hvdc grids abb growth boards · 2018. 5. 10. · 125 km subsea and 75 km underground power...
TRANSCRIPT
![Page 1: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/1.jpg)
© ABB Group October 28, 2010 | Slide 1
HVDC Grids for Integration of Renewable Power Sources EPRI’s HVDC & FACTS Conf. Oct. 28 - 29, 2010, Palo Alto, CA
Magnus Callavik, ABB Grid Systems / HVDC
![Page 2: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/2.jpg)
© ABB Group October 28, 2010 | Slide 2
Outline
HVDC Light technologies
Renewable applications
Multi-terminal HVDC and DC-grids
![Page 3: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/3.jpg)
© ABB Group October 28, 2010 | Slide 3
Core HVDC technologies from ABB
AC DC
HVDCHVDC
Indoor
Outdoor
IGBT ValvesIGBT Valves
AC
HVDCHVDC
DC
--VSCVSC--VSCVSC
Indoor
Outdoor
IGBT ValvesIGBT Valves
HVDC Classic operation experience from 1954 Current source converters Line-commutated thyristor valves Requires 50% reactive compensation (35% HF) Converter transformers Minimum short circuit capacity > 2x converter rating, > 1.3x with capacitor commutated converter (CCC)
HVDC Light operation experience from 1999 Voltage source converters (VSC) Cascaded two level converters Self-commutated IGBT valves Requires no reactive power compensation (~0-15% HF as required) Virtual generator at receiving end: P,Q Standard transformers Weak system, black start Radial wind outlet regardless of type of wind T-G, off-shore or isolated U/G or OVHD
Indoor
Outdoor
Thyristor ValvesThyristor Valves
Indoor
Outdoor
Thyristor ValvesThyristor Valves
AC DC
HVDCHVDC--CSCCSC
AC FiltersAC Filters
DC FiltersDC FiltersConverter Converter
TransformersTransformers
AC DC
--
AC FiltersAC Filters
DC FiltersDC FiltersConverter Converter
TransformersTransformers
AC Filter (if needed)
![Page 4: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/4.jpg)
© ABB Group October 28, 2010 | Slide 4
HVDC by ABB Let our experience work for you
56 HVDC Classic Projects since 195414 HVDC Classic Upgrades since 199114 HVDC Light Projects since 1997
TrollNelson River 2
CU-project
Vancouver Island Pole 1
Pacific Intertie
Pacific Intertie Upgrading
Pacific Intertie ExpansionIntermountain
Blackwater
Rio Madeira
Inga-Shaba
Brazil-Argentina Interconnection I&II
English ChannelDürnrohrSardinia-Italy
Highgate
Châteauguay
Quebec- New England
Skagerrak 1-3
Konti-Skan Baltic Cable
FennoSkan 1&2
Kontek
SwePol
ChaPad
Rihand-Delhi
Vindhyachal
SakumaGezhouba-Shanghai
Three Gorges-Shanghai
Leyte-LuzonBroken Hill
New Zealand 1&2
Gotland Light
Gotland 1-3
Murraylink
Eagle Pass
Tjæreborg
Hällsjön
Directlink
Cross Sound
Italy-GreeceRapid City
Vizag II
Three Gorges-Guandong
Estlink
Valhall
Cahora Bassa
SapeiSquare Butte
Sharyland
Three Gorges-Changzhou
Outaouais
Caprivi Link
Hülünbeir- Liaoning
Lingbao II Extension
Xiangjiaba-Shanghai
BorWin1
NorNed
Apollo Upgrade
EWIP
IPP Upgrade
Itaipu
DolWin1
![Page 5: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/5.jpg)
© ABB Group October 28, 2010 | Slide 6
HVDC Light Generation 4: Evolution since 1997 Maintained functionality, availability and reliability
Reduce losses Increase capacity
Compactness 150 x 100 m 320 kV, 1000 MW
Gen. 1
Gen. 2
Gen. 3
Gen. 4
HVDC Classic
HVDC Light
0,0%
0,5%
1,0%
1,5%
2,0%
2,5%
3,0%
3,5%
1995 2000 2005 2010 20150
200
400
600
800
1000
1200
1400
MW
Gen. 1
Gen. 2
Gen. 3
Gen. 4
Losses
Capacity
Recent : Dolwin 1 800 MW, 320 kV 2 x 165 km cable system
![Page 6: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/6.jpg)
© ABB Group October 28, 2010 | Slide 7
HVDC Light Generation 4 Features
Excellent controllability Active Power control AC-voltage Control Reactive Power Control Black start Fast recovery after AC network faults Frequency control Emergency power control ……..
Compact foot-print Low losses, approximately 1 % per
converter Short delivery time
![Page 7: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/7.jpg)
© ABB Group October 28, 2010 | Slide 8
150 m220 m
HVDC Light Generation 4 Station layout 2 x 1000 MW 320 kV
![Page 8: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/8.jpg)
© ABB Group October 28, 2010 | Slide 9
HVDC Light Gen 4: Low Losses, No Filters Required Cascaded Two-Level Converter (CTLC)
CTL converter voltage Two-level converter voltage
1 Cell
+ Ud
- Ud
![Page 9: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/9.jpg)
© ABB Group October 28, 2010 | Slide 10
HVDC Light Generation 4. Converter Valve Design Cell Main Components: IGBT:s and Capacitors
Double Cell
1
2
35
36
+
- 1- 8
1- 8
1- 8
1- 8
2.2 x 2.0 x 1.6 m3000 kg
![Page 10: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/10.jpg)
© ABB Group October 28, 2010 | Slide 11
HVDC Light Generation 4 Press pack semiconductor concept – the only way
Semiconductors tailor made for transmission applications: safety, quality, operation mode
Safe short circuit failure mode – i.e. required for safe operation of VSC for continued operation after failure of IGBT.
Integrated Press Pack diodes that withstand pole-to-pole Short circuit.
No risk for explosion or electrical arcing at failure.
No need for auxiliary equipment or mechanisms.
![Page 11: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/11.jpg)
© ABB Group October 28, 2010 | Slide 12
Key Renewable Energy Alternatives Located at remote locations and off-shore
Hydro Wind Solar
Increase the use of renewable energy:
Reduce our CO2 emissions
Reduce our dependence on fossil energy
Hugh drivers for new transmission!
![Page 12: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/12.jpg)
© ABB Group October 28, 2010 | Slide 13
Hydropower resources of about 500 GW available Transmission distance 2,000-3,000 kilometers
120 GW
50 GW
50 GW300 GW
![Page 13: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/13.jpg)
© ABB Group October 28, 2010 | Slide 14
Customer’s need Optimize the production system in
Northern Europe
Combine production systems in Scandinavia and northern Europe with 580 km long submarine HVDC cable with 700 MW rating
Benefits Increased security of supply in both
markets
Sharing of balancing power
Improved power market
Emissions reduced by 1.7 million tons/year
Data 450 kV, 700 MW, 2x580-km cable system
Low losses 3.7%
NorNed Example The world’s longest underwater cable
Customer: Statnett and TenneT
Year of commissioning: 2008
![Page 14: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/14.jpg)
© ABB Group October 28, 2010 | Slide 15
Global cumulative wind power capacity 1990-2007 (MW)
EWEA’s 20 year offshore network development plan North Sea Grid
Source: EWEA (European Wind Energy Association) 2009. 2030 EWEA Offshore grid vision
140 GW Global Wind Installed 2009. Growth 2009 + 40 GW
![Page 15: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/15.jpg)
© ABB Group October 28, 2010 | Slide 16
Wind power projects in the North Sea For connection in Germany
1
3 4
5
678
9 10
18
17
16
15
14
1211
192221
20
24
25
23
26
Borkum1st row
Helgolan d
2nd row
Helgoland1st row
2
13
27 28
31
32
33 34
30
35
?
?
OWP in VergabeOWP und Trasse gen.OWP genehmigtOWP beantragtOWP-Projekt ruht
OWP vergeben
29
Borkum2nd row
1 ALPHA VENTUS / DOTI 2 Amrumbank West3 Austerngrund4 Bard Offshore I5 Borkum Riffgat6 Borkum Riffgrund I7 Borkum Riffgrund II8 Borkum Riffgrund West I9 Borkum Riffgrund West II
10 Borkum West II11 Butendiek
12 Dan-Tysk13 Deutsche Bucht14 ENOVA North Sea Windpower III15 GlobalTech I16 Gode Wind17 Godewind II18 Hochsee Windpark Nordsee19 Hochsee WP "He dreiht„20 Hochsee Testfeld Helgoland21 Meerwind Ost22 Meerwind Süd23 MEG Offshore I24 Nordergründe25 Nördlicher Grund26 Nordsee-Ost (Amrumbank)27 OWP Delta Nordsee28 OWP Delta Nordsee II29 OWP West30 Sandbank 2431 Sandbank 24 Erw.32 Uthland33 Ventotec Nord 134 Ventotec Nord 235 Weiße Bank
Total of 39 GW off-shore wind planned in UK waters only triggers £15 B in grid investment
![Page 16: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/16.jpg)
© ABB Group October 28, 2010 | Slide 17
BorWin1, offshore wind in Germany The world’s largest offshore wind park in operation
Customer’s need 125 km subsea and 75 km underground
power connection operational in 24 months
Robust grid connection
ABB’s response Turnkey 400 MW HVDC Light system
Customer’s benefits Environmentally friendly power transport
Reduce CO2 emissions by 1.5 million tons per year by replacing fossil-fuels
Supports German wind power development
Customer: transpower Year of commissioning: 2010
![Page 17: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/17.jpg)
© ABB Group October 28, 2010 | Slide 18
DolWin1 Offshore Wind Power Connector 800 MW, ±320 kV DC
165 km long subsea and underground power connection to offshore wind farm
Robust grid connection
Turnkey 800 MW HVDC Light system
First ± 320 kV extruded cable delivery
Invisible, sustainable transmission
Low losses and high reliability
Reduce CO2 emissions by 3 million tons per year replacing fossil-fuel generation
Supports German wind power
14th HVDC Light project, 4th with wind, 4th offshore, proven black start
Customer: transpower Year of commissioning: 2013
![Page 18: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/18.jpg)
© ABB Group October 28, 2010 | Slide 19
Solar energy from deserts 90 percent of people live within 2,700 km of a desert
Source: DESERTEC 2008
Surface of Sahara9 million km2
Area needed to produce all
European electricity18 000 km2
Area needed for all world energy 650 000 km2
![Page 19: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/19.jpg)
© ABB Group October 28, 2010 | Slide 20
Hydro power
Solar power
Wind power
DC transmission
99LFC0825
Wind300 GW
25 000 km sq5000 x 10 km
Hydro200 GW
Europe 20XX Scenario ABB’s DC grid vision already in the 1990’s
Solar700 GW
8000 km sq90 x 90 km
Cables (Solar)140 pairs of5 GW and
3000 km each
![Page 20: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/20.jpg)
© ABB Group October 28, 2010 | Slide 21
Key wind locations
Regulating hydro
Large scale PV
Copyright Power Circle
Why do we need a stronger grid? 35% Renewable Wind & Solar integrated by a Pan-European Super Grid and supported by distributed demand side participation
![Page 21: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/21.jpg)
© ABB Group October 28, 2010 | Slide 22
Statnett
DC Grids are popular in the public debate Supergrid initiatives are competing for attention
wind-energy-the-facts.org mainstreamrp.com pepei.pennnet.com
Statnett
wikipedia/desertec
claverton-energy.com
Desertec-australia.org
![Page 22: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/22.jpg)
© ABB Group October 28, 2010 | Slide 23
USA: Examples of proposed new power lines & renewable energy resources
Source: NREL, G Washington University, N.Y. Times
Off-shore wind
On-shore wind
Solar
![Page 23: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/23.jpg)
© ABB Group October 28, 2010 | Slide 24
Why DC Grids?
Significant loss reduction
Increased power capacity per line/cable vs. AC
Stabilized AC & DC grid operation
Less visual impact and lower electromagnetic fields
Easier acceptance of new DC projects if lines can be tapped
DC = only solution for subsea connections > 60 km
Connection of asynchronous AC Networks
Circumvent right of way limitations
Technology required for visions like Desertec & North Sea Offshore Grid
![Page 24: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/24.jpg)
© ABB Group October 28, 2010 | Slide 25
What is a DC grid?
A DC electricity grid that can operate:
Independent of one or several disturbances (isolate a failure)
In different operation modes in the connected AC- & DC-systems
Technology gaps for the full realization includes:
DC breaker
Power flow control
Automatic network restoration
High voltage DC/DC converters
Global rules/regulations for operation required for market acceptance
![Page 25: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/25.jpg)
© ABB Group October 28, 2010 | Slide 26
DC grids- Where do we stand today
Vision: A system that that can operate independent of one or several disturbances
Available (HQ delivery in the 90s): 3-node multi-terminal DC grid that goes out of operation when disturbed, i.e. one protection zone
![Page 26: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/26.jpg)
© ABB Group October 28, 2010 | Slide 27
DC Grid Advantages: Reduce number of AC/DC converters in a grid with high penetration of HVDC
Point-to-point HVDC transmission Today: Scattered point-to-point connections Future: HVDC-point-to-point covering whole regions
HVDC Grid example: only ¼ converter stations needed
![Page 27: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/27.jpg)
© ABB Group October 28, 2010 | Slide 28
HVDC evolution towards a DC grid
Connection of asynchronous AC
Networks
Point-2-Point Power in-feed Tapping DC-grid
Tapping-off from long-distance DC-
transmissions
Strengthening the combined
AC and DC grid
Redundancy
Connection of remote
renewables
![Page 28: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/28.jpg)
© ABB Group October 28, 2010 | Slide 29
Existing palette to gain experience from Some examples
The multi-terminal Québec - New England transmission link (three terminals), in service since 1992
The worlds longest subsea cable in the 700 MW NorNed transmission project, in service since 2008
The 400 MW BorWin1 offshore wind HVDC Light connection
The 500 MW East West Interconnector transmission link, in operation 2012
Several multi-terminal HVDC transmission systems currently in development phase
![Page 29: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/29.jpg)
© ABB Group October 28, 2010 | Slide 30
Examples of Installed HVDC Breaker Technologies
Passive Resonance Breaker Arc negative resistance causes
current oscillations over the capacitor, resulting in current zero crossings
Classic HVDC dc-neutral switchyards
Speed and voltage rating to be improved for grid applications
Semiconductor Breaker Very fast interruption < 1ms
On-state losses a drawback
10 kV pilot in Hällsjön, Sweden
![Page 30: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/30.jpg)
© ABB Group October 28, 2010 | Slide 31
Summary
HVDC Light technology is mature and available for renewable connections
Regional DC grids with one protection zone can be built today – no technology gaps to be solved
Interregional DC grids will be built in the near future. Technology gaps are worked on
Regulatory issues such as how to manage such new grids need to be solved
HVDC Light Generation 4 Artists view
BorWin1 Off-shore platform
![Page 31: HVDC Grids ABB Growth Boards · 2018. 5. 10. · 125 km subsea and 75 km underground power connection operational in 24 months Robust grid connection ABB’s response Turnkey 400](https://reader036.vdocuments.site/reader036/viewer/2022071006/5fc403e4961dc86b0f2c43f5/html5/thumbnails/31.jpg)
© ABB Group October 28, 2010 | Slide 32