The Grand Parkway Association
Annual Report to the
Texas Transportation Commission
December 13, 2012
Grand Parkway/SH99 Overall Project Status
184 miles total project length
86 miles of studies are complete, Segments D, E, F-1, F-2, G & I-2
29 miles, Segment D, part of E, and part of I-2 are open to traffic
15 miles, Segment E, is under construction
38 miles, Segments F-1, F-2 & G, developer selected - ZOPB
92 miles, Segments B, C, and H & I-1, are under study
6 miles, Segment A, Feasibility Study is complete
Grand Parkway/SH99 FY2012 Activity Summary
Segment B DEIS approved
Segment B Public Hearings held
Segment C FEIS approved Segment D Fort Bend County
constructing 8 overpasses TxDOT completed 2 DC’s at IH10W Segment E construction advancing
on schedule Segments F-1, F-2 & G, RFP
process completed Segment H & I-1 comments
received and FEIS being prepared
Segment I-2 toll collection began Segment I-2 phase 2 Re-Eval for
tolling approved
Grand Parkway/SH99 Anticipated FY2013 Activity
Receive Segment B comments from the Public Hearing
Prepare Segment B FEIS Receive Segment C FEIS
comments, host a Public Workshop , prepare responses to comments and request the issuance of a ROD
Fort Bend County will continue work on their overpasses
Begin construction of 4 DC’s at IH10(W)
Continue construction of Seg. E Complete transaction with ZOPB
for Segments F-1, F-2 and G Approve Phase II of Segment I-2
FEIS Re-Eval for tolling