ground water remediation system and engineered …

166
)00004 FINAL DESIGN / (REPORT & APPENDIX A thru E) GROUNDWATER REMEDIATION SYSTEM AND ENGINEERED LANDFILL CLOSURE MOTOR WHEEL DISPOSAL SITE LANSING, MICHIGAN Prepared by: Sharp and Associates, Inc. 982 Crupper Avenue Columbus, Ohio 43229 December 23,1996 Revised May 1,1997

Upload: others

Post on 11-Jun-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

)00004

FINAL DESIGN /(REPORT & APPENDIX A thru E)

GROUND WATER REMEDIATION SYSTEMAND ENGINEERED LANDFILL CLOSURE

MOTOR WHEEL DISPOSAL SITELANSING, MICHIGAN

Prepared by:

Sharp and Associates, Inc.982 Crupper AvenueColumbus, Ohio 43229

December 23,1996Revised May 1,1997

Page 2: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

T A B L E O F C O N T E N T S

1.0 INTRODUCTION............................................................................................. 11.1 General Background and Site History........ . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11.2 Previous Studies....................................................................................... 41.3 Record of Decision . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41.4 Report Organization .................................................................................. 6

2.0 LANDFILL CAP...............................................................................................72.1 Landfill Cap Description ............................................................................ 7

2.1.1 Cap System Components . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82.1.2 North Slope Reconstruction Area. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 102.1.3 Health and Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 102.1.4 Project Organization and Schedule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 102.1.5 Cost Estimate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

2.2 Landfill Cap Drawings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 122.3 Landfill Cap Spec i f ica t ions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12

3.0 GROUNDWATER REMEDIATION SYSTEM.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 133.1 Glacial Aquifer Groundwater Remediation System Description . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

3.1.1 Groundwater Remediation Stra tegy. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 133.1.2 Basis of Design. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 133.1.3 Applicable or Relevant and Appropriate Requirements............................ 183.1.4 List of Major Equipment ................................................................ 183.1.5 Cost Estimate ... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19

3.2 Groundwater Remediation System Drawings. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 203.3 Groundwater Remediation System Specifications.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 233.4 Groundwater Remediation System Permits. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23

3.4.1 National Pollution Discharge Elimination System (NPDES) Permit . . . . . . . . . . . . 233.4.2 Air Discharge Permit.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 233.4.3 Railroad Right-of-Way Issues........................................................... 233.4.4 City of Lansing Right-of-Way Issues.................................................. 23

3.5 Saginaw Groundwater Remediation System ................................................... 24

4.0 PROJECT SCHEDULE.................................................................................... 25

5.0 REFERENCES............................................................................................... 27

95RPT.DOC

Page 3: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

L I S T O F F I G U R E S

Figure 1-1 Site Area Map ......................................................................................... 2Figure 1-2 Site Map ................................................................................................ 3Figure 3-1 Groundwater Extraction Zones................................................................... 14Figure 3-2 Groundwater Process Flow Diagram............................................................ 15

L I S T O F T A B L E S

Table 1-1 ROD Cleanup Criteria ...............................................................................5Table 3-1 Groundwater System Design Concentrations .... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

A P P E N D I C E S

A. Operations and Maintenance ManualB. Construction Quality Assurance PlanC. Health and Safety PlanD. Remedial Action PlanE. Landfill Drawings

JF..... Boring LogsG. Drainage Layer CalculationsH. Slope Stability CalculationsI. Landfill Technical SpecificationsJ. Extraction Well Boring PlanK. Groundwater Modeling InformationL. Groundwater Remediation System DrawingsM. Sizing CalculationsN. PLC Control LogicO. Groundwater Remediation System SpecificationsP. Draft NPDES PermitQ. Air Emissions EvaluationR. Railroad Right-of-Way Application

95RPT.DOC

Page 4: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 1 INTRODUCTION

The Motor Wheel Disposal Site Group has contracted with Sharp and Associates, Inc. (SHARP) andHWH Engineers (HWH) to prepare the Draft Final Design for the Motor Wheel Disposal Site(MWDS). This design is for the landfill cap and for the groundwater remediation system that addressesthe glacial aquifer plume and the potential flows from the Saginaw aquifer plume. These systems arebeing designed in order to comply with the Record of Decision (ROD) (September, 1991) and theRemedial Design Consent Order, and accompanying statement of work.

1.1 GENERAL BACKGROUND AND SITE HISTORY

The MWDS is a 24-acre property located at 1401 Lake Lansing Road on the northeast edge of the Cityof Lansing, Michigan. The site lies in the NE 1/4 of the SW 1/4 of Section 3 in Lansing Township(T4N, R2W), Ingham County, Michigan (Figure 1-1, page 2). The MWDS and surrounding propertiesare illustrated in Figure 1-2 (page 3). The property was used by Motor Wheel Corporation as adisposal site for industrial wastes from 1938 until about 1978 (US EPA, 1991). The types of disposedwastes included solid and liquid industrial wastes, such as paints, solvents, liquid acids, caustics, andsludges. Wastes were disposed of on the property in tanks, barrels, seepage ponds, and open filloperations (US EPA, 1991).

Between 1970 and 1982, at least three cleanup actions were initiated, which resulted in the excavationand off-site disposal of waste materials (Hunter/Keck Environmental Services [Hunter/Keck], 1990).In 1970, the Michigan Department of Natural Resources (MDNR) requested that the Motor WheelCorporation remove solid wastes, paint sludges, and oils from seepage pond areas for disposal off-site.Some of the excavated materials were disposed off-site and the former pond areas were backfilled (USEPA, 1991). Three 10,000-gallon tanks, their contents and contaminated soil, and fill surrounding thetanks were removed and disposed off-site in December, 1982. An unknown number of drums werealso disposed of off-site at this time (US EPA, 1991).

In 1978, MSV Associates acquired the property and began open-pit sand and gravel mining. Themining operations exposed some of the buried industrial wastes. The exposed materials weresubsequently excavated, stockpiled on the western part of the site, and covered with clay (US EPA,1991).

The site was placed on the National Priorities List on October 4, 1986 (50 FR 41015). On June 26,1987, Motor Wheel Corporation, W.R. Grace & Co. (Grace), and The Goodyear Tire & RubberCompany (Goodyear) signed an AOC agreeing to conduct a Remedial Investigation (RI) and FeasibilityStudy (FS) at the MWDS (US EPA, 1991). Following USEPA's ROD in September, 1991, Goodyear,Grace, Textron, Inc., and the Lansing Board of Water and Light entered into a consent agreement toconduct the Remedial Design.

Site gravel/sand mining operations were discontinued in 1987. MSV Associates is the current owner ofthe property. The site is presently inactive (US EPA, 1991).

Final Design ReportHotflr Wheel Disposal SiteSharp and Associates. Inc95rpt.doc/rev. 4/30/97

Page 5: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

ThuDec19 17:41 1996Scale 1:62,500 (at center)

1 Miles

Secondary SR/Road/Hwy Ramp

Major Connector

State Route

Interstate/Limited AccessUS Highway

SITE LOCATION MAPMOTOI nan. DISPOSAL snr

UNSINC. MICHIGAN

Page 6: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

»/;•••//.-v/'-.rv"

IN>

If! DDODDa ? Project Rt'venC« ^5104-16

SITEMAP

if!!. MOTOR WIIEFL DISPOSAL SITELANSING. MICHIGAN

Diem MOTOR WHFri PRP GROUP

SHARPAND ASSOCIATES, INC.982 Crupper Avenue

Columbus, Ohio 4J229

Page 7: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

1.2 PREVIOUS STUDIES

In accordance with the AOC, an RI for the site was conducted by Hunter/Keck. The results of the RIwere summarized in a report dated February 8, 1990, and titled, Remedial Investigation Report, MotorWheel Disposal Site, Lansing, Michigan. An FS was conducted by ENSR Consulting and Engineering(ENSR). The results of this study were summarized in a report titled, Final Draft Feasibility StudyReport for Motor Wheel Disposal Site, dated May, 1991. The Declaration for the Record of Decision(ROD) was signed by the US EPA on September 30, 1991. An investigation of the Saginaw aquifer atthe MWDS was conducted by ENSR, and the results summarized in a report titled, Saginaw AquiferInvestigation for the Motor Wheel Disposal Site, Lansing, Michigan, Consultants Report, dated April,1992, Document No. 3144-02-574. Another investigation of the Saginaw aquifer at the MWDS wasconducted by Fishbeck, Thompson, Carr and Huber (FTC&H), and the results summarized in a reporttitled, Saginaw Aquifer Investigation Report for Motor Wheel Disposal Site, Lansing, Michigan,Consultants Report, dated March 1995. Additional investigations were performed and a Predesign wasdeveloped by FTC&H. These activities are summarized in Final Additional Studies/Predesign Report,1996.

1.3 RECORD OF DECISION

The ROD for the first operable unit at the MWDS was signed on September 30, 1991. The firstoperable unit included the waste mass and the groundwater contamination in the perched and glacialaquifers at the MWDS. The groundwater contaminants of concern, as determined by the RI, and therisk and toxicity assessments, included the volatile organic compounds (VOCs):

1,1 -Dichloroethene (1,1 -DCE) Chloromethane1,2-Dichloroethane (1,2-DCA) Ethylbenzene1,2-Dichloroethene (1,2-DCE) Methylene Chloride2-Butanone Naphthalene2-Hexanone Tetrachloroethene (PCE)4-Methyl-2-pentanone Trichloroethene (TCE)Benzene TolueneChloroethane Vinyl Chloride (VC)Choroform Xylenes, Total

The semivolatile organic compound (SVOC) contaminants of concern included bis(2-ethylhexyOphthalate and 2,4,5-trichlorophenol, and the inorganic contaminants of concern includedammonia nitrogen, chloride, fluoride, iron, lead, nitrate, sulfate, and zinc.

The ROD cleanup criteria for the respective constituents are presented in Table 1-1 (page 5). In June1995, Michigan amended the Michigan Environmental Response Act, Act No. 307 of 1982 andincorporated the amended act into the Natural Resources and Environmental Protection Act, Act No.451 of 1994. This new legislation included changes in the cleanup standards that were previously citedas Applicable or Relevant and Appropriate Requirements (ARARs) in the ROD.

Final Design ReportMotor Wheel Disposal SiteSharp and Associates, Inc95rpi.doc/rev. 4/30/97

Page 8: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Table 1-1ROD Cleanup Criteria

Motor Wheel Disposal SiteLansing, Michigan

CONTAMINANTS

VOCs1,1-DichJoroethene1.2-Dichloroethane1 ,2-Dichloroethene2-Butanone2-Hexanone4-Methyl-2-pentanoneBenzeneChloroe thaneChloroformChloromethaneEthylbenzeneMethylene ChlorideNaphthaleneTetrachloroetheneTrichioroetheneTolueneVinyl ChlorideXylenes (total)

Semi - VOCsBis(2-ethylhexyl)phthalate2.4.5-Trichlorophenol

InorganicsAmmoniaChlorideFluorideIronLeadNitrateSulfateZinc

MEANCONC.

3.062.6

258.385.75

9.56.9

11.48

4.933.94.136.752.8133.4342.7585.1038.13

19.3622.19

-401,47022.2863,190

161.851432,8002.600

MAXCONC.

77

1,700114341282309.75

17010165

380380790150

12225

453,0001,380,000101.000

3001,249.6001,700,000

10.000

MCL

7570---5

-

-

5

•>-

--

--

4,000--

-10.000

MCLG

7070

--0-------0

0-

--

.-

4,000--

10.000

SMCL

--

.----

-

.

--

--

-250,0002,000300

-

250,0005.000

Exceeded 1 x10"* LifetimeIncrementalCancer Risk

YESYESNANANANAYESNANANONANANAYESYESNA

YESNA

YESYES

NANA

NO*NANAN. .NANA

MI. Act307

TypeB

70.470

4005

4001.09.06.03.0

700**5.0400.73.0

800**0.02300

T

700

34.000250.0002.0003005

10.000250.000

1.000

MDL

111555111111511111

55

--3-

20All concentrations inMCL: Maximum Contaminant LevelMCLG: Maximum Contaminant Levels GoalsSMCL: Secondary MCLMDL: Method Detection Limit(-): Not established

NA: No slope factor available for these compounds, therefore cancer risk was not calculated.

* Exceeded Hazard Index (HD of 1 for non -carcinogenic effects in adults and children** Michigan Act 307 Type B Secondary Maximum Contaminant Level or taste/odor threshold value, if lower than

lexicologically based standard.

Note: The cleanup standards are being re-evaluated.

Final Design ReportMotor Wheel Disposal SiteSharp and Associates. Inc95rpt.doc/rev. 4/30/97

Page 9: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

The major elements of the remedial alternative selected in the ROD include:

• Installation of an engineered landfill cover system over the disposal area.

• Backfilling to cover exposed fill areas and to establish an acceptable slope in the excavatedarea of the site, for extension of the cover system.

• Extraction of contaminated groundwater from the perched zone and the glacial aquifer, andtreatment of the groundwater by air stripping.

• Site deed restrictions to limit development and land use, and to prevent installation ofdrinking water wells or other intrusive activities at the site.

1.4 REPORT ORGANIZATION

The Final Design Report is divided into five sections: Introduction, Landfill Cap. Glacial AquiferGroundwater Remediation System, Project Schedule, and References. The Operations andMaintenance Manual is located in Appendix A. The Construction Quality Assurance Plan (QAPP) islocated in Appendix B. The Health and Safety Plan is located in Appendix C. The Remedial ActionPlan is located in Appendix D.

Final Design ReponMotor Wheel Disposal SiltSharp and Associates, Inc95rpt.doc/rev. 4/30/97

Page 10: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 2 LANDFILL CAP

2.1 LANDFILL CAP DESCRIPTION

An engineered cap and landfill cover system will be installed to provide a low-permeability, highevapotranspiration, barrier to the subsurface materials. The cap and cover system will encompassapproximately 13 acres, as shown the construction drawings (in Appendix E).

In deriving the conceptual cap design included in this submirtal, the boring logs used originally toestimate the areal extent of the waste boundary were revisited because the waste boundary appeared tocontradict strong topographical clues as to the historic manipulation of subsurface materials. A smallarea at the extreme southern edge of the estimated waste extent was also reevaluated. All examinedboring logs and a site map showing their location are included in Appendix F.

Specifically, boring logs LC-11 through 16 and LC-42 were looked at in the western portions of thelandfill, near the railroad tracks. The logs of LC-13, 16 and 42 showed no indications of any wastematerial, or the types of assumed waste materials identified in other borings, previously interpreted tobe indicative of landfilling, yet the previous extent of waste estimate either included these borings, orwas bordered by one or more of these borings. The assumed waste materials identified in theremaining borings include a 0.2 foot layer of brick fragments included in a silty sand in LC-14, a 2.1foot layer of cinders and gravel mixed with a silty sand from LC-11, and occasional coal fragmentsbetween 5 and 9 feet deep in LC-12. These materials, at these depths, located in and around anabandoned railroad track, are not necessarily indicative of historic landfilling, but may find their originin the types of material used to construct the railroad embankment itself, and/or a possible result ofrailroad operations. This hypothesis is further supported by the fact that the readjusted extent of wastein this area better coincides with the toe of the slope extending from the landfill property, and the legalboundary of the landfill property itself.

Similarly, the boring logs for MW13D, MW24, and LC-65 were evaluated, along the extreme southerntip of the waste area. The logs for the two monitoring wells indicated no waste materials, yet theselocations were shown well within the extent of waste. A fill/slag mixture included in a silty sand wasidentified up to the 4.5 foot depth in LC-65. The extent of waste was reinterpreted to exclude thesethree borings.

The net effect of the reinterpretation of the extent of waste is to decrease its total area by approximately2/3 of an acre.

The final cap configuration has been derived through careful consideration of the following designfactors:

• 3 % minimum cover slope;• 25% maximum cover slope;• minimization of waste excavation;• minimization of import of fill material; and• maximization of runoff to the gravel pit remnants.

Final Design ReportMotor Wheel Disposal SiteSharp and Associates. Inc95rpt.doc/rev. 4/30/97

Page 11: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

2.1.1 Cap System Components

The overall strategy of the landfill cap and cover system is to reduce vertical migration of water intosubsurface materials. The cap and cover system will be comprised of multiple components, including:

• Lower unclassified fill layer;• Clay mineral resource barrier layer;• Drainage layer;• Geotextile;• Upper unclassified fill layer;• Topsoil layer;• Vegetation;• Storm water diversion;• Soil erosion control; and• Gas venting.

The following section provides a description of each cap component as well as the basis for its design.This information is communicated in detail in the construction drawings. Technical Specifications, andConstruction Quality Control Plan.

Lower Unclassified Fill Layer Unclassified mineral fill will be used to achieve the grades necessary toachieve proper site drainage and slope stability. The thickness of this layer will range from 0 to 5 feet.

Clay Barrier A minimum of three feet of compacted clayey soils will be placed over the subsurfacematerials. Clayey soils shall consist of material classified as CL or CH under the United SoilsClassification System (USCS) and, when compacted in-place on the landfill to 95% of the MaximumStandard Proctor Density, shall have a permeability of no greater than 1 x 10~7 cm/s as determined bythe ASTM method for falling head permeability. It shall be placed in lifts no greater than 8 inches(before compaction).

Drainage Layer A minimum of 6 inches of an engineered aggregate will be placed on top of the claymineral resource. It will serve as the drainage layer and part of the frost protection layer. Appendix Gcontains a technical memorandum detailing the engineering justification for using a 6 inch thickdrainage layer in lieu of previously-proposed, thicker layers. The drainage layer material shall have apermeability of no less than 1 x 10"' cm/s as determined by ASTM Method D-2434 (constant headpermeability test).

Geotextile A non-woven geotextile will be placed between the drainage layer and the upperunclassified fill layer to prevent fines from migrating into the drainage layer and impeding lateralsubsurface drainage.

Upper Unclassified Fill (Frost Protection) Layer A minimum of 13 inches of unclassified mineral fillwill be placed on the geotextile. This layer, in combination with the drainage layer, geotextile, andtopsoil layer will provide a minimum of 25 inches of frost protection for the surface of the clay mineralresource barrier layer.

Topsoil Layer Six inches of resoiling medium will comprise the topsoil layer, which will be placedover the upper unclassified fill layer. The resoiling medium will be capable of sustaining a permanent,diversified mixture of grasses.Final Design Report gMotor Wheel Disposal SiteSharp and Associates. Inc95rpt.doc/rev. 4/30/97

Page 12: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Vegetation A permanent, diversified, self sustaining vegetative stand comprised of a mixture of grasseswill be established to maximize evapotranspiration, minimize erosion, and minimize desiccationcracking of the topsoil layer. The seeding, fertilizing, and mulching specification for the vegetativelayer is based on the United States Department of Agriculture Soil Conservation Service's Michiganoffice Technical Guide for Critical Area Planning, Publication 342-1. Two different seed mixtures willbe used. One will be for the milder slopes of the landfill area itself. The other mixture, featuring asignificant portion of crown vetch, will be applied to the north slope reconstruction area.

Storm Water Diversion The majority of storm water will be directed to the existing impoundment tothe north of the site, in the remnants of the former quarrying operation. Storm water conveyances havebeen designed to divert runoff generated by a 25-year storm event.

Soil Erosion Control Soil erosion control measures will be implemented in accordance with theMichigan Soil Erosion and Sedimentation Control Act, Public Act 347 of 1972. Permanent andtemporary soil erosion control will include seeding, mulching, silt fences, and straw bale filters, asshown the construction drawings and included in the Technical Specifications. A Soil Erosion AndSedimentation Pollution Control Application will be submitted to the Ingham County DrainCommissioner, in order to procure a permit.

Gas Venting The objective of passive gas venting is to prevent gas build-up beneath the cap materials,minimizing the potential for horizontal migration. Passive vertical gas vents will be installed at amaximum frequency of 1 vent per acre, or a maximum total of 13 vents. The vents will consist of 4-inch slotted PVC or high density polyethylene pipe, as shown the construction drawings. The ventswill placed in 12-inch-diameter borings augured to approximately 10 feet above the bottom of thewaste, maximizing the amount of waste exposed to the screened vent interval, while minimizing thepotential to penetrate through the bottom of the landfill. The annular space between the pipe andboring walls will be backfilled with pea gravel or equivalent granular material. The vents will becapable of being converted to active vents if future events warrant. A 4-foot long bentonite plug willbe placed between the borehole wall and vent pipe to hinder short circuiting of ambient air if a vacuumis applied to the vent. Solid-walled riser pipe will extended through the subgrade and cap to a height of6 feet above the final cover. The top of the riser pipe will be turned downward 180 degrees to preventrainwater from entering the vent. The gas vents will be constructed in such a way so that they could beconverted to soil vapor extraction points sometime in the future.

Frost-Protection The Predesign Report cites the Michigan Department of Labor, Bureau ofConstruction Codes report (1976) as stating that the average annual frost penetration in Ingham Countyis 25 inches beneath the surface. The drainage layer, geotextile, upper unclassified fill, and topsoillayer will amount to at least 25 inches of frost protection for the top of the 36-inch clay barrier layer.

Security Measures Fencing and warning signs will be installed to prevent vandalism and unauthorizedaccess to the site. A 6-foot-tall, chain link fence will be installed around the limits of waste. Threestrands of barbed wire will be placed on top of the fence, and a double, 12-foot-wide swing gate will beplaced at the entrance to the access road. Warning signs will be placed at 200-foot intervals along thefence and at the gate designating the site as a restricted area undergoing remedial action. A telephonenumber will be identified on the signs for additional information. Additionally, a reinforced pipe gatewill be provided between the fence and the main entrance from Lake Lansing Road.

Final Design RcponMotor Wh-el Disposal SiteSharp and Associates. Inc95rpt.docirev. 4/30/97

Page 13: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Health and Safety The Health and Safety Plan covering construction activities is included as AppendixC.

2.1.2 North Slope Reconstruction Area

The north slope will be reconstructed to final grade of 3:1 (H:V), using only materials presently outsidethe limits of waste placement in the north slope area and imported fill! In essence the north slopereconstruction is a separate construction element. The existing materials of the north slope area havesufficient grain size and shear strength to achieve a minimum safety factor of 3 for a 3:1 slope, asdemonstrated by the calculations included in Appendix H. The minimum suggested safety factor forthis type of embankment is 1.5 to 2. Imported fill for the north slope will have to meet rigoroustextural and shear strength requirements, as detailed in the Technical Specifications, to maintain thestability of the slope. All embankment on the north slope will be compacted to 95% of the maximumStandard Proctor Density. To minimize potential erosion, two rows of post construction silt fence willbe installed and a seeding mixture specially recommended for critical planting on slopes will be used.

2.1.3 Health and Safety

A site Health and Safety Plan (HASP) has been created following the requirements and guidelines ofCFR 190.120. It prescribes procedures designed to minimize threats to human health and safety duringimplementation of the landfill remedy. The HASP is included as Appendix C.

2.1.4 Project Organization and Schedule

A remedial Action Work Plan, identifying key project personnel responsibilities, as well as a proposedproject schedule, is included as Appendix D.

2.1.5 Cost Estimate

The preliminary cost estimate for the construction of the landfill cap is $ 3,279,973. The estimatedannual operating costs are S 32,200. A breakdown of the construction and operating costs are providedbelow. All earthwork quantities are in-place. Estimated unit prices are based on prices from similarlyscoped projects as well as published construction cost estimating resources. It is assumed that allconstruction takes place in one season.

Final Design Report i QMotor Wheel Disposal SiteSharp and Associates, Inc95rpl.doc/rev. 4/30/97

Page 14: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Estimated Engineered Cap Construction CostsTask Description

Mobilizationjob trailer/General requirements surveyorGeneral requirements PPE

Site Demolition (Fence)Clearing and GrubbingSilt FenceCulvert AbandonmentRock Channel ProtectionWaste ReconsolidationBaseline Grading: North Slope StructuralEarthwork (cut and fill at 95 % compaction)Baseline Grading: North Slope StructuralEarthwork (imported embankment @ 95%)Baseline Grading:Base Grading Earthwork (cutand fill at 92 % compaction)Baseline Grading: Base Grading of Waste (cutand fill not including reconsolidation areas)Baseline Grading: Base Grading Embankment(imported embankment @ 92%)Clay CapDrainage LayerGeotextile MaterialSettlement PlatformsUpper unclassified fill for frost protection(imported embankment @ 92%)Re-soiling material embankmentFinal grade, seed, mulch (landfill area)Final grade, seed, mulch (north slope)Gas Vents

Chain link FencePipe gate and swing gateUnderdrain PipingExtraction well pipingElectrical ConduitLandfill Construction SubtotalLandfill Construction Total with 15%ContingencyLandfill EngineeringConstruction Administration

Unitslump

Isday

per dayIfacIfIfsycycy

cy

cy

cy

cy

cycysyeacy

cysysy

If drilled

IfeaIfIfIf

IsIs

Unit Cost | Quantity$50,000.001 1$5,000.00$1,000.00

$20.00$2.00

$5,000.00$5.00

$50.00$55.00$25.00$6.00

$7.00

$5.00

$20.00

$6.50

$11.00$25.00$4.20

$1,100.00$7.00

$10.50$0.55$3.00

$30.00

$15.00$2,000.00

$7.00$15.00

5

165

6502,000

154,700

70600

5,0007,000

10,800

45,000

1,000

8,100

63,00011,00064,000

2323,000

13,20072,60024.200

560

4,0003

4,400535

1,070

Total:

Total$50,000

5,00065,00013,0004,000

75,00023,500

3,50033,000

125,00042,000

75,600

225,000

20,000

52.650

693,000275,000268,80025,300

161,000

138,60039.93072,60016,800

60.0006.000

30,8008,0255.350

$2.613.455$ 3,005,473

$ 80,000$ 194,500

$3,279,973

Final Design ReportMotor Wheel Disposal SileSharp and Associates. Inc95rpi.doc/rev. 4/30/97

11

Page 15: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Estimated Operating Costs

ITEM

InspectionsMowingCap RepairFence Repair

SUBTOTAL:Contingency @ 15%

TOTAL:

ESTIMATED COST

$5,000$9,000$10,000$4.000$28,000$4.200$ 32,200

Note: Higher annual costs for the first two years resulting from establishing adequate vegetative coverare included in the cap's capital costs.

The Operations and Maintenance Manual for the landfill cap is included as Appendix A.

2.2 LANDFILL CAP DRAWINGS

The list of drawings for the landfill cap is provided below. The landfill construction drawings arelocated in Appendix E.

Sheet Description NumberTitle Sheet 1General Notes 2Existing Site Plan 3Base Grading Plan 4Clay Cap Grading Plan 5Storm Water Management Site Map 6Grading Plan Elevations 7Grading Plan Elevations 8Grading Plan Elevations 9Proposed Site Plan 10Details 11Cross Section 12Cross Section 13Fence Detail 14Pipe Gate Detail 15Erosion Control Plan 16

2.3 LANDFILL CAP SPECIFICATIONS

The Technical Specifications for landfill cap construction are attached as Appendix I. The ConstructionQuality Control Assurance Plan (CQAP) is attached as Appendix B.

Final Design Report i 2Motor Wheel Disposal SiteSharp and Associates, Inc95rpt.doc/rcv. 4/30/97

Page 16: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 3__________GROUNDWATER REMEDIATION SYSTEM

3.1 GLACIAL AQUIFER GROUNDWATER REMEDIATION SYSTEM DESCRIPTION

3.1.1 Groundwater Remediation Strategy

The groundwater plume in the Glacial Aquifer contains volatile organic compounds (VOCs), fluoride,and ammonia that require remediation. The extraction system will consist of a well in the perchedaquifer (landfill area), two wells along the southern boundary of the site (Zone 1), two wells locatedadjacent to MW-39 (Zone 2), and four or five wells located at the trailing edge of the ammonia plumenear MW-64 (Zone 3). The tentative locations for the extraction wells in Zones 1,2, and 3 are locatedon Figure 3-1 (page 14). The exact locations of these wells will be determined through a boringprogram. Several borings will be installed in the extraction areas in order to determine the optimumlocations for the wells. The detailed boring program was submitted under separate cover to MDEQ onNovember 6, 1996. A copy of the program is provided in Appendix J.

The extraction wells in the perched aquifer and in Zones 1 and 2 will remediate groundwater containingboth VOCs, fluoride, and ammonia. Groundwater containing VOCs, from Zones 1 and 2, will betreated using an air stripper prior to being discharged to the Grand River. The groundwater near Zone3 contains ammonia only. Groundwater from Zone 3 will be discharged directly to the Grand River(contingent upon an approved NPDES permit). A process flow diagram of the remediation system isprovided as Figure 3-2 (page 15) and as Groundwater Sheet FD-1 (in Appendix D). Air strippers havebeen proven as a reliable mechanism for the removal of VOCs from groundwater. An Operations andMaintenance Manual for the groundwater remediation system is provided in Appendix A and theHealth and Safety Plan for the system is provided in Appendix C. Construction of the system will beconsistent with the Construction QAPP, located in Appendix B, and the Remedial Action Plan, locatedin Appendix D.

The groundwater modeling performed for the Site indicates that in order to maintain hydraulic controlof the groundwater plume. Zone 1 and Zone 2 require pumping rates of 90 gallons per minute (gpm)each and Zone 3 requires a pumping rate of 80 gpm. The perched aquifer will be pumped at a rate ofapproximately 10 gpm. Zone 1 is near the site with the objective of capturing the higher contaminatedground water emanating from the site. Zone 2 is a cut off zone with the objective of capturing theplume before the aquitard separating the glacial and Saginaw aquifer thins out. Zone 3 is at the leadingedge of the plume to capture the balance of the glacial plume.

3.1.2 Basis of Design

Extraction Wells Based on the calculations and discussion provided in Appendix K, therecommendations for extraction well locations are provided below. The design of the extraction wellsis provided in the Extraction Well Boring Plan located in Appendix J.

Perched Well is located in the landfill. The Perched Aquifer Extraction Well has been located toaddress three objectives: to locate the well in the lower portion of the landfill to maximize the greatestavailable drawdown; to locate the well in an area where the highest observed concentrations ofcontaminants have historically been encountered; and to locate the well in an area of the landfill wheregreater wetted thicknesses were encountered during previous boring and testing programs. The lowest

Final Design Report i -jMolar Wheel Disposal SiteSharp and Associates, Inc95rpl.doc!rev. 4/30/97

Page 17: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

IS104-16MOTOR WHEEL DISPOSAL SITE CLOSURELANSING. MICHIGAN

Ci««l MOTOR WVIEEL PRP GROUP

AND ASSOCIATES, INC.982 Crupper Avenue

Columbus. Ohio 43229

Page 18: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

1962 C

rufXW

A

ww

t I

C<A

m*ut. O

hio 4322* 1

PROJECT NUM

BER

1 DATE

5)04-16 1

12/2

J/9

6

O» z5s

is

[SHARP]AND

AM

OC

Um

, WC

GR

OU

ND

W

ATER FLOW

D

IAG

RA

MM

OTO

R

WHEEL D

ISPOSA

L SITE

CLOSURE

UN

SIN

C. M

ICHIGAN

-n

I 1m

on

n n YA o £T

< > »mo 4r- •? 1

Ts " $

tn " t

0

'4

1 ™ M — g I

f

'9

AIR

STR

IPP

ER

rTTTIi **

m

[el

-Sno

^ ACID INJCCTION (OPTIONAL)

AIR———— 1 DISCHARGE

Page 19: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

elevation of the waste bottom has been identified in the central to northeastern portion of the landfillsite. The single deepest/lowest depth of waste was encountered at the FTC&H soil boring LC-7location. However, the boring logs for this borehole do not record the presence of water.

The area of highest contaminant concentrations were encountered in the Temporary Extraction Wells(TEW) #1 and #2, which were installed north and northeast of soil boring LC-7. Total recorded wettedsection thicknesses for TEW-1 and TEW-2 were approximately 12 feet and 21 feet respectively.

From a production perspective, LC-7 represents a less attractive location due to reported higher silt andclay content, while boreholes TEW-1 and TEW-2 were reportedly higher in coarser sediment fractionsand had greater observed fluid volumes present. South of TEW-1 and TEW-2, the perched aquifermonitoring well #61 also encountered coarser sediments. However, the reported gross wetted thicknessin MW-61 was limited and layered through the perched interval.

The selected Perched Aquifer Location is offset to well TEW-2. This site was selected because: it willencounter the lower/deeper section of the landfill; will be established in the area where the highestconcentrations of contaminants have been recorded; and is predicted to have greater accumulations ofpotentially productive materials.

Zone 1 is near the source. The modeling in the Predesign Report indicates that the plume can becaptured at the source by spacing two extraction wells along the proposed southern border of the Graceproperty. The wells on the sketch are approximately 250 feet apart centered east and west betweenMW12D and MW13D. The exact locations for these wells will be determined as outlined by the boringprogram in Appendix J. The wells are estimated to yield 45 gpm each.

Zone 2 is designed to cut off the plume before entry to the lower (Saginaw) aquifer. There are twowells in this zone to cut off the plume. The tentative well locations are between New York Avenue andMassachusetts Avenue along North Street. The exact locations for these wells will be determined asoutlined by the boring program in Appendix J. The wells are estimated to yield 45 gpm each.

Zone 3 is designed to extract the end of the plume and will be directly discharged to me river. The,aquifer in this area is thinner (~20 feet) requiring more wells. The exact locations for these wells willbe determined as outlined by the boring program in Appendix J. The wells are estimated to yield 20-25 ^gpm each. Based on initial production tests, there will be 4 or 5 wells that will be needed to providesufficient capture. For planning purposes, 5 wells are shown.

Air Stripper Flow from the perched aquifer, Zone 1, and Zone 2 will be routed to an air stripper forVOC removal. Based upon review of the discharge standards, no treatment will be required forammonia. Since no treatment is required for ammonia and VOCs are not present (or are belowconcentrations requiring treatment), water from Zone 3 will be discharged directly into the GrandRiver.

A low profile Shallow Tray Aeration System, manufactured by North East Environmental Products,Inc., was chosen for VOC removal at this site primarily because of it's high removal efficiency andresistance to fouling. The low profile air stripper consists of several sequential trays in which air isbubbled through the VOC-containing groundwater causing the VOCs to be stripped. A low profile airstripper is being used at this site because it can meet the anticipated discharge limitations and will beless susceptible to fouling by calcium and iron precipitation. The anticipated discharge limits for VOCsare their respective MCLs. Sampling of the effluent will be conducted as required by the NPDESFinal Design Report i f.Motor Wheel Disposal SiteSharp and Associates, Inc95rpt.doc/rev. 4/30/97

Page 20: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

permit to ensure compliance. An air emissions study for the site has been reviewed and approved byMDEQ.

The design flow rate for .the groundwater remediation system is approximately 190 gpm. The airstripper was sized for'550 gpm in the event that the flow rate is increased by incorporation of theSaginaw aquifer extracltoti wells. Oversizing the air stripper will also decrease the requiredmaintenance. In addition, a 3-way valve was added to the effluent line of the air stripper to recycle aportion of the effluent. Recycling of the effluent will increase the overall removal efficiency of the airstripper. The concentrations used for sizing the air stripper are provided in Table 3-1. Theseconcentrations were obtained by calculating a "worst case" flow-weighted average concentration fromselected well data. The remediation system incorporates optional acid injection equipment in the eventthat precipitation causes significant operating problems. If required, the acid can be introducedupstream of the air stripper to reduce the pH of the water stream thereby reducing precipitation. Thisequipment was included in order to design the remediation building and piping; it will not be installedunless it is needed. The testing process to determine whether acid feed is necessary is described inSection 3.5 of the Operations and Maintenance Manual (Appendix A).

Table 3-1Air Stripper Design Concentrations

Motor Wheel Disposal SiteLansing, Michigan

Compound (ng/1)

Ethyl benzenetrans 1,2-DichloroetheneTolueneTrichloroetheneVinyl chlorideXylenesFlow Rate (gpm)

PerchedAquifer

46202400102313510

Zone 1

01000

451004590

Zone 2

01000

100090

Air StripperInfluent

3632122967

190

Remediation System Building The air stripper, controls systems, and optional acid feed system will behoused in a 62' by 28' building located on the southwest side of the property (Groundwater Sheet 3KP-1 in Appendix L). The building will be constructed of concrete block and be surrounded by a fence forsecurity. Details of the building are located on Groundwater Sheets A-l, A-2, A-3, S-l, PH-PP1, PH-PP2, E-l, and E-2 (Appendix L).

System Piping The routing of the system pipelines is provided in Groundwater Sheet KP-1 (AppendixL). Easements have been obtained from the railroads to install the piping along this route. The systempiping was designed as a forcemain system. The calculations for each section of pipe are provided inAppendix M.

System Controls The operation of the groundwater remediation system will be controlled byprogrammable logic controllers (PLCs). Since several of the extraction wells are located a significantdistance from the remediation system building, several PLCs are required. Control over the entiresystem will be accomplished using one PLC located in the remediation system building. It will controlthe treatment system equipment, the perched aquifer well, and the Zone 1 wells. Extraction wells inFinal Design ReportMotor Wheel Disposal SiteSharp and Associates. Inc95rpt.doc/rev. 4/30/97

17

Page 21: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

zones 2 and Zone 3 will each contain PLCs that report directly to the PLC in the treatment systembuilding via variable frequency radios. The control logic for the system is provided in Appendix N.

3.1.3 Applicable or Relevant and Appropriate Requirements

Water discharges to the Grand River will be regulated by Michigan Act 245 of the Public Acts of 1929,as amended, Part 4, Rule 57 Water Quality Standards (Rule 57). Rule 57 establishes surface waterdischarge criteria for the target VOCs among other parameters using Water Quality Based EffluentLimitations (WQBELs), Treatment Technology Based Effluent Limitations (TTBELs), andantidegradation criteria. At the present time, it is anticipated that the discharge standards for each ofthe VOCs will be no more stringent than the drinking water maximum contaminant levels (MCLs).Modeling of the ammonia discharge was performed (FTC&H, Final Additional Studies/PredesignReport, 1996) using the Streeter-Phelps Dissolved Oxygen Model to predict water quality effects. Thismodeling indicates that the anticipated discharge of ammonia to the Grand River would not cause adegradation of water quality and subsequently no treatment will be required.

The emissions limitations of VOCs from the air stripper will be based on the air toxic regulationsdeveloped by the MDEQ Air Pollution Control Commission, as defined under Administrative Rule No.R336.1230. This ruling states that the VOC concentration in the air discharge must not exceed the"maximum allowable emission rate based on the application of best available control technology fortoxics (T-BACT)" and the "initial threshold screening level" (ITSL) or the initial risk screening level(IRSL) or both." The IRSL takes precedence when the compounds are suspected carcinogens.

3.1.4 List of Major Equipment

A list of the major pieces of equipment is provided below.

ItemAir StripperSaginaw Aquifer PumpPerched Aquifer PumpZone 1 PumpZone 2 PumpZone 3 PumpAcid Storage Tank (Optional)Acid Metering Pump(Optional)3-Way ValveControl System

Flow Meters

ManufacturerNorth East EnvironmentalGrundfosGrundfosGrundfosGrundfosGrundfosTo be determinedTo be determined

FisherAlien-Bradley

Sensus

ModelModel 41200135S200-12 (20 HP)5S03-9 (1/3 HP)60S50-9 (5 HP)60S50-9 (5 HP)16S07-8 (3/4 HP)To be determinedTo be determined

To be determinedMaster: SLC 5/04Slave: SLC 5/03W-120DR/W-160DR

Final Design ReportMotor Whtel Disposal SiltSharp and Associates. Inc95rpt.doc/rtv. 4/30/97

18

Page 22: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

3.1.5 Cost Estimate

The preliminary cost estimate for the construction of the Glacial Aquifer groundwater remediationsystem is $2,702,500. The.estimated annual operating costs are $287,500. A breakdown of the capitaland operating costs are provided below.

Estimated Groundwater Remediation System Operating CostsITEM

Monitoring/ReportingWell SamplingSystem MaintenanceEquipment ReplacementLaboratoryElectricity

SUBTOTAL:Contingency® 15%

TOTAL:

ESTIMATED COST$ 60,000$60,000$ 30,000$ 25,000$ 50,000$ 25,000$250,000$ 37.500$287,500

Estimated Groundwater Remediation System Construction CostsITEM

EngineeringExtraction WellsSystem EquipmentRemediation BuildingZone 1 VaultsZone 2 and Saginaw VaultsZone 3 VaultsPerched Well Vault and PipingZone 1 PipingZone 2 and Saginaw PipingZone 3 PipingSystem Electrical and ControlsRight-of-Way AgreementsCity Inspection

UNIT

LumpEA

LumpLump

EAEAEA

LumpLumpLumpLumpLumpLumpLump

ESTIMATEDUNIT COST

$100,000$35,000$95,000$224,000$7,500$8,000$5,000$10,000$25,000$750,000$169,000$185,000$200,000$100,000

QUANTITY

112112451

SUBTOTAL:Contingency @ 15%

TOTAL:

TOTAL ESTIMATEDCOST

$100,000$420,000$95,000

$224,000$15,000$32,000$25,000$10,000$25,000

$750,000$169,000$185,000$200,000$100.000

$2,350,000$ 352.500

$ 2,702,500

Final Design ReportMotor Wheel Disposal SiteSharp and Associates, Inc95rpt.doc/rev. 4/30/97

19

Page 23: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

3.2 GROUNDWATER REMEDIATION SYSTEM DRAWINGS

The list of drawings for the groundwater remediation system is provided below. The groundwaterremediation system drawings are located in Appendix L.

Sheet Description NumberTitle Sheet TS-1

ArchitecturalPlans, Elevations, and Sections A-lSections and Details A-2Details and Specifications A-3

StructuralPlans and Details S-l

MechanicalLegend Sheet LS-1Overall Plot Plan Base Bid KP-1Flow Diagram Well Pumps and FD-1Treated Water SystemInstrumentation and Equipment IL-1IdentificationMWDS Ground Water Treatment PH-PP1Pumphouse Mechanical DetailsElevations and SectionsPumphouse Piping Details PH-PP2Process PipingPumphouse Piping Details PH-PP3Process PipingZone 1 Meter Details PH-PP4Pumphouse Piping Details PH-PP5Process Piping

Zone 3Overall Key Plan 3KP-1and Well LocationsPlot Plan & Profile East Side 3UP-1Hosmer Jerome to VinePlot Plan & Profile Hosmer 3UP-2North Side Vine West Side HaagPlot Plan & Profile West Side 3UP-3Haag Vine to Shiawassee StreetPlot Plan & Profile South Side 3UP-4Shiawassee Street Haag to SouthDorrance PlacePlot Plan & Profile South Side 3UP-5Shiawassee Street West of Dorranceto Larch StreetZone 3 Pitless Well Pumps and 3UP-6Meter Vault DetailsZone 3 Water Pit Details 3UP-7

Final Design Report 20Motor Wheel Disposal SiteSharp and Assc dales, Inc95rpt.doc/rev. 4/30/97

Page 24: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Sheet Description NumberOverall Plot Plan KP-2Pumphouse Site Plan BB1-P1Conrail Right-of-Way RRC-P1Piping Key PlanConrail Right-of-Way BBUP-1Occupation Piping PlanPlan and Profile North Side of BBUP-2Case Street North of Drury AvenuePlan and Profile South Side of BBUP-3of Case Street North of GrandRiver South of Drury AvenuePlan and Profile South Side BBUP-4North Street East of High Streetto West end North StreetPlan and Profile South Side BBUP-5North Street Massachusetts toWest of New York AvenueConrail Right-of-Way BBUP-6Occupation ProfileConrail Right-of-Way BBUP-7Occupation ProfilePlan and Profile BBUP-8Grand River & BallardPlan and Profile BBUP-9Grand River & LarchPlan and Profile BBUP-10Grand River & CedarPlan and Profile BBUP-11Grand River & RiverSaginaw Zone Pump No. 1 and BBUP-12Water Pit DetailsSaginaw Zone Pump No. 1 Water BBUP-13Pit SectionSaginaw Zone Pump No. 2 and BBUP-14Water Pit DetailsSaginaw Zone Pump No. 2 and BBUP-15Water Pit DetailsZone 2 Water Pit Details BBUP-16Zone 2 Vault Details BBUP-17Zone 1 & Perched Water Pit Details BBUP-18Outfall to River Details BBUP-19

Railroad CrossingsShiawassee St./CSX Railroad RRC-1Crossing PlanGrand River Ave./CSX Railroad RRC-2Crossing Plan

Final Design ReportMotor Wheel Disposal SiteSharp and Associates, Inc95rpi.doc/rev -1/30/97

21

Page 25: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Sheet Description NumberGrand River Ave./Conrail RRC-3Railroad Crossing PlanShiawassee St./CSX Railroad RRC-4Crossing ProfileGrand River Ave./CSX Railroad RRC-5Crossing ProfileGrand River Ave./Conrail RRC-6Railroad Crossing Profile

ElectricalMWDS Ground Water Treatment ElPumphouse Lighting/Receptacle,Power and Grounding PlanPlot Plan Pumphouse and Well E2Locations, Zone 1 ElectricalPower PlanPlot Plan Pumphouse and Well E3Locations, Zone 1 ElectricalPower PlanPlot Plan and Well Locations, Zone 2 E4Electrical Power PlanPlot Plan and Well Locations, Zone 3 E5Electrical Power PlanSaginaw Power Plan E6Saginaw Power Plan E7System One-Line, Panel Schedule E8and Miscellaneous DetailsTreatment Facility Motor Control E9Center Schematic DiagramTreatment Facility. Zone 2 and E10Perched Wells Node Diameter,Schematic I/O DiagramTreatment Facility, Zone 2 and EllPerched Wells Node Diameter,Schematic I/O DiagramTreatment Facility, Zone 1 E12and Perched Wells PanelLayout and Bill of MaterialZone 2 Wells Node 1 - E13Schematic I/O DiagramZone 2 Wells Panel Layout E14and Bill of MaterialZone 3 Wells Node 2 E15Schematic I/O DiagramZone 3 Wells Node 2 - E16Schematic I/O DiagramZone 3 Wells Node 2 E17Panel Layout and Bill of Material

Final Design ReportMotor Wheel Disposal SiteSharp and Associates. Inc95rpt.doc/rev. 4/30/97

22

Page 26: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Sheet Description NumberSaginaw Wells Node 3 - El8Schematic I/O DiagramSaginaw Wells Node 3 - E19Panel Layout and Bill of MaterialMWDS Ground Water Treatment E20Pumphouse Grounding Plan andMiscellaneous Details

3.3 GROUNDWATER REMEDIATION SYSTEM SPECIFICATIONS

The specifications for the groundwater remediation system are located in Appendix O.

3.4 GROUNDWATER REMEDIATION SYSTEM PERMITS

3.4.1 National Pollution Discharge Elimination System (NPDES) Permit

The NPDES permit application has been submitted to MDEQ. A copy of the draft permit is includedin Appendix P.

3.4.2 Air Discharge Permit

An evaluation of the air emissions from the air stripper has been submitted to MDEQ. A copy of theevaluation is located in Appendix Q.

3.4.3 Railroad Right-of-Way Issues

Railroad right-of-way permits are required for the planned routing of the groundwater system pipelines.Negotiations are currently under way for obtaining the necessary right-of-way permits. The pipelinerouting cannot be finalized until this issue is resolved. The primary pipeline route is along the railroadeasement (owned by Conrail). Additionally there are three railroad crossings required by the design.These permit applications have been submitted to the appropriate railroad company for review. CSXprovided verbal approval for the southern two crossings. Conrail, owner of the rail section for thethird crossing, has not replied. The permit applications, submitted in October, 1996, are located inAppendix R.

3.4.4 City of Lansing Right-of-Way Issues

Some of the routing of the groundwater system's piping will go under the streets and sidewalks ofLansing. Negotiations are currently under way for obtaining the necessary right-of-way permits fromthe City of Lansing.

Final Design Report 23Motor Wheel Disposal SiteSharp and Associates, Inc95rpt.docirev. 4/30/97

Page 27: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

3.5 SAGINAW GROUNDWATER REMEDIATION SYSTEM

The impact of the MWDS on the Saginaw Aquifer has been investigated by multiple consultants sincethe site was listed on the National Priorities List (NPL) on October 4, 1986. Sharp and Associates,Inc. (SHARP) has continued the investigation of the Saginaw Aquifer since January 1995. The InterimReport of the Investigation of the Saginaw Aquifer (Saginaw Report) was provided to the U.S. EPAand the MDEQ on November 18, 1996.

The conclusions published in the Saginaw Report state that the Saginaw Aquifer in the region south ofMWDS has been affected by the MWDS. The constituents of concern identified within the Saginawinclude ammonia, fluoride and vinyl chloride. These compounds are included in the suite of MWDSrelated contaminants that have been identified within the overlying Glacial Aquifer. The potentiometricdata collected determined that the dominant, natural Saginaw groundwater flow gradient is to thenorthwest. However, the City of Lansing's North Well Field and its seasonal municipal water demandshave been shown to cause localized variations to the Saginaw groundwater flowpaths.

Field investigations and laboratory analyses have shown that MWDS - related ammonia, and vinylchloride contaminant plumes are present in the Saginaw Aquifer. The ammonia plume occupies anarea of approximately 200 acres and the vinyl chloride plume an area of nearly 85 acres. The vinylchloride contaminant plume mass is wholly contained within the area of the ammonia plume. Bothgroundwater plumes lie to the east and southeast of the City's North Well Field.

SHARP considered in the design of the pipelines and treatment system the potential impact for theSaginaw active remediation. The actual extraction well location(s) are unknown at this time as theplumes are not completely delineated. However, based on the current interpretation of the Saginawaquifer ammonia and vinyl chloride plumes, an approximation of the extraction rates for the Saginawaquifer can be made. For a potential active pumping alternative in the Saginaw aquifer, two extractionwells are envisioned. Each well would be designed to produce at a rate of 100 gallons per minute, andwill have a calculated 1,200-1,500 foot radius of capture after the first 6 months of operation, therebycapturing the plume mass and preventing the North Well Field's area of pumpage influence fromdrawing the contaminants into this part of the municipal water supply. The glacial aquifer pumpingsystem will cut off further leakage into the Saginaw and reduce the remediation time.

For design purposes, the pipelines designed to convey water to and from the ground water treatmentplant located on the MWDS property have been oversized to accommodate increased flow from theSaginaw aquifer (an allocation of 200 gpm). Additionally, the treatment equipment (i.e., Shallow TrayAeration System) has been oversized to accommodate treating of up to 300 gpm above the requiredneeds of the glacial system (i.e., STAS design at 500 gpm less 200 gpm for glacial = 300 gpmadditional for Saginaw, if needed).

There are currently a number of activities that need to be conducted prior to finalizing any activepumping centers in the Saginaw aquifer including: well profiling of select BW&L wells for furtherdelineation; installation of additional monitoring wells in the Saginaw in the spring of 1997; andresolution of the ammonia cleanup standards with USEPA and MDEQ.

Final Design Report 94Molar Wheel Disposal SiteSharp and Associates, Inc95rpl.doc/rev. 4/30/97

Page 28: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 4______________________PROJECT SCHEDULE———————————————————————————————————————————

The project schedule is provided on the following page.

Final Design Report 25Molar Wheel Disposal SiteSharp and Associates, Inc95rpt.doc/rev. 4/30/97

Page 29: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Motor Wheel Disposal SiteLandfill Cap and Groundwater Remediation System

ScheduleRo Task Name

1 Submit Final Design to EPA/MDEQ2 Planned Field Activities3 Slope Stability Evaluation4 Aerial Photo5 Landfill Well Abandonment6 Extraction Well Borings _7 Profile BW&L Wells __8 Material resource availability9 Permits ~ J^

10 Approval of Water and Air Permit11 Railroad Permit Approval12 Resolve Access Agreement w/M13 Public Meeting ' ~ "~14 Select PR firm ~ ~~ ~~__ _15 Hold Public Meeting " ' ~~16 EPA/MDEQ Review17 Final Design Complete _ _18 Contractor Selection __ _19 Develop bidder short list20 Interview bidders _ _ _ _21 Send out RFP ~ ~22 Award Contract23 Ground Water Treatment System24 Well Drilling25 Glacial wells Zone 1& 2 ""25 Glacial Wells Perched27 Glacial Wells Zone 328 Sagmaw Wells (monitonng)29 Sagmaw Well(s) Extraction30 Piping Zone 1&2 __ "' ""31 Piping Zone 3 _32 Building ~33 Electrical34 Startup35 Landfill Construction _~36 Mobilization _ ___37 Clearing and Grubbing ___38 Offsite Fill "39 Landfill Base Cut/Fill — —40 Landfill Cap41 Drainage Layer42 Unclassified Fill43 Vegetative Cap44 Seeding45 Operation and Maintenance

Duration Start

\2~00_d ~ Dec/20/96~20".98"w" Oct/30/96~"S 00 d" Oct/30/96

5 60 w "Dec/02/96""3 00 w Mar/10/974.00w Mar/10/97

12.00d Mar/03/97Jan/15/97

End

Dec/23/9§fApr/07/97]

1996

_4.70m3.90m1.00m2.92 mr 00 m

" 27 50 d"200m

^ 1.00m~78.0_6 dig.so'd"lO.OOd

je.ood22.50 d"6.55~m

107.47 d44.50 d

" '500aS O O O d31.00d39.00 d

J36.50 d_34'50 d

1 00 m1 00 m4.00 w5.17m5.00 d5.00 d

35.00 d'35.00 d" 1.00m

3.00 w2.00 w

"3 00 w' 2 0 0 w

2.50m

Oct/25/96Oct/11/96Jan/13/97Jan/10/97Jan/10/97Mar/07/97Dec/23/96Feb/25/97Jan/03/97Jan/03/97Feb/02/97Mar/03/97"Mar/28/97jApr/28/97Apr/28/97Apr/28/97Sep/29/97Jul/06/97

Apr/28/97'Jun/20/97Apr/28/97Sep/16/9_7May/24/97Sep/26/97"Oct/28/97Apr/28/97"Apr/28/97Apr/28/97

May/05/97May/19/97

Jul/07/97Aug/05/97Aug/22/97Sep/08/97Sep/29/97Nov/29/97"

Jan/10/97|Mar/31/97!Apr/07/97Mar/18/97Feb/12/97jMar/25/97!Mar/25/97iFeb/16/97Feb/14/97JApr/14/97|Feb/11/97!Apr/14/97!Feb/25/97]Mar/31/97!Apr/28/971Feb/02/97JFeb/18/971

"Mar/28/97l" Apr/28/97j"Nov/28/97!Oct/06/97]Jul/06/97iOct/06/97!Sep/16/97:

Jun/13/97'Aug/18/97Sep/19/97Nov/07/97

_Jun/27/97Oct/28/97_Nov/28/97Oct/14/97

May/05/97May/05/97;Jun/27/97Jul/14/97

Aug/05/97iAug/26/97iSep/08/97JSep/29/97'Oct/14/97|Feb/20/98!

Oct Nov Dec Jan Feb Mar Apr May1997__

Jun Jul Aug Sep Oct Nov Dec_ 1998Jan

Printed: Mar/20/97 MWDS0320 tipPage 1 TJS

Milestone Summary IFixed Delay

Page 30: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 5 REFERENCES

1. U.S. EPA, 1994, Administrative Order of Consent: United States of America; Plaintiffs vs.The Motor Wheel Corporation; Defendants, Civil Action No. VW-92-C-151

2. U.S. EPA, 1992, Scope of Work: Remedial Design Motor Wheel Disposal Site, InghamCounty, Michigan, May 12, 1992

3. U.S. EPA, 1992, Statement of Work: Remedial Action Motor Wheel Disposal Site, InghamCounty, Michigan, May 12, 1992

4. Sharp and Associates, Inc., 1996, 30% Design Report for the Glacial Aquifer GroundwaterRemediation System and Engineered Landfill Closure at the Motor Wheel Disposal Site inLansing, Michigan, prepared for the Motor Wheel PRP Group, July 3, 1996

5. U.S. EPA, 1991 Record of Decision, Motor Wheel Disposal Site, Lansing, Michigan,September 30, 1991

6. FTC&H, 1996, Final Additional Studies/Predesign Report for the Motor Wheel Disposal Site,Lansing, Michigan, March 15, 1996

7. USDA Soil Conservation Service, Michigan Office for Critical Planning, Publication 342-1.

8. Michigan Soil Erosion and Sedimentation Control, Act 347, 1992.

9. Michigan Department of Labor, Bureau of Construction Codes, 1996.

10. Michigan Act 245, Rule 57, Water Quality Standards.

11. Administrative Rule No. R336.1230, MDEQ Air Pollution Control Commission.

12. Hunter/Keck Environmental Services, Remedial Investigation Report, Motor Wheel DisposalSite, Lansing, Michigan, February 8, 1990.

13. ENSR Consulting and Engineering, Final Draft Feasibility Study Report for the Motor WheelDisposal Site, May, 1991.

14. ENSR Consulting and Engineering, Saginaw Aquifer Investigation Report for the Motor WheelDisposal Site, Lansing, Michigan, Consultants Report, April, 1992, Document No. 3144-02-574.

15. FTC&H, Saginaw Aquifer Investigation for Motor Wheel Disposal Site, Lansing, Michigan,Consultants Report, March, 1995.

Final Design Repon 27Motor Wheel Disposal SiteSharp and Associates, Inc95rpi.doc/rev. 4/30/97

Page 31: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

I

oM

2

En\ i ronn i f i i t a lEngineers and Scientis ts

AND ASSOCIATES. INC.

Page 32: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

APPENDIX A

OPERATIONS AND MAINTENANCE MANUAL

Finat Design ReportMotor Wheel Disposal SiteSharp and Associates, Inc95rpt.doc/rev. 4/30/97

Page 33: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

OPERATION AND MAINTENANCE MANUAL

GROUNDWATER REMEDIATION SYSTEMAND ENGINEERED LANDFILL CLOSURE

MOTOR WHEEL DISPOSAL SITELANSING, MICHIGAN

Prepared by:

Sharp and Associates, Inc.982 Crupper AvenueColumbus, Ohio 43229(614) 841-4650

December 23, 1996Revised May 1, 1997

Page 34: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

TABLE OF CONTENTS

1.0 INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 . 1 Background ... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 .2 Source of Contamination ............................................................................... 21 . 3 Performance Objectives ................................................................................ 3

2.0 SYSTEM OVERVIEW/PROCESS DESCRIPTION. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42 . 1 Extraction Wells and Pumps ........................................................................... 4

2.1.1 Extraction Well Overview .................................................................. 42.1.2 Extraction Well Pumps ......................................................................5

2.2 Air Stripper..................... .......................................................................... 62.3 Acid Injection Equipment .............................................................................. 62.4 Flow Meters and Flow Totalizers .................................................................... 62 . 5 Discharge Pump ......................................................................................... 72.6 Program Logic Controls. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 72.7 3-Way Valve . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 72 . 8 Air Compressor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 72.9 System Piping . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 72.10 Remediation System Building ......................................................................... 82.11 Purge Water Tank. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .8

3.0 SYSTEM START UP.............................................................................................. 93.1 Extraction Well Pumps Start Up...................................................................... 93.2 Air Stripper Start Up.................................................................................... 93.3 Discharge Pump Start Up.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .93.4 Calibration of Electronics . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

3.4.1 Water Level Transducers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 103.4.2 Flow Meters . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

3 . 5 Evaluation of Acid Feed System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

4.0 SYSTEM OPERATIONS AND MAINTENANCE...... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 114. 1 Monitoring Frequency ................................................................................ 1 1

4.1.1 Flow Meters................................................................................. 114.1.2 Air Pressure Gauges ... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 114.1.3 Water Level Transducers. ................................................................. 12

4.2 Sampling Procedures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 124.3 System Maintenance .................................................................................. 12

4.3.1 Extraction Well Pumps Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 124.3.2 Well Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 124.3.3 Air Stripper Maintenance .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 134.3.4 Discharge Pump Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 134.3.5 Air Compressor Maintenance .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

4.4 Landfill Cover Maintenance ......................................................................... 134.5 Reports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14

S.OSYSTEMPERFORMANCEEVALUATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 55.1 Verification of Hydraulic Capture . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

Page 35: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

5.2 Verification of Contamination Removal........................................................... 165.3 System Logic .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 165.4 Additional Resources ................................................................................. 165.5 Petitions ................................................................................................. 175.6 Corrective Actions .................................................................................... 175.7 Groundwater Remediation System Analytical Parameters..................................... 18

6.0 SAFETY PLAN.... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19

7.0 REFERENCES.................................................................................................... 20

LIST OF TABLES

Table 2-1 Major System Components... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5Table 4-1 Maintenance Summary... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14

ATTACHMENTS

Attachment A FiguresAttachment B Manufacturers Specification Sheets and Manuals (Included after system installation)

• Extraction Well Pumps• Air Stripper• Discharge Pump• 3-Way Valve• Air Compressor• Flow Meter• Flow Totalizer

Attachment C Trouble Shooting(Included upon completion of construction)Attachment D Sample Data SheetsAttachment E Program Logic ControlAttachment F Ground Water Monitoring and Sampling PlanAttachment G As-Builts (Included upon completion of construction)

Page 36: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 1.0 INTRODUCTION——————————————————————————————————————————————————————————————————————————————————————————————————————————————————————————————————————————————————————

This manual details the operation and maintenance (O&M) procedures for the engineered landfill capand Glacial Aquifer Groundwater Remediation System at the Motor Wheel Disposal Site (MWDS) inLansing, Michigan. The O&M manual will be expanded once the Saginaw investigation is complete.After the system is constructed, the manual will be updated with specific manufacturer's manuals andprocedures. Inclusion of those equipment manuals is premature at this time. This manual is arequirement specified in Section VI, subsection 11-b of the Consent Decree between U.S. EPA and theMotor Wheel PRP Group dated February 13, 1994. This O&M manual, prepared by Sharp andAssociates, Inc. (SHARP), is submitted on behalf of the Motor Wheel Disposal Site PRP Group. Theattachments at the end of this document will become appendices when this document is updatedfollowing system startup. For conciseness, if one of these attachments is in another part of the DesignReport the reader is referred to that appendix to eliminate duplication.

Operation and Maintenance of any treatment system consists of running the system to ensure adequatehydraulic control and optimal operation of the system. Monitoring is performed to ensure the system isperforming to meet the design goals.

This manual is organized with seven sections including:

• Introduction• System Overview/Process Description• System Start Up• Operations and Maintenance• System Performance Evaluation• Safety Plan• References

All Figures are located in Attachment A. Manufacturer's data on major equipment items has beenincluded in Attachment B. The guide for trouble shooting the system is included in Attachment C (willbe included after the system is constructed). Attachment D contains Sample Data Sheets for thesystem. The logic for the control system is provided in Attachment E. Attachment F contains theGround Water Monitoring and Sampling Plan. As-built drawings for the system are provided inAttachment G (will be included after the system is constructed).

1.1 BACKGROUND

The MWDS is a 24-acre property located at 1401 Lake Lansing Road on the northeast edge of the Cityof Lansing, Michigan. The site lies in the NE 1/4 of the SW 1/4 of Section 3 in Lansing Township(T4N, R2W), Ingham County, Michigan (refer to Figure 1 in Attachment A). The property was usedby Motor Wheel Corporation as a disposal site for industrial wastes from 1938 until about 1978 (USEPA, 1991). The types of disposed wastes included solid and liquid industrial wastes, such as paints,solvents, liquid acids, caustics, and sludges. Wastes were disposed of on the property in tanks, barrels,seepage ponds, and open fill operations (US EPA, 1991).

Between 1970 and 1982, at least three cleanup actions were initiated, which resulted in the excavationand offsite disposal of waste materials (Hunter/Keck Environmental Services [Hunter/Keck], 1990). In

O&M Manual f^_ JMotor Wheel Disposal SiteSharp and Associates, Inc.OM. doc/5104-16/5/2/97

Page 37: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

1970, the MDNR requested that the Motor Wheel Corporation remove solid wastes, paint sludges, andoils from seepage pond areas for disposal offsite. Some of the excavated materials were disposedoffsite and the former pond areas were backfilled (US EPA, 1991). Three 10,000-gallon tanks, theircontents and contaminated soil, and fill surrounding the tanks were removed and disposed offsite inDecember 1982. An unknown number of drums were also disposed of offsite at this time (US EPA,1991).

In 1978, MSV Associates acquired the property and began open-pit sand and gravel mining. Themining operations exposed some of the buried industrial wastes. The exposed materials weresubsequently excavated, stockpiled on the western part of the site, and covered with clay (US EPA,1991).

The site was placed on the National Priorities List on October 4, 1986 (50 FR 41015). On June 26,1987, Motor Wheel Corporation, W.R. Grace & Co. (Grace), and The Goodyear Tire & RubberCompany signed an AOC agreeing to conduct a Remedial Investigation (RI) and Feasibility Study (FS)at the MWDS (US EPA, 1991). The ROD for the Site was signed in September 1991. Goodyear,Grace, Textron, and the Lansing Board of Water and Light entered into a consent agreement to conductthe Remedial Design for the Site in 1992.

Site gravel/sand mining operations were discontinued in 1987. MSV Associates is the current owner ofthe property. The site is presently inactive (US EPA, 1991).

1.2 SOURCE OF CONTAMINATION

Previous studies by others have determined the character and extent of contaminants associated with theMWDS and their distribution in the shallow unconsolidated sand and gravel groundwater aquifers(Glacial Aquifer). The Glacial Remedial Investigation determined that the source of the glacial plumeis the landfill and the plume extends approximately 2 miles South of the site.

The impact of the MWDS on the Saginaw Aquifer has been investigated by multiple consultants sincethe site was listed on the National Priorities List (NPL) on October 4, 1986. Sharp and Associates,Inc. (SHARP) has continued the investigation of the Saginaw Aquifer since January, 1995. TheInterim Report of the Investigation (RI) of the Saginaw Aquifer was provided to the U.S. EPA and theMDEQ on November 18, 1996.

The conclusion published in the RI states that the Saginaw Aquifer has been impacted by the MWDS.The constituents of concern identified within the Saginaw include ammonia, and vinyl chloride. Thesecompounds are included in the suite of MWDS related contaminants that have been identified within theoverlying Glacial Aquifer. The RI has determined that the dominant, natural Saginaw groundwaterflow gradient is to the northwest. However, the City of Lansing's North Well Field and its seasonalmunicipal water demands have been shown to cause localized variations to the Saginaw groundwaterflowpaths.

Field investigations and laboratory analyses have shown that MWDS-related ammonia and vinylchloride contaminant plumes are present in the Saginaw Aquifer. The ammonia plume occupies anarea of approximately 200 acres and the vinyl chloride plume an area of nearly 85 acres. The vinylchloride contaminant plume mass is wholly contained within the area of the ammonia plume. Bothgroundwater plumes lie to the east and southeast of the City's North Well Field.O&M Manual ^_2Motor Wheel Disposal SiltSharp and Associates, Inc.OM. doc/5104-16/5/2/97

Page 38: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Most of the waste material present at the Motor Wheel Disposal Site lies directly on top of a clay-richlayer. The clay-rich layer contains an upper perched zone and a lower perched zone. The lowerperched zone appears to be hydraulically connected to the upper perched zone. The Glacial Aquiferlies approximately 25 feet below the base of the waste mass. There are windows, or natural holes, inthe perching clay layers that allows vertical migration of leachate or contaminants into the lower glacialaquifer. Most of the perched aquifer water is derived from infiltration of precipitation in the immediatearea of the waste mass.

1.3 PERFORMANCE OBJECTIVES

The groundwater remediation system has been designed in order to comply with the Record of Decision(ROD) signed on September 30, 1991. The contaminants of concern at the site are chlorinated volatileorganic compounds (VOCs), fluoride, and ammonia. These contaminants shall be removed to complywith the ROD cleanup criteria. In June, 1995, Michigan amended the Michigan EnvironmentalResponse Act, Act No. 307 of 1982 and incorporated the amended act into the National Resources andEnvironmental Protection Act, Act No. 451 of 1994. This new legislation included changes in thecleanup standards that were previously cited as Applicable or Relevant and Appropriate Requirements(ARARs) in the ROD. The PRP group prepared an evaluation of the cleanup standards to USEPA andMDEQ. The final cleanup standards for ammonia is currently under review. A copy of theremediation system's draft National Pollution Discharge Elimination System (NPDES) permit isprovided in Appendix P of the Final Design Report.

The groundwater extraction and treatment system shall operate for a minimum of 10 years as stated inthe Administrative Order of Consent. After 10 years of operation, the clean-up standards and riskassessment will be re-evaluated to determine the need for continuing operation of the groundwatersystem.

0&.M ManualMotor Wheel Disposal SiteSharp ord Associates. Inc.OM.doc/5104-16/5/2/97

Page 39: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 2.0 SYSTEM OVERVIEW/PROCESS DESCRIPTION———————————————————————————————————————————The groundwater plume in the Glacial Aquifer contains VOCs and ammonia that require remediation.The extraction system consists of one well in the perched aquifer (landfill area), two wells along thesouthern boundary of the site (Zone 1), two wells located in the vicinity of MW-39 (Zone 2), and fivewells located at the trailing edge of the ammonia plume near MW-64 (Zone 3). Zones 1 ,2 , and 3 arelocated on a map on Figure 2 in Attachment A.

The extraction wells in the perched aquifer and in Zones 1 and 2 remediate groundwater containingboth VOCs and ammonia. Groundwater containing VOCs, from Zones 1 and 2, is treated using an airstripper prior to being discharged to the Grand River. A process schematic of the treatment system islocated in Figure 3. The groundwater near Zone 3 contains ammonia only. Since ammoniaconcentrations in the groundwater are below applicable Michigan discharge limits, the groundwaterfrom Zone 3 is discharged directly to the Grand River. The system has not been installed yet, so welllocations may be modified based on field results. However, the operation of the system is the same.For the purpose of this O&M manual, it is assumed that the number and location of the extraction wellsremains unchanged. A schematic of the system is located in Attachment A.

The contaminants requiring attention in the groundwater plume in the Saginaw Aquifer includeammonia and vinyl chloride. Sharp has presented a design that has the contingency for two Saginawgroundwater extraction wells be installed downgradient to the contaminant plume areas. Thegroundwater will be treated using an air stripper prior to being discharged to the Grand River.Although the Saginaw delineation is not fully completed, SHARP feels that the existing system andpipelines can accommodate the additional flow. See Section 3.5 of the Design Report for a furtherdiscussion of the Saginaw strategy.

A list of the major system components is provided in Table 2-1. Refer to the drawing in Appendix L ofthe Final Design Report for location and specification of each piece of equipment. The vendorspecification sheets and instruction manuals for each piece of equipment are provided in Attachment B.

2.1 EXTRACTION WELLS AND PUMPS

2.1.1 Extraction Well Overview

The purpose of the extraction wells is to control and intercept the groundwater contaminant plume,down-gradient of the MWDS. In addition to the extraction wells, monitoring wells are utilized forperformance monitoring, water level measurements, and for analytical sample collection points.

The number and spacing of the extraction wells was designed to maintain hydraulic capture of thegroundwater plume. The perched aquifer well will pump at a rate of 10 gpm. Zone 1 is located nearthe site with the objective of capturing the higher contaminated groundwater. Two extraction wells willbe placed along the southern boundary of the Grace property. These wells will be placedapproximately 250 feet apart centered east and west between MW12D and MW13D (refer to drawingsin Appendix L of the Final Design Report). These wells will pump at a rate of 45 gpm each.

Zone 2 is the cut off zone designed to cut off the plume before entry to the lower Saginaw aquifer.Two wells will be placed in this zone between New York Avenue and Massachusetts Avenue along

O&M Manual A-4Motor Wteel Disposal SileSharp and Associates, Inc.OM.doc/5104-16/5/2/97

Page 40: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

North Street (refer to drawings in Appendix L of the Final Design Report). These wells will pump at arate of 45 gpm each.

Table 2-1 (Subject to Change Upon Construction of the System)Major System ComponentsMotor Wheel Disposal Site

Lansing, Michigan

ItemSaginaw Aquifer PumpPerched Aquifer PumpZone 1 PumpZone 2 PumpZone 3 PumpAcid Storage Tank (Optional)Acid Metering Pump(Optional)Flow Meters

Flow Totalizer3-Way ValveAir CompressorSystem Controls

Air Stripper

ManufacturerGrundfosGrundfosGrundfosGrundfosGrundfosNot InstalledNot Installed

Sensus

SensusFisherQuincyAlien-Bradley

North East EnvironmentalProducts

Model135S200-12 (20 HP)5S03-9 (1/3 HP)60S50-9 (5 HP)60S50-9 (5 HP)16S07-8 (3/4 HP)NANA

W-120DR (1.5")W-160DR (2")HOODTo Be DeterminedQRDS-5Master: SLC 5/04Slave: SLC 5/0341200

Zone 3 is designed to extract the end of the plume and is directly discharged to the river. More wellswere required in this zone since the aquifer in this area is thinner and therefore each well is not capableof yielding as much water as Zones 1 and 2. Five wells will be installed pumping at 16 gpm each.

The actual well locations for the Saginaw groundwater extraction wells are unknown at this time as theplumes are not completely delineated. However, based on the current interpretation of the Saginawaquifer ammonia and vinyl chloride plumes, an approximation of the extraction rates for the Saginawaquifer can be made. For a potential active pumping alternative in the Saginaw aquifer, two extractionwells at 100 gpm each are envisioned thereby capturing the plume mass and preventing the North WellField's area of pumpage influence from drawing the contaminants into this part of the municipal watersupply. The glacial aquifer pumping system will cutoff further leakage into the Saginaw and reduce theremediation time.

The Glacial and Saginaw Aquifer extraction system represents a dynamic system and was developed tocontrol and treat the off-site migration of chemicals by creating a hydraulic barrier.

2.1.2 Extraction Well Pumps

All extraction well pumps chosen were Grundfos 4-inch stainless steel submersible pumps (orequivalents). These pumps have built-in jam-free check valves designed for fail-safe operation.OIM ManualMotor Wheel Disposal SiteSharp and Associates. Inc.OM.doc/5104-16/5/2/97

A-5

Page 41: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Precision Form impellers are fabricated from stainless steel to provide for long pump life, maximumhydraulic efficiency, and top performance. An exclusive Prime Inducer provides maximum pumpprotection from dry-run damage during low water situations. The pump inlet is totally screened toprevent damage from debris. These pumps (equivalents) will be installed during the construction phaseof the project.

2.2 AIR STRIPPER

A three tray 304L stainless steel Shallow Tray low profile air stripper, manufactured by North EastEnvironmental Products, Inc., will be installed to remove VOCs at this site primarily because of itshigh removal efficiency and resistance to fouling. The low profile air stripper consists of severalsequential trays in which air is bubbled through the VOC-containing groundwater. The bubbled airstrips the VOCs from the groundwater.

The design flow rate for the groundwater remediation system is approximately 190 gpm. The airstripper was sized for 550 gpm in the event that the flow rate is increased and to accommodate flowfrom the Saginaw aquifer. Oversizing the air stripper will also decrease the required maintenance.

2.3 ACID INJECTION EQUIPMENT

The remediation system was engineered to provide for the installation of acid injection equipment in theevent that precipitation causes significant operating problems. If required, the acid can be introducedupstream of the air stripper to reduce the pH of the water stream thereby reducing precipitation. Theacid injection equipment has not been installed at this time. If an acid injection system is needed, theacid feed rate will be controlled with a PID feedback loop using the downstream pH at the shallow traysump.

2.4 FLOW METERS AND FLOW TOTALIZER

Steel flow meters will be installed to measure groundwater flow from the extraction wells and throughthe remediation system. The flow meters to be installed will be similar to Sensus Magnetic DriveTurbo Meters. The Turbo Meter registers flow by combining the magnetic actions of a driver magnetembedded in the rear face of the rotor, a three-legged flux carrier and a cylindrical follower magnetattached to the gear train shaft inside the registers magnet well. Water flows through the meter causingthe meter's rotor, with magnet, to turn. As one of the magnet poles passes one of the flux carrier legs,the magnetic force is transmitted through the flux carrier leg to the follower magnet, causing theregister shaft to rotate. The rotor assembly is the only moving part in the water.

The flow meters will be installed with a flow totalizer similar to the Sensus Act-Pak (Automatic ControlTranslator Package) electronic instrumentation package. The Act-Pak instrument accepts pulses forcontact closures from the flow meters to provide flow rate data.

O&M Manual ^ £Motor Wheel Disposal SiteSharp and Associates. Inc.OM.doc/5104-16/5/2/97

Page 42: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

2.5 DISCHARGE PUMPS

The air stripper will utilize two discharge pumps for transferring treated water to the outfall. Thesepumps will be Gorman-Rupp Model 83A3-B self priming pumps (or equivalent).

2.6 PROGRAM LOGIC CONTROLS

The MWDS remediation system consists of extraction wells and an air stripper treatment facility. Theextraction wells are broken down by zones with each zone being controlled by an Alien-BradleyProgram Logic Controller (PLC). The PLC located in the treatment system building is designated asthe system master, and the PLC's located at the "remote" sites are designated as slaves to the mastersite. "Linking" of the remote and master sites is accomplished through use of the communicationschannel 0 on the PLC's and spread spectrum radio modems. Use of the radio modems prevents theneed for "hard-wiring" between sites, or the use of designated leased telephone lines. To allow fortotal system overview and control, supervisory software shall communicate via communication channel1 on the master PLC. This supervisory software provides a graphical interface between operators andthe PLC's. Plant control, system alarms, and historical data trending are all accomplished through theuse of supervisory software. Detailed information of the supervisory software can be found in Section3. Oof Attachment E.

2.7 3-WAY VALVE

A 3-inch 3-way pneumatic actuated valve will be installed to recycle effluent to the Shallow Tray AirStripper (STAS) System by means of directing the discharge back to the STAS or to the main output.This recycle will improve the efficiency of the STAS. This 3-way valve will maintain the water levelbetween the high and low level switches (refer to Attachment E) for cycling the STAS discharge pump.This should allow the pump to remain on and prevent excessive cycling. The valve comes equippedwith positive shutoff in each direction and will be controlled by the treatment systems PLC.

2.8 AIR COMPRESSOR

A 5-HP Quincy Model QRDS-5 air compressor will be used to operate the 3-way valve. The aircompressor features permanently lubricated/oil-less, direct drive design which eliminates belts andpulleys as well as oil changes. The compressor features a high torque motor with built-in thermalprotection and a durable, metal housed 4-part regulator and gauge with auto pressure setting. Thepressure range is set at 95 psi on/125 psi off with a 50/50 duty cycle. The air compressor requires 230volt, 60 Hz, 10 amp service.

2.9 SYSTEM PIPING

Diagrams, showing piping size and locations, have been provided in Appendix L of the Final DesignReport. Attachment G of the Operations and Maintenance Manual will contain the as-built drawingsfor the system.

O&M ManualMotor Wheel Disposal SiteSharp and Associates, Inc.OM.doc/5104-16/512/97

Page 43: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

2.10 REMEDIATION SYSTEM BUILDING

The air stripper and controls systems are housed in a 62' by 28' building located on the southwest sideof the property. The building was constructed of concrete block and surrounded by a fence forsecurity. Details of the building are located in Appendix L of the Final Design Report.

2.11 PURGE WATER TANK

The purge water tank will be used to introduce well purge water, developed during the purging andsampling of the various wells on-site, and air stripper cleaning water into the air stripper for treatment.The tank will have a capacity of 300 gallons. Water will be transferred from the tank to the air stripperby a Little Giant 14EH-CIM or equivalent pump.

O&M ManualMotor Wheel Disposal SiteSharp and Associates, Inc.OM. doc/5104-16/5/2/97

Page 44: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 3.0_______________________SYSTEM START UP

This section details the start up procedures for the major pieces of equipment to be used for thegroundwater remediation system.

3.1 EXTRACTION WELL PUMPS START UP

The Grundfos extraction well pumps (or equivalent) will be started by utilizing the Program LogicController (PLC). The pumps will be turned on and each pump's flow meter monitored to verifygroundwater flow. Additionally, the control system is equipped with a safety check of the extractionsystem (refer to Attachment E). The PLC will send an alarm if the pump produces no flow.

3.2 AIR STRIPPER START UP

The air stripper must be started according to the manufacturer's specifications in Attachment B.

1. Turn off all electrical components associated with the unit and close drain and sample valves (besure the sight tube valve is open).

2. Fill the sump tank with one foot of clean water. The sump tank can be filled via the clean-outports, on the left side of the unit, or through the inlet piping.

3. Turn on the master power disconnect switch on the power disconnect panel.4. Check the blower rotation by momentarily switching on the blower switch and observing whether

the blades turn in the direction of the arrow on the blower casing. If blower rotation is correct,open the air inlet damper to 14 open and turn the blower switch to "ON".

5. Start the clean water flow to the unit.

Let the feed water and blower run for about two minutes then shut them off. When the wheel to theblower stops spinning, restart both the blower, and the water flow. This procedure should fill the inletchambers. If the seal pots will not fill by this method, the operator can fill them manually. First tryspraying a stream of water through the clean-out ports, on the left side of the unit. The stream of watermust be sprayed straight across the system and hit the opposite side. The splashing action should fillthe pots. If the preceding methods do not work, remove the trays, fill the seal pots, re-assemble, andre-start.

After the unit has been operating for about 5-10 minutes, check the air pressure readings permanufacturers' recommendations (refer to manufacturers' specifications in Attachment B). Adjust thedamper to obtain the proper readings. Connect the contaminant feed water line. The system is readyfor operation. It is not necessary to perform initial start up procedures each time the system is shutdown, the system will already be primed from the last run.

3.3 DISCHARGE PUMP START UP

The discharge pumps will be started according to the manufacturer's specifications. Prior to startup,the pump will be primed and its rotation checked to ensure proper operation.

O&M Manual ^_gMotor Wheel Disposal SiteSharp and Associates. Inc.OM.doc/5104-16/5/2/97

Page 45: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

3.4 CALIBRATION OF ELECTRONICS

Confirming that the electronic sensors are correctly calibrated is to be done every month for the firstthree months of operation. This frequency is necessary to establish baseline readings for the electronicdrift of each sensor. At the end of the first three month period, the calibration procedure shall be doneperiodically if no drift is encountered. While the sensors are expected to remain stable over longperiods, the maximum calibration interval must be no longer than twelve months. If at any timereadings from sensor becomes erroneous, that sensor must be examined for calibration and confirm thatit is still functioning properly. Calibration of each sensor is done using a two point, linear method byfinding the offset and then the slope of the line created by the two data points.

3.4.1 Water Level Transducers

The pressure transducers, located in each extraction well, are calibrated by obtaining the PLC readingwhen the transducer is out of the water. This reading is the offset. The second reading is obtained bylowering the transducer to a known depth and then reading the output on the PLC. Preferably thereading at depth is taken when the depth is near the maximum normally encountered to minimize sensorerror.

3.4.2 Flow Meters

Refer to manufacturers specification sheets located in Attachment B.

3.5 EVALUATION OF ACID FEED SYSTEM

Minerals (including iron and calcium) tend to precipitate out of groundwater during the aerationprocess. This is commonly referred to as fouling. The shallow tray air stripper is designed to be foul-resistant, however, proper steps must be taken when dealing with high mineral concentrations. The airstripper shall be inspected periodically during the first three months of operation to determine ifprecipitation will be a problem. The maximum inspection interval must be no longer than two weeksduring the 3 month start up period. The inspection shall consist of visually inspecting the trays on theair stripper to ensure fouling is not occurring. The trays can be inspected by removing the clean outport covers and shining a light on the trays to ensure no deposits have developed around the aerationholes. Abnormally high pressure readings on the air stripper is a signal the air stripper is fouled.

The remediation system was engineered to provide for the installation of sulfuric acid injectionequipment in the event that precipitation causes significant operating problems. If precipitation isdeemed a problem, the acid feed system will be installed upon approval from all applicable agencies.Sulfuric acid can be introduced upstream of the air stripper to reduce the pH of the water streamthereby reducing precipitation.

O&M Manual ^, J QMolar Wheel Disposal SiteSharp und Associates, Inc.OM.doc/5104-16/5fl/97

Page 46: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 4.0 SYSTEM OPERATIONS AND MAINTENANCE'

This section details the system operation procedures along with the system components maintenancerequirements and frequency. A trouble shooting guide has been included in Attachment C in order toassist maintenance personnel in the event of system failure. The trouble shooting section will beprovided after system startup and shakedown.

4.1 MONITORING FREQUENCY

Operational parameters (including flow rates, run times, and water levels) of the system shall bemonitored monthly so that system performance can be evaluated and maintenance and repair activitiescan be scheduled, which will minimize cost and system downtime. During initial operation of thesystem, data collection shall be weekly, to account for the greater likelihood of operationalirregularities associated with start up. The program logic controls shall be used to verify properoperation of the remediation system. This shall involve periodically calling the system remotely to besure all components of the groundwater remediation system are operating normally. The groundwatermonitoring and sampling plan is located in Attachment F of this document.

4.1.1 Flow Meters

The treatment system consists of ten extraction wells, each well equipped with a flow meter. Inaddition, the discharge line and recycle line also contain flow meters. All flow meters will bemonitored remotely. The flow meters shall be periodically read and the readings recorded to ensureproper operation of the extraction wells and groundwater remediation system. The completegroundwater monitoring and sampling plan is located in Attachment F.

An air flow meter is located on the air stripper. The air flow meter shall be read and recorded duringsampling events to ensure proper operation of the air stripper.

The remediation system is equipped with an Alien-Bradley PLC control system. The control system isequipped with a safety check of the extraction pumps. The PLC sends a run signal to the pump whichactivates a timer. If the pump turns on the timer is deactivated. However, if the timer times out at oneminute, this indicates the pump has the signal to run, but is not producing flow. This will then signalan alarm system in the supervisory control system. The air stripper is equipped with a high-high levelswitch. If the high-high level switch is activated the system will shut down and an alarm signal will besent to the supervisory control system (for a complete explanation of the PLC refer to Attachment E).In the event an extraction pump or the air stripper shuts down, maintenance personnel shall be notifiedusing the system's PLC and autodialer and shall respond to evaluate the system.

4.1.2 Air Pressure Gauges

The shallow tray air stripper comes equipped with an air pressure gauge that shall be read and recordedduring sampling events.

The remediation system is equipped with an Alien-Bradley control system. The control system isequipped with a high-high level switch on the air stripper. If the high-high level switch is activated thesystem will shut down and an alarm signal will be sent to the supervisory control system (for a

O&M Manual A J 1Motor Wheel Disposal SiteSharp -nd Associates, Inc.OM.doc/5104-16/5/2/97

Page 47: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

complete explanation of the PLC refer to Attachment E). In the event the air stripper shuts down,maintenance personnel shall be notified and shall respond to evaluate the system.

4.1.3 Water Level Transducers

The extraction wells contain water level transducers so that the effectiveness of each extraction well canbe determined remotely using the systems PLC. During the first quarter of operation, the water levelsin the extraction wells shall be recorded weekly to ensure proper capture of contaminant plumes. Afterthe first quarter of operation and after all the adjustments to the system have been made, the waterlevels shall be recorded monthly.

4.2 SAMPLING PROCEDURES

Samples shall be immediately placed in a sample cooler so that a temperature of approximately 4°C canbe maintained until they are delivered to the analytical laboratory. Standard chain-of-custodyprocedures and other shipping protocols shall be used for all samples.

All samples collected at the site and sent off for laboratory analysis will be analyzed in accordance withthe Quality Assurance Project Plan (Hunter/Keck, 1988) approved for the site.

The complete groundwater monitoring and sampling plan is located in Attachment F. The monitoringwells shall be sampled for at least 10 years. At the end of 10 years U.S. EPA, after a reasonableopportunity for review and comment by the State, shall determine the need for additional monitoring.If contaminants fall below and remain below cleanup standards, the PRP Group may petition to adjustthe number of monitoring wells and parameters.

4.3 SYSTEM MAINTENANCE

System maintenance shall be performed according to manufacturers' specifications. Themanufacturers' specification sheets are located in Attachment B. Table 4-1 lists a summary of themaintenance to be performed on the system.

4.3.1 Extraction Well Pumps Maintenance

The extraction well pumps will be serviced according to the manufacturer's specifications.

4.3.2 Well Maintenance

Each extraction and monitoring well shall be inspected for corrosion, damage to the lock, positivedrainage (damage to the concrete apron if applicable) and general integrity each time water qualitysamples or water level data are collected. Well numbers shall be checked for legibility and relabeled asnecessary. The total depths of all monitoring wells are measured to the nearest 0.1 foot periodically.These measurements are compared to installed depths to evaluate changes in the depth of the well (i.e.silt build up, obstruction) with respect to the screened Glacial Aquifer interval. The results of the welldepth measurements are compared to the original completion depths of the wells. Wells which aredamaged beyond repair or which become unusable for some other reason will either be replaced or analternate well designated.0AM Manual A-12Motor Wheel Disposal SiteSharp and Associates, Inc.

Page 48: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

4.3.3 Air Stripper Maintenance

The shallow tray air stripper shall be visually inspected during sampling events to ensure normaloperation. The air stripper shall be inspected for leaks and/or abnormal operation with all observationsrecorded in the field book.

Minerals (including iron and calcium) tend to precipitate out of groundwater during the aerationprocess. This is commonly referred to as fouling. The shallow tray air stripper is designed to be foul-resistant, however, proper steps must be taken when dealing with high mineral concentrations. The airstripper shall be inspected periodically during the first three months of operation to determine ifprecipitation will be a problem. The maximum inspection interval must be no longer than two weeks.The inspection shall consist of visually inspecting the trays on the air stripper to ensure fouling is notoccurring. The trays can be inspected by removing the clean out port covers and shining a light on thetrays to ensure no deposits have developed around the aeration holes. Abnormally high pressurereadings on the air stripper is a signal the air stripper is fouled. Refer to the manufacturer's spec sheetslocated in Attachment B for suggestions on how to reduce high mineral concentrations in the influentflow and for the recommended cleaning procedure for a fouled air stripper. The use of any chemicalsfor cleaning the air stripper must be approved in the NPDES permit if the compound is to bedischarged to the Grand River.

4.3.4 Discharge Pump Maintenance

The discharge pumps will be serviced according to the manufacturer's specifications.

4.3.5 Air Compressor Maintenance

Quarterly inspect the air compressor for leaks and abnormal noises. Also, drain the water from the aircompressors tank. The air compressor will be serviced according to the manufacturer's specifications.

4.4 LANDFILL COVER MAINTENANCE

An engineered cap and landfill cover system will be installed at the Motor Wheel Disposal Site toprovide a low-permeability, high evapotranspiration, barrier to the subsurface materials. This cap shallbe inspected quarterly with the following observations recorded in the field book. Those observationsshall include:

• Location and description of any seeps• Loss of vegetation• Erosion• Verify drainage outlets are free of foreign matter

Any problems discovered with the cap shall be handled with consent of the supervising engineer. Theproblem shall be evaluated, optimal solution determined, PRPs notified if deemed a major problem andgiven chance for comment. Once a solution has been agreed upon, the plan of action shall immediatelybe put forth.

OiM Manual A-13Motor Wheel Disposal SiteSharp and Associates, Inc.OM.doc/5104-16/5/2/97

Page 49: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

The landfill cover shall be mowed twice a year; towards the middle of summer and in early fall(preferably right before the first frost).

4.5 REPORTS

Reports shall be submitted to the agencies on a monthly basis. At a minimum the reports shall includethe following information:

• Analytical data obtained• Maintenance performed• List of any emergency system shutdowns• Record of all readings taken

Table 4-1 Maintenance SummaryMotor Wheel Disposal Site

Lansing, Michigan

EquipmentExtraction Well Pumps

Air Stripper

Discharge Pump

Air Compressor

Wells

Landfill Cover

MaintenanceClean screensInspect intakesVisually inspect for leaks andabnormal behaviorVisually inspect trays for signsof foulingClean stripper if fouledVisually inspect for leaksAbnormal noisesInspect for leaksAbnormal noisesDrain water in tankInspect for corrosionCheck well labelsDamage to lockInspect concrete apron whereapplicableLocation and description of anyseepsInspect vegetationInspect for signs of erosionVerify drainage outlets are freeof foreign matterMow landfill

FrequencyQuarterlyQuarterlyQuarterly

Periodically (min. bi-weekly) forthe first 3 months.As necessaryQuarterlyQuarterlyQuarterlyQuarterlyQuarterlyQuarterly

QuarterlyQuarterly

Quarterly

QuarterlyQuarterlyQuarterly

Semi-annually

O&M ManualMotor Wheel Disposal SiteSharp and Associates, Inc.OM.doc/S104-I6/5/2/97

A-14

Page 50: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 5.0 SYSTEM PERFORMANCE EVALUATION———————————————————^————^———-——————Once the system is on-line, the performance of the system will be verified. There are two categories ofperformance: treatment of contaminated water by the Shallow Tray Air Stripper and hydraulic capture.The former shall be evaluated by comparing the influent concentrations of groundwater contaminants tothe effluent concentrations of groundwater contaminants of the air stripper to ensure appropriatetreatment of the groundwater. The later will be evaluated by determining the cone of capture and theconcentration trends of the monitoring wells. The evaluation criteria are discussed below.

5.1 VERIFICATION OF HYDRAULIC CAPTURE

Hydraulic capture shall be evaluated on a quarterly basis. Baseline data shall be gathered monthly from thebackground transducer and the system's transducers along with pumping rates from the extraction wells.The Troll data loggers will be programmed to gather data on at least a daily basis. During the initial threemonths of operation, electronic monitoring of the water levels will be done on a weekly basis to evaluatesystem performance, verify capture, and adjust pumping rates. The capture zones will be calculated usingstandard industry methods and graphically displayed on the groundwater table maps for the period. Duringthe initial shakedown period, capture zone equations based upon the Dupuit assumptions will be used.After the extraction well system approaches equilibrium with the aquifer, USEPA approved computer codesmay be used on a continuing basis for this task.

The data which are reduced to evaluate hydraulic capture include manual water level measurements frommonitoring wells (see Attachment F, comprehensive Groundwater Monitoring and Sampling Plan),electronic water level recordings from a transducer in a background monitoring well, from transducers inthe extraction wells, and electronic water level measurements from the compliance monitoring wells locatedlaterally from the extraction wells. The electronic data will be retrieved from the extraction wells viatelemetry and from the compliance wells manually by downloading these data monthly or quarterly inpreparation of the quarterly evaluation of groundwater hydraulic capture. The hydrographs from the dataloggers in the compliance well network and the background well will be evaluated to distinguish naturalfluctuations in the groundwater table from pumping the extraction wells.

Evaluation of extraction well maintenance records will be performed to evaluate system performance and topredict potential problem areas. This routine evaluation will be completed on a quarterly basis initially thenon a less frequent basis as baseline data is gathered with findings and corrective actions taken (as necessary)presented in the monthly reports. Data evaluation will include:

• Compilation of a listing that summarizes maintenance activities for the period.• Construction of graphical plots comparing well characteristics over time.• Analysis of capture zones. The capture zones will be displayed on the water level maps.• A review of equipment performance, primarily of the system's pumps and flow meters.

Graphical plots of specific capacity, observation well differential, and recovery data will be constructed asappropriate in order to track system efficiencies over time. In order to account for interference frompumping, observation well differentials will be calculated using the observation well closest to an extractionwell following the equation below:

O&M Manual A-15Motor Wheel Disposal SiteSharp and Associates, Inc.OH. doc/5104-16/5/2/9 7

Page 51: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

D = (DWL-PWL) / Q

D = differential, ft/gpmDWL = water level elevation in nearby observation well, ft. above MSLPWL = water level elevation in pumping well, ft. above MSLQ = pumping rate, gpm

Comparing specific capacity and observation well differentials over time will indicate when interceptor wellredevelopment is warranted. Additionally, graphical plots of specific capacity versus time will be used totrace well efficiencies in conjunction with interceptor well/observation well differential results.

Since the interceptor well network is a dynamic system, individual well pumping rates are subject to changeover time based on changes in the saturated thickness of the aquifer, degradation of well efficiencies, andsystem improvements. Therefore changes in design pumping rates will also be evaluated annually based onground water table maps and capture zone analysis. The results will be reported as part of the monthlyreports.

Any significant repairs or changes to the extraction well system will be discussed in the annual evaluation.This maintenance plan will be revised as necessary to accommodate those repairs or changes.

5.2 VERIFICATION OF CONTAMINATION REMOVAL

The air stripper is rated to remove VOCs to below the required discharge standards. In order to verifythe effectiveness of contaminant removal, the influent concentrations of the extracted groundwater shallbe checked against the effluent concentrations from the treatment system. By converting the influentconcentrations and the effluent concentrations to mass values and taking the difference shall reveal themass of contaminants being emitted from the air stripper stack. This shall enable the operator to ensurethe air stripper emissions are not exceeding applicable air quality standards.

5.3 SYSTEM LOGIC

The Glacial Aquifer Groundwater Remediation System is controlled by a Alien Bradley Program LogicController (PLC). The PLC controls a variety of fail safes to guard against contaminant releases in theevent of system failure. For a complete description of the PLC controls and fail safes refer toAttachment E.

In the event of system shutdown, the PRPs and all applicable agencies shall receive verbal notificationwithin 72 hours and written notification within 7 days. The event shall also be detailed in the monthlyreports.

5.4 ADDITIONAL RESOURCES

In order to minimize downtime due to equipment failure, an inventory of replacement parts shall bemaintained at the MWDS. Available replacement parts include at least one replacement pump andmotor of each type used in the extraction wells, spare transducers, and a stock of miscellaneous partssuch as fuses, low flow alarms and pump controls. This inventory allows equipment repair of minorO&M Manual ^. J gMotor Wheel Disposal SiteSharp and Associates, Inc.OM.doc/5104-16/5/2/97

Page 52: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

problems within a reasonable time frame. To assist in operational failure evaluation, a trouble shootingguide is presented in Attachment C.

5.5 PETITIONS

The U.S. EPA may be petitioned after the system has been operating for a minimum of ten years andappropriate adjustments have been made to improve contaminant removal, to waive compliancethe Ground Water Cleanup Standards set forth upon initial startup of the system. The basis for thepetition is set forth in the Consent Decree, United States of America vs. Motor Wheel Corporation , , - (Section 12-b. '

The U.S. EPA may be petitioned after the system has been operating for a minimum of ten years andappropriate adjustments have been made to improve contaminant removal, to terminate groundwaterextraction and treatment. The PRPs must demonstrate the groundwater cleanup standards have beenmet throughout the entire area of contamination or that there is no longer a risk at the site. Thisdemonstration shall cover 4 consecutive semi-annual monitoring periods during which none of diecontaminated groundwater levels in any of the monitoring wells may exceed any groundwater cleanupstandard.

Upon completion of the groundwater restoration and/or petitioned shutdown of the remediation system,groundwater monitoring indicates the concentrations of contaminants have increased above the aquifercleanup standards the groundwater extraction and treatment system shall be reactivated.

5.6 CORRECTIVE ACTIONS

In me event cleanup standards and/or hydraulic capture is not being attained, the appropriate agenciesand parties shall be kept informed of the adjustments made to the system to correct the problem throughtelephone conversations and the monthly reports. All adjustments performed on the remediation systemshall be monitored for performance and results recorded in the monthly reports.

If the potentiometric surface maps and the analysis of hydraulic capture indicates that the zones ofcapture are insufficient to meet the remedial objectives of this program, the efficiency data from thepumping well(s) involved will be examined and a determination made as to the probable cause.Corrective actions may include cleaning, repairing, or replacing downhole equipment; or rehabilitatingthe well. If rehabilitation is warranted the work will be performed within three months of the date thatthe problem was identified.

The treatment system is equipped with a recycle line. In the event the NPDES discharge limits are notbeing met, the recycle line shall be utilized to ensure discharge criteria are met. The control of therecycle line is described in Section 2.3 line description 50-51 in Attachment E.

Leaks within the treatment building will be detected by a water sensor. This water sensor will beconnected to the system controls and shut down the system and also notify operations personnel of thesituation. If any significant leaks are detected within the system, the effected equipment will beshutdown until properly repaired.

O&M Manual A-17Motor Whtel Disposal SiteSharp and Associates, Inc.OM.doc/5104-16/1/2/97

Page 53: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

5.7 GROUNDWATER REMEDIATION SYSTEM ANALYTICAL PARAMETERS

Water discharged to the Grand River is regulated by Michigan Act 245 of the Public Acts of 1929, asamended, Part 4, Rule 57 Water Quality Standards (Rule 57). Rule 57 establishes surface waterdischarge criteria for the target VOCs among other parameters using Water Quality Based EffluentLimitations (WQBELs), Treatment Technology Based Effluent Limitations (TTBELs), andantidegradation criteria. Discharge standards for each of the VOCs are no more stringent than thedrinking water maximum contaminant levels (MCLs). Modeling of the ammonia discharge wasperformed (FTC&H, Final Additional Studies/Predesign Report, 1996) using the Streeter-PhelpsDissolved Oxygen Model to predict water quality effects. This modeling indicates that the discharge ofammonia to the Grand River will not cause a degradation of water quality and subsequently notreatment is required except during summer months. During the summer months, the dischargeammonia has been determined by MDEQ to cause a degradation of the water quality. This results fronv-^the low flow and higher temperature of the Grand River. The PRP group is currently reviewingtreatment technologies for the removal of ammonia during the summer months.

The emission limitation of VOCs from the air stripper is based on the air toxic regulations developedby the MDEQ Air Pollution Control Commission, as defined under Administrative Rule No.R336.1230. This ruling states that the VOC concentration in the air discharge must not exceed the"maximum allowable emission rate based on the application of best available control technology for'toxins (T-BACT)" and the "initial threshold screening level" (ITSL) or the initial risk screening level(IRSL) or both." The IRSL takes precedence when the compounds are suspected carcinogens.

Since hazardous substances shall remain on Site, ground water monitoring shall at least meet therequirements of Michigan Hazardous Waste Management Act, 1979 P.A. 64, as amended. Rule299.9612, Ground Water Monitoring and Rule 299.9613, Closure and Post closure.

The treatment system effluent will be sampled on a regular basis in order to ensure that the waterdischarged to the Grand River will meet the prescribed NPDES permit limits. The draft NPDESpermit is located in Appendix P of the Design Report. Based upon this information, the system will besampled for chlorinated solvents, benzene, ethylbenzene, toluene, xylenes, naphthalene, ammonia, totaldissolved solids, pH, and dissolved oxygen.

VM-jw*11

OAM ManualMotor Wheel Disposal SiteSharp and Associates. Inc.OM.doc/5104-16/5/2/97

Page 54: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 6.0__________________________SAFETY PLAN

The site safety plan has been prepared as a separate document and is included as Appendix C in theGroundwater Remediation System and Engineered Landfill Closure Design Report.

OtM Manual A-19Motor Wheel Disposal SiteSharp and Associates, Inc.OM.doc/5104-16/5/2/97

Page 55: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 7.0 REFERENCES

1. U.S. EPA, 1994, Administrative Order of Consent: United States of America; Plaintiffs vs.The Motor Wheel Corporation; Defendants, Civil Action No. VW-92-C-151.

2. U.S. EPA, 1992, Scope of Work: Remedial Design Motor Wheel Disposal Site, InghamCounty, Michigan, May 12, 1992.

3. U.S. EPA, 1992, Statement of Work: Remedial Action Motor Wheel Disposal Site, InghamCounty, Michigan, May 12, 1992.

4. Sharp and Associates, Inc., 1996, 30% Design Report for the Glacial Aquifer GroundwaterRemediation System and Engineered Landfill Closure at the Motor Wheel Disposal Site inLansing, Michigan., prepared for the Motor Wheel PRP Group, July 3, 1996.

5. U.S. EPA, 1991, Record of Decision, Motor Wheel Disposal Site, Lansing, Michigan,September 30, 1991.

6. FTC&H, 1996, Final Additional Studies/Predesign Report, March 15, 1996.

7. Hunter/Keck Environmental Services, April 5, 1988 (amended November 17, 1988), QualityAssurance Project Plan: Motor Wheel Disposal Site, Lansing, Michigan.

O&M Manual A-20Motor Wheel Disposal SiteSharp and Associates, Inc.OM.doc/5104-16/5/2/97

Page 56: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

ATTACHMENT A

Figures

Page 57: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

JLSITF.

iy

/ Vss§1*fJ

I... 3

scj

-""jraj

-—

.....

V

^

1roi

L.1

LSOURCE OF BASE MAP:FISHBECK, THOMPSON, CARR* HUBER, INC. LANSING,MICHIGAN, JANUARY 1995 400 aoo

DATE:

12/23/96FIGURE ORSHEET NUMBER: REV 1

PROJECT NUMBER:5104-16

FILE NAME:FIG74216

SHAREAND ASSOCIATES, INC

PROJECT TITLE:

MOTOR WHEEL DISPOSAL SITELANSING, MICHIGAN

SHEET TITLE:

FIGURE 1SITE MAP

Page 58: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

PERCHED AQUIFER WELL

SHE

TREATMENT SYSTEM

SOURCE OF BASE MAP:FISHBECK, THOMPSON, CARRA HUBER. INC. LANSPNG,MICHIGAN. JANUARY 1995

DATE:12/23/96

FIGURE ORSHEET NUMBER: REV 1

PROJECT NUMBER5104-16

FILE NAME:

FIG24216

PROJECT TITLE:

MOTOR WHEEL DISPOSAL SITELANSING, MICHIGAN

FIGURE 2EXTRACTION ZONE LOCATIONS

ANDASSOCIATM.INC.

Page 59: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

iE

-1*-

nAIR

SIRIPPfR

TAN DISCIIARCCPUMP

-10)-

IDGRANDRIVER

PCRCHCDMXJlrCR

SAGINAWVEILS

ZONC I ZONE 2

161 Ciufftt Am»uCttunkut. OM* DIM

GROUND WATER FLOW DIAGRAMMOTOR •HEEL DISPOSAL 8IIf CUMUM

UNBINC. MICHIGAN

PROJCC1 NUMBER5104-16

DATE12/21/96

THE NAME510416)2

SCALENONE

FIGURE

Page 60: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

ATTACHMENT B

Manufacturers Specification Sheets

Page 61: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Flow Meter

Page 62: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SCNSUS, MOOEL W-120 ORBronzfl Mtgnmlc Drive

EndsSize m- (DN 40mm)

*-iaORTgpu Htm *eauf4un'tut wangitB QOWEbnQ fVR^V *4 TQW tp 120

pv .ivmjM [Q.J ID IT iw* ! «ntft rvQMraoon sccuncy ofT ^ -5^ "3t **ttt^ ftntouLOCNFQMUNC£ TO VTANDAMOS; 3«iaus

ANSVAWWA tenewn croi :moai -wentKM aunleu»

TNflow r BBB WVffitn H 30WAft^ f Ol.

n JD a •»

TOUT. TTM

i oor fvracnvjl ww or imom** *•»» or ____

I 19 »' LI BHpfctH^ by 1»OIT1QMWQ ^S nttOjMOCm* -ur fte» of 79

• i

TM474!

to arowa tn» mar. 1 !ft«r» • am ni tmtujom nmrmt «curt rwua aom^:And i

ID 9Jf i27*C5 wnn taw in an*

OPCHATMG

ACCURACY

U3WW.CW

MATOMLS

100%

jpm

g* (1OO bar)AWWA

t2S 90IM<

WOl UH» Pom

100

10.000,00010

108,000 IT*3.1 iHf»w

ThruKCarmdi

— Oraenw3IM

— Tanjwi

— Canone

P. 35

Page 63: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

KseNsus, MODEL W-160 WBronze Magnetic Drive

Size 2" (ON 50mm)

W-1fB 3ff TUMUMI1UI

pwr mtautt •,«.» 9 3t m*«i) <M»I* 1.3*0* MMIUifUOUtCOMPCWUNCI TO ITAflO SWIM

'•*"" accuracy or

of t»o iOOmriniCTIOflf TTw rMOT nA0 fnttnCBV IP3 ?W rH9ttW^^9in 3M "naBxaM iiiiiiniia 3H IMtp^rae 0i» low M«ny>e uw reMMnv y itfudBv ifttt roior. irih•MMd Otad M«Mkig (Off) rtg

CTBVt; ; TM MMntrpj •omt or

rjran* .3y oomommg aw maanwc

x> s

Angit

^van laowaij 3D turn* av onv v Ifta ^aB,flaiof OM fXn camar taQ& Bw rrwoncoc cu^

rvQa^Br tfMR V ^xtfa. TTi only ^ovifl ,9a ^ waMr '• *

AOTQBb Th» awrmegtaaae rotar «*»» gmmrta oawviq ra

•McrBUNQ: T)ip naaunnq i!hamo»r ins amgrnmOM inara •• n 'J» *». A sow* cftunMr an ^*

n OM «««it .TMrHCftane* « r*quf*d. Caw am an

s/oonma

nonmtfy rtJQWPKf tt JPOWG V

d* V* ^B f^ f iM^ ff B ^a^w4 Tt^ft ftVJ

SCKV1C2JO"* ia7"Ci wttfi low

jo

'OFWUTMQ Comnuoua -•am*.*to;90 yr\ (0.9 'e 36

mifTVHfl V r*iOWK200 gpm rrmx. (45 -rr*0l)

ACCUIUCT

•fVMUMBO CONNECTION

RCOMTBR

•ATEMAL3

i mruout(O.r

14 g*t a i «0 gpm (.4 bar« 36 «w>j

180

NPT:

10QUXO.OQO100rvvoi

10.800, OOP euBte IBM10 cu»K

100,000

Qtmaoer —

TUM — TlwrmogtBac

Tun ran Cortnoe

Page 64: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Flow Totalizer ^-

Page 65: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SCNSUSAct-Pak

electronic SignalTransmitting Registers

High Speed Pickup RegisterSofld StMe Signel From S«nau» TUrbo-Metam. SB Meters and Propctar Meter*

1 IONTht Higfi 5o**O .on S«nius SB

r. for us*"UfDo MBMTI and -ntti ACT-PAK in«ruin«ms.

If i

llQTMJ MtSfiW 'Of QQ*TCOOn ofACT>?on in* r0t <9f tenrffwun in* m

PIATUAfiSTh» HSP 1ig»MM *sou*» magnetic onvec'•parmanantty hi

ACT. PAX :/uvuflMnt sftouMjauMC toth* icp^oartiCB MIICI'JBC.

«r«Whar Hign Sp^dunlucd in cowrmat CM praoaty d d«d fr

V «• mew ?n *rjr of tour pornon* w»tt»•n im»m«l 'oati/ia. ma w**en arwwm* touniutfiorzad removal. A

IIQM or Qnojnt aQ]tt» inna «un-

flrv«m* rvgiMr 'jnttmtM )H*. itt aignat isdMMtaovd m« LED (l&t SmOnq QtocM•draJBd pnoflo CB€ wMcn wd net iuixssonin direct sunfigm or arigm i»flec:ec :igntA aoeceUty dmqred ftood to protact a»e

APPUCATiONSi Hign Jaaad P%SQJO a usrc

ontn«r»»o<flowineiBf is rtQUirso.

•wlQpl vd trafivniM• Mgh rrBquaner pulwijp 4v«n*(v c*

i intOMnM

•ny t pe or cowff will provide eraprocecoon tof Die feginer to

CONNECTION

undv a

9am, andof volume, rwm at

ctntra furwttorw.ip

!B«e win « *6con» ojMaat en too ct

ingu»(wi«aq or pwM*l prooorOoruu to

0 v^Bia xiourv tfrw sro^

I in tnanliumidity or

INPUT12VQHOC -SA*. SO

*• rsauna: .TMwnum oui-.330

18VMOC

Maximum cart* «ngm Sam on tm rnaarind ACT-PAX ranumcm a 'COO?••(OQCm) (-17 -wrt AC 90MT '3 racuirw n*• ACT-PAX 4i«tnjm*nt locator). Largerdlwina nqulr* t danaua n«p»«i«r or*o« taiMTMa-f •cuienwit.

TROUBVg-SHOOTING FEATURETh« Hign SpMd P>aku8 logntar «sqtdoprt with *o<2} inMmafly moumadirourt* «h«oang. lionta. Th« oontimjou*

%n brtvnorfsong ttM QdOT^atw/awACT-PAXi,«tn« Htqn 3o**d P^cxup'i larminaJ irp.

^9 T^wgti tne meter

inwnur wmil ctfeiK in snoorflon to (M (taw IMS*.

9WWMd old ttw tfvw (3) conductor

. If ItM BQIII ic iwt bitfilono^ ortfwr T^VHSP'a 4taetrania dreut is cMiaulw orth« corncciing <aoM • me somlnueus.

CNVWONMENTU. OPHUT1NGUMITBThe w(«n Soevd 3icxw> ^aqiafer a

:n mn-«ialo«v« «rmo»-Pooood aits and rtigp frumicjtyorw wu not irtwei ma oa*raacri

Pt*gutar vrfiM propwiy

= .39

Page 66: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SCNSUSAct-Pak

Electronic Instrumentation

Model 1100 SeriesFlow Rate Indicator/Totalizer

?ada»CMUC* (Auaratie• i in <i cNLScnc JIUMIOT <Uteng *d ttMtag caws and 00 marttn-guLT^ AC7-JAK nagunnam pcs tar

VMM I VMV 9UOUS iflljidlin) 1 liU<lllHBdBH.

rt Ufitttf. i «tt -ncwattt iftv-

IndioHo* - » rid LS3 *atQttOQ CP wd cfl 'o *»nr HE» wise rcama "rom

IndicaMi - M 'wetf td 'JD.

21 31 OQtlt}• 'QtV amMM 8K)w

wraoar x ngn votct i rt-aaoua «41 3iwpa«d.! A :a1(9> iti ifcjyiiW By ft 3. "f*

an x aqgio *vu>iy **" 3n tart arw 2£-l£CT swtai 7 wanBaur '0 dsca» w sen-«raa. T?n OMr !•» * leitvnbv o* cm* <9qn OBOBTCJ on i

Caw Cowc nous -• 1Vw-3?Sr 'Vcano3t

ecnuoorq am - S) "i* .TV.'

M csv rt*<TTy ttBQn W'T""*} 10 i*rttn

1100DH

>o««r • '0 vat arcs •

mrjwau Ckwacmj Ccaeidora -

'0 rvnmit .war 'o :rar jasunwa

Qpton COption (OuguCL A sirgii C'(SS5. or

at* ourout svnttrorauj

Sort <ffr«J

ri prc r&nmnq swwen JTS n caxi 01tMl JC*W ' J ' WCMIL

xout

BESET:2Wi« afeuy 1 1 sregrarmwq -aa,

CO..ST ^ST^Y- i iftl. ite»r toes w in

MII»i»ftl3e.

Option 0: Sow Otaut • Ajcun *« t «srr

svnsRv 19•r. tTpaiy ^oAo as aimoirum <l«r rm raror 30 son * '500 GPM.Conct .-rap BI *• «r» « Ct .Option H: =les«tjDi« "ottTr- iVhwcmdSe7 9taQ are aaertd. 3» M caan 3 ysrt a wc-ity i s aitf mutfrOpOon I: ingur CJWMWW -

oiOCT Ou^ufr 4 *

a rtmneno n amtut •• a 4-a rmCC ow-Option U Uw "w OUW • A SPOTdean nt s A^M n*»» tf* tar

itr*.«q d*nct "tw ji«rji

vuonwt ^

. i* not Si«<w oreriq. Ccnaa airgi: ameas CatenaCoton 7: 3v« Uounooq - Mnnm i

onQurtlnQ OQCM5.sanoac SK8u-'«Jin-a> 'jaa

•: "sQlUw'CuBU — x 60SPUT anao WMV (md i anos. -oainw WVOC tv 3 am «a»*. n/ VAC. Otaaran •gm.41 nwc.) -wnw*: i neortd »curz. :l 3 <afa*

s set :o « an

anus aeui (mna ?» ran ' BTO 24j.": arp 4 "7 v*c MI .

wi s !•

Oeten TTIt Sen a «W« r M n l .H8AWIM toalur 3 mountia * ai marral

arc VMMQ rcugn *•*««• aknwq n in>numeni 3> rnoraan a N04MX .•«•«.Opten TT: Soeorw an onKMra 1M tir-cutttT fWUiraq •'or Slot Snar- TOJiw W <»>>•nftan iHi &o a .-aquraa <•«•« «JOiiwc rr* nauna ace orent met Be < i

-c:

Page 67: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

ATTACHMENT C

Trouble Shooting (to be included after system installation)

Page 68: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

ATTACHMENT D

Sample Data Sheets

Page 69: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Table 4-1 Remediation System Data SheetMotor Wheel Disposal Site

Lansing, Michigan

Date:Time:Initials:

Monitoring Wells: (actual number of wells adjusted upon completion of boring program)

Monitoring WellPerched Well

Z1-P1Z1-P2Z2-P1z:-?:ZJ-P!z:-?:Z3-P3Zj-?^Z3-P5

Water Level (ft.)

Meter Readings:

Flow Meter Flow Rate (gpm) Total Flow (gal)Perched Well

Z1-P1Z1-P2Z2-P1Z2-PCZj-PlZ3-P2Z3-P3Z3-P4Z3-P5

Flow Meter < on STAS)Flow Meter (erfluent line of

STAS)Flow Meter (recycle line)

Air Pressure Gauge on STAS: PSI

Page 70: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Table 4-2 Sampling Data SheetMotor Wheel Disposal Site

Lansing, Michigan

Monitoring Wells: (actual number of wells adjusted upon completion of boring program)

Monitoring WellPerched Well

Zl-PlZ1-P2Z2-P1Z2-P2Z3-P1Z3-P2Z3-P3Z3-P4Z3-P5

FrequencyQuarterly

AnaJyteChlorinated VOCsAmmonia

Date Initials

Note: All wells will be sampled in the first year and reduced in succeeding years as analytical datapermits

Treatment System:

(Chart will be developed to represent requirements of the NPDES permit yet to be issued)

Page 71: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Table 4-3 Maintenance SummaryMotor Wheel Disposal Site

Lansing, Michigan

EquipmentExtraction Well Pumps

Air Stripper

Discharge Pump

Air Compressor

Wells

Landfill Cover

MaintenanceClean screensInspect intakesVisually inspect for leaks andabnormal behaviorVisually inspect trays for signsof foulingClean stnpper if fouledVisual lv insoect for leaksAbnormal noisesInspec: for leaksAbnormal noises

FrequencyQuarterlyQuarterlyQuarterly

Periodically (min. bi-weekly) forthe first 3 months.As necsssarvQuarterlyQuarterly |QuarterlyQuarterly |

Dram water in rank QuarterlyInspec: for corrosion i QuarterlyCheck well labels ;Damage to lockInspec: concrete apron whereapplicableLocation and description of anyseeosInspec: vegetationInspect rbr sizns of erosionVerify drainage outlets are freeof foreign matter

Quarterly \Quarterly

Quarterly

Quarterly |QuarterlyQuarterly

Mow landfill Semi-annually

Page 72: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

ATTACHMENT E

Program Logic Control

(See Appendix N in the Final Design Report

Page 73: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

ATTACHMENT F

Comprehensive Ground Water Monitoring and Sampling Plan

Page 74: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

REPORT

COMPREHENSIVE GROUNDWATER MONITORINGand SAMPLING PLAN

for the

MOTOR WHEEL DISPOSAL SITE (MWDS)

LANSING, MICHIGAN

Prepared for:

The MWDS PRP Group

Prepared by:

Sharp and Associates, Inc.982 Crupper AvenueColumbus, Ohio 43229

December 23, 1996Revised May 1, 1997

Page 75: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Table of Contents

1.0 INTRODUCTION ..............................................................................................11.1 Site History ...................................................................................................... 11.2 Site Investigation Activities ................................................................................... 41.3 Recordof Decision (ROD).................................................................................41.4 Surrounding Land Use ......................................................................................71.5 Geology/Hydrogeology .....................................................................................71.6 Potential Contaminant Sources and Transport..........................................................7

2.0 OBJECTIVES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

3.0 RATIONALE FOR SELECTION OF SAMPLE LOCATIONS AND FREQUENCY.........83.1 Perched Glacial, and Saginaw Aquifer Sampling Plan................................................8

4.0 RATIONALE FOR ANALYTICAL PARAMETERS.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 1

5.0 FIELD METHODS AND SAMPLING PROCEDURES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 35.1 Water Level Measurements ................................................................................ 135.2 Sample Collection Procedures ............................................................................ 13

5.2.1 Well Purging Requirements...................................................................... 145.2.2 Sample Collection................................................................................. 145.2.3 Quality Assurance/Quality Control Samples .................................................15

5.3 Equipment Decontamination............................................................................... 165.4 Disposal of Contaminated materials ...................................................................... 165.5 Sample Documentation and Shipment.................................................................... 16

5.5.1 Sample Labels .....................................................................................175.5.2 Field Logbook......................................................................................175.5.3 Chain of Custody Record......................................................................... 175.5.4 Sample Custody Seals............................................................................. 18

LIST OF FIGURESFigure 1 Site Location Map .........................................................................................2Figure 2 Site Map... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3

LIST OF TABLESTable 1 - Record of Decision Cleanup Criteria (ROD) ........................................................6Table 2 - Perched, Glacial, and Saginaw Aquifer Wells to be Sampled.....................................9Table 3 - Perched, Glacial, and Saginaw Aquifer Well Sampling Schedule................................ 11Table 4 - Sampling Methods, Holding Times, and Container Requirements .............................. 12

Page 76: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

1.0 INTRODUCTION

The Motor Wheel Disposal Site PRP Group contracted with Sharp & Associates, Inc. (SHARP) toprepare the Comprehensive Groundwater Monitoring Plan for the Motor Wheel Disposal Site (MWDS)in Lansing, Michigan. This Comprehensive Groundwater Monitoring Plan addresses sampling andanalysis requirements for groundwater contained in the Perched Aquifer, Glacial Aquifer, and theSaginaw Aquifer wells in the vicinity of the MWDS.

This plan follows requirements specified in the Administrative Order of Consent (AOC) between theUnited States of America, the State of Michigan, and MWDS PRP Group which was signed on June 26,1987. This plan follows the EPA Guidance on Remedial Actions for Contaminated Ground Water atSuperfund Sites.

1.1 SITE HISTORY

The MWDS site is a 24-acre property located at 1401 Lake Lansing Road in the northeastern portion ofthe City of Lansing, Michigan. The site is situated within the NE 1/4 of the SW 1/4 of Section 3 inLansing Township (T4N, R2W), Ingham County, Michigan (Figure 1, Site Location Map). TheMWDS site and the surrounding properties are further illustrated on Figure 2, the Site Map. This latterfigure shows the spatial relationships of the MWDS, the current property ownership, and the site'srelationships to adjacent properties.

Historically, the MWDS was used by the Motor Wheel Corporation as a disposal site for industrialwastes from 1938 until approximately 1978 (U.S. EPA, 1991). The types of wastes disposed at theMWDS included solid and liquid industrial wastes such as paints, solvents, liquid acids, caustics, andsludges. These waste products were disposed of on the property in the forms of: tanks, barrels,seepage ponds and open fill operations (U.S. EPA, 1991).

A minimum of three cleanup operations/actions were conducted on the site between 1970 and 1982.The result of these actions was the excavation and offsite disposal of excavated waste materials(Hunter/Keck Environmental Services(Hunter/Keck), 1990). In 1970, the Michigan Department ofNatural Resources (MDNR) requested that the Motor Wheel Corporation remove solid wastes, paintsludges, and oils from seepage pond areas. Some of the excavated materials generated during thisoperation were disposed of offsite, and the former seepage pond areas were backfilled (U.S. EPA,1991). During December 1982, three 10,000 gallon tanks, their contents and associated contaminatedsoil and fill materials were removed and disposed offsite. Concurrent with the tank removaloperations, an unknown quantity of drums were also removed from the MWDS and disposed offsite(U.S. EPA, 1991).

MSV Associates acquired the MWDS property in 1978, and began an open pit sand and gravelquarrying operation. During their quarrying, buried wastes were encountered and exposed. Thesewastes were subsequently excavated and stockpiled on the western part of the site, and later partiallycovered with clay (U.S. EPA, 1991).

Comprehensive Groundtvater Monitoring and Sampling PlanMotor Wheel Disposal SitePrepared frv Sharp and Associates. Inc.AttachF.DOC/rev. 4/3W97

Page 77: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Mag 12.00Thu Dec 19 17:41 1996 •*Scale 1:62,500 (at center)

1 Miles

Secondary SR/Road/Hwy Ramp

Major Connector

State RouteInterstate/Limited Access

US HighwayRest Area with facilities

ake JL.ans.in

SITE LOCATION MAPMOTOR VHEZL DISPOSAL SOT

UNSINC. MICHIGAN

Page 78: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

|5104-16

MOTOR WHEEL DISPOSAL SITELANSING, MICHIGAN SHARP!

AND ASSOCIATtS. INCAND ASSOCIATtS. INC9B2 Crupper Avenue

Columbul, Ohio 4J229

Page 79: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

The MWDS was placed on the National Priorities List (NPL) on October 4, 1986 (50 FR 41015). TheMotor Wheel Corporation, W.R. Grace & Co., and the Goodyear Tire & Rubber Company signed anAdministrative Order of Consent (AOC) agreeing to conduct a Remedial Investigation (RI) and aFeasibility Study (FS) at the MWDS on June 26, 1987 (U.S. EPA, 1991).

As a result of the RI/FS investigations, the MWDS was divided into two operable units. One operableunit consists of the landfill mass and the on-site and off-site groundwater contamination present withinthe perched and Glacial Aquifers. The second operable unit is the Saginaw Sandstone Aquifer.

MSV Associates discontinued the sand and gravel quarrying operations at the site in 1987. MSVremains the property owner, although the site is inactive.

1.2 SITE INVESTIGATION ACTIVITIES

In accordance with the June 26, 1987 AOC Agreement, an RI for the MWDS was conducted byHunter/Keck. The results of the Hunter/Keck RI investigation were reported on February 8, 1990, intheir report titled Remedial Investigation Report, Motor Wheel Disposal Site. Lansing, Michigan. A FSwas conducted by ENSR Consulting and Engineering (ENSR). The FS report was published in May1991 by ENSR in their report titled Final Draft, Feasibility Study Report for Motor Wheel DisposalSite. On September 30, 1991, the Declaration for the Record of Decision (ROD) for the MWDS wassigned by US EPA.

In April 1992, Fishbeck, Thompson, Carr and Huber (FTC&H) issued the Saginaw AquiferInvestigation Report for the Motor Wheel Disposal Site, Lansing Michigan, to summarize theirinvestigations of the deeper and municipally developed Saginaw groundwater aquifer. Additionalinvestigations of the MWDS and both the glacial and Saginaw Aquifers were performed by FTC&H.Their activities and a predesign for remediation of Operable Unit 1 (the MWDS and the GlacialAquifer) were published in Final Additional Studies/Predesign Report, 1996. Subsequent to thepublication of the FTC&H field investigations, Sharp and Associates. Inc. (SHARP) was retained bythe MWDS Potentially Responsible Parties (PRP) Group to further the investigation of the SaginawAquifer. SHARP submitted the Saginaw Formation Aquifer Investigation Work Plan Addendum No. Ifor the Motor Wheel Disposal Site, Lansing, Michigan, was submitted by SHARP on April 13, 1995.Subsequent revisions to this work plan were submitted on August 11, 1995 and November 11, 1995.The work plan and subsequent revisions were approved by the U.S. Environmental Protection Agency(EPA) Region V and the Michigan Department of Environmental Quality (MDEQ). In November 1996,SHARP issued the Interim Report for The Investigation of the Saginaw Aquifer at the Motor WheelDisposal Site. In addition to the Saginaw Aquifer work plan and its revisions, SHARP has continuedwork on the Operable Unit remedial system design as published in: The 30% Design Report for theGlacial Aquifer Groundwater Remediation System and Engineered Landfill Closure, July 1996 and theDraft Final Design submitted on December 23, 1996.

1.3 RECORD OF DECISION (ROD)

The ROD for the first operable unit at the MWDS was signed on September 30, 1991. The firstoperable unit includes the waste mass and the groundwater contamination in the perched and GlacialAquifers at the MWDS. The groundwater contaminants of concern, as determined by theHunter/Keck, 1990 RI, and the risk and toxicity assessments include the following volatile organic

Comprehensive Groundwater Monitoring and Sampling PlanMotor Wheel Disposal SilePrepared frv Sharp and Associates. Inc.Altachf DOC'rev 4/30/97

Page 80: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

compounds (VOCs):

1,1 Dichloroethene (1,1-DCE) Chloromethane1,2-Dichloroethane (1,2-DCA) Ethylbenzene1,2-Dichloroethene (1,2-DCE) Methyl Chloride2-Butanone Naphthalene2-Hexanone Tetrachloroethene (PCE)4-Methyl-2-pentanone Trichloroethene (TCE)Benzene TolueneChloroethane Vinyl Chloride (VC)Chloroform Xylenes, Total

The semi-volatile organic compound (SVOC) contaminants of concern included bis(2-ethylhexyl)phthalate and 2,4,5-trichlorophenol. Inorganic contaminants of concern included ammonia,chloride, fluoride, iron, lead, nitrate, sulfate, and zinc

The ROD cleanup criteria for these respective constituents are presented in Table 1. In June 1995,Michigan amended the Michigan Environmental Response Act, Act No. 307 of 1982, and incorporatedthe amended Act into the Natural Resources and Environmental Protection Act, Act No. 451 of 1994.This new legislation included changes to the cleanup standards that had been previously cited asApplicable or Relevant and Appropriate Requirements (ARARs) in the ROD.

The September 30, 1991 ROD did not specifically address the Saginaw Aquifer, its investigation, orcontaminants of concern, nor did it specify cleanup standards. The Saginaw investigative effortsconducted thus far have identified three constituents of concern within the Saginaw Aquifer. Theyinclude ammonia, fluoride, and vinyl chloride. As a point of departure for this RI, SHARP used thecleanup standards assigned to the glacial and perched water aquifers as described under "Clean-UpStandards" listed on page 6 of the Final Scope of Work for the Remedial Design, Motor Wheel DisposalSite, Ingham County, Michigan, May 12, 1992, and on Table 10 of the ROD (Table 1 of thisdocument). The clean-up standards noted by these documents for Saginaw Aquifer constituents ofconcern are as follows:

• ammonia 34,000 micrograms per liter (ng/1)• fluoride 2,000 micrograms per liter (ng/1)• vinyl chloride 1 microgram per liter (|o.g/l)

However, subsequent to the Operable Unit 1 ROD and the 1992 Final Scope of Work,, the clean-upstandards for vinyl chloride and ammonia have been revised (Ref. Natural Resources andEnvironmental Protection Act, Act No. 451 of 1994, Part 201, the Safe Drinking Water Act, andMaximum Concentration Levels (MCLs)). Current MCL values and this investigation's recommendedclean-up values for these constituents are as follows:

• ammonia There is no MCL for ammonia.• nitrate (as N) 10,000 micrograms per liter• nitrite (as N) 1,000 micrograms per liter• fluoride 4,000 micrograms per liter. It should be noted that the fluoride

standard is currently under review.• vinyl chloride 2 micrograms per liter

Comprehensive Groundwater Monitoring and Sampling PlanMotor Wheel Disposal SitePrepared tn Sharp and Associates, Inc.MachF.DOC'rev. 4/30/97

Page 81: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Table 1ROD Cleanup Criteria - Perched and Glacial Aquifers

Motor Wheel Disposal Site, Lansing MichiganContaminants

Volatile Organic Compounds1,1-Dichloroethene1 ,2-Dichloroethane1 ,2-Dichloroethene2-Butanone2-Hexanone4-Methyl-2-pentanoneBenzeneChloroethaneChloroformChloromethaneEthylbenzeneMethylene ChlorideNaphthaleneTetrachloroetheneTrichloroetheneTolueneVinyl ChlorideXylenes (total)Semi- Volatile Organic CompoundsBis(2-ethylhexyl)phthalate2 ,4 , 5-TrichlorophenolInorganicsAmmoniaChlorideFluorideIronLeadNitrateSulfateZinc

Cleanup Criteria*(Results in ug/1)

70.4(1)

704005

4001.09.06.03.07005.040

0-7(1)3.0800

0.02 (1)300

2(5)700

34,000250,0002,0003005

10,000250,000

1,000

* The cleanup standards is the greater of the Type B standard or the method detection limit (MDL) as noted in Table 10 of theROD. The standards presented in (parenthesis) are the MDL for those parameters where the MDL is greater than the Type BStandard.

Note: The cleanup standards for vinyl chloride and fluoride are being revised to 2 ng/L and 4,000 ug/1,respectively. The standard for ammonia is currently under review. These modified cleanup standardswill be included in the amended ROD to be prepared by the USEPA.

Comprehensive Groitndwaicr Montionn$ and Sampling PlanMotor Wheel Disposal SitePrepared fry Sharp and Associates. Inc.AttachF.DOarev. 4/30/97

Page 82: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

1.4 SURROUNDING LAND USE

Current land use adjacent to, and surrounding the MWDS includes light and heavy industrial properties,commercial businesses, a sanitary landfill, a demolition debris/clean fill landfill, and residential singleand multi-family housing areas.

1.5 GEOLOGY/HYDROGEOLOGY

The MWDS is located within the south-central portion of the Michigan Basin physiographic province.Geologically, the topography of the area is relatively flat to gently rolling and reflects the erosionaland depositional processes associated with multiple periods of Pleistocene glaciation. The surfacesediments of the area are largely reworked recent materials which largely reflect the overprint ofurban, commercial, and industrial activities. The native surface and near surface sediments of thearea consist of mature soils and unconsolidated sediments which have been developed from multipleglacial parent materials. Regionally, these uppermost Recent and Late-Pleistocene sediments havebeen unconformably deposited on Pennsylvanian aged bedrock strata (Westjohn et al., 1994).

1.6 POTENTIAL CONTAMINANT SOURCES AND TRANSPORT

The contamination present within the Perched and Glacial Aquifers at the MWDS is attributable to thehistoric dumping, landfilling and quarrying operations that have occurred at the site. The contaminationpresent in the downgradient plumes of the Glacial Aquifer related to the MWDS is a source ofcontamination to the underlying Saginaw Aquifer in this region. The downward flow of contaminantsfrom the glacial into the Saginaw occurs where the erosion of the upper Pennsylvanian black shale,coupled with the reduction in quality of the basal till unit, create "windows" where the downwardmovement of Glacial Aquifer waters can occur. Specifically in this area of investigation, the"window" present south and west of MW-68 serves as a leakage area where the contaminated,relatively high velocity, south-flowing Glacial Aquifer waters can enter and mix with the relativelyslower velocity, northwesterly flowing waters of the Saginaw.

2.0 OBJECTIVES

The primary objectives of this Comprehensive Groundwater Monitoring Plan for the MWDS include:

• The collection of water level data to monitor the groundwater extraction systems to showhydraulic capture of contaminant concentrations in excess of the cleanup goals;

• The collection of water chemical data to monitor the progress of the groundwater cleanup;

• The preparation of a consolidated plan for monitoring the contaminant plumes present within thePerched, Glacial, and Saginaw Aquifers; and

• The collection of effluent concentrations from die treatment plants to verify compliance withdischarge limits.

The numerical cleanup goals for the Perched and Glacial Aquifers are shown on Table 1 . The currentcleanup goals assigned to the Saginaw aquifer are as follows:

Ammonia 34,000 u,g/LComprehensive Groundwater Monitoring and Sampling PlanMotor Wheel Disposal SitePrepared by Sharp and Associates, Inc.AttachF.DbOrev. 4/30/97

Page 83: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

• Fluoride 4,000• Nitrate 10,000• Nitrite 1,000 ug/L• Vinyl Chloride 2 jig/L

However, the cleanup goal for ammonia is presently under review by MDEQ. The PRP group hasrecommended to the Agency that the ammonia constituent be removed as there is no MCL for ammonia,and nitrate and nitrite be substituted.

3.0 RATIONALE FOR SELECTION OF SAMPLING LOCATIONS AND FREQUENCY

This section describes the rationale for the selection of wells to be sampled and the frequency ofsampling. The Perched, Glacial and Saginaw Aquifer wells included in this comprehensive monitoringprogram are intended to monitor the following:

• the effectiveness of extraction on the aquifers in development of a zone of capture for thecontaminated groundwater;

• the reduction of the concentrations of the contaminants of concern created by the pumping andtreatment process; and

• the effectiveness of the pump and treat process to control the migration of the contaminantplumes.

3.1 PERCHED, GLACIAL AND SAGINAW AQUIFER PLUME SAMPLING PLAN

Groundwater samples will be collected from monitoring wells and extraction wells located around theperimeter, downgradient, and within the contaminant plumes. The groundwater samples will be fieldmonitored for pH, temperature, conductivity, and analyzed for VOCs, selected semivolatiles, ammonia,and fluoride. Groundwater levels will be measured in the extraction, monitoring and compliancemonitoring wells.

The number of measurements and samples to be collected has been determined based upon the datarequired to monitor the Perched, Glacial and Saginaw Aquifers, proper plant operation, and theeffectiveness of the pumping and treatment system. Groundwater levels will be manually measuredaccording to the schedule shown in Table 3. These measurements will be used to evaluate groundwaterelevation changes caused by pumping. For the first month, the groundwater levels in the wells equippedwith transducers will be programmed to collect levels at least 4 times per day and downloaded from theTroll transducers on a weekly basis.

Following the initial "shake-down" of the system (3 months), the data collection frequency of wells withtransducers will increase to one per day (downloaded monthly), and then eventually to greatermonitoring intervals. The Troll transducers will be programmed so that unusual changes in water levelsdetected at a regular sampling interval will "trigger" increased frequency of measurements to helpdetermine the cause of the change and it's effects with respect to the extraction system.

The frequency of sampling the Perched and Glacial Aquifer wells will be initially on a quarterly basis,with the Saginaw Aquifer wells on a semi-annual basis until the plume delineation is completed and aremedy selected. A total of forty-four (44) Perched, Glacial and Saginaw Aquifers wells will beComprehensive Groundwater Monitoring and Sampling PlanMotor Wheel Disposal SitePrepared by Sharp and Associates. Inc.AttachF DOCIrn. 41)0/97

Page 84: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

sampled as part of the quarterly sampling program (5 wells in the Perched Aquifer, 31 wells in theGlacial Aquifer, and 8 wells in the Saginaw Aquifer).

Table 2 lists the Perched, Glacial and Saginaw Aquifers wells which will be sampled under this MWDSMonitoring Plan. Table 3 lists the wells to be sampled for analytical parameters and water levelmeasurements. Figures 3 and 4 illustrate the well locations for the glacial aquifer for water levelmeasurements and analytical sampling, respectively. Similarly, Figures 5 and 6 illustrate the locationsfor water levels and analytical sampling for the Saginaw Aquifer. These figures will be revised toinclude the new wells after installation.

TABLE 2PERCHED, GLACIAL AND SAGINAW AQUIFERS: WELLS TO BE SAMPLED

Well Number

Bl-3BL-MW-1-SBL-MW-2-SBL-MW-3-SIC-4IC-5MW-10MW-11DMW-12DMW-13DMW-14MW-19MW-2 LABMW-20MW-29MW-2DMW-3MW-3LABMW-30MW-31MW-32MW-33*MW-34MW-35MW-36MW-37MW-38MW-39MW-40MW-41MW-42MW-43MW-44MW-45MW-46MW-47MW-49MW-5MW-50MW-51

Top-of InnerCasing Elevation

857.12869.44883.77874.54879.91873.78871.18869.75845.92875.26870.68870.14868.8846.28870.38878.85867.05859.42865.67875.83877.4876.66873.57876.85847.69855.41864.28871.93867.18842.72842.52

852.42877.69839.97889.68

Aquifer

GlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacial

Status

MonitoringMonitoringMonitoringMonitoringMonitoringMonitoring

To Be AbandonedMonitoringMonitoringMonitoringMonitoringMonitoringMonitoringMonitoring

To Be AbandonedTo Be AbandonedTo Be Abandoned

MonitoringTo Be Abandoned

MonitoringMonitoringMonitoringMonitoringMonitoringMonitoringMonitoringMonitoringMonitoringMonitoringMonitoringMonitoringMonitoringMonitoringMonitoringMonitoring

To Be AbandonedMonitoringMonitoringMonitoringMonitoring

AnalyticalSampling

YesYesYesYesYes

Yes

YesYesYesYesYesYesYes

YesYesYesYesYes

Yes

Yes

YesYes

WaterLevels

YesYesYesYesYesYes

YesYesYesYesYesYesYes

Yes

YesYesYesYesYesYesYesYesYesYesYesYesYesYesYesYes

YesYesYesYes

Comprehensive Groundwater Monuonng and Sampling PlanMotor Wheel Disposal SitePrepared bv Sharp and Associates. Inc.AttachF DOC/rev. 4/30/97

Page 85: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Well Number

MW-53MW-57MW-58MW-59MW-6MW-60MW-62MW-63MW-64MW-7MW-8MW-4TEW-3MW-12SMW-13SMW-15MW-16MW-17MW-18MW-25MW-27MW-28MW-2SMW-48MW-61TEW-1TEW-225-1025-1325-1425-1525-1625-1825-1925-225-2525-2625-2825-29MW-21MW-22MW-23MW-24MW-54MW-55MW-56MW-65MW-66MW-67MW-68

Top-of InnerCasing Elevation

861.38879.37870.19872.16871.8862.86843.19846.69857.98870.75874.1825.7

879.91873.78

870.14

850840.3826.7839.1844.5838.2843.9850

862.6851867

864.9872.86865.39873.02872.81852.46860.59846.17852.05865.13851.6876.18

Aquifer

GlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialGlacialPerchedPerchedPerchedPerchedPerchedPerchedPerchedPerchedPerchedPerchedPerchedPerchedPerchedPerchedSaginawSaginawSaginawSaginawSaginawSaginawSaginawSaginawSaginawSaginawSaginawSaginawSaginawSaginawSaginawSaginawSaginawSaginawSaginawSaginawSaginawSaginawSaginaw

Status

MonitoringMonitoringMonitoringMonitoring

To Be AbandonedMonitoringMonitoringMonitoringMonitoring

To Be AbandonedMonitoringMonitoring

To Be AbandonedMonitoringMonitoringMonitoringMonitoring

To Be AbandonedTo Be AbandonedTo Be AbandonedTo Be AbandonedTo Be AbandonedTo Be AbandonedTo Be AbandonedTo Be AbandonedTo Be Abandoned

MonitoringProductionProductionProductionProductionProductionProductionProductionProductionProductionProductionProductionProduction

To Be AbandonedTo Be Abandoned

MonitoringMonitoring

To Be AbandonedMonitoringMonitoringMonitoringMonitoringMonitoringMonitoring

AnalyticalSampling

YesYesYes

YesYesYesYes

YesYes

YesYesYesYes

Yes************************

YesYes

YesYesYesYesYesYes

WaterLevels

YesYesYesYes

YesYesYesYes

YesYes

YesYesYesYes

YesYesYesYesYesYesYesYesYesYesYesYesYes

YesYes

YesYesYesYesYesYes

Note: The treatment plant influent and effluent will be sampled monthly to ensure performance of the STAS and to ensurecompliance with the NPDES permit.

Comprehensive Grotindwater Monuortng and Sampling PlanMolar Wheel Disposal SitePrepared t>v Sharp and Associates. Inc.Aaachf DOC/m. 4/30/97

10

Page 86: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

* Troll transducer or equivalent will be placed in MW-33 to collect water level measurements to represent the natural fluctuation ofthe glacial aquifer.** The results of Samples taken from these wells by BVf&L will be included as part of the database.

TABLESWELLS TO BE USED FOR ANALYTICAL SAMPLING AND

GROUNDWATER LEVEL MEASUREMENTS

Glacial

Perched

Saginaw

Existing WellsSamplingFrequency

Quarterly for First2 quarters, thenSemi-annuallyQuarterly for First2 quarters, thenSemi-annuallyQuarterly for 2years, then Semi-Annually*

New Wells SamplingFrequency

Monthly for shakedownperiod**, Quarterly for 2years, then Semi-annuallyMonthly for shakedownperiod. Quarterly for 1-year,then Semi-AnnuallyMonthly for shakedownperiod, Quarterly for 1 year,then Semi-Annually

Existing WellsWater levels

Quarterly for First2 quarters, thenSemi-annuallyQuarterly for First2 quarters, thenSemi-annuallyQuarterly for oneyear, then Semi-Annually

New Wells Water levels

Monthly for shakedownperiod, then Quarterly

Monthly for shakedownperiod, then Quarterly

Weekly for shakedownperiod, monthly for 6Months, Quarterly for 1Year, then Semi-Annually

* The objective of the extended quarterly sampling is to establish historic baseline data for this aquiferwhich does not currently exist.** "Shakedown period" is three months.

4.0 RATIONALE FOR ANALYTICAL PARAMETERS

The comprehensive groundwater monitoring plan for the Glacial Aquifer has been pared down to the listof analytes that have been historically detected. These analytes include ammonia, fluoride, and vinylchloride. For the Saginaw Aquifer, only Ammonia and vinyl chloride have been detected. Therefore,fluoride has been dropped as a parameter for that aquifer. Nitrate has been analyzed for in samplesfrom wells in the Glacial Aquifer and the Saginaw Aquifer and has not been detected to date (with theexception of two on-site wells completed in the landfill). For the analysis of wells completed in thePerched Aquifer, nitrate and the chemicals required for the NPEDS permit have been added to the suite(i.e., analyze for ammonia, fluoride, chlorinated solvents, BTEX, naphthalene, and nitrate. CurrentlyMDEQ is evaluating the PRP group's proposal to drop the ammonia as a clean-up criteria and substitutenitrate. Pending the outcome, the sampling suite will be altered.

At die conclusion of remediation for the Perched, Glacial and Saginaw Aquifers, a final comprehensiveround of samples will be collected from the entire well network. For that sampling, methods will beselected to assure appropriate testing for all analytes in the 1991 ROD.

See Tables 2 and 3 for the selected sampling frequencies and corresponding analyses for the Perched,Glacial and Saginaw Aquifers. Interim sampling methods, preservatives, holding times and containerrequirements are presented in Table 4.

The laboratory methods and specific laboratory protocols are included in the approved QAPP(Hunter/Keck Environmental Services, Revised November 17, 1988)Co<nprehensive Groundwater Monitoring and Sampling PlanMotor Wheel Disposal SitePnpartd try Sharp and Associates, Inc.AaachF.DOC/rev. 4/30/97

11

Page 87: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

TABLE 4SAMPLING METHODS, PRESERVATIVES, HOLDING TIMES AND CONTAINER REQUIREMENTS

Contaminants

Volatile Organic CompoundsMethod SW846:80101 , 1-Dichloroethene1 ,2-Dichloroethane1,2-Dichloroethene2-Butanone2-Hexanone4-Methyl-2-pentanoneBenzeneChloroe thaneChloroformChloromethaneEthylbenzeneMethylene ChlorideNaphthalene *TetrachloroetheneTrichloroetheneTolueneVinyl ChlorideXylenes (total)InorganicsAmmonia, Method USEPA 350.3

Fluoride, Method USEPA 340.2Nitrate, Method USEPA 353.2

Current CleanupCriteria ug/L**

71

704005

4001963

70054013

8002

300

34,000

4,00010,000

Preservation

l : lHCl topH<2;Cool to 4°C

H2S04; 4°C

Cool to 4°CCool to 4°C

Holding Time

14 days

28 Days

28 Days28 Days

Sample Volume

2x40 mlGlass

8 oz. Plastic

8 oz. Plastic

* Naphthalene will be identified as a TentativelyIdentified Compound (TIC) during the VOC scan.

QA7QC Analysis:

• Trip Blank: I/day (VOCs only)• MS/MSD: 2/sample delivery group• Duplicate: 1/20 samples collected• Equipment and Rinseate Blanks: I/day

e Groundwuer Monitoring and Sampling PlanMotor Whett Disposal SitePrtpartd trv Sharp and Associates. Inc.Attachf DOOrrv. 4/30/97

12

Page 88: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

5.0 FIELD METHODS AND SAMPLING PROCEDURES

The groundwater monitoring program at the MWDS includes the measurement of groundwater levels inthe designated wells, field measurements, and analysis of groundwater samples by an analyticallaboratory. The water level data is used for determining the flow direction of groundwater at the site.Field measurement data is collected during well purging to ensure a representative analytical sample iscollected. The analytical samples are collected to determine the progress of the remediation efforts at thesite.

The wells selected for water level measurements and sampling and analyses are shown in Tables 2 and3. Table 4 provides the relevant information pertaining to analytes, analytical methods, preservation,holding times, sample volumes, and required quantitation limits.

5.1 WATER LEVEL MEASUREMENTS

Upon arrival at each well, the sampler will observe and record the condition of the surface seal and wellprotector, including the lock. Any evidence of vandalism, insect/rodent intrusion or damage by vehiclesor other activities will be noted and corrected. If the wells are fitted with airtight caps they will beopened and allowed to equilibrate to atmospheric pressure for 24 hours prior to the time water levelmeasurements are taken.

These observations will be recorded on field sampling sheets or in a bound field book. Records shouldinclude the names of the sampler(s), date and time of activities, list of equipment used as well as otherpertinent data.

Prior to sampling each well, a measurement of the groundwater level below the top of the well casingwill be obtained. Water levels will be measured from the top of the measuring tube (measuring point) atthe permanently marked, surveyed point at the north side of the well casing, not from the top of the steelprotective casing.. Three successive measurements will be taken in each monitoring or observation wellwith an electric water level indicator (Solinst or equivalent) and recorded to the nearest 0.01 foot. Thewater level indicator will be decontaminated with distilled/de-ionized water between each well. Thegroundwater levels in the monitoring wells, compliance wells, observation wells and extraction wellswill be measured with an electronic water level indicator and/or the dedicated pressure transducer.Water level measurements will be collected according to the schedule presented in Table 3. Water levelmeasurements will also be recorded in the process of sampling for analytical parameters (Table 4). Thewater levels will be measured to the nearest 0.01 foot and recorded. Prior to inserting the water levelindicator into each well, the probe will be decontaminated by rinsing with distilled/deionized water.

Groundwater elevations will be calculated based on the reference point elevations listed in Table 2, lessthe measured depths to groundwater.

5.2 SAMPLE COLLECTION PROCEDURES

Sample collection and analysis for this project shall be conducted in accordance with applicable US EPAmethods and procedures.

Groundwater samples taken from the groundwater extraction wells, compliance wells, observation wells,and selected monitoring wells will be analyzed for selected VOCs, and ammonia, fluoride, and nitrate.Comprehensive Croundwater Monitoring and Sampling PlanMotor Wheel Disposal SitePrepared by Sharp and Associates. Inc.AnadiF.DOCJrev. 4/30/97

13

Page 89: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Groundwater samples will be collected according to the schedule presented in Tables 3. The sampleswill be collected utilizing either dedicated or decontaminated submersible pumps capable of pumping aminimum of one gallon per minute (gpm), bailers fabricated of stainless steel or disposable PVC, ordedicated extraction pumps. Bailer rope will consist of new or dedicated braided polypropylene rope.Decontamination of sampling equipment is discussed in Section 5.3.

Sampling will generally proceed from the lowest to highest expected contaminant concentrations basedon previous analytical results.

5.2.1 Well Purging and Stabilization Testing

Prior to sample collection, static water level measurements will be taken at each well using theprocedures described in Section 5.1. The static water level will be measured to the nearest 0.01 foot andrecorded on the field sampling sheets and in the field logbook. The height of the water column will becalculated by subtracting the static water level from the total depth of each well (see Table 6). The wellvolume will be calculated by multiplying the water column height by the cross sectional area of the well.

At least three well volumes of water will be removed from each well with a decontaminated stainlesssteel or new disposable PVC bailer, sampling pump or a dedicated extraction pump. The bailer ordownhole pumps will be used to purge and sample the two-inch diameter wells. New or dedicatedpolypropylene rope will be used to raise and lower the bailer during sampling and will be discarded afteruse or dedicated to the well. The volume of water purged (bailed wells) or the time and rate of pumpingwill be recorded on the field sampling sheets and in the field logbook. When the well is purged, thepumping or bailing rate will be set so that the water level in the well will not fall below the top of thescreen.

Stabilization tests will be performed during the purging and prior to the sampling of each well. Thepurpose of the stabilization test is to ensure that a sufficient volume of water has been removed from awell to allow representative sampling of the formation water.

During the purging of each well, the parameters representing specific conductance, pH and, temperaturewill be measured in the field. The parameters will be measured before purging is initiated, after eachpurged well volume, and after sampling is completed. These procedures will be continued until at leastthree successive readings of conductivity, pH and temperature are established within 10 percent. Allreadings will be recorded on the field sampling sheets or in the field notebook. The visual condition ofthe groundwater will also be recorded on the field sampling sheets or in the field book.

5.2.2 Sample Collection

Samples will be collected after the well has been adequately purged as defined by Section 5.2.1. Thesample will be collected utilizing either a stainless steel or new disposable PVC bailer, sampling pumpor submersible extraction pump or dedicated extraction pump. Wells that are to be sampled quarterly ormore frequently will be equipped with dedicated pumps. The bailer used for purging will be used tocollect the samples. Bailers equipped with bottom emptying devices will be used to minimize loss ofvolatiles. Containers will be filled in such a manner as to ensure minimal aeration of the sample.Sample collection for analysis of VOCs will be followed by collection of samples for inorganic analyses.

Samples from dedicated submersible pumps will be collected from Teflon tubing attached to a "tee"connected to the discharge end of pump. Sample flow rates will follow the USEPA's low flow protocolsComprehensive Crounttwater Monitoring and Sampling PlanMotor Wheel Disposal SitePrepared 4y Sharp and Associates. Inc.MacnF.DOCIm. 4/3CU97

14

Page 90: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

(100 to 500 ml/minute) for filling the VGA vials and will not exceed 1 gpm during the remainder ofsample collection. Sample containers will be filled to overflowing and then capped to ensure zeroheadspace. Table 4 lists the sample containers.

All samples will be appropriately labeled and all sampling activities recorded on field sampling sheets orin the field logbook. Groundwater samples will be stored immediately after collection in coolers at 4°Cfor transport/shipment to the laboratory. All sampling equipment will be decontaminated after eachsample collection is complete and prior to sampling the next well. Decontamination procedures arepresented in more detail in Section 5.3.

Sampling personnel will wear gloves during all stages of sample collection, handling anddecontamination. Clean or new inner gloves will be worn at each new sampling location. Thedecontaminated equipment will be covered with plastic sheeting, as necessary, to prevent contaminationwhen not in use.

The instruments for collection of field measurements (including temperature, pH and conductivity) willbe calibrated in accordance with the manufacturer's instructions for each unit.

5.2.3 Quality Assurance/Quality Control Samples

The quality control (QC) samples include equipment rinseate blanks, trip blanks, duplicate samples, andlaboratory QC samples. The QC samples are collected at the following frequencies:

• Equipment Rinseate Blank - one per day for each day that non-dedicated equipment is used;collected after the decontamination of equipment used at the highest concentration well (ifknown) and analyzed for all parameters of interest.

• Trip Blank - one per day for sampling days that involve volatile organics; container is suppliedby the laboratory and accompanies the shipped samples.

• Duplicate - one per 20 samples collected; collected at high concentration wells (if known) usingdifferent wells for different sampling rounds; submitted blind (without identification of the well)to the laboratory.

The method for collecting duplicate samples is the same for collecting regular samples. Duplicatesamples should be collected from those wells with suspected contamination or from those wells with thehighest known concentrations of VOCs. Water samples for VOC analysis will be collected directly intothe sample container from the bailer or sampling valve, in order to minimize loss of VOCs. Duplicatesamples will be collected immediately after the regular sample is collected and will be assigned a uniquenumber for submittal to the laboratory as a blind sample.

Equipment rinseate blanks will be collected by pouring distilled/deionized water over decontaminatednon-dedicated sampling equipment. This sample will be collected once per sampling day after thedecontamination of the sampling equipment used for sampling the well with the highest levels of knownVOCs.

Blanks and duplicates will be handled in the same way as the regular samples which they accompany.These samples will be submitted to the laboratory as blind samples.

Comprehensive Groundwater Monitoring and Sampling PlanMotor Wltett Disposal SitePrepared trf Sha/p and Associates. Inc.AaacnF.DOC/rev. 4/30/97

15

Page 91: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

5.3 EQUIPMENT DECONTAMINATION

Decontamination is an important process that is required to prevent the spread of contamination and toprotect the health and safety of on-site personnel. The procedures outlined here are designed to preventthe spread of contamination and possible cross contamination of samples.

All non-dedicated equipment that comes in contact with potentially contaminated materials will bedecontaminated prior to being used. Initially the decontamination will serve to remove any dust or dirtaccumulated during transit to the site or possible residual contamination from previous use. Thereafter,the decontamination will be to remove any residual contamination from the preceding sampling.

All equipment will be disassembled to the extent practicable prior to decontamination. Since organicsare of primary contaminant of concern, decontamination will consist of the following:

• Wash with a non-phosphate based detergent• Rinse with potable water• Double rinse with distilled/deionized water• Final rinse with HPLC grade water

The equipment will then be allowed to air dry and will be wrapped in plastic sheeting until needed.

For wells infrequently sampled by using non-dedicated pumps, the procedures for these type wells willinclude equipment decontamination prior to sampling. The discharge tubing from the sampling pump ison a reel and is an integral part of the sampling pump system, hence will not be discarded betweensampling events. The discharge tubing will be cleaned by pumping non-phosphate, mildly soapy waterthrough the assembly, followed by a complete flush using potable water. The entire external assembly(including the discharge tubing) is washed and decontaminated per the protocol. The equipment rinsesamples are collected from the discharge side of the pump and tubing to document complete cleaning ofthe equipment.

5.4 DISPOSAL OF CONTAMINATED MATERIAL

All purge water from well sampling activities will be contained in an on-site potable water tank anddisposed of by treatment through the treatment plant facilities. Other contaminated material will becontainerized, labeled, and disposed of at an off-site facility in accordance with applicable regulations.

5.5 SAMPLE DOCUMENTATION AND SHIPMENT

Each sample shipment will be subjected to a tracking program. This program is designed to ensure theintegrity of each sample from the time of collection until the samples are delivered to the laboratory foranalysis. The program consists of:

• Sample labels• Field logbook• Chain-of-Custody Forms

Comprehensive Groundwater Monitoring and Sampling PlanHoar What Disposal SitePnpand by Sharp and Associates, Inc.AttacnF.DOC/m 4/30/97

16

Page 92: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

5.5.1 Sample Labels

The sample labels will be used to prevent mis-identification of the samples. Each sample label will befilled out in the field by the sampling team, using indelible (water-proof) ink on prepared sample labels.The label will then be firmly affixed to the sample container.

The sample label will include the following information:

• Client Name• Project Number• Sample Identification Number• Initials of person collecting the sample• Date and time of sample collection• Analysis to be performed on the sample• Number of sample containers collected for the location• Preservative used (if any)

The sample container's cap will also be labeled with the sample identification number.

5.5.2 Field Logbook

Each sample will be noted on the field sampling sheets or in the field logbook at the time of collection.The field logbook will be a bound book with numbered pages. Each day's entry will be signed anddated by the individual making the entry. The sampling form or field logbook will contain the followinginformation:

• Identification of the sample location• Purge rate and method• Collection method and rate as applicable• Sampling sequence• Sample identification (must match sample tag)• Notation of QA/QC sample type and corresponding sample identification• Type of container• Preservatives used• Physical description of sample• Field observations of sampling event• Name of sample collector(s)• Climatic conditions during sampling

5.5.3 Chain-of-Custody Record

In order to establish the documentation necessary to trace sample possession from me time of collection,a chain-of-custody record will be prepared. The chain-of-custody record will accompany the samplesfrom the time of collection until they are delivered to the laboratory for analysis. The chain-of-custodyrecord will identify the following:

• Sample number• Date and time of collection• Sample type

Comprehensive Groundwater Monitoring and Sampling PlanMotor Wheel Disposal SitePrepared try Sharp and Associates, Inc.AtuchF.DOGrrr. 4/30/97

17

Page 93: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

• Number of containers• Parameters requested for analysis• Signature of person(s) involved in chain of possession• Date and time of possession transfer• Method of sample transport.

5.5.4 Sample Custody Seals

The samples can be either delivered by the sampling team to the laboratory, picked up at the site by alaboratory courier, or sent to the laboratory via an express/overnight delivery service. The purpose of thecustody seals is to ensure that the samples are not tampered with in transit from the sampling team to thelaboratory.

Sample custody seals will be placed on each sample to ensure that the samples have not been tamperedwith during their shipment to the laboratory. If the samples are shipped to the laboratory via anexpress/overnight delivery service, the shipping container enclosing the samples will be sealed with twocustody seals, secured with clear plastic tape, before being released from the sampler's custody. Thelaboratory sample custodian will inspect all custody seals and notify the sampler if any of them are brokenon either the cooler or sampling containers. Resampling may be necessary if the custody seals are broken.The custody seal will be signed and dated, by the person responsible for packaging, prior to being placed

on the shipping container.

Comprehensive GrOMlHaer Moniunnf ami Sampling FlatHour Wheel Disposal SitePrepared by Shatp and Associates, Inc.Attodf.DOCJm. 4/30/97

18

Page 94: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

ATTACHMENT G

As-Builts

(to be included after completion of installation)

Page 95: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

APPENDIX B - CQAP

Page 96: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

APPENDIX B

CONSTRUCTION QUALITY ASSURANCE PLAN

Final Design ReportMotor Wheel Disposal SiteSlurp and Associates, Inc9Srpt.doc/rev. 4/30/97

Page 97: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

CONSTRUCTION QUALITY ASSURANCE PLAN

GROUNDWATER REMEDIATION SYSTEMAND ENGINEERED LANDFILL CLOSURE

MOTOR WHEEL DISPOSAL SITELANSING, MICHIGAN

Prepared by:

Sharp and Associates, Inc.982 Crupper AvenueColumbus, Ohio 43229

December 23,1996Revised May 1,1997

Page 98: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

CONSTRUCTION QUALITY ASSURANCE PLANMOTOR WHEEL DISPOSAL SITE

LANDFILL CLOSURELANSING, MICHIGAN

T A B L E O F C O N T E N T S

SECTION 1.0

SECTION 2.0

SECTION 3.0

SECTION 4.0

SECTION 5.0

SECTION 6.0

SECTION 7.0

INTRODUCTION............................................................................................... 1

RESPONSIBILITY AND AUTHORITY.......................................................... 2

2.1 Owner....................................................................................................... 22.2 Owner's Representative............................................................................ 22.3 Responsibilities of the Owner's Representative....................................... 2

QUALITY ASSURANCE PERSONNEL AND INSPECTION....................... 4

3.1 Construction Quality Assurance Officer..................................................43.2 Site Inspection .......................................................................................... 4

3.2.1 Site Inspection Personnel Requirements........................................ 43.2.2 Site Inspection Requirements.........................................................43.2.3 Inspection Documentation.............................................................. 5

SITE CLEARING................................................................................................ 6

SITE GRADING..................................................................................................?

5.1 Base Material Requirements..................................................................... 75.1.1 Lower Unclassified Fill Layer........................................................ 75.1.2 North Slope Structural Fill............................................................. 7

5.2 Base Material Placement.......................................................................... 85.2.1 Lower Unclassified Fill Layer........................................................ 85.2.2 North Slope Structural Fill............................................................. 9

5.3 Site Grading Conformance.......................................................................9

CLAY MINERAL CAP..................................................................................... 10

6.1 Clay Mineral Cap Material Requirements.............................................. 106.2 Clay Mineral Cap Material Placement................................................... 106.3 Verification of Final Clay Cap Thickness.............................................. 11

AGGREGATE DRAINAGE LAYER.............................................................. 13

7.1 Aggregate Drainage Layer Material Requirements................................ 137.2 Aggregate Drainage Layer Placement.................................................... 137.3 Verification of Final Aggregate Drainage Layer Thickness .................. 13

Page 99: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 8.0

SECTION 9.0

SECTION 10.0

SECTION 11.0

SECTION 12.0

SECTION 13.0

SECTION 14.0

SECTION 15.0

TABLE OF CONTENTS (continued)

GEOTEXTILE FABRIC LAYER............... 15

8.1 Geotextile Fabric Requirements............................................................. 158.2 Placement and Acceptance of Geotextile Material................................ 15

13" FROST PROTECTION LAYER.............................................................. 16

9.1 13" Frost Protection Layer Material Requirements ............................... 169.2 13" Frost Protection Layer Placement.................................................... 169.3 Verification of Final Frost Protection Layer Thickness......................... 17

RESOILING LAYER........................................................................................ 18

10.1 Resoiling Layer Material Requirements................................................. 1810.2 Resoiling Layer Material Placement...................................................... 1810.3 Verification of Final Topsoil Layer Thickness ...................................... 19

VEGETATIVE COVER...................................................................................20

11.1 Vegetative Cover Materials Requirements............................................. 2011.2 Vegetative Cover Placement ..................................................................2011.3 Vegetative Cover Acceptance ................................................................21

DRAINAGE AND EROSION CONTROL .....................................................22

12.1 Drainage and Erosion Control Materials................................................ 2212.2 Placement and Acceptance of Drainage and Erosion Control

Materials................................................................................................. 22

PIPELINE ABANDONMENT......................................................................... 23

CHAIN LINK FENCE AND GATES.............................................................. 24

14.1 Chain Link Fence and Gate Materials.................................................... 2414.2 Placement and Acceptance of Chain Link Fence and Gates.................. 24

TRENCHING AND PLACING PIPE.............................................................. 25

15.1 Underground Piping and Backfill Materials .......................................... 2515.2 Trenching, Installing Underground Piping and Backfilling................... 2515.3 Acceptance of Underground Piping ....................................................... 26

SECTION 16.0 SERVICE LINES AND POTABLE WATER PIPING.................................. 27

Page 100: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

TABLE OF CONTENTS (continued)

SECTION 17.0

SECTION 18.0

SECTION 19.0

NATURAL GAS PIPING................................................................................. 28

BUILDING CONSTRUCTION........................................................................ 29

19.1 Materials for Pump House Construction................................................2919.2 Building Construction and Acceptance................................................. 29

SITE DAMAGE REPAIR................................................................................. 30

ATTACHMENTS

Attachment A - Organization Table for Construction

Page 101: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 1.0 INTRODUCTION

The Motor Wheel Disposal Site located in Lansing, Michigan is the subject of a remedial actionplan to provide an engineered closure of the landfill and the installation of a groundwaterextraction and treatment system.

Work at the location known as the Motor Wheel Disposal Site, (MWDS), includes the grading ofon-site inert materials, grading on-site waste materials, placing and grading unclassified fillmaterial, constructing a clay mineral barrier layer, placing an engineered aggregate drainagelayer, placing a 13" frost protection layer and placing top soil. In addition, the site will beseeded and fencing will be installed. A groundwater extraction treatment system wil l beinstalled to restore groundwater to cleanup standards.

Construction QAPP g. jMotor Wheel Disposal SiteSharp and Associates, Inc.CQAP.doc/5/2/97

Page 102: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 2.0 RESPONSIBILITY AND AUTHORITY ^_________________________________ Q

2.1 OWNER

The project owner is the Motor Wheel Site PRP Group consisting of the following:

The Goodyear Tire & Rubber Company1144 East Market StreetAkron, Ohio 44316-0001Contact: Mr. M. E. Whitmore (330) 796-3863

W. R. Grace & Co.6401 Poplar Avenue, Suite #301Memphis, Tennessee 38119Contact: Mr. William Porter (901) 820-2026

Textron Automotive Exteriors750 Stevenson HighwayTroy, Michigan 48083Contact: Mr. Phillip Brown (616) 739-2678

City of LansingBoard of Water and LightP.O. Box 13007123 West Ottawa StreetLansing, Michigan 48901

The project owner shall have final responsibility for the implementation of this remedial actionplan and will participate in all phases of construction and project oversight.

2.2 OWNER'S REPRESENTATIVE

The Engineer and Owner's Representative is:

Sharp and Associates, Inc.982 Crupper AvenueColumbus, Ohio 43299Contact: Ms. Julia Miller. P.E. (614) 841-4650

2.3 RESPONSIBILITIES OF THE OWNER'S REPRESENTATIVE

The owner's representative shall be responsible for the administration and satisfactorycompletion of the project and will assign a project manager/resident engineer to oversee theproject. The project manager/resident engineer shall henceforth be known as the Engineer. TheEngineer shall have immediate charge of the engineering details of the project and shall resolveany issues that arise during construction activities. The Engineer will ensure that all projectConstruction QAPP B_2Motor Wheel Disposal SiteSharp and Associates. Inc.CQAP.doc/5/1/97

Page 103: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

activities are conducted in accordance with the remedial design. The Engineer will oversee allphases of construction, inspection, technical coordination and monitoring of project budget andschedule. The Engineer will also be responsible for assessing the qualifications of constructioncompanies, testing firms and inspection services that will be employed in the construction of thisproject. The Engineer has the authority to reject defective material and to suspend work that isbeing improperly performed. See attachment A for the "Motor Wheel Disposal Site - Table ofOrganization for Construction".

Construction QAPP g_3Motor Wheel Disposal SiteSharp and Associates, Inc.CQAP.doc/S/2/97

Page 104: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 3.0 QUALITY ASSURANCE PERSONNEL^__________AND INSPECTION

3.1 CONSTRUCTION QUALITY ASSURANCE OFFICER

The owner's representative will assign an individual from a qualified firm to act as theConstruction Quality Assurance, (CQA), officer. This representative will ensure that theConstruction Quality Assurance Plan, (CQAP), is implemented to provide compliance with thedesign, the technical specifications and standards. The CQA officer shall have experience inconstruction and remedial action projects with qualifications and education in the civilengineering profession.

3.2 SITE INSPECTION

Site inspection will be provided during all construction activities. The site inspector shall beresponsible for ensuring that construction activities and materials incorporated in the project arein compliance with the plans, technical specifications and applicable standards. The siteinspector shall keep and maintain a daily diary and all pertinent project documentation. Theproject diaries, test reports, survey data and any related documentation shall be a part of thepermanent project records and shall become the property of the PRP group and shall be stored atthe offices of the PRP group.

3.2.1 Site Inspection Personnel Requirements

The site inspector shall have prior experience in civil construction inspection including grading,earthwork, erosion control, surveying, piping, drainage, concrete and structural components.The owner's representative shall select site inspectors based on qualifications and related priorexperience.

3.2.2 Site Inspection Requirements

The site inspector shall be present during all construction related activities and shall beauthorized to inspect all work performed and materials furnished. The site inspector shallprovide documentation of all work in a daily diary format. Documentation shall include thecontractor's conformance to the plans and specifications, special conditions encountered,resolution of problems, corrective measures taken and shall be recorded in the project dailydiary.

Frequency of visual inspection shall be at least three times per working day or as required by thework in progress. Other inspection requirements shall be as specified within the CQAP.

The site inspector shall have the authority to notify the contractor when the work or materials donot conform to the plans, specifications, or the provisions of the contract and shall have theauthority to direct corrective action if the contractor's work is not in conformance with the plansand specifications. The site inspector shall have the authority to reject materials that do not meetspecification requirements or suspend work until any questions can be referred to and decided bythe Engineer.

Construction QAPP 9.4Motor Wheel Disposal SiteSharp and Associates. Inc.CQAP.doc/5/2/97

Page 105: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

The project manager/resident engineer and site inspector shall be provided access to all parts ofthe work and shall be furnished with such information and assistance by the contractor as neededto make a complete and thorough inspection.

Any work done or materials used without inspection may be ordered removed and replaced at thecontractor's expense.

3.2.3 Inspection Documentation

The site inspection documentation shall include a daily diary during all construction activities.This daily diary shall include weather, on site personnel, equipment, pay items, specialconditions, conflicts, resolutions, construction activities, testing activities, conformance to plansand specifications, corrective work, adherence to the health and safety plan, and any otherinformation pertinent to the project.

A photo log will be kept to document all phases of the work in progress.

Other project documentation required shall be, but not limited to, soil test reports, nuclear testreports, survey data, borrow pit information, bills of lading, and bills of materials.

Construction QAPPMotor Wheel Disposal SiteSharp and Associates. Inc.CQAP.doc/5/2/97

Page 106: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 4.0 SITE CLEARINGM^^MH^MMB^^MMM^HM^MM^M^^MI^MM^^MiMHB^^HMM

Clearing and grubbing shall consist of complete removal of woody vegetation (including stumps)with a trunk diameter of 2 inches or greater. All woody vegetation shall be mechanicallychipped, shredded, or otherwise processed so that the greatest dimension in any direction of asingle particle is less than 2 inches. All cleared areas will be mowed to within 6 inches of theexisting surface. All cut and processed plant material shall be removed from the landfill andstockpiled at the location indicated on the plans. The contractor shall implement all necessaryerosion prevention controls.

Visual inspection will be required to ensure that clearing and grubbing operations are inconformance to the plans and technical specifications. The site inspector shall be present duringclearing and grubbing activities and shall provide documentation as to conformance.

The site inspector shall have the authority to direct corrective action if the contractor's work isnot in conformance with the plans and specifications.

Construction QAPPMotor Wheel Disposal SiteSharp and Associates, Inc.CQAP.doc/5/2/97

Page 107: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 5.0______________________SITE GRADING

5.1 BASE MATERIAL REQUIREMENTS

5.1.1 Lower Unclassified Fill Layer

The base material shall be unclassified fill used to achieve base grading elevations as shown inthe plans. The material used for unclassified fill shall consist of excavated on-site material aswell as material from other construction excavations and overburden from sand and graveloperations.

The contractor shall direct sampling and testing of the offsite unclassified fill, from each source,by an independent soils laboratory to determine necessary data to establish field controls forcompliance to the specified in-place compaction of 92% of Standard Proctor Density.(Moisture-Density Test ASTM D698). Potential borrow areas shall be sampled from bore holesor test pits at the rate of one per acre per two feet of subsurface horizon. Spoils from pipelineexcavations to be utilized as borrow shall be sampled at the rate of one sample for every distinctsubsurface horizon for every 1000 feet of trench length.

The site inspector shall confirm that the material used for unclassified fill has been sampled andtested prior to use and meets the requirements of the technical specifications. Documentationfrom the independent soils laboratory shall be provided to the Engineer and inspector for eachmaterial source indicating field parameters required to meet the specified in-place compaction.This documentation shall become a part of the project records.

Visual inspection shall be required to ensure that all lower unclassified fill material delivered tothe site remains in compliance with the technical specifications. If the material deviates from theapproved representative sample based on visual inspection, the contractor shall be notified. Thecontractor shall cease excavating and placing material and shall retest the material at the rate ofone test per 3,000 cubic yards of material in place in the borrow area.

Visual inspection shall be required to ensure that material imported to the site is from thepreviously approved source. The contractor shall provide documentation as to the source of thematerial if requested.

All soils testing reports and visual inspections shall become a part of the project records.

5.1.2 North Slope Structural Fill

Only on-site material designated in the plans shall be used to construct the north slope to a 3:1(H:V) slope. This material has been shown to provide the necessary characteristics in terms ofgrain size distribution and shear strength to allow construction of a stable 3:1 slope.

The project inspector shall confirm that material used to construct the north slope is from theareas designated on the plans and shall be documented as part of the daily diary.

Material imported for construction of the north slope shall be granular in nature, classified underthe Unified Soil Classification System (ASTM D2487) as SP, SW, SC, SM, or GC. TheConstruction QAPP g_7Motor Wheel Disposal SiteSharp and Associates. Inc.CQAP.doc/5/2/97

Page 108: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

minimum internal friction angle shall be 25° (as determined by ASTM method D3080) at 95% ofthe maximum Standard Proctor density. The contractor shall direct sampling and testing of theoffsite material, from each source, by an independent soils laboratory to determine compliance tothe technical specifications and to determine necessary data to establish field controls forcompliance to the specified in-place compaction of 95% of Standard Proctor Density.(Moisture-Density Test ASTM D698). Potential borrow areas shall be sampled from bore holesor test pits at the rate of one per acre per two feet of subsurface horizon. Spoils from pipelineexcavations to be utilized as borrow shall be sampled at the rate of one sample for every distinctsubsurface horizon for every 1000 feet of trench length.

The site inspector shall confirm that the material used for north slope structural fill has beensampled and tested prior to use and meets the requirements of the technical specifications.Documentation from the independent soils laboratory shall be provided to the Engineer andinspector for each material source indicating field parameters required to meet the specified in-place compaction. This documentation shall become a part of the project records.

Visual inspection shall be required to ensure that all north slope fill material delivered to the siteremains in compliance with the technical specifications. If the material deviates from theapproved representative sample based on visual inspection, the contractor shall be notified. Thecontractor shall cease excavating and placing material and shall retest the material at the rate ofone test per 3,000 cubic yards of material in place in the borrow area.

Visual inspection shall be required to ensure that material imported to the site is from thepreviously approved source. The contractor shall provide documentation as to the source of thematerial if requested.

All soils testing reports and visual inspections shall become a part of the project records.

5.2 BASE MATERIAL PLACEMENT

5.2.1 Lower Unclassified Fill Layer

Unclassified fill shall be placed in loose lifts of no greater than 8 inches and shall be compactedto no less than 92% of Standard Proctor density.

Visual inspection shall be required to ensure that the material is placed in loose lifts of 8 inchesor less and that the material is compacted after each lift. The project inspector shall verifycompliance at least three times per working day.

Nuclear density testing shall be performed to ensure 92% compaction and water content withinthe laboratory parameters established for the material for every 500 cubic yards (cy) of fillmaterial placed using ASTM D2922. Test reports shall become part of the project records.

The site inspector shall have the authority to direct corrective action if the contractor's work isnot in conformance with the plans and specifications.

Construction QAPPMotor Wheel Disposal SiteSharp and Associates, Inc.CQAP.doc/5/2/97

Page 109: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

5.2.2 North Slope Structural Fill

On-site and imported structural fill shall be placed in loose lifts of no greater than 8 inches andshall be compacted to no less than 95% of Standard Proctor density.

Visual inspection shall be required to ensure that the material is placed in loose lifts of 8 inchesor less and that the material is compacted after each lift. The project inspector shall verifycompliance at least three times per working day.

Nuclear density testing shall be performed to ensure 95% compaction and water content withinthe laboratory parameters established for the material for every 500 cubic yards (cy) of fil lmaterial placed using ASTM D2922. Test reports shall become part of the project records.

The site inspector shall have the authority to direct corrective action if the contractor's work isnot in conformance with the plans and specifications.

5.3 BASELINE GRADING CONFORMANCE

Grade stakes shall be required and the contractor shall be responsible for establishing allne:essary survey controls for layout staking in conformance with the plan lines, grades.elevations, and dimensions. A licensed surveyor shall certify all confirming horizontal andvertical survey data.

The contractor shall survey 50% of the control points in the grading plan and shall verify that90% of those surveyed points are within 0.3 feet of the plan specified grade with positivedrainage maintained at all times.

Deficiencies of more than 0.3 feet of the required grade shall be corrected by either removing oradding material to obtain the specified grade.

The contractor shall provide the Engineer with horizontal and vertical survey data certified by alicensed surveyor. The survey data shall provide sufficient information to allow verification ofcompliance to the plan grades by the Engineer.

Visual inspection shall also be required to ensure that the site grading is in conformance to theplans and specifications and shall be free of debris, boulders, ruts, rills, depressions or any othertopography of obstruction that would prevent proper construction of the subsequent layers.

The site inspector shall have the authority to direct corrective action if the contractor's work isnot in conformance with the plans and specifications.

Construction QAPPMotor Wheel Disposal SiteSharp and Associates, Inc.CQAP.doc/5/2/97

Page 110: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 6 . 0 M I N E R A L C A P

6.1 CLAY MINERAL CAP MATERIAL REQUIREMENTS

The clay mineral material used in construction of the cap shall be classified as CL or CH underthe United Soils Classification System (USCS) using ASTM D2487. The clay mineral materialshall also have a permeability of no greater than 1 x 10EE-7 cm/sec as determined using ASTMD5084, falling head permeability test. The potential borrow area shall be sampled from boreholes or test pits at the rate of one per acre per two feet of subsurface horizon. An independentsoils testing laboratory shall be employed to ensure compliance to this classification.

The contractor shall direct sampling and testing of the clay mineral material, from each source,by an independent soils laboratory to determine necessary data to establish field controls forcompliance to the specified in-place compaction of 95% of Standard Proctor Density.(Moisture-Density Test ASTM D698).

The contractor shall supply the borrow area geotechnical data and soil sampling test results to theEngineer and site inspector for approval prior to beginning construction of the cap.

Visual inspection shall be required to ensure that all clay mineral material delivered to the siteremains in compliance with the technical specifications. If the material deviates from theapproved representative sample based on visual inspection, the contractor shall be notified. Thecontractor shall cease excavating and placing material and shall retest the material at the rate ofone test per 3,000 cubic yards of material in place in the borrow area.

Visual inspection shall be required to ensure that material imported to the site is from thepreviously approved source. The contractor shall provide documentation as to the source of thematerial if requested.

All soils testing reports and visual inspections shall become a part of the project records.

6.2 CLAY MINERAL CAP MATERIALS PLACEMENT

The clay mineral cap shall be placed in loose lifts of not more 8 inches and shall be compactedafter each lift to 95% of the maximum Standard Proctor density. The clay fill surface shall bekept moistened to prevent shrinkage cracks. For prolonged delays in clay placement the surfaceshall be protected with a six (6) inch layer of unconsolidated material or covered with plasticsheets.

Visual inspection using a graduated rod shall be required to ensure that the material is placed inloose lifts of 8 inches or less and that the material is compacted after each lift. The site inspectorshall verify compliance at least three times per working day.

Nuclear density testing shall be performed to ensure at least 95% compaction and water contentwithin 2% to 4% wet of the established optimum water content for the material for every 500

Construction QAPP B-10Motor Wheel Disposal SiteSharp and Associates. Inc.CQAP.doc/5/2/97

Page 111: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

cubic yards (cy), or at least one per lift, of fill material placed using ASTM D2922. Nuclear test••;• reports shall become part of the project records.

A one point Standard Proctor test shall be used to confirm validity of the optimum moisturerange as determined from the borrow soil testing. The frequency of inspection shall be everythird and fifth lifts.

A moisture density relation using ASTM D698 shall be checked every 5,000 cubic yards ofplacement to determine if the representative optimum water content as previously determined isstill valid.

Undisturbed samples of the compacted clay layer shall be taken and tested for permeabilityduring the advancement of the construction. Samples shall be taken for every 10,000 cubic yardsof compacted clay layer, or a minimum of three tests per cover. These samples shall be testedusing the Falling Head Permeability Test, ASTM D5084. In situ permeability shall be no greaterthan 1 x 10EE-7 cm/sec.

•^ The site inspector shall have the authority to direct corrective action if the contractor's work isnot in conformance with the plans and specifications.

All cavities and holes formed during testing shall be filled with Bentonite as directed by theEngineer.

6.3 VERIFICATION OF FINAL CLAY CAP THICKNESS

Grade stakes shall be required and the contractor shall be responsible for establishing allnecessary survey controls for layout staking in conformance with the plan lines, grades,dimensions, and cap thickness. A licensed surveyor shall certify all confirming horizontal andvertical survey data. Holes from grade stakes shall be filled with Bentonite as directed by theEngineer.

Settlement platforms, as specified in the design plans and technical specifications shall berequired for monitoring clay layer thickness. The contractor shall be responsible for furnishingall materials for the construction, placing, monitoring, and maintaining of settlement platforms.

The settlement platforms shall be placed at the locations as specified and shall be approved bythe Engineer.

The clay layer thickness at each settlement platform shall be recorded for conformance.Minimum clay layer thickness shall be 3 feet with up to 0.3 feet additional thickness allowed.

Deficiencies in the minimum clay layer thickness shall be corrected.

Visual inspection shall also be required to ensure that the site grading is in conformance to theplans and specifications and shall be free of debris, boulders, ruts, rills, depressions or any othertopography of obstruction that would prevent proper construction of the subsequent layers.

Construction QAPP g. J JMotor Wheel Disposal SiteSharp and Associates. Inc.CQAP.doc/5/2/97

Page 112: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

The site inspector shall have the authority to direct corrective action if the contractor's work isnot in conformance with the plans and specifications.

Construction QAPP B-12Motor Wheel Disposal SiteSharp and Associates, Inc.CQAP.doc/S/2/97

Page 113: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 7.0 AGGREGATE DRAINAGE LAYER

7.1 AGGREGATE DRAINAGE LAYER MATERIAL REQUIREMENTS

The aggregate drainage layer material shall have a permeability of no less than 1 x 10EE-1cm/sec as determined by ASTM Method D-2434, constant head permeability test. Thecontractor shall direct sampling and testing of the aggregate drainage layer material, from eachsource, by an independent soils laboratory. Potential borrow areas shall be sampled from boreholes or test pits at the rate of one per acre per two feet of subsurface horizon. Spoils frompipeline excavations to be utilized as borrow shall be sampled at the rate of one sample for everydistinct subsurface horizon for every 1000 feet of trench length.

The contractor shall supply the borrow area geotechnical data and soil sampling test results to theEngineer and site inspector for approval prior to beginning construction of the cap.

Visual inspection shall be required to ensure that all aggregate drainage layer material deliveredto the site remains in compliance with the technical specifications. If the material deviates fromthe approved representative sample based on visual inspection, the contractor shall be notified.The contractor shall cease excavating and placing material and shall retest the material at the rateof one test per 3,000 cubic yards of material in place in the borrow area.

Visual inspection shall be required to ensure that material imported to the site is from thepreviously approved source. The contractor shall provide documentation as to the source of thematerial if requested.

All soils testing reports and visual inspections shall become a part of the project records.

7.2 AGGREGATE DRAINAGE LAYER PLACEMENT

The aggregate drainage material shall be placed to the thickness and dimensions as shown in theplans.

Visual inspection using a graduated rod shall be required to ensure that the material is placed tothe required thickness of 6 inches. The site inspector shall verify compliance at least three timesper working day.

The site inspector shall have the authority to direct corrective action if the contractor's work isnot in conformance with the plans and specifications.

7.3 VERIFICATION OF FINAL AGGREGATE DRAINAGE LAYER THICKNESS

Grade stakes shall be required and the contractor shall be responsible for establishing allnecessary survey controls for layout staking in conformance with the plan lines, grades,dimensions, and drainage layer thickness. A licensed surveyor shall certify all confirminghorizontal and vertical survey data.Construction QAPP Q. J 3Motor Wheel Disposal SiteSharp and Associates, Inc.CQAP.doc/512/97

Page 114: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Settlement platforms, as specified in the design plans and technical specifications shall be ''"~*s

required for monitoring the aggregate drainage layer thickness. The contractor shall beresponsible for furnishing all materials for the construction, placing, monitoring, and maintainingof settlement platforms.

The settlement platforms shall be placed at the locations as specified and shall be approved bythe Engineer.

The aggregate drainage layer thickness at each settlement platform shall be recorded forconformance. Minimum aggregate drainage layer thickness shall be 6 inches with up to 0.2 feetadditional thickness allowed.

Deficiencies in the minimum aggregate drainage layer thickness shall be corrected.

The contractor shall provide the Engineer with horizontal and vertical survey data certified by alicensed surveyor. The survey data shall provide sufficient information to allow verification ofcompliance to the plan grades by the Engineer.

Visual inspection shall also be required to ensure that the site grading is in conformance to theplans and specifications and shall be free of debris, boulders, ruts, rills, depressions or any othertopography of obstruction that would prevent proper construction of the subsequent layers.

The site inspector shall have the authority to direct corrective action if the contractor's work isnot in conformance with the plans and specifications.

Construction QAPP B-14Motor Wheel Disposal SiteSharp and Associates. Inc.CQAP.doc/5/2/97

Page 115: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 8.0 GEOTEXTILE FABRIC LAYER

8.1 GEOTEXTILE FABRIC REQUIREMENTS

The geotextile fabric for placement between the drainage layer the unclassified fill layer shall bea nonwoven material meeting the requirements of the technical specifications. The contractorshall furnish certified test data for all material used on the site.

Each shipment of geotextile fabric shall be inspected for certified test data which shall becomepart of the project records. No material shall be accepted without certified test data. Each roll ofgeotextile fabric shall be wrapped in opaque, watertight wrapping.

8.2 PLACEMENT AND ACCEPTANCE OF GEOTEXTILE MATERIAL

The areas on which the geotextile fabrics are to be placed shall be accepted as to grade andcompaction and shall be free from debris, roots, rocks or other objects that could damage thefabric. Overlaps of geotextile fabric shall be as specified in the plans and technicalspecifications. Geotextile fabrics shall be secured with pins when necessary. On slopes steeperthan 10% all seams shall be continuously sown and end to end horizontal seams shall not beallowed. On all slopes, the geotextile fabric shall be continuously kept in tension.

Each shipment of geotextile fabric shall be visually inspected for damage prior to use.

Visual inspection of the prepared areas shall be required and accepted prior to placing anygeotextile fabric.

The site inspector shall have the authority to direct corrective action if the contractor's work isnot in conformance with the plans and specifications.

Construction QAPP g. 15Motor Wheel Disposal SiteSharp and Associates, Inc.CQAP.doc/5/2/97

Page 116: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 9.0 13" FROST PROTECTION LAYER

9.1 13" FROST PROTECTION LAYER MATERIAL REQUIREMENTS

The material used for the 13" frost protection layer shall consist of excavated on-site material aswell as material from other construction excavations and overburden from sand and graveloperations.

The contractor shall direct sampling and testing of the material from each source, by anindependent soils laboratory to determine necessary data to establish field controls forcompliance to the specified in-place compaction of 92% of Standard Proctor density. (Moisture-Density Test ASTM d698). The contractor shall also demonstrate through laboratory testing thatthe frost protection layer has a permeability of no greater than 4.2 x 10EE-5 cm/s. (Falling HeadPermeability Test ASTM D5084). Potential borrow areas shall be sampled from bore holes ortest pits at the rate of one per acre per two feet of subsurface horizon. Spoils from pipelineexcavations to be utilized as borrow shall be sampled at the rate of one sample for every distinctsubsurface horizon for every 1000 feet of trench length.

The site inspector shall confirm that the material used for the 13" frost protection layer has beensampled and tested prior to use and meets the requirements of the technical specifications.Documentation from the independent soils laboratory shall be provided to the inspector for eachmaterial source indicating field parameters required to meet the specified in-place compaction.This documentation shall become a part of the project records.

Visual inspection shall be required to ensure that material imported to the site is from thepreviously approved source. The contractor shall provide documentation as to the source of thematerial if requested.

All soils testing reports and visual inspections shall become a part of the project records.

9.2 13" FROST PROTECTION LAYER PLACEMENT

The 13" frost protection layer shall be placed in loose lifts of no greater than 8 inches and shallbe compacted to no less than 92% of Standard Proctor density.

Visual inspection shall be required to ensure that the material is placed in loose lifts of 8 inchesor less and that the material is compacted after each lift. The project inspector shall verifycompliance at least three times per working day.

Nuclear density testing shall be performed to ensure 92% compaction and water content withinthe laboratory parameters established for the material for every 500 cubic yards (cy) of fillmaterial placed using ASTM D2922. Test reports shall become part of the project records.

The site inspector shall have the authority to direct corrective action if the contractor's work isnot in conformance with the plans and specifications.

Construction QAPP g. 15Motor Wheel Disposal SiteSharp and .Associates, Inc.CQAP doc/5/2/97

Page 117: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

9.3 VERIFICATION OF FINAL 13" FROST PROTECTIONLAYER THICKNESS

Grade stakes shall be required and the contractor shall be responsible for establishing allnecessary survey controls for layout staking in conformance with the plan lines, grades,dimensions, and the frost protection layer thickness. A licensed surveyor shall certify allconfirming horizontal and vertical survey data.

Settlement platforms, as specified in the design plans and technical specifications shall berequired for monitoring the frost protection layer thickness. The contractor shall be responsiblefor furnishing all materials for the construction, placing, monitoring, and maintaining ofsettlement platforms.

The settlement platforms shall be placed at the locations as specified and shall be approved bythe Engineer.

The frost protection layer thickness at each settlement platform shall be recorded forccnformance. Minimum frost protection layer thickness shall be 13 inches with up to 0.2 feetadditional thickness allowed.

Deficiencies in the minimum frost protection layer thickness shall be corrected.

The contractor shall provide the Engineer with horizontal and vertical survey data certified by alicensed surveyor. The survey data shall provide sufficient information to allow verification ofcompliance to the plan grades by the Engineer.

Visual inspection shall also be required to ensure that the site grading is in conformance to theplans and specifications and shall be free of debris, boulders, ruts, rills, depressions or any othertopography of obstruction that would prevent proper construction of the subsequent layers.

The site inspector shall have the authority to direct corrective action if the contractor's work isnot in conformance with the plans and specifications.

Construction QAPP g. ] jMotor Wheel Disposal SiteSharp and Associates, Inc.CQAP.doc/5/2/97

Page 118: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 10.0 RESOILING LAYER

10.1 RESOILING LAYER MATERIAL REQUIREMENTS

The material used for the resoiling layer shall have a USDA texture classification of sandy clayloam, clay loam, silty clay loam, loamy coarse sand, loamy sand, loamy fine sand or loamy veryfine sand. The pH range of the resoiling layer material shall be 5.0 to 7.8 and have an availablewater capacity of 0.05 to 1.0 in/in. The resoiling layer material shall have a coarse fragmentweight percentage of 0% to 20% by weight. In addition the material shall have a minimumphosphorus level of 60 Ib./acre and minimum of exchangeable potassium level of 260 Ib./acre.All material provided shall be free of contaminants and any compounds or elements that areharmful to human health or the environment.

The contractor shall direct sampling and agronomic soil testing of the resoiling layer material,from each source. Agronomic soil testing shall include pH, lime deficit, available phosphorus,exchangeable potassium, calcium and magnesium; cation exchange capacity, percent basesaturation, sodium, salt, sulfur, copper, nickel, lead, mercury, cadmium and zinc. All testingshall be conducted by an independent testing laboratory approved <n advance by the Engineer.Approval for use may be conditional based on the supplementation of the proposed resoilinglayer including the use of nitrogen, phosphorous, potassium and lime.

The site inspector shall confirm that the material used for resoiling layer has been sampled andtested prior to use and meets the requirements of the technical specifications. Documentationfrom the independent soils laboratory shall be provided to the inspector for each material source.This documentation shall become a part of the project records.

Visual inspection shall be required to ensure that material imported to the site is from thepreviously approved source. The contractor shall provide documentation as to the source of thematerial if requested.

All soils testing reports and visual inspections shall become a part of the project records.

10.2 RESOILING LAYER MATERIAL PLACEMENT

The resoiling layer material shall be placed to the thickness and dimensions as shown in theplans.

Visual inspection using a graduated rod shall be required to ensure that the material is placed tothe required thickness of 6 inches. The site inspector shall verify compliance at least three timesper working day.

The site inspector shall have the authority to direct corrective action if the contractor's work isnot in conformance with the plans and specifications.

Construction QAPP B-18Motor Wheel Disposal SiteSharp and Associates, Inc.CQAPdof/5/2/97

Page 119: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

10.3 VERIFICATION OF FINAL RESOILING LAYER THICKNESS

Grade stakes shall be required and the contractor shall be responsible for establishing allnecessary survey controls for layout staking in conformance with the plan lines, grades,dimensions, and resoiling layer thickness. A licensed surveyor shall certify all confirminghorizontal and vertical survey data.

Settlement platforms, as specified in the design plans and technical specifications shall berequired for monitoring resoiling layer thickness. The contractor shall be responsible forfurnishing all materials for the construction, placing, monitoring, and maintaining of settlementplatforms.

The settlement platforms shall be placed at the locations as specified and shall be approved bythe Engineer.

The resoiling layer thickness at each settlement platform shall be recorded for conformance.Minimum resoiling layer thickness shall be 6 inches with up to 0.2 feet additional thicknessallowed.

Deficiencies in the minimum resoiling layer thickness shall be corrected.

The contractor shall provide the Engineer with horizontal and vertical survey data certified by alicensed surveyor. The survey data shall provide sufficient information to allow verification ofcompliance to the plan grades by the Engineer.

Visual inspection shall also be required to ensure that the site grading is in conformance to theplans and specifications and shall be free of debris, boulders, ruts, rills, depressions or any othertopography of obstruction that would prevent proper construction of the subsequent layers.

The site inspector shall have the authority to direct corrective action if the contractor's work isnot in conformance with the plans and specifications.

Construction QAPP B-19Motor Wheel Disposal SiteSharp and Associates, Inc.CQAP.doc/5/2/97

Page 120: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 11.0 VEGETATIVE COVER

11.1 VEGETATIVE COVER MATERIALS REQUIREMENTS

The seed required for vegetative cover shall be as specified in the technical specifications. Allseed shall be labeled with germination rate and purity as tested within the last 9 months.

Mulching materials shall be unweathered weed-free small grain, hay or straw.

Visual inspection shall be required to ensure seed and mulch delivered to the job conforms to thetechnical specifications. Seed shall be labeled with a current germination rate and purity (withinthe last 9 months), and shall not be wet, moldy or otherwise defective. Mulch materials shall beas specified and shall be in an unweathered condition.

The site inspector has the authority to reject any or all seeding and mulching materials that donot comply with the plans and technical specifications.

11.2 VEGETATIVE COVER PLACEMENT

The seedbed shall be thoroughly prepared to at least a 3 inch depth. The seedbed shall be free ofdebris, clumps and rocks greater than 3 inches in any dimension. Soil amendments asdetermined during agronomic soil testing, by an independent laboratory at the expense of thecontractor, shall be thoroughly incorporated in the seedbed at the previously decided rates. Theseed shall be applied to the prepared seed bed at the mixture rates specified in the technicalspecifications. Planting depths shall be 1/4 inch to 1/2 inch deep. Mulch shall be appliedimmediately after seeding at the rate of 2 tons/acre as specified. Mulching shall be anchored inplace using a mulching tool or fibrous netting. The technical specifications require thatmulching tools crimp the mulch at least 2 inches into the seedbed. Fibrous netting shall beplaced as per the manufacturer's recommendation. Seeding must be done within 48 hours of theplacement of the topsoil. Seeding shall not take place when the ground is frozen or snowcovered.

The contractor shall be responsible for obtaining the correct quantities of materials based on thespecified rates and the size of the area to be seeded and shall provide weight tickets or otherdocumentation as required.

mixtures, rate ofThe site inspector shall verify proper seedbed preparation, correct seedapplication and mulching procedures.

The site inspector shall have the authority to direct corrective action if the contractor's work isnot in conformance with the plans and specifications.

Construction QAPP B-20Motor Wheel Disposal SiteSharp and Associates, Inc.CQAP.doc/5/2/97

Page 121: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

11.3 VEGETATIVE COVER ACCEPTANCE

The contractor shall guarantee a stand of vegetative cover and shall re-seed areas that have notadequately germinated.

The seeded areas shall be visually inspected for adequate growth. Corrective action shall berequired if growth is of poor quality. The owner's representative reserves the right to determinewhich areas require corrective action.

Construction QAPP g_2 \Motor Wheel Disposal SiteSharp ami Associates. Inc.CQAP.doc/5/2/97

Page 122: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 12.0 DRAINAGE AND EROSION CONTROL

12.1 DRAINAGE AND EROSION CONTROL MATERIALS

Underdrain piping, perforated and non-perforated, shall be High Density Polyethylene (HDPE).Corrugated, perforated HDPE piping shall conform to ASTM F 405, type C, class 1. Riprapmaterials shall conform to MDOT specification 8.19.03 for heavy riprap.

All material shall be visually inspected for conformance to the technical specifications. Inaddition the contractor shall supply material certification/documentation verifying that thematerials imported to the site conform to the plans and technical specifications. Material shallbe approved prior to use.

12.2 PLACEMENT AND ACCEPTANCE OF DRAINAGE AND EROSIONCONTROL MATERIALS

The contractor shall place all drainage and erosion control materials in accordance with the plansand specifications.

The site inspector shall visually inspect and document the placement of drainage and erosioncontrol materials for compliance to the plans and technical specifications.

The site inspector shall have the authority to direct corrective action if the contractor's work isnot in conformance with the plans and specifications.

Construction QAPP B-22Motor Wheel Disposal SiteSharp and Associates, Inc.CQAP.doc/5/2/97

Page 123: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 13.0 PIPELINE ABANDONMENT

The contractor shall abandon existing underground culvert piping as identified on the plans.Abandonment procedures shall be as detailed in the technical specifications.

The site inspector shall visually inspect and document all abandonment procedures forcompliance to the plans and technical specifications.

The site inspector shall have the authority to direct corrective action if the contractor's work isnot in conformance with the plans and specifications.

Construction QAPP B-23Motor Wheel Disposal SiteSharp and Associates. Inc.CQAP.doc/5/2/97

Page 124: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 14.0 CHAIN LINK FENCE AND GATES

14.1 CHAIN LINK FENCE AND GATE MATERIALS

The contractor shall provide all fencing and gate materials as detailed in the technicalspecifications and shall supply certification from the manufacturer as to conformance to thosespecifications. The contractor shall also provide a bill of materials listing fencing componentsand quantities.

Concrete for post footings shall conform to the technical specifications and the contractor shallsubmit for approval a concrete mix design from an independent materials laboratory. Concretedelivered to the project shall be from a previously approved supplier and shall be accompaniedby delivery tickets indicating total quantity and batch weights used.

The site inspector shall visually inspect all materials imported to the project site for conformanceto the plans and specifications. Manufacturer's material certifications for fencing materials shallbe checked against the technical specifications for conformance. No material shall beincorporated into the project without prior approval.

The site inspector shall have the authority to disapprove for use materials imported to the projectsite that do not conform to the plans and technical specifications.

14.2 PLACEMENT AND ACCEPTANCE OF CHAIN LINK FENCE AND GATES

The contractor shall place chain link fence and gates as detailed and dimensioned on the plansand technical specifications. The contractor shall survey and stake the layout of the fence andgates prior to beginning construction.

The site inspector shall visually inspect the proposed fence and gate layout for conformance andapproval prior to beginning construction. The site inspector shall visually inspect all fencing andgate installations for post embedment, horizontal deflection, post spacing, bracing and hangingof fabric to ensure compliance to the plan and technical specifications.

The site inspector shall have the authority to direct corrective action if the contractor's work isnot in conformance with the plans and specifications.

Construction QAPP B-24Motor Wheel Disposal SiteSharp and Associates, Inc.CQAP.doc/5/2/97

Page 125: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 15.0 TRENCHING AND PLACING PIPE

15.1 UNDERGROUND PIPING AND BACKFILL MATERIALS

The materials for piping and fittings shall be as detailed in the plans and in the technicalspecifications. The contractor shall provide manufacturer's certification stating that the materialhas been manufactured, tested and inspected in accordance with all ASTM/DFN specifications.The material shall be stamped with the country of origin, the manufacturer's name, pressurerating and ASTM specification.

Backfill materials shall be fine clean bank sand and shall meet the requirements for backfill asspecified by the city of Lansing.

All material shall be visually inspected for conformance to the plans and technical specifications.In addition the contractor shall supply material certification/documentation verifying that thematerials imported to the site conform to the plans and technical specifications. All materialshall be approved prior to use.

The site inspector shall have the authority to disapprove for use materials imported to the projectsite that do not conform to the plans and technical specifications.

15.2 TRENCHING, INSTALLING UNDERGROUND PIPING AND BACKFILLING

The contractor shall excavate trenches for the installation of underground piping in accordancewith the locations and elevations shown in the plans. The bottom of the trench shall be firmlycompacted to provide uniform bearing over the entire length of the pipe section. The contractorshall provide all shoring and protection as required to ensure safe working conditions and toprotect passers-by. All trenching shall be left open until all work is inspected and approved. Thecontractor shall remove and dispose of all excess excavations.

The contractor shall install piping at roadway and railroad crossings in accordance with thetechnical specifications.

Pipe shall be of the type and size specified in the plans and technical specifications. Joints shallbe made in accordance with the manufacturer's specifications. Underground clamps shall berequired for all 1/8 bends, flanges, spigot pieces, and etc. Care shall be taken to prevent theinfiltration of debris, soil or stones from into the piping.

Pipe that has been tested and approved shall be backfilled with approved clean bank sand.Backfill shall be placed in 6 inch layers and thoroughly and carefully tamped, with a vibratorytamper, until the pipe has a cover of not less than 1 foot.

The site inspector shall visually inspect the proposed piping layout for conformance andapproval prior to inspection. Manufacturer's material certifications for piping and appurtenancesshall be checked against the technical specifications for conformance No material shall beincorporated into the project without prior approval. The site inspector shall ensure thatConstruction QAPP B-^SMotor Wheel Disposal SiteSharp and Associates, Inc.CQAP.doc/5/2/97

Page 126: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

trenching is in accordance with the plans and technical specifications and that all shoring, safetyfencing and other safety items are in place. All backfilling shall be inspected for conformance tothe technical specifications.

The site inspector shall have the authority to direct corrective action if the contractor's work isnot in conformance with the plans and specifications.

15.3 ACCEPTANCE OF UNDERGROUND PIPING

All underground piping shall be pressure tested in accordance with the technical specifications.Piping joints shall be pressure tested and accepted prior to backfilling.

The site inspector shall witness all pressure testing and ensure that testing is as per the technicalspecifications. The contractor shall provide a test report for each section of piping pressuretested which shall contain all pertinent information as to test pressure location of piping, size ofpiping, test pressure, duration of test and disposition. This record shall become a permanent partof the project records. The site inspector shall approve all underground piping before backfillingcan proceed.

The site inspector shall have the authority to direct corrective action if the contractor's work isnot in conformance with the plans and specifications.

Construction QAPP B-26Motor Wheel Disposal SiteSharp and Associates, Inc.CQAP.doc/5/1/97

Page 127: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 16.0 SERVICE LIVES AND POTABLE WATER PIPING

The contractor shall install service line as per the technical specifications.Potable water lines shall be installed and materials for shall be as directed by the City of LansingBoard of Water and Light.

The site inspector shall ensure that the contractor complies with the technical specifications andwith the directions of the City of Lansing Board of Water and Light.

The site inspector shall have the authority to direct corrective action if the contractor's work isnot in conformance with the plans and specifications.

Construction QAPP B-27Motor Wheel Disposal SiteSharp and Associates, Inc.CQAP.doc/5/1/97

Page 128: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 17.0 NATURAL GAS PIPING

The contractor shall install natural gas piping as per the technical specifications and inaccordance with the local gas company and the City of Lansing requirements.

The site inspector shall ensure that the contractor complies with the technical specifications andwith the directions of the local gas company and the City of Lansing requirements.

The site inspector shall have the authority to direct corrective action if the contractor's work isnot in conformance with the plans and specifications.

Construction QAPP B-28Motor Wheel Disposal SiteSharp and Associates. Inc.CQAP.doc/S/2/97

Page 129: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 18.0 BUILDING CONSTRUCTION

18.1 MATERIALS FOR PUMP HOUSE CONSTRUCTION

The contractor shall provide a bill of materials for all building construction for approval prior tocommencing construction. All materials shall be as shown in the plans and technicalspecifications and shall be accompanied by certification, manufacturer's documentation or shopdrawings as applicable.

Concrete for slabs and footings shall conform to the technical specifications and the contractorshall submit for approval a concrete mix design from an independent materials laboratory.Concrete delivered to the project shall be from a previously approved supplier and shall beaccompanied by delivery tickets indicating total quantity and batch weights used. Fresh concreteshall be tested and cylinders shall be cast and tested by an independent testing laboratory inaccordance with ASTM standards C172-90, C143-90a, C31/C31M-95, C173-94aand C39-94.

The site inspector shall visually inspect all materials imported to the project site for conforrnanceto the plans and specifications. Manufacturer's material certifications, shop drawings anddocumentation for building materials shall be checked against the technical specifications forconformance. No material shall be incorporated into the project without prior approval. Allmaterial certifications, documentation, shop drawings and test reports shall be part of the projectrecords.

The site inspector shall have the authority to disapprove for use materials imported to the projectsite that do not conform to the plans and technical specifications.

18.2 BUILDING CONSTRUCTION AND ACCEPTANCE

The contractor shall lay out the pump house as detailed and dimensioned on the plans andtechnical specifications. The layout shall be approved prior to beginning construction.All electrical installations shall be governed by the National Electric Code (NEC).

The site inspector shall visually inspect the proposed pump house layout for conformance andapproval prior to construction. The site inspector shall verify that construction is in compliancewith the plans and technical specifications and all local and national codes as applicable.

The site inspector shall have the authority to direct corrective action if the contractor's work isnot in conformance with the plans and specifications.

Construction QAPP B-29Motor Wheel Disposal SiteSharp and Associates, Inc.CQAP doc/5/2/97

Page 130: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 19.0 SITE DAMAGE REPAIR

The contractor shall be responsible for all damage to buildings, sidewalks, roadways, driveways,existing utility installations trees and any private or public property that occurs due to thecontractor's construction activities.

The site inspector shall inspect and document all damage due to the contractor's constructionactivities. All repairs shall be subject to the City of Lansing standards. A record of all repairsshall be a part of the project records.

Construction QAPP B-30Motor Wheel Disposal SiteSharp and Associates, Inc.CQAP.doc/5/2/97

Page 131: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Attachment A

Organization Table for Construction

Construction QAPPMotor Wheel Disposal SiteSlurp and Associates. Inc.CQAP.doc/S/I/97

Page 132: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

MOTOR WHEEL DISPOSAL SITETABLE OF ORGANIZATION FOR CONSTRUCTION

PRP GROUPTEXTRON AUTOMOTIVE EXTERIORS

PHILLIP BROWNW.R. GRACE & COMPANY

WILLIAM PORTERTHE GOODYEAR TIRE& RUBBER COMPANY

MARK WHITMORE

CITY OF LANSINGBOARD OF WATER AND LIGHT

PROJECT MANAGERAND

OWNER'S REPRESENTATIVETOOO STRUTTMANN

SHARP AND ASSOCIATES, INC.

RESIDENT ENGINEERAND

CQA OFFICERCRAIG ESCHBERGER

SHARP AND ASSOCIATES, INC.

LANDFILL CAPPING CONTRACTORROBERT GARRETT-PRESIDENT

BOBBY STILES-SUPERINTENDENTGARRETT CONSULTING, INC.

SOILS TESTING TECHNICIANAND INSPECTOR

TIMOTHY PRIDESTS CONSULTANTS. LTD

GROUNDWATER EXTRACTIONSYSTEM CONTRACTORKIM DRAEGER-PRESIDENT

SCOTT AMMARMAN-SUPERINTENDENTAIC, INC.

c ATTA JENT A TO CQAF

Page 133: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

E n v i r o n m r n t a lM u t i n e e r s and Sc ien t i s t s

AND ASSOCIATES. INC.

c.

'•f."Cr

Page 134: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

APPENDIX C

HEALTH AND SAFETY PLAN

Final Design ReportMotor Wheel Disposal SiteSharp and Associates, Inc9Srpt.doc/rev. 4J30/97

Page 135: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

APPENDIX 1) - RAP

a:c

Page 136: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

APPENDIX D

REMEDIAL ACTION WORK PLAN

Final Design ReportMotor Wheel Disposal SiteSharp and Associates. Inc95rpt.doc/rev. 4/30/97

Page 137: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

REMEDIAL ACTION PLAN

GROUNDWATER REMEDIATION SYSTEMAND ENGINEERED LANDFILL CLOSURE

MOTOR WHEEL DISPOSAL SITELANSING, MICHIGAN

Prepared by:

Sharp and Associates, Inc.982 Crupper AvenueColumbus, Ohio 43229

December 23,1996Revised May 1,1997

Page 138: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

_ T A B L E O F C O N T E N T S' • ' ' "N

1.0 I N T R O D U C T I O N . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11.1 General Background and Site History............................................................. 11.2 Previous Studies.......................................................................................21.3 Record of Decision ...................................................................................2

2.0 REMEDIATION SCHEDULE ............................................................................. 3

3.0 REMEDIAL ACTION T E A M . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53.1 Project Owner ......................................................................................... 53.2 Owner's Representative.............................................................................. 5

4.0 QUALITY ASSURANCE.................................................................................... 84.1 Construction Quality Assurance Officer.... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84.2 Site Inspection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8

^^ 4.2.1 Site Inspection Personnel Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84.2.2 Site Inspection Requirements ... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84.2.3 Inspection Documentation................................................................. 9

5.0 REFERENCES............................................................................................... 10

RAP.DOC

Page 139: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 1 INTRODUCTION

The Motor Wheel Disposal Site Group has contracted with Sharp and Associates, Inc. (SHARP), HWHEngineers (HWH), and Fishbeck, Thompson, Carr, & Huber (FTC&H) to prepare the RemedialAction Plan for the Motor Wheel Disposal Site (MWDS). This Remedial Action Plan covers theOrganization and the Project Schedule for the installation of the landfill cap and the Glacial Aquifergroundwater remediation system. This document is being prepared in order to comply with the Recordof Decision (ROD) (September, 1991).

1.1 GENERAL BACKGROUND AND SITE HISTORY

The MWDS is a 24-acre property located at 1401 Lake Lansing Road on the northeast edge of the Cityof Lansing, Michigan. The site lies in the NE 1/4 of the SW 1/4 of Section 3 in Lansing Township(T4N, R2W), Ingham County, Michigan. The property was used by Motor Wheel Corporation as adisposal site for industrial wastes from 1938 until about 1978 (US EPA, 1991). The types of disposedwastes included solid and liquid industrial wastes, such as paints, solvents, liquid acids, caustics, andsludges. Wastes were disposed of on the property in tanks, barrels, seepage ponds, and open filloperations (US EPA, 1991).

Between 1970 and 1982, at least three cleanup actions, which resulted in the excavation and off sitedisposal of waste materials, were initiated (Hunter/Keck Environmental Services [Hunter/Keck], 1990).In 1970, the MDNR requested that the Motor Wheel Corporation remove solid wastes, paint sludges,and oils from seepage pond areas for disposal offsite. Some of the excavated materials were disposedoff site and the former pond areas were backfilled (US EPA, 1991). Three 10,000-gallon tanks, theircontents and contaminated soil, and fill surrounding the tanks were removed and disposed offsite inDecember 1982. An unknown number of drums were also disposed of offsite at this time (US EPA,1991).

In 1978, MSV Associates acquired the property and began open-pit sand and gravel mining. Themining operations exposed some of the buried industrial wastes. The exposed materials weresubsequently excavated, stockpiled on the western pan of the site, and covered with clay (US EPA,1991).

The site was placed on the National Priorities List on October 4, 1986 (50 FR 41015). On June 26,1987, Motor Wheel Corporation, W.R. Grace & Co. (Grace), and The Goodyear Tire & RubberCompany signed an AOC agreeing to conduct a Remedial Investigation (RI) and Feasibility Study (FS)at the MWDS (US EPA, 1991). Following USEPA's ROD in September 1991; Goodyear, Grace,Textron, Inc., and the Lansing Board of Water and Light entered into a consent agreement to conductthe Remedial Design.

Site gravel/sand mining operations were discontinued in 1987. MSV Associates is the current owner ofthe property. However, the site is presently inactive (US EPA, 1991).

RAP.DOC D-lSharp and Associates. Inc.

Page 140: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

1.2 PREVIOUS STUDIES

In accordance with the AOC, an RI for the site was conducted by Hunter/Keck. The results of the RIwere summarized in a report dated February 8, 1990, and titled, Remedial Investigation Report, MotorWheel Disposal Site, Lansing, Michigan. An FS was conducted by ENSR Consulting and Engineering(ENSR). The results of this study were summarized in a report titled, Final Draft, Feasibility StudyReport for Motor Wheel Disposal Site, dated May 1991. The Declaration for the Record of Decision(ROD) was signed by the US EPA on September 30, 1991. An investigation of the Saginaw aquifer atthe MWDS was conducted by Fishbeck, Thompson, Carr an Huber (FTC&H), and the resultssummarized in a report titled, Saginaw Aquifer Investigation Report for the Motor Wheel Disposal Site,Lansing, Michigan, dated April 1992. Additional investigations were performed and a predesign wasdeveloped by FTC&H. These activities are summarized in Final Additional Studies/Predesign Report,1996

1.3 RECORD OF DECISION

The ROD for the first operable unit at the MWDS was signed on September 30, 1991. The firstoperable unit included the waste mass and the groundwater contamination in the perched and glacialaquifers at the MWDS. The groundwater contaminants requiring remediation, as determined by theRI, and the risk and toxicity assessments, are chlorinated volatile organic compounds (VOCs) andammonia.

RAP.DOC D-2Sharp and Associates, Inc.

Page 141: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 2________________REMEDIATION SCHEDULE

The planned remedial action schedule is presented on the following pages. The schedule has beendeveloped using Timeline Software. Timeline will be used by SHARP'S project manager to providereal-time monitoring and scheduling updates as the project progresses.

Initiation of site preparation and mobilization activities for construction of the landfill cap andgroundwater remediation system will occur in early April, 1997. Completion of the landfill cap isanticipated in October, 1997 with completion of the groundwater remediation system occurring inSeptember, 1997.

The Motor Wheel PRP group will provide monthly written progress reports to MDEQ and willschedule meetings as required to resolve outstanding issues. The monthly reports will include monthlyupdates and contractors logs as well as a summary of work completed.

RAP. DOC D-3Sharp and Associates, Inc.

Page 142: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Motor Wheel Disposal SiteLandfill Cap and Groundwater Remediation System

ScheduleRo , , ..Task Name

1 Submit Final Design to EPA/MDEQ2 Planned Field Activities3 Slope Stability Evaluation4 Aerial Photo5 Landfill Well Abandonment6 Extraction Well Borings7 Profile BW&L Wells8 Material resource availability9 Permits

1 0 Approval of Water and Air Permit1 1 Railroad Permit Approval12 Resoive Access Agreement w/M13 Puolic Meeting14 SelecPRfirm15 Hold Public Meeting16 EPA/MDEQ Review17 Final Design Complete

1 9 Deveioc bidder short list20 Interview bidders21 Send out RFP22 Award Contract^3 Ground Water Treatment System24 Well Cnllmg25 Glacai wells Zone 1 & 226 G!ac;a! Wells Perched27 Glaciai Wells Zone 323 Sagmaw Wells (monitonng)29 Sagmaw Well(s) Extraction30 Piping Zone 1 &231 Piping Zone 332 Building33 Electncal34 Startup35 Landfill Construction36 Mobilization37 Cleanng and Grubbing38 Offsite Fill39 Landfill Base Cut/Fill40 Landfill Cap41 Drainage Layer42 Unclassified Fill

_43_Vegetative Cap44 Seeding45 Operation and Maintenance

e, r- 1996 1"7 1998

Duration otart End Sep Qa Noy ^ Jgn Feb Mar Apr May Jun Ju| Aug Sep Oct Nov Dec Jan

2.00 d Dec/20/S6 Dec/23/96 i , I *

5.00 d Oct/30/96 Nov/08/96 ! mf i ,5.60 w Dec/02/96 Jan/1 0/97J ! : IHMiMt3.00 w Mar/10/97 Mar/31/971 . ! ! »•»4.00 w Mar/10/97 Apr/07/97 , ; : ••»12.00d Mar/03/97 Mar/18/97 ! : : •»18.00d Jan/15/97 Feb/12/97| j ' , «^^ :

1.00m Jan/13/97 Feb/14/97 BBB2.92m Jan/10/97 Aor/14/97 I H^ HBB HB BB B1.00m Jan/10/97 Feb/11/97: MMI

27.50 d Mar/07/97 Apr/14/971 -••••••2.00m Dec/23/96 Feb/25/97! "••••• •1.00m Feb/25/97 Mar/31/97! -m^m^t-

19.50d Jan/03/97 Feb/02/97! MM^ :10.00d Feb/02/97 Feb/18/97: -••••18.00d Mar/03/97 Mar/28/97! - "»»22.50 d Mar/28/97 Apr/28/97! : ^ "»

44.50 d Apr/28/97 Jul/06/97i * ™" ^ ^ ^5.00 d Sep/29/97 Oct/06/97 _ :•

50.00 d Jul/06/97 Sep/16/97i - ••i«^ ^31.00d Apr/28/97 Jun/13/97i - •"• .39.00 d Jun/20/97 Aug/18/97 : . - ^^^^^

34.50 d Sep/16/97 Nov/07/97 j : ' " ^^^^~1.00m May/24/97 Jun/27/97 : ^^^^1.00m Sep/26/97 Oct/28/97 : ~^^^^4.00 w Oct/28/97 Nov/28/97 : : "•• —"*1.

5.00 d Apr/28/97 May/05/97 -»5.00 d Apr/28/97 May/05/97 , , »

35.00 d May/05/97 Jun/27/97 j -«""" ""-35.00d May/19/97 Jul/14/97 ; ^^^^^^^^^1.00m Jul/07/97 Aug/05/97l • • ; ~ ^™*3.00 w Aug/05/97 Aug/26/97 ' ^"*2.00 w Aug/22/97 Sep/08/97 : , , "•^3.00 w Sep/08/97 Sep/29/97! ""l2.00w Sep/29/97 Oct/14/971 *^ !

2.50m Nov/29/97 Feb/20/98 • : ^ ""l

Pnnted: Mar/20/97 MWDS0320 tipPage 1 TJS

Milestone 1 SummaryFixed Delav -

Page 143: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 3_________________REMEDIAL ACTION TEAM

3.1 PROJECT OWNER

The project owner is the Motor Wheel Site PRP Group consisting of the following:

The Goodyear Tire and Rubber Company1144 East Market StreetAkron, Ohio 44316-0001Contact: Mr. M. E. Whitmore (330) 796-3863

W. R.. Grace & Co.6401 Poplar AveMemphis, Tennessee 38119Contact: Mr. William Porter (901) 820-2026

Textron Automotive Exteriors750 Stevenson HighwayTroy, Michigan 48083(616) 739-2678

City of LansingBoard of Water and LightP.O. Box 13007123 West Ottawa StreetLansing, Michigan 48901

The project owner shall have final responsibility for the implementation of this remedial action plan andwill participate in all phases of construction and project oversight.

3.2 OWNER'S REPRESENTATIVE

The Engineer and Owner's Representative is:

Sharp and Associates, Inc.982 Crupper AvenueColumbus, Ohio 43299Contact: Ms. Julia Miller, P.E. (614) 841-4650

The owner's representative shall be responsible for the administration and satisfactory completion ofthe project and will assign a project manager/engineer to oversee the project. The projectmanager/engineer shall have immediate charge of the engineering details of the project and shallresolve any issues that arise during construction activities. The project manager/engineer will ensurethat all project activities are conducted in accordance with the remedial design. The projectmanager/engineer will oversee all phases of construction, inspection, technical coordination andmonitoring of project budget and schedule. The project manager/engineer will also be responsible for

RAP.DOC D-5Sharp and Associates, Inc.

Page 144: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

assessing the qualifications of construction companies, testing firms and inspection services that will beemployed in the construction of this project The project manager/engineer has the authority to rejectdefective material and to suspend work that is being improperly performed. A Table of Organizationhas been provided on the following page.

RAP. DOC D-6Sharp and Associates, Inc.

Page 145: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

MOTOR WHEEL DISPOSAL SITETABLE OF ORGANIZATION FOR CONSTRUCTION

PRP GROUPTEXTRON AUTOMOTIVE EXTERIORS

PHILLIP BROWNW.R. GRACE & COMPANY

WILLIAM PORTERTHE GOODYEAR TIRE& RUBBER COMPANY

MARK WHITMORE

CITY OF LANSINGBOARD OF WATER AND LIGHT

PROJECT MANAGERAND

OWNER'S REPRESENTATIVETODO STRUTTMANN

SHARP AND ASSOCIATES, INC.

RESIDENT ENGINEERAND

CQA OFFICERCRAIG ESCHBERGER

SHARP AND ASSOCIATES. INC.

ILANDFILL CAPPING CONTRACTOR

ROBERT GARRETT-PRESIOENTBOBBY STILES-SUPERINTENDENT

GARRETT CONSULTING, INC.

SOILS TESTING TECHNICIANAND INSPECTOR

TIMOTHY PRIDESTS CONSULTANTS, LTD

GROUNDWATER EXTRACTIONSYSTEM CONTRACTORKIM DRAEGER-PRESIDENT

SCOTT AMMARMAN-SUPERINTENDENTAIC, INC.

ATTACHMENT A TO CQAP

Page 146: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 4 QUALITY ASSURANCE

4.1 CONSTRUCTION QUALITY ASSURANCE OFFICER

The owner's representative will assign an individual from within a qualified firm to act as theConstruction Quality Assurance, (CQA), officer. This representative will ensure that the ConstructionQuality Assurance Plan, (CQAP), is implemented to provide compliance with the design, the technicalspecifications and standards. The CQA officer shall have experience in construction and remedialaction projects with qualifications and education in the civil engineering profession.

4.2 SITE INSPECTION

Site inspection will be provided during all construction activities. The site inspector shall beresponsible for ensuring that construction activities and materials incorporated in the project are incompliance with the plans, technical specification and applicable standards. The site inspector shallkeep and maintain a daily diary and all pertinent project documentation. The project diaries, testreports, survey data and any related documentation shall be a part of the permanent project records.

4.2.1 Site Inspection Personnel Requirements

The site inspector shall have prior experience in civil construction inspection including grading,earthwork, erosion control, surveying, piping, drainage, concrete and structural components. Theowner's representative shall select site inspectors based on qualifications and related prior experience.

4.2.2 Site Inspection Requirements

The site inspector shall be present during all construction related activities and shall be authorized toinspect all work performed and materials furnished. The site inspector shall provide documentation ofall work in a daily diary format. Documentation shall include the contractor's conformance to theplans and specifications, special conditions encountered, resolution of problems, corrective measurestaken and shall be recorded in the project daily diary.

Frequency of visual inspection shall be at least three times per working day or as required by the workin progress. Other inspection requirements shall be as specified within the CQAP.

The site inspector shall have the authority to notify the contractor when the work or materials do notconform to the plans, specifications, or the provisions of the contract and shall have the authority todirect corrective action if the contractor's work is not in conformance with the plans and specifications.The site inspector shall have the authority to reject materials that do not meet specification requirementsor suspend work until any questions can be referred to and decided by the project manager/engineer.

The project manager/engineer and site inspector shall be provided access to all parts of the work andshall be furnished with such information and assistance by the contractor as needed to make a completeand thorough inspection.

RAP.DOC D-8Sharp and Associates. Inc.

Page 147: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

Any work done or materials used without inspection may be ordered removed and replaced at thecontractor's expense.

4.2.3 Inspection Documentation

The site inspection documentation shall include a daily diary during all construction activities. Thisdaily diary shall include weather, on-site personnel, equipment, pay items, special conditions, conflicts,resolutions, construction activities, testing activities, conformance to plans and specifications,corrective work, adherence to the health and safety plan, and any other information pertinent to theproject.

Other project documentation required shall be, but not limited to, soil test reports, nuclear test reports,survey data, borrow pit information, bills of lading, and bills of materials.

RAP.DOC D-9Sharp and Associates, Inc.

Page 148: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SECTION 5 REFERENCES

1. U.S. EPA, 1994, Administrative Order of Consent: United States of America; Plaintiffs vs.The Motor Wheel Corporation; Defendants, Civil Action No. VW-92-C-151

2. U.S. EPA, 1992, Scope of Work: Remedial Design Motor Wheel Disposal Site, InghamCounty, Michigan, May 12, 1992

3. U.S. EPA, 1992, Statement of Work: Remedial Action Motor Wheel Disposal Site, InghamCounty, Michigan, May 12, 1992

4. Sharp and Associates, Inc., 1996, 30% Design Report for the Glacial Aquifer GroundwaterRemediation System and Engineered Landfill Closure at the Motor Wheel Disposal Site inLansing, Michigan, prepared for the Motor Wheel PRP Group, July 3, 1996

5. U.S. EPA, 1991 Record of Decision, Motor Wheel Disposal Site, Lansing, Michigan,September 30, 1991

6. FTC&H, 1996, Final Additional Studies/Predesign Report for the Motor Wheel Disposal Site,Lansing, Michigan, March 15, 1996

7. Hunter/Keck, Remedial Investigation Report, Motor Wheel Disposal Site, Lansing, Michigan,February 8, 1990.

8. ENSR Consulting and Engineering, Final Draft Feasibility Study Report for the Motor WheelDisposal Site, Lansing, Michigan, May, 1991.

9. U.S. EPA, Declaration for the Record of Decision, Motor Wheel Disposal Site, Lansing,Michigan, September 30, 1991.

10. FTC&H, Saginaw Aquifer Investigation Report for the Motor Wheel Disposal Site, Lansing,Michigan, April, 1992.

RAP.DOC D-10Sharp and Associates. Inc.

Page 149: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

APPKNDIX E - LANDFILL DRAWINGS

-?»".••

Sl;

Page 150: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

APPENDIX E

LANDFILL DRAWINGS

Final Design KeponMotor Wheel Disposal SiteSharp and Associates, IncJSrpi.doc/rev. 4/30/97

Page 151: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

MOTOR WHEEL DISPOSAL SITE CLOSURE :*.:| t

MICHIGAN

MOTOR WHEELDISPOSAL SITE

aLTC

o0-

ySr 2£,..-

Project Status:

Q.DC

GENERAL LOCATION MAP VICINITY MAP

DRAWING INDEX

DRAWINGJUMBE8 DESCRIPTION

1 TITLt SHEET2 GENERAL NOTES1 EXISTING SITE PLAN4 BASE GRADING PLAN5 CLAY CAP GRADING PLANC STORM WATER MANAGEMENT SITE MAP7 GRADING PLAN ELEVATIONS SHEET 18 GRADING PLAN ELEVATIONS SHEET 29 GRADING PLAN ELEVATIONS SHEET 1

10 PROPOSED SITE PLAN11 DETAILS12 SITE CROSS SECTIONS SHEET 113 SITE CROSS SECTIONS SHEET 214 FENCE DETAIL15 PIPE GATE DETAIL16 EROSION CONTROL PLAN

Comm No.Oro«n Br SHARP ASSOC.

BJ« Dolt: 4/2V&7

Page 152: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

1 CONSTRUCTION QUALITY CONTROL WILL BE MAXIMIZED BY THE PROCEDURES AND THE STANDARDS SET FORTH IN THETECHNICAL SPECIFICATIONS. AS WELL AS THE CONSTRUCTION DUALITY ASSURANCE PLAN (COAP). IT IS THE RESPONSIBILITYOF THE CONTRACTOR TO MAINTAIN COMPLIANCE WITH BOTH THE TECHNICAL SPECIFICATIONS AND THE COAP. IT IS STRONGLYRECOMMENDED THAT THE CONTRACTOR FULLY UNDERSTAND THE PROCEDURES AND REQUIREMENTS GIVEN IN THE CQAPIN ORDER TO ACCURATELY COMPUTE HIS PRICING.

2 ALL MANUFACTURED MATERIALS SHALL BE NEW ALL MATERIALS AND WORKMANSHIP SHALL BE OF THE HIGHEST QUALITYAVAILABLE OR UTILIZED WITHIN THE INDUSTRY.

3. THE CONTRACTOR IS RESPONSIBLE FOR FOLLOWING AND OPERATING WITHIN THE GUIDELINES AND REQUIREMENTS SETFORTH BY OSHA. EPA, AND ANY OTHER REGULATORY AGENCY OR POLITICAL ENTITY HAVING JURISDICTION OVER THEPROJECT. THIS INCLUDES THE PROCUREMENT OF ANY AND ALL PERMITS. BONDS. OR OTHER ASSURANCES REQUIREDBY LOCAL. STATE. OR FEDERAL AGENCIES.

4. UTILITY LOCATIONS ON THE DRAWINGS ARE PROVIDED IN GOOD FAITH WITHOUT ANY WARRANTY TO THEIR COMPLETENESS ORACCURACY. THE CONTRACTOR IS RESPONSIBLE FOR LOCATING ALL UTILITIES WHICH MAY BE IMPACTED BY HIS WORK. THECONTRACTOR IS RESPONSIBLE FOR THE COMPLETE REPAIR OF ANY UTILITY DAMAGED BY THE CONTRACTOR. TO THE SATIS-FACTION OF THE UTILITY OWNER, AT NO COST TO THE PROJECT OWNER.

5. CONTRACTOR'S ACTIVITIES SHALL BE RESTRICTED TO THOSE PROPERTIES SHOWN ON THE DRAWINGS AS BEING OWNED BY"MSV ASSOCIATES", OR "WR GRACE". EXCEPT WHERE NOTED.

6. CONSTRUCTION ACTIVITIES AT ANY WASTE DISPOSAL SITE HAVE THE POTENTIAL OF EXPOSING THE CONTRACTOR, HISPERSONNEL, PERSONNEL OF OTHER CONTRACTORS HIRED BY THE OWNER TO PERFORM WORK AT THIS PROJECT SITETO POTENTIALLY HAZARDOUS SITUATIONS AND ELEMENTS. THE CONTRACTOR IS RESPONSIBLE FOR IMPLEMENTING ANDENFORCING SAFE WORK PRACTICES AND A SAFE WORK POLICY AT ALL TIMES DURING THE CONTRACT PERIOD. SAFEWORK PRACTICES INCLUDED IN THE POLICY SHALL INCLUDE BUT NOT BE LIMITED TO:

A. CONFINED SPACE ENTRY;B. GASES FROM MATERIALS USED IN CONSTRUCTION;C. GASES FROM EXISTING WASTE MATERIALS;D. USE OF TRENCHING. SHEETING AND SHORING;E. SCAFFOLDING;F. MATERIALS HANDLING;G. DRILLING;H. OPERATION OF EQUIPMENT;I. SAFETY OF PUBLIC DURING PROGRESS OF WORK.

7. THE CONTRACTOR SHALL COMPLY WITH BASIC PROVISIONS OF OSHA HEALTH AND SAFETY STANDARDS 29CFR 1910 ANDGENERAL CONSTRUCTION STANDARDS (29CFR 1926) AS APPROPRIATE TO THIS CONSTRUCTION AND SITE ACTIVITY.

8. THIRD PARTY CONSTRUCTION AND MATERIAL SPECIFICATIONS REFERENCED BY THESE DRAWINGS MAY INCLUDE THOSE PUBLISHEDBY BUT NOT LIMITED TO: AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM). AMERICAN ASSOCIATION OF STATE HIGHWAYTRANSPORTATION OFFICIALS (AASHTO), AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI). AMERICAN PETROLEUM INSTITUTE (API).UNITED STATES DEPARTMENT OF AGRICULTURE (USDA), AND MICHIGAN DEPARTMENT OF TRANSPORTATION STANDARD SPECIFICATIONSFOR CONSTRUCTION (MOOT).

9. THE CONTRACTOR IS RESPONSIBLE FOR SITE SECURITY. THE OWNER SHALL NOT BE LIABLE FOR DAMAGE TO OR LOSS OFCONTRACTOR'S EQUIPMENT OR MATERIAL. THE OWNER SHALL NOT BE LIABLE FOR COST OF LOST OR DAMAGED MATERIALS STOREDON SITE OR INSTALLED. FOR WHICH THE CONTRACTOR HAS RECEIVED PARTIAL OR FULL PAYMENT FROM THE OWNER. THROUGHOUTTHE DURATION OF THE CONTRACT. SECURITY OF SUCH ITEMS BELONGS TO THE CONTRACTOR.

10. THE CONTRACTOR SHALL CONDUCT HIS WORK ACTIVITY IN SUCH A MANNER AS TO PREVENT THE RELEASE OF ANY EXISTINGMATERIALS (WASTE OR OTHERWISE) TO THE ENVIRONMENT. THIS INCLUDES BUT IS NOT LIMITED TO THE RELEASE OF LEACHATE.CONSTRUCTION DEWATERING DISCHARGES AND/OR THE ESCAPE OF ANY LIQUID GAS OR SOLID MATERIAL TO THE SURROUNDINGENVIRONMENT WHICH WOULD BE CONSTRUED AS THE DISCHARGE OF A WASTE OR CONTAMINANT TO THE ENVIRONMENT.

11. INSTALLATION OF PERCHED EXTRACTION WELL SHALL BE PERFORMED BY OTHERS BETWEEN PLACEMENT OF THE FROST PROTECTIONLAYER AND THE RESOILING LAYER. EACH CONTRACTOR SHALL CONDUCT HIS WORK SO AS NOT TO INTERFERE WITH OR HINDER THEPROGRESS OR COMPLETION OF THE WORK BEING PERFORMED BY OTHER CONTRACTORS. CONTRACTORS WORKING ON THE SAMEPROJECT SHALL COOPERATE WITH EACH OTHER AS DIRECTED.

ngsi'j<<»°

~ *~ 7 *~m o < c*2 5 2

Sletu*

D*iM*piivilOCwwvucM* Oee»n»ia

Comm. Mo.Dro-i BfSHMP »SSOClout Dote 4/2V97

CCLJLJI—ZOujzo

Page 153: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

EXISTINGSITEPLAN

I f f ?? ?f iI s

#5104

MOTOR WHfF.1. DISPOSAL SITE CLOSURELANSING. MICHIGAN

MOTOR WHFEL PRP GROUP

HARPAND ASSOCIATES, INC.982 Crupper Avenue

Columbus. Ohio 43229

Page 154: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

BASEGRADING

PLAN

? « ? 3SSB?S ? p'0|tc' "'""""• #5'04» I mil I MOTOF

? « , 'IZIl - I AMCIIf * f.S«

r MOTOR WHEEL DISPOSAL SITE CLOSURELANSING. MICHIGAN

Cil«nl: MOTOR WHFEL PRP GROUP

SHAREDAND ASSOCIATES, INC.982 Crupper Avenue

Columbus, Ohio 43229

Page 155: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

CLAY CAPGRADING

PLAN

MOTOR WHFEL DISPOSAL SITE CLOSURELANSING. MICHIGAN

aunt: MOTOR WIIFFI PRP GROUP

SHARE.AND ASSOCIATES, INC982 Crupper Avenue

Columbus. Ohio 43229

Page 156: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

05104MOTOR WHEEL DISPOSAL SITE CLOSURELANSING. MICHIGANSTORM WATER

MANAGEMENTPLAN

DIM: MOTOR WHFFI. PRP GROUP

SHARPAND ASSOCIATES, INC982 Crupper Avenue

Columbus. Ohio 43229

Page 157: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

i i i i i lHii i Ililllillli - ' - j - i

tittftttttt i t t t f t t t t t t ? . t t t t f t t s t t t t , t t f f t f t t t t ' f s t t t t t t t t t t i i i t s i t i * t t t t t: i x m s i i g g K i g E f g * E K 5 5 ! E ! ! g g *s?.*$>m***s *.tKsssi.ls*\*i*isy$li*lillZylUilvllltuti ; x x z x x z z x z i xlil

l i f i f f f f f f i ||f| f e f f 3 |iiitlii iiii

«

Pi

t i S a a i i s K s s f c a t i j i 5 i S B • 3 K • 8 « Is SSae i l f S » S 8 S B E l < 5 a

iiiliiiifi

ft S J;11

Siiij||ittttii

I f i t i l ^ l\nillr-\ s3

3OODDO y P'o)eet R«ler«ncr 05104

GRADING PLANELEVATIONS

SHEET 1

Mo.

y S

;;ff *

i * ~MOTOR WHEEL DISPOSAL SITE CLOSURELANSINC, MICHIGAN

MOTOR WMFFI PRP GROUP

SHAREAND ASSOCIATES, INC982 Crupper Avenue

Columbus. Ohio 43229

Page 158: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

T t l t t i t t

*

e 8 e «if fe B 5 *

33|l"3333333 333J3335.33353

ss

itiiilii

tf H

* i ! I

«SI a g a § B B « a a

mule

a 8 5 »is B 5 a e B «« * s s "3333*53353""s » a v : k a s a « B 8 s

.« a a . . r.SI?689

333I3JJ3J33J3353 33333P8MM333:

1

CO

1* * fllll * MOTOR WHFEI DISPOSAL SITE CLOSURE f^

GRADING PLAN f** iVir a LANSING, MICHIGAN XtfAWPELEVATIONS s| .) \ ^^^^

OhLLI £. "ft '" 982 Crupper Avenue5 g * CIM: MOTOR WICEL PRP GROUP Columbus, Ohio 43229

Page 159: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

ESTIMATED TOP (f iO*CT ESTIMATEDTOP or WASTt UKO.ASSnED FINISH

H- HQ. NOftTH,HC FASTtNC tLTVATlM FIL. L1SYAT1QH CSAQE

459060 '»**090 UMNtM. •».» £«402 459060 tWOD I****.. •"•"> _ « " »403 ——— -^tfovf: —————————— - —————————— - ——— -__-- .— - - ———————— i«i» -v-404 -- - •«'««** — -- ————— - ——— ——————————401 45*010401 45901 0407 4»010

108 «590>04QS 4590104)0 4590104-1 458*93417 4190104?3 45B*B<

41i T -^ t . - : ————— •- --- - - -41i 4509*0

4:7 4589*041 « 458960.-9 4589K

7- 4589*0V 458*602J 45892424 458*60K, ' j •

17 45691078 4SW1029 4S»1030 458*10

13 45B910U 458910» 4*026035 4*02603fc 46021037 460160IB 460160x «BQ110

44C 460010

441 45*960*42 459710«3 459660*u 45M1D«5 459*10446 459580447 459510

448 459510

449 4594*0

«5C 4594*0.51 45*410

12 459410

S3 4594105* 4193*0ii 418360» «Sfl36C57 459310be 459J10

46= 459»C«- '59160*6? 459260*«3 45871046* 45S210 . - —

945800 IWNOM BTO-»945850 l»«MOWi KJ.BO945900 WKuam 1-Ot9*5950 IWKHOX*" 7' M

946QQC UNKMOW T'-M94*050 lWWO*t "-«9-160*1 868.7 W'W»4e,00 l*«t.O«N M.20»46106 866.2 T4 to

945000 utKMOt*. 87383943030 UNKNOWN 889 50945900 UNKHO*. 8*9.90145950 UN«t(0«»" 870.30«45»84 Ml 6*93094*000 UWWO*. 67050946Q90 jNKNOVk 6 TO. 8094*051 LMKMOMi 874.90946100 UMKNOW 874.20

——————————————————— 'tfva^T - --

945800 UNOO*H 873945850 LMKHO1M 874.04*45900 ifHtHOm 874945950 UWXNO"* 074.7094*000 LWO.* B74 40

94*050 UWrMWPi 874.55»*6,W UMKNOW. 874.08941619 UNKNOm 86*B45B5G .HMOMi 824.38»4iiOO tWKMOWl •**

945550 LHKNOVk 86694560C U-«N». 8*789945590 UNKMOW. 864.50945500 iMHOMN aee94COOC tX*MC™t. 821.30946200 IMIttO** V 4094*700 iMKHOm, 8727194U50 LWKNOW 885*994*200 LMKNOM 829.26945330 UN.UJOW 0H.M94i350 jWtMOW. 6*8,519454QC (JtMMO«*t 872.5094S350 L"<HO4fc 0*9.109454OD UUKtOWi 871 3694540C L^KNOWH B70 73945450 UNKNOWN 871.82945500 WflCMO** 872. TO945400 JNKK9W 869.**94545C ^MKMOWl 871945500 iWKHO*< 871.6k94540C LHMNOt* TC8994 1450 IWKMOW. 7'. IJ943300 UMKNSWi 73.39945400 UMKKOW. 71.43

945450 L**»CM- TO. 93945500 i*««0»» M 159454OO LMKNOVN 71 87945450 UNNNOVM 869.87

4*5 459710 1949500 ifMMOmt 74.324*6 4590*0 1945550 itatHOmt 72.01447 49*010 1*45150 IMKMOVX 72.934*8 45*010 1845700 IWMOfc 7410tM 4S*010 1*45790 UN**** 74.5070 4SAMO 1945700 LWKMOWI 73.70

471 450*60 1*43730 l*«NW, 72,08

875.60876

8761987648§7163871.93875.X879.30878.20

B7B.*2874.60

675875.X87440873.60B75.9087910B79X

" ———

678.108791487*10B79.30879.50B796187918871 10879 48071.10871 10B72.79871.60671.10B76XSTB 50837.81870*9(34.31I74.*5873.1177.60

§74 70 gftHT MQ.17646173.83 176.92 377.80 373.01 4

STB 10 5767* |

73.** 776.23 l784* *76.33 10TBOJ ti79.25 127197 ij74.97 147*42

877 11 \7B.O379.7079.6077.3077.16

STOL PLATTORy SASC «» *+*<*» >*«

f™ T - /Nl ''"I/^\ 1 !» 4^

f r i l V — ' —— ® — — ^ ttOTES:^ U / ^ ^ ! CWWACTOR HAS OPTOW OF U»C tITMCT SIED. OR BOGD PLATFQW.

1

, 1 ^ _L\ . _____ 1 i— X —— 3r^r-' i r^r-

1 CONDUCTOR TO FURNTSH MATCMALS AW LABOR TO CXTENO P*t UPMtom> ENWK HLL.

_ — — — I—1 j

\_ „. ... .-. _-,. „ Vi-rf- i« P*£SSU«-T«t»ltD*- 3£ *36 «1/T 5TCE. PL. myBEH N4JOB TOCfTveft

^- 2 t/7* STO BlAtt MALL «Pt CAP -,

_y -^- 2 1/T STD BLACK P»C. -*^^ W^^^ TWIEAOCD BOT>- EWJS ^^^

• —~f- ( SPUES V 4 HOLES *64_ AT OOARTTP PO»-T5 (TW>) .6-t \

_ d|^__j:'/t- ^;

6't ]"., \ SEHrfiS Of 4 HOLES6 /*T OJARTEB PONTS (TYF)

1^=.='"i __ ,• __ [^ ^^^^ -mt giK

SETTLEMENT PLATFORM DETAILSCALE NONE

EDGE OF CLAY CAP COORDINATES

awnac tismic P;"T "°- KOBIHM tssmc4X900 't<«0»43»4ft* l»4«001

4S.43J '*•»".!!]• IWMOt4SA311 1MU34.MJ.5 1KJ«1I.»MJ IHS«J54HU1 I*4»M&4XXI '»»«OM4M2JB 1M407049HI' '•»«»'4M14I I»4WH4MOU '•"'"»4M042 l«4«m4SM2 IMIU4UM7 1»4«iat4SHU 1»4<0«4HC1I 1D4MJ143MOB lt49MT4JIT9 I>45M'43M90 1»43B34JMM 1*49*1749M7 1t49ru45(021 1*45TO4JI042 l»45'444U047 II4KM4*041 t«4S»434MOKI 1t45SM4JK71 '»4»734MOI7 l**»n490113 '"M"4»n '«™43KS '"SMJ4901K '•>»•4901M t*4V«B45.ro 'X9a«4S1JJ4 1«4*U«49m2 1*495454S4JJ. 049WI49U» '•«"•49*422 1*499114S04I1 1*4946049*4« '*41444.5,933 1*4941149*110 '»«•»49M* '*49407490*7* 1»45<l*491774 1*49433

IHIHI 19454*349MOB 1B4S801490*92 i**S33245MB0 '**U3<4*004* •**U81«*OOH 19455*0

7 4*0087 1*453774*0171 '*4»*014*0156 '»*9UO4*0106 19451304*0316 !*491334*0231 1*456344*0740 1*451514*07*4 '*4S*574*0274 1*490*14*0279 <»**«440367 1*490*24*0711 IVU7114*01*9 '**973l4*010* l**STU4*01*6 1M97H4*0173 1*45*154*0190 1**90J44*0107 1*4509*4*0000 1*491754*0031 1*45177498**B 1*490*1490074 1*45*J145**43 1*49775490*72 1*45796490*04 1*45791450M1 <M9n*45M*» 1*43718490*40 >**3tn345*t3S 1*4519143*030 'MOT490*23 1**M90

) 4501.2 1*45*t*45*7*1 1*4*04449*754 1*460774907D0 1*4*0*745M90 1*4*10745*630 1*4*111 MQTE:

"•** '***!'0. • DWQTCS LOCATW OT*SS 55 .nif^T-wwi.*45*133 1*4*0*145H13 1*4*007 , ———————————————— .

; j*4 o,

! fciiisP^g<?:^ 3 •- £<B £°i h-sts! 3,3 o|

rj\a sii CA^iiSl1 ^" ••" o

UJcrr>en0_juUJ*~LO a

< Iw Ro °0-2 0.^< ec:a a

, iuj U u.UJ v U.

5U *_ (± 2 o:S °i/> £

si! §! i1fIoa

PTOIKI SloluK

D04«iirOi mi i 'DCMMICI4M OaCMmvtenil 1 1n*. 1 1n

Comm. No.D>o«< Br SHARP «S5tXtt»~ Dole 4/25/07

Z<(/!— 'ZrO°-o,.r^t-O^JUJZ<LJ5^S<_|(/)Q:LJ0

45V500 1*4*012 B5U3> f«R H -45*773 1*41447 --—— ;~—— cSSSirtS. 1 1 045*0.1 1»4S4«5 100 49»» '•<«"> ^mS7 3

Page 160: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

PROPOSEDSITE PLAN

MOTOR WHFEL DISPOSAL SHE CLOSURELANSING, MICHIGAN

cita.1: MOTOR W1IFFL PRP CROUP

SHAREJAND ASSOCIATES, INC.982 Crupper Avenue

Columbus. Ohio 43229

Page 161: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

DETAILS

mn't1(15104MOTOR WHEEL DISPOSAL SHE CLOSURELANSING, MICHIGAN

MOTOR WUFFl PRP GROUP

LS:HAREAND ASSOCIATES, INC982 Crupper Avenue

Columbus. Ohio 4J229

Page 162: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

SITE CROSSSECTIONSSHHET 1

in ii!'SI 3

i05104

MOTOR WHEEL DISPOSAL SITE CLOSURELANSING. MICHIGAN

cu«.i: MOTOR WHCFL PRP GROUP

SHARPAND ASSOCIATES, INC.982 Crupper Avenue

Columbus. Ohio 43229

Page 163: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

1IZZI 1 ——————————————————————————

3 7 P oogoDD y"*i ibiflSITE CROSS Iff ,Vp ;SECTIONS I| HiSHEET 2 S* II [I "

MOTOR WHFFL DISPOSAL SITE CLOSURE £-*LANSING, MICHIGAN ^%IX A U "P

AND ASSOCIATES, INC.982 Crupper Avenue

ai«»ii MOTOR VWIEFL PRP GROUP Columbus, Ohio 43229

Page 164: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

ii llPPi11W s>^!»? e^I;?

FENCEDETAIL

Protect R«ltf*n«: #5104

MOTOR WHFEL DISPOSAL SITE CLOSURELANSING, MICHIGAN

ai.ni: MOTOR WHFFI. PRP GROUP

SHARRAND ASSOCIATES, INC.982 Crupper Avenue

Columbus. Ohio 4J229

Page 165: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

9".

"•5iS

i f 35. f8 s iij3 I IB ?

I § 53 s

PIPEGATE

SHEET

05104

MOTOR WHFKL DISPOSAL SITE CLOSURELANSING, MICHIGAN

an-ti MOTOR WHRFI. PRP GROUP

SHAREDAND ASSOCIATES, INC.982 Crupper Avenue

Columbus. Ohio 43229

Page 166: GROUND WATER REMEDIATION SYSTEM AND ENGINEERED …

CONSTRUCTIONEROSION

01 CONTROLPLAN

^5104MOTOR WHFTL DISPOSAL SITE CLOSURELANSING, MICHIGAN

MOTOR WHFFI PRP CROUP

SHARPAND ASSOCIATES, INC992 Crupper Avenue

Columbus, Ohio 43229