greater visakhapatnam municipal corporation comprehensive water...
TRANSCRIPT
GREATER VISAKHAPATNAM MUNICIPAL CORPORATION
Comprehensive Water Supply Scheme forKollapur Nagara Panchayat
in Mahbubnagar District of Telangana State
NCPE Infrastructure India Pvt. Ltd.12-2-826/A/12, LIC Colony, Mehdipatnam, Hyderabad - 500028.
Tel.: 040-2351 7558. Fax: 040- 2351 4379. Cell.: 0-98480 35377, 98490 35377Email : [email protected] Web site : www.ncpe.org.in
Social Impact AssessmentVolume VIII
Zone-X
TH:349.82m
TH:348.57m
Max RH:25.67mMin RH:14.44m
Max RH:19.96mMin RH:8.01m
+317.25m
+324.7m
Max RH:19.33mMin RH:14.24m
2011
TH:348.79m
Zone-III
P : Prospective Demand in MLDU : Ultimate Demand in MLDV : Velocity in m/secHL : Head Loss in 'm'TH : Total Head in 'm'RH : Residual Head in 'm'
+314.03m +317.9m
Max RH:19.82mMin RH:14.51m
Max RH:18.98mMin RH:9.14m
Zone-IX
+330.8m
TH:344.68m
Max RH:20.62mMin RH:9.31m
Zone-VI
TH:349.59m
NoteAll Discharges in MLD
TH:348.18m
Max RH:21.47mMin RH:11.95m
Max RH:19.46mMin RH:14.46m
Zone-V+310.6m
Flow Diagram of Feeder Mains and Proposed/Existing Service Reservoirs ofWater Supply Scheme for Kollapur Nagara Panchayath
Zone-VIII
+329.7m
25,225
Zone-VII
TH:348.73m
TH:347.84m
Zone-IV
Max RH:21.60mMin RH:15.13m
+318.5m
+330.68m
B
200KL324.03m340.03m343.03m346.64m
Zone-VIPendyla Buchaih
:::::
V
T
0.28
0.0
4
1.36
ProposedGLLWLMWLTH
SALIENT FEATURES:-
P
0.45
U
HL
Existing ELSRCapacity: 100KLGL :330.55mLWL : 340.55mMWL : 343.55mTH :347.79m
V
P
2.69
0.36
3.41
Q
U
I
0.19
7.20
3.93
V
J
0.20
2018
D
0.14
5.1
9
7.20
169m
, 150
mm
Ø D
IK7
U
HL
U N
0.59
0.27
ExistingGLLWLMWLTH
HL
HL
P
0.93
4) Major Components of Scheme
U
U
P
0.71
Q
V
0.66
0.18
0.56
Consultant
V
2.09
Q
Existing ELSRCapacity: 100KLGL :330.55mLWL : 340.55mMWL : 343.55mTH :347.79m
610m
, 300
mm
Ø D
IK7
HL
V
3.55
1.21
P
U
0.64
1731
m, 1
50m
mØ
DIK7
HL
P
0.12
V
ProposedGLLWLMWLTH
0.29
0.09
0.33
1.02
:::::
HL
0.25
0.63
0.43
Zone-IIIMadhavaswamyTemple
0.33
0.38
:::::
Year
Zone-VPendyla Buchaih
ProposedGLLWLMWLTH
0.53
0.03
1.11
400KL325.085 m341.085 m344.085 m347.24m
1968m, 150m
mØ
DIK7
U 0.77
326m
, 200
mm
Ø D
IK7
Zone-IXNarsimhapuram
HL
V
0.54
V
0.29
0.15
1.77
- 135 lpcd
HL
0.11
375 KL321.44m337.44m340.44m346.04m
0.08
5) House Service Connections - 5063 Nos
0.40
4.83
Q
1) Population Projections & Water Demand
HL
P
0.24
5.90
3.22
Not to Scale
U
0.41
0.79
Q
2033
V
0.52
5.27
46,000
150 KL323.89 m339.89 m342.89 m348.68m
Zone-IIJameengadda
U0.12
0.22
Q
Population
P
U
ProposedGLLWLMWLTH
0.45
0.55
> 300 KL RCC Sump> DIK7 Gravity Mains - 21.89 km> 8No of ELSRs of Total Capacity - 1600 KL> Total Distribution Network Proposed - 60.68 km
SingotamCheruvu
150KL317.60 m333.60m336.60m349.66m
V
U
0.16
Q
504m, 150mmØ DIK7
200mmØ DIK7
U
0.34
0.61
NCPE Infrastructure India Pvt. Ltd.
0.85
Q
V
P
Q
ProposedGLLWLMWLTH
0.500.22
0.6
8
Consultant
HL
0.89
Q
225m, 300mmØ DIK7
:::::
V
G
0.26
38,000
P
HL
K
0.10
0.15
1.97
Q
:::::
CW(MLD)
1340
m, 1
50m
mØ
DIK
7
UC
0.12
4.50
Zone-IBandaih Gutta
V
HL
M
ProposedGLLWLMWLTH
0.58
0.13
0.40
1.25
TH:345.43m
Flow Diagram of Feeder Mains and Proposed/Existing Service Reservoirs ofWater Supply Scheme for Kollapur Nagara Panchayath
TH:350.47m
Zone-II
Max RH:22.21mMin RH:15.12m
Zone-I
V0.17
7.4
9
5.90
425m, 350mm Ø DIK7
P
P HL
0.35
350 KL329.81 m341.81 m344.81m348.41m
2774m, 150mmØ DIK7
118m
, 200
mm
Ø D
IK7
:::::
0.22
0.56
1.61Q
ProposedGLLWLMWLTH
0.27
29,000
V
1.45
5.90
Q
Flow Diagram
U
0.11
6) Total Project Cost Rs.38.85 Crores
0.23
0.30
2.79
Q
P
U
Zone-XNarsingaraopally
S0.
37
0.64
0.18
2.16
3) Per Capita Supply
:::::
610m
, 200
mm
Ø DI
K7
P
P
0.16
Q
CW Sump : 300KLMWL : 360.500LWL : 358.000
0.35
0.54
Zone-VIIIChukkaipally
125 KL319.76m335.76m338.76m345.16m
0.38
R
2) Source
7646
m, 4
00m
m Ø
DIK
7
905m, 300mmØ DIK7
U
V
0.65
0.44
181m, 350mmØ DIK7
Zone-VIIChotabetla
0.46
Tapping from Telangana Drinking Water Grid
+316.4m
O
5.04
1.48
P
HL
U
H
A
0.54
Q
2048
:::::
20m
P
0.50
231m, 150mmØ DIK7
Infrastructure Designers, Urban P lanners and Project Management Consultants
0.58
Q
PF
0.35
0.76
0.52
:::::
Zone-IVGanagamma Gutta
P
0.73
0.45
100 KL311.15m327.15m330.15m344.32m
HL
E
0.74
6.44
V
L
ProposedGLLWLMWLTH
0.63
0.46
100KL319.84m335.84m338.84m344.51m
1354m, 150mmØ DIK7
HL1.84
Q601m
, 150
mm
Ø D
IK7
P
V
HL
U
30m
, 150
mm
Ø D
IK7
(Formerly known as National Consultancy for Planning and Engineering)12-2-826/A/12, LIC Colony, Mehdipatnam, Hyderabad - 500028.Tel.: 040-2351 7558. Fax: 040- 2351 4379. Cell.: 0-98480 35377, 98490 35377
HL
0.73
Q
129m
, 150
mm
Ø D
IK7
U
Social Impact Assessment for Kollapur Water Supply Project
NCPE Infrastructure India Pvt.Ltd., Hyderabad Page a
SOCIAL IMPACT ASSESSMENT FOR KOLLAPUR WATER SUPPLY PROJECT IN KOLLAPUR NAGARA PANCHAYAT
TELANGANA MUNICIPAL DEVELOPMENT PROJECT
Kollapur Nagara Panchayat February, 2016.
Social Impact Assessment for Kollapur Water Supply Project
NCPE Infrastructure India Pvt.Ltd., Hyderabad Page 13
INTRODUCTION
1. The Telangana Municipal Development Project (TMDP) is being implemented by Government of
Telangana with support from World Bank. The project is aimed at improving urban services in select ULBs
mainly in water supply and sewerage sectors. The project will also support improvements in the financial,
technical and management capacities of select ULBs of Telangana through technical assistance to sustain the
infrastructures being created. This sub-project for Kollapur Nagara Panchayat is one of the water supply
service improvement projects taken up under Telangana Municipal Development Project (TMDP).
2. Kollapur Nagar Panchayat is spread over an area of 26.92 Sq Km having a population of 25225 as per
2011 census and located on banks of river Krishna. Kollapur is located at 16°10’29”N 78°20’26”E in
Mahaboobnagar of Telangana State. The average elevation of Kollapur Nagar Panchayat is 322m above sea
level. Kollapur is about 175Km from Hyderabad on NH44. A massive lift irrigation project is near Kollapur. The
Somasila temple is located just 9 km from Kollapur.
3. Present Scheme contains Intake arrangements by winch and trolley system at Somasila. Water is
drawn from River Krishna by 30 HP pumpsets arranged on trolley. This water is directly pumped in slow sand
filters constructed at bank of river Krishna. After Treatment water will reach to Clear water sump and then it
will be pumped to Kollapur town by using 100HP Pumpsets.
However, presently scheme is not running accordingly. Slow sand filters are totally abandoned and
water is directly pumped into clear water sump and from there by using 100 HP pump sets it is conveyed to
350KL ELSR constructed at Bundaihgutta. From there water is distributed directly to consumers and also water
is used to fill other reservoirs. i.e. the 350KL reservoir is being used as balancing reservoir as well as service
reservoir. Presently water from pumping station located at Somasila to ELSR is conveyed by using 300mm/200
mm AC pipes of class 25/20/15. This pipeline is demanding frequent repairs and it got damaged at many
places.
There are about 30 Km. of water supply lines ranging from 50 mm dia to 100 mm dia PVC for
distribution network and up-to 300 mm dia for transport of water. The city has about 30 Public Stand Posts for
water supply to weaker section of the society / Slums.
The objective of this sub-project is to provide wholesome potable water @ 135 LPCD to 100%
population, throughout the day in 24x7 module, at required minimum pressure head as stipulated in the
Design basis.
4. Hence a comprehensive water supply scheme is taken up for medium and long term requirements
with the following salient components.
Social Impact Assessment for Kollapur Water Supply Project
NCPE Infrastructure India Pvt.Ltd., Hyderabad Page 14
• Construction of 300KL RCC sump at Singotam
• Construction of 8 ELSRs (Jameengadda, MadhavaSwamy Temple, Gangamma Temple,
PendyalaBuchaiah, Chowtabetla, Chukkaipally, Narsimhapuram and Narsinga Rao Pally) of total
capacity 2000 KL.
• DI K7 Feeder mains from sump to ELSRs for a length of 21877 Rmt.
• Distribution network with DI and HDPE pipes in Zones 1, 2, 3, 4, 5, 6, 7, 8, 9 and 10.
STAKEHOLDERS’ CONSULTATION
5. Local Level consultation has been conducted on 05-11-2015 and Stake holder consultation conducted
at KLI guest house in Kollapur town on 16-11-2015. Minutes of meeting and issues emerged from stakeholder
and local level consultation is attached as Annexure 1. Persons attended and newspaper clippings are shown in
Annexure 2 and 3. The primary and secondary stake holders are identified -
The primary stakeholders are:
• Residents, shopkeepers and businesspeople who live around project area where improvements will be
provided and near sites where facilities will be built;
• Custodians and users of socially and culturally important buildings in affected areas if any; and
• State and local authorities responsible for the protection and conservation of sensitive area if any
• The secondary stakeholders are:
• Urban Local Body (ULB) Kollapur Municipality, as the Executing Agency;
• Other Government institutions include areas or issues affected by the subproject (State and local
planning authorities such as PWD, PHED);
• Other community representatives (prominent citizens, political leader, religious leaders, elders,
women’s groups);
Issues raised / suggestions in the Stake holders meeting and responses provided
Table 1
Sl.No. KeyIssuesIdentified ResponsebytheUrbanLocalBody 1
TechnicalIssue:Entiremunicipal
areaincluding slums/ BPLareatobe
coveredbythenewWaterSupply scheme.
TheCommissionerfullyendorsed theviews expressedby
theparticipants.
2
Technical Issue: Non use of old pipe
lines. Laying of new pipes to prevent
frequent leakages in the distribution
system.
TheCommissionerfullyendorsed theviews expressedby
theparticipants. Consultant informed that complete new distribution system will
be designed
Social Impact Assessment for Kollapur Water Supply Project
NCPE Infrastructure India Pvt.Ltd., Hyderabad Page 15
3
Technical Issues: Construction of water
storage reservoirs to cover entire
Kollapur town and distribution of
water to all the zones after discussion
with NGO’S
The Commissioner appraised that the present scheme will be
for 24x7 water supply for all the areas of Nagara Panchayat
and added areas
4
Technical Issues: Restoration of
concrete road, damaged utility services
should be done at earliest. Cost should
be considered within the project
Commissioner appraised that this issue will be definitely taken
care and consultant will take up the restoration and utility
shifting/ repairing cost in their budget estimate
5
Technical Issues: Requirement of
additional water reservoir at Different
Zones for coverage of the particular
area
ULB informed that consultant will consider inclusion of new
reservoir after technical study
6
Technical Issues: Further discussion
with all Ngo’s before finalization of the
design of present water supply scheme
Commissioner appraised that it will be definitely taken care
7
Common Technical &
Environmental Issue Public disturbance
during project implementation
ULB agreed for implementation of traffic management plan
(during construction) as per design and accordingly the
mitigation measures will be considered in environmental
assessment report
8
Environmental Issue - Presence of
trees at different project locations –
necessity of tree falling and
compensation should be taken into
consideration
During selection of locations of different project components
like – laying of clear water mains, distribution network, and
storage reservoirs these issues will be considered. In case of
any tree felling compensation will be planned as per state and
national rules
9
Environmental Issue – Applicable
environmental rules regulation related
to the project
Will be studied before preparation of environmental report
10
Environmental Issue – Generation of
dust and other pollutants during
project implementation
Environmental report will be prepared considering protection
of environment like dust suppression and pollution reduction
11
Environmental Issue – Presence of any
sensitive areas like forest area,
religious places, institutions and
protection during implementation of
the project
Project will be planned in such a way to avoid any sensitive
receptors. All project locations will be screened during field
visit. No religious site will be affected
12
Environmental Issue- Application of
mitigation measures for protection of
air, noise and water environment
Definitely considered in environmental management plan in
environment report
Social Impact Assessment for Kollapur Water Supply Project
NCPE Infrastructure India Pvt.Ltd., Hyderabad Page 16
13
Social issue - Saving of water
The ULB fully endorsed the views expressed by the
participants.
14
Social Issue- Financially better off
households pump water from the
supply
This will be resolved with upgraded water supply system with
high pressure and whole town coverage
15
Social Issue- There is no fixed supply
time
This will be resolved with upgraded water supply system as 24
hours supply is proposed
16
Technical and Social issue - Micro level
planning
The Commissioner fully approved the views expressed by the
participants.
17
Technical & social issue - Regular
maintenance of system
The ULB fully approved the views expressed by the
participants.
18
Environmental and Social issue -
Potential impact on people
The municipal authority had taken steps to make the
participants under the Project strategy and mitigation
measures.
ASSESSMENT OF ADVERSE SOCIAL IMPACTS
6. In order to ensure that the project do not harm the livelihood of the people due to the proposed
project interventions, an assessment of adverse impacts was carried out with an objective of proposing
suitable mitigation measures where such impacts are envisaged. While formulating the subproject, various
efforts have been made to avoid resettlement. During planning and designing, attempt has been made to
restrict the construction works within the ULB lands and RoW of Government/ ULB land.
The impacts are ascertained for each component of the project based on the proposed site of
construction /alignment. Necessity of land acquisition, Impacts on public/ private properties, necessity for
temporary relocation of roadside kiosks and disturbance to business have been ascertained for each
component. The details of proposed investment components and the potential impacts in those components
are described below.
The purpose of this Resettlement Action Plan (RAP) is to propose the mitigation measures to those few
shopkeepers affected due to the project activities in order to support them during the transition period. These
impacts are of minor in nature and only impact for few days during laying of distribution lines (which will be
done in stretches). All affected people may continue to do their business activities after completion of pipeline
work at their current place of vending / business subject to the local laws.
Social Impact Assessment for Kollapur Water Supply Project
NCPE Infrastructure India Pvt.Ltd., Hyderabad Page 17
Component wise impacts:
Table 2
S. No Component
Land Acquisition & Resettlement
Impact
Land Requirement
Current Use Land
Ownership Remarks
1 300 KL RCC Sump at Tapping Point No impact 550 Sq.m
Vacant land Govt. Land Will be
constructed at Singotam
2
ELSR at JameenGadda No impact 500 Sq.m
Vacant land ULB land
ELSR at MadhavaSwamy temple
No impact 500 Sq.m
Vacant land ULB land
ELSR at Gangamma Temple
No impact 500 Sq.m
Vacant land ULB land
ELSR at PendyalaBuchaiah
No impact 500 Sq.m
Vacant land ULB land
ELSR at Chowtabelta No impact 500 Sq.m
Vacant land ULB land
ELSR at Chukkaipally No impact 500 Sq.m
Vacant land ULB land
ELSR at Narsimhapuram
No impact 500 Sq.m
Vacant land ULB land
ELSR at NarsingaRaopally
No impact 500 Sq.m
Vacant land ULB land
3 Laying of Feeder Mains
Impact is limited to temporary
disturbance to some shops
Will be laid along RoW of
mostly Municipal
roads and a short stretch of
R & B roads
RoW RoW
R & B department has been addressed for permission to lay pipeline
Social Impact Assessment for Kollapur Water Supply Project
NCPE Infrastructure India Pvt.Ltd., Hyderabad Page 18
S. No Component
Land Acquisition & Resettlement
Impact
Land Requirement
Current Use Land
Ownership Remarks
4 Distribution System
Impact is limited to temporary
disturbance to some shops
Will be laid along RoW of
mostly Municipal
roads
RoW RoW
Pipeline will be laid in the RoW
of existing roads.
5 Construction of
Watchman quarters(8 Nos)
100X8=800 Sq.m
Vacant land ULB Land
Watchmen quarters are proposed at
ELSRs
Total Land requirement: 5350 Sq.m
No land acquisition is required all the components are proposed in the Kollapur Nagara Panchayat lands
7. In order to assess the impacts of the sub- project, a social impact assessment was carried out by the
DPR consultants. As per this assessment, lying of pipelines will affect few shops during laying of pipelines in
front of them and the shopkeepers didn’t want any compensation for the temporary disturbance. However,
provision for this is made in the RAP keeping in view of additional impacts which may arise during execution.
Tentative list of shops on RoW is provided as Annexure –II. The list of shops going to be affected during lying of
pipelines will be finalized by joint inspection of consultant and S&E Officer of the ULB.
POSITIVE BENEFITS DUE TO THE SUB-PROJECTD:
8. Notwithstanding of the few above mentioned adverse impacts, the proposed project will have positive
impacts in the form of:
ü Reduction in water shortage
ü Improved access to potable water
ü Reduction in waterborne diseases
ü Time spent for fetching water at present will be saved for the citizens
ü Job opportunity in the Project
ü Scope for improved quality of life
ü Exposure to awareness programmers and hence updating of knowledge
POLICY LECAL AND ADMINISTRATIVE FRAMEWORK:
9. Policy will be governed by,
• RTFCTLARR Act, 2013 and TS Govt. rules vide G.O. Ms No. 50 Revenue (JA & LA) Dept date 19-12-2014
• SEAMF September-2015
• World Bank Operational Policy 4.12 on Involuntary Resettlement
Social Impact Assessment for Kollapur Water Supply Project
NCPE Infrastructure India Pvt.Ltd., Hyderabad Page 19
ENTITLEMENTS
10. The following are the entitlement provisions.
Category Assistance
Kiosk / Roadside Vendor on RoW requiring shifting. Shifting Allowance of Rs.2000 and Transitional
Allowance of Rs.3000
Temporary Disturbance to Business / Restriction of
access for encroachers on RoW.
Disturbance allowance of Rs.3000
TENTATIVE BUDGET ESTIMATE FOR RAP:
11. There are PAPs due to implementation of the sub-project. However, keeping in view of additional
impacts which may arise during laying of pipelines on RoW’s due to roadside vendors/Kiosk, a tentative budget
has been estimated and described as follows.
Table 3
Assistance type Entitlement No. of affected
shops
Amount
Assistance to Kiosk/Road side Vendor on RoW requiring shifting
Shifting allowance of Rs.2000 and Transitional allowance of
Rs.3000
70 Rs.3,50,000
Temporary Disturbance to Business / Restriction of access for encroachers on RoW.
Disturbance allowance of Rs.3000
15 Rs.45,000
Contingencies Rs.30,000
Total Rs.4,25,000
The budget is indicative of outlays for different expenditure categories. The costs may be updated due to
change in the project designs/alignment and additional impacts.
Social Impact Assessment for Kollapur Water Supply Project
NCPE Infrastructure India Pvt.Ltd., Hyderabad Page 20
IMPLEMENTATION OF RAP:
Payment of Assistance:
12. List of the affected Roadside Vendors / Kiosks has been prepared jointly by S&E Officer of the ULB and
the consultant which was endorsed by the Municipal Commissioner before. A video of the affected shops and
proposed sites for ELSRs was taken for cut-off data.
• Based on the list, the Budget as per the above entitlements will be approved by the Municipal Commissioner.
• The assistance will be paid through cheques to the eligible people before execution of work is taken up. The Municipal Commissioner will certify to this effect.
ADDITIONAL IMPACTS DURING THE IMPLEMENTATION OF SUB-PROJECT:
13. During the implementation, if any additional impacts are encountered in addition to those described
in this RAP, they will be promptly addressed through additional measures in line with the policy provisions.
The contractor will communicate promptly to bring to the notice of S&E officer about any additional impacts
that he may encounter during the execution of works and these will be mitigated promptly. The S&E Officer of
the ULB is responsible for initiating the process for addressing the additional impacts and the supplementary
plans will be processed in a similar manner by which this RAP is prepared and approved. The S&E officer will
provide a confirmation to MSU, TMDP once in quarter during the construction period about the details of new
impacts encounter and measures taken to deal with those impacts or confirm that no impacts were
encountered.
14. SYNCHRONIZATION OF R&R AND CONSTRUCTION SCHEDULE:
Table 4
Construction Schedule R&R Activities Tentative Time Table
Issuance of bids for the sub-project Approval and Disclosure of RAP.
March 2016
Award of / signing the contract Setting up of Grievance Redressal Mechanism.
May 2016
Execution of pipe lines. Payment of assistance to the affected people and certification on payments
Before the award of the work.
Social Impact Assessment for Kollapur Water Supply Project
NCPE Infrastructure India Pvt.Ltd., Hyderabad Page 21
GRIEVANCE REDRESSAL MECHANISM:
16. The grievances can be registered at the complaint cell established at the ULB. The complaint cell will
also act as a Public Information Centre, where the grievances of the community will be registered and other
information with regard to the project, the sub-projects, social and environmental safeguards will be provided.
The grievances can pertain to any social and /or environmental issues triggered by sub-projects under the
TMDP. The Complaint Cell would forward the grievance to the S&E officer. If the grievance could not be
redressed by S&E Officer, it will be forwarded to the Revenue Officer and the NGO/Community representative
in the ESMC (Environmental and Social Management Committee) for redressing. A District Urban Grievance
Redressal Body will be established for redressing the grievances that could not be solved by S&E Officer and
ESMC at ULB level. The District Grievance Redressal body will be established prior to award of contract in
Kollapur Nagara Panchayat. This body will consist of 4 to 5 eminent citizens in the District and are from
diverse backgrounds such as education, health and sanitation, urban infrastructure, civic affairs, etc. In an
advisory capacity, it will facilitate and suggest suitable action to redress the grievances of the community /
public. At the State Level the Project Appraisal Committee (PAC) will act as ‘State Urban Grievance Redressal
Body’. If the S&E Officer cannot redress the grievance within a specified time period, the grievance would be
forwarded to the ESMC and further to the District Urban Grievance Redressal Body constituted at the District
level.. The grievance that cannot be redressed at the District Urban Grievance Redressal Body level would be
referred to the State Urban Grievance Redressal Body. Each of these authorities can be approached directly
for grievance redressal by the aggrieved person/party.
PUBLIC DISCLOSURE:
17. The RAP in English and Summary in Telugu will be placed at public places and the web sites of
Municipality and CDMA for the benefit of all concerned. The public disclosure places, at the minimum, include
the following:
• Offices and libraries of the project area (Commissioner Office and Municipal Libraries)
• District Collectorate
• Departmental websites
MONITORING AND REPORTING :
18. A report on payment of assistance will be sent to MSU-TMDP once the payments are completed along
with the certification of payments. In addition, quarterly Confirmation Note will be sent indicating the details
of additional impacts or otherwise, throughout the construction period.
Social Impact Assessment for Kollapur Water Supply Project
NCPE Infrastructure India Pvt.Ltd., Hyderabad Page 22
LAND ALIENATION PROCESS
19. Government Order relating to alienation in respect of Local Bodies :
G.O.Ms.No.216, Rev.Q.Dept 19-2-76
20. Procedure for Alienation of Govt. Land:
Alienation of Govt. Land to the extent of 550 Sq. Mt. is required for construction of Sump at Singotam.
The Municipal Commissioner will obtain a council resolution from the Council and submit the requisition letter
to RDO/Collector duly enclosing a sketch showing the land applied for alienation and the adjoining lands. on
receipt of application the Revenue Department will process as per their procedures and handover the land to
the ULB.
Social Impact Assessment for Kollapur Water Supply Project
NCPE Infrastructure India Pvt.Ltd., Hyderabad Page 23
ANNEXURE I
STAKEHOLDERS MEETING ONCOMPREHENSIVE PLANNING OF WATERSUPPLYSERVICE IMPROVEMENTS INKOLLAPUR NAGAR
PANCHAYATFEASIBILITY &CONCEPT Proceedings of the Meeting
Date: November 16th, 2015 Time:11.00A.MVenue:KLI guest house –Kollapur
Commissioner of Kollapur Nagara Panchayat,
Public representors along with project consultants
briefing about Water supply project in Stakeholder
meeting
Stakeholder attended For Stakeholder Meeting at
Kollapur Nagara Panchayat Venue at KLI Guest House
G. Ramalimgam, Municipal Commissioner
inaugurated stakeholder consultation and he has
given a brief indtorductionon the present project “Comprehensive
Planning of Water Supply Service Improvements in
Kollapur” funded by World Bank
Social Impact Assessment for Kollapur Water Supply Project
NCPE Infrastructure India Pvt.Ltd., Hyderabad Page 24
Mr. A.M. Hanumanthu Nayak Z.P.T.C Leader
informed that project is very important for Kollapur.
He explained that after completion of the project
people of Kollapur will get good quality water. He
assured all kind of help for successful completion of
the project. He requested consultant to complete the
project report at the earliest
Mr. B. Vinod, Team Leader of Environmental Expert (Consultant of the project) explaining the concept plan on water supply scheme at Kollapur and pointing out different options related to water supply scheme
Social Impact Assessment for Kollapur Water Supply Project
NCPE Infrastructure India Pvt.Ltd., Hyderabad Page 25
Mr. Md Siddique, Project Engineer (Consultant of the project) explained the Concept of the project and methodology to be followed during feasibility and detail stage of the project. He also pointed out possible impacts and requirement of mitigation measures during implementation of the project
Mr. Md Siddique, Project Engineer (Consultant of the project) Recording. The Complaints and Suggestions.
Mr. M Ramdu TRS Leader expressed the need of concrete road restoration after laying of pipes and repairing of damage utility as priority basis. He requested consultant to consider the restoration and damage/ repairing cost within the project budget Establishing drinking water project through World Bank fund is very much helpful for people of Kollapur Nagar Panchayat. He expressed that drinking water project will be done without any burden during construction
Social Impact Assessment for Kollapur Water Supply Project
NCPE Infrastructure India Pvt.Ltd., Hyderabad Page 26
ANNEXURE7
ATTENDANCESHEETSOFSTAKEHOLDERSMEETINGINKOLLAPUR
Social Impact Assessment for Kollapur Water Supply Project
NCPE Infrastructure India Pvt.Ltd., Hyderabad Page 27
Social Impact Assessment for Kollapur Water Supply Project
NCPE Infrastructure India Pvt.Ltd., Hyderabad Page 28
Social Impact Assessment for Kollapur Water Supply Project
NCPE Infrastructure India Pvt.Ltd., Hyderabad Page 29
ANNEXURE2
NEWSPAPERCLIPPINGS
Social Impact Assessment for Kollapur Water Supply Project
NCPE Infrastructure India Pvt.Ltd., Hyderabad Page 30
Social Impact Assessment for Kollapur Water Supply Project
NCPE Infrastructure India Pvt.Ltd., Hyderabad Page 31