how microsoft it migrated sharepoint to office 365
DESCRIPTION
For 12 years Microsoft IT built and maintained a global SharePoint deployment at Microsoft. In 2012 MSIT was given a new mission – get Microsoft’s SharePoint deployment into the cloud. This session lead by Sam Crewdson explores some of the challenges that MSIT faced in moving an enterprise deployment to the cloud and will talk about lessons learned during that experience.TRANSCRIPT
MSIT Office 365 Migration
Phase I - Extranet
1
Seattle Dublin
Singapore
23.38 TB121,907 Sites
269,862 Sub-
sites
5.38 TB36,716 Sites
66,670 Sub-
sites
7.65 TB41,064 Sites
96,184 Sub-sites36.41 TB( 36,140,018 MB )
199,687 Sites
432,716 Sub-
sites
64%21%
15%
SharePoint
UtilityCustom Portals &
Applications
Cost Savings
• Less infrastructure to maintain
• No more SharePoint upgrades
• HA and DR built into the service
• Lower cost per user
User Benefits
• Social collaboration
• SkyDrive Pro
• Access to corporate SharePoint resources
regardless of location or device
• Enabler of MSIT’s Consumerization of IT strategy
Why the Cloud?
"Each Microsoft product group is moving to the cloud as a fundamental business platform.”
-Microsoft Build, 2011
“This is the bet for the company. For the cloud, we’re all in”
-University of Washington, 2010
MSIT should have the goal of "making the cloud the center of our IT development and planning process."
-Memo 2011
BackupsBackupsSourceDB
BackupUpgradeDB
Backup BackupsUpload Target
MSIT Data Center
40 GB/hour
v14 v15 v15DBs
Incremental Sync
Read/Write
Database Backup & Restore
• Two concepts
• Fly all databases to SPO datacenter and restore
• Longer read only window, done in one fell swoop
• Break into batches
• Sites stay in Read/Write while db’s flown over
• Sites locked when incremental updates flown over following weekend
• Limits Read Only window to 72 hours; weekend maintenance windows
Attach,
Fix Links, Scrub
Perms,
Delete Deferred
DB
Restore
Scrub
Customizations
BackupsBackupsSourceSite
BackupUpgradeMirror BackupsUpload BackupsBackupsBackups Target
Site
Restore
MSIT Data Center
Site Collection Backup/Restore :
• Granularity to keep the read/only window ~ 24 hours, enabled weekday execution
• Site Restore triggers the link fix-up we need to move the host name
• ~ 200 GB or ~1000 sites per day (whichever comes first)
• Requires two staging environments, very manual
40 GB/hour
v14 v15 v15
Read Only
Scrub
IdentityScrub
Customizations
MSIT Site
CollectionFull Migration Office365
MSITOffice 365
(Datacenter)
Migration
ToolRead/Write
Third-party tool migration process:
• Perform full migration using migration tool.
• Once full migration complete, reminder to site owner of pending
site collection move
• Start incremental migrations to run continuously until move cut-
over window =<48 hours
• Sites set to Read Only, final incremental completed
• On-premise sites locked, redirected to SharePoint Online
• Completion mail sent to site owner
Read Only
Incremental Migration
Site Lock
Scenario Recommendation
http://technet.microsoft.com/en-us/library/jj838715.aspx
www.bpcs.com
Contact Us
Thank you for
attending
29