guidance for good practice in bored pile and diaphragm ... · pdf fileguidance for good...

39
Independent expertise in depth Guidance for good practice in bored pile and diaphragm wall design and construction for marine structures

Upload: docong

Post on 25-Mar-2018

240 views

Category:

Documents


6 download

TRANSCRIPT

Page 1: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Independent expertise in depth

Guidance for good practice in bored pile and diaphragm wall design and construction for marine structures

Page 2: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Contents

• Introduction

• Recent developments

• Diaphragm wall finish

• Cage detailing practice

• Tremie concreting practice

• Panel stability

• Improvements in safety

• conclusions

Page 3: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Introduction

Page 4: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Introduction

Page 5: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Introduction

Page 6: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Introduction

Page 7: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Introduction

Page 8: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Why concrete at London Gateway ?

• Illustrative design based on combi wall

• Safer installation of DWall on dry land

• Risk of driving into very dense Thanet Sand mitigated

• Dwalls will act as foundations for the gantry cranes

• Steel prices high and volatile in 2007

• Much reduced steel content in DWall

Page 9: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Design of Diaphragm Wall

• Key challenges

• Relatively high retained height (ca. 28m lowest dredge)

• Changing ground conditions

• Complex soil-structure interaction

• Tight displacement criteria - limit permanent change of gauge ca. 14.75 mm

• Complex load cases involving tidal lag, crane, vessel berthing and mooring

• Crack widths limited to 0.24 mm (SLS) in the splash zone

Page 10: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Thanet Sand Section

Soil Model One

London Clay Section

Soil Model Three W E

Transition

Soil Model Two

Page 11: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

London Gateway Port – Typical Section

Page 12: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Recent developments - deeper CFA

Soil Mech SF50 Fundex F3500

CFA pile reach limited by mast height and pull back winch capacity • Dia. 300 to 1500mm • Length max 32 metres

Page 13: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Recent developments – cased CFA secant walls

Cased CFA Rotary CFA

Page 14: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

CFA - Secant wall examples

Page 15: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Cased CFA - Secant wall examples

Page 16: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Diaphragm walls – new horizons

100m+ wall depth 1800mm thickness Verticality 1 in 300 C60 concrete

Page 17: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Rotary drum cutters

Mud Pump

Inclinometer

Guide Frame

Mud to the

desanding

plant

Mud return into the trench

after treatment

Diaphragm wall - Hydrofraise

Page 18: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Excavation verticality control

Hydraulically operated verticality control pads

Page 19: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Adjust alignment as excavation proceeds

Diaphragm wall – Grab versus Hydrofraise comparison

Theoretical position of wall

Re-excavate to correct alignment

Grab Hydrofraise

Specified limits of deviation

Page 20: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Diaphragm wall – What does a finished Dwall look like?

Page 21: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Diaphragm wall – What does a finished Dwall look like ?

Page 22: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Diaphragm wall – What can a finished Dwall look like ?

Bleed channels Mud inclusion Mattressing

Page 23: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Diaphragm wall – Latest design and execution practice?

• Careful mix design • Pre-start concrete trials • Monitor concrete

production facility • Observe good cage

detailing practice • Follow good tremie

practice • Slump and strength are

not sufficient testing eg. bleed and stability tests

Page 24: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Diaphragm wall – latest guidance on cage detailing

Page 25: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Diaphragm wall – Latest guidance on cage detailing

• Final clear horizontal distance on vertical bars at least 100 mm

• Can be reduced at laps to 80 mm

• Multiple layers of vertical bars to be lined up behind eachother

• Final clear vertical distance on horizontal bars at least 150 mm provided max aggregate is 20 mm

• 3D model may be required in areas of high congestion to avoid clashes

• Minimum distance between cages 200 mm

• Ensure nominal cover is sufficient to achieve required design cover, to satisfy durability requirements, allowing for construction tolerances

Page 26: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Diaphragm wall – Latest guidance on tremie practice

Page 27: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Diaphragm wall – Latest guidance on tremie practice

• At start of pour tremie to the panel bottom and raise <200 mm

• Prior to first discharge install effective separator ie. ball or vermiculite volume to create plug length at least 2x tremie diameter

• Discharge to all tremies simultaneously until at least 3 m depth of concrete

• Thereafter keep difference in concrete level to a minimum

• Avoid repeated raising and lowering of the tremie (surging)

• Minimum tremie embedment 3 m (may be reduced to 2 m if concrete level accurately known)

• Excessive tremie embedment to be avoided (preferably less than 10m)

• Remember the first concrete which enters the tremie will not usually reach the top of the pour

Page 28: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Trench instability

Page 29: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

How do we check trench stability?

OVERALL STABILITY

• Limit Equilibrium Method

• Finite Element Model

• Limit Analysis

T

T

G

θ

E

Ls

H

Y

X

Z

q

σy,surcharge

q‘K0

σy,poids

Ls

Z Z

Fc

dS

FoS required: 1.1 to 1.3

Page 30: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

0.0

2.0

4.0

6.0

8.0

10.0

12.0

14.0

16.0

18.0

20.0

0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00

Pressure (KPa)

De

pth

(m

)

Active Pressure Bentonite Pressure

Trench stability example

Page 31: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

0.0

2.0

4.0

6.0

8.0

10.0

12.0

14.0

16.0

18.0

20.0

0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00

Pressure (KPa)

De

pth

(m

)Active Pressure Bentonite Pressure

0.0

2.0

4.0

6.0

8.0

10.0

12.0

14.0

16.0

18.0

20.0

0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00

Pressure (KPa)

De

pth

(m

)

Active Pressure Bentonite Pressure

Add 20KPa surcharge I.0m drop in

bentonite level

Guidewall depth

Potentially unstable

Trench stability considerations

Page 32: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

How to improve trench stability in poor ground

Standard measures

• Slurry level min 1.5m higher than groundwater level

• Reinforcement continuity along guide wall sections

• L-shaped guide walls

• Careful consideration of where to position the plant

• Use short panels (single bite)

Additional measures

• Elevated guide walls (no more than 500mm)

• Increased density of support fluid

• Lower groundwater

• Ground improvement

Page 33: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Horizontal to vertical - Tandem lift D-wall

Page 34: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Temporary works rebar – very important

Additional rebar to ensure safe: • Fabrication • Transportation • On and off loading • Storage • Lifting from horizontal to vertical • Hanging • splicing

All elements require design e.g. bars, welds and connectors

Page 35: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Horizontal to vertical lift – tandem lift

Tandem lifting points @ top of z bars and cathedral bar

Page 36: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

• Were developed to splice ropes, not reinforcement bars

• Must use lowest tested strength and robust procedure due to high variation of tensile strength results

Cage splicing - Bulldog grips

Page 37: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

New cage splicing systems - SuperlatchTM

• Size of superlatch varies with cage weight

• No fingers in cage

• Expensive but safe

Page 38: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Improvements in safe working – platforms and barriers

Page 39: Guidance for good practice in bored pile and diaphragm ... · PDF fileGuidance for good practice in bored pile and diaphragm wall design and construction for marine ... •Panel stability

Conclusions

• Cast in situ concrete diaphragm and secant pile walls have many potential applications in marine works

• Diaphragm walls in particular have been used on many quay wall projects

• Plant and material developments have brought opportunities and risks

• Recently published industry guidance designed to achieve better outcomes in terms of quality and safety

• Good practice should be shared by all