Page 1 HMI/AIA Science Meeting – February 13, 2006 HMI Instrument Status HM/AIA Science Meeting February 13, 2006 Barbara Fischer HMI Deputy Program Manager LMSSC*ATC*LMSAL [email protected] 650-424-2838

Upload: otto-wilder

Post on 04-Jan-2016

19 views

Category:

Documents


0 download

DESCRIPTION

HMI Instrument Status HM/AIA Science Meeting February 13, 2006. Outline. A year in the life of HMI development HMI assembly progress HMI testing progress Near term events Schedule summary The last time we met, we had finished CDR and were starting structural model testing. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: HMI Instrument Status HM/AIA Science Meeting February 13, 2006

Page 1 HMI/AIA Science Meeting – February 13, 2006

HMIInstrument Status

HM/AIA Science MeetingFebruary 13, 2006

Barbara Fischer

HMI Deputy Program Manager

LMSSC*ATC*LMSAL

[email protected]

650-424-2838

Page 2: HMI Instrument Status HM/AIA Science Meeting February 13, 2006

Page 2 HMI/AIA Science Meeting – February 13, 2006

Outline

• A year in the life of HMI development

– HMI assembly progress

– HMI testing progress

• Near term events

• Schedule summary

The last time we met, we had finished CDR and were starting structural model testing.

Page 3: HMI Instrument Status HM/AIA Science Meeting February 13, 2006

Page 3 HMI/AIA Science Meeting – February 13, 2006

HMI Assembly Status

Structural model testing completed ETU oven testing completed BB HEB fabrication completedSUROM acceptance test completed

mission CDR

Received flight MichelsonsAll flight optics in house

Received flight metering tubeCompleted telescope alignment

Received flight structureStart alignment on GSE bench

Hollow core motors completedReceived DM cameras

Received 4 grade zero CCDs

Alignment mechanism completedStarted optical alignment of HOP

BB HEB and EGSE readyShutter & F/C wheels completed

Internal harness completed

Lyot completedInternal mechanisms tested

Focal plane completedOven completed

First image

Page 4: HMI Instrument Status HM/AIA Science Meeting February 13, 2006

Page 4 HMI/AIA Science Meeting – February 13, 2006

HMI Assembly Status

Optics Package Assembly

Detector Assembly(Non-Flight)

CEB (Non-Flight, DM1)

Flex-Cables(Eng Model)

Telescope(Flight)

Front Window(Flight)

Primary work after Sun testing:• Bond optics in place• Replace painted parts (including the oven)• Replace one HCM and focus/cal optical mounts

ISS Mirror(Flight)

Polarization Selector(Flight)

Focus/Cal Wheels(Flight)

Limb Sensor(Non-Flight)

ISS Beam Splitter(Flight)

Oven Assembly(non-flight)Parts to replace:E1 and E2 in LyotNB MichelsonPainted housing

BDS Beamsplitter(Flight, hidden by shutter)

Shutters(Flight)

BDS Fold Mirror(Flight)

CCD Fold Mirror(Flight, hidden by detector)

Alignment Mechanism(Flight, hidden in view)

Internal Harness(Flight, not complete)

Limb Pre-amp Box(Flight, not complete)

StructureW/ legs and heaters(Flight)

Oven Controller(ETU)

Page 5: HMI Instrument Status HM/AIA Science Meeting February 13, 2006

Page 5 HMI/AIA Science Meeting – February 13, 2006

HMI Testing Progress

12/22/06 02/01/0601/30/0601/25/0601/11/06

Tests Performed:

Initial set up w/ lampFocus test w/ lampDistortion, field curvature and MTF w/ lampFocus test w/ SunFilter wavelength dependence w/ Sun

Filter wavelength dependence w/ laserField curvature and MTF w/ SunPolarization calibration w/ Sun

Tests In Progress:

Laser dotBefore holidayNo relay lensNo Lyot No frt Window

Special targetLamp - stim telLyot installedTemp mnt for relay lensNot fully aligned stim tel

Air Force targetLamp - stim telAll together

Laser intensity improved

“HMI is Alive”First Image “Special Target”

First Lamp Image “Ready to Test”Instrument All Together “No More Moon”

Better Laser Image “It’s a Beautiful Day”First Sun Image

Just sunlightWith air/vac corrector

Page 6: HMI Instrument Status HM/AIA Science Meeting February 13, 2006

Page 6 HMI/AIA Science Meeting – February 13, 2006

HMI Testing Progress

First Magnetogram First Dopplergram

Page 7: HMI Instrument Status HM/AIA Science Meeting February 13, 2006

Page 7 HMI/AIA Science Meeting – February 13, 2006

Upcoming Events

• Near term key hardware items

– Continue Sun testing

– Continue ISS testing

– Complete rebuild of oven• Replace Lyot E1 and E2

• Replace narrow band Michelson

– Replace one wave plate mount and focus block mounts

– Bond optics in mounts

– Install flight focal planes and align CCDs

• Further out

– In air calibration Mid April – May

– Vacuum calibration June – mid July

Page 8: HMI Instrument Status HM/AIA Science Meeting February 13, 2006

Page 8 HMI/AIA Science Meeting – February 13, 2006

Schedule Summary

• Complete initial testing Feb 06

• Complete instrument integration April 06– Except flight camera electronics box

• Pre-Environmental Review April 06

• Instrument calibration April – July 06– In air April – May 06

• Need brassboard camera interface board

• Use demonstration camera electronics box

– In vacuum June – July 06• Mid-stream install flight camera electronics box

• HOP vibration & acoustic test July 06

• Comprehensive performance test Aug 06– With flight HMI electronics box

• Instrument EMI/EMC test Sept 06

• HMI electronics box vibration test Oct 06

• Thermal vacuum cycling and balance test Nov – Dec 06

• Comprehensive performance test Dec 06

• Alignment with instrument module panel Jan 07

• Pre-Ship Review Jan 07

• Ship to Goddard Feb 07