HP 3PAR StoreServ 7000 Series StorageCabling Configuration Guide B:Two Node System with M6720 Enclosures
AbstractThis guide provides information about connecting data cables for authorized technicians performing installation and maintenanceservices on HP 3PAR StoreServ 7000 Series Storage systems.
HP Part Number: QR482-96796Published: August 2014
© Copyright 2014 Hewlett-Packard Development Company, L.P.
The information contained herein is subject to change without notice. The only warranties for HP products and services are set forth in the expresswarranty statements accompanying such products and services. Nothing herein should be construed as constituting an additional warranty. HP shallnot be liable for technical or editorial errors or omissions contained herein.
Acknowledgments
Microsoft®, Windows®, are U.S. registered trademarks of Microsoft Corporation.
Warranty
WARRANTY STATEMENT: To obtain a copy of the warranty for this product, see the warranty information website:
http://www.hp.com/go/storagewarranty
Printed in the US.
Contents1 Introduction...............................................................................................5
Audience.................................................................................................................................5Advisories................................................................................................................................5
2 Getting Started..........................................................................................6Following Precautions................................................................................................................6Identifying the Components, Enclosure Ports, and Labels................................................................6
3 Cabling Configurations...............................................................................92 Controller Nodes 1 Drive Enclosure..........................................................................................9
Labeling the Storage Drive Enclosures...................................................................................10Labeling the Cables for Controller Node 0............................................................................11Labeling the Cables for Controller Node 1............................................................................11Connecting the Cables to Controller Node 0 and 1................................................................12
2 Controller Nodes 2 Drive Enclosures......................................................................................14Labeling the Storage Drive Enclosures...................................................................................14Labeling the Cables for Controller Node 0............................................................................16Labeling the Cables for Controller Node 1............................................................................16Connecting the Cables to Controller Node 0 and 1................................................................18
2 Controller Nodes 3 Drive Enclosures......................................................................................19Labeling the Storage Drive Enclosures...................................................................................19Labeling the Cables for Controller Node 0............................................................................21Connecting Red-Labeled Cables to Controller Node 0............................................................22Labeling the Cables for Controller Node 1............................................................................22Connecting the Cables to Controller Node 1.........................................................................24
2 Controller Nodes 4 Drive Enclosures......................................................................................25Labeling the Storage Drive Enclosures...................................................................................25Labeling the Cables for Controller Node 0............................................................................27Connecting Red-Labeled Cables to Controller Node 0............................................................28Labeling the Cables for Controller Node 1............................................................................28Connecting the Cables to Controller Node 1.........................................................................30
2 Controller Nodes 5 Drive Enclosures......................................................................................31Labeling the Storage Drive Enclosures...................................................................................31Labeling the Cables for Controller Node 0............................................................................33Connecting Red-Labeled Cables to Controller Node 0............................................................34Labeling the Cables for Controller Node 1............................................................................34Connecting the Cables to Controller Node 1.........................................................................36
2 Controller Nodes 6 Drive Enclosures......................................................................................37Labeling the Storage Drive Enclosures...................................................................................37Labeling the Cables for Controller Node 0............................................................................39Connecting Red-Labeled Cables to Controller Node 0............................................................40Labeling the Cables for Controller Node 1............................................................................41Connecting the Cables to Controller Node 1.........................................................................43
2 Controller Nodes 7 Drive Enclosures......................................................................................44Labeling the Storage Drive Enclosures...................................................................................44Labeling the Cables for Controller Node 0............................................................................46Connecting Red-Labeled Cables to Controller Node 0............................................................47Labeling the Cables for Controller Node 1............................................................................48Connecting the Cables to Controller Node 1.........................................................................50
2 Controller Nodes 8 Drive Enclosures......................................................................................51Labeling the Storage Drive Enclosures...................................................................................51Labeling the Cables for Controller Node 0............................................................................53
Contents 3
Connecting Red-Labeled Cables to Controller Node 0............................................................54Labeling the Cables for Controller Node 1............................................................................55Connecting the Cables to Controller Node 1.........................................................................57
2 Controller Nodes 9 Drive Enclosures......................................................................................58Labeling the Storage Drive Enclosures...................................................................................58Labeling the Cables for Controller Node 0............................................................................60Connecting Red-Labeled Cables to Controller Node 0............................................................61Labeling the Cables for Controller Node 1............................................................................62Connecting the Cables to Controller Node 1.........................................................................64
4 Additional Resources and Related Documentation.........................................65Contacting HP........................................................................................................................65HP 3PAR Documentation..........................................................................................................65
4 Contents
1 IntroductionAudience
This guide is intended for HP field engineers and authorized personnel installing or servicing HP3PAR StoreServ systems.
AdvisoriesTo avoid injury or damage to data and equipment, always observe the notes, cautions, andwarnings within this guide. Always be aware of the operating environment and handle electricalequipment carefully.
WARNING! Warnings alert you of actions that can cause injury to people or irreversible damageto the equipment, software, or data.
CAUTION: Cautions alerts you of actions that can cause damage to the equipment, software, ordata.
NOTE: Notes are reminders, tips, or suggestions that supplement the procedures included in thisguide.
Audience 5
2 Getting StartedRead the following sections as it list important instructions, precautions, and information aboutinstallation and cable connection options for the HP 3PAR StoreServ Storage system.
NOTE: The following diagrams do not present a storage-centric solution with the controller nodesmounted in the center of the rack or other non-HP supported component configurations. If the currentcomponents situated on the rack do not reflect the layout of the diagrams, continue to follow thecable instructions and carefully validate the port cable connections between all the controller nodesand storage drive enclosures to ensure proper operation and redundancy.
Following PrecautionsFollow these general precautions to avoid injury, data loss, and damage before and duringinstallation or while servicing the HP 3PAR StoreServ Storage system:• Avoid using improper tools
• Prepare an Electrostatic Discharge-safe (ESD) work surface by placing an antistatic mat onthe floor, or table, near the storage system. Attach the ground lead of the mat to an unpaintedsurface of the rack
• Always use a wrist-grounding strap, provided with the storage system. Attach the groundingstrap clip directly to an unpainted surface of the rack
• Avoid contact between electronic components and clothing which can carry an electrostaticcharge
• Ensure all cables are properly labeled and easily identifiable prior to removing a component
• Observe local occupational safety requirements and guidelines for handling heavy equipment
• Always load the heaviest item first, and start from the bottom when loading the rack. Loadingfrom the bottom makes the rack bottom-heavy and helps prevent the rack from becomingunstable
• Do not attempt to move a fully-loaded equipment rack. Remove all equipment from the rackbefore moving the rack
• Use at least two people to safely move the rack from the pallet
Identifying the Components, Enclosure Ports, and LabelsThe content in this section applies to all configurations and provides instructional guidance forcabling the HP 3PAR StoreServ 7000/7450 according to a specific configuration.
NOTE: The following diagrams do not present a storage-centric solution with the controller nodesmounted in the center of the rack or other non-HP supported component configurations. If the currentcomponents situated on the rack do not reflect the layout of the diagrams, continue to follow thecable instructions and carefully validate the port cable connections between all the controller nodesand storage drive enclosures to ensure proper operation and redundancy.
Controller Node and Storage Drive EnclosuresDepending on the system configuration, the HP 3PAR StoreServ 7200 enclosure is equipped withtwo controller nodes and the HP 3PAR StoreServ 7400/7450 supports either two or four controllernodes.
6 Getting Started
Figure 1 HP 3PAR StoreServ 7200 and 7400/7450 Controller Node Enclosure and SAS Ports
DP-1
DP-2M
fg
PULL
FC-2
FC-1
PCI-H
BA
MG
MT
RC-1M
fg
Mfg
1 2
2110G
be HP
3PAR
7200
CAUTION:
CAUTION:
PCM
PCM
1
0
1
0
DP-
1
DP-
2 Mfg
PULL
FC-2
FC-1
PCI-
HBA
MG
MT
RC-1 M
fg
Mfg
12
2 1 10Gbe
HP
3PA
R72
00
CAUTION:
CAUTION:
PCM
PCM
DP-1DP-2
DP-2
1
0
DP-
1
DP-
2
DP-1
DP-2
DP-
1
DP-
2
1
0
DP-1
DP-2
Node 1
DP-1
Node 0
CAUTION:
CAUTION:
PCM
PCM
CAUTION:
CAUTION:
PCM
PCM
DP-1
DP-2M
fg
PULL
FC-2
FC-1
PCI-H
BA 41 2 3
MG
MT
RC-1
Intr 0
Intr 1
HP
3PAR
7400
1
0
1
0
DP-
1
DP-
2 Mfg
PULL
FC-2
FC-1
PCI-
HBA4 123
MG
MT
RC-1
Intr
0
Intr
1
HP
3PA
R74
00
CAUTION:
CAUTION:
PCM
PCM
CAUTION:
CAUTION:
PCM
PCM
DP-1
DP-2M
fg
PULL
FC-2
FC-1
PCI-H
BA 41 2 3
MG
MT
RC-1
Intr 0
Intr 1
HP
3PAR
7400
3
2
3
2
DP-
1
DP-
2 Mfg
PULL
FC-2
FC-1
PCI-
HBA4 123
MG
MT
RC-1
Intr
0
Intr
1
HP
3PA
R74
00
DP-2DP-1
DP-2DP-1
DP-1DP-2
DP-1DP-2
3
2
1
0
DP-
1
DP-
2
DP-1
DP-2
DP-1
DP-2
DP-
1
DP-
2
DP-
1
DP-
2
1
0
3
2
DP-1
DP-2
DP-1
DP-2
DP-
1
DP-
2
Node 1
Node 2
Node 3
Node 0
The HP 3PAR StoreServ systems support a combination of small form-factor (SFF) M6710 and largeform-factor (LFF) M6720 storage drive enclosures. The M6710 (SFF) storage drive enclosure uses2.5-inch storage drives and the M6720 (LFF) enclosure supports 3.5-inch storage drives.
Figure 2 HP 3PAR M6710 and M6720 Storage Drive Enclosures and SAS Ports
CAUTION:
CAUTION:
PCM
PCM
CAUTION:
CAUTION:
PCM
PCM
1
0
1
0
DP-1
DP-2
Mfg
Mfg
DP-
1
DP-
2
Mfg
Mfg
DP-1DP-2
DP-2DP-1
1
0
DP-
1
DP-
2
DP-1
DP-2
1
0
DP-
1
DP-
2
DP-1
DP-2
IOM 1
IOM 0
CAUTION:
CAUTION:
PCM
PCM
CAUTION:
CAUTION:
PCM
PCM
DP-
1
DP-
2
Mfg
Mfg
DP-
1
DP-
2
Mfg
Mfg
1
0
1
0
DP-2DP-1
DP-2DP-1
1
0
DP-
1
DP-
2
DP-
1
DP-
2
1
0
DP-
1
DP-
2
DP-
1
DP-
2
IOM 1
IOM 0
Identifying the Components, Enclosure Ports, and Labels 7
Controller Node, Storage Drive Enclosure, and Cable Label KitsAll HP 3PAR StoreServ Storage systems contain special label kits for controller nodes, storage driveenclosures and cables. The labels are essential for identification purposes and part of the cablingprocess.The cabling configurations are identifiable by the specific number of nodes connecting to acombination of SFF and LFF storage drive enclosures. Each label specifies a direct connect froma controller node to a storage drive enclosure. All system cabling configurations use both red andgreen labels to assist with identifying and connecting the cables. Only connect a cable tocomponents sharing the same color.
Figure 3 Enclosure Labels
Figure 4 Cable Labels
N0:
DP2
- E
1:0:
DP1
E1:0:DP1 - N
0:DP2
00 0Port
Node
Enclosure
IOM
Port 11 1E4
:1:D
P2 -
E2:
1:D
P1
E2:1:DP1 - E4:1:D
P2
Enclosure
IOM
Port
Enclosure
IOMPort
NodeNode
Red Data Loop Green Data Loop
NOTE: Apply all the labels on to the appropriate system components and cables before connectingthe cables.
8 Getting Started
3 Cabling ConfigurationsThe following illustrative sections provide a rear view of the rack with recommended rackingconfiguration of the system.
NOTE: The following diagrams do not present a storage-centric solution with the controller nodesmounted in the center of the rack or other non-HP supported component configurations. If the currentcomponents situated on the rack do not reflect the layout of the diagrams, continue to follow thecable instructions and carefully validate the port cable connections between all the controller nodesand storage drive enclosures to ensure proper operation and redundancy.
2 Controller Nodes 1 Drive EnclosureBefore you begin cabling the storage system, carefully read or print the section, “Identifying theComponents, Enclosure Ports, and Labels” (page 6).
NOTE: Apply all the labels on to the appropriate system components and cables before connectingthe cables.
This cabling configuration consists of the following:• 1 medium (2m) SAS cable
• 1 short (1m) SAS cable
Figure 5 2 Controller Nodes with 1 Large Form-Factor Drive Enclosure
Nodes 0/1
E1
2 Controller Nodes 1 Drive Enclosure 9
Labeling the Storage Drive EnclosuresThis section describes the procedures for labeling the storage drive enclosures connecting tocontroller nodes 0 and 1.1. Locate the enclosure labels for controller nodes 0 and 1.
Figure 6 Controller Node Enclosure Labels
2. Apply the labels to the left rail of each storage drive enclosure.
NOTE: Do not label the controller node enclosures.
Figure 7 Applying the Labels
Nodes 0/1
E1
10 Cabling Configurations
Labeling the Cables for Controller Node 0Review the contents intended for controller node 0 in the red table before you proceed with labelingthe cables.
Figure 8 Controller Node 0 Cable Configuration
Node 0Number of cables Length Labels
- 6m -- 2m -1 1m A
1. Locate the labels for controller node 0 in the label kit.
Figure 9 Controller Node 0 Cable Labels
2. Select a short (1m) cable. Remove the two labels from row A and apply the labels four inchesaway from the connectors.
Figure 10 Labeling the Cable
Labeling the Cables for Controller Node 1Review the contents intended for controller node 1 in the green table before you proceed withlabeling the cables.
2 Controller Nodes 1 Drive Enclosure 11
Figure 11 Controller Node 1 Cable Configuration
Node 1Number of cables Length Labels
- 6m -1 2m A- 1m -
1. Locate the labels for controller node 1 in the label kit.
Figure 12 Controller Node 1 Cable Labels
2. Select a medium (2m) cable. Remove the two labels from row A and apply the labels fourinches away from the connectors.
Figure 13 Labeling the Cable
Connecting the Cables to Controller Node 0 and 11. Connect the short (1m) cable to the identified ports of controller node 0.
Figure 14 Identifying Port Numbers on Red Label
N0:
DP2
- E
1:0:
DP1
E1:0:DP1 - N
0:DP2
00 0Port
Node
Enclosure
IOM
Port
Node
Red Data Loop
12 Cabling Configurations
2. Connect a medium (2m) cable to the identified ports of controller node 1.
Figure 15 Identifying Port Numbers on Green Label
11 1
N1:
DP2
- E
1:1:
DP1
E1:1:DP1 - N
1:DP2
Port
Node
Enclosure
IOM
Port
Node
Green Data Loop
3. Use the diagram to verify all cabling is correct after connecting the cables to the controllernodes.
Figure 16 Reviewing Controller Nodes 0 and 1 Cable Connections
Nodes 0/1
E1
DP-1 DP-2
DP-2 DP-1
DP-1 DP-2
DP-1 DP-2
2 Controller Nodes 1 Drive Enclosure 13
2 Controller Nodes 2 Drive EnclosuresBefore you begin cabling the storage system, carefully read or print the section, “Identifying theComponents, Enclosure Ports, and Labels” (page 6).
NOTE: Apply all the labels on to the appropriate system components and cables before connectingthe cables.
This cabling configuration consists of the following:• 2 medium (2m) SAS cables
• 2 short (1m) SAS cables
Figure 17 2 Controller Nodes with 2 Large Form-Factor Drive Enclosures
Nodes 0/1
E1
E2
Labeling the Storage Drive EnclosuresThis section describes the procedures for labeling the storage drive enclosures connecting tocontroller nodes 0 and 1.
14 Cabling Configurations
1. Locate the enclosure labels for controller nodes 0 and 1.
Figure 18 Controller Node Enclosure Labels
2. Apply the labels to the left rail of each storage drive enclosure.
NOTE: Do not label the controller node enclosures.
Figure 19 Applying the Labels
Nodes 0/1
E1
E2
2 Controller Nodes 2 Drive Enclosures 15
Labeling the Cables for Controller Node 0Review the contents intended for controller node 0 in the red table before you proceed with labelingthe cables.
Figure 20 Controller Node 0 Cable Configuration
Node 0Number of cables Length Labels
- 6m -- 2m -2 1m A, B
1. Locate the labels for controller node 0 in the label kit.
Figure 21 Controller Node 0 Cable Labels
2. Select two short (1m) cables and do the following:• Remove the two labels from row A and apply the labels four inches away from the
connectors• Remove the two labels from row B and apply the labels four inches away from the
connectors
Figure 22 Labeling the Cable
Labeling the Cables for Controller Node 1Review the contents intended for controller node 1 in the green table before you proceed withlabeling the cables.
16 Cabling Configurations
Figure 23 Controller Node 1 Cable Configuration
Node 1Number of cables Length Labels
- 6m -2 2m A, B- 1m -
1. Locate the labels for controller node 1 in the label kit.
Figure 24 Controller Node 1 Cable Labels
2. Select two medium (2m) cables and do the following:a. Remove the two labels from row A and apply the labels four inches away from the
connectorsb. Remove the two labels from row B and apply the labels four inches away from the
connectors
Figure 25 Labeling the Cable
2 Controller Nodes 2 Drive Enclosures 17
Connecting the Cables to Controller Node 0 and 11. Connect the two short (1m) cables to the identified ports of controller node 0.
Figure 26 Identifying Port Numbers on Red Label
N0:
DP2
- E
1:0:
DP1
E1:0:DP1 - N
0:DP2
00 0Port
Node
Enclosure
IOM
Port
Node
Red Data Loop
2. Connect the two medium (2m) cables to the identified ports of controller node 1.
Figure 27 Identifying Port Numbers on Green Label
11 1
N1:
DP2
- E
1:1:
DP1
E1:1:DP1 - N
1:DP2
Port
Node
Enclosure
IOM
Port
Node
Green Data Loop
3. Use the diagram to verify all cabling is correct after connecting the cables to the controllernodes.
Figure 28 Reviewing Controller Nodes 0 and 1 Cable Connections
Nodes 0/1
E1
E2
DP-1 DP-2
DP-2 DP-1
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
18 Cabling Configurations
2 Controller Nodes 3 Drive EnclosuresBefore you begin cabling the storage system, carefully read or print the section, “Identifying theComponents, Enclosure Ports, and Labels” (page 6).
NOTE: Apply all the labels on to the appropriate system components and cables before connectingthe cables.
This cabling configuration consists of the following:• 2 medium (2m) SAS cables
• 4 short (1m) SAS cables
Figure 29 2 Controller Nodes with 3 Large Form-Factor Drive Enclosures
Nodes 0/1
E1
E2
E3
Labeling the Storage Drive EnclosuresThis section describes the procedures for labeling the storage drive enclosures connecting tocontroller nodes 0 and 1.
2 Controller Nodes 3 Drive Enclosures 19
1. Locate the enclosure labels for controller nodes 0 and 1.
Figure 30 Controller Node Enclosure Labels
2. Apply the labels to the left rail of each storage drive enclosure.
NOTE: Do not label the controller node enclosures.
Figure 31 Applying the Labels
Nodes 0/1
E1
E2
E3
20 Cabling Configurations
Labeling the Cables for Controller Node 0Review the contents intended for controller node 0 in the red table before you proceed with labelingthe cables.
Figure 32 Controller Node 0 Cable Configuration
Node 0Number of cables Length Labels
- 6m -- 2m -3 1m A-C
1. Locate the labels for controller node 0 in the label kit.
Figure 33 Controller Node 0 Cable Labels
2. Select three short (1m) cables and do the following:• Remove the two labels from row A and apply the labels four inches away from the
connectors• Remove the two labels from row B and apply the labels four inches away from the
connectors• Remove the two labels from row C and apply the labels four inches away from the
connectors
Figure 34 Labeling the Cable
2 Controller Nodes 3 Drive Enclosures 21
Connecting Red-Labeled Cables to Controller Node 01. Connect the three short (1m) cables to the identified ports of controller node 0.
Figure 35 Identifying Port Numbers on Red Label
N0:
DP2
- E
1:0:
DP1
E1:0:DP1 - N
0:DP2
00 0Port
Node
Enclosure
IOM
Port
Node
Red Data Loop
2. Use the diagram to verify all cabling is correct after connecting the cables to the controllernodes.
Figure 36 Reviewing Controller Node 0 Cable Connections
Nodes 0/1
E1
E2
E3
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
Labeling the Cables for Controller Node 1Review the contents intended for controller node 1 in the green table before you proceed withlabeling the cables.
22 Cabling Configurations
Figure 37 Controller Node 1 Cable Configuration
Node 1Number of cables Length Labels
- 6m -2 2m B, C1 1m J
1. Locate the labels for controller node 1 in the label kit.
Figure 38 Controller Node 1 Cable Labels
2. Do the following:a. Select two medium (2m) cables:
• Remove the two labels from row B and apply the labels four inches away from theconnectors
• Remove the two labels from row C and apply the labels four inches away from theconnectors
b. Select a short (1m) cable. Remove the two labels from row J and apply the labels fourinches away from the connectors.
Figure 39 Labeling the Cable
2 Controller Nodes 3 Drive Enclosures 23
Connecting the Cables to Controller Node 11. Do the following:
a. Connect the two medium (2m) cables to the identified ports of controller node 1.b. Connect the short (1m) cables to the identified ports of controller node 1.
Figure 40 Identifying Port Numbers on Green Label
11 1
N1:
DP2
- E
1:1:
DP1
E1:1:DP1 - N
1:DP2
Port
Node
Enclosure
IOM
Port
Node
Green Data Loop
2. Use the diagram to verify all cabling is correct after connecting the cables to the controllernodes.
Figure 41 Reviewing Controller Node 1 Cable Connections
Nodes 0/1DP-2 DP-1
E1
E2
E3
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-2 DP-1
24 Cabling Configurations
2 Controller Nodes 4 Drive EnclosuresBefore you begin cabling the storage system, carefully read or print the section, “Identifying theComponents, Enclosure Ports, and Labels” (page 6).
NOTE: Apply all the labels on to the appropriate system components and cables before connectingthe cables.
This cabling configuration consists of the following:• 2 medium (2m) SAS cables
• 6 short (1m) SAS cables
Figure 42 2 Controller Nodes with 4 Large Form-Factor Drive Enclosures
Nodes 0/1
E1
E2
E3
E4
Labeling the Storage Drive EnclosuresThis section describes the procedures for labeling the storage drive enclosures connecting tocontroller nodes 0 and 1.
2 Controller Nodes 4 Drive Enclosures 25
1. Locate the enclosure labels for controller nodes 0 and 1.
Figure 43 Controller Node Enclosure Labels
2. Apply the labels to the left rail of each storage drive enclosure.
NOTE: Do not label the controller node enclosures.
Figure 44 Applying the Labels
Nodes 0/1
E1
E2
E3
E4
26 Cabling Configurations
Labeling the Cables for Controller Node 0Review the contents intended for controller node 0 in the red table before you proceed with labelingthe cables.
Figure 45 Controller Node 0 Cable Configuration
Node 0Number of cables Length Labels
- 6m -- 2m -4 1m A-D
1. Locate the labels for controller node 0 in the label kit.
Figure 46 Controller Node 0 Cable Labels
2. Select four short (1m) cables and do the following:• Remove the two labels from row A and apply the labels four inches away from the
connectors• Remove the two labels from row B and apply the labels four inches away from the
connectors• Remove the two labels from row C and apply the labels four inches away from the
connectors• Remove the two labels from row D and apply the labels four inches away from the
connectors
Figure 47 Labeling the Cable
2 Controller Nodes 4 Drive Enclosures 27
Connecting Red-Labeled Cables to Controller Node 01. Connect the four short (1m) cables to the identified ports of controller node 0.
Figure 48 Identifying Port Numbers on Red Label
N0:
DP2
- E
1:0:
DP1
E1:0:DP1 - N
0:DP2
00 0Port
Node
Enclosure
IOM
Port
Node
Red Data Loop
2. Use the diagram to verify all cabling is correct after connecting the cables to the controllernodes.
Figure 49 Reviewing Controller Node 0 Cable Connections
Nodes 0/1
E1
E2
E3
E4
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
Labeling the Cables for Controller Node 1Review the contents intended for controller node 1 in the green table before you proceed withlabeling the cables.
28 Cabling Configurations
Figure 50 Controller Node 1 Cable Configuration
Node 1Number of cables Length Labels
- 6m -2 2m C, D2 1m J, K
1. Locate the labels for controller node 1 in the label kit.
Figure 51 Controller Node 1 Cable Labels
2. Do the following:a. Select two medium (2m) cables:
• Remove the two labels from row C and apply the labels four inches away from theconnectors
• Remove the two labels from row D and apply the labels four inches away from theconnectors
b. Select two short (1m) cables:• Remove the two labels from row J and apply the labels four inches away from the
connectors• Remove the two labels from row K and apply the labels four inches away from the
connectors
Figure 52 Labeling the Cable
2 Controller Nodes 4 Drive Enclosures 29
Connecting the Cables to Controller Node 11. Do the following:
a. Connect the two medium (2m) cables to the identified ports of controller node 1.b. Connect the two short (1m) cables to the identified ports of controller node 1.
Figure 53 Identifying Port Numbers on Green Label
11 1
N1:
DP2
- E
1:1:
DP1
E1:1:DP1 - N
1:DP2
Port
Node
Enclosure
IOM
Port
Node
Green Data Loop
2. Use the diagram to verify all cabling is correct after connecting the cables to the controllernodes.
Figure 54 Reviewing Controller Node 1 Cable Connections
Nodes 0/1DP-2 DP-1
E1
E2
E3
E4
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-2 DP-1
30 Cabling Configurations
2 Controller Nodes 5 Drive EnclosuresBefore you begin cabling the storage system, carefully read or print the section, “Identifying theComponents, Enclosure Ports, and Labels” (page 6).
NOTE: Apply all the labels on to the appropriate system components and cables before connectingthe cables.
This cabling configuration consists of the following:• 2 medium (2m) SAS cables
• 8 short (1m) SAS cables
Figure 55 2 Controller Nodes with 5 Large Form-Factor Drive Enclosures
Nodes 0/1
E1
E2
E3
E4
E5
Labeling the Storage Drive EnclosuresThis section describes the procedures for labeling the storage drive enclosures connecting tocontroller nodes 0 and 1.
2 Controller Nodes 5 Drive Enclosures 31
1. Locate the enclosure labels for controller nodes 0 and 1.
Figure 56 Controller Node Enclosure Labels
2. Apply the labels to the left rail of each storage drive enclosure.
NOTE: Do not label the controller node enclosures.
Figure 57 Applying the Labels
Nodes 0/1
E1
E2
E3
E4
E5
32 Cabling Configurations
Labeling the Cables for Controller Node 0Review the contents intended for controller node 0 in the red table before you proceed with labelingthe cables.
Figure 58 Controller Node 0 Cable Configuration
Node 0Number of cables Length Labels
- 6m -- 2m -5 1m A-E
1. Locate the labels for controller node 0 in the label kit.
Figure 59 Controller Node 0 Cable Labels
2. Select five short (1m) cables and do the following:• Remove the two labels from row A and apply the labels four inches away from the
connectors• Remove the two labels from row B and apply the labels four inches away from the
connectors• Remove the two labels from row C and apply the labels four inches away from the
connectors• Remove the two labels from row D and apply the labels four inches away from the
connectors• Remove the two labels from row E and apply the labels four inches away from the
connectors
Figure 60 Labeling the Cable
2 Controller Nodes 5 Drive Enclosures 33
Connecting Red-Labeled Cables to Controller Node 01. Connect the five short (1m) cables to the identified ports of controller node 0.
Figure 61 Identifying Port Numbers on Red Label
N0:
DP2
- E
1:0:
DP1
E1:0:DP1 - N
0:DP2
00 0Port
Node
Enclosure
IOM
Port
Node
Red Data Loop
2. Use the diagram to verify all cabling is correct after connecting the cables to the controllernodes.
Figure 62 Reviewing Controller Node 0 Cable Connections
Nodes 0/1
E1
E2
E3
E4
E5
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
Labeling the Cables for Controller Node 1Review the contents intended for controller node 1 in the green table before you proceed withlabeling the cables.
34 Cabling Configurations
Figure 63 Controller Node 1 Cable Configuration
Node 1Number of cables Length Labels
- 6m -2 2m D, E3 1m J-L
1. Locate the labels for controller node 1 in the label kit.
Figure 64 Controller Node 1 Cable Labels
2. Do the following:a. Select two medium (2m) cables:
• Remove the two labels from row D and apply the labels four inches away from theconnectors
• Remove the two labels from row E and apply the labels four inches away from theconnectors
b. Select three short (1m) cables:• Remove the two labels from row J and apply the labels four inches away from the
connectors• Remove the two labels from row K and apply the labels four inches away from the
connectors• Remove the two labels from row L and apply the labels four inches away from the
connectors
Figure 65 Labeling the Cable
2 Controller Nodes 5 Drive Enclosures 35
Connecting the Cables to Controller Node 11. Do the following:
a. Connect the two medium (2m) cables to the identified ports of controller node 1.b. Connect the three short (1m) cables to the identified ports of controller node 1.
Figure 66 Identifying Port Numbers on Green Label
11 1
N1:
DP2
- E
1:1:
DP1
E1:1:DP1 - N
1:DP2
Port
Node
Enclosure
IOM
Port
Node
Green Data Loop
2. Use the diagram to verify all cabling is correct after connecting the cables to the controllernodes.
Figure 67 Reviewing Controller Nodes 1 Cable Connections
Nodes 0/1DP-2 DP-1
E1
E2
E3
E4
E5
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-2 DP-1
36 Cabling Configurations
2 Controller Nodes 6 Drive EnclosuresBefore you begin cabling the storage system, carefully read or print the section, “Identifying theComponents, Enclosure Ports, and Labels” (page 6).
NOTE: Apply all the labels on to the appropriate system components and cables before connectingthe cables.
This cabling configuration consists of the following:• 2 medium (2m) SAS cables
• 10 short (1m) SAS cables
Figure 68 2 Controller Nodes with 6 Large Form-Factor Drive Enclosures
Nodes 0/1
E1
E2
E3
E4
E5
E6
Labeling the Storage Drive EnclosuresThis section describes the procedures for labeling the storage drive enclosures connecting tocontroller nodes 0 and 1.
2 Controller Nodes 6 Drive Enclosures 37
1. Locate the enclosure labels for controller nodes 0 and 1.
Figure 69 Controller Node Enclosure Labels
2. Apply the labels to the left rail of each storage drive enclosure.
NOTE: Do not label the controller node enclosures.
Figure 70 Applying the Labels
Nodes 0/1
E1
E2
E3
E4
E5
E6
38 Cabling Configurations
Labeling the Cables for Controller Node 0Review the contents intended for controller node 0 in the red table before you proceed with labelingthe cables.
Figure 71 Controller Node 0 Cable Configuration
Node 0Number of cables Length Labels
- 6m -- 2m -6 1m A-F
1. Locate the labels for controller node 0 in the label kit.
Figure 72 Controller Node 0 Cable Labels
2 Controller Nodes 6 Drive Enclosures 39
2. Select six short (1m) cables and do the following:• Remove the two labels from row A and apply the labels four inches away from the
connectors• Remove the two labels from row B and apply the labels four inches away from the
connectors• Remove the two labels from row C and apply the labels four inches away from the
connectors• Remove the two labels from row D and apply the labels four inches away from the
connectors• Remove the two labels from row E and apply the labels four inches away from the
connectors• Remove the two labels from row F and apply the labels four inches away from the
connectors
Figure 73 Labeling the Cable
Connecting Red-Labeled Cables to Controller Node 01. Connect the six short (1m) cables to the identified ports of controller node 0.
Figure 74 Identifying Port Numbers on Red Label
N0:
DP2
- E
1:0:
DP1
E1:0:DP1 - N
0:DP2
00 0Port
Node
Enclosure
IOM
Port
Node
Red Data Loop
40 Cabling Configurations
2. Use the diagram to verify all cabling is correct after connecting the cables to the controllernodes.
Figure 75 Reviewing Controller Node 0 Cable Connections
Nodes 0/1
E1
E2
E3
E4
E5
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
E6DP-1 DP-2
Labeling the Cables for Controller Node 1Review the contents intended for controller node 1 in the green table before you proceed withlabeling the cables.
Figure 76 Controller Node 1 Cable Configuration
Node 1Number of cables Length Labels
- 6m -2 2m E, F4 1m J-M
2 Controller Nodes 6 Drive Enclosures 41
1. Locate the labels for controller node 1 in the label kit.
Figure 77 Controller Node 1 Cable Labels
2. Do the following:a. Select two medium (2m) cables:
• Remove the two labels from row E and apply the labels four inches away from theconnectors
• Remove the two labels from row F and apply the labels four inches away from theconnectors
b. Select four short (1m) cables:• Remove the two labels from row J and apply the labels four inches away from the
connectors• Remove the two labels from row K and apply the labels four inches away from the
connectors• Remove the two labels from row L and apply the labels four inches away from the
connectors• Remove the two labels from row M and apply the labels four inches away from the
connectors
Figure 78 Labeling the Cable
42 Cabling Configurations
Connecting the Cables to Controller Node 11. Do the following:
a. Connect the two medium (2m) cables to the identified ports of controller node 1.b. Connect the four short (1m) cables to the identified ports of controller node 1.
Figure 79 Identifying Port Numbers on Green Label
11 1N
1:D
P2 -
E1:
1:D
P1
E1:1:DP1 - N
1:DP2
Port
Node
Enclosure
IOM
Port
Node
Green Data Loop
2. Use the diagram to verify all cabling is correct after connecting the cables to the controllernodes.
Figure 80 Reviewing Controller Node 1 Cable Connections
Nodes 0/1DP-2 DP-1
E1
E2
E3
E4
E5
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-2 DP-1
E6DP-1 DP-2
2 Controller Nodes 6 Drive Enclosures 43
2 Controller Nodes 7 Drive EnclosuresBefore you begin cabling the storage system, carefully read or print the section, “Identifying theComponents, Enclosure Ports, and Labels” (page 6).
NOTE: Apply all the labels on to the appropriate system components and cables before connectingthe cables.
This cabling configuration consists of the following:• 2 medium (2m) SAS cables
• 12 short (1m) SAS cables
Figure 81 2 Controller Nodes with 7 Large Form-Factor Drive Enclosures
Nodes 0/1
E1
E2
E3
E4
E5
E6
E7
Labeling the Storage Drive EnclosuresThis section describes the procedures for labeling the storage drive enclosures connecting tocontroller nodes 0 and 1.
44 Cabling Configurations
1. Locate the enclosure labels for controller nodes 0 and 1.
Figure 82 Controller Node Enclosure Labels
2. Apply the labels to the left rail of each storage drive enclosure.
NOTE: Do not label the controller node enclosures.
Figure 83 Applying the Labels
Nodes 0/1
E1
E2
E3
E4
E5
E6
E7
2 Controller Nodes 7 Drive Enclosures 45
Labeling the Cables for Controller Node 0Review the contents intended for controller node 0 in the red table before you proceed with labelingthe cables.
Figure 84 Controller Node 0 Cable Configuration
Node 0Number of cables Length Labels
- 6m -- 2m -7 1m A-G
1. Locate the labels for controller node 0 in the label kit.
Figure 85 Controller Node 0 Cable Labels
46 Cabling Configurations
2. Select seven short (1m) cables and do the following:• Remove the two labels from row A and apply the labels four inches away from the
connectors• Remove the two labels from row B and apply the labels four inches away from the
connectors• Remove the two labels from row C and apply the labels four inches away from the
connectors• Remove the two labels from row D and apply the labels four inches away from the
connectors• Remove the two labels from row E and apply the labels four inches away from the
connectors• Remove the two labels from row F and apply the labels four inches away from the
connectors• Remove the two labels from row G and apply the labels four inches away from the
connectors
Figure 86 Labeling the Cable
Connecting Red-Labeled Cables to Controller Node 01. Connect the seven short (1m) cables to the identified ports of controller node 0.
Figure 87 Identifying Port Numbers on Red Label
N0:
DP2
- E
1:0:
DP1
E1:0:DP1 - N
0:DP2
00 0Port
Node
Enclosure
IOM
Port
Node
Red Data Loop
2 Controller Nodes 7 Drive Enclosures 47
2. Use the diagram to verify all cabling is correct after connecting the cables to the controllernodes.
Figure 88 Reviewing Controller Node 0 Cable Connections
Nodes 0/1
E1
E2
E3
E4
E5
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2E6
DP-1 DP-2
DP-1 DP-2
E7
DP-1 DP-2
Labeling the Cables for Controller Node 1Review the contents intended for controller node 1 in the green table before you proceed withlabeling the cables.
Figure 89 Controller Node 1 Cable Configuration
Node 1Number of cables Length Labels
- 6m -2 2m F, G5 1m J-N
48 Cabling Configurations
1. Locate the labels for controller node 1 in the label kit.
Figure 90 Controller Node 1 Cable Labels
2. Do the following:a. Select two medium (2m) cables:
• Remove the two labels from row F and apply the labels four inches away from theconnectors
• Remove the two labels from row G and apply the labels four inches away from theconnectors
b. Select five short (1m) cables:• Remove the two labels from row J and apply the labels four inches away from the
connectors• Remove the two labels from row K and apply the labels four inches away from the
connectors• Remove the two labels from row L and apply the labels four inches away from the
connectors• Remove the two labels from row M and apply the labels four inches away from the
connectors• Remove the two labels from row N and apply the labels four inches away from the
connectors
Figure 91 Labeling the Cable
2 Controller Nodes 7 Drive Enclosures 49
Connecting the Cables to Controller Node 11. Do the following:
a. Connect the two medium (2m) cables to the identified ports of controller node 1.b. Connect the five short (1m) cables to the identified ports of controller node 1.
Figure 92 Identifying Port Numbers on Green Label
11 1
N1:
DP2
- E
1:1:
DP1
E1:1:DP1 - N
1:DP2
Port
Node
Enclosure
IOM
Port
Node
Green Data Loop
2. Use the diagram to verify all cabling is correct after connecting the cables to the controllernodes.
Figure 93 Reviewing Controller Node 1 Cable Connections
Nodes 0/1
E1
E2
E3
E4
E5
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2E6
DP-1 DP-2
DP-1 DP-2
E7
DP-1 DP-2
DP-2 DP-1
50 Cabling Configurations
2 Controller Nodes 8 Drive EnclosuresBefore you begin cabling the storage system, carefully read or print the section, “Identifying theComponents, Enclosure Ports, and Labels” (page 6).
NOTE: Apply all the labels on to the appropriate system components and cables before connectingthe cables.
This cabling configuration consists of the following:• 2 medium (2m) SAS cables
• 14 short (1m) SAS cables
Figure 94 2 Controller Nodes with 8 Large Form-Factor Drive Enclosures
Nodes 0/1
E1
E2
E3
E4
E5
E6
E7
E8
Labeling the Storage Drive EnclosuresThis section describes the procedures for labeling the storage drive enclosures connecting tocontroller nodes 0 and 1.
2 Controller Nodes 8 Drive Enclosures 51
1. Locate the enclosure labels for controller nodes 0 and 1.
Figure 95 Controller Node Enclosure Labels
2. Apply the labels to the left rail of each storage drive enclosure.
NOTE: Do not label the controller node enclosures.
Figure 96 Applying the Labels
Nodes 0/1
E1
E2
E3
E4
E5
E6
E7
E8
52 Cabling Configurations
Labeling the Cables for Controller Node 0Review the contents intended for controller node 0 in the red table before you proceed with labelingthe cables.
Figure 97 Controller Node 0 Cable Configuration
Node 0Number of cables Length Labels
- 6m -- 2m -8 1m A-H
1. Locate the labels for controller node 0 in the label kit.
Figure 98 Controller Node 0 Cable Labels
2 Controller Nodes 8 Drive Enclosures 53
2. Select eight short (1m) cables and do the following:• Remove the two labels from row A and apply the labels four inches away from the
connectors• Remove the two labels from row B and apply the labels four inches away from the
connectors• Remove the two labels from row C and apply the labels four inches away from the
connectors• Remove the two labels from row D and apply the labels four inches away from the
connectors• Remove the two labels from row E and apply the labels four inches away from the
connectors• Remove the two labels from row F and apply the labels four inches away from the
connectors• Remove the two labels from row G and apply the labels four inches away from the
connectors• Remove the two labels from row H and apply the labels four inches away from the
connectors
Figure 99 Labeling the Cable
Connecting Red-Labeled Cables to Controller Node 01. Connect the eight short (1m) cables to the identified ports of controller node 0.
Figure 100 Identifying Port Numbers on Red Label
N0:
DP2
- E
1:0:
DP1
E1:0:DP1 - N
0:DP2
00 0Port
Node
Enclosure
IOM
Port
Node
Red Data Loop
54 Cabling Configurations
2. Use the diagram to verify all cabling is correct after connecting the cables to the controllernodes.
Figure 101 Reviewing Controller Node 0 Cable Connections
Nodes 0/1
E1
E2
E3
E4
E5
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2E6
DP-1 DP-2
DP-1 DP-2
E7
DP-1 DP-2
DP-1 DP-2
E8
Labeling the Cables for Controller Node 1Review the contents intended for controller node 1 in the green table before you proceed withlabeling the cables.
Figure 102 Controller Node 1 Cable Configuration
Node 1Number of cables Length Labels
- 6m -2 2m G, H6 1m J-O
2 Controller Nodes 8 Drive Enclosures 55
1. Locate the labels for controller node 1 in the label kit.
Figure 103 Controller Node 1 Cable Labels
2. Do the following:a. Select two medium (2m) cables:
• Remove the two labels from row F and apply the labels four inches away from theconnectors
• Remove the two labels from row G and apply the labels four inches away from theconnectors
b. Select six short (1m) cables:• Remove the two labels from row J and apply the labels four inches away from the
connectors• Remove the two labels from row K and apply the labels four inches away from the
connectors• Remove the two labels from row L and apply the labels four inches away from the
connectors• Remove the two labels from row M and apply the labels four inches away from the
connectors• Remove the two labels from row N and apply the labels four inches away from the
connectors• Remove the two labels from row O and apply the labels four inches away from the
connectors
Figure 104 Labeling the Cable
56 Cabling Configurations
Connecting the Cables to Controller Node 11. Do the following:
a. Connect the two medium (2m) cables to the identified ports of controller node 1.b. Connect the six short (1m) cables to the identified ports of controller node 1.
Figure 105 Identifying Port Numbers on Green Label
11 1N
1:D
P2 -
E1:
1:D
P1
E1:1:DP1 - N
1:DP2
Port
Node
Enclosure
IOM
Port
Node
Green Data Loop
2. Use the diagram to verify all cabling is correct after connecting the cables to the controllernodes.
Figure 106 Reviewing Controller Node 1 Cable Connections
Nodes 0/1
E1
E2
E3
E4
E5
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2E6
DP-1 DP-2
DP-1 DP-2
E7
DP-1 DP-2
DP-2 DP-1
DP-1 DP-2
E8
2 Controller Nodes 8 Drive Enclosures 57
2 Controller Nodes 9 Drive EnclosuresBefore you begin cabling the storage system, carefully read or print the section, “Identifying theComponents, Enclosure Ports, and Labels” (page 6).
NOTE: Apply all the labels on to the appropriate system components and cables before connectingthe cables.
This cabling configuration consists of the following:• 2 medium (2m) SAS cables
• 16 short (1m) SAS cables
Figure 107 2 Controller Nodes with 9 Large Form-Factor Drive Enclosures
Nodes 0/1
E1
E2
E3
E4
E5
E6
E7
E8
E9
Labeling the Storage Drive EnclosuresThis section describes the procedures for labeling the storage drive enclosures connecting tocontroller nodes 0 and 1.
58 Cabling Configurations
1. Locate the enclosure labels for controller nodes 0 and 1.
Figure 108 Controller Node Enclosure Labels
2. Apply the labels to the left rail of each storage drive enclosure.
NOTE: Do not label the controller node enclosures.
Figure 109 Applying the Labels
Nodes 0/1
E1
E2
E3
E4
E5
E6
E7
E8
E9
2 Controller Nodes 9 Drive Enclosures 59
Labeling the Cables for Controller Node 0Review the contents intended for controller node 0 in the red table before you proceed with labelingthe cables.
Figure 110 Controller Node 0 Cable Configuration
Node 0Number of cables Length Labels
- 6m -- 2m -9 1m A-I
1. Locate the labels for controller node 0 in the label kit.
Figure 111 Controller Node 0 Cable Labels
60 Cabling Configurations
2. Select nine short (1m) cables and do the following:• Remove the two labels from row A and apply the labels four inches away from the
connectors• Remove the two labels from row B and apply the labels four inches away from the
connectors• Remove the two labels from row C and apply the labels four inches away from the
connectors• Remove the two labels from row D and apply the labels four inches away from the
connectors• Remove the two labels from row E and apply the labels four inches away from the
connectors• Remove the two labels from row F and apply the labels four inches away from the
connectors• Remove the two labels from row G and apply the labels four inches away from the
connectors• Remove the two labels from row H and apply the labels four inches away from the
connectors• Remove the two labels from row I and apply the labels four inches away from the
connectors
Figure 112 Labeling the Cable
Connecting Red-Labeled Cables to Controller Node 01. Connect the nine short (1m) cables to the identified ports of controller node 0.
Figure 113 Identifying Port Numbers on Red Label
N0:
DP2
- E
1:0:
DP1
E1:0:DP1 - N
0:DP2
00 0Port
Node
Enclosure
IOM
Port
Node
Red Data Loop
2 Controller Nodes 9 Drive Enclosures 61
2. Use the diagram to verify all cabling is correct after connecting the cables to the controllernodes.
Figure 114 Reviewing Controller Node 0 Cable Connections
Nodes 0/1
E1
E2
E3
E4
E5
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2E6
DP-1 DP-2
DP-1 DP-2E7
DP-1 DP-2
DP-1 DP-2E8
DP-1 DP-2
DP-1 DP-2E9
DP-1 DP-2
Labeling the Cables for Controller Node 1Review the contents intended for controller node 1 in the green table before you proceed withlabeling the cables.
Figure 115 Controller Node 1 Cable Configuration
Node 1Number of cables Length Labels
- 6m -2 2m H, I7 1m J-P
62 Cabling Configurations
1. Locate the labels for controller node 1 in the label kit.
Figure 116 Controller Node 1 Cable Labels
2. Do the following:a. Select two medium (2m) cables:
• Remove the two labels from row H and apply the labels four inches away from theconnectors
• Remove the two labels from row I and apply the labels four inches away from theconnectors
b. Select seven short (1m) cables:• Remove the two labels from row J and apply the labels four inches away from the
connectors• Remove the two labels from row K and apply the labels four inches away from the
connectors• Remove the two labels from row L and apply the labels four inches away from the
connectors• Remove the two labels from row M and apply the labels four inches away from the
connectors• Remove the two labels from row N aand apply the labels four inches away from the
connectors• Remove the two labels from row O and apply the labels four inches away from the
connectors• Remove the two labels from row P and apply the labels four inches away from the
connectors
Figure 117 Labeling the Cable
2 Controller Nodes 9 Drive Enclosures 63
Connecting the Cables to Controller Node 11. Do the following:
a. Connect the two medium (2m) cables to the identified ports of controller node 1.b. Connect the seven short (1m) cables to the identified ports of controller node 1.
Figure 118 Identifying Port Numbers on Green Label
11 1
N1:
DP2
- E
1:1:
DP1
E1:1:DP1 - N
1:DP2
Port
Node
Enclosure
IOM
Port
Node
Green Data Loop
2. Use the diagram to verify all cabling is correct after connecting the cables to the controllernodes.
Figure 119 Reviewing Controller Node 1 Cable Connections
Nodes 0/1
E1
E2
E3
E4
E5
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
DP-1 DP-2
E6
DP-1 DP-2
E7
DP-1 DP-2
DP-1 DP-2
E8
DP-1 DP-2
E9
DP-1 DP-2
DP-2 DP-1
64 Cabling Configurations
4 Additional Resources and Related DocumentationContacting HP
For worldwide technical support information, see the HP support website:http://www.hp.com/support
Before contacting HP, collect the following information:
• Product model names and numbers
• Technical support registration number (if applicable)
• Product serial numbers
• Error messages
• Operating system type and revision level
• Detailed questionsSpecify the type of support you are requesting:
Support RequestHP 3PAR Storage System
StoreServ 7000 Series StorageHP 3PAR StoreServ 7200, 7400, and 7450 Storagesystems
HP 3PAR DocumentationFor additional information about other related system cable configurations, refer to the followingdocuments:
• HP 3PAR StoreServ 7000 Series Storage Cabling Configuration Guide A: Two Node Systemwith M6710 Enclosures
• HP 3PAR StoreServ 7000 Series Storage Cabling Configuration Guide B: Two Node Systemwith M6720 Enclosures
• HP 3PAR StoreServ 7000 Series Storage Cabling Configuration Guide C: Two Node Systemwith M6710/M6720 Enclosures
• HP 3PAR StoreServ 7000 Series Storage Cabling Configuration Guide D: Four Node Systemwith M6710 Enclosures
• HP 3PAR StoreServ 7000 Series Storage Cabling Configuration Guide E: Four Node Systemwith M6720 Enclosures
• HP 3PAR StoreServ 7000 Series Storage Cabling Configuration Guide F: Four Node Systemwith M6710/M6720 Enclosures
Contacting HP 65