how to improve the ramp-up of block caving mines
TRANSCRIPT
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 1/29
“How to improve the ramp-up of
block caving mines” “Cómo mejorar la subida de producción enminas de block caving”
Alfonso Ovalle, Dr. Peter CepuritisAmec Foster Wheeler, Chile
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 2/29
How to improve the ramp-up of block caving mines
MOTIVATION
(Ref. 1)
90
80
70
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Years
10% 0.91 0.83 0.75 0.68 0.62 0.56 0.51 0.47 0.42 0.39 0.35 0.32 0.29 0.26 0.24 0.22 0.20 0.18 0.16 0.15 0.14 0.12 0.11 0.10 0.09 0.08 0.08 0.07 0.06 0.06 0.05 0.05
8% 0.93 0.86 0.79 0.74 0.68 0.63 0.58 0.54 0.50 0.46 0.43 0.40 0.37 0.34 0.32 0.29 0.27 0.25 0.23 0.21 0.20 0.18 0.17 0.16 0.15 0.14 0.13 0.12 0.11 0.10 0.09 0.09
6% 0.94 0.89 0.84 0.79 0.75 0.70 0.67 0.63 0.59 0.56 0.53 0.50 0.47 0.44 0.42 0.39 0.37 0.35 0.33 0.31 0.29 0.28 0.26 0.25 0.23 0.22 0.21 0.20 0.18 0.17 0.16 0.15
k t / d
D i s c o u
n t
r a t e s
Discount factors
Better production ramp-up will greatly affect NPV of the
project because of higher production in the early years,
usually of the better grades and at higher discount factors
Page 1 of 28
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 3/29
How to improve the ramp-up of block caving mines
BC RAMP UPS
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
0 1 2 3 4 5 6 7 8 9 10 11
P r o d u c t i o n , t /
d
Years
Production Ramp-up of BC Mines ____
Teniente 4 S Sector Dec. 1981
Page 2 of 28
(Ref. 2)
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 4/29
How to improve the ramp-up of block caving mines
BC RAMP UPS
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
0 1 2 3 4 5 6 7 8 9 10 11
P r o d u c t i o n , t
/ d
Years
Production Ramp-up of BC Mines ____
Teniente 4 S Sector
Esmeralda, El Teniente
Sep. 1997
Page 3 of 28
(Ref. 2)
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 5/29
How to improve the ramp-up of block caving mines
BC RAMP UPS
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
0 1 2 3 4 5 6 7 8 9 10 11
P r o d u c t i o n , t /
d
Years
Production Ramp-up of BC Mines ____
Palabora Lift 1
Teniente 4 S Sector
Esmeralda, El Teniente
Jun. 2001
Page 4 of 28
(Ref. 3)
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 6/29
How to improve the ramp-up of block caving mines
BC RAMP UPS
0
10
20
30
40
50
60
70
8090
100
110
120
130
140
0 1 2 3 4 5 6 7 8 9 10 11
P r o d u c t i o n , t /
d
Years
Production Ramp-up of BC Mines ____
Cadia East
Palabora Lift 1
Teniente 4 S Sector
Esmeralda, El Teniente
Dec. 2012
Page 5 of 28
(Ref. 4)
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 7/29
How to improve the ramp-up of block caving mines
BC RAMP UPS
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
0 1 2 3 4 5 6 7 8 9 10 11
P r o d u c t i o n , t
/ d
Years
Production Ramp-up of BC Projects ------
NNM, El Teniente 2019
Page 6 of 28
(Ref. 5)
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 8/29
How to improve the ramp-up of block caving mines
BC RAMP UPS
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
0 1 2 3 4 5 6 7 8 9 10 11
P r o d u c t i o n , t
/ d
Years
Production Ramp-up of BC Projects ------
PMCHS,
Chuquicamata
NNM, El Teniente
2018
Page 7 of 28
(Ref. 6)
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 9/29
2018?
How to improve the ramp-up of block caving mines
BC RAMP UPS
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
0 1 2 3 4 5 6 7 8 9 10 11
P r o d u c t i o n , t
/ d
Years
Production Ramp-up of BC Projects ------
Palabora Lift 2
PMCHS, Chuquicamata
NNM, El Teniente
Page 8 of 28
(Ref. 3)
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 10/29
How to improve the ramp-up of block caving mines
BC RAMP UPS
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
0 1 2 3 4 5 6 7 8 9 10 11
P r o d u c t i o n , t
/ d
Years
Production Ramp-up of BC Projects ------
Oyu TolgoiPalabora Lift 2
PMCHS, Chuquicamata
NNM, El Teniente
2018?
Page 9 of 28
(Ref. 7)
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 11/29
How to improve the ramp-up of block caving mines
BC RAMP UPS
0
10
20
30
40
50
60
70
8090
100
110
120
130
140
0 1 2 3 4 5 6 7 8 9 10 11
P r o d u c t i o n , t /
d
Years
Production Ramp-up of BC Mines ____
and Projects ------
Cadia East
Oyu Tolgoi
Palabora Lift 2
PMCHS, Chuquicamata
Palabora Lift 1
NNM, El Teniente
Teniente 4 S Sector
Esmeralda, El Teniente
Page 10 of 28
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 12/29
How to improve the ramp-up of block caving mines
ATTAINABLE BC RAMP UP
0
10
20
30
40
50
60
70
80
90100
110
120
130
140
0 1 2 3 4 5 6 7 8 9 10 11
P r o d u c t i o n , t / d
Years
Production Ramp-up of BC Mines ____
and Projects ------
PossibleCadia East
Oyu Tolgoi
Palabora Lift 2
PMCHS, Chuquicamata
Palabora Lift 1
NNM, El Teniente
Teniente 4 S Sector
Esmeralda, El Teniente
How?
Page 11 of 28
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 13/29
How to improve the ramp-up of block caving mines
ASPECTS THAT GOVERN THE RAMP UP
• Primary issue: the Cave Back Velocity (CBV)must be greater than the extraction velocity
• Undercutting rate Air gaps are to be avoided or minimized
• During cave propagation
Avoid big seismic events
• Extraction rate Fragmentation size at draw point
Design of caving system
Design of materials handling system design
• Risk prevention Operational hazards: rockburst, airblast
Design hazards, due to incorrect assessment of theground conditions
Page 12 of 28
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 14/29
How to improve the ramp-up of block caving mines
CAVE BACK VELOCITY
• Rock mass properties
– Intact strength & modulus
– Major structures
– Joint network geometry
– Joint strength & stiffness
• Stresses – In situ stress
– Induced stresses• Undercut size, shape and direction
• Draw strategy
• Adjacent mining
• Improving cave propagation
– Breakthrough to lowest elevation
– High undercutting
– Preconditioning the rock mass
Preconditioning
Page 13 of 28
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 15/29
How to improve the ramp-up of block caving mines
PRECONDITIONING THE ROCK MASS
• Teniente (widespread use of hydrofracturing)
Mitigation of rock bursts
Faster cave back velocity
• Cadia East (intensive pre-conditioning cave back velocity of 1.1 m/d)
Hydrofracturing High undercutting Confined Blasting
150 m
450 m
1,200 m to surfacetook less than 3 years
Page 14 of 28
(Ref. 3)
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 16/29
How to improve the ramp-up of block caving mines
GREEN LIGHT FOR FASTER RAMP UP
• Cave propagation velocity in hard rock of 1.1 m/d…
NOW A DESIGN PROBLEM
Increase Increase
undercutting rate extraction rate
Page 15 of 28
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 17/29
How to improve the ramp-up of block caving mines
FASTER RAMP UP
•Increase undercutting rate: – Maximize undercutting velocity
• Post undercutting, if possible
• Establish more than one undercutting front
• Undercutting front in spear shape
•Split levels
– Simple design
– Enhance planning, equipment, services and logistics
• Increase extraction rate:
– Design for more area availability• If LHD, shorter tramming
• RGO option (rock breaker, grizzly, ore pass)
• Continuous mining option
Page 16 of 28
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 18/29
How to improve the ramp-up of block caving mines
DRAW RATE WITH LHD’s
•
Draw rate with LHD system. Rim crushers arrangement. Long tramming distances
- At 300 m from DP to crusher, a 12 t/bucket LHD produces 3,000 tpd
- If Production Drift is 240 m long and distance between drifts is 30 m, it uses 7,200 m2
- Maximum draw rate possible is 3,000 / 7,200 = 0,42 tpd/m2
- If density is 2.70 t/m3
- Maximum draw down rate is 0.50 / 2.7 = 0.15 m/d- Using 75% utilization factor:
- Maximum Planning draw down rate is 0.12 m/d
240 m
30 mTo rim
crusher
Page 17 of 28
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 19/29
How to improve the ramp-up of block caving mines
MAKING DRAW RATE FASTER WITH LHD’s
•
Draw rate with LHD system. Ore passes at 120 m & haulage level. Ore pass and rock breaker in Production Drift arrangement
- A 12 t/bucket LHD produces 4,000 t/d (controlled by interference with rock breaker)
- With 120 m between OP and distance between drifts of 30 m, it uses 3,600 m2
- Independent ventilation for each 120 m segment to use an LHD
- Maximum draw rate possible is 4,000 / 3,600 = 1.11 tpd/m2
- If density is 2.70 t/m3
- Maximum draw down rate is 1.11 / 2.7 = 0.41 m/d
- Using 75% utilization factor
- Maximum Planning draw down rate is 0.31 m/d
120 m
30 m
120 m
Ore passes to Haulage Level
Page 18 of 28
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 20/29
How to improve the ramp-up of block caving mines
MAKING DRAW RATE FASTER WITH LHD’s
•
Draw rate with LHD system. Ore passes at 80 m & haulage level. Ore pass and rock breaker in Production Drift arrangement
- A 12 t/bucket LHD produces 4,200 t/d (controlled by interference with rock breaker)
- With 80 m between OP and distance between drifts of 30 m, it uses 2,400 m2
- Independent ventilation for each 80 m segment to use an LHD
- Maximum draw rate possible is 4,200 / 2,400 = 1.75 tpd/m2
- If density is 2.70 t/m3
- Maximum draw down rate is 1.11 / 2.7 = 0.65 m/d
- Using 75% utilization factor
- Maximum Planning draw down rate is 0.49 m/d
80 m 80 m 80 m
30 m
Ore passes to Haulage Level
Page 19 of 28
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 21/29
How to improve the ramp-up of block caving mines
MAKING DRAW RATE FASTER WITH RGO
• RGO System (rock breaker, grizzly, ore pass)
Rock breaker directly on draw point to a grizzly
Grizzly connected to short ore pass
Lower collection level (with panzer feeder going to sizer or central OP)
• Concepts of RGO System
Rock breakers are teleoperatedo Less ventilation required
o More operating hours possible
Production drifts belong to secondary blasting and hang up crews! High area utilization possible
No diesel drives
Page 20 of 28
(Ref. 8)
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 22/29
How to improve the ramp-up of block caving mines
MAKING DRAW RATE FASTER WITH RGO
2.000
2.500
3.000
3.500
4.000
4.500
5.000
0 30 60 90 120
P r o d u c t i v i t y ,
t / d
% Extraction
t/d, 20" x 36" grizzly
t/d, 20" x 20" grizzly
• Rock Breaker Productivity (Ten 4 Fw test, primary ore)
Page21 of 28
(Ref. 8)
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 23/29
How to improve the ramp-up of block caving mines
MAKING DRAW RATE FASTER WITH RGO
• RGO System (rock breaker, grizzly, ore pass)
Draw rate calculation of RGO System
- One rock breaker produces 2,300 t/d (lowest rate at 30% extraction)
- One rock breaker for every 4 DP, or 40 m. Distance between drifts of 30 m, it uses 1,200 m 2
- Independent ventilation for every three rock breakers
- Maximum draw rate possible is 2,500 / 1,200 = 1.92 tpd/m2
- If density is 2.70 t/m3
- Maximum draw down rate is 2.08 / 2.7 = 0.71 m/d
- Using 75% utilization factor
- Maximum Planning draw down rate is 0.53 m/d
|
40 m
30 m
40 m 40 m 40 m 40 m 40 m
Page 22 of 28
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 24/29
How to improve the ramp-up of block caving mines
MAKING DRAW RATE FASTER
LHD,
240m
LHD,
120m
LHD,
80mRGO,
15%E
RGO,
45%E
RGO,
75%E
RGO,
105%E
0,00
0,10
0,20
0,30
0,40
0,50
0,60
0,700,80
0,90
1,00
1,10
1,20
D r a w
R a t e , m / d
Block Caving Systems
Draw Rates,LHD and RGO Systems
Page 23 of 28
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 25/29
How to improve the ramp-up of block caving mines
EVALUATION OF RAMP-UP INCREASE
The following block cave project was evaluated with normal and steeper
ramp-up production periods, caused by the following:
UNDERCUTTING RATE:
Increased from
34,000 m2/yr to
48,000 m2/yr for 2 years
DRAW RATE:
Increased from
0.20 m/d to 0.40 m/d
RESULT:
Ramp up was shortened
from 9 to 4 years
Page 24 of 28
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 26/29
How to improve the ramp-up of block caving mines
EVALUATION OF RAMP-UP INCREASE
MUS$ %
NPV (8%) SLOW RAMP UP: 455 100
NPV (8%) FAST RAMP UP: 1,009 222
Total increase: 554 122
Due to Draw Rate increase: 400 88
Due to Undercutting Rate increase: 154 34
Page 25 of 28
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 27/29
How to improve the ramp-up of block caving mines
CONCLUSIONS
• Intensive preconditioning of the rock mass green light for higherextraction rates
– High Undercut: helps early draw rates and prevents collapses
– HF preconditioning: proven technology to improve the caving velocity
– Forced Fragmentation Blasting: drill and blast to break base of columns
– Vertical Shaft: to connect UCL to surface that serving as path/guide
• BC designs need to increase extraction rates
– LHD systems: can go up to around 0.50 m/d, with difficulty
– RGO system: can go beyond 0.50 m/d, with ease
• Ramp up of BC projects can be shortened, with very important increase of
the NPV.
Page 26 of 28
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 28/29
How to improve the ramp-up of block caving mines
REFERENCES
1. Mass caving maximum production capacity, Alfonso W. Ovalle, Amec International; University of Chile,
MASSMIN 2012, June 11-14, 2012, Sudbury, Ontario, CANADA2. Lecciones Aprendidas Explotación El Teniente, A. Ovalle, Set. 2006
3. Block caving with Rio and NCM, Credit Suisse, 27 Set 2012, Visit Report
4. Newcrest Mining Company Quarterly Reports
5. Presentación NNM, J. Revuelta, Nov. 2013
6. Presentación PMCHS, S. Fuentes, Abr. 2013
7. Turquoise Hill Resources Ltd. Oyu Tolgoi 2014 Technical Report, October 2014, Job N° 14003, OreWin,
Independent Mining Consultants, Figure 1.7, 2014 Reserve Case processing, pg. 28
8. Martillos picadors semi-móviles en Teniente 4 Norte Fw, 1990. Comunicaciones con A. Moyano.
Page 27 of 28
7/23/2019 How to improve the ramp-up of block caving mines
http://slidepdf.com/reader/full/how-to-improve-the-ramp-up-of-block-caving-mines 29/29
How to improve the ramp-up of block caving mines
END
Thank you for your attention
Page 28 of 28