel No 31 1 5.20 2.86

    2 2.86 0.10

    T Sl b P l N 32 1 5 20 2 84

  • 8/8/2019 IIIrd RA Bill Dallupura

    71/351

    Top Slab, Panel No 33 1 5.20 2.87

    2 2.87 0.10

    Top Slab, Panel No 34 1 5.20 2.84

    2 2.84 0.10

    Top Slab, Panel No 35 1 5.20 2.84

    2 2.84 0.10

    Top Slab, Panel No 36 1 5.20 2.80

    2 2.80 0.10

    Top Slab, Panel No 37 1 5.20 2.86

    2 2.86 0.10

    Top Slab, Panel No 38 1 5.20 2.87

    2 2.87 0.10

    Top Slab, Panel No 39 1 5.20 2.842 2.84 0.10

    Top Slab, Panel No 40 1 5.20 2.85

    2 2.85 0.10

    Top Slab, Panel No 41 1 5.20 2.86

    2 2.86 0.10

    Top Slab, Panel No 42 1 5.20 2.84

    2 2.84 0.10

    Top Slab, Panel No 43 1 5.20 2.87

    2 2.87 0.10

    Top Slab, Panel No 44 1 5.20 2.85

    2 2.85 0.10

    Top Slab, Panel No 45 1 2.28 2.76

    2 2.76 0.10

    Top Slab, Panel No 46 1 2.74 1.36

    1 1.36 0.10

    Top Slab, Panel No 47 1 3.84 2.83

    2 2.83 0.10

    Top Slab, Panel No 48 1 5.20 2.81

    2 2.81 0.10

    Top Slab, Panel No 49 1 5.20 2.812 2.81 0.10

  • 8/8/2019 IIIrd RA Bill Dallupura

    72/351

    Top Slab, Panel No 51 1 5.20 2.82

    2 2.82 0.10

    Top Slab, Panel No 52 1 5.20 2.82

    2 2.82 0.10

    Top Slab, Panel No 53 1 5.20 2.81

    2 2.81 0.10

    Top Slab, Panel No 54 1 5.20 2.85

    2 2.85 0.10

    Top Slab, Panel No 55 1 5.20 2.82

    2 2.82 0.10

    Top Slab, Panel No 56 1 5.20 2.80

    2 2.80 0.10

    Top Slab, Panel No 57 1 5.20 2.85

    2 2.85 0.10

    Top Slab, Panel No 58 1 0.95 2.80

    1 2.80 0.10

    Top Slab, Panel No 59 1 5.20 2.78

    2 2.78 0.10

    Top Slab, Panel No 60 1 5.20 2.822 2.82 0.10

    Top Slab, Panel No 61 1 5.20 2.81

    2 2.81 0.10

    Top Slab, Panel No 62 1 5.20 2.83

    2 2.83 0.10

    Top Slab, Panel No 63 1 5.20 2.80

    2 2.80 0.10

    Top Slab, Panel No 64 1 5.20 2.81

    2 2.81 0.10

    Top Slab, Panel No 65 1 5.20 2.80

    2 2.80 0.10

    Top Slab, Panel No 66 1 4.10 2.82

    1 2.82 0.10

    7 P idi d l i i iti d i d

  • 8/8/2019 IIIrd RA Bill Dallupura

    73/351

    Raft.

    Noida Bound, Box Drain

    R.D 840.00 to 900.00 2 30.00 1.30

    Wall

    R.D 810.00 to 900.00 2x2 30.00 0.15

    7

    Noida Bound, Box Drain

    Raft.

    Noida Bound, Box Drain

    R.D 930.00 to 1019.20 2 30.00 1.30

    1 29.20 1.30

    Wall

    R.D 930.00 to 1019.20 2x2 30.00 0.15

    1x2 29.20 0.15

    7

    Raft.

    Noida Bound, Box Drain

    R.D 351.00 to 387.00 1 5.00 (1.27+1.08)/2

    1 5.00 (1.08+0.95)/2

    1 5.00 (0.95+0.93)/2

    1 5.00 (0.93+1.15)/2

    1 5.00 (1.15+1.28)/2

    1 5.00 (1.28+1.30)/2

    1 6.00 (1.30+1.30)/2

    R.D 483.50 to 501.00 1 15.00 1.30

    1 2.50 1.30

    R.D 900.00 to 930.00 1 15.00 1.30

    1 15.00 1.30

    R.D 1019.20 to .00

    Wall

    Noida Bound, Box Drain

    R.D 351.00 to 387.00 1x2 15.00 0.15

    1x2 15.00 0.15

    1x2 6.00 0.15

    R.D 483.50 to 501.00 1x2 15.00 0.15

    1x2 2.50 0.15

    R.D 900.00 to 930.00 1x2 15.00 0.15

    1x2 15.00 0.15

    R.D 1019.20 to .00

    Wall

    R.D 348.00 to R.D 1019.20 2 12.00 (0.05+0.05)/2

    2 15.00 (0.05+0.10)/2

    Providing and laying in position ready mixed

    concrete manufactured in fully automatic batching

    Providing and laying in position ready mixedconcrete manufactured in fully automatic batching

  • 8/8/2019 IIIrd RA Bill Dallupura

    74/351

    2 15.00 (0.21+0.21)/2

    2 15.00 (0.21+0.28)/2

    2 15.00 (0.28+0.25)/2

    2 15.00 (0.25+0.25)/2

    2 15.00 (0.25+0.21)/2

    2 15.00 (0.21+0.22)/2

    2 15.00 (0.22+0.22)/2

    2 15.00 (0.22+0.20)/2

    2 15.00 (0.20+0.27)/22 15.00 (0.27+0.23)/2

    2 15.00 (0.23+0.22)/2

    2 15.00 (0.22+0.24)/2

    2 15.00 (0.24+0.23)/2

    2 15.00 (0.23+0.24)/2

    2 15.00 (0.24+0.21)/2

    2 15.00 (0.21+0.25)/2

    2 15.00 (0.25+0.32)/2

    2 15.00 (0.32+0.33)/2

    2 15.00 (0.33+0.45)/22 15.00 (0.45+0.43)/2

    2 15.00 (0.43+0.45)/2

    2 15.00 (0.45+0.45)/2

    2 15.00 (0.45+0.52)/2

    2 15.00 (0.52+0.50)/2

    2 15.00 (0.50+0.54)/2

    2 12.00 (0.54+0.57)/2

    2 3.00 (0.57+0.58)/2

    2 15.00 (0.58+0.60)/2

    2 15.00 (0.60+0.66)/22 15.00 (0.66+0.75)/2

    2 15.00 (0.75+0.77)/2

    2 15.00 (0.77+0.78)/2

    2 15.00 (0.78+0.75)/2

    2 15.00 (0.75+0.70)/2

    2 15.00 (0.70+0.67)/2

    2 15.00 (0.67+0.72)/2

    2 15.00 (0.72+0.77)/2

    2 15.00 (0.77+0.85)/2

    2 15.00 (0.85+0.87)/22 15.00 (0.87+0.85)/2

    2 14.20 (0.85+0.83)/2

    7

    Slab

    R.D 303.80 to R.D 967.00 1 11.20 (1.30+1.30)/2

    1 15.00 (1.30+1.30)/2

    Providing and laying in position ready mixedconcrete manufactured in fully automatic batching

  • 8/8/2019 IIIrd RA Bill Dallupura

    75/351

    1 15.00 (1.20+1.26)/2

    1 15.00 (1.26+1.29)/2

    1 15.00 (1.29+1.25)/2

    1 15.00 (1.25+1.26)/2

    1 15.00 (1.26+1.27)/2

    1 15.00 (1.27+1.28)/2

    1 15.00 (1.28+1.22)/2

    1 15.00 (1.22+1.26)/2

    1 15.00 (1.26+1.28)/21 15.00 (1.28+1.26)/2

    1 15.00 (1.26+1.29)/2

    1 15.00 (1.29+1.28)/2

    1 15.00 (1.28+1.24)/2

    1 15.00 (1.24+1.33)/2

    1 15.00 (1.33+1.32)/2

    1 15.00 (1.32+1.32)/2

    1 15.00 (1.32+1.25)/2

    1 15.00 (1.25+1.24)/2

    1 15.00 (1.24+1.29)/21 15.00 (1.29+1.30)/2

    1 15.00 (1.30+1.26)/2

    1 15.00 (1.26+1.35)/2

    1 15.00 (1.35+1.29)/2

    1 15.00 (1.29+1.29)/2

    1 15.00 (1.29+1.34)/2

    1 15.00 (1.34+1.38)/2

    1 15.00 (1.38+1.36)/2

    1 15.00 (1.36+1.30)/2

    1 15.00 (1.30+1.28)/21 15.00 (1.28+1.27)/2

    1 15.00 (1.27+1.28)/2

    1 15.00 (1.28+1.23)/2

    1 15.00 (1.23+1.31)/2

    1 15.00 (1.31+1.31)/2

    1 15.00 (1.31+1.27)/2

    1 15.00 (1.27+1.29)/2

    1 15.00 (1.29+1.32)/2

    1 15.00 (1.32+1.29)/2

    1 15.00 (1.29+1.33)/21 7.00 (1.33+1.30)/2

    R.D 967.00 to R.D 974.10,Culvert 1 7.10 (1.30+1.28)/2

    R.D 974.10 to R.D 1019.20 1 0.90 (1.28+1.28)/2

    1 15.00 (1.28+1.22)/2

    1 15.00 (1.22+1.34)/2

    1 14.20 (1.34+1.35)/2

    Less for openings 126 1.22 1.17

    Culvert at Dallupura Mkt. 1 5.70 1.20

    Culvert at Bhudh Singh Chowk 1 4.00 1.40

    At D ll R d & Rd N 102 T P i t

  • 8/8/2019 IIIrd RA Bill Dallupura

    76/351

    7

    Budh Singh Marg Dallupura bound 1 7.50 (1.10+1.20)/2

    Ist Cut 1 7.50 (1.20+1.35)/2

    1 7.50 (1.35+1.43)/2

    1 7.50 (1.43+1.61)/21 6.35 (1.61+1.84)/2

    1 7.50 (1.84+2.17)/2

    1 7.50 (2.17+2.34)/2

    1 1.30 (2.34+2.40)/2

    1./3 1.00 2.40

    Deduction For I.Tiles

    Deduction For Tree 1 0.40 0.40

    IInd Cut 2./3 1.43 2.80

    1 5.40 (2.80+2.98)/2

    1 15.00 (2.98+2.80)/21 15.00 (2.80+2.80)/2

    1 15.00 (2.80+2.80)/2

    1 4.15 (2.80+2.82)/2

    2./3 1.35 2.82

    IIIrd Cut 2./3 1.57 2.5

    1 15.00 (2.50+2.65)/2

    1 4.25 (2.65+2.63)/2

    Deduction For Block Area

    IVth Cut 1 1.33 (2.52+2.60)/21 15.00 (2.60+2.60)/2

    1 15.00 (2.60+2.55)/2

    1 15.00 (2.55+2.65)/2

    1 15.00 (2.65+2.63)/2

    1 15.00 (2.63+2.55)/2

    1 15.00 (2.55+2.60)/2

    1 15.00 (2.60+2.40)/2

    1 3.50 (2.40+2.32)/2

    Deduction For Block Area

    Deduction For Tree 6 0.40 0.41 1.44 1.4

    Budh Singh Marg Vasundhara Bound 1 10.00 (1.90+2.24)/2

    1 10.00 (2.24+2.23)/2

    1 6.05 (2.23+2.23)/2

    Deduction For Block Area

    Budh Singh Marg Vasundhara Bound 1 15.00 (2.20+2.67)/2

    1 15.00 (2.67+2.45)/2

    1 15.00 (2.45+2.55)/2

    1 15.00 (2.55+2.45)/21 15.00 (2.45+2.42)/2

    1 15 00 (2 42 2 48)/2

    Providing and laying in position ready mixedconcrete manufactured in fully automatic batching

    plant and transported to site of work in transit

  • 8/8/2019 IIIrd RA Bill Dallupura

    77/351

    1 15.00 (2.55+2.50)/2

    1 15.00 (2.50+2.58)/2

    1 15.00 (2.58+2.58)/2

    1 15.00 (2.58+2.68)/2

    1 15.00 (2.68+2.58)/2

    1 6.65 (2.58+2.60)/2

    Deduction For Block Area

    Deduction For Tree 9 0.40 0.40

    Ramp Dustbin 1 (10.70+10.75+12.15)/3 (3.05+3.90+4.55)/31./3 10.70 0.40

  • 8/8/2019 IIIrd RA Bill Dallupura

    78/351

    D or H Quantity Unit

    0.20 3.00 Cum.

    0.10 0.06 "

    0.20 2.91 Cum.

    0.10 0.06 "

    0.20 2.94 Cum.

    0.10 0.06 "

    0.20 2.93 Cum.

    0.10 0.06 "

    0.20 2.94 Cum.0.10 0.06 "

    0.20 2.93 Cum.

    0.10 0.06 "

    0.20 2.94 Cum.

    0.10 0.06 "

    0.20 2.94 Cum.

    0.10 0.06 "

    0.20 2.95 Cum.

    0.10 0.06 "

    0.20 2.95 Cum.

    0.10 0.06 "

    0.20 2.95 Cum.

    0.10 0.06 "

    0.20 2.96 Cum.

    0.10 0.06 "

    0.20 0.58 Cum.

    0.10 0.03 "

    0.20 2.96 Cum.

    0.10 0.06 "

  • 8/8/2019 IIIrd RA Bill Dallupura

    79/351

    0.20 2.94 Cum.

    0.10 0.06 "

    0.20 2.95 Cum.

    0.10 0.06 "

    0.20 2.94 Cum.

    0.10 0.06 "

    0.20 2.94 Cum.

    0.10 0.06 "

    0.20 2.98 Cum.

    0.10 0.06 "

    0.20 2.96 Cum.

    0.10 0.06 "

    0.20 2.94 Cum.0.10 0.06 "

    0.20 2.93 Cum.

    0.10 0.06 "

    0.20 2.94 Cum.

    0.10 0.06 "

    0.20 2.95 Cum.0.10 0.06 "

    0.20 2.93 Cum.

    0.10 0.06 "

    0.20 2.95 Cum.

    0.10 0.06 "

    0.20 1.75 Cum.0.10 0.06 "

    0.20 1.79 Cum.

    0.10 0.03 "

    0.20 3.00 Cum.

    0.10 0.06 "

    0.20 2.97 Cum.

    0.10 0.06 "

    0 20 2 95 C

  • 8/8/2019 IIIrd RA Bill Dallupura

    80/351

    0.20 2.98 Cum.

    0.10 0.06 "

    0.20 2.95 Cum.

    0.10 0.06 "

    0.20 2.95 Cum.

    0.10 0.06 "

    0.20 2.91 Cum.

    0.10 0.06 "

    0.20 2.97 Cum.

    0.10 0.06 "

    0.20 2.98 Cum.

    0.10 0.06 "

    0.20 2.95 Cum.0.10 0.06 "

    0.20 2.96 Cum.

    0.10 0.06 "

    0.20 2.97 Cum.

    0.10 0.06 "

    0.20 2.95 Cum.

    0.10 0.06 "

    0.20 2.98 Cum.

    0.10 0.06 "

    0.20 2.96 Cum.

    0.10 0.06 "

    0.20 1.26 Cum.

    0.10 0.06 "

    0.20 0.75 Cum.

    0.10 0.01 "

    0.20 2.17 Cum.

    0.10 0.06 "

    0.20 2.92 Cum.

    0.10 0.06 "

    0.20 2.92 Cum.0.10 0.06 "

  • 8/8/2019 IIIrd RA Bill Dallupura

    81/351

    0.20 2.93 Cum.

    0.10 0.06 "

    0.20 2.93 Cum.

    0.10 0.06 "

    0.20 2.92 Cum.

    0.10 0.06 "

    0.20 2.96 Cum.

    0.10 0.06 "

    0.20 2.93 Cum.

    0.10 0.06 "

    0.20 2.91 Cum.

    0.10 0.06 "

    0.20 2.96 Cum.

    0.10 0.06 "

    0.20 0.53 Cum.

    0.10 0.03 "

    0.20 2.89 Cum.

    0.10 0.06 "

    0.20 2.93 Cum.0.10 0.06 "

    0.20 2.92 Cum.

    0.10 0.06 "

    0.20 2.94 Cum.

    0.10 0.06 "

    0.20 2.91 Cum.

    0.10 0.06 "

    0.20 2.92 Cum.

    0.10 0.06 "

    0.20 2.91 Cum.

    0.10 0.06 "

    0.20 2.31 Cum.

    0.10 0.03 "

    185.69

  • 8/8/2019 IIIrd RA Bill Dallupura

    82/351

    0.15 11.70 Cum.

    1.20 21.60 "

    Total= 33.30 Cum.

    0.15 11.70 Cum.

    0.15 5.69 "

    1.20 21.60 "

    1.20 10.51 "

    Total= 49.50 Cum.

    0.15 0.88 Cum.

    0.15 0.76 "

    0.15 0.71 "

    0.15 0.78 "

    0.15 0.91 "

    0.15 0.97 "

    0.15 1.17 "

    0.15 2.93 "

    0.15 0.49 "

    0.15 2.93 "

    0.15 2.93 "

    1.20 5.40 Cum.

    1.20 5.40 "

    1.20 2.16 "

    1.20 5.40 "

    1.20 0.90 "

    1.20 5.40 "

    1.20 5.40 "

    0.15 0.18 Cum.

    0.15 0.34 "

  • 8/8/2019 IIIrd RA Bill Dallupura

    83/351

  • 8/8/2019 IIIrd RA Bill Dallupura

    84/351

    0.15 2.77 "

    0.15 2.87 "

    0.15 2.86 "

    0.15 2.82 "

    0.15 2.85 "

    0.15 2.87 "

    0.15 2.81 "

    0.15 2.79 "

    0.15 2.86 "0.15 2.86 "

    0.15 2.87 "

    0.15 2.89 "

    0.15 2.84 "

    0.15 2.89 "

    0.15 2.98 "

    0.15 2.97 "

    0.15 2.89 "

    0.15 2.80 "

    0.15 2.85 "0.15 2.91 "

    0.15 2.88 "

    0.15 2.94 "

    0.15 2.97 "

    0.15 2.90 "

    0.15 2.96 "

    0.15 3.06 "

    0.15 3.08 "

    0.15 2.99 "

    0.15 2.90 "0.15 2.87 "

    0.15 2.87 "

    0.15 2.82 "

    0.15 2.86 "

    0.15 2.95 "

    0.15 2.90 "

    0.15 2.88 "

    0.15 2.94 "

    0.15 2.94 "

    0.15 2.95 "0.15 1.38 "

    0.15 1.37 "

    0.15 0.17 "

    0.15 2.81 "

    0.15 2.88 "

    0.15 2.86 "

    0.15 -26.98 "

    111.18 "

    0.20 1.37 "

    0.20 1.12 "

  • 8/8/2019 IIIrd RA Bill Dallupura

    85/351

    32.40 "

    0.08 0.65

    0.08 0.72

    0.08 0.78

    0.08 0.860.08 0.82

    0.08 1.13

    0.08 1.27

    0.08 0.23

    0.08 0.06

    0.08 -0.01

    0.08 0.2

    0.08 1.17

    0.08 3.250.08 3.15

    0.08 3.15

    0.08 0.87

    0.08 0.19

    0.08 0.2

    0.08 2.9

    0.08 0.84

    0.08 0.260.08 2.93

    0.08 2.9

    0.08 2.93

    0.08 2.97

    0.08 2.91

    0.08 2.9

    0.08 2.81

    0.08 0.62

    0.08 -0.070.08 -0.15

    0.08 1.55

    0.08 1.68

    0.08 1.03

    0.08 2.74

    0.08 2.88

    0.08 2.81

    0.08 2.810.08 2.74

    0 08 2 76

  • 8/8/2019 IIIrd RA Bill Dallupura

    86/351

    0.08 2.84

    0.08 2.86

    0.08 2.9

    0.08 2.96

    0.08 2.96

    0.08 1.29

    0.08 -0.11

    0.13 5.370.08 0.11

    91.32

  • 8/8/2019 IIIrd RA Bill Dallupura

    87/351

    I.No Description No L B

    8

    (a) TMT bars.

    Dallupura Bound, DDA Drain

    Start from R.D 607.50

    Top Slab, Panel No 1 to 4

    16mm Dia.

    Bottom main, crank 4x35 2.83

    Bottom main,straight, at both ends 4x2 2.78Top, Extra 4x35 0.75

    @ 1.579 kg/m,

    Marked

    Top Slab

    10mm Dia.

    Bottom, Distribution 4x19 5.35

    Top, Distribution 4x10 5.15

    Bottom, Chair 4x6 1.05

    @ 0.617 kg/m, 6

    Marked

    Total Weight [A] + [B] =

    8

    (a) TMT bars.

    Dallupura Bound, DDA Drain

    Start from R.D 607.50

    Top Slab, Panel No 5 to 8

    16mm Dia.

    Bottom main, crank 4x35 2.83

    Bottom main,straight, at both ends 4x2 2.78

    Top, Extra 4x35 0.75

    @ 1.579 kg/m,

    Marked

    Top Slab

    10mm Dia.

    Bottom, Distribution 4x19 5.35

    Top, Distribution 4x10 5.15

    Bottom, Chair 4x6 1.05

    @ 0.617 kg/m,

    Marked

    Total Weight [A] + [B] =

    8

    (a) TMT bars.

    Dallupura Bound, DDA DrainStart from R.D 607.50

    Top Slab Panel No 9 to 12

    Reinforcement for RCC work including straightening, cutting,

    Reinforcement for RCC work including straightening, cutting,

    Reinforcement for RCC work including straightening, cutting,

  • 8/8/2019 IIIrd RA Bill Dallupura

    88/351

    Bottom main,straight, at both ends 4x2 2.78

    Top, Extra 4x35 0.75

    @ 1.579 kg/m,

    Marked

    Top Slab

    10mm Dia.

    Bottom, Distribution 4x19 5.35

    Top, Distribution 4x10 5.15Bottom, Chair 4x6 1.05

    @ 0.617 kg/m,

    Marked

    Total Weight [A] + [B] =

    8

    (a) TMT bars.

    Noida Bound, Box Drain

    Between R.D.407 to R.D.410(3m)

    Top Slab, Culvert Panel No. 13

    16mm Dia.

    Top & Bottom, main 2x2 3.10

    2x2 3.00

    2x3 2.85

    Top Slab, Panel No 14 to 16

    Bottom main, crank 3x35 2.83

    Bottom main,straight, at both ends 3x2 2.78

    Top, Extra 3x35 0.75

    @ 1.579 kg/m,

    Marked

    Top Slab, Culvert Panel No. 13

    10mm Dia.

    Top & Bottom, Distribution 2x19 1.00

    Chair 2x2 1.05

    Top Slab, Panel No 14 to 16

    Bottom, Distribution 3x19 5.35

    Top, Distribution 3x10 5.15

    Bottom, Chair 3x6 1.05

    @ 0.617 kg/m, 5

    Marked

    Total Weight [A] + [B] =

    8

    (a) TMT bars.

    Dallupura Bound, DDA Drain

    Start from R.D 607.50

    Top Slab, Panel No 17 to 20

    Reinforcement for RCC work including straightening, cutting,

    Reinforcement for RCC work including straightening, cutting,

  • 8/8/2019 IIIrd RA Bill Dallupura

    89/351

  • 8/8/2019 IIIrd RA Bill Dallupura

    90/351

    @ 0.617 kg/m,

    Marked

    Total Weight [A] + [B] =

    8

    (a) TMT bars.

    Noida Bound, Box Drain

    Top Slab, Culvert Panel No. 2916mm Dia.

    Top & Bottom, main 2x20 2.82

    Top Slab, Panel No 30 to 32

    Bottom main, crank 3x35 2.83

    Bottom main,straight, at both ends 3x2 2.78

    Top, Extra 3x35 0.75

    @ 1.579 kg/m,

    Marked

    Top Slab, Culvert Panel No. 2910mm Dia.

    Top & Bottom, Distribution 2x19 3.02

    Chair 2x2 1.05

    Top Slab, Panel No 30 to 32

    Bottom, Distribution 3x19 5.35

    Top, Distribution 3x10 5.15

    Bottom, Chair 3x6 1.05

    @ 0.617 kg/m, 5

    MarkedTotal Weight [A] + [B] =

    8

    (a) TMT bars.

    Dallupura Bound, DDA Drain

    Start from R.D 607.50

    Top Slab, Panel No 33 to 36

    16mm Dia.

    Bottom main, crank 4x35 2.83

    Bottom main,straight, at both ends 4x2 2.78

    Top, Extra 4x35 0.75

    @ 1.579 kg/m,

    Marked

    Top Slab

    10mm Dia.

    Bottom, Distribution 4x19 5.35

    Top, Distribution 4x10 5.15

    Bottom, Chair 4x6 1.05

    @ 0.617 kg/m,

    Reinforcement for RCC work including straightening, cutting,

    Reinforcement for RCC work including straightening, cutting,

  • 8/8/2019 IIIrd RA Bill Dallupura

    91/351

    8

    (a) TMT bars.

    Dallupura Bound, DDA Drain

    Start from R.D 607.50

    Top Slab, Panel No 37 to 40

    16mm Dia.

    Bottom main, crank 4x35 2.83

    Bottom main,straight, at both ends 4x2 2.78

    Top, Extra 4x35 0.75

    @ 1.579 kg/m,

    Marked

    Top Slab

    10mm Dia.

    Bottom, Distribution 4x19 5.35

    Top, Distribution 4x10 5.15

    Bottom, Chair 4x6 1.05

    @ 0.617 kg/m,Marked

    Total Weight [A] + [B] =

    8

    (a) TMT bars.

    Dallupura Bound, DDA Drain

    Start from R.D 607.50

    Top Slab, Panel No 41 to 44

    16mm Dia.

    Bottom main, crank 4x35 2.83

    Bottom main,straight, at both ends 4x2 2.78

    Top, Extra 4x35 0.75

    @ 1.579 kg/m,

    Marked

    Top Slab

    10mm Dia.

    Bottom, Distribution 4x19 5.35

    Top, Distribution 4x10 5.15

    Bottom, Chair 4x6 1.05

    @ 0.617 kg/m,

    Marked

    Total Weight [A] + [B] =

    8

    (a) TMT bars.

    Dallupura Bound, DDA Drain

    Start from R.D 607.50Top Slab, Panel No 45

    16mm Dia

    Reinforcement for RCC work including straightening, cutting,

    Reinforcement for RCC work including straightening, cutting,

    Reinforcement for RCC work including straightening, cutting,

  • 8/8/2019 IIIrd RA Bill Dallupura

    92/351

    Top, Extra 13 0.75

    Top Slab, Panel No 46

    Bottom main, crank 8 2.75

    Bottom main,straight, at both ends 2 2.70

    Top, Extra 8 0.75

    Top Slab, Panel No 47 to 48

    Bottom main, crank 2x35 2.80

    Bottom main,straight, at both ends 2x2 2.75

    Top, Extra 2x35 0.75

    @ 1.579 kg/m,

    Marked

    Top Slab, Panel No 45

    10mm Dia.

    Bottom, Distribution 19 2.20

    Top, Distribution 10 2.20

    Chair 2x2 1.05

    Top Slab, Panel No 46

    Bottom, Distribution 19 1.31Top, Distribution 10 1.31

    Chair 2x2 1.05

    Top Slab, Panel No 47 to 48

    Bottom, Distribution 2x19 5.35

    Top, Distribution 2x10 5.15

    Bottom, Chair 2x2 1.05

    @ 0.617 kg/m, 4

    Marked

    Total Weight [A] + [B] =

    8

    (a) TMT bars.

    Dallupura Bound, DDA Drain

    Start from R.D 607.50

    Top Slab, Panel No 49 to 52

    16mm Dia.

    Bottom main, crank 4x35 2.80

    Bottom main,straight, at both ends 4x2 2.75

    Top, Extra 4x35 0.75

    @ 1.579 kg/m,

    Marked

    10mm Dia.

    Bottom, Distribution 4x19 5.35

    Top, Distribution 4x10 5.15

    Bottom, Chair 4x6 1.05

    @ 0.617 kg/m,

    Marked

    Total Weight [A] + [B] =

    Reinforcement for RCC work including straightening, cutting,

  • 8/8/2019 IIIrd RA Bill Dallupura

    93/351

    Dallupura Bound, DDA Drain

    Start from R.D 607.50

    Top Slab, Panel No 53 to 56

    16mm Dia.

    Bottom main, crank 4x35 2.80

    Bottom main,straight, at both ends 4x2 2.75

    Top, Extra 4x35 0.75

    @ 1.579 kg/m,Marked

    10mm Dia.

    Bottom, Distribution 4x19 5.35

    Top, Distribution 4x10 5.15

    Bottom, Chair 4x6 1.05

    @ 0.617 kg/m,

    Marked

    Total Weight [A] + [B] =

    8

    (a) TMT bars.

    Dallupura Bound, DDA Drain

    Start from R.D 607.50

    Top Slab, Panel No 57 to 60

    16mm Dia.

    Bottom main, crank 4x35 2.80

    Bottom main,straight, at both ends 4x2 2.75

    Top, Extra 4x35 0.75

    @ 1.579 kg/m,

    Marked

    10mm Dia.

    Bottom, Distribution 4x19 5.35

    Top, Distribution 4x10 5.15

    Bottom, Chair 4x6 1.05

    @ 0.617 kg/m,

    Marked

    Total Weight [A] + [B] =

    8

    (a) TMT bars.

    Dallupura Bound, DDA Drain

    Start from R.D 607.50

    Top Slab, Panel No 61 to 64

    16mm Dia.

    Bottom main, crank 4x35 2.80

    Bottom main,straight, at both ends 4x2 2.75

    Top, Extra 4x35 0.75

    Reinforcement for RCC work including straightening, cutting,

    Reinforcement for RCC work including straightening, cutting,

  • 8/8/2019 IIIrd RA Bill Dallupura

    94/351

    Bottom, Distribution 4x19 5.35

    Top, Distribution 4x10 5.15

    Bottom, Chair 4x6 1.05

    @ 0.617 kg/m,

    Marked

    Total Weight [A] + [B] =

    8(a) TMT bars.

    Dallupura Bound, DDA Drain

    Start from R.D 607.50

    16mm Dia.

    Top Slab, Panel No 65

    Bottom main, crank 35 2.80

    Bottom main,straight, at both ends 2 2.75

    Top, Extra 35 0.75

    Top Slab, Panel No 66

    Bottom main, crank 27 2.80Bottom main,straight, at both ends 1 2.75

    Top, Extra 27 0.75

    @ 1.579 kg/m,

    Marked

    10mm Dia.

    Top Slab, Panel No 65

    Bottom, Distribution 19 5.35

    Top, Distribution 10 5.15

    Bottom, Chair 6 1.05

    Top Slab, Panel No 66.

    Bottom, Distribution 19 4.05

    Top, Distribution 10 3.90

    Bottom, Chair 5 1.05

    @ 0.617 kg/m, 2

    Marked

    Total Weight [A] + [B] =

    8

    (a) TMT bars.

    Noida Bound, Box Drain

    Between RD.825 to 870(45m)

    Raft & Wall

    10mm Dia.

    Bottom, main 300 6.15

    Top, main 300 5.55

    Bottom, Chair 150 1.00

    Wall, U- Chair 44 0.60

    Reinforcement for RCC work including straightening, cutting,

    Reinforcement for RCC work including straightening, cutting,

  • 8/8/2019 IIIrd RA Bill Dallupura

    95/351

    Raft & Wall

    8mm Dia.

    Bottom, Distribution 8 15.00

    Top, Distribution 7 15.00

    Over Lap 45 0.50

    Road side wall, Distribution ,(9+9) 18 45.00

    STP Boundary Side Wall, Distribution,(9+9)

    18 45.00

    Over Lap 105 0.50

    @ 0.395 kg/m, 19

    Marked

    Total Weight [A] + [B] =

    8

    (a) TMT bars.

    Noida Bound, Box Drain

    Between RD.870 to 900(30m)

    Raft & Wall10mm Dia.

    Bottom, main 200 6.20

    Top, main 200 5.60

    Bottom, Chair 100 1.00

    Wall, U- Chair 30 0.60

    @ 0.617 kg/m, 24

    Marked

    Raft & Wall

    8mm Dia.Bottom, Distribution 8 30.00

    Top, Distribution 7 30.00

    Over Lap 30 0.50

    Road side wall, Distribution ,(9+9) 18 30.00

    STP Boundary Side Wall, Distribution,(9+9)

    18 30.00

    Over Lap 72 0.50

    @ 0.395 kg/m, 15

    Marked

    Total Weight [A] + [B] =

    8

    (a) TMT bars.

    Noida Bound, Box Drain

    Between RD.900 to 930(30m)

    Raft & Wall

    10mm Dia.

    Bottom, main 200 6.10

    Top, main 200 5.50

    Reinforcement for RCC work including straightening, cutting,

    Reinforcement for RCC work including straightening, cutting,

  • 8/8/2019 IIIrd RA Bill Dallupura

    96/351

    @ 0.617 kg/m, 24

    Marked

    Raft & Wall

    8mm Dia.

    Bottom, Distribution 8 30.00

    Top, Distribution 7 30.00

    Over Lap 30 0.50

    Road side wall, Distribution ,(9+9) 18 30.00

    STP Boundary Side Wall, Distribution,(9+9)18 30.00

    Over Lap 72 0.50

    @ 0.395 kg/m, 15

    Marked

    Total Weight [A] + [B] =

    8

    (a) TMT bars.

    Noida Bound, Box DrainBetween RD.930 to 975.00(45m)

    Raft & Wall

    10mm Dia.

    Bottom, main 300 6.20

    Top, main 300 5.60

    Bottom, Chair 150 1.00

    Wall, U- Chair 44 0.60

    @ 0.617 kg/m, 37

    MarkedRaft & Wall

    8mm Dia.

    Bottom, Distribution 8 45.00

    Top, Distribution 7 45.00

    Over Lap 45 0.50

    Road side wall, Distribution ,(9+9) 18 45.00

    STP Boundary Side Wall, Distribution,(9+9)

    18 45.00

    Over Lap 105 0.50

    @ 0.395 kg/m, 23

    Marked

    Total Weight [A] + [B] =

    8

    (a) TMT bars.

    Noida Bound, Box Drain

    Between RD.975.00 to 1019.20 (44.20m)

    Raft & Wall

    10mm Dia.

    Reinforcement for RCC work including straightening, cutting,

    Reinforcement for RCC work including straightening, cutting,

  • 8/8/2019 IIIrd RA Bill Dallupura

    97/351

    Wall, U- Chair 44 0.60

    @ 0.617 kg/m, 37

    Marked

    Raft & Wall

    8mm Dia.

    Bottom, Distribution 8 44.20

    Top, Distribution 7 44.20

    Over Lap 43 0.50Road side wall, Distribution ,(9+9) 18 44.20

    STP Boundary Side Wall, Distribution,(9+9)

    18 44.20

    Over Lap 105 0.50

    @ 0.395 kg/m, 23

    Marked

    Total Weight [A] + [B] =

    8(a) TMT bars.

    Noida Bound, Box Drain

    Between RD.303.80 to 382.00

    Slab (13+1 Nos.)

    10mm Dia.

    Bottom, main 13x30 1.25

    Top, main 13x30 1.25

    Bottom, Chair 13x7 0.90

    Bottom, main 24 1.25

    Top, main 24 1.25

    Bottom, Chair 6 0.90

    @ 0.617 kg/m, 10

    Marked

    Slab

    8mm Dia.

    Bottom, Distribution 13x8 4.35

    Top, Distribution 13x8 4.35

    Bottom, Distribution 8 3.62

    Top, Distribution 8 3.62

    @ 0.395 kg/m, 9

    Marked

    Total Weight [A] + [B] =

    8

    (a) TMT bars.

    Noida Bound, Box Drain

    Between RD.382.00 to 460.00

    Slab (14 Nos.)

    10mm Dia.

    Reinforcement for RCC work including straightening, cutting,

    Reinforcement for RCC work including straightening, cutting,

  • 8/8/2019 IIIrd RA Bill Dallupura

    98/351

    @ 0.617 kg/m, 11

    Marked

    Slab

    8mm Dia.

    Bottom, Distribution 14x8 4.35

    Top, Distribution 14x8 4.35

    @ 0.395 kg/m, 9Marked

    Total Weight [A] + [B] =

    8

    (a) TMT bars.

    Noida Bound, Box Drain

    Between RD.460. to 540.00

    Slab (14 Nos.)

    10mm Dia.

    Bottom, main 14x30 1.25Top, main 14x30 1.25

    Bottom, Chair 14x7 0.90

    @ 0.617 kg/m, 11

    Marked

    Slab

    8mm Dia.

    Bottom, Distribution 14x8 4.35

    Top, Distribution 14x8 4.35

    @ 0.395 kg/m, 9

    Marked

    Total Weight [A] + [B] =

    8

    (a) TMT bars.

    Noida Bound, Box Drain

    Between RD.540.00 to 617.00

    Slab (14 Nos.)

    10mm Dia.

    Bottom, main 14x30 1.25

    Top, main 14x30 1.25

    Bottom, Chair 14x7 0.90

    @ 0.617 kg/m, 11

    Marked

    Slab

    8mm Dia.

    Bottom, Distribution 14x8 4.35

    Top, Distribution 14x8 4.35

    Reinforcement for RCC work including straightening, cutting,

    Reinforcement for RCC work including straightening, cutting,

  • 8/8/2019 IIIrd RA Bill Dallupura

    99/351

    8

    (a) TMT bars.

    Noida Bound, Box Drain

    Between RD.617.00 to 695.00

    Slab (14 Nos.)

    10mm Dia.

    Bottom, main 14x30 1.25

    Top, main 14x30 1.25Bottom, Chair 14x7 0.90

    @ 0.617 kg/m, 11

    Marked

    Slab

    8mm Dia.

    Bottom, Distribution 14x8 4.35

    Top, Distribution 14x8 4.35

    Wall

    Road side wall, Distribution ,(1+1) 2 20.00STP Boundary Side Wall, Distribution,(1+1)

    2 20.00

    Over Lap 4 0.50

    @ 0.395 kg/m, 10

    Marked

    Total Weight [A] + [B] =

    8

    (a) TMT bars.

    Noida Bound, Box Drain

    Between RD.695.00 to 775.00

    Slab (14 Nos.)

    10mm Dia.

    Bottom, main 14x30 1.25

    Top, main 14x30 1.25

    Bottom, Chair 14x7 0.90

    @ 0.617 kg/m, 11

    Marked

    Slab

    8mm Dia.

    Bottom, Distribution 14x8 4.35

    Top, Distribution 14x8 4.35

    Wall

    Road side wall, Distribution ,(1+1) 2 80.00

    STP Boundary Side Wall, Distribution,(1+1)

    2 80.00

    Over Lap 24 0.50

    @ 0.395 kg/m, 13

    Reinforcement for RCC work including straightening, cutting,

    Reinforcement for RCC work including straightening, cutting,

  • 8/8/2019 IIIrd RA Bill Dallupura

    100/351

    8

    (a) TMT bars.

    Noida Bound, Box Drain

    Between RD.775.00 to 850.00

    Slab (14 Nos.)

    10mm Dia.

    Bottom, main 14x30 1.25

    Top, main 14x30 1.25

    Bottom, Chair 14x7 0.90

    @ 0.617 kg/m, 11

    Marked

    Slab

    8mm Dia.

    Bottom, Distribution 14x8 4.35

    Top, Distribution 14x8 4.35

    Wall

    Road side wall, Distribution ,(2+2) 4 75.00

    STP Boundary Side Wall, Distribution,(2+2)4 75.00

    Over Lap 40 0.50

    @ 0.395 kg/m, 15

    Marked

    Total Weight [A] + [B] =

    8

    (a) TMT bars.

    Noida Bound, Box Drain

    Between RD.850.00 to 930.00

    Slab (13+1 Nos.)

    10mm Dia.

    Bottom, main 13x30 1.25

    Top, main 13x30 1.25

    Bottom, Chair 13x7 0.90

    Bottom, main 19 1.25

    Top, main 19 1.25

    Bottom, Chair 5 0.90

    @ 0.617 kg/m, 11

    Marked

    Slab

    8mm Dia.

    Bottom, Distribution 13x8 4.35

    Top, Distribution 13x8 4.35

    Bottom, Distribution 8 2.88

    Top, Distribution 8 2.88

    Wall

    Road side wall, Distribution ,(2+2) 4 80.00

    STP Boundary Side Wall, Distribution,(2+2)

    Reinforcement for RCC work including straightening, cutting,

    Reinforcement for RCC work including straightening, cutting,

  • 8/8/2019 IIIrd RA Bill Dallupura

    101/351

    @ 0.395 kg/m, 16

    Marked

    Total Weight [A] + [B] =

    8

    (a) TMT bars.

    Noida Bound, Box Drain

    Between RD.930.00 to 967.00

    Slab (6 Nos.+1 Nos. Culvert)10mm Dia.

    Bottom, main 6x30 1.25

    Top, main 6x30 1.25

    Bottom, Chair 6x7 0.90

    Bottom, Distribution, Culvert 7 7.05

    Top, Distribution, Culvert 7 7.05

    Bottom, Chair, Culvert 7 1.00

    @ 0.617 kg/m, 5

    MarkedSlab

    8mm Dia.

    Bottom, Distribution 6x8 4.35

    Top, Distribution 6x8 4.35

    Wall

    Road side wall, Distribution ,(3+3) 6 37.00

    STP Boundary Side Wall, Distribution,(3+3)

    6 37.00

    Over Lap 36 0.50

    @ 0.395 kg/m, 8

    Marked

    Culvert

    16mm Dia.

    Bottom, main 45 1.20

    Top, main 45 1.20

    @ 0.617 kg/m, 1

    Marked

    Total Weight [A] + [B] +[C] =

    8

    (a) TMT bars.

    Noida Bound, Box Drain

    Between RD.974.10 to 1019.20

    Slab (8 Nos.)

    10mm Dia.

    Bottom, main 8x30 1.25

    Top, main 8x30 1.25

    Bottom, Chair 8x7 0.90

    Reinforcement for RCC work including straightening, cutting,

    Reinforcement for RCC work including straightening, cutting,

  • 8/8/2019 IIIrd RA Bill Dallupura

    102/351

    8mm Dia.

    Bottom, Distribution 8x8 4.35

    Top, Distribution 8x8 4.35

    Wall

    Road side wall, Distribution ,(3+3) 6 45.10

    STP Boundary Side Wall, Distribution,(3+3)

    6 45.10

    Over Lap 36 0.50

    @ 0.395 kg/m, 1

    Marked

    Total Weight [A] + [B] =

    8

    (a) TMT bars.

    Noida Bound, Box Drain

    Between RD.974.10 to 1019.20

    Slab (8 Nos.)

    10mm Dia.Bottom, main 8x30 1.25

    Top, main 8x30 1.25

    Bottom, Chair 8x7 0.90

    @ 0.617 kg/m, 11

    Marked

    Slab

    8mm Dia.

    Bottom, Distribution 8x8 4.35

    Top, Distribution 8x8 4.35

    Wall

    Road side wall, Distribution ,(3+3) 6 45.10

    STP Boundary Side Wall, Distribution,(3+3)

    6 45.10

    Over Lap 36 0.50

    @ 0.395 kg/m, 1

    Marked

    Total Weight [A] + [B] =

    8

    (a) TMT bars.

    16mm Dia.

    Culvert at Dallupura Mkt.

    Bottom, main 39 1.15

    Top, main 39 1.15

    Culvert at Bhudh Singh Chowk

    Bottom, main 36 1.34

    Top, main 36 1.34

    @ 1.579 kg/m, 1

    Reinforcement for RCC work including straightening, cutting,

    Reinforcement for RCC work including straightening, cutting,

  • 8/8/2019 IIIrd RA Bill Dallupura

    103/351

    Bottom, Distribution 7 5.65

    Top, Distribution 7 5.65

    Bottom, Chair 8 1.05

    Culvert at Bhudh Singh Chowk

    Bottom, Distribution 8 3.75

    Top, Distribution 8 3.75

    Bottom, Chair 6 1.05

    @ 0.617 kg/m,Marked

    Total Weight [A] + [B] =

  • 8/8/2019 IIIrd RA Bill Dallupura

    104/351

    D or H Quantity Unit

    396.20 m

    22.24 "105.00 "

    Total 523.44 m

    23.44 x1.579= 826.51 kg.

    [A] 826.51 kg.

    406.60 m

    206.00 "

    25.20 "

    Total 637.80 m37.80 x 0.617= 393.52 kg.

    [B] 393.52 kg.

    1220.03 kg.

    396.20 m

    22.24 "

    105.00 "

    Total 523.44 m

    23.44 x1.579= 826.51 kg.

    [A] 826.51 kg.

    406.60 m

    206.00 "

    25.20 "

    Total 637.80 m

    637.8 x 0.617= 393.52 kg.

    [B] 393.52 kg.

    1220.03 kg.

  • 8/8/2019 IIIrd RA Bill Dallupura

    105/351

    22.24 "

    105.00 "

    Total 523.44 m

    23.44 x1.579= 826.51 kg.

    [A] 826.51 kg.

    406.60 m

    206.00 "25.20 "

    Total 637.80 m

    637.8 x 0.617= 393.52 kg.

    [B] 393.52 kg.

    1220.03 kg.

    12.40 m

    12.00 "

    17.10 "

    297.15 m

    16.68 "

    78.75 "Total 434.08 "

    34.08 x1.579= 685.41 kg.

    [A] 685.41 kg.

    38.00 m

    4.20 "

    304.95 m

    154.50 "

    18.90 "

    Total 520.55 m

    20.55 x 0.617= 321.18 kg.

    [B] 321.18 kg.

    1006.59 kg.

  • 8/8/2019 IIIrd RA Bill Dallupura

    106/351

    105.00 "

    Total 523.44 m

    23.44 x1.579= 826.51 kg.

    [A] 826.51 kg.

    406.60 m

    206.00 "

    25.20 "Total 637.80 m

    637.8 x 0.617= 393.52 kg.

    [B] 393.52 kg.

    1220.03 kg.

    396.20 m

    22.24 "

    105.00 "

    Total 523.44 m

    23.44 x1.579= 826.51 kg.

    [A] 826.51 kg.

    406.60 m

    206.00 "

    25.20 "

    Total 637.80 m

    637.8 x 0.617= 393.52 kg.

    [B] 393.52 kg.

    1220.03 kg.

    396.20 m

    22.24 "

    105.00 "

    Total 523.44 m

    23.44 x1.579= 826.51 kg.

    [A] 826.51 kg.

  • 8/8/2019 IIIrd RA Bill Dallupura

    107/351

    Total 637.80 m

    637.8 x 0.617= 393.52 kg.

    [B] 393.52 kg.

    1220.03 kg.

    112.80 m

    297.15 m

    16.68 "

    78.75 "

    Total 505.38 "

    05.38 x1.579= 798.00 kg.

    [A] 798.00 kg.

    114.76 m

    4.20 "

    304.95 m

    154.50 "

    18.90 "

    Total 597.31 m

    97.31 x 0.617= 368.54 kg.

    [B] 368.54 kg.1166.54 kg.

    396.20 m

    22.24 "

    105.00 "

    Total 523.44 m

    23.44 x1.579= 826.51 kg.

    [A] 826.51 kg.

    406.60 m

    206.00 "

    25.20 "

    Total 637.80 m

    637.8 x 0.617= 393.52 kg.

  • 8/8/2019 IIIrd RA Bill Dallupura

    108/351

    396.20 m

    22.24 "

    105.00 "Total 523.44 m

    23.44 x1.579= 826.51 kg.

    [