greater manchester health and social care strategic partnership board 7 · 2018-05-03 · 1 greater...
TRANSCRIPT
1
GREATER MANCHESTER HEALTH AND SOCIAL CARE
STRATEGIC PARTNERSHIP BOARD
Date: 28 October 2016
Subject: Delivering Theme 3: Standardising Acute and Specialised Services
Report of: Rob Bellingham
PURPOSE OF REPORT:
The attached report was presented to the Strategic Partnership Board Executive on 10th
October and the Joint Commissioning Board on 18th October. Its purpose is to outline the
arrangements for the development of the Theme 3 governance and programme to ensure
that it is fit for purpose to drive the delivery of Theme 3 priorities.
Detailed recommendations are covered within the body of this paper. In summary this paper:
Makes recommendations to reset the governance of Theme 3 (outlined in Section 2).
Outlines how Theme 3 proposes to deliver (outlined in Section 3).
Highlights and makes recommendations to resolve some key issues (outlined in
Section 4).
In supporting the paper the SPB Executive raised a number of issues where further work will
be required as the programme moves forward, notably with regard to:
Delivery and implementation arrangements.
Inter-connections to the other transformation themes including, but not limited to, the
need to more formally recognise the opportunity and requirement surrounding
digital/IT based solutions.
Connectivity and linkages to wider devolution governance, for example the Cancer
and Mental Health Boards.
Further work on the development of the system leadership arrangements to ensure
clarity on roles and responsibilities and underpinning the commitment to co-design
across the work programme.
7
2
.
The JCB reviewed the paper on the 18th October together with the above comments and
have endorsed it.
RECOMMENDATIONS:
The Strategic Partnership Board is asked to:
Receive the paper, noting the support and feedback of the SPB Executive and the
Joint Commissioning Board.
Note the approaches suggested to resolve the issues outlined in section 4.0.
CONTACT OFFICERS:
Rob Bellingham
3
1.0 Background
1.1. The Theme 3 Standardising Acute and Specialised Services Programme was set
up to deliver the commitments outlined in the Greater Manchester Strategic Plan,
Taking Charge specifically:
1. Improving the safety and quality of services and reducing variation
2. Improving productivity: hospitals are drawing up plans to achieve efficiency
savings of 2.5 per cent in 2016/17, and 2 per cent per annum in subsequent
years
3. Improving delivery and the interface with out of hospital models: hospitals are
working to introduce new care models to avoid emergency admissions and cut
very long lengths of acute hospital stays. Trusts are working to deliver the four
priority clinical standards for seven day working as part of the first phase of
implementation by 2017
4. Increasing collaboration: trusts have agreed to a programme of collaborative
efficiency and to joint working to achieve significant savings targets
Since then, the programme has been set a target financial contribution at GM level
of £140m.
1.2. The Greater Manchester Service Transformation Directorate, which became the
NHS Transformation Unit on the 1st April 2016, was asked in January 2106 to
deliver the first phase of work to agree and mobilise the programme governance,
provide a methodology for prioritising acute services, and use this to seek system
agreement to a shortlist of priority projects.
1.3. Governance arrangements for the programme were proposed and endorsed by the
Provider Federation Board in March 2016 and endorsed by the Joint
Commissioning Board in July 2016. The Theme 3 Clinical Reference Group was set
up in April to develop a clinical prioritisation matrix, and provide a recommendation
on which services should be prioritised. The Theme 3 Steering Group was fully
mobilised in July, reviewed the proposed Theme 3 priorities, and put forward a final
proposal which was endorsed by the AGG, the Provider Federation Board, and the
Strategic Partnership Board Executive in September.
1.4. With changes being made to the Governance of the Health and Social Care
Partnership; the new hosting arrangements of the NHS Transformation Unit coming
into effect on the 1st April 2016, and Theme 3 now entering a new delivery phase of
work, there is now a need to reset the governance to put the programme on a firmer
footing to deliver, and set out an approach to delivery that builds on what is in place
and is agile and flexible to quickly bring about change.
4
2.0 Resetting the governance
2.1. Establishment of a ‘client function’
2.1.1. Recognising the NHS Transformation Unit’s new hosting arrangements and
operating as a supplier of the GM Health and Social Care Partnership, there is a
need to establish a ‘client function’ within the Partnership to manage the
relationship between the Partnership and the Transformation Unit, the delivery of
agreed work from the Transformation Unit and the commissioning of services for
the future delivery of Theme 3.
Recommendation: Client management function to be established within the
Population Health Transformation and Commissioning function to manage the
existing contract with the NHS Transformation Unit and the commissioning of
services to deliver Theme 3.
2.1.2. Similarly, there is also a need for clear separation between the strategic leadership
of Theme 3, and the commissioning of work to support Theme 3. As such, the
Theme Lead for Theme 3 should be a member of the Greater Manchester Health
and Social Care Partnership team.
Recommendation: Theme 3 Leadership should transfer to the Executive Lead for
Population Health Transformation and Commissioning, to be fulfilled by the Director
of Commissioning, Rob Bellingham in the interim.
2.2. Simplification and alignment of the governance
2.2.1. The Theme 3 programme governance was set up with reporting lines from the
Executive Team and Steering Group directly into the wider GM Health and Social
Care Partnership Governance, through The Provider Federation Board and the
Joint Commissioning Board. The Steering Group is jointly chaired by Ann Barnes
and Dr Chris Brookes while the Theme 3 Clinical Reference Group currently
provides an advisory function to Theme 3 and is chaired by Dr Chris Brookes. The
Theme 3 programme governance and co-ordination management is currently
provided by the NHS Transformation Unit.
Recommendation: Simplify the governance so that the Theme 3 Steering Group
becomes a Delivery Board, responsible for the oversight of all Theme 3
programmes. The Delivery Board will form part of the GM Health and Social Care
Partnership’s governance, reporting into the newly created GM Transformation
Portfolio Board, and serviced by the Partnership.
Recommendation: Work to confirm preferred option for chairing of the Delivery
Board. Current options are for the lead of the client management function to
assume the chair or to appoint an independent chair. In either case, the need to
maintain close working arrangements with the above name clinical and
management leads will be paramount.
5
2.2.2. Healthier Together, which is part of Theme 3, and is in implementation, currently
has separate governance arrangements which pre-date the establishment of the
GM Health and Social Care Partnership. Healthier Together is a critical priority for
Theme 3, to deliver on commitments made to the public to improve the quality,
safety and effectiveness of general surgery, A&E and acute medicine; estimated to
save 300 lives per year. However, the governance now needs to be fully aligned to
Theme 3 and the GM Health and Social Care Partnership. Full details of proposed
changes are outlined in a separate paper and are being overseen by the Chief
Officer in his role as Programme Sponsor for Healthier Toghether; those relevant to
Theme 3 are noted below.
Recommendation: As one of the programmes in implementation under Theme 3
Healthier Together should report into Theme 3. The detailed implementation of the
new model of care for general surgery, acute medicine and A&E is currently
overseen by the monthly Healthier Together Programme Board. It is proposed that
this group shifts its reporting arrangements to report directly into the Theme Three
Delivery Board, and changes its name in line with other equivalent sub-groups. It
will retain its working arrangements to ensure continuity and momentum with
implementation.
2.3. Delivery through co-design and partnership
2.3.1. The principle of co-design and partnership working, in particular between providers
and commissioners has been the driving force behind the mobilisation of the Theme
3 Steering Group, and Clinical Reference Group in their current forms, and has
provided direction and input to shape proposals before they are put to the wider
system. Membership of the Steering Group is currently drawn from providers,
commissioners and AGMA, while membership of the Clinical Reference Group is
currently drawn from providers, commissioners, and NHS England, with medical
and nursing representation. With the shift in focus now to delivery, membership of
the Delivery Board and Clinical Reference Group will need to be revised to cover
the agreed priority projects, and co-partnership needs to be supported by specific
system leadership roles to drive implementation.
Recommendation: Co-design and partnership working should be recognised as a
vital principle for the successful delivery of Theme 3. Membership of the Theme 3
Delivery Board and Clinical Reference Group should be reviewed in the light of the
agreed priority projects for Theme 3 and supported by specific system leadership
roles; these are outlined below.
2.4. System Leadership
2.4.1. Taking the learning from previous reconfigurations in GM, there are a number of
system leadership roles that will be critical to the successful delivery of Theme 3.
The leadership required will need to reflect the scale of the programme; drive the
rapid delivery of benefits; and deliver the longer term strategic changes required to
unlock the system. Three roles are proposed: System Clinical Sponsor, System
6
Provider Sponsor and System Commissioner Sponsor. These three roles would
provide leadership in each of the four areas of delivery in Theme 3:
Women’s and Children’s
Medicine (Cardiology and respiratory)
Consolidation of surgery
Specialised Services
2.4.2. System Clinical Sponsor – role outline
This role will provide GM-wide clinical leadership, within the relevant area, to
identify and drive the implementation of immediate interventions to improve the
quality, safety and efficiency of patient care;
articulate and promote the vision for change with clinical colleagues and
champion the sharing of innovation and standardisation of hospital care across
GM
develop agreed GM clinical standards, and models of care to inform new
service specifications
act as a key clinical advisor to the Delivery Board through the Theme 3 Clinical
Reference Group, and is a member of the clinical alliance
This would need to be a paid role (1-2 sessions per week) for a period of 12
months with review after 6 months. A formal recruitment process (job description
and expression of interest followed by interview) will be required. This could be
completed within six weeks once a full role specification and EOI has been
finalised.
2.4.3. System Provider Sponsor and System Commissioner Sponsor– role outline
This role will provide GM-wide executive leadership, within the relevant area, to
Articulate and promote the vision for change
Provide direction to support delivery within agreed timescales, and advise on
the resolution of issues blocking the progress of delivery
Lead the reporting and stakeholder management with the Provider Federation
Board and Joint Commissioning Board
7
Oversee and drive the implementation of immediate interventions to improve
the quality, safety and efficiency of patient care; and longer term strategic
changes
Advise on strategic issues affecting the delivery of the change
Represent and champion the project within the wider GM Health and Social
Care Partnership key stakeholders and groups
This role would be provided from within the system with nominations received
through an expression of interest for decision by the Partnership.
Recommendation: it is recommended that the processes to fill the above roles are
initiated as soon as possible to ensure that leadership is in place for when the
scope and specification of work (PIDs) is agreed by the Partnership.
3.0 How will Theme 3 deliver its work?
3.1. Theme 3 priorities
3.1.1. The following Theme 3 priorities received system endorsement from the AGG, The
Provider Federation Board, and the Strategic Partnership Board in September, with
agreement to start work on the scope and specification of work (PIDs) immediately:
Paediatrics (including specialised children’s services)
Maternity and obstetrics
Respiratory and cardiology
Benign urology
MSK and Orthopaedics
Breast services
Neuro-rehabilitation
Vascular
Ophthalmology and HIV were also endorsed to commence PID work as part of a
second phase of work.
3.2. The challenge
3.2.1. With the pressures faced by acute hospital services to deliver high quality care
against increasing demand, workforce shortages and a significant financial shortfall
across GM, there is need for Theme 3 to accelerate the pace of change and be
agile, flexible and task focused to successfully bring about the required benefits.
8
3.2.2. For larger-scale service changes where a GM decision is required, there is a need
to understand and learn the lessons from previous reconfigurations to design
decision making processes that deliver robust decisions able to withstand
challenge. There is also a need to build on recent successes such as the approach
developed by the NHS Transformation Unit for the commissioning of “world class”
OG and Urology cancer services for Greater Manchester (and East Cheshire) that
previously has been undeliverable for nearly a decade, despite many previous
attempts.
3.2.3. To effectively deliver change that releases the expected benefits requires:
1. Design and implementation of an effective model of care through a
detailed commissioning specification that resolves the issues identified and
improves the service for patients. Key considerations include:
What clinical issues are we trying to resolve?
What is the best model of care to resolve these issues?
How do we standardize and ensure every patient receives a high standard of
care?
How do we ensure clinical services are as efficient as possible?
How do we ensure the required interfaces and expected integration with the out
of models are put in place to deliver the expected service benefits?
2. Execution of a robust decision making process that can withstand
challenge (as appropriate for the change in question). Key considerations
include:
What decision making process is relevant for each project? (e.g. procurement,
option appraisal etc.)
What governance is appropriate for each project?
What is the likelihood of challenge for each project? What actions and
governance is required to ensure a robust decision that withstands challenge?
How will the statutory requirements be met? How will the Four Tests for Service
Reconfiguration be met?
How will patients and the wider population be involved and engaged in the co-
design of changes? Is formal consultation required?
How will clinicians be engaged? What scale of clinical engagement and
consensus is needed?
9
How will the Greater Manchester JHSC be engaged?
What level of strategic service change assurance is required? NHS England /
Clinical Senate / Gateway review?
3. Strategic coordination at the system level to deliver a clinically coherent
future configuration of services across Greater Manchester that:
makes best use of all estate;
releases cost from the system (both short term cashable savings and medium
term savings) and contributes towards the financial savings position across
Greater Manchester;
improves performance;
engages with other themes and enablers in a coordinated way, and;
is delivered efficiently.
3.3. Clinically-led standardisation and innovation at pace
3.3.1. The Clinical Alliance has been a key asset in the delivery of Healthier Together with
a number of leading clinicians employed in clinical leadership roles to drive change.
It is a pan-GM group with a strong sense of ‘team’ and is well respected in the
clinical community. The agenda is based on exploring clinical themes that are
specific to the operationalisation of Healthier Together, for example enhanced
recovery for patients prior to surgery (ERAS+), ambulatory care models etc.
3.3.2. The model is one which could be adopted for Theme 3 to drive standardisation and
the implementation of immediate interventions to improve the quality, safety and
efficiency of patient care through the sharing of data, evidence-based changes and
innovations. At the same time it also provides a forum for the development / testing
of pan-GM clinical standards and models of care as part of any required clinical
redesign work.
3.3.3. This model could be adopted, building upon existing structures where relevant,
such as strategic clinical service networks but widening their multi–disciplinary
membership and using them as part of a Theme 3 task and finish group
Recommendation: Adopt the Clinical Alliance model to accelerate the delivery of
‘quick win’ improvements, starting implementation immediately.
3.4. Phases of work
3.4.1. The diagram below outlines the high-level phases of work and timescales starting
with the development of the scoping of work for each project (PIDs) which is already
underway:
10
3.5. On the assumption the system will work at pace, it is proposed that by the end of
Quarter 3 all priority projects deliver an overall assessment and high-level proposals
for change that can be subject to a ‘Gateway’ style review by the system
governance groups and Theme 3 Delivery Board, early in Quarter 4. This would
include decisions to fast track any early implementation opportunities where
possible (i.e. not requiring option appraisal, formal consultation etc.).
3.6. It is also proposed that these proposals for change are reviewed against a GM
Acute Clinical Services Strategy framework.
High-level phases of work and timescales for delivering Theme 3 priorities
3.7. The proposals for change would include the following a combination of sub-
products, subject to the project:
Case for change and root cause analysis of issues
Vision and proposed approach (options, service model) to deliver the change
Summary of the opportunities and evidenced quality, safety and efficiency
benefits, including quantification and type of savings
An indicative assessment of any long-list options for change
Task and finish recommendations for immediate implementation.
3.8. For some of the priority services, clinical redesign work has already been done to
develop standards, and new models of care (for example Paediatrics), and in these
cases, work needs to build on previous work that has previously be done by the
system and in many cases, the NHS Transformation Unit.
11
4.0 Issues to resolve
4.1. Interfaces with other parts of the GM system and Programme work streams
4.1.1. The standardisation of GM hospital services is one part of a much larger system
change driven by localities delivering improved primary, community and social care
services, with the interface between the two critical to delivering improved care;
illustrated below:
4.1.2. As part of the Theme 3 scoping of projects, links with other themes and Programme
work streams are already being made to identify and define the supporting pieces of
work that are needed from other parts of the GM system, to help bring about
change.
4.1.3. There will need to be clear understanding of the key priorities and deliverables from
other work streams. In addition, a number of these projects may be viewed as GM
cross-cutting work where inputs from other task and finish groups may be required
with overall co-ordination of work plans.
4.1.4. As part of this process of alignment, work will take place with the Strategic Clinical
Networks (SCN), to ensure appropriate levels of connectivity and support to the
Theme 3 work.
Recommendation: Assurance from the Partnership that the work programmes of
the Themes align, and interfaces are aligned to Theme 3’s delivery plan and vice
versa.
4.2. System ownership for cross-system changes (e.g. Children’s Services)
12
4.2.1. There will need to be some thought given to system wide ownership (and
subsequent implementation arrangements) where multiple change proposals are
anticipated for one service area across tertiary, secondary, primary and community
care and local government. Children’s services would be one such area.
Recommendation: System leadership roles are clearly identified and work with the
relevant theme leads to provide overall direction and co-ordination.
4.3. Timescales for agreement of resourcing projects and use of Transformation
Unit and any other suppliers
4.3.1. The PIDs are currently being prepared for Theme 3 priority projects that will outline
the projected resource requirements to take the project thorough the initial gateway
review and subsequent phases of service re-design as outlined above.
4.3.2. Projected resource requirements will cover the following:
expected resource in kind - use of available organisational resource
(commissioners and providers)
proposed clinical leadership backfill
expected specialist expertise required to deliver the different phases of the
project over the next 18 months given the expected return on investment
specific project management inputs required.
In addition, the overall strategic and programme co-ordination of the proposed
projects will need to be resourced we propose that this is outlined in a separate
PID. Administrative support to the Theme 3 governance will need to be provided by
the Partnership. This is currently resourced by the NHS Transformation Unit.
4.3.3. There is a risk that Theme 3 projects will be subject to a delay as result of the need
to commission resources, whether this is from internal sources such as the NHS
Transformation Unit or other suppliers. A quick approval process, so that work can
commence off the back of gateway review points would resolve this.
Recommendation: Implementation of a quick and clear process to commission
resources thorough the Partnership’s client function off the back of agreed resource
budgets and work briefs.
4.4. Communication of the programme work
4.4.1. As projects progress, there will be an increasing need to keep the system well
briefed of progress, on major stakeholder and engagement events, and the overall
direction of service models as they are developed. This will need to be properly
resourced to facilitate the change process.
13
Recommendation: Partnership Communication lead to assess and advise on the
communication and engagement programme budget required.
5.0 Summary recommendations
The Strategic Partnership Board is asked to:
1. approve the proposed governance changes as outlined in Section 2
2. endorse and provide feedback on the proposed approach and high-level
phasing of work and suggested gateway review points to deliver Theme 3
3. endorse or refine the approaches suggested to resolve the issues outlined in
section 4.0.