ht line est for 2012-13
DESCRIPTION
HT Line Est for 2012-13TRANSCRIPT
![Page 1: HT Line Est for 2012-13](https://reader035.vdocuments.site/reader035/viewer/2022080222/563db921550346aa9a9a554a/html5/thumbnails/1.jpg)
Quantity Description Rate Per Amount
18 7.5 M RCC pole 2,401 E 43218
18 Base Plates 91 E 1638
21 Back Clamps 73 E 1533
21 LT 3 phase cross arms (Angle) 592 E 12432
54 LT pin insulator with pin (11+32) 43 E 2322
4 Earthing device 1682 E 6728
21 Aluminium knobs 21 Set 441
18 LT shackle with hardware (10+33) 43 E 774
6 Stay set complete 866 Set 5196
6 Guy insulators 13 Set 78
4.08 7/2.59 mm ACSR 21,480 E 87638
2 Concreting 783 Loc 1566
4 Earthing (Coil) 910 Loc 3640
Cost of materials 167204
Contingencies 1% 1672
168876
Labour as per Statement A (II) 19460
Transport as per Statement B (3321+942) 4263
192599
Estt. & Supervision charges 15% 28890
Total 221489
Or Say Rs. 221490
NB CONTINGENCIES & STORAGE
For Deposit Contributary Works (DCW), Contingencies may be worked out @ 5%
& storage worked out @ 3% may be included.
WITH 7/2.59 MM ACSR FOR PHASEAND NEUTRAL ,140KG W.L. & 75 KG/Sq.M W.P.
44
D.2. EXTENSION OF 1 KM. OF LT 3 PHASE 4 WIRE LINE AT 60 M SPAN ON 7.5M RCC POLES,