heartland community college college development plan phase ii project schedule august 26, 2009

10
HEARTLAND COMMUNITY COLLEGE COLLEGE DEVELOPMENT PLAN PHASE II PROJECT SCHEDULE August 26, 2009

Upload: kerry-tucker

Post on 17-Jan-2016

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: HEARTLAND COMMUNITY COLLEGE COLLEGE DEVELOPMENT PLAN PHASE II PROJECT SCHEDULE August 26, 2009

HEARTLAND COMMUNITY COLLEGE

COLLEGE DEVELOPMENT PLANPHASE II PROJECT SCHEDULE

August 26, 2009

Page 2: HEARTLAND COMMUNITY COLLEGE COLLEGE DEVELOPMENT PLAN PHASE II PROJECT SCHEDULE August 26, 2009

College Development Plan Schedule

Project Bids received January 31, 2008Project bid accepted & funding strategy adopted February 27,

2008Notice of Award issued February 28,

2008Contracts executed March 2008Pre-Construction Meeting March 20, 2008Notice to Proceed issued April 2, 2008Construction April 2008–Aug 2010

Page 3: HEARTLAND COMMUNITY COLLEGE COLLEGE DEVELOPMENT PLAN PHASE II PROJECT SCHEDULE August 26, 2009

Child Development Lab

Community Education Center

Fitness & Recreation Center

Receiving & Storage Building

Student Commons Addition

Instructional Commons

North

Page 4: HEARTLAND COMMUNITY COLLEGE COLLEGE DEVELOPMENT PLAN PHASE II PROJECT SCHEDULE August 26, 2009

Building Substantial Completion

Receiving & Storage Bldg December 4, 2008

Child Development Lab January 16, 2009Community Ed Center 1st Floor August 3, 2009Community Ed Center 2nd Floor February 19,

2010SCB Addition February 1, 2010Instructional Commons North December 18, 2009Fitness & Recreation Center May 10, 2010SCB Remodel August 2, 2010

Site Development – As needed to progress with building construction

Page 5: HEARTLAND COMMUNITY COLLEGE COLLEGE DEVELOPMENT PLAN PHASE II PROJECT SCHEDULE August 26, 2009

Building Ready for Use

Receiving & Storage Building Dec 15, 2008Child Development Lab Feb 2, 2009SCB Addition March 10, 2010Community Education Center April 1, 2010Instructional Commons North May 15, 2010Fitness and Recreation Center June 1, 2010 SCB Remodel August 24, 2010Project Closeout Dec 31, 2010

Page 6: HEARTLAND COMMUNITY COLLEGE COLLEGE DEVELOPMENT PLAN PHASE II PROJECT SCHEDULE August 26, 2009

Contracted Services Timeline

Food Service and Bookstore Open Operations in New Space

March 15, 2010

Page 7: HEARTLAND COMMUNITY COLLEGE COLLEGE DEVELOPMENT PLAN PHASE II PROJECT SCHEDULE August 26, 2009

CDP Construction Progress Slide Show

Z:\index.htm\College Development Plan

Page 8: HEARTLAND COMMUNITY COLLEGE COLLEGE DEVELOPMENT PLAN PHASE II PROJECT SCHEDULE August 26, 2009

HCC Facilities Master Plan Update

Page 9: HEARTLAND COMMUNITY COLLEGE COLLEGE DEVELOPMENT PLAN PHASE II PROJECT SCHEDULE August 26, 2009

HCC Facilities Master Plan Update

Page 10: HEARTLAND COMMUNITY COLLEGE COLLEGE DEVELOPMENT PLAN PHASE II PROJECT SCHEDULE August 26, 2009

Other Projects

Challenger Learning Center Interior_Renderings.pdf

SCB 2009 Remodel Project

CCB 2010 Remodel Project

SCB 2011 Remodel Project