ODEQ Heating Oil Tank Program
!• Developed in 2000 !• Set standards for Soil Samples, Decommissioning and
Cleanups !• Purpose is to Protect Human Health and Environment
– Contaminating Groundwater – Indoor Air Quality !
• 20,000 closed files • ~ 50,000 open files
www.eworksnw.com
DEQ Requirements
Soil Samples• One sample from each
end of the tank • Within 6” of the end of
the tank and from 1-2’ below
Decommissioning• Must have Soil Samples • Fill and Vent Pipes
removed • Cleaned and Filled • *Voluntary Certification !
Clean Soil Samples may be used for DEQ Certification if decommission takes place within 90 days
!Contaminated Samples (>50 ppm) must be reported to DEQ
within 72 hours Leaking Underground Storage Tank Database (LUST): www.deq.state.or.us/lq/
tanks/LUST/LustPublicLookup.asp !
www.eworksnw.com
DEQ Requirements….!
DEQ considers who ever owns the property when contamination is identified as the responsible party
!Source of contamination must be removed immediately (tank
pumped & cleaned)
www.eworksnw.com
Three options for DEQ Cleanup & Certification
• Soil Matrix (50 – 500 ppm)**most often seen after excavation has taken place
– Depth to groundwater
– Annual precipitation
– Native soil or rock type
– Sensitivity to upper most aquifer
– Potential receptors
• Generic Remedy (500 – 2500 ppm)
– Contamination limited to soil – No free product
– No ecological risk posed by release
– Volume of soil >2,500 ppm doesn't exceed 65 cubic yards
– At least 3 feet of non contaminated soil above contamination
– Contaminated soil above seasonal high groundwater
• Risk Based (2,500 – 39,000 ppm) (air sampling)
– No free product
– Full vertical and lateral extent of contamination has been delineated
– Representative sample has been evaluated for BTEX (benzene) and PAH (ethylbenzene & naphthalene) – Exposure pathways of constituents of concern are explored and no human or ecological risk is present !
If Soil Samples > 2,500 ppm new regulations come into play
www.eworksnw.com
In The Past
• Diesel levels up to ~40,000 ppm could be left in place
!• Benzene was the driving factor determining if a site
meet DEQ Standards !
• Under most circumstances contamination could be left in place !
• Only a small portion of sites required soil removal or further investigation
www.eworksnw.com
New DEQ Regulations!• In 2008 EPA changed the classification of two constituents contained
in Diesel (ethylbenzene & naphthalene) from non - carcinogenic to carcinogenic
!• Created new screening levels for evaluating the effects on human
health from volatilization and vapor intrusion into indoor air
!• Recently the DEQ’s Heating Oil Tank Program adopted these
screening levels for residential heating oil tank projects
!• Ethylbenzene and Napthalene will be the driver determining cleanup
activities
!• Ethylbenzene must be < .82ppm
!• Napthalene must be < 6.5ppm
www.eworksnw.com
Evaluating Risk from Vapor Intrusion!!!• Ethylbenzene must be < .82ppm (in soil) • Napthalene must be < 6.5ppm (in soil) !Extremely overprotective of
human health due to uncertainties associated
with environmental modeling
! Excavation or Soil Gas Sampling is the next
step
www.eworksnw.com
Excavation vs. Air Sampling
Many variables to consider • volume of soil • depth to groundwater • concentration • potential impacts to property • projected costs • Overall likelihood to meet
DEQ requirements
www.eworksnw.com
Soil Gas Sampling!
• Valuable in situations where excavation is not an option
!• Collect air samples from soil pore
space ~5ft below ground surface
!• 1-2 samples needed
!• More direct evaluation of risk
!• $1,800 - $2,500.00
www.eworksnw.com
What does this mean for your clients?
• Only sites with minimal contamination will meet Risk Based Standards and not require further evaluation !
• Many more residential heating oil tank sites will require additional work (air sampling or excavation) !
• More Expensive !
• More impact to property (removal of fences, landscaping, decks and porches) !
• Take more time
www.eworksnw.com