hampton roads bridge tunnel expansion...2020/06/04  · project full notice to proceed (ntp) october...

25
Hampton Roads Bridge Tunnel Expansion June 4, 2020 Stakeholders Meeting 0002

Upload: others

Post on 10-Oct-2020

11 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

Hampton Roads Bridge Tunnel Expansion

June 4, 2020

Stakeholders Meeting 0002

Page 2: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

Purpose of Stakeholders Meetings

Share Information and Promote a Common Understanding

Update Stakeholders on Activity Progress and Projections

Engage and Solicit Stakeholder Feedback

Provide an Open Venue for Discussion

2

Page 3: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

Activity/Milestone Progress

3

ACTIVITY DATE

Contract Award April 3, 2019

LNTP1 (Permit Applications) April 12, 2019

HRCP Joint Permit Application (JPA) Submitted August 30, 2019

LNTP2 (Tunnel Boring Machine) September 25, 2019

LNTP3 (South Island Early Works) September 25, 2019

Tunnel Boring Machine Purchase Order February 18, 2020

Project Full Notice to Proceed (NTP) October 2020

Note:LNTP: Limited Notice to ProceedHRCP: Hampton Roads Connector Partners, the Design-Builder

Page 4: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

2019 2020 2025

Contract Execution + LNTP104/15/19

Anticipated JPA Approval Date = NTP540 days (18 months) after LNTP1

= October 2020

LNTP 1

LNTP 3

LNTP2 + LNTP39/25/19

Substantial Completion 06/30/25

LNTP3 : Launching Pit Construction to start

LNTP 2 LNTP2 : Authorization for TBM Procurement

Contractual - Substantial Completion Deadline 09/01/25

Contractual - Final

Completion Deadline 11/01/25

Launch & Receiving pit ready for TBM

4

The Project Timeline

4

2021 2022 2023 2024

Design and Investigation Works for Environmental Permitting

6 MONTHS OF SCOPE VALIDATION

Permanent Works over 55 Months

TBM Assembly and Mining

Interior Work Tunnels

Commissioning and Testing

North and South Marine Trestles

Land Works I-64 Widening

Today

Page 5: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

Project Progress

5

Page 6: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

Financial Progress

6

❖ HRTAC Board Action: VDOT Authorized to Execute Bridge Repair Works Option

✔ Optional Work in Contract to Include the Preventative Maintenance (~$41.3M) and Required Repair Improvements (~$32.2M) to Landside Bridges in Norfolk.

❖ HRTAC Board Action: Approved FY2020-FY2026 Plan of Finance Update – COVID-19 Potential Impact Review - Continuation of Current Approved Plan of Finance with Stress Test Adjustments

Page 7: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

Environmental Progress

7

USACE/DEQ/VMRC Joint Permit Application (JPA)

Target Permit Receipt – October 2020Draft USACE Permit Received – Still Needed: - NOAA Incidental Take Authorization (IHA) - USACE Section 408 Determination VMRC Commission ApprovedVMRC Draft Permit ReceivedDEQ Permit Public Notice Period in ProgressCurrent Permit Receipt Projection – July 2020

USCG Bridge Permit Bridge Permit Application Submitted – December 26, 2019USCG Preliminary Public Notice in ProgressTarget USCG Bridge Permit – July 2020

Page 8: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

Design Progress

8

ACTIVITY DATESouth Island Utility Relocations (Ready for Construction) March 2020South Island Launch Pit (Stage 2 Design) March 2020North Island Expansion (Stage 2 Design) April 2020South Island Access Improvements (Ready for Construction) May 2020South Island Launch Pit (Ready for Construction) June 2020North Island Utility Relocations (Ready for Construction) June 2020North and South Trestle Bridges Replacement (In Design)Willoughby Bay Bridge Widening (In Design)Roadways Widening Packages Hampton and Norfolk (In Design)Landside Bridges (In Design)Tunnel Spaceproofing and Concepts (In Design)

Page 9: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

Planned Construction Progress (Narrative)

9

South Island Utilities Relocations; South Island Field Offices; Temporary Equipment Slab Placements

South Island Utilities Relocations; TBM Receiving Dock Landside; South Island Equipment Slabs; Office Trailers; Willoughby Spit Site Work; Hampton Batch Plant Installations; South Island Guide Walls; Water Treatment Plant; Slurry Treatment Plant

TBM Receiving Dock Landside; South Island Water and Slurry Treatment Plants; South Island Slurry Walls; North Island Utility Relocations*; Hampton Batch Plant Installations; North Island Preparations*

TBM Receiving Dock Landside; South Island Water and Slurry Treatment Plants; South Island Slurry Walls (Launch Pit); North Trestle Mobilization and Test Piles*; South Trestle Test Piles*

May 2020

June 2020

July 2020

August 2020

Note: * - Activity Requires Permits and Full NTP

Page 10: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

10

Key Construction Activities

Activity Planned StartSouth Island Early Works March 2020North Island Expansion September 2020North Trestle Replacement September 2020South Trestle Replacement October 2020Oastes Creek Bridge Widening December 2020Mallory Street Bridge Replacement December 2020Hampton Roadwork December 2020Norfolk Roadwork December 2020Willoughby Bridge Widening December 2020Mason Creek Bridge Widening March 2021Tunnel Boring Operations March 2022

Page 11: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

Stakeholder

Interactions

11

Page 12: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

Stakeholder Interactions

12

U.S. Navy:• Regular Progress Updates• Technical Coordination with NAVFAC• Establishing Breakout Briefings on Project Design• Solution Focused Interactions

Hampton University:• Regular Progress

Updates• Information Sharing• Emancipation Oak

Assessment

City of Hampton:• Regular Progress Updates• Technical Coordination• Maintenance of Traffic Coordination• Establishing Breakout Briefings on Project Design• Solution Focused Interactions

City of Norfolk:• Regular Progress Updates• Technical Coordination• Maintenance of Traffic Coordination• Establishing Breakout Briefings on Project Design• Solution Focused Interactions

Page 13: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

Queen CrittendonCivil Rights

13

Page 14: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

DBE/SWaM Update

14

Contractor (HRCP) recently completed a small business Bonding Education Program (BEP) with USDOT for a record number of small business graduates

Page 15: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

DBE/SWaM Opportunities

15

HRCP held a Virtual Public Update for Disadvantaged Business Enterprises (DBE) and Small, Women, and Minority-Owned Businesses (SWaM) on May 11, 2020

Compliance Manager Malcolm Kates led discussion with 218 in “virtual” attendance

Malcolm shared:

• 106 DBE/SWaM subcontractors have already been awarded contracts totaling over 30.8 million dollars.

Page 16: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

HRBT Expansion ProjectWorkforce Development: Project Goals

Virginia Department of Transportation

VDOT has assigned the following aggressive contract goals for the Project, required by HRCP:

▪ 12% Disadvantaged Business Enterprise (DBE)

▪ 20% Small, Woman and Minority-Owned Business (SWaM)

▪ 80 On-the-Job (OJT) Trainee Goal

16

Page 17: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

To ensure compliance with contract requirements, the Contractor is responsible for submitting to VDOT the following:

❖ Workforce Participation PlanDetails specific affirmative steps taken to ensure EEO throughout the life of the Project

❖ OJT Training PlanTrain and upgrade the qualifications of minorities and women toward journey worker status as outlined in VTCA/VDOT OJT Manual

HRBT Expansion ProjectWorkforce Development Programs

17

Page 18: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

Communications/Outreach

18

Page 19: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

19

Visitor’s Center

Page 20: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

Virtual Public Outreach

Community Outreach through Zoom, Teams, HangOut, etc.

Maritime Community Meetings

Video Podcast with Bob McKenna-Peninsula Chamber

Podcast recorded through virtual outreach

20

Page 21: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

First of two yearly issues of HRBT Magazine released June 1, 2020

Monthly newsletters began in February 2020

21

Page 22: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

MediaBorder Collies

on South Island

U.S. Air Force F-22 Raptor flies over HRBT South Island during salute to Virginia’s Health Care Heroes

▪ Daily Press▪ Virginian-Pilot ▪ Virginia Mercury▪ Chesapeake Bay Magazine▪ LinkedIn▪ Facebook▪ TODAY Show (future air date)

22

Page 23: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

Next Steps

Stretch and Flex-It’s How We Roll!

Thank You

for

Participating

Today!

23

Page 24: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

Stakeholder FeedbackOpen Discussion

24

Page 25: Hampton Roads Bridge Tunnel Expansion...2020/06/04  · Project Full Notice to Proceed (NTP) October 2020 Note: LNTP: Limited Notice to Proceed HRCP: Hampton Roads Connector Partners,

Thank You25

August 27, 2020

1 P.M.

Next STAKEHOLDERS MEETING