hall clearance completed revisiting water & cryo plant prepare for shutdown ’04 –beam tube...
TRANSCRIPT
• Hall clearance completed
• Revisiting Water & Cryo Plant
• Prepare for shutdown ’04– beam tube– Contract hole cutting
• Negotiating with DF to help target work along at Sheffield
• Discussion with ASTeC on RF Support
Beam & Infrastructure
MICE
• Technical Board meeting– Adopted change control – process in place– Plan to revise MICE design for March CB– This is also the timescale to complete the WBS (ISIS
Shutdowns!)
• WBS– All parts now represented except
slow controls and instrumentation– Negotiations…. Interfaces…
• Absorber review– December 9-10
Tasks to end 2003
• Manufacture beam tube
• R&D on absorber window (welding samples)
• Continue Cryogenic & Hydrogen System design (absorber) – establish heat load
• Complete Beam Line performance evaluation
Plans for 2004/5
• Cut into synchrotron vault ◄• Bring PSI Solenoid to RAL ◄• Assembly of an RF Test Stand ◄• Engineering design of beam line• Engineering of Target Mechanism• Design MICE support structure• Complete water & Cryo. plant design
– Begin building design (contract)– Start building work (contract)
Tracker technology decision
• Light yield 4-5 pe• Expectation ~10• Systematic analysis in hand
• Simulation updated to include more realistic models of inefficiency, noise etc.• Reconstruction of simulated data shows adequate performance•Outstanding issue: resolution (MCS dominated) needs to be shown to give adequate resolution in emittance
•MICE adopted SciFi detector as baseline tracker … will be used subject to satisfactory resolution of above