    Joint Recreation Bond Projects Stat

    Project Design Bid Started Finished Bond $

    Maxfield Farm 3,100,00WABA and town shareof utility work- no East add-on

    2,500,00

    HMMS gym andcafeteria

    900,00

    Field House, KiddiePool, Pump House andschool share of utilitywork

    1,690,00

    Track & Turf plus fieldimprovements

    800,00

    Totals 8,990,00

  • 7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status

    3/19

    Why were some numbers good and othe

    Maxfield already designed and bid out

    WABA sketch design estimated in 2010 Full design and engineering revealed significant util

    Final design differs from sketch design

    There was no design or engineering work in of middle school, track & turf, or Fieldhouse

    Engineering expenses to date > $100K

    revealed need of $1.7 million for prep work for track

  • 7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status

    4/19

    Lessons Learned

    Major capital projects should be designed and

    engineered before developing a bond amount Example: School Bond of 2011 based on $50K engineerin

    $4.5 million only $4 million was needed = everyone ha

    Double any guesstimate for bond language, an

    up borrowing less Example: HMMS guesstimated at 900K. 900K x 2 = $1.8 million

    Project comes in at $1.5 million = everyone happy

  • 7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status

    5/19

    Moving Ahead

    To accomplish minimum objectives of original bo

    additional $3.6 million is needed WABA east eliminated (-708K); reuse bleachers (-40

    lights (-75K), black track instead of brick red (-60K)

    To accomplish full objectives of original bond $4.

    is needed This would include the East wing of WABA with full

    full replacement of field improvements, miscellaneoimprovements

  • 7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status

    6/19

    Alternatives?

    Supplemental Joint bond for $3.6 million

    Town could dip into emergency funds, and cut pavbudget, tap other reserve funds

    Town & School could go back to drawing board oncombination Field House & WABA

    School could cancel Track/Turf and Field House

    Town could get out of hockey business and close W

    Individual bonds from town and school

  • 7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status

    7/19

    Pros and Cons

    Supplemental Bond Pro: projects done well, work as investments attract

    residents and new revenues

    Pro: affirms town school cooperation

    Pro: meets needs of all sport constituencies among r

    Pro: low interest rate environment, borrowing now i

    Con: tax levy impact goes from 2% to 3%

    Con: if defeated creates confusion over intent of vote

  • 7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status

    8/19

    Pros and Cons

    Town uses existing resources to do WABAPro: Project gets done regardless of what happens with

    Pro: No need to borrow more

    Pro: Gives future taxpayers 20%+ break on project cos

    Con: Will be stripped down version of great vision

    Con: Current taxpayers foot 20%+ of project cost imm

    Con: Where does tapping paving budget or emergencyrepurposing reserves end?

  • 7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status

    9/19

    Pros and Cons

    Town & School go back to drawing boardPro: Fieldhouse / WABA integration satisfies Hurricanfor dedicated locker rooms for football and hockey sea

    Pro: Possible net savings on ideal projects

    Pro: Preserves spirit of town-school cooperation

    Con: Nothing settled for some time

    Con: Possible additional cost to minimum projects

  • 7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status

    10/19

    Pros and Cons

    School cancels Track/Turf/Fieldhouse Pro: Unnecessary, grandiose scheme avoided

    Pro: Frees up bonding space for more pressing capit

    Con: Baseball and Hockey constituencies seen to hatrack and football to have lost, dividing town

    Con: Town misses opportunity to show positive beli

    Con: Future of high school back on table in regionalconsolidation discussions

  • 7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status

    11/19

    Pros and Cons

    Town closes WABA Pro: Oversupply of rinks in region keeps prices low,

    pressure on viability of all rinks; if one closed all resstronger

    Pro: If financially viable with renovation why not selcompany to run at a profit and reap tax benefits

    Con: Would damage HHS hockey programs and attrof school to tuition students

    Con: Creates community discord (even suggesting it

  • 7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status

    12/19

    Current Thinking / Estimated Cos

    School will put up $3 million supplemental bond

    Town continues to discuss options

    Cost of 8.9 million Joint Rec Bond of 2012 is about $600K annually for principal and interest for 20 years at 3%

    4.5 cents of $2.225 tax rate

    $45 per year on a $100K property

    Cost of going to 12.25 million total bonding is about $842K annually for principal and interest for 20 years at 3%

    6.4 cents of $2.244 tax rate

    $64 per year on a 100K property

  • 7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status

    13/19

    New Track and Field, Field House and W

  • 7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status

    14/19

    Appendix 1: WABA Illustrations

    West Addition E

    Wendall A. Barwood Arena as seen from HHS/Pool

  • 7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status

    15/19

    Existing WABA layout

    East detail

  • 7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status

    16/19

    WABA Full Renovation

  • 7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status

    17/19

    West Detail

  • 7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status

    18/19

    WABA concept for 2010 estimate

  • 7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status

    19/19

    Town / School District Joint Recreation Projects Status and Options

    Excludes Maxfield Farm sports fields complex - underway and on budget ($3.1 million of bond)

    PriorityRating System

    required by bond 1 must bedone, coreproject

    implicitrequirement 2 must bedone, coreproject requires it

    All sitework, materials, labor costs putout to bid

    All design, permiting, etc. not put outto bid

    protects investment 3 should bedoneto minimizefutureexpenses

    cheaperto doat sametime 4 should bedone tominimizecurrent expenses

    nice-to-haveadd on 5 would havebeen included in bond with perfect information last summer

    Component Owner Justifica tion Notes and Comments Priority Direct Costs Related Costs Total Cost

    HMMS Gym and related renovations School Recover cafeteria in anticipation of Field House having weight room This work has been finished 1 $ 1,250,000 $ 250,000 $ 1,500,000

    New 8 lane rubber track with all-weather multi-purposefield at high school / middle school / ice hockey arenacampus

    School Principal component of joint rec bond, now includes Fencing(100K), Field lightmove/modify(75K), move bleachers (10K), new goalposts(30K); prepare ground forinstallation (1.7 million)

    1 $ 2,624,868 $ 264,000 $ 2,888,868

    Misc Field Improvements School New: Press Box (25K) code req 2 $ 25,000 $ - $ 25,000

    Misc Field Improvements School New: Bleachers (400K), Scoreboard (45K), Equip Storage Shed (100K) Nice-to-have improvements being foregone now 3 $ 545,000 $ - $ 545,000

    Fields Utility Work Joint Required by WABA and HHS Fields Amount is 1/2 of total 2 $ 206,620 $ - $ 206,620

    Green Mtn elec upgrade Joint Cost unknown, likely to be 100K +/- Amount is 1/2 of total 2 $ 50,000 $ 50,000

    Field House School Principal component of joint rec bond; includes pump house/pool town portion 220K,140K bond)

    1 $ 1,363,732 $ 330,000 $ 1,693,732

    All items: $ 6,065,220 $ 844,000 $ 6,909,220

    what school needs to come up with 1's and 2's $ 5,520,220 $ 844,000 $ 6,364,220

    Wendall A Barwood Arena (WABA)- West addition only Town New West addition with 4 locker rooms to accomodate tournament play, make arenauseful year-round

    1 $ 2,476,000 $ 300,000 $ 2,776,000

    WABA - East addition Town Meets needs of HS hockey teams for dedicated lockers Nice-to-have improvements being foregone now 3 $ 708,000 $ 708,000

    WABA Utility Work Joint Required by WABA and HHS Fields Amount is 1/2 of total 2 $ 206,620 $ - $ 206,620

    Green Mtn elec upgrade Joint Cost unknown, likely to be 100K +/- Amount is 1/2 of total 2 $ 50,000 $ 50,000

    WABA w/East addn $ 3,440,620 $ 300,000 $ 3,740,620

    what town needs to come up with WABA no East addn $ 2,732,620 $ 300,000 $ 3,032,620

    Town & School total $ 9,505,839 $ 1,144,000 $ 10,649,839

    Quick Summary of Required Supplemental Funding For slide show (rounded to nearest 10K)

    WABA no East plus Utility share $ 3,033,000

    School projects: Field House/Pump House/Kiddie Pool and utilityshare

    $ 1,951,000

    Track/Turf/Field sitework and related improvements $ 2,113,868 More than anticipated; actual track and turf alone only slightly over estimate of 800K Track/T urf and improvements $ 2,914,000

    Cost overrun on HMMS work $ 600,000 Unanticipated findings during construction Maxfield $ 3,100,000

    Unanticipated utility work on site $ 256,620 School share of total cost HMMS $ 1,500,000

    Field House / Pump House bid over estimate by $ 3,732

    Total all Joint Rec Bond Projects $ 12,498,000

    School portion of Joint Rec Bond project requiring funding $ 2,974,220 Bond Total $ 8,990,000

    Shortfall $ 3,508,000

    Appendix 2 - Spreadsheet with detailed breakout of costs