iemr-oil & gas transmission & distribution pipelines

Upload: abhinav-gupta

Post on 03-Apr-2018

230 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    1/78

    INTRODUCTION TOHYDROCARBON PIPELINES

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    2/78

    OIL & GAS PIPELINES

    Crude oil is often transported between

    continents in large tankers, but oil and natural3

    gas is transported (transmitted) across

    continents by pipelines.

    Transmission pipelines are the main arteries

    of the oil and gas business

    Pipelines are 40 times safer than rail tanks, and

    100 times safer than road tanks for transportingenergy

    According to the USA Association of Oil

    Pipelines, Oil pipeline spills amount to about 1

    gallon per million barrel-miles

    Source: Oil & Gas Pipeline By Phil Hophinks (Penspen

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    3/78

    WHY WE ALL SHOULD BE INTERESTED

    IN PIPELINES

    We rely on pipelines to deliver our energy needs, but everyone is astakeholder in oil and gas transportation:

    Pipeline operators (transporters) want a safe, reliable supply, and a

    reasonable profit;

    The general public (consumers) want cheap gasoline, natural gas, etc.,

    delivered reliably and safely, with minimal environmental damage;

    Shippers (producers) want cheap, reliable supplies and transportation,

    and a reasonable profit;

    Regulators want a fair and competitive market;

    Government groups want safe, environmentally-friendly, delivery;

    Advocacy groups (focussing on environmental, cultural, etc., aspects)

    have focussed interests;

    The biggest challenge facing the pipeline engineer today and tomorrow is

    safetySource: Oil & Gas Pipeline By Phil Hophinks (Penspen

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    4/78

    TYPES OF HYDROCARBON

    PIPELINES

    These pipelines are made from high quality steel (line pipe steel), constructed

    using well-established methods, and operated using procedures developed over

    many decades.Source: Oil & Gas Pipeline By Phil Hophinks (Penspe

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    5/78

    PIPELINE COMPONENTS Metallic pipes

    Ordinary steel pipe

    Corrugated

    Cast-iron

    Ductile-iron

    Stainless steel

    Aluminum Copper

    Non metallic pipes

    Plastic

    Rubber and elastomer

    Glass

    Tubings & pipe designation

    Connections

    Fittings

    Pressure relief and pressure regulating valves

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    6/78

    METALLIC PIPES Metallic pipes are stronger and tougher to break but they have

    disadvantages like more sensitive to heat and electricity,

    corrosion sensitive

    More conductive to heat and electricity.

    Following are some of the commercial metal pipelines:

    1. Ordinary (Wrought ) steel pipelines seamed or seamless Seamed made up of steel sheets/plates rolled into circular

    shape, with edge of each pipe closed by welding

    Different types welding are-

    1) Butt Welding2) Lap Welding

    3) Electric Arc Welding (Single or Double Welded joint)

    Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    7/78

    CORRUGATED STEEL PIPE

    Thin-wall, large-diameter, made of galvanized steel sheetshaving either helical or annular corrugations

    Used extensively in sewer and drainage systems

    Flow is often gravity flow rather than pressure flow.

    Have large variety of fittings and great range of sizes.

    Some fabricated to have a pecan-shaped instead of circular

    cross section

    Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    8/78

    CAST-IRON PIPE

    Two types: ordinary or gray cast-iron pipe, and the ductile-iron pipe.

    The ordinary cast-iron pipe made of iron containing 3 to

    4% of carbon in the form of graphite flakes.

    Gray cast-iron pipe has relatively strong corrosion-resistance ability and long life

    Two strength designations: 18/40 and 21/45.

    18 means that the min bursting tensile strength is 18,000

    and 40 means that the min modules of rupture is 40,000psi.

    Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    9/78

    DUCTILE-IRON PIPE

    Made of iron containing 3.5% carbon in sheroidal ornodular form, and a magnesium alloy

    Has the advantage of gray cast-iron pipe (corrosion

    resistance and long life) and steel pipe (ductility).

    Strength designation is 60/42/10

    Min tensile strength of 60,000psi

    Min yield strength of 42,000 psi

    10% min elongation

    Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    10/78

    STAINLESS STEEL PIPE

    Contains chrome-nickel alloys

    300 series such as SS304 or SS316, are the most used stainless

    steel pipes.

    Corrosion resistant

    High price, used only in special applications such as:

    When the fluid or environment is corrosive

    When no rusting of pipe can be tolerated such as in

    pharmaceutical or food industries.

    Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    11/78Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    12/78

    NON METALLIC PIPES

    Not as strong as metallic pipes

    Light in weight

    More economical

    Certain advantages such as being more corrosion resistant.

    The one used in oil and gas is plastic pipes.

    Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    13/78

    PLASTIC PIPES 3 types of plastic pipes commonly used

    PVC (Polyvinyl chloride) PE (polyethylene)

    PP (polypropylene)

    Used for

    Water Waste water

    Natural gas

    Other fluids that do not dissolve or chemically interact with

    plastics Deform easily

    Expand 5 times as much as steel due to temperature

    Becomes brittle in very cold weather

    Long term performance not known

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    14/78

    Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    15/78

    CONNECTIONS (JOINTS)

    Bonded joints-welding, brazing or soldering and fusing.

    Threaded joints-connecting threaded pipe sections together

    Flanges-provide strong joint without permanently joining the

    pipe sections.

    Mechanical joints-for ease in assembly/disassembly

    Bell-and-spigot-used in pressure concrete pipes, glass and

    plastic pipes also use

    Push-on-connected together simply by pushing two pipe

    sections against each other

    Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    16/78

    Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    17/78

    VALVES

    Gate valve

    Closed/opened by turning handle connected to it Takes many turns to completely open or close a gate valve

    Head loss is small when gate fully opened

    Maybe a wedge or a disk or a knife

    Has a conduit with a full round bore for smooth passage ofpigs

    Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    18/78

    VALVES

    Globe valve

    Outside is globe shaped

    Flow changes direction as it goes through the valve

    Large head loss when valve fully opened

    Gives better control or flow than gate valves-good for flow

    throttling

    Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    19/78

    VALVES

    Check valves Flow cannot reverse through a check valve, unidirectional

    flow

    3 types of check valves are swing check, tilt disk, ball check

    valve.

    Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    20/78

    Source: PE 607 : Oil & Gas pipeline Design, maintenance & Repair

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    21/78

    PIPELINE CONSTRUCTION

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    22/78

    Following are reference/codes followed during Laying ofpipeline & Line-pipe coating:

    1. API 1105 : Construction practices for Oil & Productpipelines

    2. ASME B 31.4 : Pipeline transportation System for liquidHydrocarbon

    3. ASME B 31.8 : Gas Transmission & Distribution PipingSystem

    4. OISD B 141 : Design & Construction requirement forcross country Hydro Carbon Pipelines

    5. API 6 D : Construction & Inspection of valves

    6. API 1104 : For welding of pipeline & related activities

    7. DIN 30670 : For 3LPE coating for line pipes

    CODES & STANDARDS

    Source: eil.co.in/ eil specification

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    23/78

    1. ROU (Right of Use) SURVEY

    2. ROU CLEARING AND GRADING3. STRINGING

    4. TRENCHING

    5. BENDING

    6. WELDING7. FIELD JOINT COATING

    8. LOWERING

    9. BACKFILLING

    10.CROSSING

    11. HYDROTESTING

    12. PIPELINE MARKERS, CLEAN UP & RESTORATION

    13. MAGNETIC PIGGING & EGP PRE COMMISSIONINGACTIVITY

    PIPELINE LAYING ACTIVITIES

    Source: eil.co.in/ eil specification

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    24/78

    ROU Survey, ROU Clearing and

    Grading, Stringing

    Source: eil.co.in/ eil specification

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    25/78

    1. ROU (Right of Use) SURVEY:

    Installation of Bench Marks, Turning Points

    Stake markers in center line of pipeline at a distance of max100m for center line and for horizontal bends 10 m and

    reference point for same

    Stake two ROU markers at least at every 100m, Painted in Red

    and numbers in white in direction of flow

    Chainage markers at every 250m

    2. ROU CLEARING AND GRADING

    All obstacles causing hindrance in construction / laying pipeline

    are removed Entire ROU is Graded for movement of equipments and vehicle

    Temporary approaches/bridges, if required, are constructed for

    movement of equipments, vehicles & personnels

    Source: eil.co.in/ eil specification

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    26/78

    3. STRINGING

    Stringing shall be done after blasting & trenching when

    ROU is in rocky area

    Coating pipes shall be strung on approved soft earth/sand

    filled bag and wedge in such a way that bottom of coated

    pipe remain above ground

    Pipes shall be supported at minimum two locations

    Pipe number, Heat number, coat number & length shall be

    transferred and recorded in serial order

    Source: eil.co.in/ eil specification

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    27/78

    Trenching

    Source: eil.co.in/ eil specification

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    28/78

    4. TRENCHING

    Trench excavation is carried out along staked centerline of

    Pipeline.

    The width of excavation for trench shall be minimum(pipe diameter

    plus 200 mm either side).

    Depth of trench shall be specified (Normal =1M;

    Road=1.2M;River=1.5M,Rly=1.7M etc.

    In case of trenching in rocky areas, blasting is performed with the

    guidelines/Safety Rules Of CCOE, Nagpur.

    In case where rock/gravel or hard soil is encountered in the bottom

    of the trench, padding material(minimum compacted thickness of

    150mm) shall be provided.

    When up floating of the pipeline after backfilling is anticipitated &

    anti-buoyancy measures are provided in such areas e.g. by

    installing saddle weight

    Source: eil.co.in/ eil specification

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    29/78

    Welding

    Manual Welding

    Automatic WeldingSource: eil.co.in/ eil specification

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    30/78

    5. WELDING

    Automated welding involves using mechanical or electronicmeans to control welding conditions such as welding current,

    arc length, filler wire, or electrode feed, as well as travelspeeds. Movement and guidance of the electrode, torch orwelding head along the line of weld can be similarlycontrolled.

    Advantages of automated welding1. A less experienced operator can handle the welding machine andhave satisfactory end results.

    2. A smaller percentage of welding electrodes is lost in stub ends. Amuch shorter arc is uniformly maintained by the automated

    welding process than is possible by a manual operator.3. A much higher current can be used with a given size of welding

    wire to produce better fusion. A much higher welding speed canalso be obtained.

    Source: eil.co.in/ eil specification

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    31/78

    6. BENDING

    For changes in vertical &

    horizontal alignment, prefabricated

    coal field bends are provided. Over bends are made in a manner

    that centre of bend clears the

    highest point of trench bottom. Sag

    bend shall fit the bottom of trench.

    Side bends shall have specified

    clearance to the outside wall of

    trench.

    The radius of coal field bend shall

    be not more than 40 times the dia.of pipe(for 18 and above) and 30

    times the dia. of pipe(for 17

    below)

    Source: eil.co.in/ eil specification

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    32/78

    7. FIELD JOINT COATING The cut-back areas of Coated

    Pipes where weld joints are

    made to be coated by fieldjoint coating.

    Field joint coating material isheat shrinkable wraparoundsleeve used as anticorrosioncoating of buried onshorepipeline.

    Sleeve consist of radiationcross-linked thermallystabilized, ultraviolet resistantsemi rigid polyolefin backingwith a uniform thickness ofhigh shear strengththermoplastic melt adhesive.

    Source: eil.co.in/ eil specification

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    33/78

    The joint coating system shall consist of a solvent free epoxy

    primer applied to pipe surface prior to sleeve application. The

    surface area is blast cleaned to SA-2.5 followed by pre

    heating of pipe surface, application of epoxy primer andapplication of sleeve by heat shrinking.

    One out of 50 joints coating or one coating out of every day

    production shall be tested to establish peel strength on steel

    and factory applied coating.

    Source: eil.co.in/ eil specification

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    34/78

    Lowering

    Source: eil.co.in/ eil specification

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    35/78

    8. LOWERING

    Lowering shall commence after inspection of trench

    Lowering shall commence as soon as possible after

    completion of joint coating The pipeline must be laid without interruption for the

    whole or the length of section available

    Ends of the lowered pipeline section shall be closed with

    night cap to prevent ingress of water, mud etc.

    Source: eil.co.in/ eil specification

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    36/78

    9. BACKFILLING

    Backfilling shall be carried outimmediately after pipelinelowering in trench after

    inspection, so as to provide anatural anchoring for pipeline.

    Backfilling material shall notcontain any extraneousmaterial or hard lumps of soilwhich can damage pipeline or

    coating or leave the voids inbackfilled trench

    If trench are excavated insteep area where the slope ismore than 10%, slopebreakers shall be installed toprevent erosion of backfill,stabilization of backfill shall bedone in sandy area to haveconsolidated cover over thepipeline

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    37/78

    Crossing

    CROSSING

    Cased & Un-cased

    crossings for Roads &

    Railways

    Open cut & Horizontal

    Directional Drilling (HDD) forminor & major river crossing

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    38/78

    11. HYDROTESTING

    After the acceptance of gauging operation, uninhabitedwater is pumped into the section using four cup batching

    pigs which are launched at specific intervals.After water filling the thermal equilibrium is maintained

    between pipeline & environment using thermocouples.

    After thermal stabilization, pressurization is carried out in

    cycles at 50% test pressure & 75% test pressure andheld for 1 hr at each test pressure and depressurized tozero pressure & then pressurized to final pressure.

    The test shall be considered positive if pressure has

    kept a constant value throughout the test duration,except for change due to temperature effects. Thepressure value thus added shall be compared with initialvalue and test shall be considered as acceptable ifdifference is less than to 0.3 bar

    Source: eil.co.in/ eil specification

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    39/78

    Hydro Testing

    Source: eil.co.in/ eil specification

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    40/78

    12. PIPELINE MARKER, CLEAN UP &

    RESTORATION

    Following markers shall be installed along pipeline route such that

    they do not caught any hindrance to regular land user and traffic.

    Aerial Markers - At every 5 Kms

    Kilometer Markers - At every 1 Kms as per Alignment

    sheet

    Pipeline Warning Markers - At Road/Railways/CrossingROU Boundary Markers - At every 750 m as per

    alignment sheet

    Navigational Markers - At bank of navigational course

    On completion clean up of pipelines ROU shall be restored to suchstable and unstable as may be reasonably consistent with the

    condition of ROU prior to laying of Pipeline

    Source: eil.co.in/ eil specification

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    41/78

    13. MAGNETIC PIGGING & ELECTRONIC GEOMETRICPIGGING

    This is a part of pre-commissioning activity, which ensure thatthere is no deformity in pipeline. This is done prior to filling line

    with the product. Magnetic PIG loaded with high capacity magnets spread uniformly

    with high density polyethylene four cup PIG is launched to removeferrous debris, mill scale, electrode pieces etc. The accumulatedweight of ferrous debris is checked after running the PIG throughpipeline section. When the collected weight of ferrous debris iswithin limit for specific length of pipeline section, the line is ready forlaunching Electronic Geometric Pigging (EGP) tool.

    After successful completion of magnetic pig run EGP tool islaunched. The tool is mounted with battery operated battery device,which give the reduction in pipeline Dia. At specific location in

    electronic form. Defect upto more than 3% internal diameter of pipe is physically

    verified at site. Defect of more than 5% internal diameter of pipe arerepaired by cutting suitable length of pipe and re-welding.

    Source: eil.co.in/ eil specification

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    42/78

    Horizontal Directional Drilling (HDD) is a trenchless excavation processthat provides the installation of pipelines beneath a wide range of

    surface obstacles like Rivers, Highways, Railway Xings, and Right ofWays through Developed Areas etc.

    It offer a number of benefits over traditional open-cut methods.

    It can be implemented with very little disruption to Surface activities,requires less working space, and quicker than Open-cut methods.

    Equipm ent required for HDD are -

    1. A rig, which provides the physical means thrust and torque, to open thehole and pull in the product.

    2. A transmitter/receiver system for tracking the location of the bore.

    3. The down-hole equipment - drill pipe, drill bits, and reamers, whichconverts the physical properties of the rig to open the hole and pull in theproduct.

    4. The drilling fluid, which serves to stabilize the hole, cool the down-hole5. equipment, and remove the spoils from the hole.

    6. The drilling fluid delivery and recovery system made up of tanks, mixingsystems, pumps; and, when recycling fluids, a system of screens, filters,

    7. Shakers, cones, etc. to remove spoils brought to the surface from the fluid.

    Continue..

    HORIZONTAL DIRECTIO NAL DRILLING

    Source: Trenchless Technologies Ltd (website)

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    43/78

    The HDD process begins with boring a small, horizontal hole(Pilot Hole) under the crossing obstacle (i.e. a River) with acontinuous string of steel drill rod, using technology thatallows the drill to be steered and tracked from the surface.

    When one of the key considerations in the design of the drill-path is creating as large a radius of curvature as possiblewithin the limits of the right-of-way.

    The Curvature requirements are dependent on site geometrycrossing length, required depth to provide safe cover, stagingsite location, etc.

    The Drilling operation consists of using an appropriate tool toopen the pilot hole to a slightly larger diameter than the

    carrier pipeline. The percentage oversize depends on many variables

    including soil types, soil stability, depth, drilling mud, boreholehydrostatic pressure, etc. Normal over-sizing Varies from120% to 150% of the carrier pipe diameter

    Continued..

    HORIZONTAL DIRECTIO NAL DRILLING

    Source: Trenchless Technologies Ltd (website)

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    44/78

    Enlarging the pilot hole is accomplished using pre-reamingpasses prior to pull back.

    Pre-reaming tools are typically attached to the drill pipe at theexit point. The reamers are then rotated and drawn to the drillingrig thus enlarging the pilot hole. Drill pipe is added behind thereamers as they progress toward the drill rig in pull backoperation. This insures that a string of pipe is always maintained

    in the drilled hole. Reaming tools typically consist of a circulararray of cutters and drilling fluid jets. Drilling fluid is pumpedthrough the reamers to aid in cutting, support the reamed hole,and lubricate the trailing pipe.

    Pull-Back Operation - Involves pulling the entire pipeline lengthin one segment

    back through the drilling mud along the reamed-hole pathway.Axial tension force readings, constant insertion velocity, mud flowcirculation/exit rates, and footage length installed should berecorded. The pullback speed ranges usually between 1 to 2 feetper minute. A swivel is utilized to connect the pull section to theleading reamers to minimize torsion transmitted to the pipeline.

    HORIZONTAL DISTANCE DRILLING

    Source: Trenchless Technologies Ltd (website)

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    45/78

    PIGGING, INSPECTION

    &CORROSION CONTROL

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    46/78

    PIG stands for Pipeline Intervention Gadget/ PipelineInspection Guage

    A pig is a device inserted into a pipeline which travels

    freely through it, driven by the product flow to do a specific

    task within the pipeline Functional Classification of pigs:

    (a) Utility pigs which perform a function such as cleaning,

    separating products in-line or dewatering the line

    (b) Inline inspection pigs which are used to provideinformation on the condition of the pipeline and the extent and

    location of any problem (such as corrosion for example) and

    (c) Special Duty Pigs such as plugs for isolating pipelines.

    PIGGING

    Source: www.ppsa-online.com

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    47/78

    Pigging is a maintenance tool

    During the construction of the line, pigs can be used toremove debris that accumulates

    During Hydro-testing, pigs are used to fill the line withwater and subsequently to dewater the line after the

    successful test During operation, pigs can be used to remove liquid

    hold-up in the line, clean wax off the pipe wall or applycorrosion inhibitors

    Inspection pigs are used to assess the remaining wallthickness and extent of corrosion in the line, thusproviding timely information for the operator regardingthe safety and operability of the line

    PURPOSE OF PIGGING

    Source: www.ppsa-online.com

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    48/78

    Offshore pipelines are of thicker wall than onshore-sometimes up to

    35mm thick. Offshore pipelines can have greater operating pressures, particularly

    the deepwater pipelines - Maximum operating pressures onshore cabe 100bar(GP) but offshore can be 300bar(GP)

    Flow rates of products both onshore and offshore are the samedependant upon the type of pipeline or its position with regard totransporting product either between offshore platforms or fromplatform to shore.

    Offshore pipelines tend to be protected by a concrete outer coatingand sacrificial anodes fitted to the pipeline every 100 metres so theoutside of offshore pipelines tend not to suffer corrosion but may get

    damaged by sea bed movement or anchors from ships Generally running pigs in offshore pipelines is very similar to running

    in onshore lines

    One very important thing to realise with offshore inspection is that thepig must not get stuck in the pipeline as retrieving it will be muchmore expensive than from an onshore pipeline

    ONLINE & OFFLINE PIPELINE PIGGING

    Source: www.ppsa-online.com

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    49/78

    The main inspection techniques used are

    Magnetic Flux Leakage1. MFL is an inferred method where a strong magnetic flux is

    induced into the pipeline wall. Sensors then pick up any leakage

    of this flux and the extent of this leakage indicates a flaw in the

    pipe wall. For instance, internal material loss in the line will cause

    flux leakage that will be picked up by the sensors.2. Defect libraries are built up to distinguish one defect from another.

    Ultrasonic Inspection

    1. Ultrasonic inspection is a direct measurement of the thickness of the pipe

    wall. A transducer emits a pulse of ultrasonic sound that travels at a

    known speed. The time taken for the echo to return to the sensor is a

    measurement of the thickness of the pipe wall.

    2. The technique needs a liquid through which the pulse can travel. The

    presence of any gas will affect the output.

    INSPECTION TECHNIQUES

    Ultrasonic can inspect very thick wall pipe but magnetic flux is limited because

    of how strong the magnets need to be to get enough magnetism in the wall

    of the pipe to enable good results to be obtained.

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    50/78

    Corrosion is an electrochemical reaction requiring

    the following conditions to be met :

    1. There must be an anode and a cathode.

    2. There must be an electrical potential between the anode

    and the cathode.

    3. There must be a metallic path between the anode and the

    cathode. Normally this will be the pipeline itself.

    4. The anode and the cathode must be immersed in an

    electrically conductive electrolyte which is ionized -

    meaning that some of the water molecules are brokendown intp positively charged hydrogen ions (H+) and

    negatively charged hydroxyl ions (OH-).The usual soil

    moisture surrounding pipelines normally fulfils this

    condition.

    CORROSION

    Source: VC Pipeline Protection Ltd.

    CORROSION

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    51/78

    Once these conditions are met , an electric current will flow and metal will

    be consumed .

    The pressure exerted by the potential difference between the anode and

    the cathode results in migration of electrons from the anode to the

    cathode along the metallic connection between the anode and cathode.

    Anode Loss of electrons positive charged iron atom combine with

    OH- FE(OH)2 Further reacts to form Fe2(OH)3 which is familiar

    RUST.

    At the cathode , a surplus of electrons arrives from the anode. These

    surplus negatively charged electrons combine with positively charged

    hydrogen ions from the environment to form hydrogen (H2).

    CORROSION

    Source: VC Pipeline Protection Ltd.

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    52/78

    CORROSION

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    53/78

    Earth buried pipelines are usually expensive investments . In order

    to defend against the threat of corrosion they are protected by

    coatings and coverings.

    However, the smallest damage of the coating or any cracks in the

    covering steadily lead to pitting corrosion.

    Corrosion causes an electrochemical reaction which leads to loss of

    metal. As a result pipelines become leaky and can cause enormousdamage to property and environment.

    The expected lifespan of a pipeline network is, depending on the

    transport medium, a minimum of 50 years. However, a pipeline

    should be functional for up to 100 years. Cathodic corrosion

    protection offers an optimum of safety and efficiency because

    With a cathodic protection system pipelines can be operated even in

    critical soils reliably.

    CORROSION

    Source: VC Pipeline Protection Ltd.

    PRINCIPLES OF CORROSION CONTROL

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    54/78

    There are two possibilities for designing an activecorrosion

    protection system of earth buried pipelines:

    1. Cathodic protection with impressed current.

    2. Cathodic Corrosion Protection with a galvanic anodes

    system.

    PRINCIPLES OF CORROSION CONTROL

    Source: VC Pipeline Protection Ltd.

    Cathodic Protection with an

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    55/78

    Current is produced by a RECTIFIER and transmitted by foreign current

    anodes to the earth buried object to be protected.

    The advantage of this method lies primarily in the possibility that the

    output voltage can be regulated depending on the soil resistance and the

    protecting current requirements of the pipeline.

    Furthermore cathodic corrosion protection with an impressed currentsystem enables automatic recording of the state of the pipeline and thereby

    possible irregularities can be immediately recognised and remedied .

    Cathodic Protection with an

    Impressed Current Protection System

    Source: VC Pipeline Protection Ltd.

    Cathodic Protection with an Impressed

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    56/78

    The anodes which are used for the protective current Supply

    can be built horizontally or vertically in the ground.

    Primarily FeSi anodes used, either single or pre-finished as

    canister anode with backfill.

    The effectiveness of the cathodic protection system is

    monitored through potential mapping through permanent

    reference cells at measuring points and then sent to the

    rectifier station for an internal comparison with preset

    thresholds.

    The cable connections of the pipeline, rectifier and reference

    electrode come together at the measuring station too.

    Cathodic Protection with an Impressed

    Current Protection System

    Source: VC Pipeline Protection Ltd.

    Cathodic Corrosion Protection With a

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    57/78

    For smaller objects or those where a power supply with rectifier is difficult

    (e.g. in less conductive grounds) cathodic protection with galvanic anodesis used.

    The method is based on the difference between the anode material and the

    object to be protected.

    Current flows automatically from the anode to the pipeline because of the

    voltage gradient.

    The required number and size of anodes depend on the size of the object to

    be protected, the specific soil resistance and the planned term of protection.

    Galvanic anodes have a lifetime of maximum 20 years and have to be

    changed at the end of this time. However, in contrast to impressed current systems galvanic anode systems

    are less expensive.

    Cathodic Corrosion Protection With a

    Galvanic Anode System

    Source: VC Pipeline Protection Ltd.

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    58/78

    TELECOMMUNICATION,

    INSTRUMENTATION& SCADA

    Flow of Data:

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    59/78

    Flow of Data:

    PAS

    SCADA-MCS

    SCADA-SCC

    PLC BASED CONTROL SYSTEM

    FIELD INSTRUMENTATION

    Source: http://petrofed.winwinhosting.net

    Modes of communication in pipelines:

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    60/78

    p p

    H.F. Communication system

    V.H.F. Communication system

    Public leased circuits on hire

    Line of Sight Communication system

    Optical fiber Communication system

    Satellite Communication system

    Source: http://petrofed.winwinhosting.net

    VHF Communication:

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    61/78

    VHF Communication:

    Used for communication in a pipeline station / tank farm

    Base stations and hand held trans-receivers available

    Suitable for short range - typically 2 km to 25 km

    Cannot be used for inter station communication in pipelines

    Supports voice, data, fax, computer networking and SCADA

    systems

    Comparable cost with other modes

    Source: http://petrofed.winwinhosting.net

    Optical Fibre Communication:

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    62/78

    p

    Works by sending signals down hair thin strands of glass fiber.

    Has incredibly high transmission capacity i.e. bandwidth.

    Immune to Noise.

    Freedom from Cross talk.

    Source: http://petrofed.winwinhosting.net

    OFC:

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    63/78

    Overall Cable diameter : 13 14 mm

    Wavelengths used: 1310 nm/ 1550 nm

    Attenuation @ 1310 nm : 0.36 dB/km

    Attenuation @ 1550 nm : 0.23 dB/km

    Source: http://petrofed.winwinhosting.net

    Telecommunication Equipment:

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    64/78

    q p

    SDH:Synchronous_Digital_Hierarchy

    SDH

    D/I MUX

    EP

    A

    B

    X

    ConferenceSet

    Subscriber

    Lines

    FCBC

    48V

    Battery

    Bank

    PC

    Printer

    Source: http://petrofed.winwinhosting.net

    Instrumentation Equipments:

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    65/78

    q p

    Pressure Indicators

    Pressure Switches

    Pressure Transmitters

    Flow Meters/ Flow Computers

    Temperature Transmitter

    Temperature Indicator

    Level Switches

    Flow Switches

    Density Meters

    Control Valve

    Tank Gauging System

    Emergency Shutdown System

    Source: http://petrofed.winwinhosting.net

    Instrumenation Equipments:

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    66/78

    q p

    PRESSURE

    SWITCHES

    LEVEL SWITCHES

    FLOW SWITCHES TEMP. SWITCHES

    FLOW METERS

    LEVEL

    TRANSMITTERS

    PRESSURE

    TRANSMITTERSDENSITY METERS

    Source: http://petrofed.winwinhosting.net

    Hazardous Area Classification & Protection Standards:

    http://www2.emersonprocess.com/en-US/brands/micromotion/density-viscosity-meters/7835-liquid-concentration-density-meters/Pages/index.aspx
  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    67/78

    Hazardous environments exist in oil refineries, pipeline installations, offshore platforms,

    chemical plants, mines etc.

    Electrical equipment must be suitable for the environment in which they are to be used.

    Hazardous areas are classified with respect to the potential danger of explosion and the

    areas are divided into zones according to the probability of the hazardous atmosphere-

    Zone 0, Zone 1, Zone 2.

    Source: http://petrofed.winwinhosting.net

    Hazardous Area Classification & Protection Standards :

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    68/78

    Instruments, Equipments in pipeline installations are deployed keeping in view

    the hazardous area classification.

    Protections like Flameproof-Explosion proof, Intrinsic Safety and are ensured

    while selection of instruments & equipments.

    Each chemical gas or vapour used in industry is classified into a gas group.

    Also, to ensure that there is no risk of ignition due to hot surfaces, the

    equipments/ instruments are classified with regard to the maximum surface

    temperature of any part of the equipment.

    Source: http://petrofed.winwinhosting.net

    Hazardous Area Classification & Protection Standards :

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    69/78

    Explosion Protection Methods/ equipment- common types

    Flameproof - (Ex d)

    Increased Safety - (Ex e)

    Pressurisation - (Ex p)

    Intrinsically Safe - (Ex i)

    Source: http://petrofed.winwinhosting.net

    SCADA:

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    70/78

    Dedicated SCADA system is installed to provide effective and efficient monitoring

    and control of the entire pipeline from Master Control Station (MCS).

    SCADA system has a MCS and Station Control Centres (SCCs) at attended stations viz.

    pump stations/ delivery stations/ pump - cum - delivery stations.

    Source: http://petrofed.winwinhosting.net

    State Control Centre & Master Control centre:

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    71/78

    Designed to provide effective & efficient monitoring, safe operation and control

    of local station and scraper station/ block valves under its control.

    Acquires data from local PLC and scraper station/ block valves under its control in

    real time and transmits the same to MCC.

    Configured with dual redundant hot standby computer systems.

    Programmable Logic Controllers (PLCs) are installed at attended stations/ scraper

    stations for interfacing the field devices.

    Remote Terminal Units (RTUs) are installed at unattended block valve stations for

    interfacing the field devices.

    Source: http://petrofed.winwinhosting.net

    Typical SCC Configuration:

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    72/78

    Source: http://petrofed.winwinhosting.net

    Typical MCS Configuration:

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    73/78

    Source: http://petrofed.winwinhosting.net

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    74/78

    Case Study

    Mallavaram-Bhopal-Bhilwara-Vijaipur Gas Pipeline(MBBVPL)

    Being built by the consortium of Gujarat State

    Petronet Limited (GSPL), IOC, HPCL and BPCL

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    75/78

    Case Study The pipeline is being laid by the consortium through a separate JV company.

    GSPL is the lead partner of the consortium with 52% equity holding, followed by IOC with26% and HPCL and BPCL holding 11% each.

    Elaborate due diligence has shown that the pipeline will be viable under a sensitivity analysisthrough different parametric conditions. The total investment for constructing the pipeline hasbeen pegged at INR 7,257 crore.

    The MBBVPL will be laid from Mallavaram (Kakinada) to Bhopal, passing through Godavari,Waranagl, Karimnagar, Adilabad and Nagpur. From Bhopal, the line will bifurcate into two.While one line will go northwards to Vijaypur meeting the HVJ pipeline of GAIL there, the

    other branch line will go to Bhilwara in Rajasthan. In between the pipeline will cover Sehore,Indore and Chittorgarh.

    The pipeline is scheduled to be completed within 36 months in line with PNGRB guidelines.The major project activities to be completed within the following duration are listed below:--12 months: Pipeline route survey, preparation of Emergency Management Plan (EMP),

    carrying out Environmental Impact Assessment (EIA) and engineering activities.--Next 6 months: To initiate the bidding process and award contracts--Next 18 months: Completion of detailed engineering, procurement, construction and

    commissioning activities

    The pipelines would be implemented in a phased manner in line with the development planincorporated in the financial model to improve the internal rate of return (IRR) of the projects.

    The consortium has drawn up plans to partly commission the pipeline project in 24 months(Mallavaram to East Godavari district in Andhra Pradesh) instead of one time commissioningof the whole project in 36 months to improve the profitability of the project.

    Source: IndianPetro, Jan 22, 2012

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    76/78

    Case Study A maximum period of thirty six months, from the date of issue of the authorization

    letter, has been given for commissioning of the gas pipeline project. The pipeline will achieve a total capacity of 76.25 MMSCMD by 25th year of its

    operation.

    Of this, the extra capacity in the natural gas pipeline, which will be available foruse on a ''common carrier'' basis by any third party on an open-access and non-discriminatory basis, will be 19.06 MMSCMD.

    However during the first year of operation, the design capacity will be only 52.87

    MMSCMD, which will remain constant till the tenth year of operation. Though the design capacity is 52.87 MMSCMD, the volume considered for

    transportation is much lower at 39.65 MMSCMD in the first year of operation.

    The MBBVPL will be hooked up with the Mehsana-Bhatinda (MBPL) at Bhilwara(Rajasthan).

    The pipeline has been designed in such a way that gas can be injected in thepipeline at both Mallavaram and Bhiwara.

    This will help in flowing of volumes from Mehsana into central India and volumesfrom the KG basin (Kakinada) into central as well as north India.

    Source: IndianPetro, Jan 22, 2012

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    77/78

    Case Study Though the design capacity, in the first year of operation (expected in 2014-15),

    of the MBBVPL has been pegged at 52.87 MMSCMD, the volume considered fortransportation is much lower at 39.65 MMSCMD. Out of this, as of now, a total of25.5 MMSCMD has been considered for the pipeline from the following sources:

    Domest ic sources--Additional gas from RIL's KG basin: 6 MMSCMD--GSPC's KG basin fields; 8 MMSCMD

    Gujarat LNG term inals--Another 11.5 MMSCMD is estimated to come from four LNG terminals inGujarat, namely PLL Dahej, Mundra LNG terminal, HLPL Hazira and FSRU(Floating, Storage, Regas and Unloading) facility, Pipavav.

    The total share of gas for the MBBVPL -- both from domestic sources and LNGterminals -- adds up to 25.5 MMSCMD in the first year (2014-15) of operationagainst the total anticipated supply of 93.8 MMSCMD.

    The total anticipated supply of 93.8 MMSCMD in 2014-15 is expected to go upto

    183 MMSCMD by 2020-21. With this, the share of gas to the MBBVPL system will also go up proportionately.

    Source: IndianPetro, Jan 22, 2012

  • 7/28/2019 IEMR-Oil & Gas Transmission & Distribution Pipelines

    78/78

    Case Study: Costs The total investment for constructing the Mallavaram-Bhopal-Bhilwara-Vijaipur

    Gas Pipeline (MBBVPL) has been pegged at Rs 7,257 crore The capital expenditure, including IDC (interest during construction period) and

    cash deficit in initial years, for the pipeline has been estimated as under:

    Land and RoU (including land compensation): Rs 198 crore

    Pipelines: Rs 4,338 crore

    SCADA and telecom: Rs 78 crore

    Buildings: Rs 182 crore Others: Rs 417 crore

    Contingency at 10%: Rs 521 crore

    Total core project cost: Rs 5,735 crore

    IDC and financing charges: Rs 492 crore

    Funding of cash deficit: Rs 1029 croreTotal 'As Built' project cost: Rs 7,257 crore