gradual re-start of the experiments and involvement of the ...€¦ · experience from pre-t0 phase...
TRANSCRIPT
Gradual re-start of the experiments and Involvement of the user community
Eckhard Elsen
Online information meeting: Plan for CERN’s gradual re-start, May 5, 2020
Information provided by the 4 LHC Experiments
Progress during lock-down
• Limited progress with sub-detectors wherever possible including in remote institutes
• Teleworking has been used everywhere
• Analysis unhindered thanks to availability of IT infrastructure
• Design – access to CAD software (incl. remote licence usage)
• ASIC development
• design requires access to licensed software
• chip submission depending on availability of foundry access2
Big Thank you to
IT department
ASICs have been a
major concern of
upgrades
Logistics is a challenge
• Delivery of components from other institutes (or companies)
• Production halted
• Delivery chain broken
• Availability of foreign experts is a major uncertainty
• Varying travel restrictions
• entry to France and Switzerland
• departure from home country and uncertainty of returning home (quarantine)
• permission from some countries for work at CERN still needs to be granted
3
Progress is very
difficult to predict
Example ATLAS NSW: Saclay has to resume Micromegas assembly before integration onto wheels at CERN.
Priority: completion of Phase 1 and preparation of Phase 2 upgrades
LS2 Shutdown, where we are now
27/04/20 R.Carlin RRB-2020-027
HCAL barrel (last phase I):
install SiPM+QIE11-based
5Gbps readout
Pixel detector:
• replace barrel layer 1 (guideline
250 fb-1 max lumi)
• replace all DCDC converters
Muon system (already phase II):• install GEM GE1/1 chambers
• Upgrade CSC FEE for HL-LHC trigger rates
• Shielding against neutron background
Keep strip tracker cold to avoid reverse annealing
Install new beam pipe for phase II
MAGNET (stays cold!) & Yoke Opening • Cooled freewheel thyristor+power/cooling
• New opening system (telescopic jacks)
• New YE1 cable gantry (Phase2 services)
Near beam & Forward Systems • BRIL BCM/PLT refit
• New Totem T2 track det
• PPS: RP det & mechanics
upgrade
9
Civil engineering on P5 surface to prepare for Phase-2 assembly and logistics
Coarse schedule:• 2019: Muons and HCAL interleaved• 2020: beam pipe installation, then pixel re-
installation
• Some Phase 1 and maintenance, improvements
• Many activities already related to Phase 2 detector upgrades and relate services and infrastructure
Operations Spectroscopy CP violation Heavy ions Upgrade
LHCb upgrade I
LHCb-TDR-12
Emilie Maurice (LAL, LLR) LHCb status report 16/26
ALICE
CMS LHCb
ATLAS
4
Experience from pre-T0 phase
• Experiments have started to work under COVID-19-like safety measures both in laboratories and at the experimental points
• Feedback to HSE on
• wearing masks and Personal Protection Equipment in general; duration of work and practicalities of maintaining physical distance
• access to experimental points: hands-free use of doors and elevators
• density of people
Provides in
stant feedback
- good
training
Re-start of Experiments depends on Availability of Users (experts)
May June July August September October November December
T0: Begin of gradual re-start
June 8, LHC experiments and Accelerator: LS2 and Run 3
2020
Today
CERN all open
Users returning
Practicing work under COVID-19 rules
High priority work resuming where possible
User presence depends on travel restrictions
6
Selection of ALICE activities during first 4-weeks of re-start
ALICE phase 2 activities 205.05.20
• Cabling and connectors • Cooling and ventilation pipes • Patchpanels • Support structures • Installation tests …
Miniframe (Service support structure)
SX2 surface building P2 ALICE Cavern
• Inox cooling pipe installation • MFT cooling plant installation • Cabling and connectors • Rack turbine replacement • TPC heatscreens • TOF readout modules and cooling • Muon system electronics upgrade
ALICE experiment cavern Cleanrooms and workshops
• TPC commissioning SXL2 (P2) • ITS commissioning Bat. 167 (Meyrin) • Mechanical workshop Bat. 162 (Meyrin)
Bat 167
SXL2 surface building P2
7
ATLAS focus during first 4 weeks
• Highest priority
• New Small Wheel and Liquid Argon
• TDAQ upgrade (also as support for the other remote activities)
• BIS 7/8 muon spectrometer
• but also urgent maintenance on cryogenics and magnet
• and then
• SCT and Tile Calorimeter
• Phase II upgrade (ITK, HGTD and Tile)
Progress slowed down since
even some experts in the area
cannot yet access CERN.
8
CMS focus during initial period
• Warm-up of magnet ongoing (30 days)
• CSC removal and refit (P5-UXC, P5-SX)
• CSC electronics revision (867/904)
• GEM assembly and test (904, P5)
• HCAL control module diagnostics (904)
• Beam pipe/pixel/lumi monitor upgrade (P5,186)
9
Initial LHCb activities
• Vertex Locator
• Installation of RF foil, preparation done, in collaboration with EN and TE, week 19/20.
• Upstream Tracker
• Cleaning of CO2 cooling test station, together with EP-DT, started 30 April.
• RICH
• RICH 2 column installation in test rack and commissioning, in collaboration with EP-DT, started 4 May
• Muon
• Installation of new electronic boards, replacing old backplanes, cabling up control boards, registration into the DB, started 28 April
10
Gradual re-start of non-LHC experiments and activities
• NA-experiments, ISOLDE, AD-experiments begin some small activities after T0 (to allow e.g. progress on thesis work) where easily and safely feasible
• Re-start of the EP workshops to support experiments where needed
• IT will slowly bring back small teams to allow working from adequate work places
• Library will reopen once there is a sufficient population at CERN to warrant presence. All library staff can be contacted remotely in the meantime (btw: New INSPIRE rolled-out during Lock-down).
11
Conclusion
• Many activities continuing in home laboratories on sub-components
• Teleworking continues (analysis, simulation, engineering, documentation)
• Gradual re-start
• practicing social distancing and learning to work in space restricted areas
• progress difficult to predict while travel restrictions persist; experiments making efforts to circumvent bottlenecks
12