hydraulic source control and containment system groundwater

39
HYDRAULIC SOURCE CONTROL AND CONTAINMENT SYSTEM GROUNDWATER MODEL UPDATE REPORT NW NATURAL GASCO SITE Prepared for NW Natural Prepared by Anchor QEA, LLC July 2013

Upload: hadang

Post on 02-Jan-2017

224 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Hydraulic Source Control and Containment System Groundwater

HYDRAULIC SOURCE CONTROL AND CONTAINMENT SYSTEM GROUNDWATER MODEL UPDATE REPORT NW NATURAL GASCO SITE

Prepared for NW Natural

Prepared by Anchor QEA, LLC

July 2013

Page 2: Hydraulic Source Control and Containment System Groundwater

I:\Projects\NW Natural\Gasco\Source Control Evaluation\Deliverables\Hydraulic SC & Containment System GW Model Update\GW Model Update Report_2013-07-29.docx.docx

HYDRAULIC SOURCE CONTROL AND CONTAINMENT SYSTEM GROUNDWATER MODEL UPDATE REPORT NW NATURAL GASCO SITE

Prepared for NW Natural

Prepared by Anchor QEA, LLC

July 2013

Page 3: Hydraulic Source Control and Containment System Groundwater

Hydraulic SC and Containment System GW Model Update Report July 2013 NW Natural Gasco Site i 000029-02.26

TABLE OF CONTENTS 1 INTRODUCTION .............................................................................................................................. 1

1.1 Background ................................................................................................................................. 1

1.2 Previous Model Development Efforts ..................................................................................... 2

1.2.1 2007 Model ............................................................................................................................ 2

1.2.2 2008 Model ............................................................................................................................ 3

1.2.3 2009 Model ............................................................................................................................ 3

1.2.4 2011 Model ............................................................................................................................ 4

1.3 Objectives and Scope of the Current Model ........................................................................... 4

2 MODEL DEVELOPMENT ................................................................................................................ 6

2.1 Model Grid Development ......................................................................................................... 6

2.1.1 Model Layering .................................................................................................................... 6

2.1.2 Revisions to Geological Contacts ....................................................................................... 6

2.2 Boundary Conditions ................................................................................................................ 8

2.2.1 No-Flow Boundaries ........................................................................................................... 8

2.2.2 Constant Head Boundaries ................................................................................................. 8

2.2.3 General Head Boundary ..................................................................................................... 9

2.2.4 Recharge ................................................................................................................................ 9

2.2.5 Pumping ................................................................................................................................ 9

2.2.6 Liquefied Natural Gas Basin ............................................................................................ 11

2.3 Initial Conditions...................................................................................................................... 11

2.4 Model Parameterization .......................................................................................................... 11

2.4.1 Summary of Extraction Well Pump Tests ...................................................................... 11

2.4.2 Hydraulic Conductivity Zones Used in Model ............................................................. 13

3 MODEL CALIBRATION AND VALIDATION APPROACH................................................. 14

3.1 Calibration/Validation Datasets ............................................................................................. 14

3.2 General Approach .................................................................................................................... 14

3.3 Model Application ................................................................................................................... 16

4 REFERENCES .................................................................................................................................... 17

Page 4: Hydraulic Source Control and Containment System Groundwater

Table of Contents

Hydraulic SC and Containment System GW Model Update Report July 2013 NW Natural Gasco Site ii 000029-02.26

List of Tables Table 1 Extraction Wells Specified in the Groundwater Model ............................................ 10

Table 2 Summary of Hydraulic Conductivities Derived from Step Tests ........................... 12

List of Figures Figure 1 Groundwater Model Domain Figure 2 Monitoring Well and Cross Section Location Map Figure 3a – 3c Geologic Cross Section A-A' (Figure 2-3 from CDR, latest version) Figure 4 Stratigraphic Units Represented in Model Row 59, Approximately Comparable

to Cross-Section A-A’ Figure 5 Geologic Cross Section B-B' Figure 6 Stratigraphic Units Represented in Model Column 75, Approximately

Comparable to Cross-Section B-B’ Figure 7 Geologic Cross Section C-C' Figure 8 Stratigraphic Units Represented in Model Column 93, Approximately

Comparable to Cross-Section C-C’ Figure 9a –9b Geologic Cross Section F-F' Figure 10 Stratigraphic Units Represented in Model Column 119, Approximately

Comparable to Cross-Section F-F’ Figure 11 Model Boundary Conditions Figure 12 Initial Horizontal Hydraulic Conductivity Values Specified for the Upper

Alluvial Water Bearing Zone Figure 13 Initial Horizontal Hydraulic Conductivity Values Specified for the Lower

Alluvial Water Bearing Zone

Page 5: Hydraulic Source Control and Containment System Groundwater

Hydraulic SC and Containment System GW Model Update Report July 2013 NW Natural Gasco Site i 000029-02.26

LIST OF ACRONYMS AND ABBREVIATIONS CDR Revised Groundwater Source Control Construction Design Report

CHD time-variant specified head

DEQ Oregon Department of Environmental Quality

EPA U.S. Environmental Protection Agency

HAI Hahn and Associates, Inc.

HC&C hydraulic control and containment

LNG liquefied natural gas

Plan Groundwater Source Control Extraction System Test Plan

PLC programmable logic control

RAO Remedial Action Objective Report Hydraulic Source Control and Containment System Groundwater

Model Update Report

Site Gasco site

WBZ water bearing zone

Page 6: Hydraulic Source Control and Containment System Groundwater

Hydraulic SC and Containment System GW Model Update Report July 2013 NW Natural Gasco Site 1 000029-02.26

1 INTRODUCTION 1.1 Background The Oregon Department of Environmental Quality (DEQ) and the U.S. Environmental Protection Agency (EPA) provided comments in July 2012 in response to the groundwater model documentation provided as Appendix F of the Revised Groundwater Source Control Construction Design Report (CDR; Anchor QEA 2012). DEQ and EPA also provided responses to NW Natural’s responses to DEQ and EPA’s comments on the groundwater model development report provided as part of the Draft Groundwater Source Control Final Design Report (Anchor QEA 2011). In Section 3.2.3 of the CDR, NW Natural proposed to update the model with aquifer property information derived from the step drawdown tests conducted on the extraction wells. Construction of the source control extraction wells, pipelines, and control system is complete. This Hydraulic Source Control and Containment System Groundwater Model Update Report (Report) describes the work accomplished to update the model with new information from installation and testing of new extraction wells, monitoring wells, and piezometers that have been installed since the submittal of Appendix F to the CDR. This Report was prepared consistent with the Groundwater Model Update Plan submitted to DEQ on February 15, 2013 (Anchor QEA 2013a) and was also prepared consistent with DEQ and EPA’s April 8, 2013 comments on the update plan, as addressed in NW Natural’s May 24, 2013 response to comments memorandum (Anchor QEA 2013b). This Report is a companion to the Groundwater Source Control Extraction System Test Plan (Plan) that is scheduled for submittal to DEQ on August 1, 2013. That Plan describes the design of a two-phase program of testing the extraction system that will take approximately 1 year. Section 3.1 describes how the Plan is designed to provide a calibration dataset for the groundwater model. The Plan also describes the Remedial Action Objectives (RAOs) for groundwater source control measures. On page 7, paragraph 1, of DEQ’s September 22, 2011 letter, DEQ states that the RAOs for groundwater source control are as follows:

1. prevent migration of contaminated groundwater from the uplands to the Willamette River along shoreline Segments 1 and 2, in a manner that;

Page 7: Hydraulic Source Control and Containment System Groundwater

Introduction

Hydraulic SC and Containment System GW Model Update Report July 2013 NW Natural Gasco Site 2 000029-02.26

2. minimizes [dense non-aqueous phase liquid] DNAPL mobilization resulting from groundwater [source control measures] SCMs along the portion of Segment 1 where DNAPL occurs.

1.2 Previous Model Development Efforts Groundwater modeling has been an integral part of the evaluation of remedial technologies for the Gasco site (Site). The model has evolved over time with increasing refinement as new data became available, in response to DEQ and EPA comments and as new objectives for remedial actions were developed. The following subsections summarize the groundwater modeling effort at the Site. The summary is organized by the year when major model refinements were made.

1.2.1 2007 Model The initial groundwater flow modeling analysis for the Site was prepared in 2007 to evaluate the feasibility of controlling Site groundwater using an extraction system in possible combination with a containment wall. The 2007 model boundaries extended from the foot of the Tualatin Mountains at Highway 30 to the southwest of the Site and across the Willamette River navigation channel to the northeast. The model extended from the BNSF Railway bridge over the river upstream of the Siltronic property to the boat basin on the U.S. Moorings property downstream of the Site. The model used a 40- by 40-foot uniform grid and consisted of 14 model layers extending from the ground surface to bedrock. One model layer represented the Fill water bearing zone (WBZ), two model layers represented the shallow silt, and the remaining model layers represented the Alluvium WBZ. The Alluvium WBZ was divided into a relatively low hydraulic conductivity Upper Alluvium WBZ and a higher conductivity Lower Alluvium WBZ. The Lower Alluvium WBZ in the model extended upland approximately 200 feet from the river based on the change in water level gradients between upland and nearshore wells. Model layers within the Alluvium WBZ were set at specific depth intervals related to the depth of proposed containment walls and various screen intervals of extraction wells. Model boundaries included the following:

• Areal recharge (this recharge boundary is constant across the entire model domain) • Steady-state constant head in the river

Page 8: Hydraulic Source Control and Containment System Groundwater

Introduction

Hydraulic SC and Containment System GW Model Update Report July 2013 NW Natural Gasco Site 3 000029-02.26

• Constant heads along the upland boundary at Highway 30 of the Upper Alluvium WBZ • No flow boundaries at the upstream river bridge and downstream U.S. Moorings boat

basin model boundaries where groundwater flow is expected to be approximately parallel to the model boundary

• No flow at the lower model boundary (bedrock)

In addition, a general head boundary was applied to the Upper Alluvium WBZ layers on the east side of the river to represent groundwater flow to the river from that direction. The above-described model structure with respect to model layers and boundary conditions continued to be used in the post-2007 modeling except for the refinements described in Sections 1.2.2 through 1.2.4.

1.2.2 2008 Model The model was refined in 2008 to extend the Lower Alluvium WBZ hydraulic conductivity zone to the upland model boundary at Highway 30 and to increase the Upper Alluvium WBZ hydraulic conductivity by 50 percent. These changes were made in response to comments from DEQ concerning the difference between the upland boundary flux in the model compared to predicted flux in the vicinity of the Site in a regional model developed by the U.S. Geologic Survey (Morgan and McFarland 1996). The 2008 model was used to simulate the pumping test at extraction well PW-3 (designated as PW-4 at that time). In this model application, the river boundary condition was changed from a steady-state constant head to a time-varying constant head. After 2008, both steady-state and time-varying constant head boundary conditions were used for the river boundary depending on whether the simulation was for a steady-state or transient application.

1.2.3 2009 Model The model was refined in 2009 to include the liquefied natural gas (LNG) basin sump and the Alluvium WBZ aquitard. The basin was incorporated using the MODFLOW drain package. The drain package conductance was calibrated to dry weather LNG basin flows when the flow at the sump is due to groundwater entering the sump.

Page 9: Hydraulic Source Control and Containment System Groundwater

Introduction

Hydraulic SC and Containment System GW Model Update Report July 2013 NW Natural Gasco Site 4 000029-02.26

The Alluvium WBZ aquitard was identified in TarGost borings at an elevation of approximately -100 to -120 feet. The model layering was modified to represent the depth, thickness, and extent of the Alluvium WBZ aquitard. This model was used in support of the Groundwater Source Control Interim Design Report (Anchor QEA 2009).

1.2.4 2011 Model Between 2009 and 2011, the groundwater flow model was changed in several ways to address DEQ comments on the Groundwater Source Control Interim Design Report. These changes included the following:

• The model area was extended in the downstream direction to include the U.S. Moorings site. The original model extended approximately mid-way through the U.S. Moorings site.

• The model grid spacing was redefined from 40 by 40 feet to 20 by 20 feet. As in the original model, a uniform grid spacing was used throughout the model area.

• The hydraulic conductivity of the Upper Alluvium was modified to represent spatial heterogeneity observed in pumping test results at PW-1-80, PW-3-85, and PW-8-39.

The 2011 model was used in support of the Groundwater Source Control Interim Design Report and the Draft Groundwater Source Control Final Design Report (Anchor QEA 2009, 2011).

1.3 Objectives and Scope of the Current Model The constructed hydraulic control and containment (HC&C) system is designed to contain Site groundwater by extraction wells screened in the Upper and Lower Alluvium WBZ. The extraction wells will be controlled by a programmable logic control (PLC) system that will operate the pumps to maintain a water level difference (∆H) between the river and selected monitoring wells known as control wells. Transducers in the control wells and a transducer at an in-river stilling well will be connected to the PLC, which will monitor the water level difference between each control well and the river. If the water level difference at a control well is less than ∆H, then the PLC will increase the pumping rate at the extraction well that is assigned to that control well. The objective is to maintain a net average gradient from the river to the HC&C system, which will ensure that Site groundwater is contained. The groundwater model in this report is being developed to serve as a mechanistic tool that can support the evaluation of system-wide containment of groundwater under a range of operating

Page 10: Hydraulic Source Control and Containment System Groundwater

Introduction

Hydraulic SC and Containment System GW Model Update Report July 2013 NW Natural Gasco Site 5 000029-02.26

conditions. Specifically, it will be used to evaluate whether the selected ∆H values between the HC&C wells and the river attain groundwater containment across tidal and seasonal fluctuations in water surface elevation at the Willamette River. The model will also serve as a basis for identifying long-term operational parameters (for example, ∆H) for the HC&C system. In addition, in conjunction with data analysis from the full-system start-up tests described in the Plan (Anchor QEA 2013), the model will be applied to provide guidance on selecting wells from the suite of existing wells to support a long-term monitoring program. To support the objectives, the 2011 model has been redeveloped to consider new information that has become available during the construction and the extraction system and will be calibrated and applied under transient conditions. This report describes the redevelopment of the 2011 model. From hereon the redeveloped 2011 model is referred to as the current model. The dataset for calibration will be collected during full system start-up testing. Details of the full system testing are described in the Plan. Details of the transient calibration of the current model will be documented in 2014 after the completion of the initial phase of full system start-up tests.

Page 11: Hydraulic Source Control and Containment System Groundwater

Hydraulic SC and Containment System GW Model Update Report July 2013 NW Natural Gasco Site 6 000029-02.26

2 MODEL DEVELOPMENT The current model was redeveloped to use improved interpretations of the stratigraphic units obtained from the installation and testing of the extraction wells, monitoring wells, and piezometers.

2.1 Model Grid Development The current model footprint is unchanged from the 2011 groundwater model (see Section 1.2.4), which was developed for the CDR (Anchor QEA 2012). Figure 1 shows the domain for the current model. It extends from the BNSF Railway bridge upstream of the Siltronic property to the downstream side of the small boat basin in the U.S. Moorings property and from the foot of the Tualatin Mountains at Highway 30 southwest of the Site and across the navigation channel to the northeast. Horizontally, the model grid cells are developed at a uniform spatial resolution of 20 by 20 feet. The vertical resolution of the model is described in greater detail in the following sections.

2.1.1 Model Layering The layers of the current model were refined to reflect the constructed screen intervals of the extraction wells. Overall, the current model contains 12 layers of varying thickness. The layer thicknesses were adjusted in the vicinity of extraction wells to entirely capture the screen interval within one model layer. The layering in the current model differs from the 2011 model in that the layers in the current model follow the topography, and therefore, the stratigraphic units are not necessarily limited to a single or few layers that pinch out toward upland, as in the 2011 model.

2.1.2 Revisions to Geological Contacts Interpretations of geological contacts were revised following issuance of the CDR using new lithology information from the geologic logs of newly completed extraction wells, monitoring wells, and piezometers. Figure 2 shows the locations of all the borings that were used in developing and revising the stratigraphic interpretations. The revisions focused on improving the interpretation for all stratigraphic units to the extent the new wells provided additional information for each unit. The revised interpretations of the alluvial soil layers from the new borings were applied to refine the contacts between the hydrogeologic WBZs in the model. The new data did not

Page 12: Hydraulic Source Control and Containment System Groundwater

Model Development

Hydraulic SC and Containment System GW Model Update Report July 2013 NW Natural Gasco Site 7 000029-02.26

change the sequence or nomenclature for the WBZs, but the thickness, elevation, and lateral extent of some of the alluvial layers were modified. Based on the new geologic information the WBZ contact elevations were adjusted in the model. Figures 3a, 3b, and 3c show the up to date boundaries of the geological contacts along Section A-A’, which is parallel to the Willamette River near the top of the riverbank (see Figure 2 for location of cross sections). Figure 4 shows the stratigraphic zones represented in Row 59 of the model; the location of Row 59 near the shoreline is about the same as Section A-A’ on Figure 3. The lower boundary of the bottommost layer of the model is the contact with the basalt bedrock, which is not shown in the model cross sections, but coincides with the bottom of the cross section shown on Figure 4. Figure 4 shows that the WBZs and the extraction well screen zones are correctly represented in the model. Not all of the wells shown on Figure 3 are represented on Figure 4 because some wells are projected onto the Figure 3 cross section, whereas Figure 4 accurately preserves the spatial locations of the wells in the model. Thus, some of the extraction wells were placed in adjacent model rows (Rows 57 through 61), depending on the surveyed coordinates of the wells. Figures 5 through 10 show subsurface geology and the corresponding translations to the model at cross sections B-B’, C-C’, and F-F’ that are oriented from upland to the Willamette River. These cross sections cover extraction wells PW-8-39 and PW-8-68, PW-6-U and PW-6-L, and PW-3-U and PW-3-118, respectively. As with some of the wells in cross section A-A’, PW-3-118 is not shown on the Figure 10 model profile because the well is not located in the 20- by 20-foot model node that crosses the cross section line. All three sets of cross sections show that the approximate elevations of the WBZs, the extent of the deep aquitard, contact with basalt bedrock (lower interface of the bottommost model layer), and the positions of the extraction wells are well represented in the model. In some portions of the geological cross sections, an interpretation was not possible due to limitations in data availability (for example, in cross section F-F’ shown on Figure 9, direct push borings were extended to refusal, but soil samples could not be obtained below the upper stratigraphic units). These are shown as blank white spaces on Figures 5, 7, and 9. A full geospatial specification of stratigraphic units is required for the model, which was achieved through geospatial interpolation. Thus, the model cross sections show the interpolated units on Figures 6, 8, and 10 in the corresponding spaces.

Page 13: Hydraulic Source Control and Containment System Groundwater

Model Development

Hydraulic SC and Containment System GW Model Update Report July 2013 NW Natural Gasco Site 8 000029-02.26

2.2 Boundary Conditions The boundary conditions applied to the model are shown on Figure 11. Each boundary condition is described in greater detail in the following sections.

2.2.1 No-Flow Boundaries The upstream and downstream model boundaries adjacent to the U.S. Moorings and Siltronic properties, respectively, are modeled as no-flow boundaries. This was based on the Site-wide groundwater level contours developed during the Remedial Investigation Report (HAI 2007), which concluded that the groundwater flow direction in both the Fill and Upper Alluvium WBZ (shallower than 85 feet below ground surface) were predominantly north-northeast toward the Willamette River. The report indicated that the flow direction is more northerly in the Lower Alluvium WBZ but cast doubts over this conclusion because of insufficient data in the Lower Alluvium. For the purposes of the current model, the no-flow boundary conditions specified for the Fill WBZ and Upper Alluvium WBZ are extended down to the Lower Alluvium WBZ. The sensitivity of the model predicted water levels to this assumption will be evaluated during model calibration by performing simulations that employ a constant head boundary for the Lower Alluvium WBZ. A no-flow boundary is also assumed at the Alluvium WBZ and bedrock contact at the bottom of the model.

2.2.2 Constant Head Boundaries A constant head boundary is applied to the southwest upland boundary at Highway 30. The value of the constant head will be based on the contours developed from new water level measurements made during full system start-up tests. The Willamette River boundary will be specified as a constant head boundary using the time-variant specified head (CHD) package. The CHD package allows for specification of a tidal and time-varying river stage boundary that changes within and between MODFLOW stress periods1, thus supporting the simulation of transient conditions encountered during the full-system start-up tests. The stress period durations will be determined based on the river

1 Each model simulation period is divided into one or more stress periods. During each stress period, boundary conditions are usually kept constant. However, some specific packages (such as time-variable constant head) permit limited variations in boundary conditions within a stress period.

Page 14: Hydraulic Source Control and Containment System Groundwater

Model Development

Hydraulic SC and Containment System GW Model Update Report July 2013 NW Natural Gasco Site 9 000029-02.26

stage hydrograph measured during the start-up tests and are likely to be on the order of an hour. The Willamette River ordinary high water line was used to identify cells interfacing with the Willamette River (see Figure 11). The model grid is structured such that only the topmost model layer interfaces with the Willamette River boundary. Thus, the Willamette River boundary condition does not extend beyond the first layer of the model, whereas the upland constant head boundary is applied over all 12 layers of the model. As described in Section 2.1.1, even though the upland boundary condition is applied over all 12 layers in the current model, it extends only to the Fill and Upper Alluvium WBZs because the Lower Alluvium WBZ and the deep aquitard do not extend upland. Thus, effectively the upland constant boundaries are applied over the same stratigraphic units as the 2011 model.

2.2.3 General Head Boundary As with the 2011 model, the northeast boundary of the model below the Willamette River is specified as a general head boundary. This will allow bi-directional exchanges from the far shore depending on the river stage.

2.2.4 Recharge Site-wide recharge will be estimated based on the precipitation records reported at the Portland International Airport National Oceanic and Atmospheric Administration Weather Station. Recharge will be minimally simulated in model cells that are below impervious areas, such as paved areas or buildings. The 2011 groundwater model used a recharge rate of 2 inches per year for paved areas (Anchor QEA 2012), which will be carried forward here. In the 2007 model, a constant areal recharge of 10 inches per year was determined for the unpaved areas (see Appendix F in Anchor QEA 2009), and this value was carried forward in subsequent modeling efforts. In the current model, a similar approach will be adopted to specify recharge in the unpaved areas (i.e., it will be specified to enter the uppermost active layer in model, and the infiltration rate will be developed based on precipitation records, estimated runoff, and model calibration).

2.2.5 Pumping A total of 21 extraction wells are represented in the model, as shown in Table 1. The previous models were applied to simulate only a subset of extraction wells because many wells currently

Page 15: Hydraulic Source Control and Containment System Groundwater

Model Development

Hydraulic SC and Containment System GW Model Update Report July 2013 NW Natural Gasco Site 10 000029-02.26

developed at the Site were not present at that time. Thus, the current model is the first attempt to simulate the full set of extraction wells currently installed at the Site. As described in Section 2.1.1, the current model was constructed so that each extraction well screen interval does not cross model layer boundaries (see Figures 4, 6, 8 and 10). Extraction well pumping rates during system testing will vary to maintain a constant ∆H between the river and the control wells due to changing river stage and groundwater elevations. These variations in extraction well discharge rates during the model stress periods will be recorded by the PLC and will be accounted for in the transient simulations to be conducted after the full system startup tests.

Table 1 Extraction Wells Specified in the Groundwater Model

Well ID Easting1

(feet) Northing1

(feet) Top of Screen

(feet(2)) Bottom of

Screen (feet(2)) Model Row

Model Column

Model Layer

PW-1U 7,624,718.0 705,053.1 -20.1 -35.1 58 139 4

PW-2U 7,624,549.5 705,175.1 -23.3 -38.3 57 128 4

PW-3U 7,624,359.0 705,220.4 -17.2 -32.2 60 119 3

PW-4U 7,624,207.1 705,313.8 -18.9 -33.9 60 110 3

PW-5U 7,624,057.8 705,377.5 -17.4 -32.4 61 102 3

PW-6U 7,623,927.7 705,490.4 -17.9 -32.9 59 93 3

PW-8-39 7,623,605.5 705,683.0 -1.0 -16.0 59 75 2

PW-11U 7,624,435.7 705,191.3 -25.8 -40.8 59 123 4

PW-12U 7,624,297.6 705,265.9 -21.6 -36.6 60 115 3

PW-13U 7,624,144.5 705,333.4 -25.4 -40.4 61 107 4

PW-14U 7,623,986.9 705,437.0 -25.9 -35.9 60 97 3

PW-1L 7,624,730.3 705,046.4 -79.9 -99.9 58 139 6

PW-2L 7,624,558.3 705,165.7 -85.6 -105.6 58 129 7

PW-3-118 7,624,353.0 705,238.0 -82.5 -92.5 60 118 6

PW-4L 7,624,216.3 705,309.2 -77.2 -97.2 60 110 6

PW-5L 7,624,049.3 705,380.6 -73.4 -93.4 61 101 6

PW-6L 7,623,921.5 705,497.0 -72.7 -92.7 59 93 6

PW-7-93 7,623,757.9 705,591.1 -49.3 -69.3 59 84 4

PW-8-68 7,623,605.5 705,683.0 -23.4 -43.4 59 75 3

PW-9-92 7,623,393.3 705,809.3 -39.6 -59.6 59 62 9

PW-10L 7,623,189.4 705,921.9 -28.3 -48.3 59 51 9

Notes: 1 = Easting and Northing are in the Oregon State Plane system. 2 = Elevations are referenced to City of Portland’s Vertical Datum.

Page 16: Hydraulic Source Control and Containment System Groundwater

Model Development

Hydraulic SC and Containment System GW Model Update Report July 2013 NW Natural Gasco Site 11 000029-02.26

2.2.6 Liquefied Natural Gas Basin The LNG basin at the Site collects shallow groundwater that seeps from the Fill WBZ. Based on the volume of water pumped to maintain water levels within the collection sump, it is estimated the annualized rate at which groundwater and stormwater enters the basin is approximately 20 gallons per minute (HAI 2013). Stormwater entering the basin are represented in the model through recharge. The groundwater entering the LNG basin during dry conditions is specified as a drain boundary in the model. The drain boundary was introduced in the 2009 model (Anchor QEA 2009), and its representation has been carried forward unchanged in the subsequent models, including the current model.

2.3 Initial Conditions Initial groundwater levels will be determined based on water level measurements from the full system startup testing.

2.4 Model Parameterization A key aquifer property that is input to the model is the hydraulic conductivity of the WBZs. Extraction well step tests were recently conducted to determine the hydraulic conductivity in the Upper and Lower Alluvium WBZs. These tests are discussed further in the following subsection. Conductance at the drain boundary will be determined during model calibration. For transient simulations, the model requires an aquifer storage coefficient to determine the change in storage per unit area per unit change in head. This parameter is usually determined through calibration. The model layers will be set up as variably confined (i.e., the Fill and Upper Alluvium WBZ model layers will dynamically switch between confined and unconfined conditions depending on the groundwater elevations encountered over the course of the simulation). The storage coefficient under confined conditions will be orders of magnitude smaller than the storage coefficient during unconfined conditions. Thus, the storage coefficient used in the model for the Fill and Upper Alluvium WBZs will be considerably higher (typically in the range of 0.05 to 0.3) compared to the Lower Alluvium WBZ (typically in the range of 0.00001 to 0.001).

2.4.1 Summary of Extraction Well Pump Tests Pump tests were conducted at extraction wells PW-1-80, PW-3-85, PW-3-118, PW-7-93, PW-8-39, PW-8-68, and PW-9-92. The findings from the test of PW-1-80 were reported by Hahn and

Page 17: Hydraulic Source Control and Containment System Groundwater

Model Development

Hydraulic SC and Containment System GW Model Update Report July 2013 NW Natural Gasco Site 12 000029-02.26

Associates, Inc. (HAI; 2006). The findings from the tests of PW-3-85 and PW-3-118 were reported by Anchor Environmental and S.S. Papadopulos and Associates (Anchor and SSPA 2008). The findings from the tests of PW-7-93, PW-8-39, and PW-9-92 were previously incorporated into the 2011 groundwater flow model (see Section 1.2.4 ). In 2012 and 2013, Upper Alluvium extraction wells PW-1U, PW-2U, PW-3U, PW-4U, PW-5U, PW-6U, PW-11U, PW-12U, PW-13U, and PW-14U were installed, developed, and step tested using the procedures described in the CDR (Anchor QEA 2012). During the same time period, Lower Alluvium extraction wells PW-1L, PW-2L, PW-4L, PW-5L, and PW-6L were installed and step tested. Extraction well PW-9-92 was redeveloped in 2012, and an additional step test was performed. These tests provide estimates of hydraulic conductivity in the vicinity of the wells, which were not available for the 2011 model. The results of the step test analyses are summarized in Table 2. A memorandum describing the derivation of the step test results will be submitted to DEQ separately.

Table 2 Summary of Hydraulic Conductivities Derived from Step Tests

Test Geological Unit Hydraulic Conductivity

(feet per day)

PW-1U Upper Alluvium 200

PW-2U Upper Alluvium 100

PW-3U Upper Alluvium 80

PW-4U Upper Alluvium 10

PW-5U Upper Alluvium 170

PW-6U Upper Alluvium 115

PW-8-39 Upper Alluvium 2 PW-11U Upper Alluvium 25

PW-12U Upper Alluvium 15

PW-13U Upper Alluvium 25

PW-14U Upper Alluvium 40

PW-1L Lower Alluvium 100

PW-2L Lower Alluvium 260

PW-3-118 Lower Alluvium 190

PW-4L Lower Alluvium 400

PW-5L Lower Alluvium 380

PW-6L Lower Alluvium 370

PW-7-93 Lower Alluvium 400(1)

PW-8-68 Lower Alluvium 400(1)

Page 18: Hydraulic Source Control and Containment System Groundwater

Model Development

Hydraulic SC and Containment System GW Model Update Report July 2013 NW Natural Gasco Site 13 000029-02.26

Test Geological Unit Hydraulic Conductivity

(feet per day)

PW-9-92 Lower Alluvium 1,250

PW-10L Lower Alluvium 490

Notes: 1 = Pump tests were not conducted at these wells. Therefore, these values were estimated from PW-4L, PW-5L, and PW-6L.

2.4.2 Hydraulic Conductivity Zones Used in Model As described in the following section, the final hydraulic conductivities used in the model will be calibrated to match the groundwater elevations measured during the full system start-up tests. The starting hydraulic conductivity values for calibration will be the values in Table 2. As with the 2011 model, the conductivity zones were delineated from the midpoint of the extraction wells. The conductivity zones for the Upper Alluvium and Lower Alluvium WBZs are shown on Figures 12 and 13, respectively. For the areas at or upland of the LNG basin, initial conductivity values of 70 feet per day and 400 feet per day will be used in the Upper Alluvium and Lower Alluvium WBZs, respectively, which are approximately the average values of the conductivities derived from the step tests for the respective units.

Page 19: Hydraulic Source Control and Containment System Groundwater

Hydraulic SC and Containment System GW Model Update Report July 2013 NW Natural Gasco Site 14 000029-02.26

3 MODEL CALIBRATION AND VALIDATION APPROACH This section describes the datasets used for model calibration and the overall approach that will be employed to calibrate and validate the model. Model calibration will be conducted in the fall of 2013 after completion of initial phase of the full system tests.

3.1 Calibration/Validation Datasets The primary dataset for calibration and validation will be groundwater elevations measured during the planned Phase 1 and Phase 2 system tests scheduled to begin in fall 2013. The data collection objectives, setup of the tests, and the period of testing are described in the Plan (Anchor QEA 2013). Phase 1 will include short-term tests that will evaluate ∆Hs of 0.1 feet and 0.15 feet; Phase 2 is being planned as long-term testing that will begin in January 2014 and continue through August 2014. The ∆H to be used in Phase 2 will be determined from the Phase 1 results. During the Phase 1 tests, the transducers in the monitoring wells, extraction wells, and piezometers will measure water levels at 15-minute intervals. The transducer recording interval for Phase 2 will be determined based on the Phase 1 results. The Phase 1 tests will provide the hydrology dataset during the dry season over a shorter period, while the Phase 2 test will provide a dataset that reflects seasonal changes and also the highest river stages likely to be encountered during the year. Combined, the two test phases will provide a robust dataset for calibrating and validating the model. In addition to the start-up tests, additional Site data may be used for constraining model parameters and testing model performance. For instance, conductance for the model cells representing the drain boundary may be refined based on the monthly extraction sump discharge records maintained for the LNG basin (HAI 2013).

3.2 General Approach The primary model calibration parameters will be the hydraulic conductivity values in the Fill and the Upper and Lower Alluvial WBZs. The hydraulic conductivities derived from the extraction well pump tests and step tests and listed in Table 2 will be used as starting values for the calibration. The calibration strategy is to use the water elevations measured during the first Phase 1 test to calibrate the model parameters (i.e., hydraulic conductivities, storage coefficients, drain boundary conductance, and recharge). Data from the second Phase 1 test (at ∆H of

Page 20: Hydraulic Source Control and Containment System Groundwater

Model Calibration and Validation Approach

Hydraulic SC and Containment System GW Model Update Report July 2013 NW Natural Gasco Site 15 000029-02.26

0.15 feet) will be used to validate the model by simulating the Phase 2 test without changing parameters that represent material properties (i.e., hydraulic conductivity and storage coefficient). The long-term dataset from the Phase 2 test will provide a second validation of the model. However, the model is anticipated to be applied to interpret the results of the Phase 1 tests and data collected prior to initiation of Phase 2 testing. Model simulations will be setup in transient mode to cover the period over which data are collected. The Willamette River stage specified in the model will correspond to the measurements from the testing period. Similarly, the pumping rates specified in the model will reflect those measured during the tests. Recharge will be reviewed to ensure that the recharge rates used are consistent with precipitation records during the testing period. Several lines of evidence will be applied to determine model calibration and validation. These will include the following:

• Groundwater elevation contour maps will be prepared for the Upper and Lower Alluvium WBZs

• Comparison of model predicted and observed groundwater elevation contour maps will be made for different time intervals during the test

• Point-by-point comparisons of hydrographs of predicted and observed groundwater elevations and drawdowns at multiple wells

• Probability distributions and cross-plots of predicted and observed elevations to determine bias in model predictions

• Comparison of predicted volume of water lost at the drain boundary to water volumes treated from the LNG Basin during the calibration period

• Statistical goodness-of-fit measures, such as sums of squared errors and correlation between predicted and observed water levels (R2)

The statistical measures and the comparisons described previously will provide an estimate of uncertainty in model predictions. The uncertainty in model predictions will be interpreted from the context of the accuracy needed for the intended model application of evaluating containment.

Page 21: Hydraulic Source Control and Containment System Groundwater

Model Calibration and Validation Approach

Hydraulic SC and Containment System GW Model Update Report July 2013 NW Natural Gasco Site 16 000029-02.26

3.3 Model Application The calibrated and validated model will be applied to evaluate containment at different ∆Hs through a particle tracking analysis. The model will be applied over different seasonal and tidal conditions to determine whether the selected ∆H values are sufficient to assure containment. In addition, the model predictions will also be used to assess vertical transport from the Lower Alluvial WBZ below the deep aquitard to the Upper Alluvial WBZ. Finally, the model results will be used to assess the adequacy and redundancy of the monitoring wells and would ultimately support the development of a long-term monitoring plan when the system is operational.

Page 22: Hydraulic Source Control and Containment System Groundwater

Hydraulic SC and Containment System GW Model Update Report July 2013 NW Natural Gasco Site 17 000029-02.26

4 REFERENCES Anchor Environmental, L.L.C. and SS Papadopulos Associates (Anchor and SSPA), 2008.

Groundwater Flow Model and DNAPL Evaluation Supplemental Report. NW Natural, Gasco Site. Prepared for NW Natural. October 2008.

Anchor QEA (Anchor QEA, LLC), 2009. Groundwater Source Control Interim Design Report. NW Natural Gasco Site. Prepared for NW Natural. November 2009.

Anchor QEA, 2011. Draft Groundwater Source Control Final Design Report. NW Natural Gasco Site. Prepared for NW Natural. May 2011.

Anchor QEA, 2012. Revised Groundwater Source Control Construction Design Report. NW Natural Gasco Site. Prepared for NW Natural. January 2012.

Anchor QEA, 2013a. NW Natural Gasco Site Groundwater Model Update Plan. Submitted to Oregon DEQ on February 15, 2013.

Anchor QEA, 2013b. Response to Comments from Oregon DEQ and U.S. EPA on NW Natural Gasco Site Groundwater Model Update Plan. HAI (Hahn and Associates, Inc.), 2006. Aquifer Test Data Evaluation Report. Revised Final. NW Natural Gasco Facility, 7900 NW St. Helens Road, Portland, Oregon. February 27, 2006.

HAI, 2007. Remedial Investigation Report. NW Natural “Gasco” Facility. Portland, Oregon. April 30, 2007.

HAI, 2013. Environmental Monitoring Report, First and Second Quarter 2012. NW Natural – Gasco Facility. May 7, 2013.

Morgan, D.S. and W.D. McFarland, 1996. Simulation Analysis of the Ground-Water Flow System in the Portland Basin, Oregon and Washington. U.S. Geological Survey Water Supply Paper 2470-B.

Page 23: Hydraulic Source Control and Containment System Groundwater

FIGURES

Page 24: Hydraulic Source Control and Containment System Groundwater

[

Q:\J

obs\

0000

29-0

2_G

asco

\Map

s\M

odel

ingU

pdat

eRep

ort\A

Q_G

W_m

odel

_dom

ain.

mxd

nko

chie

7/2

9/20

13 3

:27:

34 P

M

U.S. Moorings

NW Natural Gasco LNG P lant Siltronic

Corpora tion

McCormickand Bax ter

Willamette Cove Crawford Street

Fuel and Marine Marketing Lease Area

Groundwater Model Footprint

NOTES:1. LNG - Liquefied Natural Gas

Feet0 325 650 975 1,300

Figure 1 Groundwater Model Domain

Hydraulic Source Control and Containment System Groundwater Model Update ReportNW Natural Gasco Site

Page 25: Hydraulic Source Control and Containment System Groundwater

Jul 24, 201

3 9:46

am heriksen

K:\Projects\00

29-NW Natural Gas Co\Ga

sco So

urce Con

trols\Hy

drau

lic Con

trol\002

9-RP

-001

(GAS

CO XSEC MAP

).dwg F2

LEGEND: MW-2-12 Monitoring Well, Observation Well,

or Piezometer

PW-9L Extraction Well (U = Upper Alluvium, L = Lower Alluvium)

B-43 Sediment Sample or Soil Boring

TarGOST Boring

LW2-C276 Offshore Sediment Core

0 150

Scale in Feet

HORIZONTAL DATUM : Oregon State Plane North NAD 83 (International Feet).

VERTICAL DATUM: City of Portland

Figure 2 Monitoring Well and Cross Section Location Map

Hydraulic Source Control and Containment System Groundwater Model Update Report NW Natural Gasco Site

Page 26: Hydraulic Source Control and Containment System Groundwater

Jul 24, 201

3 9:47

am heriksen C:\U

sers\heriksen\ap

pdata\local\tem

p\Ac

Publish

_498

4\00

29-RP-00

2 (GAS

CO XSEC A,B).dwg Aa

Elevation in Fee

t (City of P

ortla

nd)

Segment 2

MW-2-32

50 GST-01 (16' S)

MW-25L (5' N)

MW-1-22 MW-1-55 MW-1-82 (44.6' S)

B-1 (26' S)

OW-10F PW-10L (17' N)

GST-02 (51' N)

MW-22-80 (31' N)

MW-22U (33' N) GST-03

(39' N)

MW-2-61 MW-2-104

(30' S) PW-9-92 OW-9-25

(19' N)

MW-23-27 MW-23U

MW-23-75 MW-23-123

(6' N)

GST-04 (17' N)

OW-8-15 OW-8-28 PW-8-39 PW-8-68

(11' N) 1

GT-11

50

25 (16' S) 25

0 0

-25 -25

* * -50 -50

-75 -75

-100 -100

-125 -125

-150 -150

-175

-200

Matchlin

e to Figure 3b

-200

-225

LEGEND: Aquitard - Primarily SILT and SANDY-SILT 0 50Potentiometric Surface of Surficial Fill MW-21-16 Boring IDinterbedded with thin sand and silty-sandFill WBZ - Fill composed of gravel, silt, sand, (measured June 3, 2009) (57' E)layers Offset Distance in Feet Scale in Feetmetal, brick, and concrete debris Potentiometric Surface of Surficial Fill

Existing Extractio

n Well

Existing Well o

r Piezometer Tar Interval

Primarily SILT and SANDY-SILT interbeddedUpper Alluvium WBZ - Primarily fine to (measured August 5, 2009) NOTE: Geologic contacts are inferred between borings.Oil or Mixed Oil and Tar Intervalwith thin sand and silty-sand layersmedium grained SAND and SILTY-SAND 1 Based on visual observations and analytical

Sheen Interval testing conducted by Hahn and Associates Potentiometric Surface of Alluvium

interbedded with thin silt and sandy-silt layers (measured August 5, 2009)Alluvial GRAVEL, sandy gravel, gravelly (Remedial Investigation Report, Hahn andWell Screen Associates, April 2007), the oil and sheen detectedsand, and gravelly silt Existing Ground SurfaceLower Alluvium WBZ - Primarily medium in the fill unit does not appear to be MGP-related,grained SAND with generally less than 5% fines. but appears to be associated with petroleum

Basalt BEDROCK * Control Well products stored in the FAMM storage tanks.

-175

Figure 3a Geologic Cross Section A-A'

Hydraulic Source Control and Containment System Groundwater Model Update Report NW Natural Gasco Site

Page 27: Hydraulic Source Control and Containment System Groundwater

-175

-200

-225

Jul 24, 201

3 9:47

am heriksen C:\U

sers\heriksen\ap

pdata\local\tem

p\Ac

Publish

_498

4\00

29-RP-00

2 (GAS

CO XSEC A,B).dwg Ab

TG-PW6-130 MW-4-35 (5' S) TG-PW14-100 MW-4-57 MW-17-79Segment 2 Segment 1(31' S) (Decommissioned)MW-16-45 GSM-07 MW-4-101 MW-38U

PW-6U MW-16-65 B-29 PW-14U TG-PW5-85 (1' S) (22.5' S)1 (15' N) (34' N) (31' S)MW-21-12 (5' S) MW-18-30 (17' S) (25' S) MW-30UPW-4LMW-21-75 MW-18-125 (27' S)B-1 B-59 B-53 PW-5U PW-13U MW-29U (16' S)MW-21-115 MW-18-180 PW-5L PW-1-80(26.5' N) (2' S) (4' N) (38' S) (30' S) (30' S)(36' S)MW-21-165 MW-24-70 (23' S) MW-27U (48' S)B-2 MW-28U(10' S) MW-24-130 MW-27LMW-21U TG-2 (7' N) MW-19-22(8' S) (17' S)B-57 MW-28L50 50GST-06 B-6(2' N) (55' S) MW-19-125PW-6L (46' S) B-5 OW-5F (30' S) PW-4UGST-05 OW-7-17 (12' N)(13' N) (4' S) B-58 MW-37U (31' S) TG-3 MW-19-180(14' N)MW-26U (17' S)B-8 (22' N) PW-7-93 TG-1 (31' S) (37' S)(20' S) (11' S)(18' S)(6' N) (11' S)(28' N)

25 25

00

-25-25

-50 -50*

-75-75 *

*

Elevation in Fee

t (City of P

ortla

nd)

-100 -100

-125 -125

-150 -150

Matchlin

e to Figure 3a

Matchlin

e to Figure 3c

LEGEND: Aquitard - Primarily SILT and SANDY-SILT 0 50 Potentiometric Surface of Surficial Fill MW-21-16 Boring IDinterbedded with thin sand and silty-sandFill WBZ - Fill composed of gravel, silt, sand, (measured June 3, 2009) (57' E) Offset Distance in Feet Scale in Feetlayersmetal, brick, and concrete debris Potentiometric Surface of Surficial Fill

Existing Extractio

n Well

Existing Well o

r Piezometer Tar Interval NOTE: Geologic contacts are inferred

Upper Alluvium WBZ - Primarily fine tomedium grained SAND and SILTY-SAND

Primarily SILT and SANDY-SILT interbedded (measured August 5, 2009)with thin sand and silty-sand layers Potentiometric Surface of Alluvium

between borings.Oil or Mixed Oil and Tar Interval Not used for geologic interpretation.Sheen Interval 1interbedded with thin silt and sandy-silt layers (measured August 5, 2009)Alluvial GRAVEL, sandy gravel, gravelly

Data from MW-18-125 used for geologic interpretation from groundWell Screen surface to -94 feet elevation. Datasand, and gravelly silt Existing Ground SurfaceLower Alluvium WBZ - Primarily medium from MW-18-180 used for geologic

grained SAND with generally less than 5% fines. interpretation from -94 to -198 feetBasalt BEDROCK Control Well* elevation.

-175

-200

-225

Figure 3b Geologic Cross Section A-A'

Hydraulic Source Control and Containment System Groundwater Model Update Report NW Natural Gasco Site

Page 28: Hydraulic Source Control and Containment System Groundwater

Jul 24, 201

3 9:47

am heriksen C:\U

sers\heriksen\ap

pdata\local\tem

p\Ac

Publish

_498

4\00

29-RP-00

2 (GAS

CO XSEC A,B).dwg Ac

MW-5-32 WS-25-96MW-5-100 Segment 1 WS-22-112 WS-26-86 Segment 3MW-20-120 MW-33U GP-99 WS-23-116 P-42 WS-25-111 OW-1-FMW-31U MW-5-175 (12' S) (19' N) (86' S) (26' N) PW-2U (31' N) (29' S) WS-26-116(4' S)MW-31L TG-10 TG-PW3-140 PW-11U TG-12S (25' N) (14' S) WS-12-125 WS-8-33GP-6MW-36U(14' N) (14' N) OW-2-F(13' S) (12' S) (24.5' N) (24' S) WS-12-161 WS-8-59B-7 (24' N) (27' N) PW-1U PW-1L (12.5' N) (19' N) A'(33' N) WS-14-125 GP-4 WS-20-112PW-3-118 PW-3U (28' S) (5' N) (5' N)(13' S) GST-09 P-2PZ-PW3 (41' S) WS-14-161 TG-PW2-130 (37' N) WS-11-125/161 GST-11 SIL-01PW-12U (Decommissioned) (24' N) (26' N)(13.5' N) (23' N) P-3TG-1S 50TG-5 WS-21-112(14' S) (40' N) (17' N)TG-7S(59' S) PW-3-85 (15' S) (15' N)GP-7MW-35U PW-2L (44' N) WS-21-131MW-34U (6' N) (25' N)(25' N) (11' S)MW-32U (16' N)GSM-08 MW-34LB-4B(14' S)(67' N) (11' S)(23' N) 25

0

-25

* -50

* -75 **

-100

-125

-150

-175

-200

-225

LEGEND: Aquitard - Primarily SILT and SANDY-SILT 0 50 Potentiometric Surface of Surficial Fill MW-21-16 Boring IDinterbedded with thin sand and silty-sandFill WBZ - Fill composed of gravel, silt, sand, (measured June 3, 2009) (57' E) Scale in FeetOffset Distance in Feetlayersmetal, brick, and concrete debris Potentiometric Surface of Surficial Fill

Existing Extractio

n Well

Existing Well o

r Piezometer Tar Interval

Primarily SILT and SANDY-SILT interbedded (measured August 5, 2009)Upper Alluvium WBZ - Primarily fine to Oil or Mixed Oil and Tar Intervalwith thin sand and silty-sand layersmedium grained SAND and SILTY-SAND Potentiometric Surface of Alluvium Sheen Intervalinterbedded with thin silt and sandy-silt layers (measured August 5, 2009)Alluvial GRAVEL, sandy gravel, gravelly NOTE: Geologic contacts are inferredWell Screen Lower Alluvium WBZ - Primarily medium sand, and gravelly silt Existing Ground Surface between borings.

Not used for geologic interpretation.grained SAND with generally less than 5% fines. Basalt BEDROCK Control Well*

Figure 3c Geologic Cross Section A-A'

Hydraulic Source Control and Containment System Groundwater Model Update Report NW Natural Gasco Site

Page 29: Hydraulic Source Control and Containment System Groundwater

Ele

vatio

n in

feet

(C

ity o

f Por

tland

)

50

0

Ordinary High Water Level

PW-8-39

-50

PW-10L

PW-9-92

PW-8-68

PW-7-93

PW-6U

PW-11U

PW-6L

-100 Fill

Upper Alluviual Silt

-150 Upper Alluvium

Lower Alluvium

-200

Deep Aquitard

Extraction Well (Layer thickness selected to match the screened interval)

0 500 1000 1500 2000 Distance from U.S. Moorings Boundary (feet)

2500 3000

Figure 4 Stratigraphic Units Represented in Model Row 59, Approximately Comparable to Cross-Section A-A’

Hydraulic Source Control and Contaiment System Groundwater Model Update Report NW Natural Gasco Site

PM - C:\AQ\Jobs\Portland_Harbor\GASCO\Model\Inputs\Preprocessors\plot_cross_section.pro Mon Jul 29 20:59:23 2013

Page 30: Hydraulic Source Control and Containment System Groundwater

Jul 24, 201

3 9:47

am heriksen C:\U

sers\heriksen\ap

pdata\local\tem

p\Ac

Publish

_498

4\00

29-RP-00

2 (GAS

CO XSEC A,B).dwg B

Elevation in Fee

t (City of P

ortla

nd)

B

25

50

TG-6 (16' W)

GT-2 (24' W)

GT-1

MW-21-12 MW-21U

MW-21-75 MW-21-116 MW-21-165

(103' E) 1

OW-8-15 PW-8-68

(27' E)

Tank Basin Wall

OW-8-28 (40' E)

1

1

PZ5-5 PZ5-20 PZ5-55 PZ5-85 (50' E)

GS-04 (54' W)

Gravel Road

PZ1-5 PZ1-20 PZ1-50 (33' W)

Proposed Interceptor Trench

PW-8-39 (31' E)

1

1

PZ2-5 PZ2-20 PZ2-43 PZ2-77 (17' E) WILLAMETTE RIVER

B'

25

50

0 PZ3-33 (Inactive)

-25 -25

-50 -50

-75 -75

-100 -100

-125 -125

-150 -150

Basalt BEDROCK -175 -175

LEGEND: Aquitard - Primarily SILT and SANDY-SILT 0 50Existing Ground Surface TG-6 Boring IDinterbedded with thin sand and silty-sandFill WBZ - Fill composed of gravel, silt, sand, (16' W)layers Offset Distance in Feet Scale in Feetmetal, brick, and concrete debris Approximate Willamette

Existing Extractio

n Well

Existing Well o

r Piezometer Tar IntervalRiver Elevation

Primarily SILT and SANDY-SILT interbeddedUpper Alluvium WBZ - Primarily fine to Oil or Mixed Oil and Tar Intervalwith thin sand and silty-sand layers NOTE: Geologic contacts are inferred betweenmedium grained SAND and SILTY-SANDinterbedded with thin silt and sandy-silt layers Sheen Interval borings.

Alluvial GRAVEL, sandy gravel, gravelly1 Based on visual observations and analytical

Well Screen testing conducted by Hahn and Associatessand, and gravelly siltLower Alluvium WBZ - Primarily medium (Remedial Investigation Report, Hahn and Associates, April 2007), the oil and sheen detectedgrained SAND with generally less than 5% fines.

Basalt BEDROCK in the fill unit does not appear to be MGP-related, but appears to be associated with petroleum products stored in the FAMM storage tanks.

Figure 5 Geologic Cross Section B-B'

Hydraulic Source Control and Containment System Groundwater Model Update Report NW Natural Gasco Site

Page 31: Hydraulic Source Control and Containment System Groundwater

1300 1200 1100 1000 900Distance to Outer Edge of Willamette River Boundary in Model (feet)

-150

-100

-50

0

50E

leva

tion

in fe

et (C

ity o

f Por

tland

)

Ordinary High Water Level

PW-8-39

PW-8-68

Fill Upper Alluviual Silt Upper Alluvium Lower Alluvium Deep Aquitard

Extraction Well (Layer thickness selected to match the screened interval)

Figure 6Stratigraphic Units Represented in Model Column 75, Approximately Comparable to Cross-Section B-B’

Hydraulic Source Control and Contaiment System Groundwater Model Update ReportNW Natural Gasco Site

PM - C:\AQ\Jobs\Portland_Harbor\GASCO\Model\Inputs\Preprocessors\plot_cross_section.pro Mon Jul 29 20:59:23 2013

Page 32: Hydraulic Source Control and Containment System Groundwater

Jul 24, 201

3 10

:40a

m heriksen

C:\U

sers\heriksen\ap

pdata\local\tem

p\Ac

Publish

_498

4\00

29-RP-00

3 (GAS

CO XSEC C,F).dwg C

0 50

Scale in Feet

LEGEND: Aquitard - Primarily SILT and SANDY-SILT NOTES:interbedded with thin sand and silty-sand Existing Ground Surface GS-06 Boring IDFill WBZ - Fill composed of gravel, silt, sand, 1. Geologic contacts are inferred between

layers (54' W) Offset Distance in Feetmetal, brick, and concrete debris borings.Approximate Willamette River 2. Tar interval in SD-7 is approximately 3Tar Interval feet higher in elevation than shown on

Soil Bo

ring or Sed

imen

t Core

Existing Extractio

n Well

Existing Well o

r Piezometer

Primarily SILT and SANDY-SILT interbedded Elevationwith thin sand and silty-sand layers

Upper Alluvium WBZ - Primarily fine tomedium grained SAND and SILTY-SAND Oil or Mixed Oil and Tar Interval cross section.

3. MW-18-125 used for geologic interbedded with thin silt and sandy-silt layers interpretation from ground surface toSheen Interval

-94 feet elevation. MW-18-180 used for Well Screen geologic interpretation from -94 to -198

Alluvial GRAVEL, sandy gravel, gravellysand, and gravelly siltLower Alluvium WBZ - Primarily medium feet elevation.

grained SAND with generally less than 5% fines. Not used for geologic interpretation.Basalt BEDROCK

Figure 7 Geologic Cross Section C-C'

Hydraulic Source Control and Containment System Groundwater Model Update Report NW Natural Gasco Site

Page 33: Hydraulic Source Control and Containment System Groundwater

Ele

vatio

n in

feet

(C

ity o

f Por

tland

)

50

Ordinary High Water Level

0

PW-6U

-50

PW-6L

-100

-150

-200

-250 1200 1100 1000 900 800 700

Distance to Outer Edge of Willamette River Boundary in Model (feet) Fill Upper Alluviual Silt Upper Alluvium Lower Alluvium Deep Aquitard

Extraction Well (Layer thickness selected to match the screened interval)

Figure 8 Stratigraphic Units Represented in Model Column 93, Approximately Comparable to Cross-Section C-C’

Hydraulic Source Control and Contaiment System Groundwater Model Update Report NW Natural Gasco Site

PM - C:\AQ\Jobs\Portland_Harbor\GASCO\Model\Inputs\Preprocessors\plot_cross_section.pro Mon Jul 29 20:59:23 2013

Page 34: Hydraulic Source Control and Containment System Groundwater

Jul 24, 201

3 10

:40a

m heriksen C:\U

sers\heriksen\ap

pdata\local\tem

p\Ac

Publish

_498

4\00

29-RP-00

3 (GAS

CO XSEC C,F).dwg Fa

50

25

0

-25

-50

-75

-100

-125

-150

-175

-200

-225

0 50

Matchlin

e to Figure 9b

LEGEND: Aquitard - Primarily SILT and SANDY-SILT GS-06 Boring IDinterbedded with thin sand and silty-sand Existing Ground SurfaceFill WBZ - Fill composed of gravel, silt, sand, (54' W) Offset Distance in Feet Scale in Feetlayersmetal, brick, and concrete debris Approximate Willamette

Soil Bo

ring or Sed

imen

t Core

Existing Extractio

n Well

Existing Well o

r Piezometer Tar Interval

Primarily SILT and SANDY-SILT interbedded River ElevationUpper Alluvium WBZ - Primarily fine to Oil or Mixed Oil and Tar Interval NOTES:with thin sand and silty-sand layersmedium grained SAND and SILTY-SAND 1. Geologic contacts are inferredSheen Intervalinterbedded with thin silt and sandy-silt layers between borings.Alluvial GRAVEL, sandy gravel, gravelly 2. PW-3-85 was initially intendedWell Screensand, and gravelly silt as an extraction well, but it hasLower Alluvium WBZ - Primarily medium

been replaced by PW-3U.grained SAND with generally less than 5% fines. Basalt BEDROCK

Figure 9a Geologic Cross Section F-F'

Hydraulic Source Control and Containment System Groundwater Model Update Report NW Natural Gasco Site

Page 35: Hydraulic Source Control and Containment System Groundwater

Jul 24, 201

3 10

:40a

m heriksen C:\U

sers\heriksen\ap

pdata\local\tem

p\Ac

Publish

_498

4\00

29-RP-00

3 (GAS

CO XSEC C,F).dwg Fb

Elevation in Fee

t (City of P

ortla

nd)

50

25

0

-25

-50

-75

-100

-125

-150

-175

-200

-225 Matchlin

e to Figure 9a

0 50LEGEND: Aquitard - Primarily SILT and SANDY-SILT interbedded with thin sand and silty-sand Existing Ground Surface Scale in FeetFill WBZ - Fill composed of gravel, silt, sand, GS-06 Boring IDlayersmetal, brick, and concrete debris (54' W) Offset Distance in FeetApproximate Willamette NOTES:

1. Geologic contacts are inferredPrimarily SILT and SANDY-SILT interbedded River Elevation

Soil Bo

ring or Sed

imen

t Core

Existing Extractio

n Well

Existing Well o

r PiezometerUpper Alluvium WBZ - Primarily fine to

medium grained SAND and SILTY-SANDTar Interval between borings.

with thin sand and silty-sand layers 2. PW-3-85 was initially intended as an extraction well, but it has beenOil or Mixed Oil and Tar Interval

interbedded with thin silt and sandy-silt layersAlluvial GRAVEL, sandy gravel, gravelly replaced by PW-3U.Sheen Interval 3. Data from PZ-PW3 used forsand, and gravelly siltLower Alluvium WBZ - Primarily medium Well Screen geologic interpretation from ground

surface to -30 feet elevation, andgrained SAND with generally less than 5% fines. Basalt BEDROCK from MW-5-175 from -30 feet to -150

feet elevation.

Figure 9b Geologic Cross Section F-F'

Hydraulic Source Control and Containment System Groundwater Model Update Report NW Natural Gasco Site

Page 36: Hydraulic Source Control and Containment System Groundwater

Ele

vatio

n in

feet

(C

ity o

f Por

tland

)

50

Ordinary High Water Level

0

PW-3U

-50

-100

-150

-200

1800 1600 1400 1200 1000 800 Distance to Outer Edge of Willamette River Boundary in Model (feet)

Fill Upper Alluviual Silt Upper Alluvium Lower Alluvium Deep Aquitard

Extraction Well (Layer thickness selected to match the screened interval)

Figure 10 Stratigraphic Units Represented in Model Column 119, Approximately Comparable to Cross-Section F-F’

Hydraulic Source Control and Contaiment System Groundwater Model Update Report NW Natural Gasco Site

PM - C:\AQ\Jobs\Portland_Harbor\GASCO\Model\Inputs\Preprocessors\plot_cross_section.pro Mon Jul 29 20:59:23 2013

Page 37: Hydraulic Source Control and Containment System Groundwater

Willamette Cove

Crawford Street

[

Q:\J

obs\

0000

29-0

2_G

asco

\Map

s\M

odel

ingU

pdat

eRep

ort\A

Q_G

W_m

odel

_bou

ndar

y_co

nditi

ons.

mxd

nko

chie

7/2

9/20

13 3

:29:

16 P

M

U.S. Moorings

NW Natural Gasco LNG P lant Siltronic

Corpora tion

Fuel and Marine Marketing Lease Area

Boundary Conditions Constant Head

Drain

No flow

Groundwater Model Footprint

NOTES:1. LNG - Liquefied Natural Gas 2. See Figure 4 for location of wells.

Feet0 250 500 750 1,000

Figure 11 Model Boundary Conditions

Hydraulic Source Control and Containment System Groundwater Model Update ReportNW Natural Gasco Site

Page 38: Hydraulic Source Control and Containment System Groundwater

T( T(T(

T( T(T( T(

T(T(

T(

T(

NW Natural GascoLNG Plant

K =25 ft/d

K =80 ft/d

K = 70 ft/d

Willamette River

K =25 ft/d K = 100 ft/d K = 200 ft/dK = 2 ft/d

K =10 ft/dK = 115 ft/d K = 40 ft/d

K =170 ft/d

K =15 ft/d

PW-8-39 PW-6U PW-14U PW-5U PW-13U PW-4U PW-12U PW-3U PW-11U

PW-2UPW-1U

Upper Alluvium Zones2 (PW-8-39)3 (PW-6U)4 (PW-14U)5 (PW-5U)6 (PW-13U)7 (PW-4U)

8 (PW-12U)9 (PW-3U)10 (PW-11U)11 (PW-2U)12 (PW-1U)13 (Upland)

T( Extraction Well

Q:\J

obs\

0000

29-0

2_G

asco

\Map

s\M

odel

ingU

pdat

eRep

ort\A

Q_G

W_m

odel

_Upp

erA

lluvi

um.m

xd n

koch

ie 7

/29/

2013

3:3

0:07

PM

0 65 130 195 260Feet

[

NOTE:1. LNG - Liquefied Natural Gas

Figure 12Initial Horizontal Hydraulic Conductivity Values Specified for the Upper Alluvial Water Bearing Zone

Hydraulic Source Control and Containment System Groundwater Model Update ReportNW Natural Gasco Site

Page 39: Hydraulic Source Control and Containment System Groundwater

T( T( T( T( T(

T(

T( T(

T(T(

NW Natural GascoLNG Plant

Willamette River

K = 260 ft/d K = 100 ft/dK = 490 ft/d K = 1250 ft/d K = 400 ft/d K = 190 ft/dK = 370 ft/d K = 380 ft/dK = 400 ft/d K = 400 ft/d

K = 400 ft/d

PW-10L PW-9-92 PW-8-68* PW-7-93* PW-6LPW-5L

PW-4L PW-3-118PW-2L PW-1L

Lower Alluvium Zones14 (PW-10L)15 (PW-9-92)16 (PW-8-68*)

18 (PW-6L) 24 (Upland)

Q:\J

obs\

0000

29

NOTES:* Values estimated based on conductivity values for PW-4L, PW-5L and PW-6L

ied Natural Gas1. LNG - Liquef

-02_

Gas

co\M

I

17 (PW-7-93*)

19 (PW-5L)20 (PW-4L)21 (PW-3-118)22 (PW-2L)23 (PW-1L)

T( Extraction Well

aps\

Mod

elin

gUpd

ateR

epor

t\AQ

_GW

_mod

el_L

ower

Allu

vium

.mxd

nko

chie

7/2

9/20

13 3

:26:

14 P

M

0 75 150 225 300Feet

[

Figure 13nitial Horizontal Hydraulic Conductivity Values Specified for the Lower Alluvial Water Bearing Zone

Hydraulic Source Control and Containment System Groundwater Model Update ReportNW Natural Gasco Site

K = ft/d

K = ft/d