hk notabletunnel cat
DESCRIPTION
HK NotableTunnel CatTRANSCRIPT
-
Catalogue of Notable
Tunnel Failures -
Case Histories
(up to April 2015)
Prepared by Mainland East Division Geotechnical Engineering Office
Civil Engineering and Development Department
-
This catalogue of notable tunnel failures is primarily
based on published information. Both local and international
cases involving collapse or excessive deformation of the
ground are included. For contractual and other reasons, there
are relatively few cases reported in technical publications, and
those reported are usually of such scale or seriousness that
they have received public attention. Even for the cases reported,
usually only limited information is available. Apart from the
cases included, readers can find other information on tunnel
failure in the list of Bibliography given at the end of this
catalogue.
This catalogue is a live document that will be updated
from time to time as further information becomes available.
Readers are always welcome to provide us with additional
information about cases in this catalogue for future update.
-
The main purpose of the catalogue is to disseminate
information and promote awareness on tunnel failures which
could pose a danger to life and property. The possible causes
of the failures, the geotechnical problems and the lessons learnt,
where these are known, are outlined in the catalogue. Readers
should refer to the source reference documents quoted for
details. Clients and works agents are advised to implement
effective geotechnical risk management measures in the
planning, investigation, design and construction of their tunnel
projects.
-
The first edition of the catalogue was issued in February
2007 and was put together by Mr W Lee, supervised by Mr K J
Roberts. The second edition issued in March 2009 was prepared
by Ms L Y Pau, supervised by Mr L P Ho. The third edition issued
in October 2012 was prepared by Ms L Y Pau, supervised by Mr K
S Chau. This fourth edition was prepared by Ms K L Wong and Mr
H H Chan, supervised by Mr K S Chau. GEO staff, members of the
Hong Kong Institution of Engineers Geotechnical Division
Working Group on Cavern and Tunnel Engineering and other
individuals have contributed to this catalogue. All contributions
are gratefully acknowledged. Special thanks are given to Mr Guy
Lance for his valuable advice and guidance given to revising the
systematic structure of this catalogue, sourcing figures and
references from tunnel publications as well as editing reported
cases.
-
If any information in this catalogue is found to be
inaccurate or out-of-date, please contact the Chief Geotechnical
Engineer/Mainland East of the Geotechnical Engineering Office,
Civil Engineering and Development Department, 101 Princess
Margaret Road, Ho Man Tin, Kowloon, Hong Kong.
N F Chan
Chief Geotechnical Engineer/Mainland East
Geotechnical Engineering Office
Civil Engineering and Development Department
April 2015
-
Civil Engineering and Development Department
The Government of the Hong Kong Special Administrative Region
1. Green Park, London, UK, 1964
2. Victoria Line Underground, London, UK, 1965
3. Southend-on-sea Sewage Tunnel, UK, 1966
4. Rrvikskaret Road Tunnel on Highway 19, Norway, 18 March
1970
5. Orange-fish Tunnel, South Africa, 1970
6. Penmanshiel Tunnel, Scotland, UK, March 1979
7. Munich Underground, Germany, 1980
8. Holmestrand Road Tunnel, Norway, 16 Dec. 1981
9. Gibei Railway Tunnel, Romania, 1985
10. Moda Collector Tunnel, Istanbul Sewerage Scheme, Turkey, 1989
-
Civil Engineering and Development Department
The Government of the Hong Kong Special Administrative Region
11. Seoul Metro Line 5 - Phase 2, Korea, 17 Nov. 1991
12. Seoul Metro Line 5 - Phase 2, Korea, 27 Nov. 1991
13. Seoul Metro Line 5 - Phase 2, Korea, 11 Feb. 1992
14. Seoul Metro Line 5 - Phase 2, Korea, 7 Jan. 1993
15. Seoul Metro Line 5 - Phase 2, Korea, 1 Feb. 1993
16. Munich Underground, Germany, 27 Sept. 1994
17. Heathrow Express, UK, 21 Oct. 1994
18. Los Angeles Metro, USA, 22 June 1995
19. Motorway Tunnels, Austria, 1993 - 1995
20. Docklands Light Rail, UK, 23 Feb. 1998
-
Civil Engineering and Development Department
The Government of the Hong Kong Special Administrative Region
21. Athens Metro, Greece, 1991-1998
22. L rdal Road Tunnel on European Highway E 16, Norway, 15
June 1999
23. Sewage Tunnel, Hull, UK, 1999
24. Taegu Metro, South Korea, 1 Jan. 2000
25. Wastewater Tunnel, Portsmouth, UK, May 2000
26. Dulles Airport, Washington, USA, Nov. 2000
27. Istanbul Metro, Turkey, Sept. 2001
28. Channel Tunnel Rail Link, UK, Feb. 2003
29. Mtor Metro Tunnel, France, 14 Feb. 2003
30. Oslofjord Subsea Tunnel, Norway, 28 Dec. 2003
-
Civil Engineering and Development Department
The Government of the Hong Kong Special Administrative Region
31. Shanghai Metro, China, 2003
32. Nikkure-yama Tunnel, Japan, 2003
33. Guangzhou Metro Line 3, China, 1 April 2004
34. Singapore MRT, 20 April 2004
35. Kaoshiung Rapid Transit, Taiwan, 29 May 2004
36. Oslo Metro Tunnel, Norway, 17 June 2004
37. Kaoshiung Rapid Transit, Taiwan, 10 Aug. 2004
38. Hsuehshan Tunnel, Taiwan, 1991-2004
39. Barcelona Metro, Spain, 27 Jan. 2005
40. Lausanne M2 Metro, Switzerland, 22 Feb. 2005
-
Civil Engineering and Development Department
The Government of the Hong Kong Special Administrative Region
41. Lane Cove Tunnel, Australia, 2 Nov. 2005
42. Kaoshiung Rapid Transit, Taiwan, 4 Dec. 2005
43. Nedre Romerike Water Treatment Plant Crude Water and Potable
Water Tunnels, Norway, 2005
44. Interstate 90 Connector Tunnel, Boston, Massachusetts, USA, July
2006
45. Hanekleiv Road Tunnel, Norway, 25 Dec. 2006
46. Stormwater Management and Road Tunnel (SMART), Malaysia,
2003 2006
47. Sao Paulo Metro Station, Brazil, 15 Jan. 2007
48. Guangzhou Metro Line 5, China, 17 Jan. 2008
49. Langstaff Road Trunk Sewer, Canada, 2 May 2008
50. Circle Line 4 Tunnel, Singapore, 23 May 2008
-
Civil Engineering and Development Department
The Government of the Hong Kong Special Administrative Region
51. M6 Motorway, Hungary, 24 Jul. 2008
52. Hangzhou Metro Tunnel, China, 15 Nov. 2008
53. Cologne North-South Metro Tram Line, Germany, 3 March 2009
54. Brightwater Tunnel, USA, 8 March 2009
55. Seattles Beacon Hill Light Rail, USA, July 2009
56. Glendoe Headrace Tunnel, Scotland, UK, Aug. 2009
57. Cairo Metro Tunnel, Egypt, 3 Sept. 2009
58. Headrace tunnel of Gilgel Gibe II Hydro Project, Ethiopia, Oct. 2006
and Jan. 2010
59. Blanka Tunnel, Czech Republic, 20 May 2008, 12 Oct. 2008 and 6
July 2010
60. Shenzhen Express Rail Link, 27 March 2011, 4 May 2011 and 10
May 2011
-
Civil Engineering and Development Department
The Government of the Hong Kong Special Administrative Region
61. Mizushima Refinery Subsea Tunnel, Japan, 14 Feb. 2012
62. Hengqin Tunnel, Macau, 19 July 2012
63. Sasago Tunnel, Japan, 2 Dec. 2012
64. Ottawas Light Rail Transit Project, Canada, 20 Feb. 2014
65. Rios Metro Line 4, Brazil, 11 May 2014
-
Civil Engineering and Development Department
The Government of the Hong Kong Special Administrative Region
1. MTR Modified Initial System, Prince Edward Station, Nathan
Road, Hong Kong,12 Sept. 1977
2. MTR Island Line, 22 Hennessy Road, Hong Kong, 1 Jan. 1983
3. MTR Island Line, Shing On Street, Shau Kei Wan, Hong Kong,
23 July 1983
4. MTR Island Line, 140-168 Shau Kei Wan Road, Hong Kong, 16
Dec. 1983
5. Kowloon Southern Link Contract KDB 200, Canton Road, Hong
Kong, 21 Oct. 2006
6. Kowloon Southern Link Contract KDB 200, Salisbury Road,
Hong Kong, 3 June 2007
-
Case No 1. Green Park, London, UK, 1964 Europe
United Kingdom
1964
Project Title Green Park to Victoria Tunnel, UK
Source of Information Clay, R.B. & Takacs, A.P. (1997). Anticipating the unexpected
Flood, fire overbreak, inrush, collapse. Proceedings of the
International Conference on Tunnelling Under Difficult Ground
and Rock Mass Conditions, Basel, Switzerland, pp 223-242.
-
Keywords (for searching) Green Park, London, UK, London Clay
Figures
Clay & Takacs (1997)
-
Background Segmental lined tunnel (Green Park to Victoria) driven through
London Clay with low soil cover
Nature and Type of Failure Construction failure
Inflow of sand and gravel, burying most of the shield
Ground and Groundwater Conditions London Clay overlain by water-bearing sands and gravels
Construction Methods and Support Using drum-digger shield
Possible Cause of Failure The crown of the shield penetrated through the London Clay
layer into sand and gravel
-
Consequence Little physical damage to the shield
Programme delayed
Emergency and Remedial Measures A shaft was sunk from the surface to enable the material to be
staunched and treated.
The loose material was dug out by hand
Lessons Learnt Unpublished
-
Case No 2. Victoria Line Underground, UK, 1965 Europe
United Kingdom
1965
Project Title Victoria Line Underground Railway
Source of Information Clay, R.B. & Takacs, A.P. (1997). Anticipating the unexpected
Flood, fire overbreak, inrush, collapse. Proceedings of the
International Conference on Tunnelling Under Difficult Ground
and Rock Mass Conditions, Basel, Switzerland, pp 223-242.
-
Keywords (for searching) Victoria Line, London, UK, London Clay
Figures
Clay & Takacs (1997)
-
Background Tunnel (300m long and 3.7m internal diameter) driven through
London Clay under a disused railway marshalling yard
Nature and Type of Failure Construction failure
Inflow of sand and gravel
Ground and Groundwater Conditions London Clay underlain by sands and gravels
Construction Methods and Support Using hand-shield and lined with cast-iron
Possible Cause of Failure The shield was ineffective in supporting the overlying ground
-
Consequence No significant damage
Programme delayed for about 6 months
Emergency and Remedial Measures Lengthy grouting operation for stabilizing the ground in the
vicinity
Lessons Learnt Unpublished
-
Case No 3. Southend-on-Sea Sewage Tunnel, UK, 1966 Europe
United Kingdom
1966
Project Title Southend-on-Sea Sewage Tunnel, UK
Source of Information Clay, R.B. & Takacs, A.P. (1997). Anticipating the unexpected
Flood, fire overbreak, inrush, collapse. Proceedings of the
International Conference on Tunnelling Under Difficult Ground
and Rock Mass Conditions, Basel, Switzerland, pp 223-242.
-
Keywords (for searching) Southend-on-Sea, London, UK, London Clay
Figures
Clay & Takacs (1997)
-
Background Tunnel 40m long with diameter of 1.35m driven mostly by hand
Nature and Type of Failure Construction failure
Water inflow into the tunnel
Ground and Groundwater Conditions London Clay overlain by sands and gravels
Construction Methods and Support Driven mostly by hand and lined with PCC segments
Possible Cause of Failure The tunnel intersected the bottom of an abandoned 600mm
diameter well
-
Consequence No loss of life or injury
Emergency and Remedial Measures The tunnel drive was continued in a timbered box heading and
two plates were fabricated for closed off the bottom of the well. Grouting was also applied
Lessons Learnt Unpublished
-
Case No 4. Rrvikskaret Road Tunnel on Highway 19, Norway, 18 March 1970
Europe
Norway
18 March 1970
Project Title Rrvikskaret Road Tunnel on Highway 19
Source of Information Karlsrud Kjell (2010). Technical Note : Experience with tunnel
failures in Norwegian tunnels. The Government of the Hong
Kong Civil Engineering and Development Department.
(Unpublished).
-
Keywords (for searching) Rrvikskaret, Norway, cave in
Figures
Karlsrud (2010)
-
Background The road tunnel was 726m long and 8m wide
Nature and Type of Failure Construction failure
Tunnel face collapsed and a 100m high cave-in shaft from the tunnel up to the ground surface was created
The top of the shaft on the ground surface had a dimension of about 25m x 50m
Although soft material was hauled out from the tunnel during the spring in 1971, cave-in continued from the shaft until autumn
1972
The cave-in zone extended 30m along the tunnel and the total volume of material hauled out from the tunnel was about
75,000m3
-
Ground and Groundwater Conditions Crystalline gneisses of granitic and syenitic composition
The tunnel was excavated into a large zone of swelling clay. The rock at the failure was completely altered to swelling clay
Construction Methods and Support Constructed by the drill-and-blast method and mainly supported
by rock bolts, steel straps and mesh
Possible Cause of Failure Preliminary investigation carried out without any drilling
Probe drilling was not performed during tunnelling
No stabilization measures to support a large swelling clay section before blasting
-
Consequence Programme delayed for more than 3 years
Double the cost of the tunnel compared to the estimated cost
Emergency and Remedial Measures Installation of corrugated steel vault, steel tubes and 500mm thick
concrete lining was not successful
The cave-in ceased after filling of about 3,000m3 concrete into the
shaft to form a plug from the tunnel up to 10m above the crown
and another 4,000m3 of sand and stone from the top of the shaft
above the concrete plug
Lessons Learnt The importance of the adequate ground investigation to identify if
weak ground is present and to provide measures to support the
weak ground before tunnel excavation
-
Case No 5. Orange-fish Tunnel, South America, 1970 South Africa
1970
Project Title Orange-fish Tunnel, South Africa
Source of Information Clay, R.B. & Takacs, A.P. (1997). Anticipating the unexpected
Flood, fire overbreak, inrush, collapse. Proceedings of the
International Conference on Tunnelling Under Difficult Ground
and Rock Mass Conditions, Basel, Switzerland, pp 223-242.
-
Keywords (for searching) Orange-fish, South Africa, fire
Figures N/A
Background Circular tunnel designed to carry irrigation water from the
Orange River (80km long and 5.3m in diameter, 1,200m above
sea level)
Nature and Type of Failure Construction failure
First failure Heavy water inflow (of about 55,000 litres/min into the tunnel at 14 bars)
Second failure Fire (Methane gas ignited by a blast, but no explosion occurred as the gas did not reach the explosive
concentration)
-
Ground and Groundwater Conditions Sandstones, siltstones and mudstones, generally horizontally
bedded with occasional dolerite dykes
Construction Methods and Support Tunnelling using the rail-mounted drill and blast method and lined
with 225mm of insitu concrete
1.5m long tensioned resin-grouted bolts at 1.5m spacing with occasional shotcrete
Possible Cause of Failure First failure The tunnel passed through a shallow anticline and
intersected a fissure, about 75mm wide, almost perpendicularly
Second failure Methane gas from a methane bearing fissure entered the tunnel during excavation
-
Consequence
First failure Entire 1.6km tunnel section flooded within 24 hours
Second failure The fire burnt for about 6 months
Emergency and Remedial Measures
First failure Grouting was carried out from the surface and the tunnel was pumped dry. Blob-grouting method with a ring of very thick grout of unhydrated bentonite to seal the fissures a short distance away from the tunnel was developed for the subsequent excavation
Second failure A wall was built across the tunnel, the void beyond, including the methane-bearing fissure, was grouted up with cement
Lessons Learnt Unpublished
-
Case No 6. Penmanshiel Tunnel, Scotland, UK, March 1979 Europe
Scotland, UK
March 1979
Project Title Enlargement of the Penmanshiel Tunnel
Source of Information McNaughton, I.K.A. (1983). Report on the collapse of Penmanshiel
Tunnel that occurred on 17th March 1979 in the Scottish Region, British Railways, Department of Transport, 7 p. .
-
Keywords (for searching) Europe, Scotland, 1979, Penmanshiel Tunnel, British Railways,
construction failure, fall of rock, anticlinal structure, over-stressed rock
Figures Penmanshiel Tunnel, near Grantshouse in Scotland
Source from http://en.wikipedia.org/wiki/Penmanshiel_Tunnel
-
Background The double rail track Penmanshiel tunnel of 7.72m span and
4.7m height was driven in 1845/1846
In 1979 the roof of the tunnel collapsed during tunnel enlargement works when the tunnel invert was being reconstructed to increase the headroom
Nature and Type of Failure
Ground failure during reconstruction
Fall of rock over a length of some 20m
Ground and Groundwater Conditions Sedimentary rock of steeply inclined and complex stratification
with an average cover of 25 to 30m
Dry conditions
Construction Methods and Support Rock bench system with an arch lined with 4 or 5 rings of bricks
-
Possible Cause of Failure The existence of complex anticlinal structure over the line of the
tunnel, which could not have been deduced from rock exposed in the tunnel but was later exposed in the open cut excavation after the diversion of the tunnel alignment
The degeneration of the rock within the anticlinal structure built up heavy loading on the arch ring and side walls
Additional excavation in the tunnel increased the stresses in the already overstressed rock in the side walls
Consequence Broken rock pouring into the tunnel with a complete blockage
13 workers escaped but 2 workers were killed
-
Emergency and Remedial Measures Immediate support provided to the adjacent portion of the tunnel
by a number of steel arches
Long term abandonment of 1,000m of the tunnel and the diversion of the line to a new alignment in open cut with the ends of the old tunnel filled in
Lessons learnt The consequences of adjusting the profile of a working tunnel
without stress analysis and appropriate support
The importance of understanding the geological conditions of the site and the need for analysis
-
Case No 7. Munich Underground, Germany, 1980 Europe
Gemany
1980
Project Title Munich Underground, Germany
Source of Information Construction Today (1994b). Unstable ground triggers Munich
tunnel collapse. Construction Today, October Issue, p 5.
-
Keywords (for searching) Munich, Germany, sinkhole
Figures
Construction Today (1994b)
-
Background New Austrian Tunnelling Method (NATM) construction of twin 6m
diameter tunnels
Nature and Type of Failure Construction failure
Huge flow of soft clay into the tunnel
Ground and Groundwater Conditions Flinty marl with 3m of cover above the tunnels, overlain by 12.5m
of soft clay
Construction Methods and Support New Austrian Tunnelling Method (NATM)
Possible Cause of Failure Local variation in geology with reduction in marl cover to 1-1.5m
and led to overstressing of the sprayed concrete temporary lining
-
Consequence 10m wide, 14m deep sinkhole
No injury
Emergency and Remedial Measures Void was backfilled with crushed rock and cement and pressure
grouted
Lessons Learnt The danger of tunnel excavation through thin marl cover
-
Case No 8. Holmestrand Road Tunnel, Norway, 16 Dec. 1981 Europe
Norway
16 December 1981
Project Title The Holmestrand Road Tunnel
Source of Information Karlsrud Kjell (2010). Technical Note : Experience with tunnel
failures in Norwegian tunnels. The Government of the Hong
Kong Civil Engineering and Development Department.
(Unpublished).
-
Keywords (for searching) Keywords (for searching) Holmestrand, Norway, cave in
Figures
Karlsrud (2010)
-
Background The road tunnel was 1.78km long and 10m wide
Nature and Type of Failure Construction failure
A minor cave-in from the face and partly from the crown occurred during the process of moving the steel formwork for
cast concrete lining forward to the face
Ground and Groundwater Conditions Various rock types (basalt, volcanic dykes, soft siltstone and
quartz conglomerate)
Construction Methods and Support Constructed by the drill-and-blast method and supported by cast
concrete lining
-
Possible Cause of Failure A weak fault zone was encountered No spiling bolts ahead of the face to support the weak ground
Consequence More time (5 hours extended to 25 hours) required for hauling out
and concreting the foundation for the mould
Emergency and Remedial Measures About 600m3 of debris was hauled in to the face for temporary
support
Until break through, the tunnel was excavated with only 2m long bore holes combined with 6m long spiling bolts from the cast concrete
lining of the former round, and cast concrete lining close to the face
Lessons Learnt Spiling bolts ahead of the face in combination with fibre reinforced
sprayed concrete, rock bolts, and reinforced ribs of sprayed concrete
are required at the fault zones with extremely poor rock mass quality
-
Case No 9. Gibei Railway Tunnel, Romania, 1985 Europe
Romania
1985
Project Title Gibei Railway Tunnel, Romania
Source of Information Clay, R.B. & Takacs, A.P. (1997). Anticipating the unexpected
Flood, fire overbreak, inrush, collapse. Proceedings of the
International Conference on Tunnelling Under Difficult Ground
and Rock Mass Conditions, Basel, Switzerland, pp 223-242.
-
Keywords (for searching) Gibei, Romania
Figures
Clay & Takacs (1997)
-
Background Railway tunnel 2.21km long and 9m in diameter
Nature and Type of Failure Construction failure
Compact fissured clay layer failed suddenly, allowing water inflow >600 litres/min into the tunnel
Ground and Groundwater Conditions Compacted Clay with fissures
Construction Methods and Support Shield (A hooded mechanical sheld 9.05 m in diameter, fitted
with a hydraulic bucket and a bottom-monuted conveyor belt)
Possible Cause of Failure The tunnel penetrated a lens of waterlogged fine-grained sand
just above the crown
-
Consequence Ingress of water at more than 10 L/s accompanied by running
sand to the tunnel covering the machine
Programme delayed for about 6 months
Emergency and Remedial Measures Unpublished
Lessons Learnt Unpublished
-
Case No 10. Moda Collector Tunnel, Istanbul Sewerage Scheme, Turkey, 1989
Europe
Turkey
1989
Project Title Moda Collector Tunnel
Source of Information Clay, R.B. & Takacs, A.P. (1997). Anticipating the unexpected
Flood, fire overbreak, inrush, collapse. Proceedings of the
International Conference on Tunnelling Under Difficult Ground
and Rock Mass Conditions, Basel, Switzerland, pp 223-242.
-
Keywords (for searching) Moda Collector, Istanbul, Turkey
Figures
Clay & Takacs (1997)
-
Background The TBM broke out 8m from the shaft with anticipated 3 m of
rock cover
Nature and Type of Failure Construction failure
Fine soil flowed into the tunnel forming a hole in the road as the TBM went through the rock into the soft ground
Ground and Groundwater Conditions Various ground conditions (very fine and unstable mud & rock)
Construction Methods and Support Tunnel constructed by Tunnel Boring Machine (TBM)
Possible Cause of Failure The tunnel intersected a hidden area of soft clay
-
Consequence A hole formed in the road some 5m above
Broken rock jammed the shield
Emergency and Remedial Measures A shaft was sunk down to release the TBM
Lessons Learnt Probe holes should be drilled to confirm the rockhead profile
-
Case No 11. Seoul Metro Line 5 Phase 2, Korea, 17 Nov. 1991 Asia Korea 17 November 1991
Project Title Second Phase of Seoul Subway
Source of Information Lee, I. M. & Cho, G. C. (2008). Underground construction in
decomposed residual soils (presentation slides). The 6th
International Symposium on Geotechnical Aspects of Underground
Construction in Soft Ground (IS-Shanghai 2008), Tongji University,
Shanghai, April.
Madrid (1996). Informe sobre el NATM del Health & Safety Executive, de Inglaterra, 1996. (1996).
-
Source of Information Shin, J.H., Lee, I.K., Lee, Y.H. & Shin, H.S. (2006). Lessons
from serial tunnel collapses during construction of the Seoul
subway Line 5. Tunnel and Underground Space Technology,
Issue no. 21, pp 296-297.
Keywords (for searching) Seoul, Korea, cave-in
Figures
Lee & Cho (2008)
-
Background Construction of Seoul Metro tunnel near Majang
Tunnel at 15-30m below ground
Nature and Type of Failure Construction failure
After blasting : daylight collapse up to ground surface, involving the embankment of a river
20m x 15m and 4m deep crater at the ground surface
Water from river flowed into the tunnel
Ground and Groundwater Conditions Various weathered granite
Groundwater table at typical 3-10m below the ground surface
Construction Methods and Support by drill and blast method
-
Possible Cause of Failure Thin weathered rock cover
Inflow of soil and groundwater
Consequence Roads collapse and gas mains fractured
Emergency and Remedial Measures Backfilling the crater with soil followed
by cement grouting and chemical grouting
Lessons Learnt Insufficient ground investigation
Unexpected groundwater inflow
No tunnel face stability analysis
No consideration of blasting effects closed to weathered zone with shallow cover
Majang Bridge
Alluvium
Soft rock
Hard rock
Cheonggye-choeon
4. grouting(JSP)
2. sand mat
3. face shotcrete
Fill(SM)Silty sand
Decomposedgranite soil
Weatheredrock
1. backfilling
-3.5m
-24.0m
-29.5m
-3.2m
18.0m
1.4m
-26.5m
1000m3
Sink hole
-12.8m
-13.3m
-18.0m
-
Case No 12. Seoul Metro Line 5 Phase 2, Korea, 27 Nov. 1991 Asia Korea 27 November 1991
Project Title Second Phase of Seoul Subway
Source of Information Lee, I. M. & Cho, G. C. (2008). Underground construction in
decomposed residual soils (presentation slides). The 6th International
Symposium on Geotechnical Aspects of Underground Construction in
Soft Ground (IS-Shanghai 2008), Tongji University, Shanghai, April.
Madrid (1996). Informe sobre el NATM del Health & Safety Executive, de Inglaterra, 1996. (1996).
Shin, J.H., Lee, I.K., Lee, Y.H. & Shin, H.S. (2006). Lessons from serial tunnel collapses during construction of the Seoul subway Line 5.
Tunnel and Underground Space Technology, Issue no. 21, pp 296-
297.
-
Keywords (for searching) Seoul, Korea, cave-in
Figures
Lee & Cho (2008)
-
Background Construction of Seoul Metro tunnel near Tangsan Tunnel at 15-30m below ground
Nature and Type of Failure Construction failure
27 November 1991 10:40am : blasting
4:00pm : rock falls at the tunnel face
10:00pm : soil and groundwater inflow into the tunnel
28 November 1991 3:20am : substantial daylight collapse up to ground surface
forming a 25m diameter crater
Ground and Groundwater Conditions Various weathered granite Groundwater table at typical 3-10m below the ground surface
Construction Methods and Support by drill and blast method
-
Possible Cause of Failure Weathered granite at the face
and high permeability soil
Consequence Three buildings collapsed
Several water mains, gas pipes and sewerage were broken
Emergency and Remedial Measures
Backfilling the crater with soil followed by cement grouting and chemical grouting
25.0
m
20.0
m
D=20.0m-1.2m
-4.8m-6.0m
-28.5m
-37.5m
-22.2m
-25.1m
-29.2m
Fill sand
Silt
Sand
Weathered
rock
Soft rock
Hard rock
: Cement mortar: Cement milk: Chemical grout
15.0m5.0m10.0m5.0m
backfilling
Lee & Cho (2008)
-
Lessons Learnt Insufficient ground investigation
Unexpected groundwater inflow
No tunnel face stability analysis
No consideration of blasting effects closed to weathered zone with shallow cover
-
Case No 13. Seoul Metro Line 5 Phase 2, Korea, 11 Feb. 1992 Asia Korea 11 February 1992
Project Title Second Phase of Seoul Subway
Source of Information Lee, I. M. & Cho, G. C. (2008). Underground construction in
decomposed residual soils (presentation slides). The 6th
International Symposium on Geotechnical Aspects of Underground
Construction in Soft Ground (IS-Shanghai 2008), Tongji University,
Shanghai, April.
Madrid (1996). Informe sobre el NATM del Health & Safety Executive, de Inglaterra, 1996. (1996).
Shin, J.H., Lee, I.K., Lee, Y.H. & Shin, H.S. (2006). Lessons from serial tunnel collapses during construction of the Seoul subway Line
5. Tunnel and Underground Space Technology, Issue no. 21, pp
296-297.
-
Keywords (for searching) Seoul, Korea, cave-in
Figures
Lee & Cho (2008)
-
Background Construction of Seoul Metro tunnel near Youido
Tunnel at 15-30m below ground
Nature and Type of Failure Construction failure
Significant inflow of groundwater
About 4.5 tonnes of soil flowed into tunnel
38m wide x 6m deep crater at the ground surface
Ground and Groundwater Conditions Various weathered granite
Groundwater table at -11.8m below the ground surface
Construction Methods and Support Excavated by road header
-
Possible Cause of Failure Weathered granite at the tunnel
face and high permeability soil
Consequence 4-lane road collapsed
Utilities damaged
Emergency and Remedial Measures
Backfilling the crater with soil followed by cement grouting and chemical grouting
Lee & Cho (2008)
-5.6m
-7.8m
-9.9m
-13.2m
-21.7m
-25.9m-26.4m
-11.8m
Fill
Alluvium(SC)
Alluvium(SP)
Alluvium(ML)
Hard Rock
Weathered rock
Soft rock
Sewer box
MBC
Sewer Box
38.0m
3. urethan grouting
2. cement mortal grouting
1. back filling
-23.5m
-33.0m
3m
Decomposed
rock
-
Lessons Learnt Insufficient ground investigation
Unexpected groundwater inflow
No tunnel face stability analysis
-
Case No 14. Seoul Metro Line 5 Phase 2, Korea, 1 Jan. 1993 Asia Korea 7 January 1993
Project Title Second Phase of Seoul Subway
Source of Information Lee, I. M. & Cho, G. C. (2008). Underground construction in
decomposed residual soils (presentation slides). The 6th International
Symposium on Geotechnical Aspects of Underground Construction in
Soft Ground (IS-Shanghai 2008), Tongji University, Shanghai, April.
Madrid (1996). Informe sobre el NATM del Health & Safety Executive, de Inglaterra, 1996. (1996).
Shin, J.H., Lee, I.K., Lee, Y.H. & Shin, H.S. (2006). Lessons from serial tunnel collapses during construction of the Seoul subway Line 5.
Tunnel and Underground Space Technology, Issue no. 21, pp 296-297.
-
Keywords (for searching) Seoul, Korea, cave-in
Figures
Lee & Cho (2008)
-
Background Construction of Seoul Metro tunnel near Yongdungpo
Tunnel at 15-30m below ground
Nature and Type of Failure Construction failure
Tunnel collapsed after removing spoil
Tunnel collapsed starting from the left side of the crown
900m3 of loose material flowed into the tunnel and water inflow of up to 300 litres/min recorded
Ground and Groundwater Conditions Various weathered granite
Construction Methods and Support By drill and blast method
-
Possible Cause of Failure Weathered granite at the tunnel
face
High groundwater pressure
Consequence 2-lane road collapsed
Utilities damaged
Emergency and Remedial Measures
Backfilling the crater with soil followed by cement grouting and chemical grouting
Fill
Alluvium(ML)
Alluvium(SP)
Weathered rock
Soft rock
-1.1m
-7.1m
-16.5m
-21.5m
-4.9m
-20.14m
-28.34m
Sewer box
900m3
2. cement mortar
3. cement mortar
4. chemical grouting
1. back filling
Lee & Cho (2008)
-
Lessons Learnt Insufficient ground investigation
Unexpected groundwater inflow
No tunnel face stability analysis
No consideration of blasting effects closed to weathered zone with shallow cover
-
Case No 15. Seoul Metro Line 5 Phase 2, Korea, 1 Feb. 1993 Asia Korea 1 February 1993
Project Title Second Phase of Seoul Subway
Source of Information Lee, I. M. & Cho, G. C. (2008). Underground construction in
decomposed residual soils (presentation slides). The 6th International
Symposium on Geotechnical Aspects of Underground Construction in
Soft Ground (IS-Shanghai 2008), Tongji University, Shanghai, April.
Madrid (1996). Informe sobre el NATM del Health & Safety Executive, de Inglaterra, 1996. (1996).
Shin, J.H., Lee, I.K., Lee, Y.H. & Shin, H.S. (2006). Lessons from serial tunnel collapses during construction of the Seoul subway Line 5.
Tunnel and Underground Space Technology, Issue no. 21, pp 296-
297.
-
Keywords (for searching) Seoul, Korea, Anyangcheon, cave-in
Figures
Lee & Cho (2008)
-
Background Construction of Seoul Metro tunnel near Anyangcheon
Tunnel at 15-30m below ground
Nature and Type of Failure Construction failure
Daylight collapse when weathered granite found at the tunnel face
Groundwater flowed into the tunnel
60m wide oval shaped area subsided
Ground and Groundwater Conditions Various weathered granite
Construction Methods and Support excavated by road header
-
Possible Cause of Failure Weathered granite and alluvium
at the tunnel face
High groundwater pressure
Consequence Six heavy plants buried
Emergency and Remedial Measures
Backfilling the crater with soil followed by cement grouting and chemical grouting
8.3m
24.0m
59.3m
cement milk
grouting
59.3m
jet grouting
5.0m-21.0m
-24.0m
-29.0m
Weathered rock
Soft rock
Anyang cheon
Alluvium2. cement milk
grouting
Sewer box
-24.0m
-32.0m
3. jet grouting
1. backfilling
Decomposed granite soil
Sewer Box
Lee & Cho (2008)
-
Lessons Learnt Insufficient ground investigation
Unexpected groundwater inflow
No tunnel face stability analysis
-
Case No 16. Munich Underground, Germany, 27 Sept. 1994 Europe Germany 27 September 1994
Project Title Munichs U-Bahn U2 Underground Extension
Source of Information Boos, R., Braun, M., Hangen, P., Hoch, C., Popp, R., Reiner, H.,
Schmid, G., & Wannick, H. (2004). Underground Transportation
Systems, Chances and Risks from the Re-insurers Point of View. Munich Re Group, Germany, pp 58-62.
(31 Jan. 2007).
Construction Today (1994a). Police probe repeat Munich tunnel breach. Construction Today, October Issue, pp 4-5.
Ground Engineering (1994). London NATM controversy. Ground Engineering, November Issue, p 6.
-
Keywords (for searching) Munich, Germany, sinkhole
Figures
Construction Today (1994a)
-
Background 7m diameter tunnel supported by sprayed concrete lining
The tunnel was assumed to be beneath a clay layer overlying water-bearing gravel and groundwater would not be drawn down
Nature and Type of Failure Construction failure
Quick inflow of water and ground materials
Large subsidence crater quickly filled with groundwater
20m wide, 18.5m deep crater
Ground and Groundwater Conditions Flinty marl overlain by some 15.5m of groundwater bearing gravel
Groundwater at about 4m below ground level
Construction Methods and Support New Austrian Tunnelling Method (NATM)
-
Possible Cause of Failure Layer of marl separating
groundwater bearing layers was
much thinner than originally
assumed
Sand-infilled cracks in the marl layer acted as preferential
pathways for water
Consequence Bus fell into the crater
Three passengers killed
30 people injured
Construction Today (1994a)
-
Emergency and Remedial Measures Bored-pile wall to form a shaft
Excavation inside the shaft for rescue
Tunnel driven again using compressed air
Lessons Learnt The danger of tunnel excavation through thin marl cover
-
2000 report
Case No 17. Heathrow Express Tunnel, UK, 21 Oct. 1994 Europe United Kingdom 21 October 1994
Project Title Heathrow Express Tunnel
Source of Information Ground Engineering (2000). Catalogue of disaster. Ground Engineering,
August Issue, pp 10-11.
HSE (1996). Safety of New Austrian Tunnelling Method (NATM) Tunnels. Health & Safety Executive, UK, 86p.
HSE (2000). The Collapse of NATM Tunnels at Heathrow Airport. Health & Safety Executive, UK, 116p.
ICE (1998b). HSE signs up QC Carlisle for HEX prosecution. New Civil Engineer, Institution of Civil Engineers, March Issue, pp 4-5.
ICE (1999). Heathrow Express court cases kicks off. New Civil Engineer, Institution of Civil Engineers, January Issue, p 6.
1996 report
-
Keywords (for searching) London, United Kingdom, NATM, sinkhole
Figures
Ground Engineering (2008) ICE (1998b)
-
Background NATM in London Clay
Nature and Type of Failure Construction failure
10m diameter crater formed
Ground and Groundwater Conditions
London Clay
Construction Methods and Support
New Austrian Tunnelling Method (NATM) ICE (1998b)
-
Possible Cause of Failure A series of design and management errors combined with
poor workmanship and quality control
Consequence Differential settlement induced at adjacent buildings
Rail services to Terminal 4 were halted for one month
Remedial measures caused chaos at Heathrow Airport
Recovery cost 150M (3 times original contract sum)
-
Central Terminal Area
Settlement Contours
-
Emergency and Remedial Measures Backfilling with 13,000m3 concrete
Lessons Learnt Measures to ensure safety must be planned
Do not lose sight of critical technical issues in the pursuit of time and cost reduction
Whilst a number of factors contributed to the collapse, half of them were matters of management
However much engineers are pressured to build quickly and cheaply, the industry will be judged by its own failures
-
Case No 18. Los Angeles Metro, USA, 22 June 1995 North America
United States of America
22 June 1995
Project Title The Los Angeles Metro
Source of Information Civil Engineer International (1995). Tunnel lining removal
prompts LA Metro cave in. Institution of Civil Engineers, July
Issue, p10.
-
Keywords (for searching) Los Angeles, USA, cave in
Figures
Civil Engineer International (1995)
-
Background Re-mining/remedial works to realign an existing TBM tunnel
(6.7m diameter, 25m deep), which had been bored off line
Nature and Type of Failure Construction failure
25m deep sinkhole caused by collapse of south bore
Serious cracking observed in temporary lining of north bore
Ground and Groundwater Conditions Hard siltstone overlain by alluvium with groundwater level 10-
12m below surface
Construction Methods and Support TBM with segmental lining
Rock bolts to stabilise segments before removal
-
Possible Cause of Failure Failure occurred during removal of segmental lining in tunnel roof
and relining of tunnel to correct the horizontal alignment
Unexpected ground conditions (alluvium found much deeper)
Fractured water mains (unconfirmed)
Consequence 30m length of a four lane road (Hollywood Boulevard) affected
leading to road closure
Collapsed 250mm water main possibly contributing to failure
Broken gas pipe
Evacuation of local residents
-
Emergency and Remedial Measures Steel rings installed in tunnel either side of the collapse
3,300m3 of grout to fill void and stabilise area
Road resurfacing
Lessons Learnt Unpubished
-
Case No 19. Motorway Tunnels, Austria, 1993-1995 Europe
Austria
1993 - 1995
Project Title Motorway Contract
Source of Information Clay, R.B. & Takacs, A.P. (1997). Anticipating the unexpected
Flood, fire overbreak, inrush, collapse. Proceedings of the
International Conference on Tunnelling Under Difficult Ground
and Rock Mass Conditions, Basel, Switzerland, pp 223-242.
-
Keywords (for searching) Motorway, Austria, inrush, water inflow
Figures Extent of overbreak
1. Rock bolts
2. Second layer WM & shotcrete
3. Support core
4. Rock debris
5. Shotcrete in the overbreak
6. Water & rock flow
7. Overbreak
Clay & Takacs (1997)
-
Background Four three-lane, twin-tube tunnels (T1-T4) with internal cross-
section of 103 m2 and 30 m apart between centrelines
constructed by the drill & blast method
T1 - 376m long; T2 - 562m; T3 2,760m and T4 1,230m
Nature and Type of Failure Construction failure
Failures at T4 in 1993
- About 131 recorded overbreak incidents with total volume of
1,461m3, maximum deformation of 120mm measured in the
tunnel
- 200m3 of loose material collapsed after a blast, resulting in
water inflow of up to 450 litres/min
-
Nature and Type of Failure (cont) Two failures at T3 in 1995
- The first collapse came with 650m3 of loose material flowed into
the tunnel, water inflow of up to 1,500 litres/min recorded
- The second collapse of the same size occurred days after the 6
months of recovery of the loss of the 10 m of tunnel. Radial
movement of rib of about 300mm recorded
Ground and Groundwater Conditions Sandstone and shale with zones of crushed and weathered
material
Construction Methods and Support Drill and blast, heading and benching
Shotcrete, rock bolts, forepoling, steel ribs and invert beams
-
Possible Cause of Failure Failures at T4 in 1993 Failure to apply the support in time
Two failures at T3 in 1995 The tunnel pierced through the water-bearing impermeable thinly bedded shale stratum, which
is located at and above the failure location
Consequence the tunnel face caved in
construction delay
Emergency and Remedial Measures Failures at T4 in 1993 For the subsequent excavation,
umbrella of forepoling with 6m long, 50mm perforated grouted
pipes was adopted. An ample central core was kept and the
excavation was carried out in small sections
Two failures at T3 in 1995 work progressed with extreme caution
-
Lessons Learnt Initial support should be installed in time
-
Case No 20. Docklands Light Rail, UK, 23 Feb. 1998 Europe
United Kingdom
23 February 1998
Project Title Docklands Light Railway Lewisham Extension
Source of Information ICE (1998a). Bulkhead location blamed for DLR blast. New
Civil Engineer, Institution of Civil Engineers, February Issue, pp
3-4.
ICE (2004) Docklands tunnel blowout down to elementary error, says judge. New Civil Engineer, Institution of Civil Engineers, January Issue, pp 8-9.
-
Keywords (for searching) Docklands, UK, sinkhole
Figures
ICE (2004)ICE (1998a)
-
Background Tunnel constructed for Docklands Light Rail (diameter 5.2m)
by slurry TBM
Nature and Type of Failure Construction failure
22m wide and 7m deep crater formed in the grounds of George Green School
ICE (1998a)
-
Ground and Groundwater Conditions Thames Sands and Gravels
Construction Methods and Support slurry TBM
Possible Cause of Failure Insufficient overburden above the tunnel
High compressed air pressure within tunnel causing blow out failure
Consequence Windows up to 100m away broken by the shower of mud and
stones released
-
Emergency and Remedial Measures Unpublished
Lessons Learnt To require specific assessments/calculations to demonstrate the
adequacy of factor of safety against blow out failure
-
Case No 21. Athens Metro, Greece, 1991-1998 Europe
Greece
1991 - 1998
Project Title The Athens Metro
Source of Information IMIA. .
IMS. .
-
Source of Information (cont) Kavvadas, M., Hewison, L.R., Laskaratos, P.G., Seferoglou,
C. & Michalis, I. (1996). Experiences from the construction
of the Athens Metro. Proceedings of International
Symposium on the Geotechnical Aspects of Underground
Construction in Soft Ground, City University, London, April.
Mihalis, I. & Kavvadas, M. (1999). Ground movements caused by TBM tunnelling in the Athens Metro Project.
Proceedings of International Symposium on the
Geotechnical Aspects of Underground Construction in Soft
Ground, Japan, July, pp 229-234.
-
Keywords (for searching) Athens, Greece, cave-in
Figures
IMS
IMIA
-
Background Construction of the Olympic Metro under a turnkey contract
(estimated cost about 2 billion ECUs)
Construction started in November 1991 and operation in 1998
TBM used for construction of 11.7km long, 9.5m diameter tunnels located at a depth of 15-20m (with penetration rate
ranging from 1.6m to 18m per day based on 18-hour-per-day
shift, depending on the ground conditions)
Cut and cover, supported by soldier piles, struts and prestressed anchor tiebacks for 6.3km long tunnels and
stations
NATM for other short auxiliary tunnels and oval-shaped stations where existence of buried antiquities precluded open
excavation
-
Nature and Type of Failure Construction failure
Roof collapses of appreciable size often occurred
Large and occasionally uncontrollable overbreaks for TBM
Ground and Groundwater Conditions Athenian schist a thick sequence of flysch-type sediments,
comprising thinly bedded clayey and calcareous sandstones,
alternating with siltstones, phyllites, meta-sedimentary shales and
occasionally, with limestones and marls
Construction Methods and Support TBM, cut-and-cover and NATM
-
Possible Cause of Failure Ravelling of the ground seems to be due to insufficient strength
in the intensely weathered and highly tectonised zones of Athenian schist (which is a flysch-type sediment consisting of thinly bedded clayey and calcareous sandstones with alterations and subjected to intense folding, thrusting, faulting and fracturing)
Large muck openings of the TBM cutterhead which cannot adequately control muck-flow (the cutterhead operates in the open air, i.e. under atmospheric pressure)
Consequence Major delay in TBM tunnelling
Emergency and Remedial Measures Cavities caused by the TBM overbreaks was backfilled by grout
(which sometimes reached the ground surface)
Lessons Learnt Unpublished
-
Case No 22. L rdal Road Tunnel on European Highway E16, Norway, 15 June 1999
Europe
Norway
15 June 1999
Project Title The L rdal Road Tunnel on European Highway E 16
Source of Information Karlsrud Kjell (2010). Technical Note : Experience with tunnel
failures in Norwegian tunnels. The Government of the Hong
Kong Civil Engineering and Development Department.
(Unpublished).
-
Keywords (for searching) L rdal, Norway, cave in
Figures The L rdal Tunnel
Ch.11080
CAVE IN
DEBRIS
1200-1500m3
Karlsrud (2010)
-
Background Road tunnel at about 1,100m depth, 24.5 km long and 9m wide
Nature and Type of Failure Construction failure
A cave-in involving 17m length of tunnel and extending up to about 11-12m above the crown. The volume of the failed rock mass was
estimated to be 1,200-1,500m3
Ground and Groundwater Conditions Precambrian gneisses with layers of amphibolities and massive
granitic rock. Excavation through a major fault zone (rock mixed
with lot of swelling clay)
Construction Methods and Support Constructed by drill-and-blast method and supported by steel fibre
reinforced sprayed concrete and rock bolts
-
Possible Cause of Failure Poor communication : the driller did not inform the engineer about
abnormal drilling rate encountered
Expansion of the swelling clay under high stress to water during drilling of the rock bolts
The combination of the swelling of the clay and high stress produced a squeezing effect, which resulted in gradual weakening of the rock mass in the tunnel
Consequence The crew was evacuated in time and no one was hurt
About 10 days delay in the excavation works and cost increased for the remedial works
-
Emergency and Remedial Measures
Reinforced ribs of sprayed concrete in addition to layers of sprayed concrete and rock bolts were installed just behind the cave-in zone
Rock material was hauled into the tunnel building up a barrier up to 2m below the crown and concrete was pumped through a steel pipe to fill the void above the debris
Debris was gradually hauled out with step wise installation of rock anchors and sprayed fibre reinforced concrete
The L rdal Tunnel
Fa
ce
be
fore
ca
ve
in
11
07
0
11
08
0
11
08
7
Debris
1200-1500 m3
Cave in
zone
Concrete
700 m3 concrete
Debris hauled out
Ch
.no
Karlsrud (2010)
-
Lessons Learnt The importance of good communication between the driller
and the engineer
Importance of having good understanding of the geological conditions and their influence on the stability
Swelling of clay in condition of high stress could provide a squeezing effect and result in weaking of the rock mass in a tunnel
-
Case No 23. Sewage Tunnel, Hull, UK, 1999 Europe
United Kingdom
1999
Project Title Hull Sewage Tunnel
Source of Information Boos, R., Braun, M., Hangen, P., Hoch, C., Popp, R., Reiner,
H., Schmid, G., & Wannick, H. (2004). Underground
Transportation Systems, Chances and Risks from the Re-
insurers Point of View. Munich Re Group, Germany, pp 58-62. (31 Jan. 2007).
-
Keywords (for searching) Hull, UK, Sewage
Figures
Boos et al (2004)
-
Background Construction of a 10.5km long underground sewer
Nature and Type of Failure Construction failure
Water and sand ingress
Tunnel subsided by 1.2m causing serious subsidence at surface
Ground and Groundwater Conditions Water-bearing ground
Construction Methods and Support EPB TBM (diameter 3.85m) supported by reinforced concrete
segmental lining
-
Possible Cause of Failure Fluctuation of groundwater level caused by tidal effects resulting
in vertical movement of the tunnel tube causing opening of joints
Consequence Damage to buildings, roads and utility lines
TBM had to be abandoned
Emergency and Remedial Measures Ground freezing
Reconstruction of tunnel using sprayed concrete
Lessons Learnt The design of the segment connections should take account of
the fluctuations of groundwater level
-
Case No 24. Taegu Metro, South Korea, 1 Jan. 2000 Asia
South Korea
1 January 2000
Project Title The Taegu Metro
Source of Information Boos, R., Braun, M., Hangen, P., Hoch, C., Popp, R., Reiner,
H., Schmid, G., & Wannick, H. (2004). Underground
Transportation Systems, Chances and Risks from the Re-
insurers Point of View. Munich Re Group, Germany, pp 58-62. (31 Jan. 2007).
-
Keywords (for searching) Taegu, South Korea, diaphragm wall, cave in
Figures
Boos et al (2004)
-
Background Construction of underground Taegu Metro
Nature and Type of Failure Construction failure
Failure of diaphragm wall
Excavation pit caved in
Ground and Groundwater Conditions Water-bearing ground
Construction Methods and Support Cut and-cover
Possible Cause of Failure Rapid fluctuation of groundwater level caused movement of
unidentified gravel and sand strata
Additional loading on diaphragm wall was not considered in design
-
Consequence Bus buried and bus driver seriously injured
Three passengers killed
Neighbouring buildings suffered considerable damage
Emergency and Remedial Measures Excavation pit backfilled
Subsoil grouted and diaphragm wall strengthened
Lessons Learnt Unpublished
-
Case No 25. Wastewater Tunnel, Portsmouth, UK, May 2000 Europe
UK
May 2000
Project Title Portsmouth Sewage Transfer
Source of Information Tunnels & Tunnelling (2000). Portsmouth scheme held up.
Tunnels & Tunnelling International, July 2000. p 9.
-
Keywords (for searching) Sewage tunnel, Lining crack, Portsmouth
Figures N/A
-
Background Wastewater tunnel 4km long and 3.3m diameter constructed
with precast concrete tunnel segments by the TBM method
Nature and Type of Failure Construction failure
Cracks were found in the tunnel segments together with associated water ingress
Ground and Groundwater Conditions Mixed ground comprising Chalk, Calcareous sands, gravels
and stiff clay
Water head of 21m above the tunnel crown
Construction Methods and Support EPB TBM
-
Possible Cause of Failure Localised poor ground conditions not account for in the design
of the tunnel segments
Consequence Tunnel drive was halted and delayed
Emergency and Remedial Measures Temporary application of compressed air, followed by ground
freezing
Replacement of damaged rings and back grouting
Lessons learnt Understanding the ground conditions and account for them in
design
-
Case No 26. Dulles Airport, Washington, USA, Nov. 2000 North America
Washington, United States of America
November 2000
Project Title Expansion at Washington DCs Dulles airport
Source of Information Tunnels & Tunnelling (2000). US airport collapse claims miners
life. Tunnels & Tunnelling International, December 2000 issue, p 8.
Stehlik, E & Srb, M. NATM Tunnelling at Dulles Airport. Proceedings of the World Tunnel Congress 2007 and 33rd ITA/AITES Annual General Assembly, Prague, May 2007, pp 1609-1612.
-
Keywords (for searching) Dulles, Washington, NATM
Figures Project Layout
Tunnels & Tunnelling (2000)
-
Background Pedestrian tunnel of approximate cross-sectional area 100m2 with
shallow ground cover of 4.5m
Excavated in 4 stages using two side drifts followed by bench and invert, using road-header
NATM design with systematic spiling, steel-fibre reinforced shotcrete and lattice girder support
Nature and Type of Failure Construction failure
One of the tunnel headings caved in without the collapse extending to the surface
Ground and Groundwater Conditions Mixed face comprising clay, silt and competent siltstone
-
Construction Methods and Support NATM, following a sequence of a top heading comprising two
side-wall drifts, followed by bench and invert. 1m-1.6m advances in each round of excavation
Steel-fibre reinforced shotcrete and lattice girders at 1m-1.6m c/c
Possible Cause of Failure Unknown
Consequence A miner was killed
Emergency and Remedial Measures An area of 40x40x10m deep was excavated from the surface to
recover the body of the trapped worker
Lessons learnt Necessity for safe application of NATM in shallow tunnelling works
Introduction of a requirement for NATM Engineer in the second contract of the project
-
Case No 27. Istanbul Metro, Turkey, Sept. 2001 Europe
Turkey
September 2001
Project Title Istanbul Metro Construction
Source of Information World Tunnelling (2001). Istanbul Metro collapse investigations,
World Tunnelling, December 2001 issue, pp. 490-492.
-
Keywords (for searching) Istanbul, Metro, boarding house
Figures Collapsed building above tunnel Longitudinal section
World Tunnelling (2001)
-
Background Metro tunnel 7.9km long with 14m wide sections of 100m2
constructed by a multiple drift technique coupled with pipe umbrella roofing and benching at central drift
Nature and Type of Failure Construction Failure
Soft clay kept falling through the gaps between the pipe umbrella and liquid mud flowed from the face.
Tunnel collapsed and a 25m wide crater was created
Three 2-storey buildings and a workshop building caved in
Ground and Groundwater Conditions Soft ground with groundwater close to ground level
Construction Methods and Support Multiple drift mined Tunnel
Pipe umbrella, shotcrete lining and lattice girders as temporary support
-
Possible Cause of Failure Existing well 1.5-2.0m above the tunnel crown not properly
filled causing the saturated clay and well water flowing into the tunnel and subsequent collapse of the well walls and surrounding clay followed by the draining of the upper fine-grained sand layer into the tunnel and the undermining of the building structures
Consequence 5 people died
Emergency and Remedial Measures Unpublished
Lessons learnt The importance of the study of the construction history of
buildings that are under-tunnelled
-
Case No 28. Channel Tunnel Rail Link, UK, Feb. 2003 Europe
United Kingdom
February 2003
Project Title Channel Tunnel Rail Link
Source of Information ICE (2003). Ground failure linked to well collapses. New
Civil Engineer, Institution of Civil Engineers, February Issue,
pp 6-7.
-
Keywords (for searching) UK, Channel, Rail, sinkhole
Figures
ICE (2003)
-
Background Boring at a depth of 21m
Nature and Type of Failure Construction failure
10m diameter and 20m deep void formed in the ground behind a row
of houses
Ground and Groundwater Conditions
Thanet Sands
Construction Methods and Support
Tunnelling using TBM (diameter 8.2m)
ICE (2003)
-
Possible Cause of Failure The vibration from the TBM may have caused the nearby wells
(30m deep and 1.8m diameter) to collapse
Consequence Three uncharted wells collapsed
Emergency and Remedial Measures The voids were backfilled with grout
Lessons Learnt Unpublished
-
Case No 29. Mtor Metro Tunnel, France, 14 Feb. 2003 Europe
France
14 February 2003
Project Title The Mtor Metro Tunnel
Source of Information Dubois, P. & Rat, M. (2003). Effondrement sur le chantier
"Mtor. Conseil Gnral des Ponts et Chausses, France, 22p. (31 Jan. 2007).
-
Keywords (for searching) Mtor, Pairs, France, sinkhole
Figures
Dubois & Rat (2003)
-
Figures Location map and section
Dubois & Rat (2003)
-
Figures Hall plan
Dubois & Rat (2003)
-
Background Construction of the extension of Mtor Metro Tunnel including
the Olympics station and a maintenance hall
Nature and Type of Failure Construction failure
About 3,000m3 of sedimentary deposits collapsed underneath a school, occupying an area of 400m2 on plan
Ground and Groundwater Conditions
Coarse limestone and plastic clay (clays of Sparnacian)
Construction Methods and Support
Supported by bolts and shotcrete
Dubois & Rat (2003)
-
Possible Cause of Failure The coarse limestone had inferior mechanical characteristics to
the homogeneous medium assumed in the design
Unfavorable orientation of the fracture
Implementation of inadequate support due to the overreliance on calculations
Consequence No casualties
The school had to be closed for a year affecting 900 students
Emergency and Remedial Measures Filling the hall under the building by concrete
Lessons Learnt Unpublished
-
Case No 30. Oslofjord Subsea Tunnel, Norway, 28 Dec. 2003 Europe
Norway
28 December 2003
Project Title The Oslofjord Subsea Tunnel
Source of Information Karlsrud Kjell (2010). Technical Note : Experience with tunnel
failures in Norwegian tunnels. The Government of the Hong Kong
Civil Engineering and Development Department. (Unpublished).
-
Keywords (for searching) Oslofjord, Norway, subsea tunnel, rock fall
Figures
First failure Third failure
Karlsrud (2010)
-
Background The road tunnel was 7.3 km long and 11.5 m wide (3 lanes)
Three major failures and many minor failures occurred
Nature and Type of Failure In service failure
First failure occurred on 28 December 2003: about 20m3 of crushed and weathered rock involving with clay, which came
down from the crown went through the frost insulated water
shielding vault and down to the carriageway
Second failure involved about 3m3 of heavily weathered rock, which came down from the springline and fell down to the invert
Third failure involved 2-3m3 of completely weathered rock, which fell down from the crown and rested on top of the water
shielding vault
-
Ground and Groundwater Conditions Precambrian gneisses with lenses of amphibolites, veins of
pegmatite, and a few dykes of diabase and rhomb porphyry
Swelling clay was found at the weakness zones
Construction Methods and Support Mainly supported by steel fibre reinforceed shotcrete combined
with rock bolts
Possible Cause of Failure The humidity behind the vault constructed for frost insulated
water shielding was high and the high content of swelling clay in the weathered rock started sucking water and expanded gradually over a long period of time
-
Consequence Closure of the tunnel for more than 3 months for extensive repairs
and upgrading of the tunnel support
Emergency and Remedial Measures Complete removal of the vault before installing additional rock
support including fiber reinforced shotcrete, rock bolts and reinforced ribs of sprayed concrete
Lessons Learnt The importance of proper geological mapping and rock mass
classification
The need to identify swelling minerals and the potential of deterioration of strength in weathered rock
The importance of adequate support design for long-term stability in weathered rock
-
Case No 31. Shanghai Metro, China, 2003 Asia
China
2003
Project Title Shanghai Metro Project
Source of Information Boos, R., Braun, M., Hangen, P., Hoch, C., Popp, R., Reiner,
H., Schmid, G., & Wannick, H. (2004). Underground
Transportation Systems, Chances and Risks from the Re-
insurers Point of View. Munich Re Group, Germany, pp 58-62. (31 Jan. 2007).
-
Keywords (for searching) Shanghai, China, water ingress, ground subsidence
Figures
Boos et al (2004)
-
Background Expansion of the Shanghai Metro () Line 4 crossing
beneath the Huangpu River ()
Two parallel tunnel tubes constructed by earth pressure balance TBM
Nature and Type of Failure Construction failure
Failure occurred during construction of a cross passage
Massive ingress of water and material at the face at a depth of 35m
Several metres ground subsidence
Ground and Groundwater Conditions Water-bearing ground
Construction Methods and Support EPB TBM
-
Possible Cause of Failure Failure of ground freezing unit
Consequence High rise office buildings seriously damaged
Flood protection dyke on the river badly damaged
Emergency and Remedial Measures Unpublished
Lessons Learnt Unpublished
-
Case No 32. Nikkure-yama Tunnel, Japan, 2003
Asia
Japan
2003
Project Title
Nikkure-yama Tunnel of the Joshinnetsu Expressway
Source of Information Takahashi, Hiroshi (2010). Huge collapse leading to ground
surface caving in 130m earth thickness.
-
Keywords (for searching) Japan, mudstone, sinkhole
Figures
Takahashi (2010)
-
Background East work section of Nikkure-yama Tunnel
Nature and Type of Failure Construction failure
Ground collapse of an avalanche type containing cobbles, gravels and water took place at the point 900m away from the tunnel portal
A large crater was observed at the ground surface about 130m above the tunnel
Ground and Groundwater Conditions
Mudstone
Construction Methods and Support
Shortcrete and ribs
Takahashi (2010)
-
Possible Cause of Failure Existence of high groundwater
pressure
Decrease in cover of the mud-stone layer
Water path created by the investigation drillhole
Consequence Programme delayed for about 2
years
Emergency and Remedial Measures
Filling the cave-in area by foam concrete
Grouting under the collapse area
Boring for drainage from the tunnel
Takahashi (2010)
-
Lessons Learnt The importance of adequate ground investigation before
tunnelling
The importance of investigations and observations during construction for adopting appropriate support measures
-
Case No 33. Guangzhou Metro Line 3, China, 1 April 2004 Asia China 1 April 2004
Project Title The Guangzhou Metro Line 3
Source of Information China Daily (2004). 100 homeless after metro site collapse.
(2 April
2004).
Soufun (2004). : 3 . (4 April 2004).
Longhoo (2004). 3 .
(2 April 2004).
-
Keywords (for searching) Guangzhou, China, diaphragm wall, building collapse
Figures
ChinaDaily (2004)
-
Background Construction of a 58.5km long underground metro in which
45.6km is a single-tube shield TBM
Nature and Type of Failure Construction failure
Failure of a diaphragm wall
Ground and Groundwater Conditions Unpublished
Construction Methods and Support Single-tube shield TBM
-
Possible Cause of Failure Rapid fluctuation of groundwater level due to the heavy rainfall
Complicated geology including a layer of swelling soil
Consequence A three-storey building collapsed and sunk into the ground
Collapse of nearby underground water mains
Emergency and Remedial Measures Backfilled with crushed rock and cement
Lessons Learnt Unpublished
-
Case No 34. Singapore MRT, 20 April 2004 Asia
Singapore
20 April 2004
Project Title Circle Line of the Singapore MTR
Source of Information Government of Singapore (2005). Report of the Committee of
Inquiry into the Incident at the MRT Circle Line Worksite That
Led to the Collapse of Nicoll Highway on 20 April 2004.
Government of Singapore, Land Transport Authority. (31 Jan. 2007).
-
Keywords (for searching) Singapore, MRT, Cut-and-Cover, diaphragm wall
Figures
Government of Singapore (2005)
-
Background An open cut tunnel excavated for Singapore MRTs new Circle
Line
Design and build
Excavated trench of 15m wide and 33m deep supported by 0.8-1.0m thick diaphragm wall which is 35-45m deep without rock
socket
Steel struts: 4-5m horizontal and 3m vertical spacing
Bottom-up construction
Jet grouted base slabs
Layer 1-1.5m thick at 28.5m below ground
Layer 2-3m thick at 33.5m below ground (Layer 2 not yet constructed when collapse occurred)
-
Nature and Type of Failure Construction failure
9th level of struts being installed when collapse took place
Unusual cracking and groaning noises heard early in the morning (6 hours)
Loud cracking noise heard in the afternoon, 15 minutes before collapse
Collapse plan area was 100m by 130m
Settlement up to 15m
Diaphragm walls displaced
Steel struts mangled
Ground and Groundwater Conditions Mainly marine clay with some fluvial clay
Government of Singapore (2005)
-
Construction Methods and Support Cut-and-Cover method
Possible Cause of Failure Under-design of the strut-waler connection in the strutting
system
Incorrect use of Finite Element Method
No proper design reviews
Disregard of different warnings, for example, excessive wall deflections and surging inclinometer readings
Poor construction quality
Ineffective instrumentation and monitoring system
Failure to implement risk management
-
Consequence Part of Nicoll Highway, Singapores major east-west harbour-front
road, destroyed
Four workers killed
Several others injured
15,000 people and 700 businesses affected
Three offices and retail towers at risk from further ground movement
Damage of a gas service line, resulting in an explosion and fire
A storm drain damaged
-
Emergency and Remedial Measures Rescue and backfilling
Structurally disconnected the Merdeka Bridge
All contracts of the Circle Line put on hold
All contracts to carry out checks and review of design and construction of temporary works
All Professional Engineers to confirm in writing the adequacy of their designs
All designs to be independently checked by the Building & Construction Authority
-
Lessons Learnt This is a need for robust design, risk management, design review
and independent checking, purposeful back analysis, an effective
instrumentation, monitoring and interpretation regime, an effective
system of management of uncertainties and quality during
construction, corporate competencies and safety management
The safety of temporary works is as important as that of permanent works and should be designed according to
established codes and checked by competent persons
-
Case No 35. Kaohsiung Rapid Transit, Taiwan, 29 May 2004
Asia
Taiwan
29 May 2004
Project Title Kaohsiung Rapid Transit
Source of Information Lee, W. F. & Ishihara, K. (2011) Forensic diagnosis of a
shield tunnel failure. Engineering Structures. Volume 32,
Issue 7, July 2010, Pages 1830-1837.
-
Keywords (for searching) Kaohsiung, Taiwan, diaphragm wall, building damaged,
sinkhole
Figures
Lee & Ishihara (2010)
-
Background Chemical Churning Piles (CCP) of
350mm diameter installed as guide walls
for the diaphragm wall construction
Soil improvement works by the use of Super Jet Grouting (SJG) method at the
reception area for break-out operations
The diaphragm wall panels were first cored through by chain saw according to
the face-shape of the shield tunnel
machine and manual power tool was
used to disassemble the reinforced
concrete residual inside the coring holes
EPB Tunnel Boring Machine 500mm away from the wall face awaiting for
break-out and invert leakage started
Lee & Ishihara (2010)
-
Nature and Type of Failure Construction failure
Sinkhole of about 10m in diameter formed at the ground surface
Ground settlement influence zone ranging from 40m to 50m in diameter with maximum settlement from 500mm to 1,500mm.
Several rings of tunnel s
Chemical Churning Pile
(CCP)
Soil Improvement Zone
Diaphragm Wall
egmental linings were damaged
CCP
Possible
Collapse Zone
Soil Improvement Zone
Leakage spot
Tunnel Boring Machine
Path of Leakage
Lee Lee & & IshiharIshihara a (2(2010)010)
Settled Area of Ground Surface
-
Ground and Groundwater Conditions Silty sand and sandy silt soil layers
Silt deposit sandwiched by impermeable clay layers
Construction Methods and Support Tunnelling by EPB Tunnel Boring Machine
Possible Cause of Failure Progressive development of unexpected cracks inside the soil
improvement zone resulting in groundwater leakages in the
reception area as a result of piping and/or hydraulic fracturing
Leakage paths at the interfaces between Chemical Churning Pile (CCP) and the diaphragm wall, CCP and Super Jet Grout (JSG)
materials, or inside the lower portion of the JSG body
Chloride assault and deterioration of CCP, which were installed two years before the wall breaking process, had significant effects on the
integrity and water tightness at the interfaces
-
Possible Cause of Failure (cont) The highly sensitive and erodible soil dispersed around the SJG
might have been disturbed due to the application of highly
pressured water jet in the grouting process
Mechanical and/or vibration disturbances occurred during the wall
breaking process leading to serious cracks and fissure
development inside the deteriorated CCP and defective SJG
blocks
Unfavourable sub-surface conditions which consisted of silty
sands and sandy silts with water contents almost reaching their
liquid limits
Consequence Adjacent buildings were damaged
Lee & Ishihara (2010)
-
Emergency and Remedial Measures Stabilizing the ground by piling-up sand bags in front of the tunnel
face to reduce leakage, backfilling the sinkhole and grouting the
tunnel crown and invert
Advancing the TBM further to reduce the gap between the D-wall
and the tunnel
Installation of steel frames to reinforce the damaged ring segments
Lee & Ishihara (2010) Lessons Learnt Unpublished
-
Case No 36. Oslo Metro Tunnel, Norway, 17 June 2004 Europe
Norway
17 June 2004
Project Title The Oslo Metro Tunnel
Source of Information Karlsrud Kjell (2010). Technical Note : Experience with tunnel
failures in Norwegian tunnels. The Government of the Hong
Kong Civil Engineering and Development Department.
(Unpublished).
-
Keywords (for searching) Oslo, Norway, cave in
Figures
F:\i\21\miljo\div\2000\ah-1.ppt
T-baneringen Modell 3
Strste hovedspenning, 1 er styrt av lagdelingssprekkene og tverrsprekken. Strekkspenninger over taket til
Hasletunnelen og videre til indre lp mot Sinsen.
Karlsrud (2010)
F:\i\21\miljo\div\2000\ah-1.ppt
Planned
concrete wall
Cave in area
F:\ i\21\miljo\div\2000\ah-1.ppt
-
Background Metro line tunnel 1.3km long and 7m wide connecting with an old
tunnel
Nature and Type of Failure Construction failure
At the junction where the two tunnels met in an acute angle, tunnel cave-in after removal of most part of the rock pillar between the
tunnels
Ground and Groundwater Conditions Interlayered shale and nodular limestone with 1-5cm thick clay
seams along many of the bedding planes
The bedding planes were dipping 20-45 and running almost parallel to the tunnel
-
Construction Methods and Support Constructed by drill-and-blast method supported by rock bolts
and fibre reinforced sprayed concrete. A concrete wall/pillar was
planned to be constructed between the old tunnel and new
tunnel
Possible Cause of Failure Unfavourable direction of the bedding planes in relation to the
geometry and span of the tunnels
Over excavation of the rock pillar and the removal of the remaining rock pillar and old concrete wall before the planned concrete pillar was constructed
Consequence Programme delayed for about 3 months
Cost implication: extra cost of the remedial works
-
Emergency and Remedial Measures Filling up the whole opening by concrete above the fallen debris
Installation of 10m long cable anchors together with permanent support of 200mm thick lining of reinforced sprayed concrete, reinforced ribs of sprayed concrete and additional 6m long rock bolts
Lessons Learnt The importance of adequate ground investigation
The need to follow the sequence of rock support installation in accordance with the design plans during construction
-
Case No 37. Kaohsiung Rapid Transit, Taiwan, 10 Aug. 2004
Asia
Taiwan
10 August 2004
Project Title Kaohsiung Rapid Transit
Source of Information Taiwan Info (2004). Nouvel incident sur le chantier du mtro
de Kaohsiung. Taiwan. (31 Jan. 2007).
-
Keywords (for searching) Kaohsiung, Taiwan
Figures
Taiwan Info (2004)
-
Background Construction of the Kaohsiung Rapid Transit Blue & Orange
Lines in Kaohsiung City
Nature and Type of Failure Construction failure
First collapse on 29 May 2004 underneath a street
Second collapse in mid June 2004
Third collapse on 13 July 2004 with formation of a large sinkhole
Fourth collapse on 10 Aug 2004
Ground and Groundwater Conditions Unpublished
Construction Methods and Support Unpublished
-
Possible Cause of Failure Possible adverse ground and groundwater conditions
Consequence First collapse - Several buildings affected and 100 people
evacuated
Third collapse - Three residential buildings evacuated and significant disruption to water/electricity supply
Fourth collapse - No casualty, one building affected and part of the works suspended
Emergency and Remedial Measures Unpublished
Lessons Learnt Unpublished
-
Case No 38. Hsuehshan Tunnel, Taiwan, 1991-2004
Asia
Taiwan
1991 - 2004
Project Title
The Taipei-Ilan Expressway
Source of Information TANEEB ( 2 0 0 5 ) . Hsuehshan Tunnel. Taiwan Area
National Expressway Engineering Bureau ( ) , Taiwan. (31 Jan. 2007).
-
Keywords (for searching) Hsuehshan, Taiwan, groundwater inflow, tunnel collapse
Figures
Taiwan Info (2004)
TANEEB (2005)
-
Background Construction of 12.9km long and 11.7m diameter Hsuehshan
Tunnel in Taiwan ()
Works commenced in 1991 and completed in 2004
Comprised 2 main tunnels (East & Westbound) and a pilot tunnel
Westbound Eastbound
Pilot Tunnel
TANEEB (2005)
-
Nature and Type of Failure Construction failure
Eastbound - 28 collapses occurred
Westbound - TBM badly damaged due to tunnel collapse and groundwater inflow of 45,000 litres/min into the tunnel
Pilot Tunnel - 8 collapses occurred
Ground and Groundwater Conditions The major geologic elements are Eocene, Oligocene and minor
Miocene folded sedimentary rock formations
Highly fractured rock with six major faults
Construction Methods and Support Eastbound by TBM method (July 1993 to Sept. 2004)
Westbound by TBM method (July 1993 to April 2004)
Pilot tunnel by drill & blast method (July 1991 to Oct. 2003)
-
Possible Cause of Failure Unexpected difficult geology with fractured rock and massive
inflows of water
6 major faults found along the tunnel alignment
Consequence Eastbound - Failure in May 1993 affected 56 buildings and 73
families
Westbound - 11 men died
Pilot Tunnel - 13 stoppages
Emergency and Remedial Measures Unpublished
Lessons Learnt Unpublished
-
Case No 39. Barcelona Metro, Spain, 27 Jan. 2005 Europe
Spain
27 January 2005
Project Title Barcelona Line 5 Metro Extension
Source of Information European Foundations (2005). Tighter NATM rules follow
Barcelona failure. European Foundations, Spring Issue, No.
26, p 3.
-
Keywords (for searching) Barcelona, Spain, sinkhole
Figures
European Foundations (2005)
-
Background Tunnel for Barcelona Line Five Metro Extension
Nature and Type of Failure Construction failure
Part of the lining collapsed
30m wide and 32m deep crater formed
Ground and Groundwater Conditions Weathered slate and ancient and weathered metamorphic
ground with a vertical and hidden fault at the location of
collapse
Construction Methods and Support Tunnelling using NATM
-
Possible Cause of Failure A hidden vertical fault located 1m behind the sprayed
concrete lining
Consequence 2 five-storey buildings and a smaller one demolished
More than 50 families made homeless
Emergency and Remedial Measures The void was backfilled with grout of about 2,000m3
The tunnel section was backfilled with 18,000m3 of grout through a horizontal borehole in the debris and five points from the surface
Additional boreholes, horizontal probes and supports for future excavation
Lessons Learnt Unpublished
-
Case No 40. Lausanne M2 Metro, Switzerland, 22 Feb. 2005 Europe
Switzerland
22 February 2005
Project Title Lausanne Metro M2 project
Source of Information Tunnels & Tunnelling (2005). Lausanne Metro Tunnel collapse.
Tunnels & Tunnelling International, April Issue, p 6.
-
Keywords (for searching) Lausanne, Switzerland, sinkhole
Figures
Tunnels & Tunnelling (2005)
-
Background Tunnel (6km long, approximately 10m wide x 7m high) for
Lausanne Metro M2 Project (cost US$472M) in Switzerland
Nature and Type of Failure Construction failure
50m3 of material displaced into the tunnel at a depth of 12m, leading to a crater at the surface
Ground and Groundwater Conditions Collapse in area of soft ground (lake deposits)
Construction Methods and Support Tunnelling using an Eickhoff ET 380-L roadheader
-
Possible Cause of Failure Tunnel driven through a pocket in the glacial moraine, causing
sudden inflow of groundwater
Consequence People in two buildings, a supermarket and a food outlet in
commercial district evacuated when their cellars collapsed
No injuries reported
Emergency and Remedial Measures A curtain of 11 piles constructed ahead of the collapsed face with
grouting to strengthen the ground and limit further flow of material into the tunnel
The void was backfilled with 800m3 of glass-sand (recycled glass)
Lessons Learnt Unpublished
-
Case No 41. Lane Cove Tunnel, Australia, 2 Nov. 2005 Australia
2 November 2005
Project Title L