I-35 Reconstruction Project
Larry Colclasure, P.E. TxDOT John Habermann, P.E., TTI
2014 Short Course
I-35 SMART WORK ZONE UPDATE
I-35 Reconstruction Project
Overview
TxDOT is committed to finishing the widening of Main Street Texas
(I-35) to six lanes from San Antonio to
Hillsboro.
2
Current scope of I-35 Widening. (South of Salado to Hillsboro)
I-35 Reconstruction Project
I-35 Demographics
3
I-35 Reconstruction Project
I-35 in WAC – Travelers by City of Origin
~66% through traffic Austin
17%
Belton 4%
Bruceville-Eddy 4%
Dallas 11%
Fort Worth 14%
Georgetown 2%
Hillsboro 3%
Round Rock 7%
Salado 7%
San Antonio 4%
San Marcos 3%
Temple 6%
Waco 18%
4
I-35 Reconstruction Project
What Do I-35 Travelers Want?
DELAYS CURRENT TRAVEL TIMES
INCIDENTS LANE CLOSURES
FORECASTED TRAVEL TIMES
DETOUR ROUTES CURRENT SPEEDS SNAPSHOTS
5
I-35 Reconstruction Project
Traveler Information Outreach
En-route – Travel times – Rest area signage (inside and out) – End-of-queue warning systems – Coordination with other TMCs
Web
– Real-time map (linked from front page of My35) • Closures, travel times, delays, trip planner • Show information by direction
– Other web site coordination Email
– Lane closures – Traffic alerts Social Media
– Twitter – Facebook
6
I-35 Reconstruction Project
Travel Time Signs
85%
7
Approval rating of signs from those that have seen them
I-35 Reconstruction Project
Comments on Travel Time Signs
“LOVE LOVE LOVE these signs. Wish they were permanent.” “I know the “normal” times and this info lets me know how slow it’s going to
be.” “They should state the reason for the delay and advise of alternate routes.”
“These are extremely helpful during my daily drive.”
“VERY HELPFUL. I can decide whether or not to use the feeder/access road.”
“Love it! Helps me on time crunch.”
8
I-35 Reconstruction Project
My35 Helpfulness
Not Helpful 8%
Occassionally 19%
Frequently 32%
Always 41%
92%
9
I-35 Reconstruction Project
I-35 Real-Time Map Topic Selection (2013-2014)
Planner 16%
Incidents 29%
Weather 10%
Signs 21%
Closures 24%
10
I-35 Reconstruction Project
Lane Closure E-Mail Subscriptions
92%
Rarely/Never Occasionally Frequently/Always
11
I-35 Reconstruction Project
Representative Comments on Lane Closure Emails
“Invaluable tool though most of my travel is leisure. Wonderful service provided by TxDOT.” “I always check these before I plan a trip.”
“We use the information to help with our bus routes and trips. I also use the
information for personal travel.” “I rely heavily on the information provided when planning my daily trips from
Waco to SMU in Dallas.” “I don’t understand why they close all these exits.”
“Same info every day. I really need weather related info and cannot get it via
the emails. Really disappointed about that.”
12
I-35 Reconstruction Project
Public Perception of Information Accuracy
Nearly Always
Most of the Time
More than Half the Time
Less than Half the Time
Almost Never
32%
9%
55%
3%
1%
87%
13
Information is accurate…
I-35 Reconstruction Project
Have You Changed Plans Based on the Information?
Never 38%
Once or Twice 15%
Occasionally 19%
Frequently 28%
62%
14
I-35 Reconstruction Project
Some of the Innovations…
Comprehensive lane closure database Delay and queue assessment for each closure
End of queue warning systems
Solar / cellular basis for corridor wide ITS equipment base
PCMS for travel times in construction zones
Lane closure email notifications
Incident alerting / updates
Advanced traveler information real-time map
Operational performance metrics
15
I-35 Reconstruction Project
Future Plans
Construction ITS serves as foundation for permanent ITS Migrate Lonestar operations to Ft. Worth TMC
Construction delay signs
Equip alternate routes
Connected vehicles applications test bed (USDOT)
16
I-35 Reconstruction Project
Project Ombudsman/Technical Advisor • Engage and assist those impacted • Keep internal / external
stakeholders informed • Facilitate flow of information • Assist Public Information Officer • Examine mobility across all I-35 construction projects • Mitigate traffic and access impacts • Listen • No Surprises/Manage Expectations
17
I-35 Mobility Coordination
TxD
OT
Mobility Coordinator
I-35 Reconstruction Project
I-35 Mobility Coordination
• Maintain Mobility • Examine mobility across all I-35 construction projects • Mitigate traffic and access impacts • Serve as technical advisor • Listen
• Communicate – “Keep People Informed” • Facilitate flow of information (e.g., lane closures, frontage roads) • Assist PIO staff
• Monthly newsletter • Flyers • Community Meetings
• Meet with stakeholders
18
I-35 Reconstruction Project 19
The Communication Challenge
• More than 30 million travelers per year pass through this corridor.
• ~2/3 travel through the corridor.
• 1,000 businesses and 13 communities are located on these 96 miles.
I-35 Mobility Coordination
I-35 Reconstruction Project
I-35 Mobility Coordination
20
I-35 Reconstruction Project
Automated monitoring near a work zone
Warning of slow speeds
Warning of end of ‘stop and go’ traffic
21
I-35 Smart Work Zones
I-35 Reconstruction Project
Crash Data Analysis
22
I-35 Reconstruction Project
Crash Data Analysis
23
I-35 Reconstruction Project
Traffic Engineering Solutions
24
I-35 Reconstruction Project
0
500
1000
1500
2000
2500
3000
0 4 8M
ON
1
2 16 20 24 4 8TU
E
12 16 20 24 4 8
WED
1
2 16 20 24 4 8TH
U
12 16 20 24 4 8
FRI
12 16 20 24 4 8
SAT
1
2 16 20 24 4 8S
UN
1
2 16 20 24
Historical Hourly Volumes on IH-35 Southbound at West South (Tokio Rd.) (6-month average)
Examples of Support: Lane Closures
25
I-35 Reconstruction Project
Examples of Support: Working with Business
26
I-35 Reconstruction Project
Examples of Support: Business Access
27
I-35 Reconstruction Project
...to be continued
28