GS -10 Caloosahatchee Cross-link Project
Issue Statement: Southwest Florida is faced with
impaired water bodies; a lack of stormwater
storage and groundwater recharge; and a loss of
both habitat and wildlife corridor connectivity.
Identifying Solutions: Regional partnership with
multiple public agencies/private entities to
proactively plan for:
water quality enhancements
storage solutions
recharge solutions
increased habitat
and enhanced wildlife corridor connectivity.
How did we get here?
Altering Historical Flows
Lake O
Transportation
Development
Over Drainage
Channelization
Reduced Wildlife Habitat
Environmental Impacts of Agriculture
Nutrient Loading
Drainage and Irrigation
PROJECT AREA
South Florida Environment Report
Joe
l Blv
d.
LA-MSID Boundaries
Regional Issue:Water
Environmental Impacts on
Caloosahatchee River
Watersheds have a need for improved water quality
The estuarine portion of the Caloosahatchee River has nitrogen impairment
Load Allocation to nonpoint sources (including Ag and non-MS4 stormwater) also have the same 23%
requirement.
Unbalanced seasonal freshwater flows
Regional Issue:Habitat
Development has eliminated habitat
Comprehensive effort to link parcels
Regional partners needed to make a larger, more timely impact
How do we make a change?
Regional private/public agency partnership
Proactively plan to reduce negative impacts on the Caloosahatchee River
Opportunity for Change:
GS10 Caloosahatchee Crosslink
New reservoir: Section10 Minor Impoundment
Inter-basin connection between C43, Carlos
Waterway, Bedman Creek, Hickey’s Creek,
Orange River and Caloosahatchee River
Water quality discharge flow path for C43
Reservoir
Additional flows for Greenbriar Swamp
restoring hydro periods, flows
Increased greenspace
Restored Habitat and Connectivity
GS-10 Caloosahatchee Cross-link Project
Project Benefits
Increased water storage
Improved water quality
C43 Reservoir connection
Multi-agency project
Large parcels from single owners
LocalBenefits/ Coordinating Agencies
DEP
Conformity with EPA regulations (Clean Water Act 1972)
Agencies will be compliant with the TMDL/BMAP credit program through this project
LocalBenefits/ Coordinating Agencies
South Florida Water Management District
All benefits directed to correcting the Caloosahatchee River
Impairments
Reduces Freshwater Imbalance
Reduces Nutrient Loading
Utilization of Publicly Owned Lands for Stormwater
Storage
2012 Caloosahatchee River Watershed Protection Plan
CRE143 – Greenbriar Preserve Project
CRE144 – Section 10 Project
Carlos Waterway Conveyance
LocalBenefits/ Coordinating Agencies
Lee County, 20/20, & Parks and Rec.
Increased Habitat
Increased Passive Recreation
Increase Wildlife Corridor Expansion
Increased Greenspace
LocalBenefits/ Coordinating Agencies
Lee County Natural Resources
Help toward MS4 Permit Requirements
Help toward TMDL/BMAP nutrient reduction requirements
LocalBenefits/ Coordinating Agencies
Lehigh Acres MSID
Helps reduce the 15,000 acre feet deficit
Helps restore historical headwaters of Hickey’s Creek
Helps recharge local drinking water aquifers
Helps restore historical hydro-periods in Greenbriar
Swamp
LA-MSID’s stormwater system has water quality and
conveyance features that would be beneficial to other
agencies for regional benefit
#1 Carlos Waterway
#2 Bedman Creek
#3 King Canal
#4 Easy Canal
C-43
Possible Flow Patterns
GS-10 Caloosahatchee Cross-link Project
Section 10Possible Flow Patterns
#1 Carlos Waterway
#2 Bedman Creek
#3 Greenbrier Preserve
#4 Hickey’s Creek
#5 Orange River
GS-10 Caloosahatchee Cross-link Project
HorseshoeSwalesFlow Pattern
Horseshoe Swales
GS-10 Caloosahatchee Cross-link Project
GS10 Project -Public Land Owners
Lee County School Board
Lee County Parks and Rec.
Lee County 20/20
SFWMD
LA-MSID
LIDARMap
GS-10 Caloosahatchee Cross-link Project
Aerial of Section 10
Aerial of Section 10 to Greenbriar Connector
Gre
enb
riar
GS10 Eastern Wildlife Corridor
GS10Western Wildlife Corridor
Project Timeline
2015-2016
July 2016
Funding Available
Jan. – March 2016
Legislative Session – Funding Request
Oct. 2015 - January 2016
Pre-Engineering Study
September 2015
Funding for Pre-Engineering Study
Project Timeline
2016-2018
July 2018Funding Available
March – May 2018Regular Session Pursue Funding for Construction
July 2017Funding Available
March – May 2017Regular Session Pursue Funding for Land Acquisition
Aug. 2016 – Dec. 2017Design
What We Need to Succeed
Proactive Planning
Identify and Involve Program Partners
Execute Pre-Engineering Study
Study Costs: Estimated $190,000
Available Support Documentation
Study Initiatives
Task 1 – Surveying
Task 2 – Hydrogeological and Geotechnical Analysis
Task 3 - Hydrologic Modeling Analysis
Task 4- Preliminary Engineering
Task 5 – Meetings and Documentation