hk notabletunnel cat

380
Catalogue of Notable Tunnel Failures - Case Histories (up to April 2015) Prepared by Mainland East Division Geotechnical Engineering Office Civil Engineering and Development Department

Upload: anar

Post on 13-Sep-2015

21 views

Category:

Documents


9 download

DESCRIPTION

HK NotableTunnel Cat

TRANSCRIPT

  • Catalogue of Notable

    Tunnel Failures -

    Case Histories

    (up to April 2015)

    Prepared by Mainland East Division Geotechnical Engineering Office

    Civil Engineering and Development Department

  • This catalogue of notable tunnel failures is primarily

    based on published information. Both local and international

    cases involving collapse or excessive deformation of the

    ground are included. For contractual and other reasons, there

    are relatively few cases reported in technical publications, and

    those reported are usually of such scale or seriousness that

    they have received public attention. Even for the cases reported,

    usually only limited information is available. Apart from the

    cases included, readers can find other information on tunnel

    failure in the list of Bibliography given at the end of this

    catalogue.

    This catalogue is a live document that will be updated

    from time to time as further information becomes available.

    Readers are always welcome to provide us with additional

    information about cases in this catalogue for future update.

  • The main purpose of the catalogue is to disseminate

    information and promote awareness on tunnel failures which

    could pose a danger to life and property. The possible causes

    of the failures, the geotechnical problems and the lessons learnt,

    where these are known, are outlined in the catalogue. Readers

    should refer to the source reference documents quoted for

    details. Clients and works agents are advised to implement

    effective geotechnical risk management measures in the

    planning, investigation, design and construction of their tunnel

    projects.

  • The first edition of the catalogue was issued in February

    2007 and was put together by Mr W Lee, supervised by Mr K J

    Roberts. The second edition issued in March 2009 was prepared

    by Ms L Y Pau, supervised by Mr L P Ho. The third edition issued

    in October 2012 was prepared by Ms L Y Pau, supervised by Mr K

    S Chau. This fourth edition was prepared by Ms K L Wong and Mr

    H H Chan, supervised by Mr K S Chau. GEO staff, members of the

    Hong Kong Institution of Engineers Geotechnical Division

    Working Group on Cavern and Tunnel Engineering and other

    individuals have contributed to this catalogue. All contributions

    are gratefully acknowledged. Special thanks are given to Mr Guy

    Lance for his valuable advice and guidance given to revising the

    systematic structure of this catalogue, sourcing figures and

    references from tunnel publications as well as editing reported

    cases.

  • If any information in this catalogue is found to be

    inaccurate or out-of-date, please contact the Chief Geotechnical

    Engineer/Mainland East of the Geotechnical Engineering Office,

    Civil Engineering and Development Department, 101 Princess

    Margaret Road, Ho Man Tin, Kowloon, Hong Kong.

    N F Chan

    Chief Geotechnical Engineer/Mainland East

    Geotechnical Engineering Office

    Civil Engineering and Development Department

    April 2015

  • Civil Engineering and Development Department

    The Government of the Hong Kong Special Administrative Region

    1. Green Park, London, UK, 1964

    2. Victoria Line Underground, London, UK, 1965

    3. Southend-on-sea Sewage Tunnel, UK, 1966

    4. Rrvikskaret Road Tunnel on Highway 19, Norway, 18 March

    1970

    5. Orange-fish Tunnel, South Africa, 1970

    6. Penmanshiel Tunnel, Scotland, UK, March 1979

    7. Munich Underground, Germany, 1980

    8. Holmestrand Road Tunnel, Norway, 16 Dec. 1981

    9. Gibei Railway Tunnel, Romania, 1985

    10. Moda Collector Tunnel, Istanbul Sewerage Scheme, Turkey, 1989

  • Civil Engineering and Development Department

    The Government of the Hong Kong Special Administrative Region

    11. Seoul Metro Line 5 - Phase 2, Korea, 17 Nov. 1991

    12. Seoul Metro Line 5 - Phase 2, Korea, 27 Nov. 1991

    13. Seoul Metro Line 5 - Phase 2, Korea, 11 Feb. 1992

    14. Seoul Metro Line 5 - Phase 2, Korea, 7 Jan. 1993

    15. Seoul Metro Line 5 - Phase 2, Korea, 1 Feb. 1993

    16. Munich Underground, Germany, 27 Sept. 1994

    17. Heathrow Express, UK, 21 Oct. 1994

    18. Los Angeles Metro, USA, 22 June 1995

    19. Motorway Tunnels, Austria, 1993 - 1995

    20. Docklands Light Rail, UK, 23 Feb. 1998

  • Civil Engineering and Development Department

    The Government of the Hong Kong Special Administrative Region

    21. Athens Metro, Greece, 1991-1998

    22. L rdal Road Tunnel on European Highway E 16, Norway, 15

    June 1999

    23. Sewage Tunnel, Hull, UK, 1999

    24. Taegu Metro, South Korea, 1 Jan. 2000

    25. Wastewater Tunnel, Portsmouth, UK, May 2000

    26. Dulles Airport, Washington, USA, Nov. 2000

    27. Istanbul Metro, Turkey, Sept. 2001

    28. Channel Tunnel Rail Link, UK, Feb. 2003

    29. Mtor Metro Tunnel, France, 14 Feb. 2003

    30. Oslofjord Subsea Tunnel, Norway, 28 Dec. 2003

  • Civil Engineering and Development Department

    The Government of the Hong Kong Special Administrative Region

    31. Shanghai Metro, China, 2003

    32. Nikkure-yama Tunnel, Japan, 2003

    33. Guangzhou Metro Line 3, China, 1 April 2004

    34. Singapore MRT, 20 April 2004

    35. Kaoshiung Rapid Transit, Taiwan, 29 May 2004

    36. Oslo Metro Tunnel, Norway, 17 June 2004

    37. Kaoshiung Rapid Transit, Taiwan, 10 Aug. 2004

    38. Hsuehshan Tunnel, Taiwan, 1991-2004

    39. Barcelona Metro, Spain, 27 Jan. 2005

    40. Lausanne M2 Metro, Switzerland, 22 Feb. 2005

  • Civil Engineering and Development Department

    The Government of the Hong Kong Special Administrative Region

    41. Lane Cove Tunnel, Australia, 2 Nov. 2005

    42. Kaoshiung Rapid Transit, Taiwan, 4 Dec. 2005

    43. Nedre Romerike Water Treatment Plant Crude Water and Potable

    Water Tunnels, Norway, 2005

    44. Interstate 90 Connector Tunnel, Boston, Massachusetts, USA, July

    2006

    45. Hanekleiv Road Tunnel, Norway, 25 Dec. 2006

    46. Stormwater Management and Road Tunnel (SMART), Malaysia,

    2003 2006

    47. Sao Paulo Metro Station, Brazil, 15 Jan. 2007

    48. Guangzhou Metro Line 5, China, 17 Jan. 2008

    49. Langstaff Road Trunk Sewer, Canada, 2 May 2008

    50. Circle Line 4 Tunnel, Singapore, 23 May 2008

  • Civil Engineering and Development Department

    The Government of the Hong Kong Special Administrative Region

    51. M6 Motorway, Hungary, 24 Jul. 2008

    52. Hangzhou Metro Tunnel, China, 15 Nov. 2008

    53. Cologne North-South Metro Tram Line, Germany, 3 March 2009

    54. Brightwater Tunnel, USA, 8 March 2009

    55. Seattles Beacon Hill Light Rail, USA, July 2009

    56. Glendoe Headrace Tunnel, Scotland, UK, Aug. 2009

    57. Cairo Metro Tunnel, Egypt, 3 Sept. 2009

    58. Headrace tunnel of Gilgel Gibe II Hydro Project, Ethiopia, Oct. 2006

    and Jan. 2010

    59. Blanka Tunnel, Czech Republic, 20 May 2008, 12 Oct. 2008 and 6

    July 2010

    60. Shenzhen Express Rail Link, 27 March 2011, 4 May 2011 and 10

    May 2011

  • Civil Engineering and Development Department

    The Government of the Hong Kong Special Administrative Region

    61. Mizushima Refinery Subsea Tunnel, Japan, 14 Feb. 2012

    62. Hengqin Tunnel, Macau, 19 July 2012

    63. Sasago Tunnel, Japan, 2 Dec. 2012

    64. Ottawas Light Rail Transit Project, Canada, 20 Feb. 2014

    65. Rios Metro Line 4, Brazil, 11 May 2014

  • Civil Engineering and Development Department

    The Government of the Hong Kong Special Administrative Region

    1. MTR Modified Initial System, Prince Edward Station, Nathan

    Road, Hong Kong,12 Sept. 1977

    2. MTR Island Line, 22 Hennessy Road, Hong Kong, 1 Jan. 1983

    3. MTR Island Line, Shing On Street, Shau Kei Wan, Hong Kong,

    23 July 1983

    4. MTR Island Line, 140-168 Shau Kei Wan Road, Hong Kong, 16

    Dec. 1983

    5. Kowloon Southern Link Contract KDB 200, Canton Road, Hong

    Kong, 21 Oct. 2006

    6. Kowloon Southern Link Contract KDB 200, Salisbury Road,

    Hong Kong, 3 June 2007

  • Case No 1. Green Park, London, UK, 1964 Europe

    United Kingdom

    1964

    Project Title Green Park to Victoria Tunnel, UK

    Source of Information Clay, R.B. & Takacs, A.P. (1997). Anticipating the unexpected

    Flood, fire overbreak, inrush, collapse. Proceedings of the

    International Conference on Tunnelling Under Difficult Ground

    and Rock Mass Conditions, Basel, Switzerland, pp 223-242.

  • Keywords (for searching) Green Park, London, UK, London Clay

    Figures

    Clay & Takacs (1997)

  • Background Segmental lined tunnel (Green Park to Victoria) driven through

    London Clay with low soil cover

    Nature and Type of Failure Construction failure

    Inflow of sand and gravel, burying most of the shield

    Ground and Groundwater Conditions London Clay overlain by water-bearing sands and gravels

    Construction Methods and Support Using drum-digger shield

    Possible Cause of Failure The crown of the shield penetrated through the London Clay

    layer into sand and gravel

  • Consequence Little physical damage to the shield

    Programme delayed

    Emergency and Remedial Measures A shaft was sunk from the surface to enable the material to be

    staunched and treated.

    The loose material was dug out by hand

    Lessons Learnt Unpublished

  • Case No 2. Victoria Line Underground, UK, 1965 Europe

    United Kingdom

    1965

    Project Title Victoria Line Underground Railway

    Source of Information Clay, R.B. & Takacs, A.P. (1997). Anticipating the unexpected

    Flood, fire overbreak, inrush, collapse. Proceedings of the

    International Conference on Tunnelling Under Difficult Ground

    and Rock Mass Conditions, Basel, Switzerland, pp 223-242.

  • Keywords (for searching) Victoria Line, London, UK, London Clay

    Figures

    Clay & Takacs (1997)

  • Background Tunnel (300m long and 3.7m internal diameter) driven through

    London Clay under a disused railway marshalling yard

    Nature and Type of Failure Construction failure

    Inflow of sand and gravel

    Ground and Groundwater Conditions London Clay underlain by sands and gravels

    Construction Methods and Support Using hand-shield and lined with cast-iron

    Possible Cause of Failure The shield was ineffective in supporting the overlying ground

  • Consequence No significant damage

    Programme delayed for about 6 months

    Emergency and Remedial Measures Lengthy grouting operation for stabilizing the ground in the

    vicinity

    Lessons Learnt Unpublished

  • Case No 3. Southend-on-Sea Sewage Tunnel, UK, 1966 Europe

    United Kingdom

    1966

    Project Title Southend-on-Sea Sewage Tunnel, UK

    Source of Information Clay, R.B. & Takacs, A.P. (1997). Anticipating the unexpected

    Flood, fire overbreak, inrush, collapse. Proceedings of the

    International Conference on Tunnelling Under Difficult Ground

    and Rock Mass Conditions, Basel, Switzerland, pp 223-242.

  • Keywords (for searching) Southend-on-Sea, London, UK, London Clay

    Figures

    Clay & Takacs (1997)

  • Background Tunnel 40m long with diameter of 1.35m driven mostly by hand

    Nature and Type of Failure Construction failure

    Water inflow into the tunnel

    Ground and Groundwater Conditions London Clay overlain by sands and gravels

    Construction Methods and Support Driven mostly by hand and lined with PCC segments

    Possible Cause of Failure The tunnel intersected the bottom of an abandoned 600mm

    diameter well

  • Consequence No loss of life or injury

    Emergency and Remedial Measures The tunnel drive was continued in a timbered box heading and

    two plates were fabricated for closed off the bottom of the well. Grouting was also applied

    Lessons Learnt Unpublished

  • Case No 4. Rrvikskaret Road Tunnel on Highway 19, Norway, 18 March 1970

    Europe

    Norway

    18 March 1970

    Project Title Rrvikskaret Road Tunnel on Highway 19

    Source of Information Karlsrud Kjell (2010). Technical Note : Experience with tunnel

    failures in Norwegian tunnels. The Government of the Hong

    Kong Civil Engineering and Development Department.

    (Unpublished).

  • Keywords (for searching) Rrvikskaret, Norway, cave in

    Figures

    Karlsrud (2010)

  • Background The road tunnel was 726m long and 8m wide

    Nature and Type of Failure Construction failure

    Tunnel face collapsed and a 100m high cave-in shaft from the tunnel up to the ground surface was created

    The top of the shaft on the ground surface had a dimension of about 25m x 50m

    Although soft material was hauled out from the tunnel during the spring in 1971, cave-in continued from the shaft until autumn

    1972

    The cave-in zone extended 30m along the tunnel and the total volume of material hauled out from the tunnel was about

    75,000m3

  • Ground and Groundwater Conditions Crystalline gneisses of granitic and syenitic composition

    The tunnel was excavated into a large zone of swelling clay. The rock at the failure was completely altered to swelling clay

    Construction Methods and Support Constructed by the drill-and-blast method and mainly supported

    by rock bolts, steel straps and mesh

    Possible Cause of Failure Preliminary investigation carried out without any drilling

    Probe drilling was not performed during tunnelling

    No stabilization measures to support a large swelling clay section before blasting

  • Consequence Programme delayed for more than 3 years

    Double the cost of the tunnel compared to the estimated cost

    Emergency and Remedial Measures Installation of corrugated steel vault, steel tubes and 500mm thick

    concrete lining was not successful

    The cave-in ceased after filling of about 3,000m3 concrete into the

    shaft to form a plug from the tunnel up to 10m above the crown

    and another 4,000m3 of sand and stone from the top of the shaft

    above the concrete plug

    Lessons Learnt The importance of the adequate ground investigation to identify if

    weak ground is present and to provide measures to support the

    weak ground before tunnel excavation

  • Case No 5. Orange-fish Tunnel, South America, 1970 South Africa

    1970

    Project Title Orange-fish Tunnel, South Africa

    Source of Information Clay, R.B. & Takacs, A.P. (1997). Anticipating the unexpected

    Flood, fire overbreak, inrush, collapse. Proceedings of the

    International Conference on Tunnelling Under Difficult Ground

    and Rock Mass Conditions, Basel, Switzerland, pp 223-242.

  • Keywords (for searching) Orange-fish, South Africa, fire

    Figures N/A

    Background Circular tunnel designed to carry irrigation water from the

    Orange River (80km long and 5.3m in diameter, 1,200m above

    sea level)

    Nature and Type of Failure Construction failure

    First failure Heavy water inflow (of about 55,000 litres/min into the tunnel at 14 bars)

    Second failure Fire (Methane gas ignited by a blast, but no explosion occurred as the gas did not reach the explosive

    concentration)

  • Ground and Groundwater Conditions Sandstones, siltstones and mudstones, generally horizontally

    bedded with occasional dolerite dykes

    Construction Methods and Support Tunnelling using the rail-mounted drill and blast method and lined

    with 225mm of insitu concrete

    1.5m long tensioned resin-grouted bolts at 1.5m spacing with occasional shotcrete

    Possible Cause of Failure First failure The tunnel passed through a shallow anticline and

    intersected a fissure, about 75mm wide, almost perpendicularly

    Second failure Methane gas from a methane bearing fissure entered the tunnel during excavation

  • Consequence

    First failure Entire 1.6km tunnel section flooded within 24 hours

    Second failure The fire burnt for about 6 months

    Emergency and Remedial Measures

    First failure Grouting was carried out from the surface and the tunnel was pumped dry. Blob-grouting method with a ring of very thick grout of unhydrated bentonite to seal the fissures a short distance away from the tunnel was developed for the subsequent excavation

    Second failure A wall was built across the tunnel, the void beyond, including the methane-bearing fissure, was grouted up with cement

    Lessons Learnt Unpublished

  • Case No 6. Penmanshiel Tunnel, Scotland, UK, March 1979 Europe

    Scotland, UK

    March 1979

    Project Title Enlargement of the Penmanshiel Tunnel

    Source of Information McNaughton, I.K.A. (1983). Report on the collapse of Penmanshiel

    Tunnel that occurred on 17th March 1979 in the Scottish Region, British Railways, Department of Transport, 7 p. .

  • Keywords (for searching) Europe, Scotland, 1979, Penmanshiel Tunnel, British Railways,

    construction failure, fall of rock, anticlinal structure, over-stressed rock

    Figures Penmanshiel Tunnel, near Grantshouse in Scotland

    Source from http://en.wikipedia.org/wiki/Penmanshiel_Tunnel

  • Background The double rail track Penmanshiel tunnel of 7.72m span and

    4.7m height was driven in 1845/1846

    In 1979 the roof of the tunnel collapsed during tunnel enlargement works when the tunnel invert was being reconstructed to increase the headroom

    Nature and Type of Failure

    Ground failure during reconstruction

    Fall of rock over a length of some 20m

    Ground and Groundwater Conditions Sedimentary rock of steeply inclined and complex stratification

    with an average cover of 25 to 30m

    Dry conditions

    Construction Methods and Support Rock bench system with an arch lined with 4 or 5 rings of bricks

  • Possible Cause of Failure The existence of complex anticlinal structure over the line of the

    tunnel, which could not have been deduced from rock exposed in the tunnel but was later exposed in the open cut excavation after the diversion of the tunnel alignment

    The degeneration of the rock within the anticlinal structure built up heavy loading on the arch ring and side walls

    Additional excavation in the tunnel increased the stresses in the already overstressed rock in the side walls

    Consequence Broken rock pouring into the tunnel with a complete blockage

    13 workers escaped but 2 workers were killed

  • Emergency and Remedial Measures Immediate support provided to the adjacent portion of the tunnel

    by a number of steel arches

    Long term abandonment of 1,000m of the tunnel and the diversion of the line to a new alignment in open cut with the ends of the old tunnel filled in

    Lessons learnt The consequences of adjusting the profile of a working tunnel

    without stress analysis and appropriate support

    The importance of understanding the geological conditions of the site and the need for analysis

  • Case No 7. Munich Underground, Germany, 1980 Europe

    Gemany

    1980

    Project Title Munich Underground, Germany

    Source of Information Construction Today (1994b). Unstable ground triggers Munich

    tunnel collapse. Construction Today, October Issue, p 5.

  • Keywords (for searching) Munich, Germany, sinkhole

    Figures

    Construction Today (1994b)

  • Background New Austrian Tunnelling Method (NATM) construction of twin 6m

    diameter tunnels

    Nature and Type of Failure Construction failure

    Huge flow of soft clay into the tunnel

    Ground and Groundwater Conditions Flinty marl with 3m of cover above the tunnels, overlain by 12.5m

    of soft clay

    Construction Methods and Support New Austrian Tunnelling Method (NATM)

    Possible Cause of Failure Local variation in geology with reduction in marl cover to 1-1.5m

    and led to overstressing of the sprayed concrete temporary lining

  • Consequence 10m wide, 14m deep sinkhole

    No injury

    Emergency and Remedial Measures Void was backfilled with crushed rock and cement and pressure

    grouted

    Lessons Learnt The danger of tunnel excavation through thin marl cover

  • Case No 8. Holmestrand Road Tunnel, Norway, 16 Dec. 1981 Europe

    Norway

    16 December 1981

    Project Title The Holmestrand Road Tunnel

    Source of Information Karlsrud Kjell (2010). Technical Note : Experience with tunnel

    failures in Norwegian tunnels. The Government of the Hong

    Kong Civil Engineering and Development Department.

    (Unpublished).

  • Keywords (for searching) Keywords (for searching) Holmestrand, Norway, cave in

    Figures

    Karlsrud (2010)

  • Background The road tunnel was 1.78km long and 10m wide

    Nature and Type of Failure Construction failure

    A minor cave-in from the face and partly from the crown occurred during the process of moving the steel formwork for

    cast concrete lining forward to the face

    Ground and Groundwater Conditions Various rock types (basalt, volcanic dykes, soft siltstone and

    quartz conglomerate)

    Construction Methods and Support Constructed by the drill-and-blast method and supported by cast

    concrete lining

  • Possible Cause of Failure A weak fault zone was encountered No spiling bolts ahead of the face to support the weak ground

    Consequence More time (5 hours extended to 25 hours) required for hauling out

    and concreting the foundation for the mould

    Emergency and Remedial Measures About 600m3 of debris was hauled in to the face for temporary

    support

    Until break through, the tunnel was excavated with only 2m long bore holes combined with 6m long spiling bolts from the cast concrete

    lining of the former round, and cast concrete lining close to the face

    Lessons Learnt Spiling bolts ahead of the face in combination with fibre reinforced

    sprayed concrete, rock bolts, and reinforced ribs of sprayed concrete

    are required at the fault zones with extremely poor rock mass quality

  • Case No 9. Gibei Railway Tunnel, Romania, 1985 Europe

    Romania

    1985

    Project Title Gibei Railway Tunnel, Romania

    Source of Information Clay, R.B. & Takacs, A.P. (1997). Anticipating the unexpected

    Flood, fire overbreak, inrush, collapse. Proceedings of the

    International Conference on Tunnelling Under Difficult Ground

    and Rock Mass Conditions, Basel, Switzerland, pp 223-242.

  • Keywords (for searching) Gibei, Romania

    Figures

    Clay & Takacs (1997)

  • Background Railway tunnel 2.21km long and 9m in diameter

    Nature and Type of Failure Construction failure

    Compact fissured clay layer failed suddenly, allowing water inflow >600 litres/min into the tunnel

    Ground and Groundwater Conditions Compacted Clay with fissures

    Construction Methods and Support Shield (A hooded mechanical sheld 9.05 m in diameter, fitted

    with a hydraulic bucket and a bottom-monuted conveyor belt)

    Possible Cause of Failure The tunnel penetrated a lens of waterlogged fine-grained sand

    just above the crown

  • Consequence Ingress of water at more than 10 L/s accompanied by running

    sand to the tunnel covering the machine

    Programme delayed for about 6 months

    Emergency and Remedial Measures Unpublished

    Lessons Learnt Unpublished

  • Case No 10. Moda Collector Tunnel, Istanbul Sewerage Scheme, Turkey, 1989

    Europe

    Turkey

    1989

    Project Title Moda Collector Tunnel

    Source of Information Clay, R.B. & Takacs, A.P. (1997). Anticipating the unexpected

    Flood, fire overbreak, inrush, collapse. Proceedings of the

    International Conference on Tunnelling Under Difficult Ground

    and Rock Mass Conditions, Basel, Switzerland, pp 223-242.

  • Keywords (for searching) Moda Collector, Istanbul, Turkey

    Figures

    Clay & Takacs (1997)

  • Background The TBM broke out 8m from the shaft with anticipated 3 m of

    rock cover

    Nature and Type of Failure Construction failure

    Fine soil flowed into the tunnel forming a hole in the road as the TBM went through the rock into the soft ground

    Ground and Groundwater Conditions Various ground conditions (very fine and unstable mud & rock)

    Construction Methods and Support Tunnel constructed by Tunnel Boring Machine (TBM)

    Possible Cause of Failure The tunnel intersected a hidden area of soft clay

  • Consequence A hole formed in the road some 5m above

    Broken rock jammed the shield

    Emergency and Remedial Measures A shaft was sunk down to release the TBM

    Lessons Learnt Probe holes should be drilled to confirm the rockhead profile

  • Case No 11. Seoul Metro Line 5 Phase 2, Korea, 17 Nov. 1991 Asia Korea 17 November 1991

    Project Title Second Phase of Seoul Subway

    Source of Information Lee, I. M. & Cho, G. C. (2008). Underground construction in

    decomposed residual soils (presentation slides). The 6th

    International Symposium on Geotechnical Aspects of Underground

    Construction in Soft Ground (IS-Shanghai 2008), Tongji University,

    Shanghai, April.

    Madrid (1996). Informe sobre el NATM del Health & Safety Executive, de Inglaterra, 1996. (1996).

  • Source of Information Shin, J.H., Lee, I.K., Lee, Y.H. & Shin, H.S. (2006). Lessons

    from serial tunnel collapses during construction of the Seoul

    subway Line 5. Tunnel and Underground Space Technology,

    Issue no. 21, pp 296-297.

    Keywords (for searching) Seoul, Korea, cave-in

    Figures

    Lee & Cho (2008)

  • Background Construction of Seoul Metro tunnel near Majang

    Tunnel at 15-30m below ground

    Nature and Type of Failure Construction failure

    After blasting : daylight collapse up to ground surface, involving the embankment of a river

    20m x 15m and 4m deep crater at the ground surface

    Water from river flowed into the tunnel

    Ground and Groundwater Conditions Various weathered granite

    Groundwater table at typical 3-10m below the ground surface

    Construction Methods and Support by drill and blast method

  • Possible Cause of Failure Thin weathered rock cover

    Inflow of soil and groundwater

    Consequence Roads collapse and gas mains fractured

    Emergency and Remedial Measures Backfilling the crater with soil followed

    by cement grouting and chemical grouting

    Lessons Learnt Insufficient ground investigation

    Unexpected groundwater inflow

    No tunnel face stability analysis

    No consideration of blasting effects closed to weathered zone with shallow cover

    Majang Bridge

    Alluvium

    Soft rock

    Hard rock

    Cheonggye-choeon

    4. grouting(JSP)

    2. sand mat

    3. face shotcrete

    Fill(SM)Silty sand

    Decomposedgranite soil

    Weatheredrock

    1. backfilling

    -3.5m

    -24.0m

    -29.5m

    -3.2m

    18.0m

    1.4m

    -26.5m

    1000m3

    Sink hole

    -12.8m

    -13.3m

    -18.0m

  • Case No 12. Seoul Metro Line 5 Phase 2, Korea, 27 Nov. 1991 Asia Korea 27 November 1991

    Project Title Second Phase of Seoul Subway

    Source of Information Lee, I. M. & Cho, G. C. (2008). Underground construction in

    decomposed residual soils (presentation slides). The 6th International

    Symposium on Geotechnical Aspects of Underground Construction in

    Soft Ground (IS-Shanghai 2008), Tongji University, Shanghai, April.

    Madrid (1996). Informe sobre el NATM del Health & Safety Executive, de Inglaterra, 1996. (1996).

    Shin, J.H., Lee, I.K., Lee, Y.H. & Shin, H.S. (2006). Lessons from serial tunnel collapses during construction of the Seoul subway Line 5.

    Tunnel and Underground Space Technology, Issue no. 21, pp 296-

    297.

  • Keywords (for searching) Seoul, Korea, cave-in

    Figures

    Lee & Cho (2008)

  • Background Construction of Seoul Metro tunnel near Tangsan Tunnel at 15-30m below ground

    Nature and Type of Failure Construction failure

    27 November 1991 10:40am : blasting

    4:00pm : rock falls at the tunnel face

    10:00pm : soil and groundwater inflow into the tunnel

    28 November 1991 3:20am : substantial daylight collapse up to ground surface

    forming a 25m diameter crater

    Ground and Groundwater Conditions Various weathered granite Groundwater table at typical 3-10m below the ground surface

    Construction Methods and Support by drill and blast method

  • Possible Cause of Failure Weathered granite at the face

    and high permeability soil

    Consequence Three buildings collapsed

    Several water mains, gas pipes and sewerage were broken

    Emergency and Remedial Measures

    Backfilling the crater with soil followed by cement grouting and chemical grouting

    25.0

    m

    20.0

    m

    D=20.0m-1.2m

    -4.8m-6.0m

    -28.5m

    -37.5m

    -22.2m

    -25.1m

    -29.2m

    Fill sand

    Silt

    Sand

    Weathered

    rock

    Soft rock

    Hard rock

    : Cement mortar: Cement milk: Chemical grout

    15.0m5.0m10.0m5.0m

    backfilling

    Lee & Cho (2008)

  • Lessons Learnt Insufficient ground investigation

    Unexpected groundwater inflow

    No tunnel face stability analysis

    No consideration of blasting effects closed to weathered zone with shallow cover

  • Case No 13. Seoul Metro Line 5 Phase 2, Korea, 11 Feb. 1992 Asia Korea 11 February 1992

    Project Title Second Phase of Seoul Subway

    Source of Information Lee, I. M. & Cho, G. C. (2008). Underground construction in

    decomposed residual soils (presentation slides). The 6th

    International Symposium on Geotechnical Aspects of Underground

    Construction in Soft Ground (IS-Shanghai 2008), Tongji University,

    Shanghai, April.

    Madrid (1996). Informe sobre el NATM del Health & Safety Executive, de Inglaterra, 1996. (1996).

    Shin, J.H., Lee, I.K., Lee, Y.H. & Shin, H.S. (2006). Lessons from serial tunnel collapses during construction of the Seoul subway Line

    5. Tunnel and Underground Space Technology, Issue no. 21, pp

    296-297.

  • Keywords (for searching) Seoul, Korea, cave-in

    Figures

    Lee & Cho (2008)

  • Background Construction of Seoul Metro tunnel near Youido

    Tunnel at 15-30m below ground

    Nature and Type of Failure Construction failure

    Significant inflow of groundwater

    About 4.5 tonnes of soil flowed into tunnel

    38m wide x 6m deep crater at the ground surface

    Ground and Groundwater Conditions Various weathered granite

    Groundwater table at -11.8m below the ground surface

    Construction Methods and Support Excavated by road header

  • Possible Cause of Failure Weathered granite at the tunnel

    face and high permeability soil

    Consequence 4-lane road collapsed

    Utilities damaged

    Emergency and Remedial Measures

    Backfilling the crater with soil followed by cement grouting and chemical grouting

    Lee & Cho (2008)

    -5.6m

    -7.8m

    -9.9m

    -13.2m

    -21.7m

    -25.9m-26.4m

    -11.8m

    Fill

    Alluvium(SC)

    Alluvium(SP)

    Alluvium(ML)

    Hard Rock

    Weathered rock

    Soft rock

    Sewer box

    MBC

    Sewer Box

    38.0m

    3. urethan grouting

    2. cement mortal grouting

    1. back filling

    -23.5m

    -33.0m

    3m

    Decomposed

    rock

  • Lessons Learnt Insufficient ground investigation

    Unexpected groundwater inflow

    No tunnel face stability analysis

  • Case No 14. Seoul Metro Line 5 Phase 2, Korea, 1 Jan. 1993 Asia Korea 7 January 1993

    Project Title Second Phase of Seoul Subway

    Source of Information Lee, I. M. & Cho, G. C. (2008). Underground construction in

    decomposed residual soils (presentation slides). The 6th International

    Symposium on Geotechnical Aspects of Underground Construction in

    Soft Ground (IS-Shanghai 2008), Tongji University, Shanghai, April.

    Madrid (1996). Informe sobre el NATM del Health & Safety Executive, de Inglaterra, 1996. (1996).

    Shin, J.H., Lee, I.K., Lee, Y.H. & Shin, H.S. (2006). Lessons from serial tunnel collapses during construction of the Seoul subway Line 5.

    Tunnel and Underground Space Technology, Issue no. 21, pp 296-297.

  • Keywords (for searching) Seoul, Korea, cave-in

    Figures

    Lee & Cho (2008)

  • Background Construction of Seoul Metro tunnel near Yongdungpo

    Tunnel at 15-30m below ground

    Nature and Type of Failure Construction failure

    Tunnel collapsed after removing spoil

    Tunnel collapsed starting from the left side of the crown

    900m3 of loose material flowed into the tunnel and water inflow of up to 300 litres/min recorded

    Ground and Groundwater Conditions Various weathered granite

    Construction Methods and Support By drill and blast method

  • Possible Cause of Failure Weathered granite at the tunnel

    face

    High groundwater pressure

    Consequence 2-lane road collapsed

    Utilities damaged

    Emergency and Remedial Measures

    Backfilling the crater with soil followed by cement grouting and chemical grouting

    Fill

    Alluvium(ML)

    Alluvium(SP)

    Weathered rock

    Soft rock

    -1.1m

    -7.1m

    -16.5m

    -21.5m

    -4.9m

    -20.14m

    -28.34m

    Sewer box

    900m3

    2. cement mortar

    3. cement mortar

    4. chemical grouting

    1. back filling

    Lee & Cho (2008)

  • Lessons Learnt Insufficient ground investigation

    Unexpected groundwater inflow

    No tunnel face stability analysis

    No consideration of blasting effects closed to weathered zone with shallow cover

  • Case No 15. Seoul Metro Line 5 Phase 2, Korea, 1 Feb. 1993 Asia Korea 1 February 1993

    Project Title Second Phase of Seoul Subway

    Source of Information Lee, I. M. & Cho, G. C. (2008). Underground construction in

    decomposed residual soils (presentation slides). The 6th International

    Symposium on Geotechnical Aspects of Underground Construction in

    Soft Ground (IS-Shanghai 2008), Tongji University, Shanghai, April.

    Madrid (1996). Informe sobre el NATM del Health & Safety Executive, de Inglaterra, 1996. (1996).

    Shin, J.H., Lee, I.K., Lee, Y.H. & Shin, H.S. (2006). Lessons from serial tunnel collapses during construction of the Seoul subway Line 5.

    Tunnel and Underground Space Technology, Issue no. 21, pp 296-

    297.

  • Keywords (for searching) Seoul, Korea, Anyangcheon, cave-in

    Figures

    Lee & Cho (2008)

  • Background Construction of Seoul Metro tunnel near Anyangcheon

    Tunnel at 15-30m below ground

    Nature and Type of Failure Construction failure

    Daylight collapse when weathered granite found at the tunnel face

    Groundwater flowed into the tunnel

    60m wide oval shaped area subsided

    Ground and Groundwater Conditions Various weathered granite

    Construction Methods and Support excavated by road header

  • Possible Cause of Failure Weathered granite and alluvium

    at the tunnel face

    High groundwater pressure

    Consequence Six heavy plants buried

    Emergency and Remedial Measures

    Backfilling the crater with soil followed by cement grouting and chemical grouting

    8.3m

    24.0m

    59.3m

    cement milk

    grouting

    59.3m

    jet grouting

    5.0m-21.0m

    -24.0m

    -29.0m

    Weathered rock

    Soft rock

    Anyang cheon

    Alluvium2. cement milk

    grouting

    Sewer box

    -24.0m

    -32.0m

    3. jet grouting

    1. backfilling

    Decomposed granite soil

    Sewer Box

    Lee & Cho (2008)

  • Lessons Learnt Insufficient ground investigation

    Unexpected groundwater inflow

    No tunnel face stability analysis

  • Case No 16. Munich Underground, Germany, 27 Sept. 1994 Europe Germany 27 September 1994

    Project Title Munichs U-Bahn U2 Underground Extension

    Source of Information Boos, R., Braun, M., Hangen, P., Hoch, C., Popp, R., Reiner, H.,

    Schmid, G., & Wannick, H. (2004). Underground Transportation

    Systems, Chances and Risks from the Re-insurers Point of View. Munich Re Group, Germany, pp 58-62.

    (31 Jan. 2007).

    Construction Today (1994a). Police probe repeat Munich tunnel breach. Construction Today, October Issue, pp 4-5.

    Ground Engineering (1994). London NATM controversy. Ground Engineering, November Issue, p 6.

  • Keywords (for searching) Munich, Germany, sinkhole

    Figures

    Construction Today (1994a)

  • Background 7m diameter tunnel supported by sprayed concrete lining

    The tunnel was assumed to be beneath a clay layer overlying water-bearing gravel and groundwater would not be drawn down

    Nature and Type of Failure Construction failure

    Quick inflow of water and ground materials

    Large subsidence crater quickly filled with groundwater

    20m wide, 18.5m deep crater

    Ground and Groundwater Conditions Flinty marl overlain by some 15.5m of groundwater bearing gravel

    Groundwater at about 4m below ground level

    Construction Methods and Support New Austrian Tunnelling Method (NATM)

  • Possible Cause of Failure Layer of marl separating

    groundwater bearing layers was

    much thinner than originally

    assumed

    Sand-infilled cracks in the marl layer acted as preferential

    pathways for water

    Consequence Bus fell into the crater

    Three passengers killed

    30 people injured

    Construction Today (1994a)

  • Emergency and Remedial Measures Bored-pile wall to form a shaft

    Excavation inside the shaft for rescue

    Tunnel driven again using compressed air

    Lessons Learnt The danger of tunnel excavation through thin marl cover

  • 2000 report

    Case No 17. Heathrow Express Tunnel, UK, 21 Oct. 1994 Europe United Kingdom 21 October 1994

    Project Title Heathrow Express Tunnel

    Source of Information Ground Engineering (2000). Catalogue of disaster. Ground Engineering,

    August Issue, pp 10-11.

    HSE (1996). Safety of New Austrian Tunnelling Method (NATM) Tunnels. Health & Safety Executive, UK, 86p.

    HSE (2000). The Collapse of NATM Tunnels at Heathrow Airport. Health & Safety Executive, UK, 116p.

    ICE (1998b). HSE signs up QC Carlisle for HEX prosecution. New Civil Engineer, Institution of Civil Engineers, March Issue, pp 4-5.

    ICE (1999). Heathrow Express court cases kicks off. New Civil Engineer, Institution of Civil Engineers, January Issue, p 6.

    1996 report

  • Keywords (for searching) London, United Kingdom, NATM, sinkhole

    Figures

    Ground Engineering (2008) ICE (1998b)

  • Background NATM in London Clay

    Nature and Type of Failure Construction failure

    10m diameter crater formed

    Ground and Groundwater Conditions

    London Clay

    Construction Methods and Support

    New Austrian Tunnelling Method (NATM) ICE (1998b)

  • Possible Cause of Failure A series of design and management errors combined with

    poor workmanship and quality control

    Consequence Differential settlement induced at adjacent buildings

    Rail services to Terminal 4 were halted for one month

    Remedial measures caused chaos at Heathrow Airport

    Recovery cost 150M (3 times original contract sum)

  • Central Terminal Area

    Settlement Contours

  • Emergency and Remedial Measures Backfilling with 13,000m3 concrete

    Lessons Learnt Measures to ensure safety must be planned

    Do not lose sight of critical technical issues in the pursuit of time and cost reduction

    Whilst a number of factors contributed to the collapse, half of them were matters of management

    However much engineers are pressured to build quickly and cheaply, the industry will be judged by its own failures

  • Case No 18. Los Angeles Metro, USA, 22 June 1995 North America

    United States of America

    22 June 1995

    Project Title The Los Angeles Metro

    Source of Information Civil Engineer International (1995). Tunnel lining removal

    prompts LA Metro cave in. Institution of Civil Engineers, July

    Issue, p10.

  • Keywords (for searching) Los Angeles, USA, cave in

    Figures

    Civil Engineer International (1995)

  • Background Re-mining/remedial works to realign an existing TBM tunnel

    (6.7m diameter, 25m deep), which had been bored off line

    Nature and Type of Failure Construction failure

    25m deep sinkhole caused by collapse of south bore

    Serious cracking observed in temporary lining of north bore

    Ground and Groundwater Conditions Hard siltstone overlain by alluvium with groundwater level 10-

    12m below surface

    Construction Methods and Support TBM with segmental lining

    Rock bolts to stabilise segments before removal

  • Possible Cause of Failure Failure occurred during removal of segmental lining in tunnel roof

    and relining of tunnel to correct the horizontal alignment

    Unexpected ground conditions (alluvium found much deeper)

    Fractured water mains (unconfirmed)

    Consequence 30m length of a four lane road (Hollywood Boulevard) affected

    leading to road closure

    Collapsed 250mm water main possibly contributing to failure

    Broken gas pipe

    Evacuation of local residents

  • Emergency and Remedial Measures Steel rings installed in tunnel either side of the collapse

    3,300m3 of grout to fill void and stabilise area

    Road resurfacing

    Lessons Learnt Unpubished

  • Case No 19. Motorway Tunnels, Austria, 1993-1995 Europe

    Austria

    1993 - 1995

    Project Title Motorway Contract

    Source of Information Clay, R.B. & Takacs, A.P. (1997). Anticipating the unexpected

    Flood, fire overbreak, inrush, collapse. Proceedings of the

    International Conference on Tunnelling Under Difficult Ground

    and Rock Mass Conditions, Basel, Switzerland, pp 223-242.

  • Keywords (for searching) Motorway, Austria, inrush, water inflow

    Figures Extent of overbreak

    1. Rock bolts

    2. Second layer WM & shotcrete

    3. Support core

    4. Rock debris

    5. Shotcrete in the overbreak

    6. Water & rock flow

    7. Overbreak

    Clay & Takacs (1997)

  • Background Four three-lane, twin-tube tunnels (T1-T4) with internal cross-

    section of 103 m2 and 30 m apart between centrelines

    constructed by the drill & blast method

    T1 - 376m long; T2 - 562m; T3 2,760m and T4 1,230m

    Nature and Type of Failure Construction failure

    Failures at T4 in 1993

    - About 131 recorded overbreak incidents with total volume of

    1,461m3, maximum deformation of 120mm measured in the

    tunnel

    - 200m3 of loose material collapsed after a blast, resulting in

    water inflow of up to 450 litres/min

  • Nature and Type of Failure (cont) Two failures at T3 in 1995

    - The first collapse came with 650m3 of loose material flowed into

    the tunnel, water inflow of up to 1,500 litres/min recorded

    - The second collapse of the same size occurred days after the 6

    months of recovery of the loss of the 10 m of tunnel. Radial

    movement of rib of about 300mm recorded

    Ground and Groundwater Conditions Sandstone and shale with zones of crushed and weathered

    material

    Construction Methods and Support Drill and blast, heading and benching

    Shotcrete, rock bolts, forepoling, steel ribs and invert beams

  • Possible Cause of Failure Failures at T4 in 1993 Failure to apply the support in time

    Two failures at T3 in 1995 The tunnel pierced through the water-bearing impermeable thinly bedded shale stratum, which

    is located at and above the failure location

    Consequence the tunnel face caved in

    construction delay

    Emergency and Remedial Measures Failures at T4 in 1993 For the subsequent excavation,

    umbrella of forepoling with 6m long, 50mm perforated grouted

    pipes was adopted. An ample central core was kept and the

    excavation was carried out in small sections

    Two failures at T3 in 1995 work progressed with extreme caution

  • Lessons Learnt Initial support should be installed in time

  • Case No 20. Docklands Light Rail, UK, 23 Feb. 1998 Europe

    United Kingdom

    23 February 1998

    Project Title Docklands Light Railway Lewisham Extension

    Source of Information ICE (1998a). Bulkhead location blamed for DLR blast. New

    Civil Engineer, Institution of Civil Engineers, February Issue, pp

    3-4.

    ICE (2004) Docklands tunnel blowout down to elementary error, says judge. New Civil Engineer, Institution of Civil Engineers, January Issue, pp 8-9.

  • Keywords (for searching) Docklands, UK, sinkhole

    Figures

    ICE (2004)ICE (1998a)

  • Background Tunnel constructed for Docklands Light Rail (diameter 5.2m)

    by slurry TBM

    Nature and Type of Failure Construction failure

    22m wide and 7m deep crater formed in the grounds of George Green School

    ICE (1998a)

  • Ground and Groundwater Conditions Thames Sands and Gravels

    Construction Methods and Support slurry TBM

    Possible Cause of Failure Insufficient overburden above the tunnel

    High compressed air pressure within tunnel causing blow out failure

    Consequence Windows up to 100m away broken by the shower of mud and

    stones released

  • Emergency and Remedial Measures Unpublished

    Lessons Learnt To require specific assessments/calculations to demonstrate the

    adequacy of factor of safety against blow out failure

  • Case No 21. Athens Metro, Greece, 1991-1998 Europe

    Greece

    1991 - 1998

    Project Title The Athens Metro

    Source of Information IMIA. .

    IMS. .

  • Source of Information (cont) Kavvadas, M., Hewison, L.R., Laskaratos, P.G., Seferoglou,

    C. & Michalis, I. (1996). Experiences from the construction

    of the Athens Metro. Proceedings of International

    Symposium on the Geotechnical Aspects of Underground

    Construction in Soft Ground, City University, London, April.

    Mihalis, I. & Kavvadas, M. (1999). Ground movements caused by TBM tunnelling in the Athens Metro Project.

    Proceedings of International Symposium on the

    Geotechnical Aspects of Underground Construction in Soft

    Ground, Japan, July, pp 229-234.

  • Keywords (for searching) Athens, Greece, cave-in

    Figures

    IMS

    IMIA

  • Background Construction of the Olympic Metro under a turnkey contract

    (estimated cost about 2 billion ECUs)

    Construction started in November 1991 and operation in 1998

    TBM used for construction of 11.7km long, 9.5m diameter tunnels located at a depth of 15-20m (with penetration rate

    ranging from 1.6m to 18m per day based on 18-hour-per-day

    shift, depending on the ground conditions)

    Cut and cover, supported by soldier piles, struts and prestressed anchor tiebacks for 6.3km long tunnels and

    stations

    NATM for other short auxiliary tunnels and oval-shaped stations where existence of buried antiquities precluded open

    excavation

  • Nature and Type of Failure Construction failure

    Roof collapses of appreciable size often occurred

    Large and occasionally uncontrollable overbreaks for TBM

    Ground and Groundwater Conditions Athenian schist a thick sequence of flysch-type sediments,

    comprising thinly bedded clayey and calcareous sandstones,

    alternating with siltstones, phyllites, meta-sedimentary shales and

    occasionally, with limestones and marls

    Construction Methods and Support TBM, cut-and-cover and NATM

  • Possible Cause of Failure Ravelling of the ground seems to be due to insufficient strength

    in the intensely weathered and highly tectonised zones of Athenian schist (which is a flysch-type sediment consisting of thinly bedded clayey and calcareous sandstones with alterations and subjected to intense folding, thrusting, faulting and fracturing)

    Large muck openings of the TBM cutterhead which cannot adequately control muck-flow (the cutterhead operates in the open air, i.e. under atmospheric pressure)

    Consequence Major delay in TBM tunnelling

    Emergency and Remedial Measures Cavities caused by the TBM overbreaks was backfilled by grout

    (which sometimes reached the ground surface)

    Lessons Learnt Unpublished

  • Case No 22. L rdal Road Tunnel on European Highway E16, Norway, 15 June 1999

    Europe

    Norway

    15 June 1999

    Project Title The L rdal Road Tunnel on European Highway E 16

    Source of Information Karlsrud Kjell (2010). Technical Note : Experience with tunnel

    failures in Norwegian tunnels. The Government of the Hong

    Kong Civil Engineering and Development Department.

    (Unpublished).

  • Keywords (for searching) L rdal, Norway, cave in

    Figures The L rdal Tunnel

    Ch.11080

    CAVE IN

    DEBRIS

    1200-1500m3

    Karlsrud (2010)

  • Background Road tunnel at about 1,100m depth, 24.5 km long and 9m wide

    Nature and Type of Failure Construction failure

    A cave-in involving 17m length of tunnel and extending up to about 11-12m above the crown. The volume of the failed rock mass was

    estimated to be 1,200-1,500m3

    Ground and Groundwater Conditions Precambrian gneisses with layers of amphibolities and massive

    granitic rock. Excavation through a major fault zone (rock mixed

    with lot of swelling clay)

    Construction Methods and Support Constructed by drill-and-blast method and supported by steel fibre

    reinforced sprayed concrete and rock bolts

  • Possible Cause of Failure Poor communication : the driller did not inform the engineer about

    abnormal drilling rate encountered

    Expansion of the swelling clay under high stress to water during drilling of the rock bolts

    The combination of the swelling of the clay and high stress produced a squeezing effect, which resulted in gradual weakening of the rock mass in the tunnel

    Consequence The crew was evacuated in time and no one was hurt

    About 10 days delay in the excavation works and cost increased for the remedial works

  • Emergency and Remedial Measures

    Reinforced ribs of sprayed concrete in addition to layers of sprayed concrete and rock bolts were installed just behind the cave-in zone

    Rock material was hauled into the tunnel building up a barrier up to 2m below the crown and concrete was pumped through a steel pipe to fill the void above the debris

    Debris was gradually hauled out with step wise installation of rock anchors and sprayed fibre reinforced concrete

    The L rdal Tunnel

    Fa

    ce

    be

    fore

    ca

    ve

    in

    11

    07

    0

    11

    08

    0

    11

    08

    7

    Debris

    1200-1500 m3

    Cave in

    zone

    Concrete

    700 m3 concrete

    Debris hauled out

    Ch

    .no

    Karlsrud (2010)

  • Lessons Learnt The importance of good communication between the driller

    and the engineer

    Importance of having good understanding of the geological conditions and their influence on the stability

    Swelling of clay in condition of high stress could provide a squeezing effect and result in weaking of the rock mass in a tunnel

  • Case No 23. Sewage Tunnel, Hull, UK, 1999 Europe

    United Kingdom

    1999

    Project Title Hull Sewage Tunnel

    Source of Information Boos, R., Braun, M., Hangen, P., Hoch, C., Popp, R., Reiner,

    H., Schmid, G., & Wannick, H. (2004). Underground

    Transportation Systems, Chances and Risks from the Re-

    insurers Point of View. Munich Re Group, Germany, pp 58-62. (31 Jan. 2007).

  • Keywords (for searching) Hull, UK, Sewage

    Figures

    Boos et al (2004)

  • Background Construction of a 10.5km long underground sewer

    Nature and Type of Failure Construction failure

    Water and sand ingress

    Tunnel subsided by 1.2m causing serious subsidence at surface

    Ground and Groundwater Conditions Water-bearing ground

    Construction Methods and Support EPB TBM (diameter 3.85m) supported by reinforced concrete

    segmental lining

  • Possible Cause of Failure Fluctuation of groundwater level caused by tidal effects resulting

    in vertical movement of the tunnel tube causing opening of joints

    Consequence Damage to buildings, roads and utility lines

    TBM had to be abandoned

    Emergency and Remedial Measures Ground freezing

    Reconstruction of tunnel using sprayed concrete

    Lessons Learnt The design of the segment connections should take account of

    the fluctuations of groundwater level

  • Case No 24. Taegu Metro, South Korea, 1 Jan. 2000 Asia

    South Korea

    1 January 2000

    Project Title The Taegu Metro

    Source of Information Boos, R., Braun, M., Hangen, P., Hoch, C., Popp, R., Reiner,

    H., Schmid, G., & Wannick, H. (2004). Underground

    Transportation Systems, Chances and Risks from the Re-

    insurers Point of View. Munich Re Group, Germany, pp 58-62. (31 Jan. 2007).

  • Keywords (for searching) Taegu, South Korea, diaphragm wall, cave in

    Figures

    Boos et al (2004)

  • Background Construction of underground Taegu Metro

    Nature and Type of Failure Construction failure

    Failure of diaphragm wall

    Excavation pit caved in

    Ground and Groundwater Conditions Water-bearing ground

    Construction Methods and Support Cut and-cover

    Possible Cause of Failure Rapid fluctuation of groundwater level caused movement of

    unidentified gravel and sand strata

    Additional loading on diaphragm wall was not considered in design

  • Consequence Bus buried and bus driver seriously injured

    Three passengers killed

    Neighbouring buildings suffered considerable damage

    Emergency and Remedial Measures Excavation pit backfilled

    Subsoil grouted and diaphragm wall strengthened

    Lessons Learnt Unpublished

  • Case No 25. Wastewater Tunnel, Portsmouth, UK, May 2000 Europe

    UK

    May 2000

    Project Title Portsmouth Sewage Transfer

    Source of Information Tunnels & Tunnelling (2000). Portsmouth scheme held up.

    Tunnels & Tunnelling International, July 2000. p 9.

  • Keywords (for searching) Sewage tunnel, Lining crack, Portsmouth

    Figures N/A

  • Background Wastewater tunnel 4km long and 3.3m diameter constructed

    with precast concrete tunnel segments by the TBM method

    Nature and Type of Failure Construction failure

    Cracks were found in the tunnel segments together with associated water ingress

    Ground and Groundwater Conditions Mixed ground comprising Chalk, Calcareous sands, gravels

    and stiff clay

    Water head of 21m above the tunnel crown

    Construction Methods and Support EPB TBM

  • Possible Cause of Failure Localised poor ground conditions not account for in the design

    of the tunnel segments

    Consequence Tunnel drive was halted and delayed

    Emergency and Remedial Measures Temporary application of compressed air, followed by ground

    freezing

    Replacement of damaged rings and back grouting

    Lessons learnt Understanding the ground conditions and account for them in

    design

  • Case No 26. Dulles Airport, Washington, USA, Nov. 2000 North America

    Washington, United States of America

    November 2000

    Project Title Expansion at Washington DCs Dulles airport

    Source of Information Tunnels & Tunnelling (2000). US airport collapse claims miners

    life. Tunnels & Tunnelling International, December 2000 issue, p 8.

    Stehlik, E & Srb, M. NATM Tunnelling at Dulles Airport. Proceedings of the World Tunnel Congress 2007 and 33rd ITA/AITES Annual General Assembly, Prague, May 2007, pp 1609-1612.

  • Keywords (for searching) Dulles, Washington, NATM

    Figures Project Layout

    Tunnels & Tunnelling (2000)

  • Background Pedestrian tunnel of approximate cross-sectional area 100m2 with

    shallow ground cover of 4.5m

    Excavated in 4 stages using two side drifts followed by bench and invert, using road-header

    NATM design with systematic spiling, steel-fibre reinforced shotcrete and lattice girder support

    Nature and Type of Failure Construction failure

    One of the tunnel headings caved in without the collapse extending to the surface

    Ground and Groundwater Conditions Mixed face comprising clay, silt and competent siltstone

  • Construction Methods and Support NATM, following a sequence of a top heading comprising two

    side-wall drifts, followed by bench and invert. 1m-1.6m advances in each round of excavation

    Steel-fibre reinforced shotcrete and lattice girders at 1m-1.6m c/c

    Possible Cause of Failure Unknown

    Consequence A miner was killed

    Emergency and Remedial Measures An area of 40x40x10m deep was excavated from the surface to

    recover the body of the trapped worker

    Lessons learnt Necessity for safe application of NATM in shallow tunnelling works

    Introduction of a requirement for NATM Engineer in the second contract of the project

  • Case No 27. Istanbul Metro, Turkey, Sept. 2001 Europe

    Turkey

    September 2001

    Project Title Istanbul Metro Construction

    Source of Information World Tunnelling (2001). Istanbul Metro collapse investigations,

    World Tunnelling, December 2001 issue, pp. 490-492.

  • Keywords (for searching) Istanbul, Metro, boarding house

    Figures Collapsed building above tunnel Longitudinal section

    World Tunnelling (2001)

  • Background Metro tunnel 7.9km long with 14m wide sections of 100m2

    constructed by a multiple drift technique coupled with pipe umbrella roofing and benching at central drift

    Nature and Type of Failure Construction Failure

    Soft clay kept falling through the gaps between the pipe umbrella and liquid mud flowed from the face.

    Tunnel collapsed and a 25m wide crater was created

    Three 2-storey buildings and a workshop building caved in

    Ground and Groundwater Conditions Soft ground with groundwater close to ground level

    Construction Methods and Support Multiple drift mined Tunnel

    Pipe umbrella, shotcrete lining and lattice girders as temporary support

  • Possible Cause of Failure Existing well 1.5-2.0m above the tunnel crown not properly

    filled causing the saturated clay and well water flowing into the tunnel and subsequent collapse of the well walls and surrounding clay followed by the draining of the upper fine-grained sand layer into the tunnel and the undermining of the building structures

    Consequence 5 people died

    Emergency and Remedial Measures Unpublished

    Lessons learnt The importance of the study of the construction history of

    buildings that are under-tunnelled

  • Case No 28. Channel Tunnel Rail Link, UK, Feb. 2003 Europe

    United Kingdom

    February 2003

    Project Title Channel Tunnel Rail Link

    Source of Information ICE (2003). Ground failure linked to well collapses. New

    Civil Engineer, Institution of Civil Engineers, February Issue,

    pp 6-7.

  • Keywords (for searching) UK, Channel, Rail, sinkhole

    Figures

    ICE (2003)

  • Background Boring at a depth of 21m

    Nature and Type of Failure Construction failure

    10m diameter and 20m deep void formed in the ground behind a row

    of houses

    Ground and Groundwater Conditions

    Thanet Sands

    Construction Methods and Support

    Tunnelling using TBM (diameter 8.2m)

    ICE (2003)

  • Possible Cause of Failure The vibration from the TBM may have caused the nearby wells

    (30m deep and 1.8m diameter) to collapse

    Consequence Three uncharted wells collapsed

    Emergency and Remedial Measures The voids were backfilled with grout

    Lessons Learnt Unpublished

  • Case No 29. Mtor Metro Tunnel, France, 14 Feb. 2003 Europe

    France

    14 February 2003

    Project Title The Mtor Metro Tunnel

    Source of Information Dubois, P. & Rat, M. (2003). Effondrement sur le chantier

    "Mtor. Conseil Gnral des Ponts et Chausses, France, 22p. (31 Jan. 2007).

  • Keywords (for searching) Mtor, Pairs, France, sinkhole

    Figures

    Dubois & Rat (2003)

  • Figures Location map and section

    Dubois & Rat (2003)

  • Figures Hall plan

    Dubois & Rat (2003)

  • Background Construction of the extension of Mtor Metro Tunnel including

    the Olympics station and a maintenance hall

    Nature and Type of Failure Construction failure

    About 3,000m3 of sedimentary deposits collapsed underneath a school, occupying an area of 400m2 on plan

    Ground and Groundwater Conditions

    Coarse limestone and plastic clay (clays of Sparnacian)

    Construction Methods and Support

    Supported by bolts and shotcrete

    Dubois & Rat (2003)

  • Possible Cause of Failure The coarse limestone had inferior mechanical characteristics to

    the homogeneous medium assumed in the design

    Unfavorable orientation of the fracture

    Implementation of inadequate support due to the overreliance on calculations

    Consequence No casualties

    The school had to be closed for a year affecting 900 students

    Emergency and Remedial Measures Filling the hall under the building by concrete

    Lessons Learnt Unpublished

  • Case No 30. Oslofjord Subsea Tunnel, Norway, 28 Dec. 2003 Europe

    Norway

    28 December 2003

    Project Title The Oslofjord Subsea Tunnel

    Source of Information Karlsrud Kjell (2010). Technical Note : Experience with tunnel

    failures in Norwegian tunnels. The Government of the Hong Kong

    Civil Engineering and Development Department. (Unpublished).

  • Keywords (for searching) Oslofjord, Norway, subsea tunnel, rock fall

    Figures

    First failure Third failure

    Karlsrud (2010)

  • Background The road tunnel was 7.3 km long and 11.5 m wide (3 lanes)

    Three major failures and many minor failures occurred

    Nature and Type of Failure In service failure

    First failure occurred on 28 December 2003: about 20m3 of crushed and weathered rock involving with clay, which came

    down from the crown went through the frost insulated water

    shielding vault and down to the carriageway

    Second failure involved about 3m3 of heavily weathered rock, which came down from the springline and fell down to the invert

    Third failure involved 2-3m3 of completely weathered rock, which fell down from the crown and rested on top of the water

    shielding vault

  • Ground and Groundwater Conditions Precambrian gneisses with lenses of amphibolites, veins of

    pegmatite, and a few dykes of diabase and rhomb porphyry

    Swelling clay was found at the weakness zones

    Construction Methods and Support Mainly supported by steel fibre reinforceed shotcrete combined

    with rock bolts

    Possible Cause of Failure The humidity behind the vault constructed for frost insulated

    water shielding was high and the high content of swelling clay in the weathered rock started sucking water and expanded gradually over a long period of time

  • Consequence Closure of the tunnel for more than 3 months for extensive repairs

    and upgrading of the tunnel support

    Emergency and Remedial Measures Complete removal of the vault before installing additional rock

    support including fiber reinforced shotcrete, rock bolts and reinforced ribs of sprayed concrete

    Lessons Learnt The importance of proper geological mapping and rock mass

    classification

    The need to identify swelling minerals and the potential of deterioration of strength in weathered rock

    The importance of adequate support design for long-term stability in weathered rock

  • Case No 31. Shanghai Metro, China, 2003 Asia

    China

    2003

    Project Title Shanghai Metro Project

    Source of Information Boos, R., Braun, M., Hangen, P., Hoch, C., Popp, R., Reiner,

    H., Schmid, G., & Wannick, H. (2004). Underground

    Transportation Systems, Chances and Risks from the Re-

    insurers Point of View. Munich Re Group, Germany, pp 58-62. (31 Jan. 2007).

  • Keywords (for searching) Shanghai, China, water ingress, ground subsidence

    Figures

    Boos et al (2004)

  • Background Expansion of the Shanghai Metro () Line 4 crossing

    beneath the Huangpu River ()

    Two parallel tunnel tubes constructed by earth pressure balance TBM

    Nature and Type of Failure Construction failure

    Failure occurred during construction of a cross passage

    Massive ingress of water and material at the face at a depth of 35m

    Several metres ground subsidence

    Ground and Groundwater Conditions Water-bearing ground

    Construction Methods and Support EPB TBM

  • Possible Cause of Failure Failure of ground freezing unit

    Consequence High rise office buildings seriously damaged

    Flood protection dyke on the river badly damaged

    Emergency and Remedial Measures Unpublished

    Lessons Learnt Unpublished

  • Case No 32. Nikkure-yama Tunnel, Japan, 2003

    Asia

    Japan

    2003

    Project Title

    Nikkure-yama Tunnel of the Joshinnetsu Expressway

    Source of Information Takahashi, Hiroshi (2010). Huge collapse leading to ground

    surface caving in 130m earth thickness.

  • Keywords (for searching) Japan, mudstone, sinkhole

    Figures

    Takahashi (2010)

  • Background East work section of Nikkure-yama Tunnel

    Nature and Type of Failure Construction failure

    Ground collapse of an avalanche type containing cobbles, gravels and water took place at the point 900m away from the tunnel portal

    A large crater was observed at the ground surface about 130m above the tunnel

    Ground and Groundwater Conditions

    Mudstone

    Construction Methods and Support

    Shortcrete and ribs

    Takahashi (2010)

  • Possible Cause of Failure Existence of high groundwater

    pressure

    Decrease in cover of the mud-stone layer

    Water path created by the investigation drillhole

    Consequence Programme delayed for about 2

    years

    Emergency and Remedial Measures

    Filling the cave-in area by foam concrete

    Grouting under the collapse area

    Boring for drainage from the tunnel

    Takahashi (2010)

  • Lessons Learnt The importance of adequate ground investigation before

    tunnelling

    The importance of investigations and observations during construction for adopting appropriate support measures

  • Case No 33. Guangzhou Metro Line 3, China, 1 April 2004 Asia China 1 April 2004

    Project Title The Guangzhou Metro Line 3

    Source of Information China Daily (2004). 100 homeless after metro site collapse.

    (2 April

    2004).

    Soufun (2004). : 3 . (4 April 2004).

    Longhoo (2004). 3 .

    (2 April 2004).

  • Keywords (for searching) Guangzhou, China, diaphragm wall, building collapse

    Figures

    ChinaDaily (2004)

  • Background Construction of a 58.5km long underground metro in which

    45.6km is a single-tube shield TBM

    Nature and Type of Failure Construction failure

    Failure of a diaphragm wall

    Ground and Groundwater Conditions Unpublished

    Construction Methods and Support Single-tube shield TBM

  • Possible Cause of Failure Rapid fluctuation of groundwater level due to the heavy rainfall

    Complicated geology including a layer of swelling soil

    Consequence A three-storey building collapsed and sunk into the ground

    Collapse of nearby underground water mains

    Emergency and Remedial Measures Backfilled with crushed rock and cement

    Lessons Learnt Unpublished

  • Case No 34. Singapore MRT, 20 April 2004 Asia

    Singapore

    20 April 2004

    Project Title Circle Line of the Singapore MTR

    Source of Information Government of Singapore (2005). Report of the Committee of

    Inquiry into the Incident at the MRT Circle Line Worksite That

    Led to the Collapse of Nicoll Highway on 20 April 2004.

    Government of Singapore, Land Transport Authority. (31 Jan. 2007).

  • Keywords (for searching) Singapore, MRT, Cut-and-Cover, diaphragm wall

    Figures

    Government of Singapore (2005)

  • Background An open cut tunnel excavated for Singapore MRTs new Circle

    Line

    Design and build

    Excavated trench of 15m wide and 33m deep supported by 0.8-1.0m thick diaphragm wall which is 35-45m deep without rock

    socket

    Steel struts: 4-5m horizontal and 3m vertical spacing

    Bottom-up construction

    Jet grouted base slabs

    Layer 1-1.5m thick at 28.5m below ground

    Layer 2-3m thick at 33.5m below ground (Layer 2 not yet constructed when collapse occurred)

  • Nature and Type of Failure Construction failure

    9th level of struts being installed when collapse took place

    Unusual cracking and groaning noises heard early in the morning (6 hours)

    Loud cracking noise heard in the afternoon, 15 minutes before collapse

    Collapse plan area was 100m by 130m

    Settlement up to 15m

    Diaphragm walls displaced

    Steel struts mangled

    Ground and Groundwater Conditions Mainly marine clay with some fluvial clay

    Government of Singapore (2005)

  • Construction Methods and Support Cut-and-Cover method

    Possible Cause of Failure Under-design of the strut-waler connection in the strutting

    system

    Incorrect use of Finite Element Method

    No proper design reviews

    Disregard of different warnings, for example, excessive wall deflections and surging inclinometer readings

    Poor construction quality

    Ineffective instrumentation and monitoring system

    Failure to implement risk management

  • Consequence Part of Nicoll Highway, Singapores major east-west harbour-front

    road, destroyed

    Four workers killed

    Several others injured

    15,000 people and 700 businesses affected

    Three offices and retail towers at risk from further ground movement

    Damage of a gas service line, resulting in an explosion and fire

    A storm drain damaged

  • Emergency and Remedial Measures Rescue and backfilling

    Structurally disconnected the Merdeka Bridge

    All contracts of the Circle Line put on hold

    All contracts to carry out checks and review of design and construction of temporary works

    All Professional Engineers to confirm in writing the adequacy of their designs

    All designs to be independently checked by the Building & Construction Authority

  • Lessons Learnt This is a need for robust design, risk management, design review

    and independent checking, purposeful back analysis, an effective

    instrumentation, monitoring and interpretation regime, an effective

    system of management of uncertainties and quality during

    construction, corporate competencies and safety management

    The safety of temporary works is as important as that of permanent works and should be designed according to

    established codes and checked by competent persons

  • Case No 35. Kaohsiung Rapid Transit, Taiwan, 29 May 2004

    Asia

    Taiwan

    29 May 2004

    Project Title Kaohsiung Rapid Transit

    Source of Information Lee, W. F. & Ishihara, K. (2011) Forensic diagnosis of a

    shield tunnel failure. Engineering Structures. Volume 32,

    Issue 7, July 2010, Pages 1830-1837.

  • Keywords (for searching) Kaohsiung, Taiwan, diaphragm wall, building damaged,

    sinkhole

    Figures

    Lee & Ishihara (2010)

  • Background Chemical Churning Piles (CCP) of

    350mm diameter installed as guide walls

    for the diaphragm wall construction

    Soil improvement works by the use of Super Jet Grouting (SJG) method at the

    reception area for break-out operations

    The diaphragm wall panels were first cored through by chain saw according to

    the face-shape of the shield tunnel

    machine and manual power tool was

    used to disassemble the reinforced

    concrete residual inside the coring holes

    EPB Tunnel Boring Machine 500mm away from the wall face awaiting for

    break-out and invert leakage started

    Lee & Ishihara (2010)

  • Nature and Type of Failure Construction failure

    Sinkhole of about 10m in diameter formed at the ground surface

    Ground settlement influence zone ranging from 40m to 50m in diameter with maximum settlement from 500mm to 1,500mm.

    Several rings of tunnel s

    Chemical Churning Pile

    (CCP)

    Soil Improvement Zone

    Diaphragm Wall

    egmental linings were damaged

    CCP

    Possible

    Collapse Zone

    Soil Improvement Zone

    Leakage spot

    Tunnel Boring Machine

    Path of Leakage

    Lee Lee & & IshiharIshihara a (2(2010)010)

    Settled Area of Ground Surface

  • Ground and Groundwater Conditions Silty sand and sandy silt soil layers

    Silt deposit sandwiched by impermeable clay layers

    Construction Methods and Support Tunnelling by EPB Tunnel Boring Machine

    Possible Cause of Failure Progressive development of unexpected cracks inside the soil

    improvement zone resulting in groundwater leakages in the

    reception area as a result of piping and/or hydraulic fracturing

    Leakage paths at the interfaces between Chemical Churning Pile (CCP) and the diaphragm wall, CCP and Super Jet Grout (JSG)

    materials, or inside the lower portion of the JSG body

    Chloride assault and deterioration of CCP, which were installed two years before the wall breaking process, had significant effects on the

    integrity and water tightness at the interfaces

  • Possible Cause of Failure (cont) The highly sensitive and erodible soil dispersed around the SJG

    might have been disturbed due to the application of highly

    pressured water jet in the grouting process

    Mechanical and/or vibration disturbances occurred during the wall

    breaking process leading to serious cracks and fissure

    development inside the deteriorated CCP and defective SJG

    blocks

    Unfavourable sub-surface conditions which consisted of silty

    sands and sandy silts with water contents almost reaching their

    liquid limits

    Consequence Adjacent buildings were damaged

    Lee & Ishihara (2010)

  • Emergency and Remedial Measures Stabilizing the ground by piling-up sand bags in front of the tunnel

    face to reduce leakage, backfilling the sinkhole and grouting the

    tunnel crown and invert

    Advancing the TBM further to reduce the gap between the D-wall

    and the tunnel

    Installation of steel frames to reinforce the damaged ring segments

    Lee & Ishihara (2010) Lessons Learnt Unpublished

  • Case No 36. Oslo Metro Tunnel, Norway, 17 June 2004 Europe

    Norway

    17 June 2004

    Project Title The Oslo Metro Tunnel

    Source of Information Karlsrud Kjell (2010). Technical Note : Experience with tunnel

    failures in Norwegian tunnels. The Government of the Hong

    Kong Civil Engineering and Development Department.

    (Unpublished).

  • Keywords (for searching) Oslo, Norway, cave in

    Figures

    F:\i\21\miljo\div\2000\ah-1.ppt

    T-baneringen Modell 3

    Strste hovedspenning, 1 er styrt av lagdelingssprekkene og tverrsprekken. Strekkspenninger over taket til

    Hasletunnelen og videre til indre lp mot Sinsen.

    Karlsrud (2010)

    F:\i\21\miljo\div\2000\ah-1.ppt

    Planned

    concrete wall

    Cave in area

    F:\ i\21\miljo\div\2000\ah-1.ppt

  • Background Metro line tunnel 1.3km long and 7m wide connecting with an old

    tunnel

    Nature and Type of Failure Construction failure

    At the junction where the two tunnels met in an acute angle, tunnel cave-in after removal of most part of the rock pillar between the

    tunnels

    Ground and Groundwater Conditions Interlayered shale and nodular limestone with 1-5cm thick clay

    seams along many of the bedding planes

    The bedding planes were dipping 20-45 and running almost parallel to the tunnel

  • Construction Methods and Support Constructed by drill-and-blast method supported by rock bolts

    and fibre reinforced sprayed concrete. A concrete wall/pillar was

    planned to be constructed between the old tunnel and new

    tunnel

    Possible Cause of Failure Unfavourable direction of the bedding planes in relation to the

    geometry and span of the tunnels

    Over excavation of the rock pillar and the removal of the remaining rock pillar and old concrete wall before the planned concrete pillar was constructed

    Consequence Programme delayed for about 3 months

    Cost implication: extra cost of the remedial works

  • Emergency and Remedial Measures Filling up the whole opening by concrete above the fallen debris

    Installation of 10m long cable anchors together with permanent support of 200mm thick lining of reinforced sprayed concrete, reinforced ribs of sprayed concrete and additional 6m long rock bolts

    Lessons Learnt The importance of adequate ground investigation

    The need to follow the sequence of rock support installation in accordance with the design plans during construction

  • Case No 37. Kaohsiung Rapid Transit, Taiwan, 10 Aug. 2004

    Asia

    Taiwan

    10 August 2004

    Project Title Kaohsiung Rapid Transit

    Source of Information Taiwan Info (2004). Nouvel incident sur le chantier du mtro

    de Kaohsiung. Taiwan. (31 Jan. 2007).

  • Keywords (for searching) Kaohsiung, Taiwan

    Figures

    Taiwan Info (2004)

  • Background Construction of the Kaohsiung Rapid Transit Blue & Orange

    Lines in Kaohsiung City

    Nature and Type of Failure Construction failure

    First collapse on 29 May 2004 underneath a street

    Second collapse in mid June 2004

    Third collapse on 13 July 2004 with formation of a large sinkhole

    Fourth collapse on 10 Aug 2004

    Ground and Groundwater Conditions Unpublished

    Construction Methods and Support Unpublished

  • Possible Cause of Failure Possible adverse ground and groundwater conditions

    Consequence First collapse - Several buildings affected and 100 people

    evacuated

    Third collapse - Three residential buildings evacuated and significant disruption to water/electricity supply

    Fourth collapse - No casualty, one building affected and part of the works suspended

    Emergency and Remedial Measures Unpublished

    Lessons Learnt Unpublished

  • Case No 38. Hsuehshan Tunnel, Taiwan, 1991-2004

    Asia

    Taiwan

    1991 - 2004

    Project Title

    The Taipei-Ilan Expressway

    Source of Information TANEEB ( 2 0 0 5 ) . Hsuehshan Tunnel. Taiwan Area

    National Expressway Engineering Bureau ( ) , Taiwan. (31 Jan. 2007).

  • Keywords (for searching) Hsuehshan, Taiwan, groundwater inflow, tunnel collapse

    Figures

    Taiwan Info (2004)

    TANEEB (2005)

  • Background Construction of 12.9km long and 11.7m diameter Hsuehshan

    Tunnel in Taiwan ()

    Works commenced in 1991 and completed in 2004

    Comprised 2 main tunnels (East & Westbound) and a pilot tunnel

    Westbound Eastbound

    Pilot Tunnel

    TANEEB (2005)

  • Nature and Type of Failure Construction failure

    Eastbound - 28 collapses occurred

    Westbound - TBM badly damaged due to tunnel collapse and groundwater inflow of 45,000 litres/min into the tunnel

    Pilot Tunnel - 8 collapses occurred

    Ground and Groundwater Conditions The major geologic elements are Eocene, Oligocene and minor

    Miocene folded sedimentary rock formations

    Highly fractured rock with six major faults

    Construction Methods and Support Eastbound by TBM method (July 1993 to Sept. 2004)

    Westbound by TBM method (July 1993 to April 2004)

    Pilot tunnel by drill & blast method (July 1991 to Oct. 2003)

  • Possible Cause of Failure Unexpected difficult geology with fractured rock and massive

    inflows of water

    6 major faults found along the tunnel alignment

    Consequence Eastbound - Failure in May 1993 affected 56 buildings and 73

    families

    Westbound - 11 men died

    Pilot Tunnel - 13 stoppages

    Emergency and Remedial Measures Unpublished

    Lessons Learnt Unpublished

  • Case No 39. Barcelona Metro, Spain, 27 Jan. 2005 Europe

    Spain

    27 January 2005

    Project Title Barcelona Line 5 Metro Extension

    Source of Information European Foundations (2005). Tighter NATM rules follow

    Barcelona failure. European Foundations, Spring Issue, No.

    26, p 3.

  • Keywords (for searching) Barcelona, Spain, sinkhole

    Figures

    European Foundations (2005)

  • Background Tunnel for Barcelona Line Five Metro Extension

    Nature and Type of Failure Construction failure

    Part of the lining collapsed

    30m wide and 32m deep crater formed

    Ground and Groundwater Conditions Weathered slate and ancient and weathered metamorphic

    ground with a vertical and hidden fault at the location of

    collapse

    Construction Methods and Support Tunnelling using NATM

  • Possible Cause of Failure A hidden vertical fault located 1m behind the sprayed

    concrete lining

    Consequence 2 five-storey buildings and a smaller one demolished

    More than 50 families made homeless

    Emergency and Remedial Measures The void was backfilled with grout of about 2,000m3

    The tunnel section was backfilled with 18,000m3 of grout through a horizontal borehole in the debris and five points from the surface

    Additional boreholes, horizontal probes and supports for future excavation

    Lessons Learnt Unpublished

  • Case No 40. Lausanne M2 Metro, Switzerland, 22 Feb. 2005 Europe

    Switzerland

    22 February 2005

    Project Title Lausanne Metro M2 project

    Source of Information Tunnels & Tunnelling (2005). Lausanne Metro Tunnel collapse.

    Tunnels & Tunnelling International, April Issue, p 6.

  • Keywords (for searching) Lausanne, Switzerland, sinkhole

    Figures

    Tunnels & Tunnelling (2005)

  • Background Tunnel (6km long, approximately 10m wide x 7m high) for

    Lausanne Metro M2 Project (cost US$472M) in Switzerland

    Nature and Type of Failure Construction failure

    50m3 of material displaced into the tunnel at a depth of 12m, leading to a crater at the surface

    Ground and Groundwater Conditions Collapse in area of soft ground (lake deposits)

    Construction Methods and Support Tunnelling using an Eickhoff ET 380-L roadheader

  • Possible Cause of Failure Tunnel driven through a pocket in the glacial moraine, causing

    sudden inflow of groundwater

    Consequence People in two buildings, a supermarket and a food outlet in

    commercial district evacuated when their cellars collapsed

    No injuries reported

    Emergency and Remedial Measures A curtain of 11 piles constructed ahead of the collapsed face with

    grouting to strengthen the ground and limit further flow of material into the tunnel

    The void was backfilled with 800m3 of glass-sand (recycled glass)

    Lessons Learnt Unpublished

  • Case No 41. Lane Cove Tunnel, Australia, 2 Nov. 2005 Australia

    2 November 2005

    Project Title L