ho bs installation
DESCRIPTION
ALVARION INSTALACIONTRANSCRIPT
-
Alvarion Training Services (ATS)
BreezeMAX
Hands on Assignment Hardware Installation
-
Hands On Assignments Hardware Installation
BreezeMAX
2
2
2
Hardware Installation
The main goal of this part is to enable the students to install the different
cards of a BreezeMAX FDD Macro Base Station. The participants can use
the information provided in the technical presentation.
1. Build the setup as described in the diagram at the end of this part. This
will be the configuration we will use for the rest of the training. (You can
have a different number of PIUs/PSUs/IDUs)
2. In the Base Station Chassis install the PIU(s) (1 or 2 per BS)
3. Install the PSUs (up to 4 per BS)
4. Install the NPU
5. Install the IDU(s) (up to 6 per BS)
6. Power up the chassis and confirm the proper operation