ie550 2/18/2016 design for production in existing facilities (dpef) richard a. wysk the pennsylvania...
DESCRIPTION
IE550 2/18/2016 Design for Production in Existing Facilities (con’t) l Answer the following questions: »Can the new product be produced in the required quantities given the current production allocation? –if so, what are the expected production costs ? –if not, can the current production be reallocated such that all of the production requirements can be met? –if not, can the design be modified to enable production within the current resource structure? –if not, how should additional resources be acquired to meet the production requirements?TRANSCRIPT
IE550 05/04/23
Design for Production in Existing Facilities (DPEF)
Richard A. WyskThe Pennsylvania State University
IE550 Manufacturing Systems
IE550 05/04/23
Design for Production in Existing Facilities (DPEF)
Given: » a product design,» the expected production requirements for the
new product,» a set of production resources and the current
configuration (production lines, cells, etc.), and
» the expected requirements for the products currently being produced,
IE550 05/04/23
Design for Production in Existing Facilities (con’t)
Answer the following questions:» Can the new product be produced in the required
quantities given the current production allocation?– if so, what are the expected production costs ?– if not, can the current production be reallocated such
that all of the production requirements can be met?– if not, can the design be modified to enable
production within the current resource structure?– if not, how should additional resources be acquired
to meet the production requirements?
IE550 05/04/23
How it’s done today: Parametric-based Feature Information
Feature information (Intra-feature specifics)» Dimensions» Size Tolerances» Surface Finishes» Geometric Tolerances
IE550 05/04/23
Product, Process and Production Models
Product EngineeringLibrary of featuresFeature interactions
Process EngineeringProcess / Feature linksInter-feature linkagesInter-process linkages
Production EngineeringSystem SpecificsMachine SpecificsFixture Specifics
Tool Specifics
Com m on Data Pool
ProductionEngineering
On-lineSFCS
ProductEngineering
CAD(Modeling,Analysis)
ProcessEngineering
CAPP(Aggregation,
Detailed)Design Data
ResourcesJob Status
Master ScheduleBills of Material
Process Plan
IE550 05/04/23
Production Resource Constaints
Geometric Constraints Machine Constraints Jig/Fixture Constraints Tooling Constraints Process Constraints
IE550 05/04/23
Key Process Planning Features
Plans based on Feature Precedence Graph
Generates AND/OR Graph Collects the resource data from
Databases Is independent of Decision Table
IE550 05/04/23
Example: Threaded hole (.250-20 UNF Class 3)
Process alternatives» Drill -> Tap» Drill -> Thread cut» Drill -> Thread form
Process plans» Drill ---> NxxG00G91X@locY@locZ@locM06 NxxG01Z-@sizeF50 NxxG01Z@sizeF100
IE550 05/04/23
Process Planner
IBM Compatible IBM Compatible
FeatureInformation
AND/ORGraph
DB
MachinesJigs/Fixtures
ToolingsLayout
Decision Table
Design Station Process Planning
IE550 05/04/23
Processes SL-20 Turning
Center» Facing» Turning» Drilling» Reaming» Boring» Tapping» Threading
VF-0E Machining Center– Milling (Face/end-
milling)– Drilling– Reaming– Boring– Tapping– Threading– Engraving (Ball-mill)
IE550 05/04/23
AND/OR Graph Generator
Creates an AND/OR Graph Representation of a process plan
Fills out Processing Node Information» PNI is used by NC code Generator
Covers MP, MT, MH and AS/RS nodes
IE550 05/04/23
Example Part
•Cylindrical Part•Center Hole•Bolt Holes •Contour•Thread
IE550 05/04/23
Process Plans Shop level plans
MT MT
Ml
Dr Tr1
MTMT
Tr2
IE550 05/04/23
Process Plans Workstation level plans
MH MH
VF-3
SL-20 VF-0
MHMT
VF-0
Workstation #1Workstation #2
IE550 05/04/23
Process Plans (cont.) Equipment Level Plans (Drilling)
Fx
Dr1
Dr2
Dr3
Dr4
Tp2
Tp3
Tp4
Tp1
Fx
IE550 05/04/23
Decision Maker Contains the hierarchical constraints
» Machine» Fixture» Tool» Process» Feature
Can be updated indendent of Process Planner
IE550 05/04/23
Decision Information
XXImpossible XXXRough TurningPUMA X Semi-finish TurningPUMA XX Finish TurningPUMA
XXXRough FacingPUMAXSemi-finish FacingPUMA
XXFinish FacingPUMA
Major CylinderMachine
F1XPUMAF1Z 0 < F1 < 20XFADAL 0 < F1 <16Y0 < F3+Hmn+Hc < 20Z
FixtureTTTTTTF1.9 < F1 < 2.0PUMAFFFFFFT0.4 < F3
FADALTool
T1PUMAT2 T3
T1FADALT2T3
Process
T F0.01 < F2ConditionT F0.01 < F4TFT 32 MU in. < F5
32 MU in. < F6 TFT32 MU in. < F7
IE550 05/04/23
IPPE Concept
Design Model Process ModelCAD System
Process PlanningSystem
ProductionAnalysis System
Resource Model Instance
IE550 05/04/23
Process Planner
IBM Compatible IBM Compatible
FeatureInformation
AND/ORGraph
MachinesJigs/Fixtures
ToolingsLayout
Decision Table
Design Station Process Planning
STEP or STEP-like PSL or PSL-like
Manufacturing Resource Model
Resource Model
Instance
Resource Model
Instance
Resource Model
Instance Resource Model
Instance
WWW
Multi-facility Planning and
Analysis
InquiriesProductionOrders
IE550 05/04/23
Technological Hurdles
Process Planning» Given a part design, what are the processes, tools,
fixtures, etc. required to manufacture the part. All feasible alternatives should be explicitly represented.
Production Planning and Analysis» Given a set of production resources and a set of
production requirements with the associated process plans, how should the production be allocated among these resources in order to efficiently satisfy the requirements.
IE550 05/04/23
Resource Model A set of definitions and symbolic descriptions
that are used to completely describe the individual resources in a facility as well as the possible interactions between these resources.
A resource model instance describes a specific facility and its resources.
IE550 05/04/23
the time required for setup for an operation (load fixture, retreive tooling , etc.)
the time required to load and unload a product for feature operation j (chuck, fixture, etc..)
the machining/processing time for feature j
tool change time/part
idle time due to scheduling control
L/UL
tj
jsetupt
tj
m
ct
t i
L/UL m c=E(t jsetup+ t j + t j + t i + t )t P A
j
IE550 05/04/23
Production time per piece
t t t t tp set l/ul m ch= + + +
•The cost associated with new tooling is also a key consideration for the designer.
•For low and medium volume products, the cost associated with tooling and setup can dominate the total product cost.
Performance Metrics
IE550 05/04/23
Concept of a manufacturing system resource model [ Wysk, R.A.,
Peters, B.A., and Smith, J.S., “ A Formal Process Planning Schema for Shop
Floor Control ” ]
» Resource Model - set of definitions and symbolic descriptions that
are required to completely describe all of the individual resources in
a facility as well as the necessary interactions between these
resources
IE550 05/04/23
Terminology
Resources (R) : Collection of assets in the facility directed towards the manufacture of the products. Includes equipment, tools, fixtures, transporters, and instruction sets
Locations (L): A precise physical location associated with a port and a part. Locations are used to link the transfer of parts between equipment types. Each location has an owner and a set of clients that can address that location
Ports (P): Ports are nodes in the graph defining the paths parts can follow through the facility (note: Graph shows the connections between the resources in the facilities
Arcs: Show which ports can be directly accessed from a particular port
Facilitator: A device than can move transporters between different ports on the MT system or move parts between a port on a MT system and a port on a MP
IE550 05/04/23
Example...
MP 3
MP 2
MH 1
MT 1
1
2
3
4
1
2
3
4
MH 1
Ports, Locations : 1,2,3,4
Facilitator : MH1
Arcs between : 1-2, 2-1, 1-4, 4-1, 4-3, 3-4, 2-3, 3-2 ( represent connections between the resources )
Resources: MP2, MP3 (type MP) MT1 (type MT) MH1 (type MH)