haldia institute of technology

Upload: prithwirajroy10

Post on 29-May-2018

227 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 Haldia Institute of Technology

    1/24

    HALDIA INSTITUTE OF TECHNOLOGY

    ECONOMIC LOAD DISPATCH PROBLEMCONSIDERING TRANSMISSION LOSS

    BY

    Abhishek Basu(06/EE/14)

    Prithwiraj Roy(06/EE/19)

    Kalyanbar Sarkar(06/EE/20)

    Rajib Manal(06/EE/28)

    Under

    Mr.Budhaditya Biswas

    DEPARTMENT OF ELECTRICAL ENGINEERING

    HALDIA INSTITUTE OF TECHNOLOGY

  • 8/8/2019 Haldia Institute of Technology

    2/24

    The Head

    Department of Electrical Engineering

    Haldia Institute of TechnologyHIT/ICARE Complex

    PO-Hatiberia,HaldiaMidnapore (E),West Bengal-721 657

    Respected Sir,

    In accordance with the requirements of the degree of bachelor of Technology in the department

    of Electrical Engineering , Haldia Institute of Technology. I present the following thesis entitled

    ECONOMIC LOAD DISPATCH PROBLEM CONSIDERING

    TRANSMISSION LOSS.

    This work was performed under the supervision of Mr.Budhaditya Biswas.

    .

    We declare that the work submitted in this thesis is our own except as acknowledge in the text

    and references ,and has not been previously submitted for a degree at the Institute or any other

    Institution.

    Your Sincerely, Guided by

    Abhishek Basu (06/EE/14) (....)

    Prithwiraj Roy(06/EE/19)

    Kalynbor Sarkar(06/EE/20)

    Rajib Mandal(06/EE/28) Mr.Budhaditya Biswas

  • 8/8/2019 Haldia Institute of Technology

    3/24

    CERTIFICATE

    This is to certify that the thesis entitled ECONOMIC LOAD DISPATCH PROBLEM

    CONSIDERING TRANSMISSION LOSS

    .is a bona fide work carried by mukesh kumar layak in partial fulfillment of the requirement for

    the degree of BACHELOR OF TECHNOLOGY in ELECTRICAL ENGINEERING under

    supervision of Mr.Budhaditya Biswas

    during the academic year 2008-2009 & this has not been submitted elsewhere for a similardegree.

    Countersigned by

    Dr. Prithwiraj Purkait

    Head

    Department of Electrical Engineering

    Haldia Institute of Technology

    Haldia

  • 8/8/2019 Haldia Institute of Technology

    4/24

    ACKNOWLEDGEMENT

    Apart from the efforts of ours, the success of this project depends largely on the encouragement

    and guidelines of many others. I take this opportunity to express our gratitude to the people who

    have been instrumental in the successful completion of this project.

    I would like to show my greatest appreciation to Mr. Budhaditya Biswas

    I cant say thank you enough for their tremendous support and help. I felt motivated and

    encouraged every time when they came for helping me. Without their encouragement and

    guidance this project would not have materialized.

    The guidance and support received from other sir in department to this project, was vital for the

    success of the project. I am grateful for their constant support and help.

  • 8/8/2019 Haldia Institute of Technology

    5/24

    INTRODUCTION

    Economic operation and planning of electric energy generating systems have always been given

    proper attention in the electric power system industry. A saving in the cost of generation

    represents a significant reduction in the operating cost (including the fuel cost) and this area has

    warranted a great deal of attention from operating and planning engineers. The original problem

    of economic dispatch of thermal power generating system used to be solved by numerous

    methods. However, with the development of mathematical tools and advanced computational

    methods, the economic scheduling of generators has become more accurate and can be applied

    even in complex networks. Thermal scheduling being the prime importance, hydrothermal

    coordination scheduling has emerged as another aspect of economic scheduling.

    The basic purpose of economic operation of power system is to reduce fuel cost

    for the operation of power system, economic operation is achieved when the generators in the

    system share load to minimize overall generation cost. The main economic factor in the power

    system operation is the cost of generation real power. In any power system, this cost has two

    components, viz.,

    The fixed being determined by the capital investment, interest charged on the moneyborrowed, tax paid, labour charge, salary given to staff and any other expenses thatcontinue irrespective of the load on the power system, and

    The variable cost, a function of loading on generating units, losses, daily loadrequirements and purchase or sale of power.

    The present text relating the economic operation of a power system is concerned about

    minimising the variable cost factor only as the persons responsible for the operation of a

    power system have little control over the fixed costs.

    A power system is a mix of different modes of generation out of which thermal, hydro

    and nuclear contribute a major share. However, economic operation has conventionally been

    considered by proper scheduling of thermal or hydrogenation only or both, as, for the safety of

    nuclear station, these types of stations are required to be operated at a fixed load only and there

    is little scope to schedule the generation of nuclear type in practice.

  • 8/8/2019 Haldia Institute of Technology

    6/24

    INPUT-OUTPUT OPERATIONAL CHARACTERISTICS OF DIFFERENT

    POWER PLANTS

    Thermal generating unit :

    It is a well-established physical principal that with increase in difference between the

    temperature and pressure of the input and output of any heat operated device (say, a turbine),

    more mechanical power will be developed for the same amount of heat energy input. The

    overall efficiency of thermal units is then determined by measuring he heat input, i.e. the

    electrical energy output. Conventionally, this represents input-output curves and can be

    developed for each generating unit involved. An efficient unit develops a given amount of

    power with less fuel input. Hence, it has become the usual practice to load the more efficient

    unit before loading the lesser efficient unit.

  • 8/8/2019 Haldia Institute of Technology

    7/24

    Hydel power station:

    The input-output characteristics for a typical hydro unit has been shown below. Though

    apparently it may seen that the input of a hydro plant costs nothing, but a little thinking reveals

    that the input water flow costs are due to capacity of the storage, agricultural requirement and

    cost of running the plant during dry season. Also, artificial storage requirement imposes cost to

    control the water output from the turbine due to agricultural needs.

  • 8/8/2019 Haldia Institute of Technology

    8/24

    INCREMENTAL FUEL RATE (IFR) CURVES

    The input-output curves, obtained from the operating data of power station, can be utilized to

    get the incremental fuel rate (IFR or IR) curve from the relation.

    IFR = incremental change in input /incremental change in output

    Thus, by calculating the shape of the input-output curves at various points of operation, the

    profile ofIFR can be obtained. IFR profiles for typical thermal and hydro power stations are

    shown below.

  • 8/8/2019 Haldia Institute of Technology

    9/24

    INCREMENTAL FUEL COST (IFC) CURVE

    This curve can be obtained from IFR curve by multiplying the IFR by the cost of fuel per Kcal.

    As in a power station, fuel cost governs the actual total cost. Hence, IFC is very significant in

    economic loading of the generation unit. The IFC curves will be similar to the IFC characteristic

    in configuration.

    It is obvious that the slopes of the input-output curve and incremental fuel rate curve

    do not change for different fuels or change in the cost of the same fuel. This time a multiplying

    factor may be used so that the actual cost is a realistic one. The unit ofIFC (or simply the IC) is

    unit of cost/MWhr.

  • 8/8/2019 Haldia Institute of Technology

    10/24

    CONSTRAINTS IN ECONOMIC OPERATION OF POWER SYSTEM

    Primary Constraints:

    These constraints arise out of the necessity for the system to balance the load demand and

    generation. They are also called equality constraints. If Pi and Qi are the scheduled electrical

    generation, Ploadi and Qloadi are the respective load demands, it is obvious that the following

    equation must be satisfied at the load bus.

    Real power position at load bus

    Pi Ploadi Pl = Mi = 0

    Qi Qloadi - Ql = Ni = 0

    Where Mi and Ni represents the power residuals at bus-i and Pl and Ql the power flow to the

    neighbouring system given by

    Pl = j=1N

    ViVjYij cos(ij-ij)

    Ql = j=1N

    ViVjYij sin(ij-ij)

  • 8/8/2019 Haldia Institute of Technology

    11/24

    Secondary Constraints:

    These constraints arise due o physical and operational limitations of respective units ands

    components and are known as inequality constraints. Power inequality constraints are applicable

    for proper operation; for each generator we should have a minimum and maximum permissible

    output and the unit production should be constrained to ensure that

    Pimin Pi Pimax, i= 1,2,., NP

    Qimin Qi Qimax , i= 1,2,.., NQ

    NP and NQ being the total number of real and reactive sources in the system.

    In addition to their inequality constraints, another constraints Pi2+Qi2(Sirated)2 must be satisfied,

    where Sirated denotes the complex power capability of the generating unit without any

    overloading.

    Dynamic Constraints:

    These constraints arise where fast changes in generation are required for picking up the

    increasing load demand. Here,

    dPi(t)/dtat=min dPi(t)/dt dPi(t)/dtat=max

    Similarly, for reactive power constraints,

    dQi(t)/dtat=min dQi(t)/dt dQi(t)/dtat=max

  • 8/8/2019 Haldia Institute of Technology

    12/24

    Spare Capacity Constraints:

    In order to account for the errors in load prediction, any sudden and fast change in load demands

    and the inadvertent loss of scheduled generation, spare capacity constraints are frequentlyutilised. In this constraints, the total generation available at any time should be in excess of he

    total anticipated load demand and any system loss by an amount not less than a specified

    minimum spare capacity PSPS.

    Therefore, Pig i=1N Pl+PSPS+Ploadi

    For groups of generators, when all plants are not equally operationally suitable for taking up

    additional load, this constraints is then given by

    Pig Pl+PSPS+Ploadi

    Where PSPS is the spare capacity generation for specified generators.

  • 8/8/2019 Haldia Institute of Technology

    13/24

    Thermal Constraints of Transmission Lines:

    These constrains arise when power injection (+S) or power drawl (-S) is allowed such that

    [Simax] Str [Simin], i= 1,2,(tr)n

    Where (tn)n represents the number of branches and Str the branch power transfer in MVA.

    Bus Voltage and Angle Constraints:

    These constraints arise in order to maintain voltage profle at load bus and limiting the overload

    capacity.

    Here,

    Vimin Vi Vimax, i= 1,2,., N

    imin i imax , j 1 j=2,.., M

    whee N represents the number of units and M the number of loads in the system.

    Operatonal Constraints:

    In case the transformer tap position needs to be included for optimization, the tap position ai

    should lie within the range available in the transformer, i.e. aimin ai aimax.

  • 8/8/2019 Haldia Institute of Technology

    14/24

    Optimal Operation

    Let us assume that it is known a priori which generators are to run to meet a particular loaddemand on the station. This is, given a station with h generators committed and the active power

    load PD given, the real power generation PGi for each generator has to be allocated so as tominimize the total cost.

    k

    C= 7 Ci (PGi) (Rs/h) (1)

    i=1

    Subject to the inequality constraint

    PGi min< PGi < PGi max i=1, 2... k (2)

    Where PGi min and PGi max are the lower and upper real power generation limits of the ith

    generator. Obviously,

    k

    7 PGi max >PD (3)

    i=1

    Considerations of spinning reserve require that

  • 8/8/2019 Haldia Institute of Technology

    15/24

    7 PGi max > PD

    In Eq.1, it is assumed that the cost C is largely dependent on the real power

    generation PGi and is insensitive to reactive power generation QGi.

    Since Ci (PGi) is nonlinear, and Ci is independent of PGj (j{i), this is a separablenonlinear programming problem.

    Only the inequality constraint of Eq. (3) is not effective, and between total power

    generation and load demand is

    k

    7 PGi PD =0 (4)

    i=1

    The problem can then be solved by the method ofLagrange multipliers, which is used for

    minimizing (or maximizing) a function with side conditions in the form of equality constraints.

    Using this method we define an augmented cost function (Lagrangian) as

    _ k

  • 8/8/2019 Haldia Institute of Technology

    16/24

    C = C -P (7 PGi PD ) (5)

    i=1

    Where P is the Lagrangian multiplier.

    Minimization is achieved by the condition

    _

    xC /x PGi =0

    or dCi/dPGi = P, i = 1, 2,, k (6)

    Where dCi/dPGi is the incremental cost of the ith generator (units: Rs/MWh).

    Equation (6) can be written as

    dC1/dPG1 = dC2/dPG2=.. = dCn /dPGn =P (7)

    i.e., optimal loading of generators corresponds to the equal incremental cost point of all the

    generators. Equation (4), called the coordination equation numbering n is solved

    simultaneously with the load demand in equation 13, to yield a solution for the Lagrange

    multiplier P and the optimal generation of n generators.

  • 8/8/2019 Haldia Institute of Technology

    17/24

    Economic allocation of generator between different plants in a

    system considering system transmission loss( economic

    dispatch) :

    Economic allocation of generator between different generating plants has been

    considered previously. When considering the economic allocation of generation between

    different plants in an integrated system, the transmission losses are to be considered. This

    leads to the dispatch of power in an economical way so as to make the overall cost to be

    minimum , Let there be N plants in a system interconnected by transmission line and

    ties

    Let P1, P2,PNrefer to the generation ofN plants, respectively in MW . Let

    the total load be Pload(constant)and loss in the lines be Pl.. The constraint equation will be

    i=1N -Pi+Pl+Pload=R

    (Rbeing the residual power and should approach zero during steady state power system

    operation)

  • 8/8/2019 Haldia Institute of Technology

    18/24

    Let the net fuel input cost per hour be F which is the summation of fuel costs per hour of

    each of the units governed by the generator powerP,

    i.e. F =i=1NFi(Pi) Rs/hr

    application of Lagrangian technique in order to optimize real power generation gives

    L=F+,be the multiplier , necessary condition for cost function to be minimum has

    been obtained by setting the first derivative of the lagrangian with respect to each of the

    independent variable to zero, i,e. L/Pi =0.

    Here L =F+(i=1N-Pi+Pl+Pload) and with L/Pi=0 we can write

    dFi(Pi)/dPi (1-Pi/Pl)=0

    or, dFi(Pi)/dPi + Pl/Pi =

    this equation represents the modified economic operation criterion for the thermal plants

    with transmission losses considered.

    This equation may be written as

    dFi(Pi)/dPi[1/1-Pl/Pi] =

    or dF(Pi)/dPi*PFi =

  • 8/8/2019 Haldia Institute of Technology

    19/24

    PFi =[1- Pl/Pi]-1

    PFi is known as Penalty factor the equation is known as the exact coordination equation .

    in dFi(Pi)/dPi beang the incremental cost Pl/Pi known as the incremental

    transmission loss. N number of optimum dispatch equations along with the constraint

    suffice for determining (N+1) unknown P1,P2,..Pn and .

    [i.e Pi-Pl=Pload

    thus dF(Pi)/dPi*PFi = dF(Pi)/dPi*1/1- (Pi-Pl) = dF(Pi)/dPi * Pi-Pload

    == dFi(Pi)/dPload

    When dFi(Pi)/dPload is the incremental cost of the received power for plant i and the

    penalty factor Pi-Pload . this also means that as Piincremental has a longer

    proportion dissipated as loss, (Pi-Pload) approaches unity and the penalty factorPFi ,

    increases without bound , thus for a larger penalty factor unit-i should be operated at low

    increment cost implying a low power output.]

    For N number of plants the coordination equation are given as

    dF1(P1)/dP1 [1- dPl/dP1]= 0

    dF2(P2)/dP2 [1- dPl/dP2]= 0

    .

    .

    .

    dFN(PN)/dPN [1- dPl/dPN]= 0

  • 8/8/2019 Haldia Institute of Technology

    20/24

    while the constraints equation is given by

    i=1N(Pi)+Pload+Pl= R

    If the numerical value f the partial derivative of the line losses with respect to each

    generator output (dPl/dPi) is known, the generator output power may be adjusted to

    satisfy the following equation

    dFi(Pi)/dPi[1/(1-dPl/dPi)]=, i=1,2,3..N

    the optimal economy is thus achieved when the products of the incremental fel cost times

    the penalty factor is the same for all plants,

    i.e.

    dF1(P1)/dP1PF1= dF2(P2)/dP2PF2=..= dFN(PN)/dPNPFN =

    stands here for the incremental cost f the received power in unit of (currency/MWhr)

    and hense during economic operation of plants with losses being considered,

    = Incremental fuel cost/(1-Incremental transmission loss)

  • 8/8/2019 Haldia Institute of Technology

    21/24

    Mathematical Calculation:

    Consider a simple power system consisting of two generating plants and one load as shown in

    below figure

    Plant 1 I1 I2 plant 2

    A C B

    I1+I2

    Fig: a simple system connecting two generating plants to one load

    Let Rac, Rbc, and Rcd be the resistance of the lines AC,BC and CD respectively. For the given

    system we can write the transmission loss as

    PL = 3 I1^2 Rac + 3 I2^2 Rbc + 3 I1 + I2^2 Rcd (1)

    If we assume that I1 and I2 are in phase,

    I1 + I2 = I1 + I2 (2)

  • 8/8/2019 Haldia Institute of Technology

    22/24

    PL = 3 I1^2 (Rac + Rcd ) + 3 I2^2 (Rbc + Rcd ) + 6 I1 I2 Rcd

    (3)

    Let P1 and P2 be the three-phase power output of plants 1 and 2 at P.F of COS J1 andCOS J2, and V1 and V2 be the bus voltage at the plants.

    I1 = P1 / (3 V1 COS J1 ), I2 = P2 / (3 V2 COS J2 )

    Substituting the values of I1 and I2 in equation (3) we get

    PL = P1^2 (Rac + Rcd ) + 2 P1P2 Rcd + P2^2 Rac + Rcd

    V1 ^2 cos J1^2 V1 V2 cos J1cosJ2 V1^2 cos J1^2...(4)

    Equation (4) can be written as

    PL = P1^2 B11 + 2 P1P2B12 + P2^2 B22

    Where, B11 = (Rac + Rcd ) , B12 = Rcd

    V1 ^2 cos J1^2 V1 V2 cos J1cosJ2

  • 8/8/2019 Haldia Institute of Technology

    23/24

    B22 = Rac + Rcd .. (5)

    V1^2 cos J1^2

    The terms B11, B12 and B22 are called loss coefficient

    If the voltage in equation (5) is line-to-line voltages in kilo volts and line resistances are in ohms,

    the unit for the loss coefficients will be in reciprocal megawatts. Then, in equation (4) with three-

    phase powers in megawatts, PL will be in megawatts also. If all the quantities are in per unit, te

    coefficients will be in per unit.

    It is seen that the loss coefficients depend on source voltages and p.f. The source voltages

    and p.f depends on and vary with system conditions. However B coefficients are constants. It is

    sufficiently accurate to calculate B coefficient for some average operating conditions use these

    value for economic loading for all the load variations. However for large load variation or major

    system changes, several sets of loss coefficients are used.

  • 8/8/2019 Haldia Institute of Technology

    24/24