hartford vt town meeting info night - joint rec bond projects status
TRANSCRIPT
-
7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status
1/19
Joint RecreaProjects Upd
-
7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status
2/19
Joint Recreation Bond Projects Stat
Project Design Bid Started Finished Bond $
Maxfield Farm 3,100,00WABA and town shareof utility work- no East add-on
2,500,00
HMMS gym andcafeteria
900,00
Field House, KiddiePool, Pump House andschool share of utilitywork
1,690,00
Track & Turf plus fieldimprovements
800,00
Totals 8,990,00
-
7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status
3/19
Why were some numbers good and othe
Maxfield already designed and bid out
WABA sketch design estimated in 2010 Full design and engineering revealed significant util
Final design differs from sketch design
There was no design or engineering work in of middle school, track & turf, or Fieldhouse
Engineering expenses to date > $100K
revealed need of $1.7 million for prep work for track
-
7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status
4/19
Lessons Learned
Major capital projects should be designed and
engineered before developing a bond amount Example: School Bond of 2011 based on $50K engineerin
$4.5 million only $4 million was needed = everyone ha
Double any guesstimate for bond language, an
up borrowing less Example: HMMS guesstimated at 900K. 900K x 2 = $1.8 million
Project comes in at $1.5 million = everyone happy
-
7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status
5/19
Moving Ahead
To accomplish minimum objectives of original bo
additional $3.6 million is needed WABA east eliminated (-708K); reuse bleachers (-40
lights (-75K), black track instead of brick red (-60K)
To accomplish full objectives of original bond $4.
is needed This would include the East wing of WABA with full
full replacement of field improvements, miscellaneoimprovements
-
7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status
6/19
Alternatives?
Supplemental Joint bond for $3.6 million
Town could dip into emergency funds, and cut pavbudget, tap other reserve funds
Town & School could go back to drawing board oncombination Field House & WABA
School could cancel Track/Turf and Field House
Town could get out of hockey business and close W
Individual bonds from town and school
-
7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status
7/19
Pros and Cons
Supplemental Bond Pro: projects done well, work as investments attract
residents and new revenues
Pro: affirms town school cooperation
Pro: meets needs of all sport constituencies among r
Pro: low interest rate environment, borrowing now i
Con: tax levy impact goes from 2% to 3%
Con: if defeated creates confusion over intent of vote
-
7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status
8/19
Pros and Cons
Town uses existing resources to do WABAPro: Project gets done regardless of what happens with
Pro: No need to borrow more
Pro: Gives future taxpayers 20%+ break on project cos
Con: Will be stripped down version of great vision
Con: Current taxpayers foot 20%+ of project cost imm
Con: Where does tapping paving budget or emergencyrepurposing reserves end?
-
7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status
9/19
Pros and Cons
Town & School go back to drawing boardPro: Fieldhouse / WABA integration satisfies Hurricanfor dedicated locker rooms for football and hockey sea
Pro: Possible net savings on ideal projects
Pro: Preserves spirit of town-school cooperation
Con: Nothing settled for some time
Con: Possible additional cost to minimum projects
-
7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status
10/19
Pros and Cons
School cancels Track/Turf/Fieldhouse Pro: Unnecessary, grandiose scheme avoided
Pro: Frees up bonding space for more pressing capit
Con: Baseball and Hockey constituencies seen to hatrack and football to have lost, dividing town
Con: Town misses opportunity to show positive beli
Con: Future of high school back on table in regionalconsolidation discussions
-
7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status
11/19
Pros and Cons
Town closes WABA Pro: Oversupply of rinks in region keeps prices low,
pressure on viability of all rinks; if one closed all resstronger
Pro: If financially viable with renovation why not selcompany to run at a profit and reap tax benefits
Con: Would damage HHS hockey programs and attrof school to tuition students
Con: Creates community discord (even suggesting it
-
7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status
12/19
Current Thinking / Estimated Cos
School will put up $3 million supplemental bond
Town continues to discuss options
Cost of 8.9 million Joint Rec Bond of 2012 is about $600K annually for principal and interest for 20 years at 3%
4.5 cents of $2.225 tax rate
$45 per year on a $100K property
Cost of going to 12.25 million total bonding is about $842K annually for principal and interest for 20 years at 3%
6.4 cents of $2.244 tax rate
$64 per year on a 100K property
-
7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status
13/19
New Track and Field, Field House and W
-
7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status
14/19
Appendix 1: WABA Illustrations
West Addition E
Wendall A. Barwood Arena as seen from HHS/Pool
-
7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status
15/19
Existing WABA layout
East detail
-
7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status
16/19
WABA Full Renovation
-
7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status
17/19
West Detail
-
7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status
18/19
WABA concept for 2010 estimate
-
7/22/2019 Hartford VT Town Meeting Info Night - Joint Rec Bond Projects Status
19/19
Town / School District Joint Recreation Projects Status and Options
Excludes Maxfield Farm sports fields complex - underway and on budget ($3.1 million of bond)
PriorityRating System
required by bond 1 must bedone, coreproject
implicitrequirement 2 must bedone, coreproject requires it
All sitework, materials, labor costs putout to bid
All design, permiting, etc. not put outto bid
protects investment 3 should bedoneto minimizefutureexpenses
cheaperto doat sametime 4 should bedone tominimizecurrent expenses
nice-to-haveadd on 5 would havebeen included in bond with perfect information last summer
Component Owner Justifica tion Notes and Comments Priority Direct Costs Related Costs Total Cost
HMMS Gym and related renovations School Recover cafeteria in anticipation of Field House having weight room This work has been finished 1 $ 1,250,000 $ 250,000 $ 1,500,000
New 8 lane rubber track with all-weather multi-purposefield at high school / middle school / ice hockey arenacampus
School Principal component of joint rec bond, now includes Fencing(100K), Field lightmove/modify(75K), move bleachers (10K), new goalposts(30K); prepare ground forinstallation (1.7 million)
1 $ 2,624,868 $ 264,000 $ 2,888,868
Misc Field Improvements School New: Press Box (25K) code req 2 $ 25,000 $ - $ 25,000
Misc Field Improvements School New: Bleachers (400K), Scoreboard (45K), Equip Storage Shed (100K) Nice-to-have improvements being foregone now 3 $ 545,000 $ - $ 545,000
Fields Utility Work Joint Required by WABA and HHS Fields Amount is 1/2 of total 2 $ 206,620 $ - $ 206,620
Green Mtn elec upgrade Joint Cost unknown, likely to be 100K +/- Amount is 1/2 of total 2 $ 50,000 $ 50,000
Field House School Principal component of joint rec bond; includes pump house/pool town portion 220K,140K bond)
1 $ 1,363,732 $ 330,000 $ 1,693,732
All items: $ 6,065,220 $ 844,000 $ 6,909,220
what school needs to come up with 1's and 2's $ 5,520,220 $ 844,000 $ 6,364,220
Wendall A Barwood Arena (WABA)- West addition only Town New West addition with 4 locker rooms to accomodate tournament play, make arenauseful year-round
1 $ 2,476,000 $ 300,000 $ 2,776,000
WABA - East addition Town Meets needs of HS hockey teams for dedicated lockers Nice-to-have improvements being foregone now 3 $ 708,000 $ 708,000
WABA Utility Work Joint Required by WABA and HHS Fields Amount is 1/2 of total 2 $ 206,620 $ - $ 206,620
Green Mtn elec upgrade Joint Cost unknown, likely to be 100K +/- Amount is 1/2 of total 2 $ 50,000 $ 50,000
WABA w/East addn $ 3,440,620 $ 300,000 $ 3,740,620
what town needs to come up with WABA no East addn $ 2,732,620 $ 300,000 $ 3,032,620
Town & School total $ 9,505,839 $ 1,144,000 $ 10,649,839
Quick Summary of Required Supplemental Funding For slide show (rounded to nearest 10K)
WABA no East plus Utility share $ 3,033,000
School projects: Field House/Pump House/Kiddie Pool and utilityshare
$ 1,951,000
Track/Turf/Field sitework and related improvements $ 2,113,868 More than anticipated; actual track and turf alone only slightly over estimate of 800K Track/T urf and improvements $ 2,914,000
Cost overrun on HMMS work $ 600,000 Unanticipated findings during construction Maxfield $ 3,100,000
Unanticipated utility work on site $ 256,620 School share of total cost HMMS $ 1,500,000
Field House / Pump House bid over estimate by $ 3,732
Total all Joint Rec Bond Projects $ 12,498,000
School portion of Joint Rec Bond project requiring funding $ 2,974,220 Bond Total $ 8,990,000
Shortfall $ 3,508,000
Appendix 2 - Spreadsheet with detailed breakout of costs