![Page 1: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/1.jpg)
member of
Institut für Print- und Medientechnik der TU Chemnitz[Institute for Print and Media Technology at Chemnitz University of Technology]
Director: Prof. Dr. Arved C. Hübler • Reichenhainer Str. 70 • 09126 Chemnitz • Germanyhttp://www.tu-chemnitz.de/pm • [email protected] • Phone: +49-371-531-23610 • Fax: -23619
how to organize a newspaper project cost saving and cost control
byArved Huebler, Institute for Print & Media Technology,Chemnitz University of Technology, Germany
Cost control, Revenue opportunities in productionWAN-IFRA Seminar for newspapers,
in association with TU Chemnitz18-19 January 2010, New Delhi
!
![Page 2: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/2.jpg)
The work during 2008-2009 was financed by IFRAin the frame of theSpecial Report #4.2009published June 2009
It was a co-operative project betweenInstitute for Print & Media Technology at Chemnitz University of Technology, Germany
and
Manipal Institute of Technology (Department for Printing) at Manipal University, India
Empowering the News Publishing Industry
04.2009
New Printing Plants
SPECIAL REPORT
www.ifra.com/specialreports
A must read for:
Managing Director/CEO/ChairmanProduction ManagerTechnical Director
Catchwords:
Business/Management/OrganisationIndustry and Company InformationProduction Management
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of
Background of this presentation
2 pmTUC/IFRA special report 04.2009A. Hübler
the method: - interviews with companies in India & Gemany- interviews with experts- case studies of 10 Indian and 10 German students- enquiry in technical literature
![Page 3: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/3.jpg)
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of
content
3 pmTUC/IFRA special report 04.2009A. Hübler
1. define the project
2. project management
![Page 4: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/4.jpg)
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of
an old rule:
4
during phases of market growth:invest in production (capacity)
during saturation of market:invest in customer (marketing)
a one-shot decision:invest in the right way !
pmTUC • image: Freie Presse 15.11.2009A. Hübler
![Page 5: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/5.jpg)
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of
»the difference between companies with success and abortive competitors often is the ability to perform structural and process changes quicker«.[1]
5[1] Wildemann: Organisatorisches Lernen "Das Geheimnis des Erfolgs"A. Hübler
the major fields of change:✦ customer✦ costs✦ lead time✦ process✦ quality✦ knowledge✦ learning✦ division of duties
establishing a new plant for newspaper production effects all:
⇨ open for new customers⇨ reducing costs⇨ optimizing lead time⇨ state of the art process⇨ better quality⇨ need of new knowledge⇨ need for learning⇨ think about the organisation
A new plant for newspaper production is a crucial point for all the further success.
![Page 6: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/6.jpg)
depreciation
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of
establishing a new plant …
6
two types of costs must be controlled:
1. the project costs.2. the later running costs of the plant.
running costs of the plant
per year
running costs of the plant
per year
project management
building
equipment
material
energy etc.
service, repair
save invest
total invest budget
increase oftechnical
running costs
?
typically, the budget is delimited:1. find out the financial 2. optimize the investment alternatives by a ranking regaring their influence to reduce running costs
![Page 7: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/7.jpg)
not used rollsdamage in logistics
100%into press
white cover layerprinting waste
2-4%
?%?%
4-9%1-3%
84-93%
postpress waste
to be distributed
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of
e.g. paper lost
7
7% difference:at 150.000 circulation per day16 pages40 g/sq. paper= at minimum savings of50 lakh INR per year
⇒ increasing invest to press for lowering later costs
Do you known,where the paper remains which you havebought.
![Page 8: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/8.jpg)
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of
find the right strategy …
8
new press
used press
high-tech
standard-tech
todays requirements
augmentation for tomorrow
higher quality
standard quality
higher investment
today
higher running
costs later?
pmTUC • image: Freie Presse 15.11.2009A. Hübler
… not only the budget must be defined at the beginning, but also all other parameters as quality level, printed volume.
![Page 9: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/9.jpg)
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of
managing the transition
9pmTUC/IFRA special report 04.2009A. Hübler
L
at the end, every development has to lead to higher volumemeans: more high tech becomes necessarybut there are different routes to go.
standard tech
![Page 10: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/10.jpg)
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of
logistics
10
paper stock & transport
standard tech high tech
problems because of- damage of rolls- old remainder rolls- lost rolls
• more space > often small enhancements in the layout of the
• software controlled inventory- barcode- RF-ID
• modern transport vehicles > take care about space for movement
better paper management also increases liquidity
time to deliver problems- transport coordination- storage management (semi-finished products)
• systematic design of plant layout
• warehouse and logistics management software
pmTUC • image: Freie Presse 15.11.2009A. Hübler
![Page 11: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/11.jpg)
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of
press criteria
11pmTUC/IFRA special report 04.2009 • image: Freie Presse 15.11.2009A. Hübler
standard tech printing plant High tech printing plant
retrofitting features later,may also become more expensive because the runningproduction is affected
![Page 12: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/12.jpg)
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of
high tech options
12pmTUC • image: Freie Presse 15.11.2009A. Hübler
for your technology decision, take also into account:• service costs• repair costs• possibilities of upgrading add. features
Not only buy a solution, but develop the full system before buying and before implementing it.
for your decision about the appropriate level of automation,take also into account:• level of knowledge of the operators• cleanness of facility• risk of break down• system approach: what all is effected
by the automated solution? (prepress, customer, material supplier, …)
![Page 13: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/13.jpg)
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of
standard tech opportunities
13
For standard technology, take also into account:In western countries some modern printing plants are in de-investment!
You may use the chance to transfer a complete newspaper production facilityfor cheap money to India.
pmTUC • image: Freie Presse 15.11.2009A. Hübler
![Page 14: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/14.jpg)
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of
postpress
14pmTUC/IFRA special report 04.2009A. Hübler
• need of flexibility for subsequent production.
• possibility to realize investment stepwise.
not only to reserve additional space …
… but also provide infrastructural links⏈ ⍔ ⍅ ⏄ ⌺ ⍝
⏈ ⍔ ⍅ ⏄ ⌺ ⍝
![Page 15: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/15.jpg)
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of
collect all the requirements for the building
15pmTUC/IFRA special report 04.2009A. Hübler
![Page 16: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/16.jpg)
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of 16
standard tech• total energy consumption
- lightning - air condition - compressed air > leakage air flows
- power outagestotal water consumption IT networkcleanness
costs at the buildingcosts at the building
high techhigh tech
optimized pipe design
optimized building layoutdaylight
backup supply
open wiring system optimized building layout
isolation of buildingsmart metering
smart E-metering, detailed consumption controlauto deactivating
smart metering the industrial trend:
design facilities for totalconsumption monitoring
pmTUC • image: Freie Presse 15.11.2009A. Hübler
![Page 17: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/17.jpg)
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of
management «costs»
17
standard tech high tech
• early knowledge of problems
• transparency of work
• quality of the products
automated operating data logging
no closed and hidden rooms
online & open display of work results, e.g. press speed, paper waste, plate imaging, …
the building and the design of a plant is also relevant to the quality of management of the later production.
automated quality control systems • paper, inks, … • customer data • own products
clear structure of the production
pmTUC A. Hübler
![Page 18: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/18.jpg)
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of
complete the decision
18
savings in production
need
ed in
vest
men
t
highlowlow
high
➊➋
➌
➍
➎
at a certain level of quality and quantity,the decision on technical alternatives is to do on
needed investment and later savings in production:
build a ranking of alternatives, until the budget limit it touched.
pmTUC A. Hübler
![Page 19: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/19.jpg)
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of
content
19pmTUC/IFRA special report 04.2009A. Hübler
1. define the project
2. project management
![Page 20: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/20.jpg)
sources:authors: Institute for Print & Media Technology of Chemnitz University of Technology Ⓒ 16. Jan. 2010
project structure
20 pmTUC/IFRA special report 04.2009A. Hübler
avoid back loops,everytime money is lost!
support, communication &
project organisation
![Page 21: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/21.jpg)
sources:authors: Institute for Print & Media Technology of Chemnitz University of Technology Ⓒ 16. Jan. 2010
don‘t save money at project organisation
21 pmTUC/IFRA special report 04.2009A. Hübler
good projects• have clear responsibilities.• have objectives as time &
resources and milestones with controlling
• have a project team which should cover the whole necessary mix of expert knowledge and methodological skills.
• schedule with three steps:1. the strategic decision for the general framework has to be done. 2. is to propose a catalogue of measures to achieve the objectives.3. The operative planning consists of detailed timelines and milestones each linked to the next step.
Make people of the initial decision process member of the later project team for
continuing responsibility.
![Page 22: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/22.jpg)
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of
1. collect really all issues
22pmTUC/IFRA special report 04.2009A. Hübler
1. Centralized or distributed fabrication2. Production capacity (back-up strategy)3. Format flexibility4. System reliability5. Market proximity6. Human resources7. Energy efficiency / green production8. Workflow, layout of the production9. Standardisation10. Legal environment
![Page 23: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/23.jpg)
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of
2. Take care about additional topics
23pmTUC/IFRA special report 04.2009A. Hübler
Standardisation
Legal issues
![Page 24: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/24.jpg)
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of
3. task planning
24pmTUC/IFRA special report 04.2009A. Hübler
project managementis possible in different detail levels
looking for interdependencies:
from strategic topics to stupid details: Is the door opening wide enough to put the inking unit in.
![Page 25: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/25.jpg)
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of 25
pmTUC/IFRA special report 04.2009A. Hübler
project management software is important
main project costs: have skilled user knowing to handle the software and setup a project
![Page 26: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/26.jpg)
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of
4. project controlling
26pmTUC/IFRA special report 04.2009A. Hübler
e.g., controlling of atarget-performance planning.typically 10% tolerances are accepted.
milestone targets →
1. analysis What happened? Why did it happen? Where? Who had been involved? When did it happen? Which consequences are expected?
2. corrective actionswithin different scenarios
finance targets ↓
![Page 27: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/27.jpg)
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of
5. risk management is helpful
27pmTUC/IFRA special report 04.2009A. Hübler
Classes of risks to take into account:• General project risks (e.g. failures in planning)• Technology risks (e.g. compatibility, feasibility)• Procedure risks (e.g. possible deficits)• Commercial risks (e.g. inflation, deficits in payment)• Personnel risks (e.g. staff availability, temporary
staff)• Environmental risks (e.g. political risks, climate,
catastrophes)• Supplier risks (e.g. deadline shift, quality assurance)• Contract risks (e. g. clear order formulation)
![Page 28: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/28.jpg)
sources:authors: Ⓒ 12.Jan.2010
Institute for Print & Media Technology of
summary
28
as early you invest in professional planningas more money you can save later.
if a decision for a new plant is made, than totally.
pmTUC A. Hübler
![Page 29: how to organize a newspaper project cost saving and cost ... · PDF filecost saving and cost control by Arved Huebler, Institute for Print & Media Technology, Chemnitz University of](https://reader031.vdocuments.site/reader031/viewer/2022011723/5a9fbc7c7f8b9a0d158d3f9d/html5/thumbnails/29.jpg)
member of
Institut für Print- und Medientechnik der TU Chemnitz[Institute for Print and Media Technology at Chemnitz University of Technology]
Director: Prof. Dr. Arved C. Hübler • Reichenhainer Str. 70 • 09126 Chemnitz • Germanyhttp://www.tu-chemnitz.de/pm • [email protected] • Phone: +49-371-531-23610 • Fax: -23619
how to organize a newspaper project cost saving and cost control
byArved Huebler, Institute for Print & Media Technology,Chemnitz University of Technology, Germany
Cost control, Revenue opportunities in productionWAN-IFRA Seminar for newspapers,
in association with TU Chemnitz18-19 January 2010, New Delhi
!