heartland community college college development plan phase ii project schedule august 26, 2009
TRANSCRIPT
HEARTLAND COMMUNITY COLLEGE
COLLEGE DEVELOPMENT PLANPHASE II PROJECT SCHEDULE
August 26, 2009
College Development Plan Schedule
Project Bids received January 31, 2008Project bid accepted & funding strategy adopted February 27,
2008Notice of Award issued February 28,
2008Contracts executed March 2008Pre-Construction Meeting March 20, 2008Notice to Proceed issued April 2, 2008Construction April 2008–Aug 2010
Child Development Lab
Community Education Center
Fitness & Recreation Center
Receiving & Storage Building
Student Commons Addition
Instructional Commons
North
Building Substantial Completion
Receiving & Storage Bldg December 4, 2008
Child Development Lab January 16, 2009Community Ed Center 1st Floor August 3, 2009Community Ed Center 2nd Floor February 19,
2010SCB Addition February 1, 2010Instructional Commons North December 18, 2009Fitness & Recreation Center May 10, 2010SCB Remodel August 2, 2010
Site Development – As needed to progress with building construction
Building Ready for Use
Receiving & Storage Building Dec 15, 2008Child Development Lab Feb 2, 2009SCB Addition March 10, 2010Community Education Center April 1, 2010Instructional Commons North May 15, 2010Fitness and Recreation Center June 1, 2010 SCB Remodel August 24, 2010Project Closeout Dec 31, 2010
Contracted Services Timeline
Food Service and Bookstore Open Operations in New Space
March 15, 2010
CDP Construction Progress Slide Show
Z:\index.htm\College Development Plan
HCC Facilities Master Plan Update
HCC Facilities Master Plan Update
Other Projects
Challenger Learning Center Interior_Renderings.pdf
SCB 2009 Remodel Project
CCB 2010 Remodel Project
SCB 2011 Remodel Project