STRUCTURAL DEVELOPMENT & DESIGN
OF A WAREHOUSE, SHOWROOM AND OFFICES
234 CAB Structural Design
GROUP 14
Imran Saro Gobir, Isa Isyaku Umar, Choudry Ali Haider Virk, Bhavesh Patil, Kirubel Girma Habtemariam.
Table of Contents:
1. Appendix A
3D view of structure
2. Appendix B
Load Transmission
3. Appendix C
Drawings
4. Appendix D
Methodology
Construction Programme
5. Appendix E
Calculations
6. Appendix F
Cost Estimation
234CAB Warehouse, Showroom and Office Detailed design Group 14
Introduction:
Our design comprises of a 3‐pinned portal frame structure for the warehouse. The columns and beams for it are steel I‐sections and the floor is a concrete screed flooring. As for the offices and showroom we adopted steel I‐sections for the beams and columns and for the flooring we opted to go with the option of a raised floor which comprises of glulam and steel decking as requested by the client
The warehouse spans 40mx60mx10m with no internal columns whereas the office is 5mx24mx40m on both floors and the showroom is 8mx24mx40m with 6 internal columns on all floors.
Advantages of adopting this design:
Pressure/Suction: As there will be a force of suction/pressure when the warehouse doors are open, rafter stays have been provided to prevent the rafter from failing.
Stability (warehouse): Steel cross‐bracing system has been implemented at 15m intervals on the north & south of the structure and at 20m intervals on the west and east of the structure to provide stability.
Stability (offices/showroom): The lift core will act as a form of stability system which will comprise of steel. It will also consist of masonry cladding as requested by the client. As this core will provide torsion on the other side of the building, Ancon tension system has been implemented to curb this whilst still maintaining aesthetics.
Economic benefits: by using steel beams & columns it is possible to use smaller sections in comparison to concrete & this in turn reduces cost.
Multiple trade avoidance: By constructing a vast majority of the structure in the same material there won’t be an issue of one contractor waiting for another to finish i.e. multiple trade avoidance.
Health and Safety: As the steel on site is pre‐fabricated, this reduces site activity & therefore contributes to safety on the construction site.
Also, as temporary restraints are provided during construction before the bracing is set up, this prevents the structure from collapsing.
Sustainability: As smaller sections are needed to take big loads, this has a positive impact on the cost as well as the environment.
Acoustics: The raised floors in the offices and showroom is insulated. This implementation not only help regulate temperature but also contributes towards the acoustics.
234CAB Warehouse, Showroom and Office Detailed design Group 14
Components:
Warehouse: Steel portal frame Steel columns (at 6m centres) Steel Zed purlins (at 1m centres) Steel rafter stays Concrete screed flooring Sliding doors Steel cross bracing Steel railings Insulated composite steel cladding Steel sheet roofing Blockwork (up to 3m) No internal columns
Offices/Showroom: Timber flat roof Glazed curtain walling Stability system: Steel Lift core and ancon tension system 6 internal steel columns Raised glulam floor with heavy duty carpet Sliding doors Steel columns Steel beams Reinforced concrete retaining wall
APENDIXA3dDrawings
APPENDIXBLoadtransmissionPlandrawings
0
0
(c"
D
(,'\ / 0 G) r.;,
/
{ {
I
G) (e 1r)
{
Concrete: screed flo�ring/ '
I0:::::
Warel-loose
I
G)
------------------------r--�-------------�-------�---------------
'
I I I I I
I
I '
------------------------i----------------+--------+----------------
Level 1
1 : 100
('
Prepared by Isa Umar
0o 11� 112)
{ { {
I I I
I -- --:1 I ,
--i--· 'I iMT11
�·11�! i
, -: ��· I
, I :: ,
--�' - :· -+---i 'I - I '
I , '
I'
I I ' ' ----- ---i------1
OfficeFloorPlan
'
_____ _J ______ J ' '
@ G
'HI j
-+-(i)
GIJ,lam-Covered ,-rr(i)
-·-/K\ \.:__}
��L' �./
--c�
'0
TITLE: LEVEL 1 FLOOR PLAN
234CAB GROUP 14
SCALE: 1 :100
Prepared by Isa Umar
Prepared by Isa Umar
Prepared by Isa Umar
y cp cp y cp ,_·"',
� 0
�c--4- 9 '----9 �---1� I 9 I ffi,s' ---+ ..
@ ----
(12"\ ,.::.J
�---------1----------�---------�----------t-------l I I
I I I I I I
I
I
I
I
I
9 IJ �
I ,,_----.--i
Ill I I I
d
, I I Stairs I @---+--11----------,1----------,-------------r----------T-------l•••�•_.•nm•m� tf[I] I I I
(iv----
I
I I I I I I I I I I I I I I I I I I I I 11 11 11 I J I I I I I I I I I 11 11 11 I
i t;;:;;;;:;;;;;i;�;., .. �-�-�--�- l I I I I I I I I I I I I I I I I I I I I 11 I I I I
I I I I I I I 11 11 11 11 I I I I I I I I I I I I 11 11 11 11 I I I I I I I I I I I I I I I I I I I I I I I I I """�"'•"•""'""'•'••••••••••LJ....
Precgst concrete! core braced Steel Core ! ! -' ···"" masonry between beams
c1 G l � � � �)
ShowRoom Floor
1: 50
Slldlog t' ------------B-
illiiii0:":"';";";·;···1,
11 11 I I I I I I I I I I I I I I I I I I I I I I I I I I
��-,--,---,--�l"���:::::::::::::i i I I I I I I I I I I I I I I I I I I I I I I I I 11 11 11 I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I e-.1....1-------------1-i...1,...1----_____ _...__ .. -�
l (0 �
!TITLE: SHOWROOM FLOOR PLAN 234CAB GROUP 14
Prepared by Isa Umar SCALE: 1:50
Prepared by Isa Umar
APPENDIXCMethodologyProgramme
Construction methodology
Retaining wall ‐Standard Mix Lean concrete of 5 cm which provides
uniform surface to the retaining walls concrete and to
prevent the direct contact of the concrete to the soil and cure
‐Brick layer to form a wall between the retaining wall and soil
and single coated with bitumen.
‐Reinforcement tied the at the base and wall.
‐Concrete casted.
‐Waterproofing the wall.
Show Room & Office Building
Detailed Connections for building.
(a) Shear connection to be made with 2 angles or a tab plate
4. Insert Bracings in North and Southbracings
5. Attach roof beams to columns 6. Connection between roof beams
7.Attach beam to Column 8. Install Drainage pipe on beams 9. Screw Bracings in place for rails and crosssections to go in place
10. Put the rails and cross sections in place and bolt
wielded to column (b) 2 angle wielded to beam web and field wielded to column (c) Shear bolts hold beam in place until wields are made (d) Stabilizing angle (e) Seat angle carries shear load
‐Steel slabs in are bolted and wielded to each other
and bolted to the beams.
‐Cross bracing placement in the building.
Raised floor on top of the steel slab
Engineered wood flooring by Placing spacers inside the expansion gap – the space between the wall and floor that allows for wood expansion from heat and humidity. Pre‐drill nail holes 1/4 inch from the narrow side of the plank at 1/2 inch from the wall. Continue at 6‐inch intervals for the length of each board.
Stair and Lift core
Lift
‐Lay brick masonry cladding
‐Guide Rail Brackets to steel partitions
‐Support rails and attached to the beams and masonry
‐Setup steel from the ground floor to the second
‐Floor and install Piston Jack
‐Assemble platform and pump
‐Cab and Doors
Stair
‐Place Steel column support in place
‐Put steel steps in place and bolt them to the
beams and columns then wield.
Roof (Timber flat roof)
‐Tape Vapour barrier on the steel deck
‐Tape the Insulation on top of the Vapour barrier on the steel deck.
‐Put the roof membrane in place and the on top of the timber beams.
Cladding and Doors
Tie the Aluminum excursions to the Rafters and
attach them to the beams and columns.
Warehouse
‐Use all terrain crane to lift and put the pre‐fabricated
steel columns and horizontal steel supports in place so
they can be bolted to the Base plate.
‐Lift and put the rafters of the 3 pinned portal frame in
and bolt them together with each other and place the
Eaves haunch in place to tie them with the columns.
‐Place and tie the vertical steel piles on the top of the
rafters and bolt them together
‐Put the purlins, side rails in place and the cross bracing on top of the steel piles and bolt the down.
Lay and bolt steel roof sheeting on top of the
cross bracing and rafters and bolt them down.
‐Mix and cast concrete of a large bulk with a big mixer
while a boom operated laser machine makes the floor
level.
‐Lay brick masonry between steel columns to 3 meters
by using a cement/aggregate mix.
‐Install the Insulated composite cladding around the warehouse starting from the top end of the brickwork 10m by 6m for the ware house doors.
‐Install the pre‐fabricated sliding doors.
Glazed curtain wall bolted
ID Task Mode
Task Name Duration Start Finish Predecessors Resource Names
1 Warehouse, Office and ShowroomConstruction
138 days Wed 14/12/16
Fri 23/06/17
2 Site preparation 17 days Wed 14/12/1Thu 05/01/17
3 Isolation of services 2 days Wed 14/12/1Thu 15/12/16 Site surveyor
4 Marking boundries and fencing
2 days Fri 16/12/16 Mon 19/12/16
3 Site Clearance gang
5 Transport of equipment to site
1 day Tue 20/12/16
Tue 20/12/16
4 Site Clearance gang
6 Pull up trees and shrubs 4 days Wed 21/12/1Mon 26/12/15 Site Clearance gan
7 Setup site offices 1 day Tue 27/12/16Tue 27/12/166 Site Clearance gan
8 Strip topsoil and site cleaning 4 days Wed 28/12/16
Mon 02/01/17
7 Site Clearance gang
9 Grading general area 1 day Tue 03/01/17Tue 03/01/178 Excavation gang
10 Transport materials to site 2 days Wed 04/01/17
Thu 05/01/17
9 Site Clearance gang
11 Groundworks 27 days Fri 06/01/17 Mon 13/02/1
12 Excavate topsoil 4 days Fri 06/01/17 Wed 11/01/110 Excavation gang
13 Compact existing ground to required height
2 days Thu 12/01/17
Fri 13/01/17 12 Backfill gang
14 Place formwork for piles 1 day Mon 16/01/1Mon 16/01/113 Formwork gang
15 Pour and vibrate concrete 1 day Tue 17/01/17Tue 17/01/1714 Concrete gang
16 Insert pile caps 3 days Wed 18/01/1Fri 20/01/17 15 Concrete gang
17 Cure concrete 7 days Mon 23/01/1Tue 31/01/1716 Concrete gang
18 Place formwork for concrete slab
1 day Wed 01/02/17
Wed 01/02/17
17 Formwork gang
19 Pour and vibrate concrete 1 day Thu 02/02/17Thu 02/02/1718 Concrete gang
20 Cure concrete 7 days Fri 03/02/17 Mon 13/02/119 Concrete gang
21 Portal frame 30 days Tue 14/02/17Mon 27/03/1
22 Erect columns 6 days Tue 14/02/17Tue 21/02/1720 General workorce
23 Attach bracings to columns 3 days Wed 22/02/1Fri 24/02/17 22 General workorce
24 Attach roof beams to columns 2 days Mon 27/02/1Tue 28/02/1723 General workorce
25 Insert drainage pipe 1 day Wed 01/03/1Wed 01/03/124 Drainage gang
26 Attach rafters to coloumns 2 days Thu 02/03/17Fri 03/03/17 25 General workorce
27 Insert top bracings 2 days Mon 06/03/1Tue 07/03/1726 General workorce
28 Lay roofing material and bolt 3 days Wed 08/03/1Fri 10/03/17 27 General workorce
29 Lay 150mm blockwork 3 days Mon 13/03/1Wed 15/03/128 Brickwork gang
30 Lay sidewall sheet material 3 days Thu 16/03/17Mon 20/03/129 General workorce
31 Backfill 5 days Tue 21/03/17Mon 27/03/130 Backfill gang
32 Retaining wall 24 days Tue 28/03/17Fri 28/04/17
33 Excavate 2 days Tue 28/03/17Wed 29/03/131 Excavation gang
34 Drain Soil 1 day Thu 30/03/17Thu 30/03/1733 Excavation gang
35 Grade and compact base layer
2 days Fri 31/03/17 Mon 03/04/17
34 Compaction gang
36 Pour blinding layer 1 day Tue 04/04/17Tue 04/04/1735 Concrete gang
37 Cure blinding layer 1 day Wed 05/04/1Wed 05/04/136 Concrete gang
38 Construct formwork for base 2 days Thu 06/04/17
Fri 07/04/17 37 Reinforcement gang
39 Place formwork for reinforcement
1 day Mon 10/04/17
Mon 10/04/17
38 Formwork gang
40 Pouring and compacting of concrete by vibration
1 day Tue 11/04/17
Tue 11/04/17
39 Concrete gang
41 Remove formwork 1 day Wed 12/04/17
Wed 12/04/17
40 Formwork gang
42 Cure concrete 5 days Thu 13/04/17
Wed 19/04/17
41 Concrete gang
43 Construct footing steel rebars25mm diameter
1 day Thu 20/04/17
Thu 20/04/17
42 Reinforcement gang
44 Place footing steel rebars 25m1 day Fri 21/04/17 Fri 21/04/17 43 Reinforcement ga
45 Place formwork for reinforcem1 day Mon 24/04/1Mon 24/04/144 Formwork gang
46 Pouring and compacting of con1 day Tue 25/04/17Tue 25/04/1745 Concrete gang
47 Cure concrete 1 day Wed 26/04/1Wed 26/04/146 Concrete gang
48 Remove formwork 1 day Thu 27/04/17Thu 27/04/1747 Formwork gang
49 Backfilling 1 day Fri 28/04/17 Fri 28/04/17 48 Backfill gang
50 Office 40 days Mon 01/05/1Fri 23/06/17
51 Marking showroom foundation2 days Mon 01/05/1Tue 02/05/1749
52 Excavate 5 days Wed 03/05/1Tue 09/05/1751
53 Install H‐Beams 2 days Wed 10/05/1Thu 11/05/1752
54 Erect screed protection 2 days Fri 12/05/17 Mon 15/05/153
55 Fix rebar and shuttering 1 day Tue 16/05/17Tue 16/05/1754
56 Construct formwork for foundation
4 days Wed 17/05/17
Mon 22/05/17
55
57 Place formwork for foundation2 days Tue 23/05/17Wed 24/05/156
58 Pouring and compacting of concrete by vibration
1 day Thu 25/05/17
Thu 25/05/17
57
59 Cure concrete 7 days Fri 26/05/17 Mon 05/06/158
60 Insert prefabricated columns 3 days Tue 06/06/17
Thu 08/06/17
59
61 Lift and insert precast floor sla 6 days Fri 09/06/17 Fri 16/06/17 60
62 Lift and insert prefabricated roof
3 days Mon 19/06/17
Wed 21/06/17
61
63 Final inspection 2 days Thu 22/06/17Fri 23/06/17 62
Site surveyor
Site Clearance gang
Site Clearance gang
Site Clearance gang
Site Clearance gang
Site Clearance gang
Excavation gang
Site Clearance gang
Excavation gang
Backfill gang
Formwork gang
Concrete gang
Concrete gang
Concrete gang
Formwork gang
Concrete gang
Concrete gang
General workorce
General workorce
General workorce
Drainage gang
General workorce
General workorce
General workorce
Brickwork gang
General workorce
Backfill gang
Excavation gang
Excavation gang
Compaction gang
Concrete gang
Concrete gang
Reinforcement gang
Formwork gang
Concrete gang
Formwork gang
Concrete gang
Reinforcement gang
Reinforcement gang
Formwork gang
Concrete gang
Concrete gang
Formwork gang
Backfill gang
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F6 12 Dec '16 02 Jan '17 23 Jan '17 13 Feb '17 06 Mar '17 27 Mar '17 17 Apr '17 08 May '17 29 May '17 19 Jun '17 10 Jul '17
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
Page 1
Project: 234 Gantt.mppDate: Wed 14/12/16
APENDIXDCalculations
APPENDIXECostestimate
ESTIMATING AND COSTING REPORT
GROUP 14 234 CAB
WAREHOUSE & SHOWROOM – TECHNICAL PHASE Calculated by – Bhavesh Patil
The Estimating and Costing Report for construction of Warehouse, showroom and office. The pricing of elements and materials includes the cost of construction and the labour costs according to ‘Spon’s Budget Estimating Handbook 2nd Edition’, ‘UK Building Costs Blackbook’ and ‘www.britishsteel.co.uk’.
Component Quantity Material Volume (m3)
Area (m2)
Mass (tonne)
Cost
1 Common Brickwork BS3921 PC £125/1000 in cement
mortar 1:3
No. Of
Bricks
Masonry £/m2
Office Brickwork 6005 86 400 1.557 60 24,750 Warehouse 8106 116 540 9.720 60 33,400
2 Warehouse roof cladding. G.S profiled cladding PVF2 coated
(Insulated)
45 Galvanized Steel
528 2640 42.24 35 £/m2
92,400
3 Timber and Asphalt coat covering flat roof
‐ Timber Asphalt
0.495 960 ‐ 45 £/m2
43,200
4 Steel roller shutters 2 Mild Steel ‐ 120 ‐ 150 £/m2
18,000
5 Purlins 10 Mild Steel 0.462 0.0077 8.155 860/t 7013.3
6 Office Beam 686x254x170
36 Mild Steel 27.843 ‐ 73.5 850/t 62,475
7 Office Beam 533x210x82
45 Mild Steel 29.736 ‐ 29.592 850/t 25,153.2
8 Warehouse Rafter Beam 914x305x253
10 Mild Steel 75.15 ‐ 590 850/t 501,500
9 Warehouse Columns 356x406x634
28 Mild Steel 19.84 ‐ 156 880/t 137,280
10 Glazed Curtain Wall ‐ Glass ‐ 1584 ‐ 118.73 £/m2
188,068.32
11 Office Timber Flooring ‐ Timber ‐ 1920 ‐ 67.88 £/m2
130329.6
12 Warehouse Wall Cladding (insulated)
Galvanized Steel
‐ 816 ‐ 35 £/m2
28,560
13 Office Columns 305x305x240
54 Mild Steel ‐ ‐ 77.76 880/t 68,428.8
14 Lift 2 ‐ ‐ ‐ ‐ 50000/floor
300,000
15 Mechanical Installations Warehouse
‐ ‐ ‐ 2400 ‐ 25 £/m2
60,000
Sa1
C…
16 Mechanical Installations Office
‐ ‐ ‐ 2880 ‐ 80 £/m2
230,400
Total Costing 1,950,958.22
17 Contractors preliminary cost 10% 195,095.822
18 Contractors overhead and profit
10% 214,605.404
19 Contingency sum 10% 236,065.95
20 Total Cost of Construction £ 2,596,725.396