ian bird lcg project leader project status report wlcg lhcc referees’ meeting 21 st september 2009

30
Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

Upload: theodore-lloyd

Post on 19-Jan-2016

219 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

Ian BirdLCG Project Leader

Project status report

WLCG LHCC Referees’ meeting21st September 2009

Page 2: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

[email protected] 2

Agenda

Overall status Planning and milestones Follow up actions from STEP’09 Status of Tier 0 Status of Tier 1 sites (seen via milestones etc) Resource requests and installation status

Comments on CRSG report & process

Status of preparations for EGEE EGI transition

Experiment reports NB LHCb external meeting, thus no LHCb representative today

Page 3: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

[email protected] 3

Overall summary

Since July has been fairly quiet Experiments did follow-up tests with some sites where problems had

been seen during STEP’09 exercise In general workloads have been continuous

WLCG service has been running according to the defined procedures Reporting and follow up of problems at

same level

Focus on stability and resolution of problems in preparation for data taking

Page 4: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

[email protected] 4

ATLAS CMS

LHCbALICE

Page 5: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

[email protected] 5

Incident reports ... fewer

Page 6: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

[email protected] 6

2009 2010 2011

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb

SU pp running HI

2009 2010 2011

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb

SU PP running HI?

STEP’09May+June

WLCG timeline 2009-2010

2009 Capacity commissioned

2010 Capacity commissioned

Switch to SL5/64bit completed?

Deployment of glexec/SCAS; CREAM; SRM upgrades; SL5 WN

EGEE-III ends EGI ... ??? ??EGI

HEP – SSC

EMI

(SA4)

Resource review

Page 7: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

[email protected] 7

Milestones - 1

01-Sep-09 WLCG High Level Milestones

      Done (green)  Late < 1 month

(orange)  Late > 1 month (red)  

ID Date Milestone ASGCCC

IN2P3CERN

DE-KIT

INFN CNAF

NDGF PIC RALSARA NIKHE

F

TRIUMF BNL FNAL

                               

Pilot Jobs Frameworks

WLCG-08-14 May 2008

Pilot Jobs Frameworks studied and accepted by the Review working groupWorking group proposal complete and accepted by the Experiments.

ALICE ATLAS CMSLHCb

Nov 2007

Tier-2 and VOs Sites Reliability ReportsWLCG-08-09 Jun

2008Weighted Average Reliability of the Tier-2 Federation above 95% for 80% of Sites Weighted according to the sites CPU resources

See separated table of Tier-2 Federations 80% of the Sites above 95% reliability

WLCG-08-11 Apr2009

VO-Specific Tier-1 Sites Reliability Considering each Tier-0 and Tier-1 site

(and by VO?)

Jul 2009                        

Aug 2009                        

Sep 2009                        

Tier2 reliabilities: published monthly40% > 95% reliability; 80% > 90% reliability (federation weighted)

Tier 1: VO-specific reliabilities now published regularly

Page 8: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

[email protected] 8

Milestones - 2

01-Sep-09 WLCG High Level Milestones

      Done (green)  Late < 1 month

(orange)  Late > 1 month (red)  

ID Date Milestone ASGCCC

IN2P3CERN

DE-KIT

INFN CNAF

NDGF PIC RALSARA NIKHE

F

TRIUMF BNL FNAL

SL5 Milestones

WLCG-09-21 Mar 2009

SL5 gcc 4.3 (WN 4.1 binaries)Tested by the ExperimentsExperiments should test whether the MW on SL5 support their grid applications

ALICE ATLAS CMS LHCb

WLCG-09-22 Jul 2009

SL5 Deployed by the Sites (64 bits nodes)Assuming the tests by the Experiments were successful. Otherwise a real gcc 4.3 porting of the WN software is needed.

                       

Tier-1 Sites Procurement - 2009

SLC5: MB issued statement urging sites to migrate asap; clarifying no show stoppers for the experiments

Ideally would like significant resources under SL5 available before data taking.

Many large sites have migrated

Page 9: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

[email protected] 9

Milestones - 3

01-Sep-09 WLCG High Level Milestones

      Done (green)  Late < 1 month

(orange)  Late > 1 month (red)  

ID Date Milestone ASGCCC

IN2P3CERN

DE-KIT

INFN CNAF

NDGF PIC RALSARA NIKHE

F

TRIUMF BNL FNAL

SCAS/glExec Milestones

WLCG-09-17 Jan 2009

SCAS Solutions Available for DeploymentCertification successful and SCAS packaged for deployment

Done in March 2009

WLCG-09-18 Apr 2009

SCAS Verified by the ExperimentsExperiment verify that the SCAS implementation is working (available at CNAF and NL-T1)

ALICEn/a

ATLASCMSn/a ?

LHCb

WLCG-09-19 09-18 + 1

Month

SCAS + glExec Deployed and Configured at the Tier-1 SitesSCAS and glExec ready for the Experiments.                        

WLCG-09-20 09-18 + 3

Month

SCAS + glExec Deployed and Configured at the Tier-2 SitesSCAS and glExec ready for the Experiments.  

Glexec/SCAS available for deployment; deployed at several test sites; general deployment is very slow

Page 10: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

[email protected] 10

Milestones – 4

Accounting Milestones

WLCG-09-02 Apr 2009

Wall-Clock Time Included in the Tier-2 Accounting Reports The APEL Report should include CPU and wall-clock accounting

APEL

WLCG-09-03 Jul 2009

Tier-2 Sites Report Installed Capacity in the Info System Both CPU and Disk Capacity is reported in the agreed GLUE 1.3 format.

% of T2 Sites Reporting

WLCG-09-04a Jul 2009

Sites publishing the User Level Accounting information                        

WLCG-09-04b Jul 2009

User Level Accounting verified and approved by the Experiments ALICE ATLAS CMS LHCb

~100

Almost all sites report CPU information

Comparison of published data and expected values tbd

Follow up on published storage information to be done

User-level accounting available in APEL; policy now approved; sites asked to enable the publishing of the data

Page 11: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

[email protected] 11

Milestones – 5

01-Sep-09 WLCG High Level Milestones

      Done (green)  Late < 1 month

(orange)  Late > 1 month (red)  

ID Date Milestone ASGCCC

IN2P3CERN

DE-KIT

INFN CNAF

NDGF PIC RALSARA NIKHE

F

TRIUMF BNL FNAL

STEP 2009 - Tier-1 Validation

WLCG-09-23 Jun 2009

Tier-1 Validation by the Experiments ALICE n/a           n/a     n/a n/a n/a

ATLAS           n/a n/a         n/a

CMS           n/a     n/a n/a n/a  

LHCb n/a         n/a       n/a n/a n/a

All Tier 1’s tested by STEP’09

Were 3 with concern: ASGC, NL-T1, FZK

FZK and NL-T1 have since demonstrated satisfactory functionality

ASGC still of concern: meeting with ASGC management in early Oct

Page 12: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

[email protected] 12

Milestones – 6

01-Sep-09 WLCG High Level Milestones

      Done (green)  Late < 1 month

(orange)  Late > 1 month (red)  

ID Date Milestone ASGCCC

IN2P3CERN

DE-KIT

INFN CNAF

NDGF PIC RALSARA NIKHE

F

TRIUMF BNL FNAL

CREAM CE Rollout

WLCG-09-25 Apr 2009

Release of CREAM CE for deployment 

WLCG-09-26 May 2009

All European T1 + TRIUMF and CERN at least 1 CE. 5 T2s supporting 1 CE n/a         n/a       n/a n/a n/a

WLCG-09-27 Jul 2009

2 T2s for each experiment provide 1 CREAM-CE each. ALICE ATLAS CMS LHCb

WLCG-09-28 Sep 2009

50 sites in addition to the ones above 

Page 13: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

[email protected] 13

Milestones – 7

01-Sep-09 WLCG High Level Milestones

      Done (green)  Late < 1 month

(orange)  Late > 1 month (red)  

ID Date Milestone ASGCCC

IN2P3CERN

DE-KIT

INFN CNAF

NDGF PIC RALSARA NIKHE

F

TRIUMF BNL FNAL

Metrics and Monitoring Milestones

WLCG-09-08 Nov 2008

Experiments Dataflows clear for the Tier-1 SitesExperiments should present the data flows they expect to reach at the Sites (a la LHCb)

ALICE ATLAS CMSLHCb

Nov 2007

WLCG-09-09 Removed

Tier-1 Sites Define Their MSS MetricsTier-1 Sites specify which metrics are going to be collected to demonstrate the dataflow supported

                       

WLCG-09-10 June 2009

Tier-1 Sites Publish Their MSS Metrics in SLSTier-1 Sites make their current MSS metrics available via SLS

                       

WLCG-09-11 TDB Automatic Alarms (SAM, etc) at the Tier-1 SitesTier-1 Sites should be able to automatically send, receive and handle alarms and problem notifications

                       

WLCG-09-12 TDB Monitoring of the Storage SystemsThe Storage systems used provide monitoring information to Sites and Experiments CASTOR dCache DPM StoRM BestMan

WLCG-09-13 TDB Performance Metrics?User Response, Services DowtimesOperations KPI                        

Page 14: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

[email protected] 14

Milestones – 8

01-Sep-09 WLCG High Level Milestones

      Done (green)  Late < 1 month

(orange)  Late > 1 month (red)  

ID Date Milestone ASGCCC

IN2P3CERN

DE-KIT

INFN CNAF

NDGF PIC RALSARA NIKHE

F

TRIUMF BNL FNAL

CPU Benchmarks/Units Milestones

WLCG-09-14 Dec 2008

CPU New Unit Working Group CompletedAgreement on Benchmarking Methods Conversion Proposal and Test Machines CPU New Benchmarking Unit Working Group

WLCG-09-15 Feb 2009

Sites Pledges in HEPSPEC-06Pledged from the Sites should be converted to the new unit LCG Office

WLCG-09-16 Apr 2009

New Experiments Requirement in HEPSPEC-06Experiments should convert their requirements to the new unit (or by LCG Office) ALICE ATLAS CMS LHCb

WLCG-09-24 May 2009

Sites Benchmark their Capacity in the HEPSPEC-06Resources from the Sites should be converted to the new unit

                       

Site benchmarking in progress

Page 15: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

[email protected] 15

STEP09 follow-up:Tier 0 + Tier 1s

All: MSS metrics Need instant real-time monitoring of

throughput (and per day overview) and to view transfers per experiment (WAN in/out; LAN – WNs)

Tools for site and grid NL-T1:

Communication & SIRs Lack of tape drives (now installed) DMF tuning needed? Unexplained low performance LAN b/w to WN too small Shared SW area problems Repeat tests

ASGC: Castor version? Job scheduling T2 v T1; ATLAS v CMS Low efficiency for CMS reprocessing jobs Repeat tests

FZK: Improve communication to world SAN issues Shared SW area problems SRM server overload dcap access problems Too many lcg-cp overload gridftp Repeat tests

NDGF: No MSS performance monitoring Low throughput Analysis jobs overloaded network No Panda pre-staging What is action to improve?

CNAF: Shared SW area problems

Site visits – planned for FZK + NL-T1

This was the summary immediately after STEP’09

Page 16: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

[email protected] 16

Tier 2s

Shared SW areas affect CPU efficiencies in some sites (also T1) ATLAS efficiencies different between WMS and PANDA

Likely due to different data access methods Data transfer timeouts (what? see analysis summary) Intra-VO fairshares how to manage? ( GDB?) VO communications

Need for VO-independent channel to reach all T2 admins Network infrastructure not good enough for data rates

This was the summary immediately after STEP’09

Page 17: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

[email protected] 17

Data management

Some detailed tuning issues; e.g.: FTS: Timeouts for large files FTS: Increase the number of concurrent jobs to increase bandwidth LFC: Deploy bulk methods (new additions)

dCache: These were discussed in August MB:

Need a clear strategy for Chimera (and risk analysis) Explain “golden” release v what we have (and risk analysis)

Site decisions, but must be based on understanding of risks Other issues:

Data transfer timeouts (dcap/rfio) at high (analysis) load Better data access strategies???

Pre-stage vs copy locally vs Posix-io General investigation of data access methods and problems

Work already done by ATLAS – extended to other experiments Shared software areas:

Site issue – NFS not a good solution Monitoring:

More real time on MSS transfers (Tier 0 and useful at Tier 1s) MSS metrics Improve dashboards – ATLAS vs CMS

Page 18: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

CERN IT Department

CH-1211 Genève 23

Switzerlandwww.cern.ch/

it

Tier0 Status - 18

Tier0 Status

• Resource Status– Still on schedule to have balance of 2009

pledge operational in October, but schedule is tight, especially for commissioning of new water-cooled racks.

– 1st pass of tape repack (to 1TB media) complete; now have 29PB of free media space

– Migration to SLC5 continues (50% of resources now on SLC5), but still concerns over general take up.• delay of switch of lxplus alias is a concern.

SLC4

SLC5

Page 19: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

CERN IT Department

CH-1211 Genève 23

Switzerlandwww.cern.ch/

it

Tier0 Status - 19

Tier0 Status

• CASTOR– Generally smooth running since STEP

• Deploying 2.1.8.10 across LHC experiments; completes tomorrow with LHCb and can then have improved monitoring of migration rates

• CASTOR 2.1.9.0 deployed on tape servers; this is the base for future tape optimisations (e.g. transfer aggregation)

– Main issue has been service degradations due to inadvertent misuse by individual users• An operations priority for future developments

Page 20: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

CERN IT Department

CH-1211 Genève 23

Switzerlandwww.cern.ch/

it

Tier0 Status - 20

CMS

Page 21: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

CERN IT Department

CH-1211 Genève 23

Switzerlandwww.cern.ch/

it

Tier0 Status - 21

ATLAS

Page 22: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

CERN IT Department

CH-1211 Genève 23

Switzerlandwww.cern.ch/

it

Tier0 Status - 22

LHCb

Page 23: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

CERN IT Department

CH-1211 Genève 23

Switzerlandwww.cern.ch/

it

Tier0 Status - 23

ALICE

Page 24: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

CERN IT Department

CH-1211 Genève 23

Switzerlandwww.cern.ch/

it

Tier0 Status - 24

Tier0 Status

• Computer Centre Infrastructure– Decision on construction of new Computer

Centre in Prévessin suspended pending clearer view of• costs for a container based solution• long-term computing requirements

– Projects now underway to• Reinforce “critical power” infrastructure in B513

to guarantee support for load of ~480kW.• Plan installation of containers in 2010 (for both

“critical” and “physics” loads.

Page 25: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

[email protected] 25

Mass storage

Upgrades for dCache and Castor – to get stable versions for data taking

dCache: 1.9.4 introduces ACLs to ensure file protection Migration to new namespace (Chimera) from pnfs for better scalability

(recommended for large sites) Site decision, but had full discussion of risks/advantages

1.9.5 will be “golden” version for support during 1st year of data taking Castor:

2.1.9 (consolidation version) will be deployed at CERN Encourage RAL, CNAF, ASGC to upgrade to this for better analysis

support

Resolution of open issues from SRM functionality requests Remember: “addendum” of functionality that had bee requested, but put on

hold in order to ensure stable versions See next slides

Page 26: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

[email protected] 26

Missing SRM features by priority

Extremely important Space protection

But at least tape protection is available everywhere File pinning

On CASTOR is almost non-existent But pinning importance is lower with file pre-staging services

Rather important VOMS awareness

Missing from CASTOR

Useful Target space selection

Missing in dCache an StoRM

Nice to have Ls returns all spaces with a copy of the file

Missing in CASTOR (where it makes sense)

Scalability and stability (CMS) Main issues at Tier-2’s It is required that the SRM front-end should guarantee that the activity of a single user

could not disrupt the service

Page 27: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

[email protected] 27

Middleware

WMS: WMS 3.2 available – can submit to CREAM and to the ARC-CE

Compute Element New version of CREAM with many bug fixes – now deployable in parallel

with existing CEs Once the old WMS have been retired, can seriously use CREAM in

production Glexec/SCAS (needed for multi-user pilot jobs)

Now ready ... But deployment take-up by sites is very slow Information system:

Latest version can also handle new schema with improved service discovery

Generally: Continuous process of patching and updating middleware as needed

Page 28: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

[email protected] 28

Resources LHCC report and CRSG report only recently available

2009 resources being installed (deadline October)

2010 resources Use requests as presented in July review/listed in final CRSG report

Except: ALICE where RSG report has wrong numbers – updates provided by ALICE; anticipate updated CRSG report

Message, agreed with CERN management, sent to funding agencies for RRB preparation: experiment requests have been reviewed by both the LHCC and C-RSG bodies who have been

working closely together. The result of their work led to agreement on the experiment requests in the attached table* to be used until data taking and the running conditions beyond 2010 are known. Their results also clearly state that computing resources should not in any way hinder the LHC physics programme.

Consequently at the next CRRB..., the main emphasis will be on the 2010 resource situation. In order to prepare the meeting, each site is asked to:

confirm that 2009 resources pledged are now available in production, or if not explain any difference

confirm 2010 pledges, and for sites supporting more than one experiment, indicate the split between the experiments 

Until first data-taking and further news about the running scenario beyond 2010 is known, the CRRB Chairman has agreed that exceptionally we do not require your pledge data beyond 2010 for this meeting.

Page 29: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

[email protected] 29

Resource installations & issues

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

3,000,000

CPU Time Delivered

month (2009)

MS

I2K

-da

ys

.

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

Disk Storage Used

month (2009)

Te

raB

yte

s

.

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

Tape Storage Used

month (2009)

Te

raB

yte

s

.

ASGC NL-T1

NL-T1NL-T1

Page 30: Ian Bird LCG Project Leader Project status report WLCG LHCC Referees’ meeting 21 st September 2009

[email protected] 30

Comments on review process/outcome

Timeliness of report and overall timing of the process Long procurement cycles are unavoidable and we must have the conclusions earlier Results needed in the Spring for requests for the following year (now in Autumn RRB) The report is essential well in advance of the RRB to allow discussion and feedback

Much effort has been invested by the RSG members and others – in future it might be better to better coordinate between the LHCC and the RSG?

Is having dedicated scrutineers per experiment most efficient? E.g. comparison of CMS and ATLAS was required.

Actually the fundamental questions have not been answered: Trigger rates Amount of MC # of reprocessings

Experiment models and RSG simple models agree within 10% (level of uncertainty any way); future understanding must be based on: Experience with data Real answers to the above basic parameter questions

C-RRB (and C-RSG) modelled on other RRBs; but computing is different and the process needs to reflect that: Combine RSG and LHCC reviews/reviewers? Change timing ...