icra internship report

83
S UMMER INTERNSHIP REPORT A Study of Indian Power Sector-Enthralling Private investors? done at ICRA Limited by Manish Kumar Urele 0911033 Under the guidance of Namita Menon Senior Analyst, ICRA ltd.

Upload: manish-kumar-urele

Post on 08-May-2015

7.842 views

Category:

Business


6 download

TRANSCRIPT

Page 1: Icra internship report

SUMMER INTERNSHIP REPORT

A Study of

Indian Power Sector-Enthralling Private investors?

done at

ICRA Limited by

Manish Kumar Urele

0911033

Under the guidance of

Namita Menon

Senior Analyst, ICRA ltd.

Page 2: Icra internship report

2

Contents

1.INDIAN POWER SECTOR: AN OVERVIEW ........................................................................................................ 5

1.1.Widening Gap between Demand & Supply ......................................................................................................... 6

1.2.Change in ownership structure: .......................................................................................................................... 6

1. 3 Trends in power generation through five year plan periods ............................................................................. 7

1. 4 Capacity addition programme-target & Achievements .................................................................................. 10

1. 5 Demand Forecast ............................................................................................................................................ 11

1. 6 Coal Availabilty likely to be a bottleneck: ......................................................................................................... 12

1. 7 Transmission: ................................................................................................................................................... 13

1. 8 Distribution:...................................................................................................................................................... 14

1. 9 Private Participation ......................................................................................................................................... 15

1. 10 Investment opportunity: ................................................................................................................................. 16

2. BOTTLENECKS IN INDIAN POWER SECTOR ................................................................................................... 18

2.1 Power Sector Policy Issue ................................................................................................................................ 18

2.2. Transportation and Handling facilities for fuel ............................................................................................... 19

2.3Power equipment supplies ................................................................................................................................. 20

2.4. Regulatory & political risk .............................................................................................................................. 20

2.5. Access to fuel, land and water ....................................................................................................................... 21

2.6 GAP IN DEMAND & SUPPLY OF REQUIRED HUMAN CAPITAL ............................................................................................. 21

2.7.Law and Order................................................................................................................................................... 22

2.8 Preferential treatment with government owned/regulated companies .......................................................... 22

2.9. Non-establishment of long-term debt market ................................................................................................ 23

4.10 Meagre investment in R&D ............................................................................................................................. 23

4.12Vicious circle of various clearances .................................................................................................................. 23

3. FUELING GROWTH ...................................................................................................................................... 24

3.1Coal Reserves in India ........................................................................................................................................ 25

3.2Coal Production .................................................................................................................................................. 25

3.3Supply & Demand of coal for power sector ........................................................................................................ 26

3.4Bridging the gap ................................................................................................................................................. 27

3.4.1.Coal import ........................................................................................................................................... 27

3.4.2. Diversify the portfolio of coal importing nations ................................................................................ 29

3.4.3. Overseas Mining .................................................................................................................................. 30

3.4.4. Captive Mining .................................................................................................................................... 30

3.4.5.Private Mining ...................................................................................................................................... 30

3.4.6. Increasing the thermal efficiency of power plants .............................................................................. 31

3.4.7. Law and Order ..................................................................................................................................... 31

3.5Key Challenges facing the coal industry ............................................................................................................. 31

3.6Key Reform Measures required .......................................................................................................................... 32

3.6.1. Policy and Regulatory Framework ..................................................................................................... 32

3.6.2. Deregulation of the coal sector .......................................................................................................... 33

3.6.3. Independent Regulatory body ............................................................................................................. 33

3.6.4. Improvement in operational efficiency of the coal companies .......................................................... 33

3.6.5. Strengthening of logistics in coal distribution .................................................................................... 34

Page 3: Icra internship report

3

3.6.6. Investment in R & D ............................................................................................................................. 34

3.6.7. Focusing on technology for future ...................................................................................................... 34

3.6.8. Information Technology for the Mining Industry ............................................................................... 34

3.7 World coal Reserve and Trends in Global production and consumption .......................................................... 36

4.TRANSMISSION ........................................................................................................................................... 38

4.1Growth in Transmission Segment ...................................................................................................................... 38

4.2.Development of National Grid .......................................................................................................................... 40

4.311TH PLAN TARGETS AND ACHIEVEMENTS Funds Requirement in Transmission Segment ........................................... 40

4.4Funds Requirement in Transmission Segment .................................................................................................... 42

4.5.Sources of Funds ............................................................................................................................................... 42

4.6.Funds Available and Sources of Funds For PGCIL .............................................................................................. 43

4.7.Private Players in the League ............................................................................................................................ 43

4.7.1. Powerlink Transmission Limited .......................................................................................................... 43

4.7.2. Reliance Power Transmission Limited ................................................................................................. 43

4.7.3. Infrastructure Leasing and Financial Services (IL&FS) ......................................................................... 44

4.74. Tata Power Limited .............................................................................................................................. 44

4.7.5. Adani Power Limited ........................................................................................................................... 44

4.7.6. Torrent Power Limited ......................................................................................................................... 45

4.7.7. Gammon Infrastructure Projects limited ............................................................................................. 45

4.7.8. Kalpataru Power Transmission Limited ............................................................................................... 45

4.8. Status of Transmission projects to be executed by Private Players in 11th

plan .............................................. 45

4.9Outlook............................................................................................................................................................... 46

5. A STUDY ON ADANI POWER LIMITED .......................................................................................................... 48

5.1Background ........................................................................................................................................................ 48

5.2.Company profile ............................................................................................................................................... 49

5.3Power Projects under construction .................................................................................................................... 50

5.4.Future projects ................................................................................................................................................. 52

5.5.Recent developmentNon-establishment of long-term debt market ................................................................ 52

5.6SWOT analysis of Adani Power Limited ............................................................................................................. 52

APPENDIX A ................................................................................................................................................... 56

A.1. Raw coal production (in million tonnes) .......................................................................................................... 56

A.2. Regression analysis to determine the linear estimate of coal production ...................................................... 56

A.3. Normative requirement of coal & status of coal linkage ................................................................................. 57

A.4. Indonesian Coal Mining Industry Projections .................................................................................................. 57

A.5. World coal reserve (Country wise data) ........................................................................................................... 58

A.6.Worldwide coal production and Consumption trend ........................................................................................ 59

A.7.Existing/Proposed Inter-Regional Power Transfer Capacity ............................................................................. 61

A.8. Proposed Transmission Line with Private Participation .................................................................................. 62

APPENDIX B ................................................................................................................................................... 63

B.1. Existing Policy framework in coal industry: A Bird Eye view ............................................................................ 63

APPENDIX C ................................................................................................................................................... 65

Page 4: Icra internship report

4

C.1. State wise status of IPPs .................................................................................................................................. 65

Page 5: Icra internship report

5

1. Indian Power Sector: An Overview

The Indian power sector has registered significant progress since the process of planned

development of the economy began in 1950. Hydro-power and coal based thermal power

have been the main sources of generating electricity. Nuclear power development, which

was introduced in late sixties, is remained on slower track. Decades of economic

planning in India following independence placed significant emphasis on the

development of the power sector. Electricity generation capacity with utilities in India

had grown from 1713 MW in December 1950 to about 157229.48 MW1 (as on 28 Feb

2010). Despite the fact that present generation capacity is being 100 times than that of

the early 1950s, the per capita consumption of electricity is still not even comparable in

any standard with per capita consumption of world average of 2,595.7 Kwh.2 Per capita

electricity consumption is even lower than some of the developing Asian economies

(Table 1.0)

Table 1.0

S. No. Country Per Capita Electricity Consumption (kWh)

1 China 1780.5 2 Thailand 1950.1 3 Korea 7803.9 4 Kazakhstan 4071.7 5 Malaysia 3301 6 India 480.5

7 USA 13635.7 8 World 2,595.7

During 2005-06 The energy is a prime mover for growth of an economy. The reason for low per capita

electricity consumption could be many such as

• Non availability of electricity in rural areas

• Wide gap between demand and supply

• Lower level of industrialization, high cost of electricity etc.

1 http://www.powermin.nic.in/indian_electricity_scenario/introduction.htm

2 http://earthtrends.wri.org/text/energy-resources/variable-574.html

International Energy Agency (IEA) Statistics Division. 2007. Energy Balances of OECD Countries (2008 edition)--Economic

Indicators and Energy Balances of Non-OECD Countries (2007 edition)--Economic Indicators. Paris: IEA. Available at

http://data.iea.org/ieastore/default.asp.

Page 6: Icra internship report

6

These reasons are evident in Indian context. The govt. has put enormous effort for rural

electrification but still there is long way to go to accomplish the mission of “Electricity

for all”. Total inhabited village according to 2001 census are 593732, So far 497709

(83.8% of total) villages are being electrified and 96023 more villages are to be electrified.

Out of these 1344 villages are being electrified in period 01-Apr-09 to 31-Jan-103.

1.1. Widening Gap between Demand & Supply: The Indian Power industry has since

independence faced the demand and supply gap4 (Table 1.1.1). The said gap is still

prevalent even after government initiated the reform process in early nineties.

Table 1.1.1

Year Energy Requirement

(MU)

Energy Availability

(MU)

Energy Shortage

(MU)

Energy Shortage %

2002-03 545983 497890 48093 8.8 2003-04 559264 519398 39866 7.1 2004-05 591373 548115 43258 7.3 2005-06 631554 578819 52735 8.4 2006-07 690587 624495 66092 9.6 2007-08 737052 664660 72392 9.8 2008-09 777039 691038 86001 11.1

It is evident from the statistics that the demand-supply gap is widening over the period

of time. In the year 2008-09, the electricity generation grew by 2.71% from 704.45

Billion Units (BU) to 723.56 BU, whereas during the same period the requirement grew

from 739.35 BU to 774.32 BU. The annual energy shortage increased to 11% from 9.8%

in the previous year. The peak shortage however declined to 11.9% in the year 2008-09

from 16.6% in the previous year. The gross electricity requirement by the end of the

Eleventh Plan as projected by the Working Group on Power is 1038 BU and peak

demand estimation is 151000 MW5.

1.2. Change in ownership structure: A natural-monopoly of government was used to justify

the argument that since power sector is a public-utility and hence better to be operating

through government. The lack of competition, accompanied by political influence and

operational inefficiency, has steered the sector towards the abyss of financial distress.

Policymakers recognized this in the early 1990s and opened up the sector for private

participation. Encouraged by favorable policy developments and the advent of

3 http://www.powermin.nic.in/rural_electrification/village_electrification.htm

4 Ministry of power Annual report 2008-2009; http://www.powermin.nic.in/reports/pdf/Annual_Report_2008-09_English.pdf

5 http://recindia.nic.in/download/ar2008-09.pdf

Page 7: Icra internship report

independent regulation, greater private participation is becoming visible in the sector,

though not to the extent desirable.

The existing ownership structure of the generating

and state utilities (Table 1.2.1

owned by the private sector6.

The fuel wise break-up of the installed generation

1.2.2, which is clearly depicting the dominance of thermal power plant

portfolio with almost two-third share.

Generation Installed Capacity (MW) of Power Utilities

Ownership

Thermal

Coal Gas

State 44002 4046.12

Private 7426.38 6307.5

Central 30915 6702.23

Total 82343.38 17055.85

Source: Infraline

1.3. Trends in power generation through five year plan periods:

growth rates since 1947 are given below (As on February 2

6 http://www.powermin.nic.in/indian_electricity_scenario/introduction.htm

7

independent regulation, greater private participation is becoming visible in the sector,

though not to the extent desirable.

The existing ownership structure of the generating capacity is still

1.2.1) and only 18% of the generating capacity in the country is

Table 1.2.1

up of the installed generation capacity in India ha

s clearly depicting the dominance of thermal power plant

third share.

Table 1.2.2

Generation Installed Capacity (MW) of Power Utilities (Up to February 28, 2010)

Mode-wise breakup

Thermal Nuclear Hydro (Renewable)Diesel Total

602.61 48650.73 0 27065

597.14 14331.02 0 1233

0 37617.23 4340 8565

17055.85 1199.75 100598.98 4340 36863.4

ion through five year plan periods: The installed capacity and its

growth rates since 1947 are given below (As on February 28, 2010

http://www.powermin.nic.in/indian_electricity_scenario/introduction.htm

50%

32%

18%

Ownership Structure

State

Central

Private

independent regulation, greater private participation is becoming visible in the sector,

still dominated by CPSUs

of the generating capacity in the country is

capacity in India has shown in table

s clearly depicting the dominance of thermal power plants in generation

February 28, 2010)

Grand Total Hydro

(Renewable) RES**

(MNRE)

27065 2662.41 78378.14

1233 12764.69 28328.71

8565.4 0 50522.63

36863.4 15427.1 157229.48

The installed capacity and its

8, 2010)

Page 8: Icra internship report

8

Table 1.3.1

Plan/Year Hydro Thermal Renewable Energy Sources

Nuclear Total CAGR

March 1985 (End of 6th Plan) 14460 27030 1095 42585 -

March 1990 (End of 7th Plan) 18308 43763 1565 63636 9.89%

March 1992 (End of 2 Annual Plans)

19194 48086 1785 69065 4.27%

March 1997 (End of 8th Plan) 21658 61912 2225 85795 4.84%

March 2002 (End of 9th Plan) 26269 74549.54 1507.46 2720 105046 4.49%

March 2007 (End of 10th Plan) 34653.77 86014.84 7760.6 3900 132329.2 5.19%

Mar-08 35908.76 91906.84 11125.41 4120 143061

Mar-09 36877.76 93725.24 13242.41 4120 147965.4

Feb-10 36863.4 100599 15427.1 4340 157229.5 6.27%

It is evident from the table that after seventh plan period we have not seen a healthy

growth in terms of capacity addition. The decline in the proportion of Hydro capacity,

which started in the early seventies, has, continued. The share of Hydro-power projects

in the total installed capacity which stood at 51% during 1962-63 slipped to 34% at the

end of 6th plan and further to 26 percent at the end of 10th plan, against an optimal

share of 40%.

The Plan wise capacity addition performance shows that the Central Sector

organizations have realized better capacity addition as compared to the State sector

utilities. As a result, the share of Central Sector in the total installed capacity, which

was 16 percent at the end of the 7th Plan, rose to around 32 percent in February, 2010.

Private companies own about 18 percent of the total installed generation capacity. Their

share, however, has expected to increase in the future with the opening up of the power

sector for private participation.

The Plant Load Factor, which is an important indicator of the performance of the

thermal power generating units, has shown steady improvement at all India level and

has increased from 64.4% at the end of eighth plan period to 77.03% at the end of

February 2010. However, there remains considerable scope for further improvement,

particularly in respect of the State Sector thermal plants. The plant load factor at

various plan periods has shown in table 1.3.2

The losses on account of transmission and distribution have declined marginally but

remain much higher than the technically acceptable levels. Partly, this is attributable to

Page 9: Icra internship report

9

Table 1.3.2 Plant load Factor

five year plans Target Actual Sector-wise (Actual)

(%) (%) Central State Private

at the end of 8th plan 63.6 64.4 71 60.3 71.2

at the end of 9th plan 69.9 69,9 74.3 67 74.7

at the end of 10th plan 76.3 76.8 84.8 70.6 86.3

2009-10 (Up to Feb 2010) 77.02 77.03 85.05 70.45 82.02

Source: Infraline

inadequate investment in the T & D system.

Though we have seen a significant growth in electricity generation over the years, the

shortage of power continues to exist primarily because of growth in demand for power,

outpacing the growth in generation and generating capacity addition. The power supply

position at the end of various plan periods has shown in table 1.3.3

Table 1.3.2

Energy

Plans Requirement Availability Shortage MU % Growth MU % Growth MU %

At the end of 7th plan 2,88,974 2,66,432 22,542 7.8 At the end of 8th plan 4,13,490 6 3,65,900 3.3 47,590 11.5 At the end of 9th plan 5,22,537 3 4,83,350 3.4 39,187 7.5 At the end of 10 th plan 6,90,587 9.3 6,24,495 7.9 66,092 9.6 2009-10* 6,88,213 - 620,074 - - -

* April 2009 to January 2010

The peak demand shortage was also remained a challenge for the Indian power sector.

However, we were able to maintain the steady growth in supplying peak load vis-à-vis

increase in demand, but we had not outwent the growth so that to meet a steady deficit

of peak load. The trends in peak deficits is shown in table 1.3.4

The main reasons for shortage of power are-

• Growth in demand for power outstripping the growth in generation and capacity

addition,

• Shortage of peaking power in the grid.

• Low Plant Load Factor of some of the thermal generating units, mostly in the State

Sector

Page 10: Icra internship report

10

Table 1.3.3(Peak Deficit trends)

Demand Met Shortage

(MW) % Growth (MW) % Growth (MW) %

At the end of 7th plan 48,055 39027 9,028 18.79%

At the end of 8th plan 63,853 32.87% 52,376 34.20% 11,477 17.97%

At the end of 9th plan 78,441 22.85% 69,189 32.10% 9252 11.79%

At the end of 10th pl an 100,715 28.40% 86,818 25.48% 13,897 13.80%

2009-10* 116,281 15.46% 101,609 17.04% 14,672 12.62%

* April 2009 to January 2010 ; CAGR = Compounded Annual Growth Rate

• High Transmission & Distribution losses

• Inadequate sub-transmission and distribution network in some States.

• Inadequate inter regional transmission capacity, for supplying power from surplus

regions to deficit regions.

• Poor financial position of State Utilities rendering it difficult for them to raise the

resources necessary for making required investments to create adequate

generation, transmission and distribution system.

1.4 Capacity addition programme-target & Achievements: The planning commission and Ministry

of Power had set the target of 41,110 MW to be added in the system to meet the growing

power requirement. Out of this, the share of Central Sector was 22832 MW and that of

the Private Sector was 7121 MW. The State Sector had a share of 11157 MW. However,

once again the actual capacity addition in the power sector has been far below the target

set by the Ministry of Power. Capacity addition during this plan period was only 21180.2

MW an achievement of trifling 51.6% of the target. The summary of actual achievement

has shown in table 1.4.1

Table 1.4.1 (Capacity Addition-10th Plan achievement)

Sector Hydro Thermal Nuclear Total % achievement

Central 4495 7330 1180 13005 56.9

State 2691 3553.6 0 6244.6 55.9

Private 700 1230.6 0 1930.6 27.1

Total 7886 12114.2 1180 21180.2 51.6

% Achievement 54.8 47.6 90.8 51.6

• However, shortfalls in all the three segments i.e. Central, State and Private Sector

has reported, the shortfalls in achieving the Private sector targets of capacity

addition are notable with only 27% achievement.

Page 11: Icra internship report

11

• In terms of fuel mix comparison, nuclear sector was able to achieve 90.8% of the

modest target set for it.

• In Hydro segment 54.8% of the target was achieved and X Plan is notable in the

context of clearing the backlog. There were number of hydro projects which were

originally due for commissioning in the Eight Plan or even before. But these

projects due to associated problems were brought into the Tenth Plan with a long

history of time and cost over run. These projects included Naptha Jhakhri HEP

(1500 MW), Tehri HEP (1000 MW), Dulhasti HEP (390 MW) and Sardar Sarovar

(1450 MW). In the Tenth Plan we have the satisfaction of bringing these projects

on track and all of them have been commissioned in the X Plan.

• The dismal performance of Thermal segment at 47.6% of the target is mainly due to

most of the coal based backup projects could not set due to supply constraint on

part of BTG equipment manufacturers especially BHEL.

The planned capacity addition in 11th plan was 78577 MW, which has further revised to

62,374MW in the 11th plan Mid-Term Appraisal. The year wise capacity addition target

and the actual achievement has shown in table 1.4.2

Table 1.4.2 (Target & Achievement of capacity Addition in 11th Plan)

1.5 Demand Forecast: According to the 17th Electrical Power Survey report the demand

projections on all India basis for the year 2011-12, 2016-17 and 2021-22 has given

below in table 1.5.1

Year Total

Hydro Thermal Nuclear Hydro Thermal Nuclear Hydro Thermal Nuclear

Target 690 3490 660 1682 4767 0 0 750 0 12039

Achievement 1030 1990 220 1393 3880 0 0 750 0 9263

Target 0 1750 660 1097 1262.2 0 0 2761 0 7530.2

Achievement 0 750 0 969 852.2 0 0 882.5 0 3453.7

Target 252 2490 660 301 4679 0 292 5833 0 14507

Achievement 0 1740 440 39 3079 0 0 4287 0 9585

Target 529 5890 1220 597.5 6012 0 219.5 5891 0 20359

Achievement - - - - - - - - - -

Private

2007-08

2008-09

2009-10

2010-11

Central State

Page 12: Icra internship report

12

Table 1.4.1

Year Electrical Energy Requirement at Power Station Bus Bars (MU)

Annual Peak Electric Load at Power Station Bus Bars (MW)

2011-12 968659 1,52,746

2016-17 1392066 2,18,209

2021-22 1914508 2,98,253

1.6 Coal availability likely to be a bottleneck: There are mainly three sources of energy for power

generation on which India is relying, namely, Thermal, Hydro and Nuclear. Power

generation through nuclear energy is although at nascent stage but nuclear deal with

US and other technological advance countries will, in long run, certainly supercharge

the power generation through this untapped source. The availability of fuel is the major

concern for the policy maker especially for Thermal segment. Coal and gas supply is

likely to become bottleneck in achieving the planned capacity addition target of current

and forthcoming five-year plans. Renewable energy is so far remained untapped, but it

seems to be the promising source of energy in near future provided we could develop the

required infrastructure and technology to reap the vast unexploited renewable energy

resource. The break-up of total generating capacity in India according to the fuel used is

given in table 1.6.1.

As per table 1.3.1, it is evident that our energy requirement is largely dependent on coal.

53.3% of our energy requirement is fulfilled through coal and hence it can be easily

inferred that in the long-run, availability of coal is going to play a substantial role in

meeting the energy requirement of the nation. The coal reserves of India up to the depth

of 1200 meters have been estimated by the Geological Survey of India at 257.38 billion

tonnes as on 01.04.2007. Coal deposits are mainly located in Jharkhand, Orissa,

Chhattisgarh, West Bengal, Madhya Pradesh, Andhra Pradesh and Maharashtra.

Table 1.6.1

Fuel MW %age

Total Thermal 100598.98 64.6 Coal 82,343.38 53.3 Gas 17,055.85 10.5 Oil 1,199.75 0.9

Hydro (Renewable) 36,863.40 24.7 Nuclear 4,340.00 2.9 Renewable Sources 15,427.10 7.7 Total 1,57,229.48

As on 28 Feb 2010

Page 13: Icra internship report

13

Hydropower is currently accounting for about 25% of nation’s energy requirement. The

hydro potential is by and large untapped because of the several issue associated with it

such as very long gestation period, relocation and rehabilitation of the affected mass

population, submergence of forest and its adverse effects on flora and fauna etc.

1.7 Transmission: Transmission of electricity is defined as bulk transfer of power over a

long distance at high voltage, generally of 132 kV. In India bulk transmission has

increased from 3708 ckm (Circuits Kilometers) in1950 to more than 265,000 ckm today. The nation is divided into five regions for transmission system, namely, Northern region,

North-Eastern region, Southern region, Eastern region and western region. The

Government of India has an ambitious mission of ‘POWER FOR ALL BY 2012’. This

mission would require that country’s installed generation capacity should be at least 2,

00,000 MW by 2012 from the present level of 1,57,229.48 MW. To be able to transmit this

power to the entire country an expansion of the regional transmission network and inter

regional capacity to transmit power would be essential. The power needs to be carried

great distances to areas where load centers exist. Table 1.7.1 shows the existing

transmission capacity in India.

As part of its ambitious mission to provide electricity to the entire nation by 2012, the

Indian government is looking to strengthen the national power grid by adding more than

60,000 circuit kilometers (37,200 miles) of new transmission at a cost of about 7.5

billion rupees (R) ($146 million).

That integrated grid is expected to carry as much as 60% of the power generated in the

country. The government is also carrying out a Rs 6.5 billion ($126 million) expansion of

the five regional systems as well as the interregional grid to boost transmission capacity

from 17,000 MW to 37,000 MW7. This project will primarily connect load centers to

generation resources that are unevenly distributed around the country.

While the predominant technology for electricity transmission and distribution has been

Alternating Current (AC) technology, High Voltage Direct Current (HVDC) technology has

also been used for interconnection of all regional grids across the country and for bulk

transmission of power over long distances. A lot of emphasis is being given to increase

the inter-regional power transmission capacity. The proposed target is to achieve

cumulative capacity (all five regional grids) of 38,650 MW8 by the end of 11th planning

year period.

7 http://www.powermag.com/nuclear/Powering-the-People-Indias-Capacity-Expansion-Plans_1858.html

8 Ministry of power annual report 2008-09

Page 14: Icra internship report

14

Table 1.7.1 (All figures in ckm)9

At the end of 10th plan 11th plan Upto March 2009

+500 kV HVDC

Central 4368 5668 State 1504 1504 Total 5872 7172

765 kV

Central 1775 2709 State 409 409 Total 2184 3118

400 kV

Central 50992 61800 State 24730 27696 Total 75722 89496

220 kV

Central 9444 10066 State 105185 112894 Total 114629 122960

1.8 Distribution: Distribution is the vital component of the entire electricity supply chain,

despite being of its crucial importance it remained as neglected element and thus,

resulting in huge Aggregate Technical and Commercial (AT&C) losses. Most of the ills of

the Indian power sector find their origin in the distribution segment. The distribution

segment has lagged both in terms of operational efficiency as well as financial

performance. The slow pace of investment generation as well as distribution segment

can be attributed to the severe cash flow problem associated with the under-recovery of

costs and poor collection efficiency. Poor operational efficiency further aggravates the

situation. Table 1.8.1 shows the All India AT&C loss10 which reveals that almost 1/3rd of

the generated power is drained away as losses. This is a great matter of concern for a

developing nation like ours. With a vision to achieve overall growth of GDP at the rate of

8-9% our planning committee estimated the installed capacity necessary to achieve the

said target. With the losses in the system of such a mammoth magnitude will land us to

nowhere near the target. Proper investment and planning is required to minimize these

losses to acceptable limits.

9 http://www.indiainbusiness.nic.in/industry-infrastructure/infrastructure/power.htm

10 http://www.cea.nic.in/power_sec_reports/Executive_Summary/2010_01/1-2.pdf

Page 15: Icra internship report

15

Table 1.8.1 (All figures in percentage)

Year AT & C losses*

2002-03 32.54 2003-04 34.78 2004-05 34.33 2005-06 34.54 2006-07 32.07

*PFC figures

PFC: Power Finance Corporation Ltd.

Recognizing the urgent need of reforms in the distribution sector the Government of

India introduces, the Accelerated Power Development Programme (APDP) in 2001, for the

strengthening of Sub Transmission and Distribution network and reduction in AT&C

losses. The main objectives of the programme include improving the financial viability of

state utilities, reducing of aggregate technical and commercial (AT & C) losses,

improving customer satisfaction, and increasing the reliability and quality of the power

supply.

1.9 Private Participation: Long after the independence, Indian government realized need of

private players to ramp up the growth of power sector. To enable the private companies

to enter in the sector, Indian government has introduced many policies/ regulation (eg.

Electricity Act 2003, National Electricity Policy) so that private players will ready to

channel their money in power sector. At present, private players share 18% of total

installed capacity in power portfolio.

The government realized that unless comprehensive reforms are undertaken it would be

difficult to attract private sector to invest in the power sector. By enactment of Electricity

act 2003, formation of central electricity regulatory commission are the steps in this

regard. The government also implemented various policies to encourage participation of

private sector. Some of these policies were liquid fuel policy, Hydro power policy, Mega

Power Policy etc. However, the outcome of these policies was not as expected. The

contribution of private sector in capacity addition during 10th plan was only 1970.6 MW

which was about 16% of the total achievement in the period.

The various issues involved in the low level of private participation are discussed below:

Most of the project are financed through Project Financing route. The main

difference between corporate financing an project financing is that primary source

of loan repayment is sponsoring company backed by entire balance sheet not the

Page 16: Icra internship report

16

project alone. If project fails, the investor can expect significant losses even if it is

sponsored by AAA- rated company. This risk is the major concern for the potential

investor and hence deterring them to invest in private power projects.

Large scale capital intensive projects usually requires huge investment up front

and only start to generate revenues after a significantly long construction period.

Therefore, matching debt repayment obligation with project revenue cash flow

implies that, on average, project finance is characterized by much longer

maturities compared to other form of financing. With the change in

macroeconomic condition the lender will prone to suffer significant losses by

investing in these projects.

There are numerous operational agreement to be executed before a development of

power project which includes EPC contract, fuel supply agreement, power

purchase agreement, Govt. clearances etc. Even if the project is being prosed by

private players there are too many hurdles which private players have to cross to

commence financially viable project. Many projects are delayed due to these

agreement and later suspended by the private players with bitter experience in the

power sector.

The source of financing for independent power project are scarce, because the risk

of development are high. Until the project reaches financial closing for

construction, ther are a multitude of risk that could reduce the value of the

project to zero. This risk include:

� Political opposition of project

� Permitting risk

� Regulatory disapproval and change in law

� Inability to obtain PPA, either because the power price is too low or the term

are not acceptable

� Inability to secure fuel and fuel transportation under long term contract

Dealing with SEBs risk: The weak financial health of the SEBs is the major

concern for private players because the ability to repay the loan by private players

is directly link with the revenue generated from SEBs. In case SEBs are not in

position to pay to the private players, this will be poses a great risk on private

players in terms of economical operation of plant and the credit worthiness

associated with the name of the private company.

However, govt is timely identifying the issues and preparing the ground so that private

players can afford to enter in the power sector. It is estimated that about 23100 MW of

thermal project for which main plans order have been placed, 21040 MW of UMPP, 8380

Page 17: Icra internship report

17

MW for which linkages/ part linkages are identified and is likely to be commissioned by

private sector in 12th plan.

For 11th plan most of the project announced are either not able to have the financial

closure or having in one or other phase of clearances seeking. The state wise detail of

the projects are shown in Appendix C.1

1.10 Investment opportunity11: The Sixteenth Electric Power Survey projects a capacity

requirement of about 100,000 MW for the period 2002–12. Apart from generation

capacity addition and associated network strengthening, additional investment is

required to extend the transmission and distribution network to meet the requirement of

the un-served population.

Government of India estimates for investments in the Power Sector, in order to meet the

required targets for Eleventh Plan, stand at Rs.10316 Billion which comprises of funds

required for adding power generation capacity, R&M of existing power plants, expansion

and up-gradation of transmission and distribution infrastructure, decentralized

distributed generation etc.

The three key components which drive the Power Sector are Generation, Transmission

and Distribution. The total requirement of funds for generation projects, during the

Eleventh Plan period is estimated at Rs.4,108,960 million, with Rs.2,020,670 million for

the central sector, Rs.1,237,920 million for the state sector and Rs.850,370 million for

the private sector. Investments for transmission system development and related

schemes during the Eleventh Plan period is estimated at Rs.1,400,000 million, with

Rs.750,000 million for the central sector and Rs.650,000 million for the state sector. The

total fund requirement for sub-transmission and distribution systems development for

urban as well as rural areas during the Eleventh Plan period is estimated at

Rs.2,870,000 million inclusive of APDRP and RGGVY schemes.

11

http://recindia.nic.in/download/ar2008-09.pdf

Page 18: Icra internship report

18

2. Bottlenecks in Indian Power Sector

There is an immense opportunity for growth in Indian Power sector, but it could be

hindered or more appropriate to say, it is being outpacing because of the below

mentioned factors:

2.1 Power Sector Policy Issue:

The Indian power sector has largely dominated by political influences. Though policy

formulation may happen at the central level, its implementation lies with states. Unlike

the telecom sector, in power, the success or failure of implementation depends largely on

the will of the ruling government at the state level. To bring about reforms, like

implementation of unbundling of SEBs, privatization of transmission and distribution

are some of the responsibilities which lies with state government and the benefits from

these reforms and policies are bearing the direct relationship with efficiency with which

state govt. are implementing them. Power is a highly politicized subject and often guided

by the possible outcome of near elections. More often than not, reforms take a backseat,

given the political nature of the sector. Most importantly, in most cases state utilities

control distribution assets along with access to end customers. Tariff for different

consumer categories, is determined by the respective state electricity regulator based on

fixed RoE norms. Since the hike in tariff has not kept pace with the cost of supplying

power, losses have been rising for distribution utilities. The table 2.1.1 below shows the

skewed nature of tariff and its consequences in terms of huge losses to the SEB’s and

table 2.1.2 shows the cumulative losses in Rs. Crore to SEBs Table 2.1.1

Year Cost of supply (Paise/kwh)

Realisation (Paise/kwh)

Only Agri (Paise/kwh)

Loss (Paise/kwh)

FY02 246 181 59 65 FY03 238 195 77 43 FY04 239 203 72 36 FY05 254 209 76 45 FY06 258 221 79 37 FY07 276 227 71 49 FY08 290 232 71 58

Source: CEA, Edelweiss research

One of the main reasons why state governments have been hesitant in hiking the

agriculture/domestic tariff is that this segment forms the largest part of their vote

banks. Consequently, tariffs are far higher for industrial users, forcing them to set-up

captive power plants. If this trend continues, it could damage state financials further as

industrial customers, who bear the burden of high tariff, are going away (captive),

Page 19: Icra internship report

19

Table 2.1.2 State wise Commercial Loss (w/o Subsidy) of Power Utilities (Rs. Crore)

Region 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07

Eastern Region

-3,128 -3,316 -1,114 -1,460 -2,461 -5,173

N-E Region -1,136 -1,238 -1,081 -1,543 -806 -946

Northern Region

-8,586 -8,223 -8,031 -14,361 -10,391 -13,722

Southern Region

-11,289 -5,833 -5,132 -4,578 -4,894 -5,996

Western Region

-5,192 -2,583 -3,748 -2,053 -1,577 -1,609

Grand Total -29,331 -21,193 -19,106 -23,995 -20,129 -27,446

Source: Infraline

leading to higher subsidy funding by state governments. Further, this type of skewed

tariff structure will work as repellent for private players to invest in this sector. Since

this tariff structure will lead to the bad financial health of SEBs, which may, in turn

default in payment to these private players. Moreover, Indian transmission and

distribution system is not efficient; we have almost 33% of AT & C losses. The theft of

electricity is also a major concern. SEB’s are carrying this burden for years and resulted

into unhealthy financial condition. Whatever power is transmitted, only two-third of its

get metered and billed. This resulted in huge losses. Unlike SEBs, private player will not

be interested in power production until they ensured that every single unit that is

produced and transferred is billed.

2.2 Transportation and Handling facilities for fuel

Manifold increase in the demand for coal in coming years, particularly to meet the

energy requirement of the country, has put an onerous responsibility on the coal sector.

Although extra efforts are being made to meet this demand, the related infrastructure

appears to be stagnating, which is creating new problems for transport of coal to various

power plants across the country. This situation will worsen if infrastructure like rail,

road and port for the import of coal has not developed apace with the capacity addition

programme. Rail infrastructure will have to be strengthened to handle this demand.

Given that the coal import figures are also likely to go up to 500 Million TPA, the ports

must also gear up and invest in infrastructure development. At present, the ports on an

average cannot handle more than 30,000-35,000 tonnes of coal. Furthermore, a well

thought-out rail-cum-sea route to the southern and western ports should be given

consideration in the 11th and 12th Plans. The government must also consider coal

Page 20: Icra internship report

20

slurry pipelines. This mode of transport has discussed several times, but unavailability

of water and high implementation costs have rendered the proposition unviable.

However, no study has made to update the earlier studies after 1992. The earlier studies

must be reviewed in light of international experience

2.3 Power Equipment Supplies

The equipment used in power plant, if not supplied on time, could cause the delay in the

execution of project. In recent times, quite a few projects have got delayed due to delayed

equipment delivery across BTG (Boiler, turbine & Generator) and BoP (Balance of Plant)

segments. Selected equipment suppliers like transformers manufacturers have

increased capacity, but most of the other equipment suppliers (BTG and BoP) are yet to

increase their manufacturing capacity.

BHEL and Thermax have been key boiler manufacturers in India; BHEL, along with

Siemens, has been a key player in turbine generators. BHEL, the largest equipment

vendor in the country, has 10 GW annual BTG capacity. However, according to the

Eleventh Plan capacity addition targets, the BTG industry is required to have an annual

capacity of ~15 GW. BHEL, the major power plant equipment manufacturer, is having

its books overbooked and to accommodate the growth in power sector we need a strong

backup of these suppliers. While in the interim, developers are resorting to imports,

equipment supply has expected to be a cause for concern for developers across the

vertical. Most of the private players are inclined to import Chinese BTG equipment

because of shorter lead-time. Given the poor performance and quality record of

accomplishment of Chinese power plant equipment in the country, the efficient and

smooth operation of the power plant could be a cause for concern. In addition, power

plants with Chinese equipment work better with imported coal compared to domestic

coal. However, the TPP is based on domestic coal. Hence, its operating and maintenance

could turn out to be a cause for worry.

2.4 Regulatory & political risk

CERC is the regulatory body that sets benchmark norms, which various states could

adopt with minor changes post approval. Since most of the existing power projects are

regulated and we expect T&D utilities to continue to be regulated over the near future,

any change in norms that would affect returns could influence earnings if the same is

not offset through scope for efficiency gains. Moreover, political risk is also played as

anti-catalyst in power sector growth.

Page 21: Icra internship report

21

2.5 Access to fuel, land and water:

Most projects, going forward, are likely to be on competitive basis. Access to fuel, land

and water are critical to complete projects on time, remaining competitive at the same

time. The requirement is likely to be significantly increase in the Twelfth Plan period.

Sourcing them at reasonable prices could be a key hurdle. Any delay in execution may

not only result in higher project costs, but could also risk penalty payments; since tariffs

are predetermined, returns could be significantly hit. Table 2.5.1 indicates the

requirement of these three essential elements per MW of electricity produced based on

coal/gas as fuel input.

Table 2.5.1

Land Water Fuel Coal 0.8-1.4 acres 29 mn ltrs p.a. 3000-5000 tonnes p.a. Gas ~0.1 acres 10 mn ltrs p.a. 0.05 mmscmd p.a.

Source: CEA, Edelweiss research

The supplies from Coal India Limited is likely to increase from ~350 MT (End of 10th

Plan period) to ~ 500 MT by FY12E (End of 11th plan period), resulting in a shortfall of

~62 MT for coal-fired power plants; the deficit is expected to be met through imports.

Looking at the potential shortfall of coal in the coming years, many companies have

started looking for coal in countries like Indonesia to meet their requirements. Even

companies like NTPC have started importing coal (imports in FY09 – 2.5 mn tonnes;

FY10E – 12.5 mn tonnes) to meet coal requirement at their existing plants. GoI, taking

cognizance of the gravity of the situation, has started allotting coal mines to the private

sector so that mining of the crucial mineral can happen at a faster pace.

The other fuel like gas, nuclear fuel etc. is also going to be act as roadblock in the

growth path of Indian power sector, because of large demand and supply gap of these

resources.

2.6 Gap in Demand & Supply of required Human Capital: The total work force in the power

sector at the end of 10th plan was approximately 9.5 lakhs as per the Planning

Commission’s Working Group on Power for 11th Plan. The following are the

requirements for additional work force for the 11th plan assuming addition of 68,869

MW of generation capacity, 100,000 ckt. Kms of HV, EHV and UHV transmission lines

and 16 crore-distribution consumers.

Page 22: Icra internship report

22

Table 2.6.1 (Figure in thousands)

Area Technical (Work Force required)

Non Tech (Work Force required)

Total (Work Force required)

Thermal 31.4 12.3 43.7 Hydro 25.3 7.1 32.5

Nuclear 3.9 1.6 5.5 T & D 202.1 60.6 262.7 Total 262.7 81.7 344.4

Source: Planning Commission Working Group on Power for 11th Plan

It is evident from the table 2.6.1., that to achieve the target for 11th plan an additional

2.5 lakhs technical and 1 lakh non-technical staff is required. While large-scale

investments have been planned and numerous projects are underway, the lack of

competent work force to execute these projects, subsequently operate, and maintain

them is already being felt. The scarcity is increasing by the day and unless the

Government, industry and all other stakeholders invest in attracting and training the

available talent on an urgent basis, it has the potential to become a major bottleneck

and derail the rapid growth in the sector that has just begun.

2.7 Law and Order: India’s major coal reserves lie in the ‘red’ belt or the Naxal-affected

regions of the country. Power plants fuelled by coal blocks in these regions face issues

like irregular supply. Coal India Ltd (CIL), officials had earlier admitted to transportation

problems from coalmines in the Naxal-affected regions of Jharkhand, Orissa,

Maharashtra, Madhya Pradesh and Chhattisgarh. Although, at superficial level, Law and

order problem is not seems to bear any relation with the coal supply but on the ground

of reality, it is. The supply from these regions could boost if government pays proper

attention to maintaining law and order in these areas and the sense of safety to the

person associated with the coal mining.

2.8 Preferential treatment with government owned/regulated companies: Building a power

utility is a capital-intensive task. To raise the money for the power project, private as

well as public company are chasing to market. As an investor, one is always interested

to invest in public bodies and prefer public company over private company since one feel

investment in public (Govt. backed) company is safer. In this regard, although the

government has opened its door for private players, but where the question of fund

raising comes, they are still competitor. Regulation and reform will be effective only

when one can have fund to enter into that domain. The first thing is money so policies

must be designed to enable private players to raise easy-funds.

Further, in India, BTG packages (major power equipments) are being manufactured by

few public companies like BHEL, private companies have to depend on them to fulfill

Page 23: Icra internship report

23

their requirement. Here also private companies are subject to less preference than govt

owned bodies in case of fulfilling order backlog. This will hamper the project execution

and made companies to bear monetary losses associated with that.

2.9 Non-establishment of long-term debt market: In India, we do not have long-term debt

market. We can see its effect in the skewed preferences of power project development.

The private companies are inclined to build the thermal power project instead of hydro,

because of longer gestation period of hydro projects. Leaving aside the fact that, more

number of clearances required for hydro than compared with thermal, the non-

availability of long-term debt is the other explanation for the said skewed tendency. The

use of insurance and pension fund for infrastructure development will boost the private

share in power sector. The corporate bond market (If allowed) could also make private

player to enter in the power business.

2.10 Meagre Investment in R & D: We have put much less attention toward R&D, due to

which, our power system is not efficient. Whether it be, generation, transmission or

distribution, we are inefficient. We know that we are going to have a huge deficit of coal

supply in near future, through R & D we could come up with new technology which can

produce more energy from per unit of coal (Fuel) consumed. Presently, we are mixing the

imported coal with domestic coal to improve the overall efficiency of power plant,

pulverized coal based firing, coal firing in-tandem with oil firing are similar technologies

which we are implemented to improve the performance of power plant. There is

significant scope through R & D to come out with technologies, which enable us to

improve the efficiency of power plant. Similar story is for transmission and distribution,

we are having so much loss in t&d (though major is accounted by theft) but we are not

emphasizing the need of R & D in this field to make the system efficient.

2.11 Vicious Circle of various clearances: There are numerous clearance required to set up a

power plant. With the project financing, for most of the power projects it become very

crucial to complete the project on-time otherwise it will poses penalties as well as

monetary loss to the developer. There is long list of clearances which must have to

sought before commencing the project like forest, environment, aviation clearance,

techno-economic clearance, fuel linkage clearance, there are hundred procedures to

make to acquire land etc. this vicious circle of clearance make it very unlikely to the

project to complete on time. Government must have to redesign the list of mandatory

clearances or assure to provide clearance at faster pace.

Page 24: Icra internship report

24

Now we will discuss the various issues concerning growth of Indian power sector in

detail:

3. Fueling Growth: Coal dominates India’s 1,57,229.48 MW power generation portfolio

with mammoth share of about 53%. According to Planning Commission scenarios, by

2030, coal-fired capacity will likely be in the range of 200 GW to 400 GW, up from the

82 GW today12.

The Indian coal industry was nationalized in the early 1970s. The production of coal

increased from 70 MT (million tonnes) at the time of nationalization to 492.95 million

tonnes in 2008-09. Coal India limited and its subsidiaries are the major producers of

coal. 403.73 Million Tonnes of coal was produced by Coal India Ltd. and its subsidiaries

during 2008-09 as against the production of 379.459 million tonnes in the year 2007-

08 showing a growth of 6.4%. Singareni Collieries Company Limited (SCCL) is the main

source for supply of coal to the southern region. The company produced 44.54 million

tonnes of coal during 2008-09 as against 40.604 million tonnes during the last year.

Small quantities of coal are also been produced by TISCO, IISCO, DVC and others.

3.1 Coal Reserves in India: India is having a huge reserve of coal (coking & non-coking), India

has endowed with 267.2 Billion Tonnes of coal reserves (table 3.1.1). The proven reserve

stands at about 105.8 Billion Tonnes corresponding to approximately 8 % of world’s

total proven reserves. Coal production is being comes from open cast mines as well as

from underground mines; about 84% of the country’s coal production is from Open Cast

Mines. Power sector is the major consumer of the domestic coal production with nearly

75% share, other being steel and cement industry. Table 3.1.1 (Figures in billion tonnes)

Total Reserve

Proven Reserve

Indicated Reserve

Inferred Reserve

Coking 33.4 17.5 13.8 2.1 Non-Coking 233.8 88.3 109.7 35.8

Total 267.2 105.8 123.5 37.9 As on 01.04.2009As on 01.04.2009As on 01.04.2009As on 01.04.2009

Source: Coal India limited

12

Source: Central Electricity Authority, “Power at a Glance”; Ministry of New and Renewable Energy

Page 25: Icra internship report

25

However, we have huge reserve of coal but it is misnomer to state them as “Huge”,

because of its poor quality. Our coal is having high ash content of the magnitude of as

high as 30-40 %, compared with ash in coal in other countries of about 15-20%.

Moreover, the calorific value is also not very high.

3.2 Coal Production: The Coal India Limited (CIL) and its subsidiaries is the major producer

of coal 431.27 million tonnes of coal was been produced by Coal India Ltd. and its

subsidiaries during 2009-10 as against the production of 403.73 million tonnes in the

year 2008-09 showing a growth of 6.82%. The raw coal production and its growth have

shown in appendix A.1. If we do the regression analysis on the growth of the total coal

production from year 1998-99 to 2009-10, we find that on an average there is an

increment of about 18 Million tonnes of coal production during the time span (Appendix

A.2).

Figure 3.2.1 Figure 3.2.2

Source of input data: Coal India Limited

Figure 3.2.1: Regression analysis of total increment in the coal production during 10th plan period

Figure 3.2.2: Regression analysis of total increment in the coal production during 11th plan (First 3 years only of the plan period)

The installed capacity addition of thermal power plants, proposed in the 11th planning

commission report, is based on the “Report of the Working Group on Coal & Lignite”. Let

us compare and contrast projection of the report and its ground reality. The report says

that

• The coal production is envisaged to reach 680 mt in the terminal year 2011-12 of

the XI Plan from the anticipated production of 432.50 mt in 2006-07 implying a

CAGR of 9.47%. The incremental production in the XI Plan is envisaged to be

247.50 mt as against 104.71 mt likely to be in the X Plan.

y = 17.74x + 271.78R² = 0.9985

0

100

200

300

400

0 2 4 6

Pro

du

ctio

n

Time span

10th plan period

y = 25.9x + 353.03R² = 0.9986

370

380

390

400

410

420

430

440

0 1 2 3 4

Pro

du

ctio

n

Time span

11th plan period

Page 26: Icra internship report

26

• The incremental production envisaged in the XI Plan from CIL is 156.70 mt, SCCL

3.30 mt, and captive blocks 86.53 mt.

To supply the fuel (coal), to the capacity added, it was projected that cumulative

increment of 247.50 Mt of coal production must be done. Figure 3.2.1 and 3.2.2 are the

regression analysis of the increment in the coal production during 10th and 11th (first

three years of the plan period only) plan respectively. It is evident from the regression

that during 10th plan period there was an average annual increment of about 18 Million

tonnes of coal. During the 11th plan period the pace is although high, of about 26 million

tonnes per year, but is far way behind the required one. With this rate we can add at

most 130 Million tonnes which is only 80% of the production required from the CIL in

the working paper. The story is similar for other coal producing agency.

It is having clear implication that even though if we could able to achieve the target of

capacity addition there must be shortage of fuel because of non-availability of coal.

3.3 Supply and demand of coal for Power Sector: The overall requirement of coal for all sectors is

projected to be 916.818 Million tonnes by Coal India Limited (cumulative for all sectors)

at the end of 2016-17. The gap between the projected demand of 916.818 Million Tonnes

and the projected domestic availability of 647.5 Million Tonnes works out to 269.32

Million Tonnes in 2016-17. This requirement would need to be met from imports.

Further increasing production from captive blocks to bridge the gap also remains as a

distinct possibility.

In 11th plan upto 2011-12 the projected demand of coal is estimated to be 731.10 Million

Tonnes, the demand of power sector utilities is 483 Million Tonnes, which is about 66%.

Including the demand for captive power plant of 57.06 Million Tonnes, the share of

power sector in the projected demand, works out to about 74%. The demand of steel

sector at 68.5 Million Tonnes forms 9.4% of the projected demand. The share of cement

sector is 4.4% and that of sponge iron sector is about 4%. The balance 8.2% is for bricks

and others sectors.

As per the projection by Central Electricity Authority (CEA), capacity addition in 11th

Plan in Coal-based projects and normative requirement of coal & status of coal linkage

has given in appendix A.3.

The Detailed coal requirement vis-à-vis capacity addition during coming years, as

projected by CEA/CIL, and Demand-Supply Gap Analysis, has shown in Table 3.3.1.

Page 27: Icra internship report

27

Table 3.3.1 (Gap between Demand & Supply of Coal )

CIL Projection (In Million Tonnes)

Particular 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17

Production 460.002 486.65 514.75 542.75 575.25 609 647.5

Supply Through E-auction

46 48.665 51.475 54.275 57.525 60.9 64.75

Committed Demand on CIL sources excluding E-Auction and requirement a/c TPP coming up beyond 1.4.2009

457.544 457.544 457.544 457.544 457.544 457.544 457.544

Availability from CIL sources for TPPs coming up after 1.4.2009

-43.542 -19.559 5.731 30.931 60.181 90.556 125.206

Commitment a/c TPP coming after 1.4.2009

81.788 298.483 394.524 394.524 394.524 394.524 394.524

Net coal balance/availability for further issuance of LoA

-125.33 -318.042 -388.793 -363.593 -334.34 303.968 -269.32

Source: Coal India limited Published on 06 April 2010

3.4 Bridging the gap: Coal based thermal power plant, accounts for more than 50% of the

total installed power generation capacity, while coal based power plants account for

about 80% of domestic consumption of coal. Thus, it remains a dominant fuel for the

Indian power sector and is expected to remain so in the near future. Growth of an

economy is a function of power consumed. To meet our power requirement we are very

much dependent on the availability of coal. It is evident from the projections that

domestic coal production is not sufficient to meet our requirement. Therefore, we have to

look at the options through which we can bridge this wide gap; some of the options and

issues involved have discussed below:

3.4.1 Coal import: We could meet our requirement through import; we are mainly importing

the coal from Indonesia, Australia and South Africa. However, this option is not as

simple as it seems, there are many issues associated with it, which have discussed

below in detail:

We are importing coal largely from Indonesia, and any local regulation or coal

policy is going to affect us. Indonesian government is planning to put a cap on the

Page 28: Icra internship report

28

total export; they are planning to have a maximum export up-to 150 Million

tonnes. In a speech on “Coal supply outlook in Indonesia”, Dr. Ir. Sukma Saleh

Hasibuan (Director, Ministry of Energy and Mineral Resources (MEMR), Indonesia)

expressed this concern. The coal production and supply projection shown by him

in the speech has shown in Appendix A.4. This will create shortage in global coal

market and put pressure on international coal prices. This is having severe

consequences in Indian context, Independent Power Producers (IPPs) who are

planning to rely on imported coal in long term, will look it as highly volatile

business which confront them with high price volatility and political risk. On

December 16, 2008, the Indonesian Parliament adopted a law on mineral and coal

mining (“New Mining Law”). The New Mining Law provides that existing contracts

will continue to be valid until their expiry, but that the terms of the existing

contracts must be modified within one year to make them comply with the New

Mining Law. However, the New Mining Law is unclear as to which of its provisions

will require amendments to the terms of existing contracts to bring those

contracts into compliance with the New Mining Law. The existing holders of

contracts may be given five years to comply with such obligation. However, the

New Mining Law does not provide any details on when these government

regulations will be issued or what specific obligations will be imposed. The legal

uncertainty raised by the adoption and implementation of the New Mining Law

has increased the risks, and may increase the costs, involved in our sourcing

Indonesian coal. We cannot rely on importing of coal because of such unseen able

events and unpredictable global political environment.

Global Pressure on acquiring coal resource: Asian countries like China, Japan,

Kazakhstan, etc are also boosting their power generation capacity and the

problem of fuel is same for them. This will create a competition in acquiring the

major portion of world coal export or they might try to acquire the coalmines in

coal exporting country by going into long-term contracts. China recently signed a

MOU of $60 billion, with an Australian Coal major Resource House for a 30

million tonne coal supply deal. Thus, China is finalizing a 20-year contract to

receive high quality Australian Coal from a newly developed mining base called

First China, which is located in Western Australia State of Queensland. China is

now searching coal resources in the entire world. While Asia Pacific countries

such as Indonesia, Australia, Vietnam and Mongolia are its traditional coal import

sources, footprints of Chinese coal hunters are now left in almost all the

continentals. Russia, Canada, the US and South Africa have become China's

important coal trade partners. China is now consuming near 45 percent of the

global coal, and has accounted for over 20 percent of the world coal trade. The

said trend will further aggravate the pressure on coal prices.

Page 29: Icra internship report

29

Infrastructure: Although theoretically, coal could have imported in large quantities

to meet any domestic shortfall, problems with coal imports arise primarily because

of the inadequacy of handling facilities at ports and the lack of inland

transportation infrastructure (particularly railways) in India. To handle the large

quantity of the imported coal we have to think about the development of our other

related infrastructure like ports, transportation etc.

3.4.2 Diversify the portfolio of coal importing nations: We are importing coal from very few nations

and mainly from Indonesia. This will lead to the risk of high price volatility and political

risk. The risk could be reduced if we could diversify our portfolio of coal exporting

countries. For example, we are almost neglecting the Australia as a source of importing

coal. Figure shown below depict the decline in Australia’s share in coal import.

In these circumstances, we have to develop our relations with some other countries.

Australia can be the option. An Australian trade commission delegation, which recently

came to India, presented a paper to the coal ministry saying reducing the import duty of

thermal coal and keeping the zero import duty on coking coal intact would not only

strengthen bilateral ties but would also enhance the availability of affordable inputs for

two Indian infrastructure industry-power and steel. The trade commission pointed out

that coking coal import, which was 12 million tonne in 2006-07 from Australia, would

touch 18-20 mt in 2010-2011 and 25 mt by 2012, taking into account India’s steel

capacity addition. While Australia has its share only in India’s coking coal space,

Indonesia commands the thermal coal space. Australia wants to make an entry into the

thermal coal space, since imports of thermal coal are likely to go up13. However, political

(policy wise) uncertainty will always be there for example recently Australian govt has

put Henry Tax on the exported coal, making the coal prices sourer for the importing

nations. The similar uncertainty/risk is associated with every coal-exporting nation

because of their internal policies. Hence, it will be wise to have tie-up with as many as

13

http://www.coalspot.com/news-detail.php?nid=908

China’s coal import is

growing and export is

decreasing. Similarly,

Indonesian govt. is

planning to put cap of

150 Million Tonnes on

the net export.

Source: Barlow Jonker

Page 30: Icra internship report

30

coal exporting countries as possible to diversify the risk. The main point to be made is

that, we should not concentrate on any one or two nation for our coal requirement but

to include more countries in our portfolio from where we could tie up long-term linkages.

3.4.3 Overseas mining: Coal supply to meet our energy requirement can be fulfilled by

acquiring mines other countries. CIL has formed a subsidiary, Coal Videsh Limited

(CVL), to acquire coal blocks in a number of countries including Indonesia, South Africa

and Australia. Coal produced by CVL will be channelled into India to meet domestic

demand in future. Private companies like Tata, Adani Power limited and GVK have

acquired the coalmines mainly in Indonesia and some in Australia. IPPs are reluctant to

acquire overseas mining right because of the volatility of business and risk associated

with country specific policies, which are keep changes with time, such as imposition of

Henry Tax by Australian govt. and introduction of New Mining law, by Indonesian govt.

3.4.4 Captive Mining: The issue of demand supply gap could be resolve through encouraging

captive mining. A major constraint in ramping up production is the failure of companies

to develop captive coal blocks allotted to them by the coal ministry. Power sector has, so

far been allotted over 100 captive coalmines. Except 5-6 of them, none has come up so

far14. For Indian coal companies, project planning, approval and commissioning make

for a protracted process, involving a multiplicity of clearances at various levels: the

Boards of the companies concerned, various Ministries, the Planning Commission, and

other Government bodies. Estimates suggest that there are over 30 separate clearances,

including environmental clearances, required before Government approves a coal-mining

project. This leads to enormous delays, at times years, at the approval stage itself. If

captive mining will supercharge its pace, the net production of the coal in the country

will certainly increase and this will reduce the burden of CIL to meet the coal

requirement.

We have abundant coal reserve, according to an estimate our coal reserve will last for

more 150 years, but the problem is in mining. For this government have to encourage

the captive mining and have to look for collaboration with technologically advanced

countries for technology transfer in mining.

3.4.5 Private mining: As the captive mining projects of private sector players have not yielded

the desired results, CIL has recently proposed that these players be allowed to produce

coal even before their main projects are commissioned. Further, CIL has offered to buy

coal from private players at prices to be decided by a committee formed by CIL and the

MoC. To overcome the problem of finance or availability of requisite skills outside the

domain of the existing Indian coal companies, the GoI has allowed an associate

14

Business Standard

Page 31: Icra internship report

31

company of an end-user company to undertake captive coal mining if the end user

company holds at least 26% equity in the associate company. The GoI has also allowed

private mining in cases where a holding company has an equity stake of at least 26% in

both the end-user company and the coal mining company. Additionally, the GoI has

permitted consortium mining for captive purposes, where a number of end-users can

come together for mining coal.

3.4.6 Increasing the thermal efficiency of power plants: The possible option to curb the widening

gap between demand & supply is, to increase the thermal efficiency of the thermal power

plants. Currently, we are in practice of mixing our low quality coal with high quality

imported coal to increase the overall thermal efficiency. There is scope to invest in R & D

to come with the technology to produce more unit of electricity from per unit of the coal

consumed. The government must have to seek collaboration with developed nations for

technology transfer in thermal power generation. This will help us to meet our energy

requirement from the domestically available coal in long run.

3.4.7 Law and order: India’s major coal reserves lie in the ‘red’ belt or the Naxal-affected

regions of the country. Power plants fuelled by coal blocks in these regions face issues

like irregular supply. Coal India Ltd (CIL), officials had earlier admitted to transportation

problems from coal mines in the Naxal-affected regions of Jharkhand, Orissa,

Maharashtra, Madhya Pradesh and Chhattisgarh. Although, at the first sight, Law and

order problem is not at all seems to be linked with the coal supply but really it is. The

supply from these regions could boost if government pays proper attention to

maintaining law and order in these area and the sense of safety to the person associated

with the coal mining.

3.5 Key Challenges facing the coal industry: The critical issues facing the coal industry are

highlighted below:

Lack of Investments in Mining: In spite of the economic liberalization of 1991 the

mining sector has not seen major investments. This is possibly due to the problems

such as government policy, land acquisition, development of infrastructure,

transportation system, social engineering and community development involved in

major green field site projects. There is a need to re-look at the total management

solution for attracting investment in new mines. The solution has to lead to the

creation of joint venture institutions with central government, state government and

private sector as partners.

The facilitation for the project through provision of land, infrastructural development,

community development etc, can be done by the government agencies whereas the

investment in the mine and the associated technological inputs can come from the

private sector. In addition, the private sector must have the freedom to run the mine

Page 32: Icra internship report

32

in a cost effective manner. This may be a long term solution for future mines in India

and it will have unique opportunities for both the government and private sector to

work together for India's development.

Historically, opencast mining has been favored over underground mining. This has

led to land degradation, environmental pollution and reduced quality of coal as it

tends to get mixed with other matter.

Further, coal mining in India is associated with poor employee productivity. The

output per miner per annum in India varies from 150 to 2,650 tonnes compared to

an average of around 12,000 tonnes in the USA and Australia.

India has still not been able to develop a comprehensive solution to deal with the fly

ash generated at coal power stations through use of Indian coal.

Clean coal technologies, such as Integrated Gasification Combined Cycle, where the

coal is converted to gas, are available, but these are expensive and need modification

to suit Indian coal specifications.

Challenges in Jharia: Jharia Coal field in Jharkhand is the richest coal bearing area

in India, which contains large quantities of high-grade coking coal. However, this

area also contains a large number of mine fires, which have been burning for several

decades. A major challenge to the mining community is that of tackling fires that

have engulfed large and densely populated coal bearing areas. A technological, cost

effective, safe and minimum disturbance solution to this problem has to be found.

3.6 Key Reforms Measures Required15: The vision for coal mining industry should be to come

out with an innovative and comprehensive action plan for providing effective solutions

and their progressive implementation. This will involve innovation and research in

satellite based remote sensing, robotics, mining equipment, mining operation,

extraction, beneficiation, processing and transportation.

The task of transformation of the coal sector is formidable given the size of investment

requirement and the level of political interference that is expected during such process.

The following efforts can become the cornerstones of reform in the sector:

3.6.1 Policy and Regulatory Framework: The coal industry in India has traditionally been

characterized by state monopoly, lack of independent regulation and lack of

transparency in tariff determination. The Government has now realized that a high

growth rate in domestic production of coal could not been sustained without carrying

15 http://www.indiacore.com/coal.html

Page 33: Icra internship report

33

out structural reform and introduction of competition through participation of the

private sector.

In this regard, the Government has taken the following measures:

• Distancing of the Government from price determination of all grades of coal

• Opening of captive coal mining for power, iron and steel, and cement to private

investment

• Foreign investment in Indian companies taking up coal mining for captive use has

been permitted.

• The allocation of coal blocks are to be done on the basis of competitive bidding

(Proposal stage)

• Allowing State Government companies or undertakings to carry out mining of coal (or

lignite) reserves (either by opencast or underground method) anywhere in the country

• Reduction in customs duty on coal imports to 5 percent (currently planning to remove

the custom duty at all)

•Downsizing of the budgetary support to the national coal industry

3.6.2 Deregulation of the coal sector: Deregulation and opening of the sector to private

participation will spur state owned Coal India Limited (CIL) to improve performance, and

help attract investments to upgrade existing mines and open new ones in the next five to

seven years. Recognizing this, Government has now decided to offer access to state-

owned mining blocks to investors. Simultaneously, Coal India is being encouraged to

further identify coal blocks wherefrom coal extraction will be commercially viable.

3.6.3 Independent Regulatory body: An independent Regulatory body to govern investment and

operation in the sector is required. Such a body will help create a level playing field and

will allow the Government to distance itself from activities like allocation of blocks,

approval for mines, etc. The body can also be expected to introduce competitive price

regulation.

3.6.4 Improvement in operational efficiency of the coal companies: Coal India is in need of an

organizational transformation to gradually align its operating costs to international

standards. Mining costs of CIL are at least 35 percent higher than that of the leading

coal exporting countries such as, Australia, Indonesia, and South Africa. The

productivity should increase from 0.5 tonnes per man-year to 5 tonnes per man-year in

underground coal mines using long wall mining and from 15 tonnes per man-year to 30

tonnes per man-year in open cast mines. To improve productivity, Coal India will need to

invest in new technologies, improve processes in planning and execution of projects, and

Page 34: Icra internship report

34

institutionalize a comprehensive risk management framework. State of the art

equipment for open cast mines and long wall mining system are required. More thrust

should be given to safety for evolving accident free mining.

3.6.5 Strengthening of logistics in coal distribution: In India, the logistics infrastructure such as

ports and railways are overburdened and costly and act as bottlenecks in development

of free market. Privatization of ports may bring the needed efficiencies and capacities. In

addition, capacity addition by the Indian Railways is necessary to increase freight

capacity from the coal producing regions to demand centers in the northern and central

parts of the country. On the Indian rail network, freight trains get a lower priority than

passenger trains, a problem that promotes delays and inefficiency. Special freight

corridors would raise speeds, cut costs, and increase the system’s reliability.

3.6.6 Investment in R & D: Work is required on clean coal technology to prevent the global

warming and environmental pollution effects. For a long time there has been a talk

about integrated gasification and combined cycle technology. Organizations like NTPC,

BHEL and CSIR laboratories should work on this project. Coal India and other

producers should help in this project by contributing in beneficiation and washing of the

coal input. There should be a time bound programme for getting the results from this

project. These results will have far reaching implications on the choice of technology for

all future mining applications.

3.6.7 Focusing on technology for future: India’s numerous technology research institutions, are

working on energy related R&D. However, there is a possibility that they are operating in

a fragmented fashion. The Government may get improved recoveries on its investment

by concentrating on few important technology areas. To start with, focus may be applied

for tighter emission standards and development of technologies for extraction of

methane from coal deposits.

All mining operations today involve continuous use of explosives, thereby generating

high noise level, vibrations and shocks and very high level of dust pollution. This also

takes away very large area as explosive safety zone and environment safety zone.

Alternative technologies for using high power laser system for safe, pollution free and

precision mining need to be evolved.

3.6.8 Information Technology for the Mining Industry: India has a unique blend of small and large-

scale mining operations. There is a need for assimilating the advances in Information &

Communication technologies into mining operations for technological up gradation.

Experiences from the oil & gas exploration where most advanced ICT have been

successfully used will be useful in the mining industry as well. Many times the oil & gas

industry has given the thrust to ICT out of necessity– 3D imaging & visualization and

Page 35: Icra internship report

35

networking of large scale super computers. Indian mining industry could further

modernize by using software for an integrated data management, analysis & 3D

geological modeling, 3D plant design and advanced real time control & monitoring

systems. Application of Information Technology should lead to robotic mining for

improving the precision, safety and overall yield from mining.

In addition to the above, the following measures, which have accepted in principle, are

awaiting implementation:

• Freeing the sector from controls on distribution

• Establishment of a regulatory authority to resolve price disputes between producer and

consumers of coal

• Granting of infrastructure status to coal sector

• Allowing public sector enterprises for joint venture projects with private sector.

Page 36: Icra internship report

3.7 World coal Reserve and Trends in Global production and consumption

The proven reserve of the coal worldw

the end of 2008, in the latest report of

Appendix A.5 is depicting the country wise proven coal reserve at the end of 2008.

Although coal deposits are widely distributed, 80 percent of the world’s recoverable

reserves are located in five regions: the United States (28.9 %), Russia (19 %), China

(13.9 %), Australia/New Zealand (9.3

taken together, produced 5090.2 Million tons of coal, representing 75.1 % of total world

coal production. By rank basis Anthracite and Bituminous coal accounts for 49%

total world reserve on tonnage basis

The coal consumption and production

2008 has shown in figure 3.7.2 and

Appendix A.6.

The trend shows that there is the spurt in the

Asia pacific region with coal production in the region is nearly double in the given period

while the consumption shoots

production in Asia Pacific is coming fr

consumption, India and China are in the head of the list, China alone had

share of 42% in the total world consumption

The reserve to production ratio

China’s reserves are going to deplete very soon. In that condition, to satisfy it domestic

requirement China will heavily rely on import of the coal and with the normal demand

36

.7 World coal Reserve and Trends in Global production and consumption

proven reserve of the coal worldwide has estimated to be 826001 Million Tones

in the latest report of “BP statistical review of world energy 2009”

Appendix A.5 is depicting the country wise proven coal reserve at the end of 2008.

Although coal deposits are widely distributed, 80 percent of the world’s recoverable

reserves are located in five regions: the United States (28.9 %), Russia (19 %), China

(13.9 %), Australia/New Zealand (9.3 %) and India (7.1 %). In 200

taken together, produced 5090.2 Million tons of coal, representing 75.1 % of total world

coal production. By rank basis Anthracite and Bituminous coal accounts for 49%

on tonnage basis and Sub-bituminous & lign

production trend over the period of ten years from 1998 to

.7.2 and 3.7.3 and the detail year wise trend

shows that there is the spurt in the coal production and coal consumption in

Asia pacific region with coal production in the region is nearly double in the given period

shoots up to more than double in the same period.

production in Asia Pacific is coming from China and Australia and India. In terms of

consumption, India and China are in the head of the list, China alone had

the total world consumption for year 2008.

The reserve to production ratio (R/P ratio) for china is only 41,

China’s reserves are going to deplete very soon. In that condition, to satisfy it domestic

requirement China will heavily rely on import of the coal and with the normal demand

Total

North

America

30%Total S. &

Cent.

America

2%

Total

Europe

33%

Total

Middle

East &

Africa

4%

Total Asia

Pacific

31%

Proven Coal Reserve

Source: BP statistical review of world energy 2009

.7 World coal Reserve and Trends in Global production and consumption

s estimated to be 826001 Million Tones at

“BP statistical review of world energy 2009”.

Appendix A.5 is depicting the country wise proven coal reserve at the end of 2008.

Although coal deposits are widely distributed, 80 percent of the world’s recoverable

reserves are located in five regions: the United States (28.9 %), Russia (19 %), China

%) and India (7.1 %). In 2008, those five regions,

taken together, produced 5090.2 Million tons of coal, representing 75.1 % of total world

coal production. By rank basis Anthracite and Bituminous coal accounts for 49% of

bituminous & lignite coal for other 51%.

of ten years from 1998 to

and the detail year wise trend has shown in

coal production and coal consumption in

Asia pacific region with coal production in the region is nearly double in the given period

up to more than double in the same period. Most of the

om China and Australia and India. In terms of

consumption, India and China are in the head of the list, China alone had a whopping

for china is only 41, which indicates that

China’s reserves are going to deplete very soon. In that condition, to satisfy it domestic

requirement China will heavily rely on import of the coal and with the normal demand-

Total S. &

America

Figure: 3.7.1

Page 37: Icra internship report

supply equation, it is evident that this will lead to

coal prices.

Figure 3.7.2(Coal Production)

Source: BP statistical review of world energy 2009

Currently, India is importing coal mainly from Indonesia, which is having only 0.5% of

the world proven coal reserve and it is having R/P ratio of 19, which is the big reason to

worry for India. India has to look for other coal

requirement. In these setting Australia is seems to be a promising solution. Australia is

having almost 10% of the world proven coal reserve and it has a potential to supply for a

longer horizon (R/P ratio for Australia is 190).

United States and Russian Federation constitute almost 50% of the total proven world

coal reserve. Production and con

domestic demand has not increased in the region, in fact, the consumption in North

America is declined during the period with Russian consumption increased marginally.

The production trend is more or less

reserve to production ratio is very high in

countries.

Implication of this could be, in long

these regions in terms of coal export, and Asian countries have to heavily dependent on

them for satisfying their coal demand.

major portion of the coal cost in near future since importing bulk coal from USA or from

Russia will not going to be

constraints.

582.3

19.7

529.5

6.8 91.6

606.9

23.3522.7

9.4

Total

North

America

Total S.

& Cent.

America

Total

Europe &

Eurasia

Total

Middle

East

1998 2008

37

it is evident that this will lead to abnormal hike in the international

Figure 3.7.3(Coal Consumption)

BP statistical review of world energy 2009

Currently, India is importing coal mainly from Indonesia, which is having only 0.5% of

ld proven coal reserve and it is having R/P ratio of 19, which is the big reason to

worry for India. India has to look for other coal-exporting nation to satisfy its

requirement. In these setting Australia is seems to be a promising solution. Australia is

having almost 10% of the world proven coal reserve and it has a potential to supply for a

longer horizon (R/P ratio for Australia is 190).

United States and Russian Federation constitute almost 50% of the total proven world

Production and consumption trends in these regions pointing that the

domestic demand has not increased in the region, in fact, the consumption in North

America is declined during the period with Russian consumption increased marginally.

The production trend is more or less remains replica of consumption.

reserve to production ratio is very high in these regions when compared with other

Implication of this could be, in long run, Asian countries will become a big market for

oal export, and Asian countries have to heavily dependent on

them for satisfying their coal demand. For India, Coal transportation cost will be the

major portion of the coal cost in near future since importing bulk coal from USA or from

ng to be an easy task for India because of the transportation cost

91.6

1031.8

110.3

2031.2

Total

Africa

Total

Asia

Pacific

648.8

29.5

437.0638.4

55.5

456.4

Total

North

America

Total S.

& Cent.

America

Total

Europe &

Eurasia

1998

hike in the international

(Coal Consumption)

Currently, India is importing coal mainly from Indonesia, which is having only 0.5% of

ld proven coal reserve and it is having R/P ratio of 19, which is the big reason to

exporting nation to satisfy its

requirement. In these setting Australia is seems to be a promising solution. Australia is

having almost 10% of the world proven coal reserve and it has a potential to supply for a

United States and Russian Federation constitute almost 50% of the total proven world

sumption trends in these regions pointing that the

domestic demand has not increased in the region, in fact, the consumption in North

America is declined during the period with Russian consumption increased marginally.

remains replica of consumption. Moreover, the

when compared with other

Asian countries will become a big market for

oal export, and Asian countries have to heavily dependent on

For India, Coal transportation cost will be the

major portion of the coal cost in near future since importing bulk coal from USA or from

easy task for India because of the transportation cost

0.6 132.0

978.9

456.4

0.5

143.4

2030.7

Total

Europe &

Eurasia

Total

Middle

East

Total

Africa

Total

Asia

Pacific

1998 2008

Page 38: Icra internship report

38

4. Transmission

India has endowed with abundant natural energy resources to generate electric power.

These resources, however, are largely concentrated in certain pockets. About 90% of coal

reserves are to be found mainly in five States of Eastern & Central India, viz. Orissa,

Jharkhand, West Bengal, Chhattisgarh & Madhya Pradesh. Renewable hydro-power

potential of about 150,000 MW is available mainly in the hilly belt of the Northern and

North-Eastern regions of India. Further, a number of nuclear power plants and coastal

location coal based power plants with large generation capacities are coming-up at

diverse places. This uneven geographical distribution of exploitable energy resources

(coal and hydro potential in the country) necessitated large scale transportation of coal

across the State boundaries. A decision was taken in the early sixties to create regional

electricity grids as basic units for power planning and operations of the electric power

system. In the seventies, the regional grids were in position and advantages of sharing

generating capacity between the States, and the inter-connected operation was being

obtained. In the eighties, with the commissioning of the Regional power stations by

Central sector Generating Companies (NTPC, NHPC) and construction of EHV

transmission lines by them transcending state boundaries, the development of regional

grids was further accelerated.

4.1. Growth in transmission segment16: By the end of 10th Plan the total length of transmission

lines in the country comprised about 1.98 lakh ckt kms. During the first two fiscal years

of the 11th plan a total of about 23239 ckt km of lines have already been commissioned.

Similarly the substation transformation capacity has gone up from about 2.62 lakh MVA

at the end of the 10th Plan to 3.06 lakh MVA at the end of fiscal 2009. Figure 4.1.1(a)

and Figure 4.1.1(b) are showing the growth in the transmission segment over the five-

year plan periods.

The focus of transmission system development is to provide adequate inter-regional and

intra-regional transmission capacity so as to consolidate and strengthen the national

grid network towards a strong all-India grid. The Government of India’s (GoI’s)

transmission perspective plans focus on the creation of a national grid in a phased

manner by adding over 60,000 ckm of transmission network by 2012. It is intended that

integrated grid will evacuate an additional 100,000 MW by the year 2012 and carry 60%

of the power generated in the country. The existing inter-regional power transfer

capacity is to be enhanced to 30,000 MW by fiscal 2012 through creation of

“Transmission Super Highways”.

16

http://recindia.nic.in/download/ar2008-09.pdf

Page 39: Icra internship report

Figure 4.1.1(a)

Figure 4.1.1(a): Growth of 400kV Transmission line (in CKM) and substation (in MVA)

Figure 4.1.1(b): Growth of 200kV Transmission line (in CKM) and substation (in MVA)

Apart from the 400 kV and 200 kV transmission line and substations, new

have been taken to introduce Extr

(HVDC) system into the transmission sector. As on Jan’10 we have

transmission line with substation of capacity 4500 MVA. For HVDC we have 7443

of 500kV DC link with substation capacity of 8700 MVA.

With the support of Asian Development Bank (ADB), Power Grid Corporation of India

Ltd. (PGCIL) is implementing

Region to Northern Region (Agra). This shall be the first

having the largest power carrying

than 2000 Kms.

765kV Extra High Voltage level has already been

In order to further meet the long

environmental considerations, development

1200kV UHVAC system has envisaged.

available for 1200kV AC system

available commercially worldwide. POWERGRID has taken

out R&D in this area to develop the 1200kV system indigenously. A 1200kV

Station along with a 1200kV test line is being

Pradesh (Western Region) of POWERGRID, as a collaborative effort with

manufacturers, for indigenous development of

0

50000

100000

150000

200000

250000

*11th plan upto Jan'10

39

Figure 4.1.1(b)

: Growth of 400kV Transmission line (in CKM) and substation (in MVA)

Growth of 200kV Transmission line (in CKM) and substation (in MVA)

Apart from the 400 kV and 200 kV transmission line and substations, new

introduce Extra-high voltage (EHV) and High Voltage Direct Current

C) system into the transmission sector. As on Jan’10 we have

transmission line with substation of capacity 4500 MVA. For HVDC we have 7443

ubstation capacity of 8700 MVA.

With the support of Asian Development Bank (ADB), Power Grid Corporation of India

Ltd. (PGCIL) is implementing +/-800kV, 6000 MW HVDC Bi-pole Line from North Eastern

Northern Region (Agra). This shall be the first of its kind

having the largest power carrying capacity and transmitting power over distance more

765kV Extra High Voltage level has already been introduced in the country in Oct’2007.

meet the long-term power transfer requirement

environmental considerations, development of an overlaying Super Grid comprising

s envisaged. At present, there are no standardized parameters

available for 1200kV AC system and equipment at this voltage level are also not

commercially worldwide. POWERGRID has taken leadership initiative to carry

develop the 1200kV system indigenously. A 1200kV

Station along with a 1200kV test line is being established at Bina substation in Madhya

Region) of POWERGRID, as a collaborative effort with

manufacturers, for indigenous development of 1200kV equipment in India.

MVA

CKM

0

50000

100000

150000

200000

250000

300000

350000

(b)

Apart from the 400 kV and 200 kV transmission line and substations, new initiatives

high voltage (EHV) and High Voltage Direct Current

C) system into the transmission sector. As on Jan’10 we have 3372 ckm of 765 kV

transmission line with substation of capacity 4500 MVA. For HVDC we have 7443 ckm

With the support of Asian Development Bank (ADB), Power Grid Corporation of India

pole Line from North Eastern

of its kind (+/-800kV HVDC line)

capacity and transmitting power over distance more

introduced in the country in Oct’2007.

erm power transfer requirement, and to take care of

of an overlaying Super Grid comprising

standardized parameters

pment at this voltage level are also not

leadership initiative to carry

develop the 1200kV system indigenously. A 1200kV UHVAC Test

stablished at Bina substation in Madhya

Region) of POWERGRID, as a collaborative effort with equipment

1200kV equipment in India.

MVA

CKM

Page 40: Icra internship report

40

4.2 Development of National Grid: The primary energy resources in India are concentrated in

certain geographical locations. This lead to asymmetry of power generation in all

territory in India and hence resulted in the problem of load balancing, some parts

having excess supply and others are in deficit. This has necessitated the formation of a

National Power Grid to fulfill the following objectives:

• Enable transfer of power from power surplus regions to deficit regions.

• Enable optimal development and utilization of coal and hydro resources, in the overall

interest of the nation.

• Improve economy, reliability and quality of power supply.

At present, the country is having five regional grids, namely, Northern region, North-

Eastern region, Southern region, Eastern region and western region. The intra-state

power transfer capability is shown in Appendix A.1

PGCIL is playing an important role for development of National Grid. In line with this

plan, various inter-regional transmission schemes have been implemented/ are under

implementation/ planned in the country to enhance the interregional power transfer

capacity of National Grid to more than 37,000 MW by the year 2012. Establishment of

National Grid is also facilitating transfer of short term surplus power from anywhere to

anywhere in the country from generation under State and Private sector as well.

4.3 11th Plan targets and achievements: To evacuate the additional power generated planned

during 11th plan, and to strengthen the transmission network, the planning commission

has targeted to have nearly 80000 ckm of transmission lines. Table 4.3.1 is showing the

year wise transmission line addition programme.

Table 4.3.1

Planned Transmission Line addition in 11th plan (all figures in ckm)

Particular 2007-08 2008-09 2009-10 2010-11 2011-12

765 kV line 160 653 632 501 1345

+/- 500kV HVDC line 0 1250 280 0 0

400 kV line 6907 8025 9548 14750 12948

200 kV line 5448 6493 7303 7548 2280.5

Total 12515 16421 17763 22799 16573.5

Source: CEA

Page 41: Icra internship report

But, the actual work done durin

April 2010, only 39285 ckm of transmission line have strung, which is

total target. Table 4.3.2 is showing the actual work done during the last three years of

11th plan and Figure 4.3.3 is showing the comparision of target and actual work done

during the last three years.

Actual Transmission Line addition in 11

Particular

765 kV line

+/- 500kV HVDC line

400 kV line

200 kV line

Total

Source: Infraline

Plan

765 kV line 160

+/- 500kV HVDC line 0

400 kV line 6907

200 kV line 5448

0

2000

4000

6000

8000

10000

12000

41

But, the actual work done during the years is not in line with the planned target. Up to

April 2010, only 39285 ckm of transmission line have strung, which is

.3.2 is showing the actual work done during the last three years of

.3.3 is showing the comparision of target and actual work done

Table 4.3.2

Transmission Line addition in 11th plan (all figures in ckm)

2007-08 2008-09 2009-10

370 564 445

120 1180 280

6947 6827 7857

4160 4171 5139

11597 12742 13721

Figure 4.3.3

Actual Plan Actual

2007-08 2008-09

370 653 564

120 1250 1180

6947 8025 6827

4160 6493 4171

g the years is not in line with the planned target. Up to

April 2010, only 39285 ckm of transmission line have strung, which is only 45% of the

.3.2 is showing the actual work done during the last three years of

.3.3 is showing the comparision of target and actual work done

plan (all figures in ckm)

10 2010-11 (up to 30 April 2010)

97

122

455

551

1225

Plan Actual

2009-10

632 445

280 280

9548 7857

7303 5139

Page 42: Icra internship report

42

The growth plan for inter-regional power transfer capacity is shown in table 4.3.4, which

depicts that by the end of 11th plan we are planning to have the total inter-regional

capacity of 37150 MW. At present, we have established the level of 20800 MW of transfer

capacity, which is only 56% of the target capacity.

Table 4.3.4

Inter Regional Transmission Capacity growth plan

Year 2002 2005 2007 2010 2012

765 kV 0 0 1100 2200 9200

400 1000 2400 7800 11400 16400

HVDC bi-pole 0 2000 2500 2500 6500

HVDC b-t-b 2000 3000 3000 3000 3000

HVDC mono-pole 200 200 200 200 200

220 kV 1850 1850 1850 1850 1850

Total 5050 9450 16450 21150 37150

Source: http://www.cea.nic.in/power_systems/National_Electricity_Plan/Chapter_1_Introduction.pdf

4.4 Funds requirement in Transmission Segment: In order to meet the projected requirement for

additional power generation capacity of 100,000 MW by 2012, the Ministry of Power

estimates that the investment requirement for the inter-state transmission network will

be Rs. 710 Billion. A significant proportion of this (Rs.500 Billion) is expected to be

undertaken by the Power Grid Corporation of India Ltd. (POWERGRID), the Central

Transmission Utility (CTU). The remainder (Rs.210 Billion) is expected to come from by

private investors.

4.5 Sources of fund: The following are the major sources of fund:

• Asian Development Bank (ADB)

• World Bank

� International Finance Corporation (IFC)

� International Bank for Reconstruction & Development (IBRD)

� Multilateral Investment Guarantee Agency (MIGA)

• India Infrastructure Finance Corporation Ltd. (IIFCL)

• Power Finance Corporation

� Consortium Lending Group

� Business Development Associates

� Equity financing

• Commercial Banks

Page 43: Icra internship report

43

• Private Equity funds

• Private Investor

• Domestic Bond market

• Domestic term lending institutes

4.6 Funding available and sources of fund for PGCIL: Towards achieving the targeted investment

programme of Rs. 55,000 Crore for XI Plan for providing matching transmission system

for generation capacity addition in Central sector and other generation projects for

which transmission system is required to be built by POWERGRID, significant progress

has been made during FY 2008-09. Out of this, investment of about Rs. 15,000 Crore

has already been made during the initial 2 years period of the Plan, an achievement of

about 27% of plan outlay. For the year 2009- 10, an outlay of about Rs. 11,500 Crore

has been kept for POWERGRID and balance about Rs. 28,500 Crore shall be utilized in

the last 2 years period of XI Plan. Loan agreement for USD 400 Million from The World

Bank has been signed in Jan’09 and loan became effective from 30th March’09. Further,

loan agreement for USD 200 Million from ADB has been signed in March’09. In addition,

The World Bank has also agreed for another loan of USD 1 Billion to POWERGRID, for

which preparatory and appraisal missions were deputed by the Bank in Feb.’09 and

May’09 respectively. Loan negotiation was been expected to take place in 2nd quarter of

FY 2009-10. Thus, till date, around 70% of total loan requirement for XI Plan has

already been tied-up or identified and balance shall be raised on year-to-year basis as

per requirement. Besides, a proposal for loan assistance of USD 1 Billion from ADB17

had been submit to Ministry of Finance in Feb.’09. ADB has agreed to consider this

assistance under ADB lending programme for 2010-11. 4.7 Private Player in the league

4.7.1 Powerlink Transmission Limited: Powerlink Transmission Ltd. is the pioneering example

of the Public Private Partnership. It is a joint venture between Tata power and PGCIL

with 51:49 stakes resp. Powerlinks transmits power from the 1,020 MW Tala Hydro

Electric Power Project in Bhutan and surplus power from the Eastern/north-eastern

region of India through its transmission lines between Siliguri (West Bengal) and

Mandola (Uttar Pradesh), spanning a distance of 1,166 kms. With a total investment of

Rs. 1,545 crores, the project, consisting of 440 kV double-circuit transmission lines, was

completed within the scheduled time frame and cost estimates.

4.7.2 Reliance Power Transmission Limited: Reliance Power Transmission Limited (RPTL), a

wholly owned subsidiary of Reliance Infrastructure Limited (RInfra), has been qualified

for 3 transmission projects- North Karanpur, Talcher-II and East-North interconnection.

The three projects are worth Rs56.5bn out of which North Karanpur is for Rs35bn,

17

Power-grid Corporation India Ltd. Annual report 2008-09

Page 44: Icra internship report

44

Talcher II for Rs12bn and East-North Interconnection for Rs9.5 billion18. The qualifying

for three transmission projects being undertaken for the first time through the

competitive bidding guidelines issued by Govt. of India.

Earlier, RPTL has bags the WRSSS II transmission project initiated by the nodal agency

POWERGRID and awarded the project of construction of 1500 kilometers transmission

line. This has envisaged the Company as the first ever private transmission utility to

build these first ever 100% privately owned inter-state transmission projects in the

country, which would, on completion facilitate the smooth flow of surplus power in

Eastern and Northern Regions of the Country to Western Region by the end of year

2010.

4.7.3 Infrastructure Leasing and Financial Services (IL&FS): On January 2009, The Public Sector

Power Grid Corporation has announced that it has tied up with Infrastructure Leasing

and Financial Services to set up a joint venture company for taking up intra-

transmission and sub-transmission projects within India and abroad. Both the company

and IL&FS are having 50 per cent stake each in the company. The JV Company,

Powergrid IL&FS Transmission, will carry out these works for state power utilities taking

the public private partnership (PPP) route in India and with neighbouring countries

subject to bilateral agreement between the countries.

4.7.4 Tata Power Limited: The Company has about 1,100 Circuit Kms. of Transmission

Network in Mumbai Licensed Area, comprising 973 Circuit Kms. of 220 kV/110 kV

overhead lines and 124 Circuit Kms of 220 kV/110 kV underground cables. The

Company’s transmission system connects Trombay and the hydro generating stations to

17 receiving stations spread across the Mumbai Licensed Area, with major ones being

Carnac, Parel, Dharavi, Salsette and Borivali receiving stations. As per the Tata Power,

annual report 2008-09, Tata power is going to expand is transmission link through PPP

route in India. Power Transmission Limited, JV of PGCIL & Tata Power, is the pioneering

step toward this.

4.7.5 Adani Power Limited: Adani Power Ltd. announces to set up the longest private HVDC

link in India. This system will provide efficient transmission of power over a distance of

approximately 1000 kilometers from Mundra power plant in Gujarat to Mohindergarh in

Haryana. Adani Power Ltd awarded Siemens a contract to install a bipolar 500-kilovolt

High-Voltage Direct Current (HVDC) transmission system of 2500 MW capacity. The first

phase of the project is scheduled to be commissioned in February, 2011 and the second

phase in July, 2011. The investment estimate for the project is about Rs. 3000 crore.

The company had issued IPO to fund its ongoing and upcoming projects.

18

http://www.kseboa.org/news/736-reliance-power-transmission-limited-qualifies-for-3-transmission-projects.html

Page 45: Icra internship report

45

4.7.6 Torrent Power Limited: The subsidiary of the company, Torrent power Grid Limited

(TPGL) – a joint venture with PGCIL is constructing the 400 kV double circuit

transmission line from SUGEN to Pirana (Ahmadabad). The company also has installed

transmission line to connect SUGEN plant with substation of GETCO. Three 220 kV

double circuit lines from SUGEN to Surat and two 220 kV receiving substation are

completed by the TPGL to take of transmission of power to meet Surat requirement.

4.7.7 Gammon Infrastructure Projects limited: Gammon Infra is keen to undertake projects in

power sector. They have already bid for two transmission projects under the Rural

Electrification Corporation (REC) and two other transmission contracts to be awarded by

the Power Finance Corporation (PFC). Though they have not achieved any success in

getting those but still they are eyeing to grab the opportunity whenever it comes.

4.7.8 Kalpataru Power Transmission Ltd: Kalpataru Power Transmission Ltd, one of the leading

global EPC players in power T&D sector has secured an order worth over Rs. 319 Crores

from Chhattisgarh State Power Transmission Co. Limited.

4.8 Status of Transmission projects to be executed by Private Players in 11th plan

Target for transmission capacity addition in 11th plan is about 80000 ckm. Out of

which as of now only 7637 ckm of transmission line has being propose or executed by

the private sector, which is a meager portion of about 10% of the total planned target.

Sl No.

Project Company Length(ckm)

Target date

Remark

1 (+/-)500 KV Mundra - Mohindergarh Bipole

Adani Power Limited

1938 Apr'11

2 Mundra-Dehgam Adani Power Limited

868 jan'09 Commissioned on July'09

3 Mohindergarh HVDC - Mohindergarh HVPNL

Adani Power Limited

20 Apr'11

4 Mohindergarh HVDC – Bhiwani

Adani Power Limited

160 Apr'11

5 Kondapalli – Nunna Lanco 44 Aug'09 Commisssioned on Oct'09

6 LILO of RTPS- Guttur at Thorangallu JSW S/S

Jindal TPC 16 Nov'08 Commissioned on Aug'09

7 Jaigad - New Koyna JSW Energy 110 Jun'10 8 Jaigad - New Karad JSW Energy 220 Jun'10 Revised to

Dec'10 9 LILO of Rourkela- Raigarh at

Sterlite TPP Sterlite 25 Apr'10

10 Tiroda TPP- Warora Adani Power 400 Mar'11

Page 46: Icra internship report

46

Limited 11 Parli(PG)-Pune(PG) Reliance 646 Jul'10 12 Pune(PG)-Aurangabad(MSEB) Reliance 472 Jul'10 13 Parli(PG)-Solapur (PG) Reliance 272 Jul'10 14 Solapur(PG)-Kolhapur(MSEB) Reliance 438 Jul'10 15 LILO of Lonikhand(MSEB)-

Kalwa(MSEB) at Pune (PG) Reliance 3 Jul'10

16 LILO of Solapur(MSEB)- Karad(MSEB)at Solapur(PG)

Reliance 232 Jul'10

17 Rajgarh(PG)-Karamsad(GEB) Reliance 468 Jul'10 18 Limbdi(Chorania((GEB)-

Ramchodpura(Vadavi)(GEB) Reliance 206 Jul'10

19 Ranchodpura(Vadavi)(GEB)- Zerda(Kansari(GEB)

Reliance 280 Jul'10

20 Akhakol-Puna torrent Power 72 Apr'07 Commissioned on May'09

21 Akhakol-Bhatar torrent Power 136 Apr'07 Commissioned on May'09

22 Akhakol-Ved(Dabholi) torrent Power 52 Apr'07 Commissioned on Jun'09

23 Allain Duhangan-Panarsa- Nalagarh D/C

Malana Power Company Ltd

349 Jun'09 Revised to May'10

24 LILO of Allain Duhangan-Nalagarh at Chhaur

Malana Power Company Ltd

1 Sep'09 Revised to Apr'10

25 Budge Budge -Kosba CESC ltd 170 Aug'09 Commissioned on Feb'10

26 Sterlite TPP - Sterlite captive plant D/C

Sterlite 9 Jan'10 Commissioned on Mar'10

27 Budhil-Chamera-III Lanco 30 Mar'10 Source: Infraline

4.9 Outlook:

In late 2006, the power ministry decided to set up around 14 mega transmission

projects through private participation, on the lines of the ultra mega power project series

(See appendix A.2 for details of project announced). The plan involves development of

independent transmission lines on BOO basis where the bidder would be selected

through the tariff-based competitive bidding route. The transmission lines mainly

included evacuation systems associated with large power generation projects of NTPC

and Damodar Valley Corporation, apart from setting up transfer systems from power-

surplus to power-deficient regions. India's experience with private participation in power

transmission projects so far is limited. The only project yet awarded on 100 per cent

Page 47: Icra internship report

47

private equity basis is the Western Region System Strengthening Scheme-II that is being

developed by Anil Ambani’s Reliance Power Transmission Ltd. In terms of private equity

in a power transmission project, the very first project is the Tala power transmission

lines bring power to India from the 1,020-Mw Tala hydropower project in that country.

This 400 kV D/C line being operated on BOO basis is India's first instance of PPP in

power transmission. Clearly, in the coming years, the private sector will need to

contribute to the power transmission network, much like it has been doing to the

generation segment. By themselves, PGCIL and state transmission utilities would not be

able to fill up the infrastructure deficit. Going by the current evolution, private

participation could be in various forms—fully independent power transmission lines,

infrastructure developed in joint venture with PGCIL and that developed in joint venture

with state utilities. There is immense scope for private participation, offering scope for

all types of risk profiles of private transmission developers. It is also clear that the power

transmission sector in future will be a breeding ground for entrepreneurship, where

long-standing EPC contractors—KEC International, Larsen & Toubro, Kalpataru Power

Transmission, to name a few—could groom themselves into independent power

transmission companies. It is also imminent that modern-day entrepreneurs that have

taken on power generation in a big way—GMR Group, Lanco, GVK Group, Sterlite

Energy, Essar, JSW, etc—and existing private power utilities like Tata Power and

Reliance Infrastructure, will make a mark on the power transmission sector. Apart from

the 14-odd transmission projects that the Centre plans to build on BOO basis, it is also

learnt that private developers will be sought for setting up evacuation systems for the

ultra mega power project series. So far, four projects—Sasan, Mundra, Krishnapatnam

and Tilaiya—have been awarded and there are at least eight more on the anvil. The

Centre has proposed that while PGCIL would set up transmission infrastructure for the

first three projects—and it has already begun work—private participation will be sought

beginning from the fourth onwards. This gives a huge window of opportunity to private

developers. Just like the UMPP series brought in efficient technology (supercritical

parameters), one could look forward to similar efficiencies in the concomitant

transmission systems. Developing power generation projects along with transmission

infrastructure also makes private entrepreneurship more holistic. Besides, competition

amongst private players might also bring down wheeling charges, eventually bringing

down end-consumer power tariffs. Although private participation in power transmission

would materialize only in degrees, it is encouraging to see that a beginning has been

made, the delay notwithstanding. The Centre could do well by using the remaining years

of the XI Plan to fine-tune guidelines and bidding procedures, so that a fertile ground is

created for private power transmission systems to bear fruit from the XII Plan onwards.

Page 48: Icra internship report

48

5. A Study on Adani Power Limited

5.1 Background

The Adani Group was been founded in 1988 as a trading house and since its inception; the company has start setting its feet into many sectors, the main ones being Power, SEZ development, Ports, Oil and Gas exploration, etc. Adani power limited is a part of Adani group. Adani Enterprise Limited (“AEL”), is the flagship company of the Adani Group, with total revenues of Rs. 11,587.89 Crores for the fiscal year 2009. AEL was one of the largest traders of coal in India for the three years period ended March 31, 2008, with coal mining rights both in the international and domestic markets, and according to Central Electricity Regulatory Commission, for the three years period ended March 31, 2008, AEL was one of the largest power traders, by volume, in India. With the commissioning of power projects, the Adani Group will have vertically integrated in power sector value-chain through presence in related activities such as coal mining, coal trading, shipping, power generation, power transmission and power trading. Another Adani Group company, Mundra Port and Special Economic Zone Limited (“MPSEZL”), owns and operates one of the largest private sector commercial ports in India, a Special Economic Zone (“SEZ”) at Mundra and a railway line between Mundra and Adipur leading to strong synergies with their projects being set up in close vicinity. In addition, the Adani Group also has operations in other industries, including commodities trading, real estate development, agro processing and logistics.

The Company has successfully forayed into power generation business through its subsidiaries, Adani Power Ltd., Adani Power Maharashtra Ltd., Adani Power Rajasthan Ltd., Adani Power Dahej Ltd., Adani Power (Overseas) Ltd. and Mundra Power SEZ Ltd. in the states of Gujarat, Maharashtra and Rajasthan.

Adani Power Ltd was been incorporated in the year 1996. The Company became a private limited company on June 3, 2002. Thereafter, it was been converted into a public limited company on April 12, 2007. It is a part of the Adani Group, a leading business group in India. The Company was been promoted by Gautam S. Adani and Rajesh S. Adani, together with their relatives. In 2004, pursuant to internal restructuring amongst the promoters, the entire shareholding of the company was been transferred to Mundra Port and Special Economic Zone Ltd ('MPSEZL'). Subsequently, on May 29, 2006. MPSEZL transferred its entire shareholding in the company to Adani Enterprises Ltd (AEL). The Company is mainly involved in power-project development activity, which is developing, and will operate and maintain, power projects in India. It has four thermal power projects under various stages of development, with a combined installed capacity of 6,600 MW. In addition, the company is also planning to develop two power projects with a combined installed capacity of 3,300 MW. The company intends to sell the power generated from these projects under a combination of long-term power purchase agreements to industrial and state-owned consumers and on merchant basis.

Page 49: Icra internship report

49

5.2 Company Profile

Promoter’s holding (As on 31 march 2010)19

• Foreign (Promoter & Group) - 3.2513%

• Indian (Promoter & Group)- 70.2484%

• Non Promoters (Institution)- 10.7239%

• Non Promoters (Non-Institution)-- 15.7764%

Subsidiaries

• Adani Power Ltd (100%)

• Adani Power Maharashtra Ltd (76.64%)

• Adani Power Dahej Ltd (100%)

• Adani Power Rajasthan Ltd (100%)

• Adani Power Overseas Ltd

• PT Adani Global, Indonesia – for coal mining in Indonesia

(Subsidiary of Adani Global Pte. Ltd., Singapore)

• PT Kapuas Coal Mining, Indonesia – for coal mining in Indonesia

(Subsidiary of Adani Global Pte. Ltd., Singapore)

• Adani Global Pte. Ltd., Singapore.

(Subsidiary of Adani Global Ltd., Mauritius)

• Parsa Kente Collieries Ltd.

• Adani Mining Pvt. Ltd.

Key persons

• Gautam S. Adani, Chairman

• Rajesh S. Adani, Managing Director

Key Company Highlights

• The company came out with an IPO in July 2009 to raise Rs. 3000 crores, which

was heavily subscribed 21 times.

• In the power sector, apart from generation the company has further ventured into

power trading, coal trading, Indonesian and Indian coal mining.

• It has made itself into a vertically integrated company with the above verticals

along with shipping.

• APL is executing 400 KV D/C transmission line of about 431 KM distance from

Mundra to Dehgam.

• It is also executing ±500 KV Bi-Pole HVDC transmission line of about 800 KM

distance from Mundra to Haryana for transmitting 2500 MW.

19

http://www.capitaline.com/user/framepage.asp?id=1

Page 50: Icra internship report

50

5.3 Power Projects Under Construction:

The Company is currently developing four thermal power projects through its said

subsidiaries, which are under various stages of development, with a combined installed

capacity of 6,600 MW. In addition, the group is also planning to develop two power

projects with a combined installed capacity of 3,300 MW at Dahej and Kawai. The group

has intended to sell the power generated from these projects under a combination of

long-term power purchase agreements to industrial and state-owned consumers and on

merchant basis. Details of the various power projects undertaken by the Company have

shown in table 5.2.1:

Mundra Phase I & II Power Project are having four sub-critical generation units of

330 MW each, with combined capacity of 1,320 MW. The boiler, turbine and

generator (“BTG”) package for Mundra I and II was been awarded to Sichuan

Machinery and Equipment Import & Export Company Limited and Kowa Company

Limited, respectively. The first 330 MW unit of Mundra Phase I and II Power

Project is already commissioned in Jan’10, and the second unit of Phase I on

Mar’10. The actual target commissioning date of these units, however, was Aug

2009 and Sept 2009 resp.

Mundra Phase III Power Project will have two super-critical generation units of

660 MW each, with combined capacity of 1,320 MW. The engineering,

procurement and construction (“EPC”) contract for Mundra III was been awarded

to SEPCO-III Electric Power Construction Corporation and Shandong Tiejun Electric

Power Engineering Company Limited. The first 660 MW unit of Mundra Phase III

Power Project has expected to commission by April 2011, and that the power

project will have fully commissioned by September 2011.

Mundra Phase IV Power Project will have three super-critical generation units of

660 MW each, with combined capacity of 1,980 MW. The EPC contract for Mundra

IV was been awarded to SEPCO-III Electric Power Construction Corporation and

Shandong Tiejun Electric Power Engineering Company Limited. The first 660 MW

unit of Mundra Phase IV Power Project has expected to commission by July 2011,

and that the power project will have fully commissioned by March 2012.

Page 51: Icra internship report

51

Table 5.2.1

Project Location Installed capacity

(MW)

Fuel Supply status

Estimated cost (Rs. Crore)

Expected commissioning

date

Off take arrangement

Mundra Phase 1

(Unit 1&2)

Gujarat 2X330 Coal supply agreement with

AEL

2280 Commissioned Long term PPA for 1000 MW entered with GUVNL

Mundra Phase 2

(Unit 3&4)

Gujarat 2X330 Coal supply agreement with AEL

2070 Unit 3: Feb’10 Unit 4: May’10

Mundra Phase 3

Gujarat 2X660 Coal supply agreement with AEL

5796 Unit 1: Apr’11 Unit 2: Sep’11

PPA for 1000 MW with

GUVNL for 25 yrs,

agreement to sell 221 MW as merchant power with

AEL Mundra Phase 4

Gujarat 3X660 Coal supply agreement with AEL; Coal linkages of 1366 MW recommended

8960 Unit 1: Jul’11 Unit 2: Nov’11 Unit 3: Mar’12

Long term PPA for 1424 MW entered

with UHBVNL and DHBVNL

Tiroda Power Project

(phase I)

Maharashtra 2X660 Captive mines allocated by

MoC for generating up to 1000 MW of

power; coal linkage of 1180

MW recommended

6560 Unit 1: May’11 Unit 2: Aug’11

Long term PPA for 1320 MA entered

with MSEDCL

Tiroda Power Project (phase

II)

Maharashtra 1X660 2730 Apr’12 -

Tiroda Power Project will have three super-critical generation units of 660 MW

each, with combined capacity of 1,980 MW. The BTG package for Tiroda was been

awarded to Sichuan Machinery and Equipment Import and Export Company

Limited. The first 660 MW unit of Tiroda Power Project has expected to

commission by May 2011, and that the power project will have fully commissioned

by April 2012. The Adani Power Maharashtra Limited (“APML”) will develop the

Tiroda Power Project, APML is 77.38% owned subsidiary of Adani Power limited.

The expected cost of the project has estimated to Rs 6560 and Rs. 2730 crores, for

Phase I and Phase II respectively.

Page 52: Icra internship report

52

5.4 Future Projects

1980 MW Thermal Coal based power project - Dahej, Gujarat- The project is been developed by the subsidiary Company, Adani Power Dahej Ltd. (APDL). The Dahej power project will utilize imported coal as primary fuel for its operations. The Company has also entered into long-term coal supply arrangements for importing coal for its Dahej power project. It is expected to have three super-critical generation units of 660 MW each, with combined capacity of 1,980 MW. The project has expected to have fully commission by June 2012. The total cost of the project is Rs 8881 crores with an expected debt equity ratio of 80:20.

1320 MW Thermal Coal based power project - Kawai, Rajasthan- The subsidiary Company, Adani Power Rajasthan Ltd. (APRL) is developing this project. The company has entered into a memorandum of understanding with the State Government of Rajasthan to use its best efforts to facilitate the provision of coal for such power project from the Government of India or other sources. The said power project shall have two super-critical generation units of 660 MW each, with combined capacity of 1,320 MW. The power project has expected to have fully commission by January 2012. The cost for the project has expected to be Rs 5889 crores that shall be financed in a debt equity ratio of 80:20.

5.5 Recent Developments

Feb 23, 2010: Adani to develop 1,320MW power project in Madhya Pradesh, India

Feb 15, 2010: Adani Power Receives LOI from Government of Madhya Pradesh on

Development Of 1,320MW Coal-Fired Power Plant

5.6 SWOT analysis of Adani Power Limited

STRENGTH:

1. Secured Fuel Supply: The Adani power is having secured fuel linkage for its on-going

projects. With India having the demand-supply gap in coal requirement, having fuel

linkages is one of the biggest advantages for Adani power ltd. Moreover, Adani group’s

past experience in coal trading will be having cutting-edge advantage over other

companies in the field. The Adani Group has coal mining rights in both the international

and domestic markets. PT Adani Global, a wholly owned subsidiary of AEL, has entered

into agreements with holders of long-term exploitation licenses to exclusively mine, coal

in Bunyu Island, Indonesia. In addition, they have also allocated two coal blocks in India

to mine coal for our Tiroda Power Project. Adani Shipping Pte Limited, Singapore, a

wholly owned subsidiary of AEL, has entered into a contract for the purchase of two

newly built capsize vessels with expected delivery by December 2010 for transportation

of coal from the Indonesian coalmines operated by AEL.

Page 53: Icra internship report

53

2. IPO Listing: The Company was come out with an IPO on July 2009 to raise Rs. 3000

crores, which was been subscribed heavily. With the IPO, company has ascertained to

meet its long-term financial requirement. An IPO, therefore, allows a company to tap a

wide pool of stock market investors to provide it with large volumes of capital for future

growth.

3. Long term Power off take arrangement: The Company has entered into power off-take

agreements with Gujarat Urja Vikas Nigam Limited (“GUVNL”), Uttar Haryana Bijli

Vitran Nigam Limited (“UHBVNL”), Dakshin Haryana Bijli Vitran Nigam Limited

(“DHBVNL”) and MSEDCL for its Mundra Power Projects and Tiroda Power Projects. Off-

take agreements generally provide that the consumer purchases power in pre-

determined quantities at fixed rates and surplus power, if any, may then be sold to other

consumers in the unregulated market. The power produced in excess of what is sold

under our Mundra Phase I and II Power Project, Mundra Phase IV Power Project, and

Tiroda Power Project off-take agreements will be sold on merchant basis. These

arrangements will allow the company to mitigate their off-take risk, while enabling them

to sell the residual power at market-determined rates.

4. Integrating power generation business with the installation of transmission lines: The Company is

vertically integrating itself in power business, with acquiring coalmines, erecting

transmission line for evacuating power, from their power station to the load center. The

first of such transmission lines from Mundra to Dahegham, Gandhinagar has already

been constructed. Having complete portfolio for power generation business, the company

has significantly diversified its risk and dependence on other utilities.

WEAKNESS:

1. No Operating History: The APL is having no significant history of operating the power

projects. Therefore, it is difficult to evaluate its future performance. If it will fail on any

ground, internal or external factor, it will not only hamper the growth of company but

also the confidence of investor in investing for the power projects being executed by the

private player.

2. High Leveraging risk: The company’s debt to equity ratio is almost tripled during the

period March ’08 to march’ 09. Moreover, for its Tiroda project, the project specific debt

to equity is planned to be 80:20. With such a high level of debt, the company is exposing

itself to a high risk of market fluctuation.

3. Nature of debt: The majority of company’s borrowings are subject to floating interest

rates, which exposes them to interest rate risk. Further, they do not currently enter into

any swap or interest rate hedging transactions in connection with their loan agreements

Page 54: Icra internship report

54

or other material agreements. Any increase in interest expense may have an adverse

effect on business prospects, financial condition and results of operations.

4. Dependency on thermal fuel sources: The Company is only focusing on coal based thermal

power projects may be because of its confidence in getting fuel supply from AEL.

However, if external environment changes, national political or foreign political, because

of any reason then the company find it difficult to take out required return on equity

and pay out the interest on the mammoth debts.

OPPORTUNITIES:

1. Power deficit in India: The India is having huge power deficit and is remained to continue

as per 11th plan. The government is looking for significant private participation to bridge

this gap. This created an immense opportunity for APL to establish itself in Indian power

business. The main thrust of capacity addition is put on through private participation;

therefore, government is willing to attract private players through subsidy, relaxation on

import duties on certain power equipment, tax holiday etc. It is a great time to reap out

all the benefits.

2. Ultra Mega Power Projects: The government has identified nine power projects as ultra

mega power projects (UMPP), which are been planned to be executed through private

participation.

3. Private Coal Mining: Although, Amendment 2000 bill is pending in parliament pertaining

to private coal mining, given the group’s exposure in coal mining ( AEL experience) there

are great opportunity for the company to establish itself as major private coal producer,

once the bill is passed. The government is also planning to go for captive mining through

private company; this further provides added opportunity to the company to set its feet

in this segment.

THREATS:

1. Global regulations: To meet the coal requirements for Mundra, AEL proposes to procure

coal from the mines in Bunyu Island, Indonesia. On December 16, 2008, the Indonesian

Parliament adopted a law on mineral and coal mining (“New Mining Law”). The New

Mining Law provides that existing contracts will continue to be valid until their expiry,

but that the terms of the existing contracts must be modified within one year to make

them comply with the New Mining Law. However, the New Mining Law is unclear as to

which of its provisions will require amendments to the terms of existing contracts to

bring those contracts into compliance with the New Mining Law. The existing holders of

contracts may be given five years to comply with such obligation. However, the New

Mining Law does not provide any details on when these government regulations will be

issued or what specific obligations will be imposed. The legal uncertainty raised by the

Page 55: Icra internship report

55

adoption and implementation of the New Mining Law has increased the risks, and may

increase the costs, involved in our sourcing Indonesian coal.

2. Long term Power Purchase Agreements: The profitability of company is largely a function of

their ability to manage costs during the terms of our PPAs and to operate power projects

at optimal levels. Failing which, under the PPAs obligation, the company is liable to

penalties and in certain specified cases, customers may also terminate such PPAs.

Moreover, if there is an industry wide increase in tariffs, the company will not be able to

renegotiate the terms of the PPAs to take advantage of the increased tariffs. In addition,

in the event of increase in operational costs, they not have the ability to reflect a

corresponding increase in tariffs. Therefore, the prices at which they supply power may

have little or no relationship with the costs incurred in generating power, which means

that company’s margins will fluctuate significantly.

3. Chinese made BTG equipments: Core equipment of all power plants under execution is of

Chinese origin, except MPP phase II, for which the core Boiler, Turbine and Generator

(BTG) order, has been placed with Kowa Company of Japan. Given the poor performance

record of accomplishment of Chinese power plant equipment in the country, the efficient

and smooth operation of the power plant could be a cause for concern. If the power

plant’s availability falls below 75%, penalty has been paid under PPA. In addition, power

plants with Chinese equipment work better with imported coal compared to domestic

coal. However, the TPP is based on domestic coal. Hence, its operating and maintenance

could turn out to be a cause for worry.

4. Depreciation of rupees against foreign currencies: A substantial portion of company’s revenues will

be denominated in Rupees, while the company is expected to incur substantial

indebtedness denominated in foreign currencies to finance the development of power

projects. Moreover, they have certain EPC contracts with foreign players, the payments

under these contracts are denominated in foreign currencies and secured by a letter of

credit. Therefore, there is a exchange rate risk for payments made pursuant to the letter

of credit until the conservation of liability from foreign currency to Rupees. In addition,

coal supply agreements with AEL are denominated in US dollars. Accordingly, any

depreciation of the Rupee against these currencies will significantly increase the Rupee

cost to them of servicing and repaying their foreign currency payables.

Page 56: Icra internship report

56

Appendix A:

A.1 Raw coal production (in million tonnes)

Source: Coal India LimitedSource: Coal India LimitedSource: Coal India LimitedSource: Coal India Limited

A.2 Regression analysis to determine the linear estimate of coal production

Source of

input data: Coal India Limited

y = 18.071x + 202.35R² = 0.9906

0

50

100

150

200

250

300

350

400

450

500

0 2 4 6 8 10 12 14

Pro

du

ctio

n

Time span

Linear Estimate of Coal Production Period 98-99 to 09-10

Page 57: Icra internship report

A.3 Normative requirement of coal & status of

Description

Coal Linkage Available Block Allocated Imported coal tied up

Total available

Linkage required to be accorded Block required to be accorded Imported coal to be tied up

Total

Total Coal based capacity addition (MW) in 11th plan

Source: Central Electricity Authority (CEA)

A.4

Source: Speech given by Dr. Ir. Sukma Saleh Hasibuan (DirectorSupply Outlook in Indonesia on 16 October 2007

0

50

100

150

200

250

300

350

400

2006 2007 2008

45 49 53

148134

193183

Indonesian Coal Mining Industry ProjectionsIndonesian Coal Mining Industry ProjectionsIndonesian Coal Mining Industry ProjectionsIndonesian Coal Mining Industry Projections

57

ormative requirement of coal & status of coal linkage

Capacity (MW) Normative requirement (MT)

32455 162.285830 29.15

0

38285 191.43

be 4500 22.5

2500 12.5

Imported coal to be tied up 1350 4.05

8350 39.05

Total Coal based capacity addition (MW) in 11th plan

46635 230.475

Source: Central Electricity Authority (CEA)

Dr. Ir. Sukma Saleh Hasibuan (Director Ministry of Energy and Mineral Resources (MEMR), Indonesia) on on 16 October 2007

2008 2009 2010 2015 2020

53

7590

130

170

145 150 150 150

198

225240

280

Domestic Export Production

Indonesian Coal Mining Industry ProjectionsIndonesian Coal Mining Industry ProjectionsIndonesian Coal Mining Industry ProjectionsIndonesian Coal Mining Industry Projections

Normative requirement (MT)

162.28 29.15

0

191.43

22.5

12.5

4.05

39.05

230.475

Ministry of Energy and Mineral Resources (MEMR), Indonesia) on Coal

2020 2025

170

220

150 150

320

370

Page 58: Icra internship report

58

A.5 World coal reserve (Country wise data)

Coal: Proved Reserves at end 2008Anthracite Sub-bituminous

Million tonnes and bituminus and lignite Total Share of Total R/P ratio

US 108950 129358 238308 28.9% 224Canada 3471 3107 6578 0.8% 97Mexico 860 351 1211 0.1% 106Total North America 113281 132816 246097 29.8% 216

Brazil - 7059 7059 0.9% *Colombia 6434 380 6814 0.8% 93Venezuela 479 - 479 0.1% 74Other S. & Cent. America 51 603 654 0.1% *Total S. & Cent. America 6964 8042 15006 1.8% 172

Bulgaria 5 1991 1996 0.2% 70Czech Republic 1673 2828 4501 0.5% 75Germany 152 6556 6708 0.8% 35Greece - 3900 3900 0.5% 58Hungary 199 3103 3302 0.4% 351Kazakhstan 28170 3130 31300 3.8% 273Poland 6012 1490 7502 0.9% 52Romania 12 410 422 0.1% 12Russian Federation 49088 107922 157010 19.0% 481Spain 200 330 530 0.1% 32Turkey - 1814 1814 0.2% 21Ukraine 15351 18522 33873 4.1% 438United Kingdom 155 - 155 � 9Other Europe & Eurasia 1025 18208 19233 2.3% 268Total Europe & Eurasia 102042 170204 272246 33.0% 218

South Africa 30408 - 30408 3.7% 121Zimbabw e 502 - 502 0.1% 287Other Africa 929 174 1103 0.1% *Middle East 1386 - 1386 0.2% *Total Middle East & Africa 33225 174 33399 4.0% 131

Australia 36800 39400 76200 9.2% 190China 62200 52300 114500 13.9% 41India 54000 4600 58600 7.1% 114Indonesia 1721 2607 4328 0.5% 19Japan 355 - 355 � 289New Zealand 33 538 571 0.1% 111North Korea 300 300 600 0.1% 17Pakistan 1 2069 2070 0.3% 496South Korea 133 - 133 � 48Thailand - 1354 1354 0.2% 75Vietnam 150 - 150 � 4Other Asia Pacific 115 276 391 � 26Total Asia Pacific 155809 103444 259253 31.4% 64

Total World 411321 414680 826001 100.0% 122

Page 59: Icra internship report

59

A.6 Worldwide coal production and Consumption trend

Source: http://www.bp.com/sectiongenericarticle.do?categoryId=9023784&contentId=7044480

Coal: Production *

Million tonnes oil equivalent 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008

US 603.2 584.3 570.1 590.3 570.1 553.6 572.4 580.2 595.1 587.7 596.9Canada 40.8 39.2 37.1 37.6 34.9 32.2 34.7 35.6 34.5 36.9 36.0Mexico 4.8 4.9 5.4 5.3 5.3 4.6 4.7 5.2 5.5 6.0 5.5Total North America 648.8 628.3 612.6 633.2 610.2 590.4 61 1.8 620.9 635.2 630.6 638.4

Brazil 2.0 2.1 2.9 2.1 1.9 1.8 2.0 2.4 2.2 2.3 2.4Colombia 21.9 21.3 24.9 28.5 25.7 32.5 34.9 38.4 42.6 45.4 47.8Venezuela 4.7 4.8 5.8 5.6 5.9 5.1 5.9 5.3 5.4 5.9 4.7Other S. & Cent. America 0.8 0.5 0.4 0.5 0.4 0.5 0.2 0.3 0.6 0.5 0.6Total S. & Cent. America 29.5 28.7 33.9 36.8 33.9 39.9 43. 0 46.3 50.9 54.0 55.5

Bulgaria 5.0 4.2 4.4 4.4 4.4 4.6 4.5 4.1 4.2 4.7 4.8Czech Republic 26.0 23.1 25.0 25.4 24.3 24.2 23.5 23.5 23.7 23.4 22.8France 3.6 3.3 2.3 1.5 1.1 1.3 0.4 0.2 0.2 0.2 0.1Germany 61.3 59.4 56.5 54.1 55.0 54.1 54.7 53.2 50.3 51.5 47.7Greece 8.1 8.0 8.2 8.5 9.1 9.5 9.6 9.4 8.6 9.0 9.1Hungary 3.0 3.1 2.9 2.9 2.7 2.8 2.4 2.0 2.1 2.0 1.9Kazakhstan 36.0 30.0 38.5 40.7 37.8 43.3 44.4 44.2 49.1 50.0 58.8Poland 79.6 77.0 71.3 71.7 71.3 71.4 70.5 68.7 67.0 62.3 60.5Romania 5.7 5.1 6.4 7.1 6.6 7.0 6.7 6.6 6.5 6.7 6.5Russian Federation 103.9 112.1 116.0 122.6 117.3 127.1 131.7 139.2 145.1 148.2 152.8Spain 9.3 8.6 8.0 7.6 7.2 6.8 6.7 6.4 6.2 6.0 5.5Turkey 13.9 13.3 13.9 14.2 11.5 10.5 10.5 12.8 13.4 15.8 17.8Ukraine 39.9 42.3 42.0 43.5 42.8 41.7 42.2 40.9 41.8 39.9 40.2United Kingdom 25.0 22.5 19.0 19.4 18.2 17.2 15.3 12.5 11.3 10.3 10.9Other Europe & Eurasia 16.7 13.4 14.0 14.4 15.3 15.8 15.6 14.7 15.7 16.7 17.1Total Europe & Eurasia 437.0 425.3 428.6 438.2 424.6 437. 2 438.7 438.4 445.3 447.0 456.4

Total Middle East 0.6 0.7 0.6 0.5 0.4 0.6 0.6 0.6 0.5 0.5 0.5

South Africa 127.1 125.6 126.6 126.1 124.1 134.1 137.2 137.7 138.0 139.6 141.1Zimbabw e 3.5 3.2 2.8 2.9 2.5 1.8 2.4 1.9 1.4 1.4 1.1Other Africa 1.4 1.3 1.2 1.2 1.3 1.6 1.3 1.2 1.2 1.1 1.1Total Africa 132.0 130.1 130.7 130.2 128.0 137.5 140.9 140. 7 140.5 142.1 143.4

Australia 149.8 160.8 166.3 179.9 184.5 190.1 198.8 206.5 211.0 218.5 219.9China 628.7 645.9 656.7 697.6 733.7 868.4 1012.1 1120.0 1205.1 1282.4 1414.5India 126.5 124.4 132.2 133.6 138.5 144.4 155.7 162.1 170.2 181.0 194.3Indonesia 38.3 45.3 47.4 56.5 63.6 70.3 81.4 93.9 119.2 133.7 141.1Japan 2.0 2.2 1.7 1.8 0.8 0.7 0.7 0.6 0.7 0.8 0.7New Zealand 2.0 2.1 2.2 2.4 2.7 3.2 3.2 3.2 3.5 3.0 3.1Pakistan 1.5 1.5 1.4 1.5 1.6 1.5 1.5 1.6 1.7 1.6 1.9South Korea 2.0 1.9 1.9 1.7 1.5 1.5 1.4 1.3 1.3 1.3 1.3Thailand 6.1 5.7 5.1 5.6 5.7 5.3 5.6 5.8 5.3 5.1 5.1Vietnam 6.4 4.9 6.5 7.5 9.2 10.8 14.7 18.3 21.8 23.1 23.6Other Asia Pacif ic 15.7 18.0 19.3 19.7 19.3 20.0 21.7 23.8 24.1 24.9 25.3Total Asia Pacific 978.9 1012.8 1040.8 1107.8 1161.0 1316 .2 1496.9 1637.1 1764.0 1875.4 2030.7

Total World 2226.8 2225.9 2247.1 2346.7 2358.1 2521.8 2732 .0 2884.2 3036.3 3149.5 3324.9

Page 60: Icra internship report

60

Coal: Consumption *

Million tonnes oil equivalent 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008

US 545.7 544.9 569.0 552.2 552.0 562.5 566.1 574.2 565.7 573.2 565.0Canada 30.8 30.5 31.8 34.0 31.6 33.4 29.9 31.7 31.0 32.3 33.0Mexico 5.9 6.0 6.2 6.8 7.6 8.6 7.0 9.1 9.4 9.1 9.0Total North America 582.3 581.4 606.9 593.0 591.1 604.5 60 3.0 614.9 606.1 614.6 606.9

Argentina 0.8 0.9 0.8 0.6 0.5 0.7 0.8 0.9 0.3 0.4 0.4Brazil 11.4 11.9 12.5 12.2 11.5 11.8 12.8 12.7 12.5 13.4 14.6Chile 3.7 3.9 3.0 2.3 2.4 2.3 2.6 2.6 3.2 3.3 3.2Colombia 2.8 2.4 2.7 2.7 2.5 2.4 2.0 2.3 2.4 2.7 2.3Ecuador - - - - - - - - - - -Peru 0.4 0.5 0.5 0.4 0.4 0.4 0.5 0.5 0.4 0.5 0.5Venezuela ^ 0.1 ^ ^ ^ ^ - ^ 0.1 0.1 ^Other S. & Cent. America 0.5 0.6 0.6 0.7 1.0 2.1 1.9 1.8 2.1 2.2 2.2Total S. & Cent. America 19.7 20.1 20.1 19.0 18.3 19.6 20. 5 20.8 20.9 22.5 23.3

Austria 3.0 3.2 3.2 2.9 3.0 2.9 2.9 2.8 2.8 3.1 3.1Azerbaijan - - - ^ ^ ^ ^ ^ ^ ^ ^Belarus 0.4 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 ^Belgium & Luxembourg 7.9 6.9 7.6 7.6 6.7 6.5 6.4 6.1 6.1 5.5 4.6Bulgaria 8.2 6.6 6.3 6.9 6.5 7.1 6.9 6.9 7.1 7.8 7.5Czech Republic 20.5 19.0 21.0 21.2 20.6 20.8 20.5 19.8 19.4 20.0 19.1Denmark 5.6 4.7 4.0 4.2 4.2 5.7 4.6 3.7 5.6 4.7 4.1Finland 3.4 3.6 3.5 4.0 4.4 5.8 5.3 3.1 5.2 4.6 3.4France 16.1 14.3 13.9 12.1 12.4 13.3 12.8 13.3 12.1 12.3 11.9Germany 84.8 80.2 84.9 85.0 84.6 87.2 85.4 82.1 83.5 85.7 80.9Greece 8.8 9.1 9.2 9.3 9.8 9.4 9.0 8.8 8.1 8.5 8.6Hungary 3.4 3.4 3.2 3.4 3.1 3.4 3.1 2.7 2.9 2.9 2.8Iceland 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1Republic of Ireland 1.9 1.6 1.8 1.9 1.8 1.7 1.8 1.8 1.6 1.5 1.4Italy 11.6 11.6 13.0 13.7 14.2 15.3 17.1 17.0 17.2 17.2 17.0Kazakhstan 22.9 19.8 23.2 22.5 22.8 25.2 26.5 27.2 28.1 30.8 33.6Lithuania 0.1 0.1 0.1 0.1 0.1 0.2 0.2 0.2 0.2 0.2 0.2Netherlands 9.4 7.7 8.6 8.5 8.9 9.1 9.1 8.7 8.5 9.0 9.2Norw ay 0.7 0.7 0.7 0.6 0.5 0.5 0.6 0.5 0.4 0.4 0.5Poland 63.8 61.0 57.6 58.0 56.7 57.7 57.3 55.7 58.0 57.9 59.4Portugal 3.6 3.6 4.5 3.7 4.1 3.8 3.7 3.8 3.8 3.3 3.2Romania 7.0 6.7 7.0 7.2 7.6 7.8 7.4 7.6 8.5 7.4 7.7Russian Federation 100.7 101.0 105.2 102.4 103.0 104.0 99.5 94.2 96.7 93.5 101.3Slovakia 4.5 4.3 4.0 4.1 4.0 4.2 4.1 3.9 3.8 3.8 3.9Spain 17.7 20.5 21.6 19.5 21.9 20.5 21.0 21.2 18.5 20.2 14.6Sw eden 2.0 2.0 1.9 2.0 2.2 2.2 2.3 2.2 2.3 2.2 2.0Sw itzerland 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1Turkey 24.0 22.6 25.5 21.8 21.2 21.8 23.0 26.1 28.8 31.0 30.4Turkmenistan - - - - - - - - - - -Ukraine 36.9 38.5 38.8 39.4 38.3 39.0 39.1 37.5 39.8 39.7 39.3United Kingdom 38.6 34.3 36.7 38.9 35.7 38.1 36.6 37.4 40.8 38.2 35.4Uzbekistan 1.2 0.9 1.0 1.1 1.0 1.0 1.2 1.1 1.1 1.4 1.4Other Europe & Eurasia 20.9 16.4 17.3 16.5 18.7 19.6 20.1 18.4 15.5 15.7 16.1Total Europe & Eurasia 529.5 504.5 525.6 518.7 518.6 533. 9 527.8 514.1 526.6 528.9 522.7

Iran 1.0 1.0 1.1 1.1 1.1 1.1 1.0 1.2 1.3 1.3 1.3Kuw ait - - - - - - - - - - -Qatar - - - - - - - - - - -Saudi Arabia - - - - - - - - - - -United Arab Emirates - - - - - - - - - - -Other Middle East 5.8 5.7 6.2 7.2 7.6 7.9 8.0 7.9 7.8 8.1 8.1Total Middle East 6.8 6.7 7.3 8.3 8.7 9.0 9.0 9.1 9.1 9.3 9.4

Algeria 0.5 0.5 0.5 0.6 0.9 0.8 0.8 0.6 0.7 0.7 0.7Egypt 0.8 0.6 0.6 0.7 0.7 0.9 0.9 1.0 0.9 1.0 1.0South Africa 83.4 82.3 81.9 80.6 83.5 89.3 94.5 91.9 93.8 97.7 102.8Other Africa 7.0 6.5 6.4 7.3 7.2 6.4 7.2 7.3 6.8 6.2 5.7Total Africa 91.6 89.9 89.4 89.3 92.4 97.4 103.4 100.8 102.3 105.7 110.3

Australia 45.8 46.2 46.5 47.9 51.3 50.5 53.1 54.9 56.9 55.8 51.3Bangladesh 0.1 ^ 0.3 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4China 651.9 656.2 667.4 681.3 713.8 853.1 983.0 1100.5 1215.0 1313.6 1406.3China Hong Kong SAR 4.4 3.9 3.7 4.9 5.4 6.6 6.6 6.7 7.0 7.5 7.0India 136.1 135.8 144.2 145.2 151.8 156.8 172.3 184.4 195.4 212.9 231.4Indonesia 9.3 11.6 13.7 16.7 18.0 17.9 20.2 26.1 24.2 28.4 30.2Japan 88.4 91.5 98.9 103.0 106.6 112.2 120.8 121.3 119.1 125.3 128.7Malaysia 1.6 1.8 1.9 2.6 3.6 4.2 5.7 6.3 7.3 7.1 5.0New Zealand 1.1 1.2 1.1 1.3 1.3 1.9 2.0 2.2 2.2 1.6 2.1Pakistan 2.1 2.1 2.0 2.1 2.4 2.9 3.8 4.1 4.2 5.1 6.7Philippines 2.7 2.9 4.3 4.5 4.7 4.7 5.0 5.7 5.5 5.9 6.2Singapore - - - - - - - - - - -South Korea 36.1 38.2 43.0 45.7 49.1 51.1 53.1 54.8 54.8 59.7 66.1Taiw an 23.6 24.8 28.7 30.6 32.7 35.1 36.6 38.1 39.6 41.8 40.2Thailand 7.3 7.9 7.8 8.8 9.2 9.4 10.4 11.2 12.4 14.1 15.4Other Asia Pacif ic 21.3 24.0 25.5 26.4 25.9 26.5 29.6 30.9 33.2 34.2 34.6Total Asia Pacific 1031.8 1048.0 1089.0 1121.5 1176.1 133 3.2 1502.5 1647.6 1777.2 1913.5 2031.2

Total World 2261.7 2250.7 2338.4 2349.7 2405.2 2597.6 2766 .2 2907.4 3042.3 3194.5 3303.7

Page 61: Icra internship report

61

A.7

Existing/Proposed Inter-Regional Power Transfer Capacity

(By the End of XI Plan i.e. 2012) in India (Figures in MW)

Region Existing Under Phase-I X Plan & XI Plan Total

East-North Dehri-Sahupuri 220 kV S/c 200 Sasaram HVDC back-to-back 500 Muzaffarpur-Gorakhpur 400 kV D/c (Tala Transmission System) 2500 Barh/Kak/N.K' pura 765 kV 3x S/c 5000 Pooling Station-West of Delhi 2000 MW HVDC Bipole Line 2500 Hirma-Jaipur HVDC bipole 2500 Sub-Total 700 12500 13200 East-West Bodhipadar-Korba 220 kV 3 circuits 450 Rourkela-Raipur 400 kV D/c 1000 Hirma-Raipur 400 kV D/c 1000 Hirma-Seepat 400 kV D/c 1000 Sub-Total 450 3000 3450 West-North Vindhyachal HVDC back-to-back 500 Existing 220 kV AC lines 350 Malanpur-Bhiwadi 765 kV S/c 2500 Zerda-Sirohi 400 kV D/c 1000 Sub-Total 850 3500 4350 East-South Gazuwaka HVDC back-to-back 500 500 Existing 220 kV AC lines 200 Talcher-Kolar HVDC bipole 2000 2nd HVDC bipole 2500 Sub-Total 700 5000 5700 West-South Chandrapur HVDC back-to-back 1000 Karnataka-Maharashtra 500 Existing 220 kV AC lines 300 Sub-Total 1300 500 1800 East-North East Bongaigaon-Malda 400 kV D/c 800 Bipara-Salakati 220 kV D/c 200 Sub-Total 1000 1000 Total 5000 24500 29500

Source: http://www.indiastat.com/table/power/26/transmissionanddistribution/284/33358/data.aspx

Page 62: Icra internship report

62

A.8

Proposed Transmission Line with Private Participation Sl. No. Project Sl. No. Project

1 1980 MW North Karanpura Project 8 1320 MW Barh-II Project 2 Talcher Augmentation Scheme 9 1000 MW Nabinagar Project 3 1000 MW Maithon Project 10 3200 MW Daripally project 4 Import of NER/ER surplus by NR 11 500 MW Kodarma Project 5 SR-WR Synchronous interconnector 12 1000 MW Mejia Ext. Project 6 Kawas-Navsari 400 kV DC 13 4000 MW Lara Project 7 Navsari-Mumbai 400 kV DC 14 1000 MW Simhadri Ext. project

Page 63: Icra internship report

63

Appendix B:

B.1 Existing Policy framework in coal industry: A Bird Eye view:

Eligibility to do Coal Mining: Under the provisions in Section 3 (3) of Coal Mines

(Nationalisation) Act, 1973, Coal mining was mostly reserved for the public sector.

Amendments to Coal Mines (Nationalisation) Act, 1973 have been done to facilitate

captive mining in approved end-use industries. The parties eligible to do coal mining in

India without the restriction of captive consumption are:

i. The Central Government, a Government company (including a State Government

company), a Corporation owned, managed and controlled by the Central Government.

ii. A person to whom a sub-lease has been granted by the above mentioned Government

company or corporation having a coal mining lease, subject to the conditions that the

coal reserves covered by the sub-lease are in isolated small pockets or are not sufficient

for scientific and economic development in a coordinated manner and that the coal

produced by the sub-lessee will not be required to be transported by rail.

Coal Mining Lease under the Mines and Minerals (Regulation & Development) Act, 1957:

Under the provisions of Section 5 (2) of the Coal Mines (Nationalisation) Act, 1973, the

Coal India Limited enjoys the status of becoming the deemed lessee of the concerned

State Governments in relation to all the nationalised coal mines. Under the provisions of

Section 11 (2) of the Coal Bearing Areas (Acquisition & Development) Act, 1957 also, the

Coal India Limited acquires the same status of becoming deemed lessee of the concerned

State Governments in relation to the lands over the coal bearing areas acquired under

this Act. The deemed leases being in the nature of statutory leases, the Coal India

Limited does not have to obtain separate leases under the MMRD Act, 1957 from the

concerned State Government in respect of the nationalised mines and the coal bearing

lands acquired under the CBA Act.

However, in case any of the companies eligible to do coal mining in India including CIL

and the other Government and private coal companies want to acquire coal bearing

lands under the Land Acquisition Act, 1894, they will be required to obtain coal mining

leases from the concerned State Governments under the MMRD Act, 1957. Coal being a

mineral listed in the First Schedule of the MMRD Act, 1957, the State Governments can

grant coal mining leases only with the previous approval of the Central Government

accorded under the proviso to Section 5 (1) of MMRD Act.

Page 64: Icra internship report

64

Before the previous approval of the Central Government is accorded, the coal mining

company is required to get the mining plan for the proposed coal mining area approved

from the Central Government. The coal mining leases under the MMRD Act are now

granted for 20-30 years initially and can be renewed for a further period of 20 years with

the previous approval of the Central Government. The coal mining leases under the

MMRD Act, 1957 are ordinarily subject to a ceiling of 10 sq. kms area.

Page 65: Icra internship report

65

Appendix C

C.1 State wise status of IPPs

1. Andhra Pradesh

Proposed Projects:

Promoter Company Name of the

Project Location Capacity

(MW) Fuel Type Status

GVK Group

400 MW Natural Gas

Based Merchant

Power Plant

Jegurupadu Village, Kadiyam Mandal, East

Godavari District, Andhra Pradesh 400 MW Natural Gas

Expected to come up in Twelfth Plan

GMR Group CCPP Vemagiri, Rajahmundry,

Andhra Pradesh 800 MW Natural Gas

Expected to come up in Twelfth Plan

Thermal Powertech

Corporation (India)

Limited (TPCIL) 1980 MW TPP

Painampuram village, Muthukur (M), Nellore

district, Andhra Pradesh 1980 MW

Blended Coal (30%-Imported +

70% -domestic)

Expected to come up in Twelfth Plan

Alfa Infraprop (P)

Limited 2640 MW

Project

Near Komarada village & Mandal, Vizianagaram

District, Andhra Pradesh 2640 MW Coal

Expected to come up in Twelfth Plan

Kineta Power

Private Limited Kineta Thermal Power Project

Tamminapatnam village, Chillakur Mandal, Nellore District, Andhra Pradesh 1980 MW Coal

Expected to come up in Twelfth Plan

Krishnapatnam

Power Corporation

Limited, an SPV of

Navayuga Group

Company Krishnapatnam TPP

Tamminapatnam and Momidi Villages,

Chillakur Mandal, SPS Nellore District, Andhra

Pradesh 1980 MW

Blended Coal (70% Indigenous Coal + 30%

Imported Coal)

Expected to come up in Twelfth Plan

Nagarjuna

Construction

Company

NCC Vamsadhara Power Project

Sompeta Mandal, Srikakulam Dist, Andhra Pradesh 2640 MW

Blended Coal- Indian Coal (70%): Imported Coal (30%)

Expected to come up in Twelfth Plan

Under Construction

Promoter Company

Name of the Project

Location Capacity (MW)

Fuel Type

Status

BPL Power Projects

(AP) Pvt. Ltd.

Ramagundam TPS

Ramagundam Town, Karimnagar District,

Andhra Pradesh

2 x 300 Coal Unit-I COD: March 2011 Unit-II COD:May 2011

East Coast Energy

Private Limited

Bhavanapadu Thermal Power Plant Project

Profile

Bhavanapadu Village, Srikakulam

District, Andhra Pradesh, India

2640 MW (Stage I:

2x660 MW Stage II:

2x660 MW)

Coal Synchronization of 1st unit - September 2011 COD of 1st unit - Dec 2011 Synchronization of 2nd unit-Feb 2012

Page 66: Icra internship report

66

Konaseema Gas

Power Ltd

Konaseema CCPP

Konaseema GT1 140 + Gas FC achieved in February 27, 2004. Construction completed.

GT2 140 + ST 165

Gas

Expected COD: GT-1 (140MW): July 2009; GT-2 (140MW): July 2009; ST (165MW): July 2009

Gautami Power Ltd

(Subsidiary of

GVKIPL)

Gautami CCPP Peddapuram GT1 145 Gas FC achieved on 29.03.2004. Construction completed.

GT2 145

Gas

Expected COD: GT-1 (140MW): May 2009; GT-2 (140MW): May 2009; ST (165MW): May 2009

GVK Power Krisnapatnam 'A'

Krisnapatnam A 2 x 260 Coal The Project is ready for testing and commissioning depending on when the natural gas is made available by GAIL.

Hinduja-National

Power

Vizag Power Project

Vizag 2 x 520 Coal Pending issue of coal linkage

Kineta Power

Private Limited

Kineta Power Private Limited

Nellore Distt, Andhra Pradesh

1980 MW Coal Under Proposal

Lanco Kondapalli

Power Pvt Ltd.

Lanco Kondapalli

CCPP Expn. Stage-II

Kondapalli, District Krishna

GT-1: 233 MW + ST: 133 MW

Gas Expected to be commissioned by November 2009

Simhapuri Power

Pvt Ltd.

Simhapuri Thermal Power

Plant

Krishnapatnam South, District Nellore

640 MW (Phase I-270 MW Phase II-370 MW)

Coal Madhucon Projects bagged EPC contract worth Rs 989.5 crore on July 14, 2008.

Vikas Power

Private Limited

Coastal Thermal Power

Project

Pynampuram, Muthukur in Nellore District of Andhra

Pradesh

2x135 MW Coal Unit-1: 24 months from the date of financial closure. Unit-2: 30 months from the date of financial closure.

Krishnaveni Sugars

Limited

Krishnaveni Sugars Limited

Mahaboob Nagar Dist, Andhra Pradesh

28 MW Coal Expected Commissioning July 2009

BBI Power Krishnapatnam 'B' TPP

Krishnapatnam (Distt. Nellore)

2 x 260 Coal Uncertain. In its load forecast till 2006-07, submitted to the AP Electricity Regulation Commission, APTransco did not mention the project.

Page 67: Icra internship report

67

Operational Projects

KVK Energy RVK energy Andhra Pradesh 16 MW Gas Operations Started on 28.01.2000

Lanco Kondapalli

Power

Kondapalli CCPP

Kondapalli 350 Gas Commissioned on 22.06.2000

Spectrum Power

Generation Limited

Godavari CCGT

Subbampeta (Distt. Kakinada)

208 Gas Commissioned on 31.03.98

BSES Andhra Power

Limited

Peddapuram CCGT

Peddapuram 2x110 Naptha/LNG Commissioned on 12.09.02

Vemagiri Power

Generation Ltd

Vemagiri CCPP

Vemagiri 370 Gas Commissioned January 13, 2006.

GVK Industries Jegurupadu CCPP

Jegurupadu Ph-I: 235 ; Ph-II: 220

Gas/Naptha Phase -I: Commissioned in July 1997 Phase-II (Ext Project ): April 2009

2. Karnataka

Proposed Projects

Company Name of the

Project Location Fuel Capacity

(MW) Status Ind-Barath

Power

(Karwar Ltd) 3x150 MW Ind-Barath TPP

Hankon village, Uttara Kannada district, Karnataka Coal 450 MW

Expected to come up in Twelfth Plan

Reliance

Industries

Limited

2x400 MW Gas Based CCPP Proposed by RIL

Village Dhumansur near Humnabad, District Bidar, Karnataka

Natural Gas 800 MW

Expected to come up in Twelfth Plan

NTPC Kudgi STPP, Stage-I

Kudgi village, Bijapur district, Karnataka Coal 2400 MW

Expected to come up in Twelfth Plan

Under Construction

Company Name of the

Project Location Capacity

(MW) Status Udipi Power

Corporation Limited

(Formerly Nagarjuna

Power Corporation)

Udupi TPP Udupi 2x507.5 Expected commissioning Unit 1: May 2010 Unit 2: September 2010

Siruguppa Sugars &

Chemicals Limited

Siruguppa Sugars & Chemicals

Limited

Mahaboob Nagar Dist,

Andhra Pradesh

40 MW Expected commissioning October 2009

JSW Energy

Limited(Vijaynagar)

Torangallu Extension

Project

Bellary 600 MW Under Execution

Page 68: Icra internship report

68

Jindal Power Co. Ltd Toranagallu Expansion

Toranagallu near Bellary

500 The Project was cleared and MoU was signed with the State Govt in 2000. Financial closure awaited and there is dispute over water availability for the project. Other pending issues pertain to allocation of additional land for ash dyke, MoEF clearance and PPA with KPTCL.

Operational Projects

Company Name of the Project

Location Capacity (MW)

Status

Bhoruka Power

Corporation

Chayadevi Plant

Near Narayanpur, Shorapur Taluk

24 MW (2 x 12 MW)

Commissioned on July 2006

KVK Energy &

MVK Energy

Paschim HEP Sakaleshapura, Hassan District

Karnataka

2 x 4.5 MW

Commissioned in 2007

Bhoruka Power

Corporation

Mandagere HEP

Mandya 2 x 1.75 Commissioned in September 2004.

Bhoruka Power

Corporation

Rajankollur HEP

Gulbarga 2 x 1 Commissioned in August 1999.

Bhoruka Power

Corporation

Shahapur HEP Shahapur 6 x 5.5 Commissioned between April 97 to November 98.

Bhoruka Power

Corporation

Madhavamantri HEP

Madhavamantri Anicut at Hemmige

Village

3 x 1 Commissioned in July 2001.

Bhoruka Power

Corporation

Shivpur HEP Shivpur 2 x 9 Commissioned in November 1992.

Bhoruka Power

Corporation

D9 Shahapur HEP

Banathihal village, Shahapur taluk

1 MW Commissioned in August 2003

Bhoruka Power

Corporation

Neria HEP Near Dharmasthala, Belthangady Taluk

9 MW (2 x 4.5 MW)

Commissioned in March 2006

Bhoruka Power

Corporation

Chitradurga Plant

Bettadanagenahalli. 2000 KW Commissioned in March 2005

Bhoruka Power

Corporation

Sri Rama Devara Katte

HEP

Near Kattebelaguli village,

Holenarasipur Taluk

1.5 MW Commissioned in September 2001

GMR Energy GMR Energy Mangalore 220 MW Commissioned in November 2001

Jindal Power

Company

Toranagallu TPS

Bellary 2 x 130 Financial closure achieved on 27.3.99; Commissioned in May , 1999.

Tata Electric

Companies

Belgaum Power Project

Belgaum 81.3 Financial closure achieved ; Commissioned on 31.3.2001.

Tannirbhavi

Power Company

Tanir Bavi Barge Mounted

Power Plant

Tannirbhavi 220 Financial closure achieved in September, 2000 ; Commissioned on November,2000.

Page 69: Icra internship report

69

3. Kerala

Under Construction

Promoter Company Name of the Project

Loc ation Capacity

(MW)

Status

Kerala State Industrial

Development

Corporation (KSIDC) Kasargode Power

Generation Limited Kasargode 2 x 800 Under Proposal

Kannur Power Projects Kannur CCGT Kannur 513

Financial closure yet to be achieved; Under approval. Gas linkage awaited. KPPL are negotiating with Reliance Industries for long term supply of natural gas. 176 acres of land acquired for this project.

Siasin Energy Vypeen CCGT Vypeen 1200 Financial closure yet to be achieved. Kerala State Industrial

Development

Corporation (KSIDC) Kasargode Power Generation Limited Kasargode

2 x 800 Under Proposal

Kannur Power Projects Kannur CCGT Kannur 513

Financial closure yet to be achieved; Under approval. Gas linkage awaited. KPPL are negotiating with Reliance Industries for long term supply of natural gas. 176 acres of land acquired for this project.

4. Tamilnadu

Proposed Projects

Promoter Company Project Name Location

Capacity (MW) Fuel Type Status

Chennai Power

Generation Ltd 1030 MW TPP Tiruvallur District,

Tamil Nadu 1030 MW Imported Coal Expected to come up in Twelfth Plan

North Chennai

Power Company

Limited, a SPV

promoted by ABAN

Group 1200 MW TPP Tiruvallur District,

Tamilnadu 1200 MW Imported Coal Expected to come up in Twelfth Plan

Tridem Port &

Power Company

Limited (TPPCL) 2140 MW TPP Nagapattinam

district, Tamil Nadu 2140 MW

Blended Coal (Indigenous + Imported)

Expected to come up in Twelfth Plan

Patel Engineering

(PEL) Group PEL Thermal Power Project

Tarangambadi, Nagapattinam

district, Tamil Nadu 1000 MW Imported Coal (Indonesia)

Expected to come up in Twelfth Plan

IL&FS Tamil Nadu

Power Co Ltd 4000 MW Cuddalore TPP

Cuddalore district, Tamil Nadu 3600 MW

Imported Coal (Indonesia)

Expected to come up in Twelfth Plan

Costal Energen's

Costal Energen's 1600 MW TPP

Tuticorin District, Tamil Nadu 1600 MW

Blended Coal (Indigenous + Imported)

Expected to come up in Twelfth Plan

Page 70: Icra internship report

70

Under Construction

Promoter Company Project Name Location Capacity (MW)

Fuel Type Status

Unnicornn Powergen

Private Ltd

Unnicorn Mega Power Plant

Tuticorin, Tamil Nadu

2x600 MW Coal Expected Commissioning:2010

Chennai Power

Generation

Kattupalli CCPP

Kattupalli 1000 Liquefied Natural Gas

Financial closure not yet achieved. No updates available.

Tri-Sakthi Energy North Madras TPP–III

North Madras

525 Imported Coal No updates available

Videocon Power North Madras TPP – II

North Madras

2 x 525 Imported Coal Ist unit - 42 months, IInd Unit - 46 months from Financial Closure

Indian Power

Projects

Vember CCGT Vembar near

Tuticorin

1,873 LNG Likely Commissioning: 2009 [uncertain]

Cuddalore Power

Corporation

Cuddalore TPP

Cuddalore 2 x 660 Imported Coal Unlikely to come up

SPIC Electric Power

Corporation

Tuticorin TPP St. IV

Tuticorin 525 Imported Coal 12th plan

Dakshin Bharat

Energy

DBEC Ennore Power Project

Ennore 5 x 370 LNG Unlikely to come up

Operational Projects

Promoter Company Project Name Location Capacity (MW)

Fuel Type

Status

GMR Vasavi Power Basin Bridge DGPP

Basin Bridge near Chennai

4 x 50 LSHS Commissioned on: December 31, 1998

Samalpatti Power Company Samalpatti DGPP Pochkanapalli; Distt. Dharampuri

105.66 LSHS Commissioned in: March 2001

PPN Power Generating

Company

Pillaiperumalnallur CCGT

Pillaiperumalnallur; Distt. Thanjavur

330.5 Gas/ Naphtha

Commissioned on: April 5, 2001

Balaji Power Corporation Samayanallur DGPP

Samayanallur, District Madurai

106 LSHS, FO, LSWR

Commissioning: September 22, 2001.

ST-CMS Electric Company Neyveli TPS - Zero Unit

Neyveli 250 Lignite Commissioned on: October 11, 2002

Aban Power Co. Ltd. Karuppur CCPP Karuppur Village Near Kuttalam,

Thanjavur District.

120 Natural Gas

Commissioned on : August 11, 2005

Arkay Energy Valantharavai GTPP

Valantharavai Unit I: 52.8

Unit II: 67.11

Liquid Fuel (Petroleum)

Commissioned on: Unit I - October 29, 2005.

Regency Power

Corporation

Ramanathapuram CCGT

Ramanathapuram 60 Natural Gas

Commissioning : 2005-06

Arkay Energy Valantharavai GTPP

Valantharavai Unit I: 52.8

Liquid Fuel

Commissioned t I - October 29, 2005.

Page 71: Icra internship report

71

5. Delhi

Proposed Project

Promoter Company

Name of the

Project

Location Capacity (MW)

Fuel Type

Status

NDPL Rithala CCPP

Rohini, District North-West in

Delhi

108 MW Natural Gas

MoEF clearance awaited

Apollo Energy New Delhi TPS

Narela 2 x 175 Coal DPR returned by CEA on 27.2.01 due to pending inputs.

KLT Power Bawana - II

Bawana - II 650 Gas On 30 January 2001, Delhi government decided to shelve the project indefinitely.

Reliance

Power

Bawana - I

Bawana - I 421 Gas Scheme returned on 19.12.97 due to pending inputs and clearances; On 30 January 2001, Delhi government decided to shelve the project indefinitely.

6. Haryana

Promoter Company Name of the Project

Location Capacity (MW)

Fuel Type

Status

Magnum Power

Generation Limited

Gurgaon CCGT Gurgaon 4 x 6.3 LSHS/HFO

Commissioned in 1998.

Phoenix Power

Development

Corporation

Phoenix Power Project

Gurgaon, Panchkula,

Ambala, Panipat

3 x 50 + 1 x 25 HFO The project has most likely been shelved.

Indian Oil Corporation Panipat Power Project

Panipat 300 Refinery Residue

The project has most likely been shelved.

Yamuna Nagar TPP Yamuna Nagar Power Project

Yamuna Nagar 500 Coal Project declared dead.

India Power Partners Bahadurgarh Power Project

Bahadurgarh 2 x 25 -- The project has most likely been shelved.

7. Himachal Pradesh

Proposed Projects

Promoter Company Name of the Project

Location Capacity (MW)

Status

Lanco Green Power Pvt Ltd Budhil HEP Chamba 2 x 35 Expected Commissioning June 2011-12

Himachal Sorang Power

Corporation Pvt Ltd

Sorang HEP Kinnaur 2 x 50 Expected Commissioning June 2010

Jaypee Karcham Hydro Corp.

Ltd

Karcham Wangtoo HEP

Kinnaur 4 x 250 Financial closure achieved on March 2006; Sch commissioning: March 2012.

Page 72: Icra internship report

72

LNJ Bhilwara Group Allain Duhangan HEP

Manali 2 x 96 Financial closure in April 2005. Infrastructure activities in progress.

Everest Power Company Malana II HEP Malana 2 x 50 Expected Commissioning: Unit I : December 2009, Unit II : January 2010

Malana Power Company

(RFQ)

Bara-Bangahal HEP

Bara-Bangahal

200 MW Under RFQ Stage

Operational Projects

Promoter Company

Name of the Project

Location Capacity (MW)

Status

Jaiprakash Hydro

Power

Baspa HEP Kinnaur 3 X 100 Financial closure achieved on January 21, 1998 ; Commissioned on May 27, 2003.

Malana Hydro

Project

Malana HEP

Malana 2 x 43 Financial closure achieved in July, 2000; Commissioned in October, 2001.

8. Bihar

Promoter Company

Name of the Project Location Capacity

Fuel Type Status

Tata Power

Company

Limited Jojobera

TPS Jamshedpur 360 Coal

Stage I (240 MW) : Financial closure achieved on December 7,1998 ; Commissioned on August 27, 2001. Stage II : Commissioned on Sept 23, 2005

9. Jharkhand

Proposed Projects

Name of the Project Location Capaci ty Fuel Type Status 2000 MW TPP

Proposed by EPJL Chandwa Tehsil, Latehar District, Jharkhand State 2000 MW Coal

Expected to come up in Twelfth Plan

HDIL Chakulia TPP Near Chakulia, district Purbi Singhbhum, Jharkhand 1320 MW Coal

Expected to come up in Twelfth Plan

Under Construction

Name of the Project Location Capacity Fuel Type Status

Ramgarh TPS-I Ramgarh in Hazaribagh

100 MW Thermal Power Plant Coal

Expected Commissioning: September 2009

KVK Nilanchal Power

Private Limited Near Torpa, District Khunti, Jharkhand 2 x 600 MW Coal

Expected Commissioning: Unit I : December 2011, Unit II : March 2012

SKS Ispat & Power Ltd.

Ramgarh District in the state of Jharkhand 1200 MW Coal

Expected Commissioning: Unit I: September 2011, Last unit by

March 2012

Page 73: Icra internship report

73

Operational Projects

Name of the Project Location Capacity Fuel Type Status

Jojobera TPP Singhbhum Unit I - 67.5 MW, Unit II: 120 MW, Unit III: 120 MW, Unit IV: 120 MW Coal

All Units Commissioned

10. Madhya Pradesh

Proposed Projects

Promoter Company Name of the Project Location

Capacity (MW)

Fuel Type Status

Aryan Coal

Beneficiations Pvt

Ltd

1200 MW TPP proposed by Aryan Coal Beneficiations Pvt Ltd

Bhumka-Musamudi village, Majhauli Tehsil, Sidhi district, Madhya Pradesh 1200 MW Coal

Expected to come up in Twelfth Plan

Bhaskar Group

1320 MW TPP Proposed By DB Power Ltd

District Sinarauli, Madhya Pradesh 1320 MW Coal

Expected to come up in Twelfth Plan

Moser Baer Power

& Infrastructure Ltd Anuppur Thermal Power Project

Anuppur district, Madhya Pradesh 2000 MW Coal

Expected to come up in Twelfth Plan

Jaiprakash Power

Ventures Limited, a

subsidiary of

Jaiprakash

Associates Limited Jaypee Nigri STPP

Nigri village, Tehsil Singrauli, Sidhi district, 1320 MW Coal

Expected to come up in Twelfth Plan

Under Construction

Promoter Company Name of the Project Location

Capacity (MW)

Fuel Type Status

Bina Power Supply

Company Bina TPS Bina 2x500 MW (Planned) Coal

Escrow cover granted; Financial closure not yet achieved.

Moser Baer Power &

Infrastructures Limited Annupur TPP

Anuppur district, Madhya

Pradesh 2000 MW Coal

Expected COD: Phase-I: March 2012, Phase-II: March 2013

Shree Maheshwar Hydel

Power Corporation Maheshwar

HEP Mandaleshwar 10 x 40 Hydel Expected Commissioning: 2011-12

Pench Power Pench TPS Pench

(Chindwara) 2 X 250 Coal Expected Commissioning: 2012-13

SJK Powergen SJK Powergen

Limited Shadol 2 x 500 Coal Expected Commissioning: December 2010

Today Homes and

Infrastructure Pvt. Ltd.

(THIPL)

Today Homes and

Infrastructure Pvt. Ltd. (THIPL)

Narsimhapur, Madhya Pradesh

2 x 600 MW Coal

Expected Commissioning: 2012-13

Page 74: Icra internship report

74

11. Chhattisgarh

Proposed Projects

Promoter Company Name of the Project Location Capacity

(MW) Fuel Type Status

Bhilai Engineering

Corporation Limited 2x250 MW BEC Power Project

Champa District, Chhattisgarh 500 MW Coal

Expected to come up in Twelfth Plan

Jain Energy Limited 4x300 MW TPP Korba District, Chhattisgarh 1200 MW Coal

Expected to come up in Twelfth Plan

Jindal Power Limited

(JPL) 4x600 MW TPP Raigarh district, Chhattisgarh 2400 MW Coal

Expected to come up in Twelfth Plan

Akaltara Power Limited -

a subsidiary of PFC 5 x 800 MW Chhattisgarh UMPP

Surguja district, Chhattisgarh 4000 MW Coal

Expected to come up in Twelfth Plan

Essar Power Chhattisgarh

Limited 2 x 600 MW Mahanadi TPP

Champa District, Chhattisgarh 1200 MW Coal

Expected to come up in Twelfth Plan

JSPL (Jindal Steel &

Power Limited)

2x150 MW Meddling and Coal Fine based TPP, Phase-II

Raigarh district, Chhattisgarh 300 MW

Washery middling & coal

fine Expected to come up in Twelfth Plan

RKM Powergen Private

Limited (PPL) 4x360 MW Uchpinda Power Project

Champa, Chhattisgarh 1440 MW Coal

Expected to come up in Twelfth Plan

Vandana Vidhyut Limited Vandana Vidhyut TPP

District- Korba, Chhattisgarh 540 MW Coal

Expected to come up in Twelfth Plan

Under Construction

Promoter Company

Name of the Project

Location Capacity (MW)

Fuel Type

Status

Wardha Power

Company Pvt.

Limited

Wardha Power Company Pvt. Limited

Wardha, Chhattisgarh

2 x 1800 Coal Expected to be commissioned by April 2012

Chhattisgarh Steel &

Power Limited

Chhattisgarh Steel & Power

Limited

Amjhar, Champa-Janjgir, Chhattisgarh 112.5 Coal Under Development

Jindal Power

Limited

4x660 MW Additional Power

Plant

Tamnar, Raigarh (Chhattisgarh)

4x660 (IPP) Coal Under Development

Jain Energy Limited 4x300 MW Jain Energy Limited

Korba, Chhattisgarh 4x300 Coal Under Process

Athena Projects

Private Ltd

Athena Chhattisgarh Power Private Ltd

Raigarh District, Chhattisgarh

1200 (2x600M

W) Coal Under Development Bhilai Power Supply

Company Bhilai TPP Bhillai (Durg) 2 x 287 Coal Financial closure not yet achieved.

Dheeru Power

Private Limited DPPL Korba 500 Coal Expected Commissioning: 2009-10

GMR Energy Limited Proposed by GMR Raipur 1200 Coal

Expected Commissioning: Twelfth Plan

Page 75: Icra internship report

75

Iffco Chhattisgarh

Power Limited ICPL Sarguja 1000 Coal Exp Commissioning: 2009-10

Lanco Amarkantak

Power

Lanco Amarkantak Mega TPS (Pathadi) - Phase I

Pithadi village, district Korba 2x300 Coal

Expected Commissioning: Unit- I: May 2009 Unit- II: Dec 2009

Lanco Amarkantak

Power

Lanco Amarkantak Mega TPS (Pathadi) Unit 3 & 4

Pithadi village, district Korba 2x600 Coal

Expected Commissioning: March 2012 (Unit IV)

KVK Power &

Infrastructure

KVK Power & Infrastructure Pvt. Ltd. Akaltara

2 x 600 MW Coal

Expected Commissioning: March 2012

KVK Energy S V Power Pvt. Ltd. Korba

2 x 63 MW Coal COD ( 1st Phase) : 2009

Patni Project Private

Limited Gorra Thermal Power Project Fatehpur

4x135 MW Coal

COD of Unit 1 & 2 is January 2011

RKM Power Project RKM Power Project -

4x350 MW Coal

Financial Closure achieved in April, 2007

Vandana Vidhyut

Limited Vandana Vidhyut Limited Korba 540 MW Coal

COD: Unit I- June : 2010, Unit II- June : 2011, Unit III-IV December : 2012

Korba West Power

Company Ltd.

Korba West Power Company Ltd. Korba 2 x 300 Coal Expected COD: 2011

Visa Power Visa Chhattisgarh Power Project

Raipur, Chhattisgarh 1200 MW Coal Under Proposal

RPG Group Korba (West) TPP (T) Korba West 2 X 260 Coal

Scheme returned on 21.5.97due to pending inputs/clearances.

Operational Projects

Promoter Company

Name of the Project

Locat ion Capacity (MW)

Fuel Type

Status

OP Jindal Thermal

Power Station Raigarh

TPP Raigarh 4 x 250

MW Coal Commissioned Unit I- May 2007; Complete project: 2007- 2008

KVK Energy -- Akaltara 15 MW Biomass Operations Started On December 2005

12. Gujarat

Proposed Projects

Promoter Company Name of Project Location Capacity (MW)

Fuel type

Status

Shapoornji Pallonji

Energy (Gujarat) Pvt Ltd

2x660 MW (Phase-I) Coal Based Super Critical TPP

Junagadh, Gujarat

2x660 MW Imported Coal

Expected to come up in Twelfth Plan

ESSAR Group Limited, Proposed by Vadinar Power Company Limited

Jamnagar, Gujarat

500 / 483 MW

Imported Coal

Expected to come up in Twelfth Plan

Page 76: Icra internship report

76

Under Construction

Promoter Company

Name of Project

Location Capacity (MW)

Fuel type Status

Torrent Power

Generation

Limited

Sugen CCPP Akhakhol, District Surat

1147.5 Gas Expected Commissioning: Block I: March 2009 Block II: March 2009 Block III: April 2009

Adani Power Mundra TPP Phase I (Unit 1&2)

Kutch 2x330 Coal Expected Commissioning Unit-1: August 2009 Unit-2: September 2009

Adani Power Mundra TPP Phase I (Unit 3 & 4)

Kutch 2x660 Coal Expected Commissioning Unit 3: February 2010 Unit 4: May 2010

Adani Power Mundra TPP Phase II

Kutch 2x660 Coal Expected Commissioning Unit 1: April 2011 Unit 2: September 2011

Adani Power Mundra TPP Phase III

Kutch 3x660 Coal Expected Commissioning Unit 1: July 2011 Unit 2: November 2011 Unit 3: March 2012

Essar Power Hazira CCGT Hazira 515 + 1500

Naphtha [Phase I] : Financial closure achieved; Commissioned on May 26, 1997 Scheduled Commissioning [Phase II] : Stage I (750 MW) : 27 months from financial closure ; Stage II (750 MW) 36 months from financial closure.

Nirma Chemical

Works Ltd.

Ghogha TPP Ghogha 250 Lignite Foundation stone to be laid after general elections (April-May 2004). No progress reported since 2004.

Essar Energy Vadinar GBPP Vadinar 1200 Refinery Residue

Financial closure yet to be achieved.

Indian Oil

Corporation

Savli Power Project

Savli 500 Refinery Residue

No Progress Reported.

KRIBHCO Pipavav TPP Pipavav 615 Gas Financial closure yet to be achieved.

Reliance Power Jamnagar Petcoke TPP

Jamnagar 2 x 250 Petroleum Coke

The power project has been shelved.

Patni Projects

Private Limited

Bharuch TPP Bharuch 230 Gas Expected Commissioning: October 2008

Pipavav Power

Development

Company

Pipavav Power Project

Pipavav, Gujarat

1000 Coal Expected Commissioning: March 2012

Visa Power Visa Pipav Power Project

Pipav, Gujrat 1000 MW Coal Under Proposal

Operational Projects

Promoter Company Name of Project

Loc ation Capacity (MW)

Fuel type

Status

Gujarat State Energy

Generation Limited

Hazira CCPP Mora near Hazira

156 Gas Commissioned in June 2002

Gujarat Industries Power Com. Baroda CCGT and Surat TPP

Baroda and Surat

160 + 2 x 125

Gas Commissioned on November 18, 1997 and January 16, 2000

Page 77: Icra internship report

77

Gujarat Paguthan Energy

Corporation

Paguthan Power Project

Bharuch 654.726 Naphtha

Commissioned on October 13, 1998

13. Maharashtra

Proposed Projects

Promoter Company Name of

the Project Location Capacity (MW) Fuel Type Status

Finolex Infrastructure

Limited, SPV of

Finolex 1000 / 1050

MW TPP

Ranpur, Pawas Bay, Ratnagiri district, Maharashtra

1x1050 MW (Super Critical) OR 2x500 MW (Sub Critical) Coal

Expected to come up in Twelfth Plan

Dhopave Coastal

Power Company

Limited (DCPCL) 1600 MW

TPP

Near Dhopave, Ratnagiri district, Maharashtra 1600 MW Imported Coal

Expected to come up in Twelfth Plan

Maharashtra Airport

Development

Company Ltd &

Abhijeet Group Mihan

Power Plant

Khairi Khurd village, Nagpur district, Maharashtra 123 MW Coal

Expected to come up in Twelfth Plan

Jinbhuvish Power

Generations (P) Ltd 2x270 MW

TPP

Dhanmukh (Bijora) village, Mahagaon Tahsil, Yavatmal District, Maharashtra 540 MW Coal

Expected to come up in Twelfth Plan

Tata Power 1600 MW

TPP

Dehrand/Shahapur, Raigad District, Maharashtra 1600 MW Imported Coal

Expected to come up in Twelfth Plan

Vidarbha Industries

Power Ltd, SPV of

Reliance Power

Limited

300 MW Captive TPP

(Phase-II)

Butibori MIDC, district Nagpur, Maharashtra

300 MW (Phase-II) Coal

Expected to come up in Twelfth Plan

Ind-Barath Power

(Konkan) Limited

Ind-Barath Group

Captive TPP

Dhakur / Ajgaon, Sawanthwadi Tehsil, Sindhudurg district, Maharashtra 1050 MW

Import/Domestic Coal

Expected to come up in Twelfth Plan

Patni Energy Pvt Ltd

(PEPL) Patni Power

Project

Medhekhar village, Taluka Alibag, Raigad district, Maharashtra 405 MW Imported Coal

Expected to come up in Twelfth Plan

Indiabulls Realtech

Limited 5x270 MW

TPP Sinnar SEZ, district Nasik, Maharashtra 1350 MW Coal -

1320 MW Astrac

Power's Supercritical

TPP

2x660 MW Super

critical TPP District - Nagpur, Maharashtra. 1320 MW Coal -

Page 78: Icra internship report

78

Under Construction

Promoter Company

Name of the Project

Location Capacity (MW)

Fuel Type

Status

Amravati

Thermal Power

Pvt. Ltd.

Amravati Thermal Power Project

Amravati 2x660MW Coal Financial closure is yet to be Achieved, Likely to be commissioned in XI Plan,

Adani Power Tirora Phase I Tirora, District Gondia

2x660 MW Coal Expected commissioning August 2011

Adani Power Tirora Phase II Tirora, District Gondia

1x660 MW Coal Financial closure not yet achieved. Applied for LT coal linkage for 1200-1250 MW capacity

JSW Energy JSW Energy Ratnagiri TPS

Ratnagiri,Mumbai

4 x 300 MW

Imported Coal

Expected Commissioning: Unit - 1 April 2010 Unit - 2 June 2010 Unit - 3 August 2010 Unit - 4 October 2010

Shalivahana

Constructions

(India) Private

Limited

Shalivahana Constructions (India) Private

Limited

Chandrapur 1 x 270MW Coal Expected Commissioning: 2013

Ideal Projects Private Limited

Ideal Projects Private Limited

Nagpur 2x135MW Coal Expected to commissioning: Phase-I: October 2010 Phase-II: March 2011

Dhariwal

Infrastructure

(P) Limited

Dhariwal Infrastructure Chandrapur

TPP

Chandrapur 2 x 300 MW

Coal Expected Commissioning: Unit-I - June 2011 Unit-2 - March 2012

Operational Projects

Promoter Company

Name of the Project

Location Capacity (MW) Fuel Type Status

Tata Power

Company

Trombay TPS Extension [Unit 8]

Trombay, Mumbai

Unit 8: 250 MW [The site already has a

Total Installed Capacity of 1480

MW]

Imported Coal

Syncronisation: January 14, 2009 CoD: March 29, 2009

Ratnagiri Gas

and Power

Private Limited

(Formerly,

Dabhol Power

Company)

Ratnagiri CCPP Ratnagiri 1480 RLNG / Naphtha

Block II CoD: 1 September, 2007 Block III CoD: 21 November, 2007

Page 79: Icra internship report

79

14. Rajasthan

Proposed Projects

Promoter Company

Name of the Project

Location Capacity (MW) Fuel Type Status

Adani Power

Rajasthan Limited 1320 MW

Project Kawai, district

Baran, Rajasthan 1320 MW Coal Expected to come up in Twelfth Plan

Under Construction

Promoter Company

Name of the Proje ct Location Capacity (MW)

Fuel Type

Status

Neyveli Lignite

Corporation Barsingsar Lignite TPP Barsingar (Bikaner) 2 X 125 Lignite

Expected Commissioning: January 2010

Raj West Power Jallipa Kapurdi TPP Barmer 8 x 135 =

1080 Lignite Expected commissioning October 2010

Raj West Power Jallipa Kapurdi TPP Barmer 2 x 135 = 270 Lignite Expected commissioning January 2013

RPG Dholpur Power Company Dholpur CCGT Dholpur 702.7 Gas

Projects development stands closed.

LNJ Bhilwara Group

Coal based Thermal Power Plant

Mordi, District Banswara 23 MW Coal Status Unavailable

Bhagat Power Kershorai Patan Power

Project Kershorai

Patan 100 Status Unavailable Bhiwadi Generation Company Alwar Power Project Alwar 100 Status Unavailable

British Power Industries

Chittorgarh Power Project

Chittorgarh, Bhilwara, Udaipur,

Rajsamand, Banswara 5 x 100 Status Unavailable

Chambal Power Kershorai Patan Power

Project Kershorai

Patan 166 Status Unavailable DLF Power Barmer Power Project Barmer 2 x 125 Status Unavailable

Euro Power Consortium India

Chittorgarh Power Project

Chittorgarh, Hanumangarh,

Bhilwara 5 x 100 Status Unavailable Indo Cal Power Ventures Jodhpur Power Project Jodhpur 100 Status Unavailable Jalipa TPP Jalipa Power Project Jalipa 900 Status Unavailable Jodhpur Electric Power Jodhpur Power Project

Jodhpur, Banswara 2 x 75 Status Unavailable

Kapurdi TPP Kapurdi Power Project Kapurdi 600 Status Unavailable Peeraj Power Generation

Sriganganagar Power Project Sriganganagar 150 Status Unavailable

Poysha Power Projects Alwar Power Project Alwar 50 Status Unavailable Vardhan Infrastructure Ltd Abu Power Project Abu 100 Status Unavailable

Page 80: Icra internship report

80

15. Orissa

Proposed Projects

Promoter Company Name of the

Project Location Capacity

(MW) Fuel Type Status

Visaka Thermal

Power Pvt Ltd 3 x 350 MW TPP

Near Ampor village, Banta Tehsil, Bhadrak District, Orissa 1050 MW Coal

Expected to come up in Twelfth Plan

FACOR Power Ltd 1x45 MW TPP Randia, district Bhadrak, Orissa 45 MW Coal

Expected to come up in Twelfth Plan

Bhushan Energy Ltd 2000 MW TPP Ghantigadia / Nuahata village, Angul district, Orissa 2000 MW Coal

Expected to come up in Twelfth Plan

Under Construction

Promoter Company Name of the

Project Location Capacity

(MW) Fuel Type Status

Bhushan Energy Ltd Bhushan Angul TPP

Ghantigadia district Angul

2000 Coal Financial closure not yet achieved

CESC Ltd CESC Dhenkanal TPP

Neulapoi , Dhenkanal

1000 Coal Financial closure not yet achieved.

Essar Power Ltd Essar Talcher TPP Talcher, Angul 1000 Coal Financial closure not yet achieved.

GMR Orissa GMR Orissa TPP Dhenkal District in Orissa

1050 Coal Expected Commissioning in February 2012

Kalinga Power

Corporation

Dubri TPP Duburi 2 x 250 Coal Financial closure not yet achieved.

KVK Nilachal Power

Private Ltd

KVK Nilanchal TPP Kandarei, Cuttack 4x350 MW Coal Expected Commissioning: December 2011

Jindal India Thermal

Power Limited

Jindal Angul TPP District Angul, Orissa

2 x 600 MW

Coal Unit-I: Sept. 2011 Unit-II: March 2012

Lanco Babandh

Power Private Ltd

Babandh TPP Babandh, District Dhenkanal, Orissa

Phase I : 2 x 660 MW

Phase II : 2 x 660 MW

Coal Unit-I COD in Quarter Fourth of 2011, within 11th Plan (Anicipated)

Lanco Group Lanco Dhenkal TPP

Kurunti & Kharagprasad

village, Dhenkanal district, Orrisa

2x660 Coal Mar-12

Navabharat Power

Private Limited

Malaxmi Mega Thermal Power

Project - Phase I

Nua-Hata in Angul district

Phase I :1040

Phase II : 1200

Coal Yet to achieve financial closure

Mahanadhi Aban

Power Company Ltd

Mahanadhi Aban Power Project

Talcher village of Angul District in

Orissa

1030 Coal Yet to achieve financial closure

Monnet Power Co.

Ltd

Monnet Angul TPP Malibrahmani, District Angul,

Orissa

3x335 MW Coal Expected commissioning by September 2011

Page 81: Icra internship report

81

Reliance Energy

Limited

Hirma Power Project

Hirma 6 x 660 Coal Financial closure not yet achieved.

Sterlite Energy

Private Limited

Sterlite TPP Jharsuguda 2400 Coal Financial Closure Achieved in July 2006. Commissioning expected within XI plan

Tata power

Company Ltd

Naraj TPP Naraj Marthapur, Cuttack

2000 MW Coal Financial closure yet to be achieved.

Visa Power Visa Power Cuttack TPP

Cuttack, Orissa 1000 MW Coal Financial closure yet to be achieved.

16. Uttar Pradesh

Under Construction

Promoter Company Name of the Project

Location Capacity (MW)

Fuel Type

Status

Reliance Energy Ltd Rosa TPP Phase I Shahjahanpur 600 Coal Expected Commissioning: June 2010

Reliance Energy Ltd Rosa TPP Phase II Shahjahanpur 600 Coal Expected Commissioning: July 2011

Reliance Energy Ltd Dadri CCPP Dadri 7480 Gas Expected Commissioning: 2011-12

Lanco Anpara Power

Pvt Ltd

Anpara ‘C’ TPP Anpara 2 x 600 Coal Expected Commissioning: Unit-I: June, 2011 Unit-II: August, 2011

Jawaharpur Power Etah TPP Etah 2 x 400 Coal Scheme returned on August 31, 2001. No progress reported.

Modi Mirrless

Blackstone

Ghaziabad Power Project

Ghaziabad 100 Naphtha No Progress Reported.

Indian Power

Partners

Chandausi Power Project

Chandausi 100 Naphtha No Progress reported.

Wasan Power Kosi Kalan Power Project

Kosi Kalan 355 Naphtha No Progress Reported

Indian Oil Corporation Kosi Kalan Power Project

Kosi Kalan, Mathura

110 -- Project has been scrapped.

17. Uttaranchal

Under Construction

Name of the Project

Promoter Location Capacity (MW)

Fuel Type

Status

Alaknanda

Project

GMR Chamoli district of Uttaranchal

140 MW Hydel Exp commissioning: 2011-12

Jaiprakash

Vishnuprayag TPP

Jaiprakash Vishnuprayag 4 x 100 MW

Hydel CoD Ut I: Apr’06 Ut II: Jun’06 Ut III: Aug’06 Ut IV: Oct’06

Page 82: Icra internship report

82

Shrinagar

Hydroelectric

Project

GVK Uttrakhand 330 MW Hydel Expected Commissioning Schedule: Unit I: July 2011 Unit II: August 2011 Unit III: September 2011 Unit IV: October 2011

Duncan's

Alakhnanda HEP

Duncans North Hydro Power Company

Paun Garhwal 5 x 66 Hydel Financial closure not yet achieved;

18. West Bengal

Under Construction

Promoter Company Name of the Project

Location Capacity (MW)

Fuel Type

Status

CESC Ltd Budge Budge TPS Stage III

South Parganas

250 Coal Expected to be commissioned by Sept ‘09

Balagarh Power Company

Ltd

Balagarh TPS Balagarh (Hoogly)

500 Coal Financial closure yet to be achieved.

Indian Oil Corporation Haldia Power Project

Haldia 700 Refinery Residue

Most likely Shelved

Gouripore Power Company Gouripore TPP Gouripore 150 Coal Shelved.

19. Arunachal Pradesh

Under Construction

Name of the Project

Location Capacity (MW)

Fuel Type

Status

Demwe Lower Lohit District 1630 MW Hydel Invited EOI for executing project

Talong Seppa district on River Kemeng 160 MW Hydel Expected commissioning: 2011

20. Assam

Project Prom oter Location Fuel Type Status Adamtilla Gas Based Power Plant

DLF Power Cachar Naptha Commissioned

Banskandi Gas Based Power Plant Cachar Naptha Commissioned

21. Punjab

Promoter Company

Name of the Project Location Capacity (MW)

Fuel Type

Status

GVK Power and

Infrastructure Ltd

Goindwal Sahib Thermal Power Project

Gowindwal Sahib, Taran Taran district

2 x 270 Coal Financial closure not yet achieved;

Page 83: Icra internship report

83

22. Goa

Under Construction

Promoter Company

Name of the Project

Location Capacity (MW)

Fuel Type

Status

Reliance

Energy Goa Power Station Sancoale,

Zuarinagar, Goa 52 Gas / Naptha

Expected to come up in Twelfth Plan

Reliance Reliance Energy's Goa Power Station

Zuarinagar 48 Naptha Financial closure achieved; Commissioned on 06.07.1999.

Goa Energy

Pvt. Ltd.

WHR Power Plant Amona, Navelim 30 Gas Orders for all the BOPs have been placed except Aux. Cooling Water Heat Exchanger, Compres sed Air System, & DG Set