identifying facility siting raw risk and the risk reduction decision

16
Identifying Facility Siting Raw Risk and the Risk Reduction Decision Process Craig Shell Stephen W. Kelly Process Safety Performance Products aeSolutions Huntsman Corporation Greenville, SC 29615 Conroe, TX 77301 Presenter E-mail: [email protected] Abstract One of the outcomes of a facility siting study is the presentation of information to the facility site leadership team so they can recognize all of the hazards that can impact buildings intended for occupancy. It is this hazard recognition and risk reduction process that will be discussed in this paper. The authors will present a methodology for completing a facility siting assessment that starts with identifying a MCE, followed by breaking the MCE into additional credible events, and identifying likelihood and additional safeguards needed to manage the risk. The authors will present examples to illustrate this process and how different models affect the results. Hazard scenarios to be presented include leaks from flammable storage and transfer systems resulting in outdoor vapor cloud explosions as well as explosions within a building. Through these examples, differences in hazard impacts will be presented. Various likelihood references and resultant risk rankings will be shown. Based on these risk rankings and a tolerable risk criteria, proposed safeguards necessary to close a gap will be described. Presenting information in this manner allows the site leadership team to better allocate resources more effectively in minimizing facility siting risks. Introduction Since the BP Texas City incident, facility siting studies have been identified by regulators as being one of the more deficient process safety requirements based on OSHA’s Refinery & Chemical National Emphasis Programs (NEP). One reason for this may be that some facility siting studies in the past have been conducted by applying a methodology based on a fixed and limited number of hazard event scenarios that are generally of very high severity and low likelihood (i.e. MCE). In these studies, a limited effort was expended to review the critical plant process conditions and define all of the maximum credible event(s) (MCE) and credible event scenarios for those hazards with reasonable probability of occurrence. These scenarios generally have lower severity with higher likelihoods but can still impact occupied buildings. The consequence of these fixed number of hazard event scenarios were then quantified to assess impacts to buildings intended for occupancy. Owners and Operators of these facilities were then left with trying to determine the true risks at the facility and what could be done to mitigate these

Upload: lyanh

Post on 27-Dec-2016

224 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: Identifying Facility Siting Raw Risk and the Risk Reduction Decision

    

Identifying Facility Siting Raw Risk and the Risk Reduction Decision Process

Craig Shell Stephen W. Kelly Process Safety Performance Products aeSolutions Huntsman Corporation Greenville, SC 29615 Conroe, TX 77301

Presenter E-mail: [email protected]

Abstract

One of the outcomes of a facility siting study is the presentation of information to the facility site leadership team so they can recognize all of the hazards that can impact buildings intended for occupancy. It is this hazard recognition and risk reduction process that will be discussed in this paper. The authors will present a methodology for completing a facility siting assessment that starts with identifying a MCE, followed by breaking the MCE into additional credible events, and identifying likelihood and additional safeguards needed to manage the risk.

The authors will present examples to illustrate this process and how different models affect the results. Hazard scenarios to be presented include leaks from flammable storage and transfer systems resulting in outdoor vapor cloud explosions as well as explosions within a building. Through these examples, differences in hazard impacts will be presented. Various likelihood references and resultant risk rankings will be shown. Based on these risk rankings and a tolerable risk criteria, proposed safeguards necessary to close a gap will be described. Presenting information in this manner allows the site leadership team to better allocate resources more effectively in minimizing facility siting risks.

Introduction

Since the BP Texas City incident, facility siting studies have been identified by regulators as being one of the more deficient process safety requirements based on OSHA’s Refinery & Chemical National Emphasis Programs (NEP). One reason for this may be that some facility siting studies in the past have been conducted by applying a methodology based on a fixed and limited number of hazard event scenarios that are generally of very high severity and low likelihood (i.e. MCE). In these studies, a limited effort was expended to review the critical plant process conditions and define all of the maximum credible event(s) (MCE) and credible event scenarios for those hazards with reasonable probability of occurrence. These scenarios generally have lower severity with higher likelihoods but can still impact occupied buildings. The consequence of these fixed number of hazard event scenarios were then quantified to assess impacts to buildings intended for occupancy. Owners and Operators of these facilities were then left with trying to determine the true risks at the facility and what could be done to mitigate these

Page 2: Identifying Facility Siting Raw Risk and the Risk Reduction Decision

    

risks. A facility siting study that includes MCE scenarios, as well as other more likely scenarios that can significantly impact buildings intended for occupancy will generate a hazard map that best reflects the site’s risks of concern.

Facility personnel need to be able to look at a facility siting plot plan and recognize hazards that can impact buildings intended for occupancy. When temporary or new buildings intended for occupancy are sited or a new process with new hazards is located, plant personnel must take the hazard into consideration to minimize unwanted consequences if things go wrong. In Andrew Hopkins book, Failure to Learn, he states:

“There is, however, as one commentator has said, a “depressing sameness” about major accidents. The causes are remarkably similar and it is apparent that companies have not learnt the lessons of earlier disasters. This is particularly evident in the Texas City case. Almost every aspect of what went wrong at Texas City had gone wrong before, either at Texas City or elsewhere. Some of these earlier failures had been extensively documented and publicized, yet BP had failed to learn from them. It exhibited a quite striking inability to learn.”

To help learn the lessons of earlier disasters, The Center for Chemical Process Safety (CCPS) has published Guidelines for Evaluating Process Plant Buildings for External Explosions, Fires, and Toxic Releases and is a good source for guidance. The Objective includes:

“The purpose of this book is to provide the methods to address the explosion, fire, and toxic impacts to process plant buildings and occupants occurring as a result of hazards associated with operations external to the building.”

Identifying hazard scenarios starts like a process hazard analysis by identifying initiating causes applicable to the type of processing units at a facility. These causes must be quantifiable in terms of frequency rates. Scenarios can encompass a small leak with a high initiating cause frequency or a large leak at a very low initiating cause frequency. The next step is to collect process conditions around the hazard scenario. This information is then used as inputs into an appropriately selected model to assess the severity of the consequence. Available models include, but are not limited to: Dow F&EI and CEI, EPA’s Aloha, PHAST, scaled blast curves, and CFD models such as FLACS. Once modeling results are validated, the impacts to buildings intended for occupancy are hazard ranked in terms of severity. With reference to the product of the initiating cause frequency and the hazard scenario severity, the unmitigated risk can be documented.

Once the unmitigated (without safeguards) event frequency has been defined, existing safeguards can be identified (independent protective layer (IPL)) with the associated probability of failure on demand (PFD) (likelihood), and used as a basis to determine if the current system meets the companies tolerable risk criteria. If a gap exists, then additional means of reducing the likelihood and/or reducing the severity will need to be identified by a competent hazard assessment team. Safeguards can be classified into passive, active, and procedural with preference based in this order respectively.

Page 3: Identifying Facility Siting Raw Risk and the Risk Reduction Decision

    

Identifying Hazard Scenarios

The facility siting example presented in this paper involves the receipt, unloading, storage and transfer of ethylene oxide (EO). Figure 1 is a plot plan showing the overall layout of the plant. EO is received on the east side of the plant primarily from railcars. The material is unloaded by use of an unloading pump into a 20,000 gal horizontal storage tank that is located nearby. An unloading operator shelter constructed of a steel frame sheet metal building is located just south of the EO storage tank. From the storage tank, EO is pumped to batch reactors in Area A located in the center of the plant, and Area B located on the west side of the plant.

The EO unloading and storage area is outdoors while the reactors in Area A and B are located inside a steel frame sheet metal building. In addition, each reactor area has a control room next to the reactor buildings constructed of cement block. Several buildings intended for occupancy are located on the south east and south side of the plant. These buildings are constructed of cement block and steel frame sheet metal.

To understand what facility siting hazards may exist, a review of the company and industry incidents was conducted. Incident reports collected by the facility and discussions during team meetings added to the list of hazard scenarios reviewed. Many raw material manufacturers compile and issue guidance documents to assist facilities that receive and handle their chemicals. For EO, an Ethylene Oxide Product Stewardship Guidance Manual1 (EO Manual) was published and contains various historical incidents that can be used as a guide for developing facility siting hazard scenarios. This EO Manual includes the following statement:

“Note that in most EO contamination incidents and EO decomposition incidents, the majority of the damage has resulted from an EO vapor cloud explosion.”

It is the loss of containment of EO that will be discussed in this paper. Many hazards

associated with facility siting studies involve leaks from transfer operations. In the CCPS book, Guidelines for Evaluating Process Plant Buildings for External Explosions, Fires, and Toxic Releases, Table 8.1 Frequency and Probability Assessment lists factors that can be used to determine explosion frequencies.

Examples of different types of piping leaks that may be appropriate in a facility siting study are listed in Table 1. This table also includes several Recognized and Generally Accepted Good Engineering Practice (RAGAGEP) resources that are available for use in setting initiating cause frequencies for the listed hazard scenarios.

Hazard Scenarios Raw Risk and Resultant Severity

                                                            1 The Ethylene Oxide Product Stewardship Guidance Manual was prepared by the American Chemistry Council's Ethylene Oxide/Ethylene Glycols Panel, third edition. 

Page 4: Identifying Facility Siting Raw Risk and the Risk Reduction Decision

    

CCPS in Guidelines for Evaluating Process Plant Buildings for External Explosions, Fires, and Toxic Releases, Analysis in the Approach Selection section notes:

“… An owner/operator may opt for a phased approach to building siting evaluation with the level of detail increasing with each step. This phased approach may consist of a consequence-based assessment using conservative assumptions as an initial step. More detailed consequence analysis that use process specific information may be used as a subsequent step to sharpen the pencil.”

A typical MCE may involve the full bore rupture of a transfer pipe or rupture of a tank. If the hazard does not impact buildings intended for occupancy, then no further assessment is required. However, if buildings intended for occupancy are impacted, then a further assessment is required to ensure the individuals inside these buildings are adequately protected. CCPS has published a very useful compilation of models that can be used for facility siting, Guidelines for Vapor Cloud Explosion, Pressure Vessel Burst, BLEVE and Flash Fire Hazards. A list of various modeling tools that were used to model hazard consequences can be found in Table 2.

EO has both toxic and flammable properties of concern. In this paper, the authors will present facility siting issues generated from the flammable characteristics of EO. Conservative TNT modeling was used for the MCE scenarios, which included pipe and tank ruptures. Based on this modeling several buildings intended for occupancy were impacted therefore additional more detail modeling was required.

For overpressure impacts due to releases of EO at the unloading, storage, transfer, and reactor areas, several different refined explosion models were used to assess nearby buildings intended for occupancy and to assess inherently safer designs. The results of the dispersion modeling for hazard scenarios are listed in Tables 3 and 4.

For the existing plant configuration, several issues appeared. The first concern is associated with outdoor releases during low wind speeds. Figure 2 depicts a wind rose diagram and shows calm (< 0.5 m/s) periods of up to 10% of the year. This amount of time was considered sufficient to be of a concern. The second concern involved potential releases of flammables inside the reactor buildings. Based on dispersion modeling, the concentration indoors could reach the lower flammable limit (LFL) and therefore result in an overpressure hazard and impact buildings intended for occupancy. Indoor releases are of particular concern because of a lack of natural ventilation that aids in the dispersion of flammable releases.

To assess flammable cloud size for various hazard scenarios, PHAST was used to assess the mass in the cloud above the LFL for outdoor releases. Table 3 shows that the leak hole size has a significant effect on the size of the flammable cloud. Of particular concern is whether the flammable cloud size is sufficiently large to generate an overpressure hazard. Lees10 looked at historical overpressure incidences from outdoor releases and noted that a certain amount of material is required to be release before a credible overpressure hazard exists. In the FM Global Property Loss Prevention Data Sheets 7-42, Guidelines for Evaluating the Effects of Vapor Cloud Explosions Using a TNT Equivalency Method, flammable materials are classified into three categories and each category has a listed minimum mass. These classes and associated minimum mass above the LFL for outdoor releases are:

Page 5: Identifying Facility Siting Raw Risk and the Risk Reduction Decision

    

Class I materials, 5 tons Class II materials, 1 ton Class III materials, 1000 lbs

In the FM Global guidance document, EO is considered a Class III material. Based upon the information in Table 3 and FM Global guidance, scenarios at low wind speeds were an area that warranted further investigation. It should be noted that PHAST dispersion software is limited to >1 m/s and so overpressure hazards below 1 m/s could not be accurately modeled with this software.

Because of this limitation, CFD modeling was conducted to assess flammable cloud size and resultant overpressure hazards for outdoor releases at low wind speeds as well as indoor releases in the reactor buildings. Figure 3 shows Reactor Building A area with buildings located near reactors. In this area one can see that the sides of the building facing the release point are the short sides of the buildings. Figure 4 shows Reactor Building B area that only has one building, the control room, located near the reactors. In this area one can see that the side of the building facing the release point is the long side of the building.

The results of the CFD dispersion modeling are presented in Table 4. Also included in Table 4 are the wind directions that resulted in the maximum and minimum flammable cloud sizes. Overpressure hazards are shown in Figures 5 and 6 for the three areas of concern: Unloading Area, Reactor Building A, and Reactor Building B. It should be noted that the control room building orientation in reference to the release point and wind direction has an impact on the flammable cloud size and therefore the resultant overpressure hazard distances. These results indicate:

Unloading Area – This area of the plant has low confinement and congestion, which results in the lowest flammable cloud size and overpressure distances compared to the other two reactor areas. The results from this scenario are presented in Figures 5 and 6.

Reactor Building A and B – These two areas of the plant have a high degree of confinement due to being indoors, which results in unacceptable damage to buildings intended for occupancy.

Reactor Building A with walls removed below 15’ elevation – In order to improve natural ventilation in this area, the sheet metal walls, starting at grade up to 15’ elevation, were removed. CFD modeling results indicated that removing walls below 7’ did not decrease the flammable cloud size and damage to buildings intended for occupancy. This area of the plant has moderate confinement and congestion which results in the next lowest flammable cloud size and overpressure distances compared to the other areas. The results from this scenario are presented in Figures 5 and 6.

Reactor Building B with walls removed below 15’ elevation – These results mirror

Reactor Building A. This area of the plant has moderate confinement and congestion, which results in the highest flammable cloud size and overpressure distances compared to the other areas. This can be attributed to the building’s orientation near the release point.

Page 6: Identifying Facility Siting Raw Risk and the Risk Reduction Decision

    

The Reactor Building B control room is perpendicular to the wind direction for the largest flammable cloud case whereas buildings near Reactor A have no large face area perpendicular to the wind direction even though the Reactor A area has more objects around the release point. The results from this scenario are presented in Figures 5 and 6.

Risk Ranking and Identifying Safeguards

After having identified the hazards and severity, API RP-752 recommends that a mitigation plan be developed that includes both mitigation measures and schedule for completing them. Safeguards can be classified into three categories as presented in API RP-752 2009, Table 1 Hierarchy of Mitigation Measures. Listed in order of priority they are:

Passive Active Procedural

To evaluate what mitigation opportunities can be implemented, a PHA team was assembled and a list of recommended safeguards was identified to meet the company’s tolerable risk criteria (see Table 5). Of most importance are the passive mitigation measures that represent inherently safer design:

Replace with reinforced gasket (inner and outer rings) Replace or reduce any bleeder to < ½” port diameter Remove Reactor Building panels below 15’ elevation Relocate Control Rooms operations away from the hazard or upgrade the Control Room

to withstand the overpressure hazard Design and Upgrade Buildings Intended for Occupancy based on Overpressure Hazards Barricade around Exposed Piping and Equipment

The PHA Team presented these recommendations to the Site Leadership Team (SLT) for acceptance and assigned a responsible individual to track closure of the accepted recommendation. The facility siting study will be kept current through the site’s Management of Change (MOC) program and will be revalidated in five years.

Page 7: Identifying Facility Siting Raw Risk and the Risk Reduction Decision

    

Conclusions

Based on this facility siting study, several key factors were identified:

1. Facility siting studies should be used as a tool to help companies learn the lessons of earlier disasters to minimize the risk of future major accidents.

2. Review of company and industry incidents can aid in the selection of the MCE and more refined credible hazard scenarios that have the potential to impact buildings intended for occupancy.

3. A phased approach to building siting evaluations with the level of detail increasing with each step will focus a company’s resources on the hazards of concern.

4. Each hazard scenario identified must be assessed with the appropriate modeling tool. Individuals tasked with completing a facility siting evaluation must be aware of the basis and limitations of each tool to ensure that it is being applied appropriately.

5. Outdoor releases during periods of low wind speed can be a hazard of concern and should be investigated based on local weather conditions for the plant.

6. Indoor process units handling flammable materials can present a significant hazard of concern.

7. The location of walls and building orientation near a flammable release point can affect the dispersion and associated hazard consequence.

8. Identifying safeguards in priority order starting with ones that are passive, and then active, followed by procedural to meet a company’s tolerable risk will result in reducing the chances of an unwanted major accident. Once these safeguards are accepted by the site leadership team, they will be assigned to a responsible individual who will track the recommendation to closure to ensure that the safeguard is implemented in a reasonable amount of time.

Page 8: Identifying Facility Siting Raw Risk and the Risk Reduction Decision

    

Table 1 Summary of Potential Leak Scenarios and Initiating Cause Frequencies

Initiating Cause Size of Release Frequency Range from Literature

(per year) Full Bore Rupture:

Pump Capacity

Mobile Equipment Impact3

10-2 to 10-4

Crane Drop of Heavy Equipment2

10-3 to 10-4 per lift

Piping residual failure – 100 m – Full Breach2

10-5 to 10-6 per 100m

Nominal diameter < 75 mm per m of pipe length4

1x10-6 per m

75 mm < nominal diameter < 150 mm per m of pipe length3

3x10-7 per m

Nominal diameter > 150 mm per m of pipe length3

1x10-7 per m

Human error:

1” Pipe Bleeder w/Standard Ball Valve, or ¾” Pipe Bleeder w/Full Port Ball Valve

¾” Pipe Bleeder w/Standard Ball Valve

d1 = ¾”

d1 = ½”

Human Factor for general error of omission4

Human Factor for error in routine simple operation4

Piping Leak (10% section)2

10-3 to 10-4 per 100 m

Leak with an effective diameter of 10% of the nominal diameter, up to a maximum of 50 mm

0.1

Nominal diameter < 75 mm per m of pipe length3

5x10-6 per m

                                                            2 LOPA, Table 5.1, pg 71, CCPS 2001 3 Bevi Risk Assessments version 3.2, 2009 4 Human Reliability Analysis, AIChE Journal Vol 20 No.2 March 1974 

Page 9: Identifying Facility Siting Raw Risk and the Risk Reduction Decision

    

Summary of Potential Leak Scenarios and Initiating Cause Frequencies Initiating Cause Size of Release Frequency Range

from Literature (per year)

75 mm < nominal diameter < 150 mm per m of pipe length3

2x10-6 per m

Nominal diameter > 150 mm per m of pipe length3

5x10-7 per m

Pump Seal Failure2

Centrifugal pumps and centrifugal compressors3

10-1 to 10-2

Canned (without gasket) Catastrophic failure

Leak (10 % diameter) 0.1

1x10-5

5x10-5

With gasket

Reciprocating pumps and reciprocating compressors3

Catastrophic failure

Leak (10 % diameter) 0.1

Catastrophic failure

Leak (10 % diameter) 0.1

1x10-4

4.4x10-3

1x10-4

4.4x10-3

Non-Metallic Leak – Gasket Leak2 10-2 to 10-6

Hole size based on raised face gap between bolt holes

Hole size based on small diameter pipe (<3”) and ¼ gasket

Reinforced Gasket/Packing Blowout2

Reinforced Gasket Leak between

Adjacent Bolt Holes, =1.5mm

10-2 to 10-6

Hole size based on raised face between bolt holes

Hole size based on small diameter pipe (<3”) and ¼ gasket

Page 10: Identifying Facility Siting Raw Risk and the Risk Reduction Decision

    

Summary of Potential Leak Scenarios and Initiating Cause Frequencies Initiating Cause Size of Release Frequency Range

from Literature (per year)

= equivalent hole diameter of leak (in), = pipe diameter (in), = flange bolt hole diameter

(in), = number of flange bolts, = pipe flange raised face diameter (in), = bolt diameter

(in), = width of flange gasket (in)

Table 2

Modeling Tools for Toxic and Flammable Hazards

CEI5 Toxic Impacts Aloha6 Toxic and Radiant Thermal Impacts F&EI7 Radiant Thermal Impacts PHAST8 Toxic, Radiant Thermal, and Explosion Impacts API9 Jet Fire Impacts Cone10 Jet Fire Impacts TNT11 Explosion Impacts Tang12 Explosion Impacts Baker-Strehlow-Tang13 Explosion Impacts TNO Multi-Energy14 Explosion Impacts FLACS15and FACET3D16 Explosion Impacts

                                                            5 Chemical Exposure Index (CEI) Method, Dow, 2nd Edition 6 U.S. Environmental Protection Agency, Emergency Management 7 Fire and Explosion Index (F&EI) Method, Dow, 7th Edition 8 DNV Technica’s Process Hazard Analysis Software Tool (PHAST) 9 Cook, J., Bahrami, Z., Whitehouse, R.J., 1990, A comprehensive program for calculation of flame radiation levels,

J. Loss Prev. Process Ind. v3 (1990) pp150-155. 10 Johnson, A. D., Brightwell, H. M., and Carsley, A. J., 1994, A model for predicting the thermal radiation hazard

from large scale horizontally released natural gas jet fires, Trans. IChemE., Vol. 72, Part B (1994) pp 157-166 11 Lees, F. P., 1996, Loss prevention in the process industries, 2nd Edition 12 Tang, M.J., Cao, C.Y., and Baker, Q.A., “Blast Effects from Vapor Cloud Explosions”, International Loss

Prevention Symposium, Bergen, Norway, June 1996 13 Tang, M. J. and Baker, Q. A., 1999, A New Set of Blast Curves from Vapour Cloud Explosion, Process Safety

Progress, Volume 18, No. 4, pp 235 - 240, Winter 1999 14 TNO "Yellow Book", 1997, Methods for the calculation of physical effects due to releases of hazardous materials

(liquids and gases), Eds: van den Bosch, C. J. H. and Weterings, R. A. P. M. (1997), Chapter 5: Vapor Cloud Explosions, Mercx, W. P. M. and van den Berg, A. C. 

15 Flame Acceleration Simulator (FLACS), Version 9.1 release 3, GexCon, Bergen, Norway, April 2011. 16 Facility Assessment and Consequence Evaluation Tool (FACET3D), Version 11.8.1, ABS Consulting, 2011 

Page 11: Identifying Facility Siting Raw Risk and the Risk Reduction Decision

    

Table 3

PHAST Modeling Results

Cloud Mass above the LFL at Various Low Wind Speeds

Leak Scenario dl

(in) 0.5 m/s17

(lbs) 0.7 m/s17

(lbs) 1.0 m/s

(lbs) 1.5 m/s

(lbs) Reinforced gasket 2" pipe 150 class 0.1175 0.18 0.14 0.11 < 0.1Gasket 2" pipe 150 class or Bleeder with standard ball vale

0.5 1,185 680 374 194

2” Piping Leak, 10% section 0.682 1,475 838 518 2621” Pipe Bleeder w/Standard Ball Valve or Full Bore Rupture, Pump Capacity

0. 75 3,243 1,733 974 559

Table 4

FLACS/FACET3D Explosion Modeling Results for ½” hole leak18

Model Leak Direction

Wind Speed (m/s)

Direction from

Flammable Cloud Size

(m3) Unloading Area Down

West 0.45 North

East 79 24

Reactor Building A Down Down

3.6 South West East

423 299

Reactor Building A - w/walls removed below 15’ elev.

Down Down

3.6 North West East

118 66

Reactor Building B Down Down

3.6 North South

1,179 453

Reactor Building B - w/walls removed below 15’ elev.

Down Down

3.6 North South West

375 100

                                                            17 Wind speed below validated model. 18 Confidential Client, US Based Consulting Firm, Consequence Analysis using CFD modeling, Final Report

Revision 2, March 29. 

Page 12: Identifying Facility Siting Raw Risk and the Risk Reduction Decision

    

Table 5

Risk Reduction Options by Hazard Scenario

Hazard Scenario Independent Protection Layer (IPL)

Gasket Leak Passive - Inherently safer design: Replace with reinforced gasket (inner and outer rings) Active - Consequence Mitigation System (CMS) Gas Detection, Isolation, and Deluge

Bleeder Vale Left Open

Passive - Inherently safer design: Replace or reduce any bleeder to < ½” port diameter Remove Reactor Building Panels Below 15’ Elev. Relocate Control Rooms Away from Hazard

Design and Upgrade Buildings Intended for Occupancy based on Overpressure Hazards or relocate to buildings away from the hazard area

Active – Consequence Mitigation System (CMS) Gas Detection, Isolation, and Deluge

Procedural - Administrative: Standard Operating Procedure (SOP)LOTO Checklist and

Diagram of Valves to be Manipulated Standard Operating Procedure (SOP) Open Ended Line

Inspection prior to Restart Piping Leak due to

Corrosion Procedural - Administrative: RAGAGEP review of Piping for Chemical Service Mechanical Integrity (MI) Program

Pipe Rupture due to impact

Passive - Inherently safer design: Barricade around Exposed Piping and Equipment Procedural - Administrative: Crane Lift Evaluation Program

Page 13: Identifying Facility Siting Raw Risk and the Risk Reduction Decision

    

Figure 1 - Facility Plot Plan

Page 14: Identifying Facility Siting Raw Risk and the Risk Reduction Decision

    

Figure 2 – Wind Rose

Page 15: Identifying Facility Siting Raw Risk and the Risk Reduction Decision

    

Figure 3 - Reactor Building A (Looking North West)18

Figure 4 - Reactor Building B (Looking South West)18

Page 16: Identifying Facility Siting Raw Risk and the Risk Reduction Decision

    

Figure 5 - Site Free-Field Pressure Contours18

Figure 6 - Site Free-Field Positive Impulse Contours18