Gujarat Solar Park World’s first Multi developer, Multi facility, Multi Technology and Multi beneficiary solar park At Charanka Village, Dist Patan - Gujarat 1

Upload: buiduong

Post on 29-Mar-2018

216 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity

Gujarat Solar Park World’s first Multi developer, Multi facility, Multi

Technology and Multi beneficiary solar park At Charanka Village, Dist Patan - Gujarat

1

Page 2: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity

Gujarat Solar Park…. What it means ?

• Multi Developer • 21 Developers from India and abroad have already commissioned the project totaling to 224 MW • With varied capacities ranging from 1 MW to 25 MW

• Multi Technology • Thin Film PV Technology • Crystalline Silicon Technology • Tracker based technology

•Multi Facility (Facilitated by GPCL – Nodal Agency) • Requisite size Plot Allotment • Approach & Access Roads • Smart Power Evacuation network up to the Project premises • Water Supply System etc

Page 3: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity

Project Location Charanka Village, Santalpur

Taluka, Patan District, Gujarat

The

Site

Radhanpur

Santalpur

Kutch Branch

Canal

Little Runn

of Kutch

Charanka

Village

Nearest Urban

Area: Radhanpur

Nearest NH: NH 15

@ 20 km

Nearest Rly

Station: Santalpur

• Total Identified Land by GPCL:

~ 2,500 Ha

• Land Selected for the

Proposed Park: ~ 2000 Ha

• Ownership: ~ 60% Govt.

Land (mostly wasteland) 3

Page 4: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity

Basic Facilities available…..

Roads uptp Plot

Raw Water Pipeline

Water Treatment Plant

Water Distribution Network

Water Tank (GLSR/OHT)

400/220/66 KV & 66 KV Auxiliary SS

Ready to Use Construction Power Distribution Network

Telecom (Broad Band) Network

Fencing to Solar Park(Boundary)

Security Towers

Availability of Construction Power

Wide ( Highway standard ) Approach Road

Power Evacuation at Door step of Plot

Proper Entrance Gate

Helipad

Solar Park Administrative Office

24 Hrs Solar Park Security

Single window facility for

Canteen facility

Medical Facility ( In near future)

Page 5: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity

In addition , Gujarat Solar Park will

facilitate …..

Ready to Use Contour data of Land allotted

Soil Investigation Data

Past two year actually measured Solar Radiation Data

Past two year actually measured Weather Data

Quick delivery of Ready to use plot

Provide facilitation to avail Construction Power

Provide facilitation to avail Power Evacuation System at Door step of Plot

Allow to create charge on the plot allotted to avail bank loans

Facilitate developer to receive necessary clearance from State / Central Government

Page 6: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity

Master Plan

6

Patrolling road

Internal roads

Nala

Reservoir

Water Pipe Line

Envisaged Capacity:

500MW

Present Installed

Capacity: 224 MW

No. of Developers : 21

Well defined Plot

Allotment Policy and

timely allocation of plots

to developers

Page 7: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity

Infrastructure development - Roads

Before After

Existing Charanka- Fangli – Jamwada village road is upgraded to 10 m wide approach road.

Page 8: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity

Existing simple earthen dam is converted to RCC dam

Capacity – 8 Lakh m3

Can provide water for irrigation to 300 Ha land – double cropping

Infrastructure Development - Water Reservoir

Before After

Page 9: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity

Existing simple culvert is converted to RCC weir cum culvert channeling water through RCC canal

Infrastructure Development - Culverts

Before After

Page 10: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity

Adoption of Innovative scheme of loop in loop out at 66 KV level,

400 x 200 x 66 KV substation is set up for evacuation of power

Infrastructure Development - Power

Before After

Page 11: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity

Other Infrastructure Development

Canal Street Lights Water supply pipeline

Continuous supply of water: Water supply pipeline is provided along canal from KBC to Water Reservoir

HDPE pipeline to prevent corrosion due to high

chloride and sulphate in soil

Astronomical switches for switching automatically.

Provision of two channel switches for timely switching

Page 12: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity

Pilot scale of 4.2 MW Windmill Implemented at Solar Park

Solar – Wind Hybridization

Page 13: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity

Gujarat Solar Park - National Award Winner

Page 14: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity

Other Prestigious Awards to Gujarat Solar Park

Project Management Institute (PMI)

"Best Project of the Year Award - Medium Term Duration (1 to 3 years)"

Page 15: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity

Other Prestigious Awards to Gujarat Solar Park

National Award, 2012 by CII Category: Most Innovative Environmental Project.

Inter Solar Awards 2012 Category: Utility-Scale Projects

6th Enertia Awards 2012 Category: Power Generation Awards - Renewable Energy - Solar"

14th Power India Awards - 2012 “Special Merit Certificate" to Gujarat Solar Park Project Management Awards - 2012 “Best Project of the Year Category“ – Medium Term

Page 16: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity

Media Reviews for Gujarat Solar Park

Page 17: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity

Gujarat Solar Park at Glance

Page 18: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity

Panoramic View of Gujarat Solar Park

19

Page 19: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity

Aerial view of Gujarat Solar Park

Aerial View of Solar Project Development

Aerial View of Observatory Deck for 360 Degree View

Page 20: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity

Night View of the Observatory Deck

Page 21: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity
Page 22: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity
Page 23: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity
Page 24: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity

25

Future Generation is eyeing to you for next generation technology for their

energy security…..

So…..

Page 25: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity

Don’t hesitate

Come &

Just plug your solar project in Asia’s largest Solar Power Park

Page 26: Gujarat Solar Park World’s first Multi developer, Multi ... NH: NH 15 ... timely allocation of plots to developers . Infrastructure development - Roads Before After ... Capacity

Want to know more about Gujarat Solar Park………….