HOUSING PARTNERS I, INC. 715 E. BRIER DRIVE, SAN BERNARDINO, CA 92408
(909) 890-0644 FAX (909) 890-2349
ADDENDUM #1 FOR RFP PC649 – Rehabilitation of 68 “HOME” funded Rental Units-various locations County of San Bernardino The following addendum to this Request for Proposal is hereby incorporated into the bid process. PLEASE NOTE: Questions and Answers: The following topics and clarificationss were asked during the Job Walk. Please review the responses and include them in your proposals.
General Information Work Hours 8:00 AM – 4:30 PM Monday- Friday
90 Days to complete
Units will be occupied, will schedule with Beacon Property for access
Site to be clean at end of each day
Davis – Bacon Wages
Contractor responsible for all permits
Contractor responsible for any damages caused by work, workers
All ADA work to meet the “2010 ADA Standards for Accessible Design”
Roofing
No access to roofs
All roofs guarantee to be water tight for ten years
Contractor to provide price for sheathing replacement
Roofing and exterior repairs to include all buildings on each property
All unused antennas or dishes to be removed, if antenna, replace after roofing
Roofer to install appropriate venting using dormer and ridge vents
All vents to be painted to match roof color
Spec: Tear off and dispose of existing roofing down to wood sheeting.
Housing Authority Of The County of San Bernardino
Thoroughly inspect roof sheeting for dry rot. If dry rot is found it shall be
replaced on a time and material basis.
Install metal edge around entire perimeter.
Nail one 30 lb. non-perforated rag felt over entire roof area.
Install new Owens Corning Oakridge Pro 30 fiberglass shingles according to
manufacturer’s specifications. Color to be determined per site
Seal all pipes and penetrations using flashing cement.
Paint all pipes and vent flashings.
Page 2 of 14
Page 2 of 14
Remove all roofing debris.
A standard 10 year guarantee shall be issued upon completion
Water Heater
Insulate each water heater replaced
Water heater – six year warranty SCAQMD Rule 1121 compliant
Replace supply lines
Can reuse venting
Can reuse pressure relief piping (new valve)
All water heaters to be earthquake strapped
Replace gas flex line
Replace gate valves with ball valves
Interior Stains/ Mold / Mildew
Maintenance staff is responsible for these repairs
Wall furnace
Williams natural gas, 35,000 BTU
Window replacement
We must keep egress
All windows must be installed and operational at end of each day
Window replacement includes sliding glass doors
Exterior painting
Repair dents and paint entry doors
Painting to include all buildings on property, trash enclosures and CMU walls
Painting to include carports
Forced Air Units
SEERs rating for FAU? These are not A/C units Furnace only
80% efficiency, up flow, three ton York Furnace
60,000 BTU output, 120,000CFM output
Reuse ducting, insulate exposed ducting, replace gas flex lines
Cooler specs
A. Unit shall be rated in accordance with AMCA Standard 210.
B. Cooler cabinets, blower housings and blower wheels shall be protected against
“rust-out” for a period five (5) years from the date of installation, but the
manufacturer’s limited warranty, providing operations and maintenance
recommendations are followed.
C. Pumps shall be protected against defective material or workmanship for a
period of two (2) years from date of installation.
2.1. CABINET
A. The cooler cabinet, blower housing and blower wheel shall be constructed of
heavy gauge, rust and corrosion inhibiting, hot-dipped galvanized steel.
B. The cooler cabinet shall be protected inside and outside with a baked polyester
enamel.
C. The water reservoir shall be die-formed, welded seam construction. Mastics or
adhesive coatings are not acceptable.
D. The water distribution internal to the unit shall be PVC.
Page 3 of 14
Page 3 of 14
E. The water troughs shall be fully visible and adjustable from the outside of the
cooler, without removing louver assembly.
PART 3-INSTALLATION
A. Remove currently installed evaporative Cooler block-out.
B. Provide and install Evaporative Cooler
C. Provide and install all plumbing piping (1/4” copper tube) and fitting as
necessary to tie to existing water source
D. Provide and install evaporative cooler support frame, attach to roof with
screws/anchors
E. Provide and install all caulking and sealant for a weather-tight installation
F. Provide and install PVC overflow drain, extend approximately 5’-0 min. to
roof gutters
Cooler service
Remove scale build up, clean pan, adjust belt, replace pads, clean out spider lines,
oil bearings, replace pump basket
7333 Dumoas, Yucca Valley Cooler replacement with same size 3500 CFM
The grading should lead the storm water out of the court yard past the trees near the street
Asphalt patch seal and strip – north driveway patch and seal up to concrete channel
ADA install two ramps one at each of the ADA parking stalls first parking space in each
lot on the west side. Include signage and markings.
Water heaters 40 Gallon
Do not paint the fence
How to replace window close to push-outs trim the flange
Landscaping
Page 4 of 14
Page 4 of 14
Page 5 of 14
Page 5 of 14
Page 6 of 14
Page 6 of 14
52601 Papago, Yucca Valley ADA parking to be the closest spot neat the laundry room, provide signage, markings and
ramp
Contractor to provide price for drywall repairs per square foot to include acoustic texture
Replace chain link fence around the playground area (laundry room to north building)
Replace the pole light around the site. Pole 10’ light fixture (Monterey Lighting provide
spec)
Price per liner foot to repair fencing
Painting to include laundry room, trash enclosure
Roofing to include laundry room
Page 7 of 14
Page 7 of 14
55730 Pueblo, Yucca Valley Replace handrails to 1-1/4 to 1/1/2 inch in diameter not the 2” currently installed. Include
handrail extensions to bring up to code.
Repair tile roof, re-roof flat roof
Replace sliding glass doors
ADA Parking spot located directly across from ramp include signage and markings
Erosion – move dirt back to low spots
Replace all fascia
Replace wood trim top half of south side of south building
Remove and replace/repair rain gutters
Steps – to include a strip of contrasting color a tread nosing to comply with accessibility
guidelines
Decks and steps, waterproof, remove existing and recoat using the three coat fiberglass
system
Replace patio gates.
Replace all wood caps around patios and stairs.
Paint trash enclosure door black, block to match exterior of buildings
Replace screen doors with security screen door – white expanded steel mesh, include
passage knob and dead bolt.
Page 8 of 14
Page 8 of 14
Page 9 of 14
Page 9 of 14
4743 - 4733 Kinsley & 4805 - 4807 Kinsley, Montclair
Grade the common area between 4743-4733 to prevent storm water from pooling on the
lot. Reseed the lawn when complete. Repair any damages caused by work.
Strip roof to sheathing and re-roof
Replace damage starter boards when roofing
Replace water heater doors at 4805 & 4807
Install earthquake straps for all units
No repair /replacement work required on CMU wall where cracked
Remove dirt from building to form a gradual slope
Repair/replace trim around garage doors
Transition asphalt coating into alley way asphalt
Page 10 of 14
Page 10 of 14
Remove pine tree and grind stump 6 inches below surface south east corner of 4807
Page 11 of 14
Page 11 of 14
10369-10379 Pradera, Montclair
Asphalt – patch holes, resurface, and strip (within the property lines)
No ADA parking or markings
Cane detection under steps per 2010 ADA Standards for Accessible Design
Enclose the open risers of the steps and paint appropriately
Paint wrought iron fencing and stair railing
Coolers replace five service three
Replace two Forced air units will Identify are start of job
Remove deck coating water proof decks with three step system
Page 12 of 14
Page 12 of 14
5161 Bandera, Montclair
Replace all pole light fixtures
Paint all buildings include common area walls, and fences
Re-roof all buildings
No ADA parking or marking
Property Management to repair sprinklers
Replace front doors – six panel metal clad door paint to match
Install and properly adjust weather stripping (ridged screw to jamb type)
Remove and rehang screen door
Four coolers to be replaced remaining to be serviced
Page 13 of 14
Page 13 of 14
18172 Larkspur / 18185 Casaba, Adelanto
Where asphalt lifted, grind and fill
Create an ADA parking stall next to building at end of carport.
Make ramp for ADA parking stall to walkway
Replace the patio slab at apartments Larkspur #7 and Casaba #3
Install correct flashing above the laundry rooms attaching to building
Page 14 of 14
Page 14 of 14
Should you have any questions regarding this Addendum, or any other part of this RFP process, please e-mail them to Marsha Zeller, [email protected]; or fax them to Marsha Zeller (909) 890-2349.