iemr-oil & gas transmission & distribution pipelines
TRANSCRIPT
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
1/78
INTRODUCTION TOHYDROCARBON PIPELINES
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
2/78
OIL & GAS PIPELINES
Crude oil is often transported between
continents in large tankers, but oil and natural3
gas is transported (transmitted) across
continents by pipelines.
Transmission pipelines are the main arteries
of the oil and gas business
Pipelines are 40 times safer than rail tanks, and
100 times safer than road tanks for transportingenergy
According to the USA Association of Oil
Pipelines, Oil pipeline spills amount to about 1
gallon per million barrel-miles
Source: Oil & Gas Pipeline By Phil Hophinks (Penspen
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
3/78
WHY WE ALL SHOULD BE INTERESTED
IN PIPELINES
We rely on pipelines to deliver our energy needs, but everyone is astakeholder in oil and gas transportation:
Pipeline operators (transporters) want a safe, reliable supply, and a
reasonable profit;
The general public (consumers) want cheap gasoline, natural gas, etc.,
delivered reliably and safely, with minimal environmental damage;
Shippers (producers) want cheap, reliable supplies and transportation,
and a reasonable profit;
Regulators want a fair and competitive market;
Government groups want safe, environmentally-friendly, delivery;
Advocacy groups (focussing on environmental, cultural, etc., aspects)
have focussed interests;
The biggest challenge facing the pipeline engineer today and tomorrow is
safetySource: Oil & Gas Pipeline By Phil Hophinks (Penspen
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
4/78
TYPES OF HYDROCARBON
PIPELINES
These pipelines are made from high quality steel (line pipe steel), constructed
using well-established methods, and operated using procedures developed over
many decades.Source: Oil & Gas Pipeline By Phil Hophinks (Penspe
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
5/78
PIPELINE COMPONENTS Metallic pipes
Ordinary steel pipe
Corrugated
Cast-iron
Ductile-iron
Stainless steel
Aluminum Copper
Non metallic pipes
Plastic
Rubber and elastomer
Glass
Tubings & pipe designation
Connections
Fittings
Pressure relief and pressure regulating valves
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
6/78
METALLIC PIPES Metallic pipes are stronger and tougher to break but they have
disadvantages like more sensitive to heat and electricity,
corrosion sensitive
More conductive to heat and electricity.
Following are some of the commercial metal pipelines:
1. Ordinary (Wrought ) steel pipelines seamed or seamless Seamed made up of steel sheets/plates rolled into circular
shape, with edge of each pipe closed by welding
Different types welding are-
1) Butt Welding2) Lap Welding
3) Electric Arc Welding (Single or Double Welded joint)
Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
7/78
CORRUGATED STEEL PIPE
Thin-wall, large-diameter, made of galvanized steel sheetshaving either helical or annular corrugations
Used extensively in sewer and drainage systems
Flow is often gravity flow rather than pressure flow.
Have large variety of fittings and great range of sizes.
Some fabricated to have a pecan-shaped instead of circular
cross section
Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
8/78
CAST-IRON PIPE
Two types: ordinary or gray cast-iron pipe, and the ductile-iron pipe.
The ordinary cast-iron pipe made of iron containing 3 to
4% of carbon in the form of graphite flakes.
Gray cast-iron pipe has relatively strong corrosion-resistance ability and long life
Two strength designations: 18/40 and 21/45.
18 means that the min bursting tensile strength is 18,000
and 40 means that the min modules of rupture is 40,000psi.
Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
9/78
DUCTILE-IRON PIPE
Made of iron containing 3.5% carbon in sheroidal ornodular form, and a magnesium alloy
Has the advantage of gray cast-iron pipe (corrosion
resistance and long life) and steel pipe (ductility).
Strength designation is 60/42/10
Min tensile strength of 60,000psi
Min yield strength of 42,000 psi
10% min elongation
Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
10/78
STAINLESS STEEL PIPE
Contains chrome-nickel alloys
300 series such as SS304 or SS316, are the most used stainless
steel pipes.
Corrosion resistant
High price, used only in special applications such as:
When the fluid or environment is corrosive
When no rusting of pipe can be tolerated such as in
pharmaceutical or food industries.
Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
11/78Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
12/78
NON METALLIC PIPES
Not as strong as metallic pipes
Light in weight
More economical
Certain advantages such as being more corrosion resistant.
The one used in oil and gas is plastic pipes.
Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
13/78
PLASTIC PIPES 3 types of plastic pipes commonly used
PVC (Polyvinyl chloride) PE (polyethylene)
PP (polypropylene)
Used for
Water Waste water
Natural gas
Other fluids that do not dissolve or chemically interact with
plastics Deform easily
Expand 5 times as much as steel due to temperature
Becomes brittle in very cold weather
Long term performance not known
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
14/78
Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
15/78
CONNECTIONS (JOINTS)
Bonded joints-welding, brazing or soldering and fusing.
Threaded joints-connecting threaded pipe sections together
Flanges-provide strong joint without permanently joining the
pipe sections.
Mechanical joints-for ease in assembly/disassembly
Bell-and-spigot-used in pressure concrete pipes, glass and
plastic pipes also use
Push-on-connected together simply by pushing two pipe
sections against each other
Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
16/78
Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
17/78
VALVES
Gate valve
Closed/opened by turning handle connected to it Takes many turns to completely open or close a gate valve
Head loss is small when gate fully opened
Maybe a wedge or a disk or a knife
Has a conduit with a full round bore for smooth passage ofpigs
Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
18/78
VALVES
Globe valve
Outside is globe shaped
Flow changes direction as it goes through the valve
Large head loss when valve fully opened
Gives better control or flow than gate valves-good for flow
throttling
Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
19/78
VALVES
Check valves Flow cannot reverse through a check valve, unidirectional
flow
3 types of check valves are swing check, tilt disk, ball check
valve.
Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
20/78
Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
21/78
PIPELINE CONSTRUCTION
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
22/78
Following are reference/codes followed during Laying ofpipeline & Line-pipe coating:
1. API 1105 : Construction practices for Oil & Productpipelines
2. ASME B 31.4 : Pipeline transportation System for liquidHydrocarbon
3. ASME B 31.8 : Gas Transmission & Distribution PipingSystem
4. OISD B 141 : Design & Construction requirement forcross country Hydro Carbon Pipelines
5. API 6 D : Construction & Inspection of valves
6. API 1104 : For welding of pipeline & related activities
7. DIN 30670 : For 3LPE coating for line pipes
CODES & STANDARDS
Source: eil.co.in/ eil specification
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
23/78
1. ROU (Right of Use) SURVEY
2. ROU CLEARING AND GRADING3. STRINGING
4. TRENCHING
5. BENDING
6. WELDING7. FIELD JOINT COATING
8. LOWERING
9. BACKFILLING
10.CROSSING
11. HYDROTESTING
12. PIPELINE MARKERS, CLEAN UP & RESTORATION
13. MAGNETIC PIGGING & EGP PRE COMMISSIONINGACTIVITY
PIPELINE LAYING ACTIVITIES
Source: eil.co.in/ eil specification
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
24/78
ROU Survey, ROU Clearing and
Grading, Stringing
Source: eil.co.in/ eil specification
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
25/78
1. ROU (Right of Use) SURVEY:
Installation of Bench Marks, Turning Points
Stake markers in center line of pipeline at a distance of max100m for center line and for horizontal bends 10 m and
reference point for same
Stake two ROU markers at least at every 100m, Painted in Red
and numbers in white in direction of flow
Chainage markers at every 250m
2. ROU CLEARING AND GRADING
All obstacles causing hindrance in construction / laying pipeline
are removed Entire ROU is Graded for movement of equipments and vehicle
Temporary approaches/bridges, if required, are constructed for
movement of equipments, vehicles & personnels
Source: eil.co.in/ eil specification
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
26/78
3. STRINGING
Stringing shall be done after blasting & trenching when
ROU is in rocky area
Coating pipes shall be strung on approved soft earth/sand
filled bag and wedge in such a way that bottom of coated
pipe remain above ground
Pipes shall be supported at minimum two locations
Pipe number, Heat number, coat number & length shall be
transferred and recorded in serial order
Source: eil.co.in/ eil specification
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
27/78
Trenching
Source: eil.co.in/ eil specification
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
28/78
4. TRENCHING
Trench excavation is carried out along staked centerline of
Pipeline.
The width of excavation for trench shall be minimum(pipe diameter
plus 200 mm either side).
Depth of trench shall be specified (Normal =1M;
Road=1.2M;River=1.5M,Rly=1.7M etc.
In case of trenching in rocky areas, blasting is performed with the
guidelines/Safety Rules Of CCOE, Nagpur.
In case where rock/gravel or hard soil is encountered in the bottom
of the trench, padding material(minimum compacted thickness of
150mm) shall be provided.
When up floating of the pipeline after backfilling is anticipitated &
anti-buoyancy measures are provided in such areas e.g. by
installing saddle weight
Source: eil.co.in/ eil specification
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
29/78
Welding
Manual Welding
Automatic WeldingSource: eil.co.in/ eil specification
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
30/78
5. WELDING
Automated welding involves using mechanical or electronicmeans to control welding conditions such as welding current,
arc length, filler wire, or electrode feed, as well as travelspeeds. Movement and guidance of the electrode, torch orwelding head along the line of weld can be similarlycontrolled.
Advantages of automated welding1. A less experienced operator can handle the welding machine andhave satisfactory end results.
2. A smaller percentage of welding electrodes is lost in stub ends. Amuch shorter arc is uniformly maintained by the automated
welding process than is possible by a manual operator.3. A much higher current can be used with a given size of welding
wire to produce better fusion. A much higher welding speed canalso be obtained.
Source: eil.co.in/ eil specification
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
31/78
6. BENDING
For changes in vertical &
horizontal alignment, prefabricated
coal field bends are provided. Over bends are made in a manner
that centre of bend clears the
highest point of trench bottom. Sag
bend shall fit the bottom of trench.
Side bends shall have specified
clearance to the outside wall of
trench.
The radius of coal field bend shall
be not more than 40 times the dia.of pipe(for 18 and above) and 30
times the dia. of pipe(for 17
below)
Source: eil.co.in/ eil specification
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
32/78
7. FIELD JOINT COATING The cut-back areas of Coated
Pipes where weld joints are
made to be coated by fieldjoint coating.
Field joint coating material isheat shrinkable wraparoundsleeve used as anticorrosioncoating of buried onshorepipeline.
Sleeve consist of radiationcross-linked thermallystabilized, ultraviolet resistantsemi rigid polyolefin backingwith a uniform thickness ofhigh shear strengththermoplastic melt adhesive.
Source: eil.co.in/ eil specification
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
33/78
The joint coating system shall consist of a solvent free epoxy
primer applied to pipe surface prior to sleeve application. The
surface area is blast cleaned to SA-2.5 followed by pre
heating of pipe surface, application of epoxy primer andapplication of sleeve by heat shrinking.
One out of 50 joints coating or one coating out of every day
production shall be tested to establish peel strength on steel
and factory applied coating.
Source: eil.co.in/ eil specification
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
34/78
Lowering
Source: eil.co.in/ eil specification
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
35/78
8. LOWERING
Lowering shall commence after inspection of trench
Lowering shall commence as soon as possible after
completion of joint coating The pipeline must be laid without interruption for the
whole or the length of section available
Ends of the lowered pipeline section shall be closed with
night cap to prevent ingress of water, mud etc.
Source: eil.co.in/ eil specification
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
36/78
9. BACKFILLING
Backfilling shall be carried outimmediately after pipelinelowering in trench after
inspection, so as to provide anatural anchoring for pipeline.
Backfilling material shall notcontain any extraneousmaterial or hard lumps of soilwhich can damage pipeline or
coating or leave the voids inbackfilled trench
If trench are excavated insteep area where the slope ismore than 10%, slopebreakers shall be installed toprevent erosion of backfill,stabilization of backfill shall bedone in sandy area to haveconsolidated cover over thepipeline
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
37/78
Crossing
CROSSING
Cased & Un-cased
crossings for Roads &
Railways
Open cut & Horizontal
Directional Drilling (HDD) forminor & major river crossing
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
38/78
11. HYDROTESTING
After the acceptance of gauging operation, uninhabitedwater is pumped into the section using four cup batching
pigs which are launched at specific intervals.After water filling the thermal equilibrium is maintained
between pipeline & environment using thermocouples.
After thermal stabilization, pressurization is carried out in
cycles at 50% test pressure & 75% test pressure andheld for 1 hr at each test pressure and depressurized tozero pressure & then pressurized to final pressure.
The test shall be considered positive if pressure has
kept a constant value throughout the test duration,except for change due to temperature effects. Thepressure value thus added shall be compared with initialvalue and test shall be considered as acceptable ifdifference is less than to 0.3 bar
Source: eil.co.in/ eil specification
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
39/78
Hydro Testing
Source: eil.co.in/ eil specification
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
40/78
12. PIPELINE MARKER, CLEAN UP &
RESTORATION
Following markers shall be installed along pipeline route such that
they do not caught any hindrance to regular land user and traffic.
Aerial Markers - At every 5 Kms
Kilometer Markers - At every 1 Kms as per Alignment
sheet
Pipeline Warning Markers - At Road/Railways/CrossingROU Boundary Markers - At every 750 m as per
alignment sheet
Navigational Markers - At bank of navigational course
On completion clean up of pipelines ROU shall be restored to suchstable and unstable as may be reasonably consistent with the
condition of ROU prior to laying of Pipeline
Source: eil.co.in/ eil specification
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
41/78
13. MAGNETIC PIGGING & ELECTRONIC GEOMETRICPIGGING
This is a part of pre-commissioning activity, which ensure thatthere is no deformity in pipeline. This is done prior to filling line
with the product. Magnetic PIG loaded with high capacity magnets spread uniformly
with high density polyethylene four cup PIG is launched to removeferrous debris, mill scale, electrode pieces etc. The accumulatedweight of ferrous debris is checked after running the PIG throughpipeline section. When the collected weight of ferrous debris iswithin limit for specific length of pipeline section, the line is ready forlaunching Electronic Geometric Pigging (EGP) tool.
After successful completion of magnetic pig run EGP tool islaunched. The tool is mounted with battery operated battery device,which give the reduction in pipeline Dia. At specific location in
electronic form. Defect upto more than 3% internal diameter of pipe is physically
verified at site. Defect of more than 5% internal diameter of pipe arerepaired by cutting suitable length of pipe and re-welding.
Source: eil.co.in/ eil specification
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
42/78
Horizontal Directional Drilling (HDD) is a trenchless excavation processthat provides the installation of pipelines beneath a wide range of
surface obstacles like Rivers, Highways, Railway Xings, and Right ofWays through Developed Areas etc.
It offer a number of benefits over traditional open-cut methods.
It can be implemented with very little disruption to Surface activities,requires less working space, and quicker than Open-cut methods.
Equipm ent required for HDD are -
1. A rig, which provides the physical means thrust and torque, to open thehole and pull in the product.
2. A transmitter/receiver system for tracking the location of the bore.
3. The down-hole equipment - drill pipe, drill bits, and reamers, whichconverts the physical properties of the rig to open the hole and pull in theproduct.
4. The drilling fluid, which serves to stabilize the hole, cool the down-hole5. equipment, and remove the spoils from the hole.
6. The drilling fluid delivery and recovery system made up of tanks, mixingsystems, pumps; and, when recycling fluids, a system of screens, filters,
7. Shakers, cones, etc. to remove spoils brought to the surface from the fluid.
Continue..
HORIZONTAL DIRECTIO NAL DRILLING
Source: Trenchless Technologies Ltd (website)
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
43/78
The HDD process begins with boring a small, horizontal hole(Pilot Hole) under the crossing obstacle (i.e. a River) with acontinuous string of steel drill rod, using technology thatallows the drill to be steered and tracked from the surface.
When one of the key considerations in the design of the drill-path is creating as large a radius of curvature as possiblewithin the limits of the right-of-way.
The Curvature requirements are dependent on site geometrycrossing length, required depth to provide safe cover, stagingsite location, etc.
The Drilling operation consists of using an appropriate tool toopen the pilot hole to a slightly larger diameter than the
carrier pipeline. The percentage oversize depends on many variables
including soil types, soil stability, depth, drilling mud, boreholehydrostatic pressure, etc. Normal over-sizing Varies from120% to 150% of the carrier pipe diameter
Continued..
HORIZONTAL DIRECTIO NAL DRILLING
Source: Trenchless Technologies Ltd (website)
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
44/78
Enlarging the pilot hole is accomplished using pre-reamingpasses prior to pull back.
Pre-reaming tools are typically attached to the drill pipe at theexit point. The reamers are then rotated and drawn to the drillingrig thus enlarging the pilot hole. Drill pipe is added behind thereamers as they progress toward the drill rig in pull backoperation. This insures that a string of pipe is always maintained
in the drilled hole. Reaming tools typically consist of a circulararray of cutters and drilling fluid jets. Drilling fluid is pumpedthrough the reamers to aid in cutting, support the reamed hole,and lubricate the trailing pipe.
Pull-Back Operation - Involves pulling the entire pipeline lengthin one segment
back through the drilling mud along the reamed-hole pathway.Axial tension force readings, constant insertion velocity, mud flowcirculation/exit rates, and footage length installed should berecorded. The pullback speed ranges usually between 1 to 2 feetper minute. A swivel is utilized to connect the pull section to theleading reamers to minimize torsion transmitted to the pipeline.
HORIZONTAL DISTANCE DRILLING
Source: Trenchless Technologies Ltd (website)
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
45/78
PIGGING, INSPECTION
&CORROSION CONTROL
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
46/78
PIG stands for Pipeline Intervention Gadget/ PipelineInspection Guage
A pig is a device inserted into a pipeline which travels
freely through it, driven by the product flow to do a specific
task within the pipeline Functional Classification of pigs:
(a) Utility pigs which perform a function such as cleaning,
separating products in-line or dewatering the line
(b) Inline inspection pigs which are used to provideinformation on the condition of the pipeline and the extent and
location of any problem (such as corrosion for example) and
(c) Special Duty Pigs such as plugs for isolating pipelines.
PIGGING
Source: www.ppsa-online.com
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
47/78
Pigging is a maintenance tool
During the construction of the line, pigs can be used toremove debris that accumulates
During Hydro-testing, pigs are used to fill the line withwater and subsequently to dewater the line after the
successful test During operation, pigs can be used to remove liquid
hold-up in the line, clean wax off the pipe wall or applycorrosion inhibitors
Inspection pigs are used to assess the remaining wallthickness and extent of corrosion in the line, thusproviding timely information for the operator regardingthe safety and operability of the line
PURPOSE OF PIGGING
Source: www.ppsa-online.com
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
48/78
Offshore pipelines are of thicker wall than onshore-sometimes up to
35mm thick. Offshore pipelines can have greater operating pressures, particularly
the deepwater pipelines - Maximum operating pressures onshore cabe 100bar(GP) but offshore can be 300bar(GP)
Flow rates of products both onshore and offshore are the samedependant upon the type of pipeline or its position with regard totransporting product either between offshore platforms or fromplatform to shore.
Offshore pipelines tend to be protected by a concrete outer coatingand sacrificial anodes fitted to the pipeline every 100 metres so theoutside of offshore pipelines tend not to suffer corrosion but may get
damaged by sea bed movement or anchors from ships Generally running pigs in offshore pipelines is very similar to running
in onshore lines
One very important thing to realise with offshore inspection is that thepig must not get stuck in the pipeline as retrieving it will be muchmore expensive than from an onshore pipeline
ONLINE & OFFLINE PIPELINE PIGGING
Source: www.ppsa-online.com
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
49/78
The main inspection techniques used are
Magnetic Flux Leakage1. MFL is an inferred method where a strong magnetic flux is
induced into the pipeline wall. Sensors then pick up any leakage
of this flux and the extent of this leakage indicates a flaw in the
pipe wall. For instance, internal material loss in the line will cause
flux leakage that will be picked up by the sensors.2. Defect libraries are built up to distinguish one defect from another.
Ultrasonic Inspection
1. Ultrasonic inspection is a direct measurement of the thickness of the pipe
wall. A transducer emits a pulse of ultrasonic sound that travels at a
known speed. The time taken for the echo to return to the sensor is a
measurement of the thickness of the pipe wall.
2. The technique needs a liquid through which the pulse can travel. The
presence of any gas will affect the output.
INSPECTION TECHNIQUES
Ultrasonic can inspect very thick wall pipe but magnetic flux is limited because
of how strong the magnets need to be to get enough magnetism in the wall
of the pipe to enable good results to be obtained.
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
50/78
Corrosion is an electrochemical reaction requiring
the following conditions to be met :
1. There must be an anode and a cathode.
2. There must be an electrical potential between the anode
and the cathode.
3. There must be a metallic path between the anode and the
cathode. Normally this will be the pipeline itself.
4. The anode and the cathode must be immersed in an
electrically conductive electrolyte which is ionized -
meaning that some of the water molecules are brokendown intp positively charged hydrogen ions (H+) and
negatively charged hydroxyl ions (OH-).The usual soil
moisture surrounding pipelines normally fulfils this
condition.
CORROSION
Source: VC Pipeline Protection Ltd.
CORROSION
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
51/78
Once these conditions are met , an electric current will flow and metal will
be consumed .
The pressure exerted by the potential difference between the anode and
the cathode results in migration of electrons from the anode to the
cathode along the metallic connection between the anode and cathode.
Anode Loss of electrons positive charged iron atom combine with
OH- FE(OH)2 Further reacts to form Fe2(OH)3 which is familiar
RUST.
At the cathode , a surplus of electrons arrives from the anode. These
surplus negatively charged electrons combine with positively charged
hydrogen ions from the environment to form hydrogen (H2).
CORROSION
Source: VC Pipeline Protection Ltd.
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
52/78
CORROSION
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
53/78
Earth buried pipelines are usually expensive investments . In order
to defend against the threat of corrosion they are protected by
coatings and coverings.
However, the smallest damage of the coating or any cracks in the
covering steadily lead to pitting corrosion.
Corrosion causes an electrochemical reaction which leads to loss of
metal. As a result pipelines become leaky and can cause enormousdamage to property and environment.
The expected lifespan of a pipeline network is, depending on the
transport medium, a minimum of 50 years. However, a pipeline
should be functional for up to 100 years. Cathodic corrosion
protection offers an optimum of safety and efficiency because
With a cathodic protection system pipelines can be operated even in
critical soils reliably.
CORROSION
Source: VC Pipeline Protection Ltd.
PRINCIPLES OF CORROSION CONTROL
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
54/78
There are two possibilities for designing an activecorrosion
protection system of earth buried pipelines:
1. Cathodic protection with impressed current.
2. Cathodic Corrosion Protection with a galvanic anodes
system.
PRINCIPLES OF CORROSION CONTROL
Source: VC Pipeline Protection Ltd.
Cathodic Protection with an
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
55/78
Current is produced by a RECTIFIER and transmitted by foreign current
anodes to the earth buried object to be protected.
The advantage of this method lies primarily in the possibility that the
output voltage can be regulated depending on the soil resistance and the
protecting current requirements of the pipeline.
Furthermore cathodic corrosion protection with an impressed currentsystem enables automatic recording of the state of the pipeline and thereby
possible irregularities can be immediately recognised and remedied .
Cathodic Protection with an
Impressed Current Protection System
Source: VC Pipeline Protection Ltd.
Cathodic Protection with an Impressed
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
56/78
The anodes which are used for the protective current Supply
can be built horizontally or vertically in the ground.
Primarily FeSi anodes used, either single or pre-finished as
canister anode with backfill.
The effectiveness of the cathodic protection system is
monitored through potential mapping through permanent
reference cells at measuring points and then sent to the
rectifier station for an internal comparison with preset
thresholds.
The cable connections of the pipeline, rectifier and reference
electrode come together at the measuring station too.
Cathodic Protection with an Impressed
Current Protection System
Source: VC Pipeline Protection Ltd.
Cathodic Corrosion Protection With a
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
57/78
For smaller objects or those where a power supply with rectifier is difficult
(e.g. in less conductive grounds) cathodic protection with galvanic anodesis used.
The method is based on the difference between the anode material and the
object to be protected.
Current flows automatically from the anode to the pipeline because of the
voltage gradient.
The required number and size of anodes depend on the size of the object to
be protected, the specific soil resistance and the planned term of protection.
Galvanic anodes have a lifetime of maximum 20 years and have to be
changed at the end of this time. However, in contrast to impressed current systems galvanic anode systems
are less expensive.
Cathodic Corrosion Protection With a
Galvanic Anode System
Source: VC Pipeline Protection Ltd.
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
58/78
TELECOMMUNICATION,
INSTRUMENTATION& SCADA
Flow of Data:
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
59/78
Flow of Data:
PAS
SCADA-MCS
SCADA-SCC
PLC BASED CONTROL SYSTEM
FIELD INSTRUMENTATION
Source: http://petrofed.winwinhosting.net
Modes of communication in pipelines:
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
60/78
p p
H.F. Communication system
V.H.F. Communication system
Public leased circuits on hire
Line of Sight Communication system
Optical fiber Communication system
Satellite Communication system
Source: http://petrofed.winwinhosting.net
VHF Communication:
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
61/78
VHF Communication:
Used for communication in a pipeline station / tank farm
Base stations and hand held trans-receivers available
Suitable for short range - typically 2 km to 25 km
Cannot be used for inter station communication in pipelines
Supports voice, data, fax, computer networking and SCADA
systems
Comparable cost with other modes
Source: http://petrofed.winwinhosting.net
Optical Fibre Communication:
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
62/78
p
Works by sending signals down hair thin strands of glass fiber.
Has incredibly high transmission capacity i.e. bandwidth.
Immune to Noise.
Freedom from Cross talk.
Source: http://petrofed.winwinhosting.net
OFC:
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
63/78
Overall Cable diameter : 13 14 mm
Wavelengths used: 1310 nm/ 1550 nm
Attenuation @ 1310 nm : 0.36 dB/km
Attenuation @ 1550 nm : 0.23 dB/km
Source: http://petrofed.winwinhosting.net
Telecommunication Equipment:
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
64/78
q p
SDH:Synchronous_Digital_Hierarchy
SDH
D/I MUX
EP
A
B
X
ConferenceSet
Subscriber
Lines
FCBC
48V
Battery
Bank
PC
Printer
Source: http://petrofed.winwinhosting.net
Instrumentation Equipments:
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
65/78
q p
Pressure Indicators
Pressure Switches
Pressure Transmitters
Flow Meters/ Flow Computers
Temperature Transmitter
Temperature Indicator
Level Switches
Flow Switches
Density Meters
Control Valve
Tank Gauging System
Emergency Shutdown System
Source: http://petrofed.winwinhosting.net
Instrumenation Equipments:
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
66/78
q p
PRESSURE
SWITCHES
LEVEL SWITCHES
FLOW SWITCHES TEMP. SWITCHES
FLOW METERS
LEVEL
TRANSMITTERS
PRESSURE
TRANSMITTERSDENSITY METERS
Source: http://petrofed.winwinhosting.net
Hazardous Area Classification & Protection Standards:
http://www2.emersonprocess.com/en-US/brands/micromotion/density-viscosity-meters/7835-liquid-concentration-density-meters/Pages/index.aspx -
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
67/78
Hazardous environments exist in oil refineries, pipeline installations, offshore platforms,
chemical plants, mines etc.
Electrical equipment must be suitable for the environment in which they are to be used.
Hazardous areas are classified with respect to the potential danger of explosion and the
areas are divided into zones according to the probability of the hazardous atmosphere-
Zone 0, Zone 1, Zone 2.
Source: http://petrofed.winwinhosting.net
Hazardous Area Classification & Protection Standards :
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
68/78
Instruments, Equipments in pipeline installations are deployed keeping in view
the hazardous area classification.
Protections like Flameproof-Explosion proof, Intrinsic Safety and are ensured
while selection of instruments & equipments.
Each chemical gas or vapour used in industry is classified into a gas group.
Also, to ensure that there is no risk of ignition due to hot surfaces, the
equipments/ instruments are classified with regard to the maximum surface
temperature of any part of the equipment.
Source: http://petrofed.winwinhosting.net
Hazardous Area Classification & Protection Standards :
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
69/78
Explosion Protection Methods/ equipment- common types
Flameproof - (Ex d)
Increased Safety - (Ex e)
Pressurisation - (Ex p)
Intrinsically Safe - (Ex i)
Source: http://petrofed.winwinhosting.net
SCADA:
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
70/78
Dedicated SCADA system is installed to provide effective and efficient monitoring
and control of the entire pipeline from Master Control Station (MCS).
SCADA system has a MCS and Station Control Centres (SCCs) at attended stations viz.
pump stations/ delivery stations/ pump - cum - delivery stations.
Source: http://petrofed.winwinhosting.net
State Control Centre & Master Control centre:
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
71/78
Designed to provide effective & efficient monitoring, safe operation and control
of local station and scraper station/ block valves under its control.
Acquires data from local PLC and scraper station/ block valves under its control in
real time and transmits the same to MCC.
Configured with dual redundant hot standby computer systems.
Programmable Logic Controllers (PLCs) are installed at attended stations/ scraper
stations for interfacing the field devices.
Remote Terminal Units (RTUs) are installed at unattended block valve stations for
interfacing the field devices.
Source: http://petrofed.winwinhosting.net
Typical SCC Configuration:
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
72/78
Source: http://petrofed.winwinhosting.net
Typical MCS Configuration:
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
73/78
Source: http://petrofed.winwinhosting.net
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
74/78
Case Study
Mallavaram-Bhopal-Bhilwara-Vijaipur Gas Pipeline(MBBVPL)
Being built by the consortium of Gujarat State
Petronet Limited (GSPL), IOC, HPCL and BPCL
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
75/78
Case Study The pipeline is being laid by the consortium through a separate JV company.
GSPL is the lead partner of the consortium with 52% equity holding, followed by IOC with26% and HPCL and BPCL holding 11% each.
Elaborate due diligence has shown that the pipeline will be viable under a sensitivity analysisthrough different parametric conditions. The total investment for constructing the pipeline hasbeen pegged at INR 7,257 crore.
The MBBVPL will be laid from Mallavaram (Kakinada) to Bhopal, passing through Godavari,Waranagl, Karimnagar, Adilabad and Nagpur. From Bhopal, the line will bifurcate into two.While one line will go northwards to Vijaypur meeting the HVJ pipeline of GAIL there, the
other branch line will go to Bhilwara in Rajasthan. In between the pipeline will cover Sehore,Indore and Chittorgarh.
The pipeline is scheduled to be completed within 36 months in line with PNGRB guidelines.The major project activities to be completed within the following duration are listed below:--12 months: Pipeline route survey, preparation of Emergency Management Plan (EMP),
carrying out Environmental Impact Assessment (EIA) and engineering activities.--Next 6 months: To initiate the bidding process and award contracts--Next 18 months: Completion of detailed engineering, procurement, construction and
commissioning activities
The pipelines would be implemented in a phased manner in line with the development planincorporated in the financial model to improve the internal rate of return (IRR) of the projects.
The consortium has drawn up plans to partly commission the pipeline project in 24 months(Mallavaram to East Godavari district in Andhra Pradesh) instead of one time commissioningof the whole project in 36 months to improve the profitability of the project.
Source: IndianPetro, Jan 22, 2012
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
76/78
Case Study A maximum period of thirty six months, from the date of issue of the authorization
letter, has been given for commissioning of the gas pipeline project. The pipeline will achieve a total capacity of 76.25 MMSCMD by 25th year of its
operation.
Of this, the extra capacity in the natural gas pipeline, which will be available foruse on a ''common carrier'' basis by any third party on an open-access and non-discriminatory basis, will be 19.06 MMSCMD.
However during the first year of operation, the design capacity will be only 52.87
MMSCMD, which will remain constant till the tenth year of operation. Though the design capacity is 52.87 MMSCMD, the volume considered for
transportation is much lower at 39.65 MMSCMD in the first year of operation.
The MBBVPL will be hooked up with the Mehsana-Bhatinda (MBPL) at Bhilwara(Rajasthan).
The pipeline has been designed in such a way that gas can be injected in thepipeline at both Mallavaram and Bhiwara.
This will help in flowing of volumes from Mehsana into central India and volumesfrom the KG basin (Kakinada) into central as well as north India.
Source: IndianPetro, Jan 22, 2012
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
77/78
Case Study Though the design capacity, in the first year of operation (expected in 2014-15),
of the MBBVPL has been pegged at 52.87 MMSCMD, the volume considered fortransportation is much lower at 39.65 MMSCMD. Out of this, as of now, a total of25.5 MMSCMD has been considered for the pipeline from the following sources:
Domest ic sources--Additional gas from RIL's KG basin: 6 MMSCMD--GSPC's KG basin fields; 8 MMSCMD
Gujarat LNG term inals--Another 11.5 MMSCMD is estimated to come from four LNG terminals inGujarat, namely PLL Dahej, Mundra LNG terminal, HLPL Hazira and FSRU(Floating, Storage, Regas and Unloading) facility, Pipavav.
The total share of gas for the MBBVPL -- both from domestic sources and LNGterminals -- adds up to 25.5 MMSCMD in the first year (2014-15) of operationagainst the total anticipated supply of 93.8 MMSCMD.
The total anticipated supply of 93.8 MMSCMD in 2014-15 is expected to go upto
183 MMSCMD by 2020-21. With this, the share of gas to the MBBVPL system will also go up proportionately.
Source: IndianPetro, Jan 22, 2012
-
7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines
78/78
Case Study: Costs The total investment for constructing the Mallavaram-Bhopal-Bhilwara-Vijaipur
Gas Pipeline (MBBVPL) has been pegged at Rs 7,257 crore The capital expenditure, including IDC (interest during construction period) and
cash deficit in initial years, for the pipeline has been estimated as under:
Land and RoU (including land compensation): Rs 198 crore
Pipelines: Rs 4,338 crore
SCADA and telecom: Rs 78 crore
Buildings: Rs 182 crore Others: Rs 417 crore
Contingency at 10%: Rs 521 crore
Total core project cost: Rs 5,735 crore
IDC and financing charges: Rs 492 crore
Funding of cash deficit: Rs 1029 croreTotal 'As Built' project cost: Rs 7,257 crore