Honeoye Falls-Lima Central School District
2016 Additions and Alterations Phase 2
Project Update
December 2019
2016 Additions and Alterations Phase 2
Referendum Value $29,986,084
Incidental Budget $ 4,632,681
Construction Contingency $ 1,564,311
Contracts Awarded $22,848,873
State Contract $ 940,219
Construction Contingency Budget Update
•Construction Contingency Budget $1,564,311
•Additional Co-Op Purchases $ 100,877
•Additional Credit $ 63,092
•Approved Change Orders $ 985,680
•Remaining Construction Contingency $ 540,846
•Construction Project is 69% Complete
•Contingency Budget is 65% spent
•Contract allowance approved totals $0
•Project Team is following approximately $290,744 in pending issues
and $55,080 in pending State Contract Purchases.
2016 Additions and Alterations Phase 2
Project Status/Schedule Update
Manor Intermediate
• Construction is complete in the Art
Room and Discovery Lab and
moveable furniture is being delivered.
• The Faculty Lounge, Sensory Room
and Work Room are complete and
have been turned over to the District.
• Demolition has begun in Rooms 301,
304 and 306.
Transportation Building
• Foundation work continues, while
structural masonry walls are being
installed along with plumbing and
electrical rough-in.
Senior High School
• Construction continues in the Flex Space and
Conference Room on the 2nd Floor.
• The Cafeteria ductwork is roughed in and
soffits are being framed. Masonry walls are
being built and all under slab MEP’s are
roughed in.
• The Girls Pool Locker Room is complete.
• Electrical rough in is on going for door access
in the lobby and conduit has been roughed in
on the stairwell wall in preparation for the wood
paneling.
2016 Additions and Alterations Phase 2
Project Status/Schedule Update
Lima Intermediate
• Construction continues in room 116
with the rough in of mechanical piping
for the radiant heaters in the
classrooms above.
• Ductwork is being roughed in in
room 116.
• Rooms 206 and 210 are being
roughed in electrically and
mechanically and await wall repairs
which will be followed with radiant
heat installation and casework.
Middle School
• The Projection Screen has been installed,
wired and the work for the proscenium has
been completed.
• The casework for the Alumni Hall of Fame is
being built and is scheduled to be delivered the
week of the Jan 20th.
2016 Additions and Alterations Phase 2
What to expect in the upcoming Month
Manor Intermediate
• Construction will continue in rooms
301, 304 and 306.
• Room 302 will be completed and
turned over by the end of the month.
• Demo will begin in rooms 308, 310,
312 and 314 with the completion of
rooms 301, 304 and 306.
Senior High School
• Paneling is scheduled to arrive for the
Lobby and installation will follow.
• Wall and soffits will continue to be built
in the Kitchen and Cafeteria Area.
• The Flex Space and Conference Room
will continue to be under construction.
2016 Additions and Alterations Phase 2
What to expect in the upcoming Month
Middle School
• The Alumni Hall of Fame installation
will begin.
Lima Elementary
• Construction will be nearly complete in
room 116 and will continue in rooms 206
and 210.
Honeoye Falls-Lima Central School District
2016 Additions and Alterations Phase 2
Progress Photos
Existing Bays – Transportation Center
Existing Bays – Tansportation Center
Art Room - Manor
Art Room - Manor
Sensory Room - Manor
Faculty Lounge - Manor
Work Room – Manor
Classroom 301- Manor
Classroom 306 - Manor
Classroom 304 - Manor
Discovery Lab – Manor
Cafeteria Corridor – High School
Cafeteria – High School
Cafeteria – High School
Flex Center – High School
Flex Corridor – High School
Art Room – High School
Art Room – High School