ieng 451
DESCRIPTION
IENG 451. JIT. Production Physics. Little’s Law Throughput = WIP/Cycle time For fixed capacity, cycle time and WIP or proportional – thus you can increase throughput either by increasing WIP or by decreasing cycle time . Production Physics. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/1.jpg)
IENG 451
JIT
![Page 2: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/2.jpg)
Production Physics
• Little’s LawThroughput = WIP/Cycle time
• For fixed capacity, cycle time and WIP or proportional – thus you can increase throughput either by increasing WIP or by decreasing cycle time
![Page 3: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/3.jpg)
Production Physics
• Law of variability – increasing variability inevitably degrades the performance of the system
• Law of variability buffering – variability in a production system will be buffered by some combination of inventory, capacity, or time
![Page 4: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/4.jpg)
JIT Principles
• Don’t produce something unless a customer has ordered it
• Level demand so that work may proceed smoothly throughout the plant
• Link all processes to customer demands through visual tools (kanbans)
• Maximize the flexibility of people and machinery
![Page 5: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/5.jpg)
Pull Systems
• Nobody upstream produces a good or a service until somebody downstream asks for it
![Page 6: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/6.jpg)
Pull Systems
• Nobody upstream produces a good or a service until somebody downstream asks for it
![Page 7: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/7.jpg)
Pull Systems
• Nobody upstream produces a good or a service until somebody downstream asks for it
![Page 8: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/8.jpg)
Kanban Rules
• Never ship defective items• Customer withdraws only what is needed • Produce only quantity withdrawn by the
customer • Level production • Use kanban to fine-tune production• Stabilize and strengthen the process
![Page 9: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/9.jpg)
Production orders
• Batch of 10 vs Batch of 100– Adjust more quickly to demand– Better sense of takt time– Fewer peaks and valleys– Better control of abnormality production
![Page 10: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/10.jpg)
Pull Systems
• Type A– Frequent orders with short lead times, most
common, replenishing gaps created in the finished goods storage
• Type B– Infrequent orders or long lead times, pacemaker is usually
midstream • Type C– Combination of type A and type B running in parallel
![Page 11: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/11.jpg)
Process Flow Tools
• Process Mapping • SIPOC – Supplier, Inputs, Process, Outputs, Customers
• Spaghetti diagrams• Swim Lane flow charts• Value Stream Mapping
![Page 12: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/12.jpg)
![Page 13: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/13.jpg)
![Page 14: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/14.jpg)
![Page 15: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/15.jpg)
SIPOC Charts
![Page 16: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/16.jpg)
![Page 17: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/17.jpg)
![Page 18: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/18.jpg)
![Page 19: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/19.jpg)
![Page 20: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/20.jpg)
![Page 21: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/21.jpg)
![Page 22: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/22.jpg)
Value Stream Mapping
• VSM helps grasp current condition and identify improvement opportunities
• Improvement events create localized improvements; VSM provides a vision and plans that connect all improvement activities
• VSM allows you to see waste and plan to eliminate it
![Page 23: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/23.jpg)
What is VSM
• Planning tool to optimize results of reducing waste
![Page 24: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/24.jpg)
Five Principles for VSM
• Specify value from end customer standpoint• Identify value stream for each product family• Make the product flow• Customer pulls the system • Manage towards
perfection
![Page 25: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/25.jpg)
Value to Customer ?
• How does current product / process disappoint customers value expectation:– Price ?– Quality ?– Delivery ?
![Page 26: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/26.jpg)
What Flows
• Manufacturing; materials are the items that flow
• Design & development; designs flow• Service; customer needs are the items• Administration; internal customer needs are
the items
![Page 27: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/27.jpg)
![Page 28: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/28.jpg)
![Page 29: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/29.jpg)
![Page 30: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/30.jpg)
![Page 31: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/31.jpg)
![Page 32: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/32.jpg)
Current State (Manuf.)
![Page 33: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/33.jpg)
Future State – (Manuf.)
![Page 34: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/34.jpg)
![Page 35: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/35.jpg)
![Page 36: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/36.jpg)
VSM Steps
• Determine the individual product or service you will map
• Draw the process flow
![Page 37: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/37.jpg)
VSM Steps
• Add material flow
![Page 38: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/38.jpg)
VSM Steps
• Add Information flow
![Page 39: IENG 451](https://reader036.vdocuments.site/reader036/viewer/2022070422/568165f8550346895dd921e0/html5/thumbnails/39.jpg)
VSM Steps• Collect process data and connect it to boxes on chart • Add process and lead times