1) Project Cost management processes
a. Estimate cost developing an approximation of proj costb. Determine Budget Aggregation of indic=vidual activity cost or work package cost
c. Control cost - Monitoring status of project to update project budget.
2) The ability to influence cost is greatest at the early stages making early scope definition critical.
3) Cost management plan has the following
a. Level of accuracyb. Units of measure
c. Organizational process link
d. Control thresholde. Rules of performance measurement
f. Reporting formats and frequency
g. Process descriptions
4) Samples Unit of measures for Resourcesa. Staff hours
b. Staff daysc. Staff weeks
d. Lump sume. Currency
NOTE : First 4 are considered to eliminate effect of currency fluctuation
5) Some earned Value techniques
a. Weighted milestonesb. Fixed formula
c. Percent complete
6) Ways and Times for measuring costs of Aquired items
a. When acquisition decision is made
b. When acquisition is commited
c. Order is placedd. Item is delivered
e. Actual cost is incurred
f. Actual cost is recorded
7) Project Cost management should be concerned about
a. Cost of resources needed to complete the project
b. Recurring cost of usingc. Recurring cost of maintaining
d. Cost of Supporting the product , service , or result of the project
8) General management techniques used in predicting and analyzing the prospective financial
performance of the projecta. Return on Investment
b. Discounted cash Flow
c. Investment payback analysis
-
7/28/2019 GR Types Contd
2/27
9) Estimation degree
a. Rough Order of estimation - +-50%b. Definitive - +-10%
10) Types of resource costa. Labor
b. Material
c. Equipment
d. Servicese. Facilities
f. Special Category Inflation allowance
g. Special Category Contingency Costs
11) Types of cost
a. Direct Cost b. Indirect Cost Costs that cannot be directly traced to a specific project
Accumulated and Allocated Equiatbly between multiple projects
Allocation follows some Approved & documented accounting procedure12) Time Sensitive costs -
a. Union Labour with regularly expiring collective bargaining agreementsb. Materials with seasonal cost variations
13) Cost Inputs from Human resource paln
a. Project staffing attributes
b. Personnel ratesc. Rewards and Recognition
14) Cost associated with Risk- Risk mitigation cost
15) Cost contingency reserves can be
Used
ReducedEliminated
16) basis of estimate is also important output of estimate cost
17) Funding limits/constraints etc can be got from the Project scope statement
18) Budget reserve Analysis establishesContingency reserves
Management resreves
19) Management reservesa. Budgets reserved for Unplanned changes to project scope and cost
b. Need prior approval from management for spending
c. Not part of cost baselined. Part of project budget
e. Not included as part of EVM
20) Funding limit reconciliation
a. Expenditure vs Commitment of Fund
21) Cost performance baseline
-
7/28/2019 GR Types Contd
3/27
a. Summation of approved budget by time period
b. Typically displayed as a S curve ( Time vs Cumulative Values)c. In EVM technique its called as performance measurement baseline (PMB)
22) Project Fundinga. Total Funding requirements
b. Periodic funding requirements (quarterly, annual)
23) Project Cost Control includesa. Influence the factors that creates change to the cost baseline
b. Ensure all change requests are acted in a timely manner
c. Managing the actual changes when and as they occurd. Ensuring cost expenditure go beyond funding
e. Monitor cost performance to isolate and understand variances from the approved cost
baselinef. Monitoring work performance against funds expended
g. Preventing unapproved changes from being included
h. Informing appropriate stakeholders of all approved changes and appropriate costi. Acting to bring expected cost runs within acceptable limits
24) 3 key dimensions developed and monitored in EVM
a. Planned valueb. Earned Value
c. Actual Cost
25) Total PV of a project is BAC
26) Types of variances
a. Schedule Variance = EV - PVb. Cost variance = EV AC
i. ( any negative CV is non-recoverable)
27) Performance Index
a. Schedule performance index = EV/PV
i. < 1 less work was completed than planned
ii. > 1 more work is completed than plannedb. Cost performance index = EV/AC
i. < 1 Cost overrun for work completed
ii. > 1- Cost underrun for work completed
28) Forecasting EMV
a. EAC Estimate at Completion
b. ETCc.
29) Forecasting the EAC involves making estimates or predictions of condition or events in theprojects future based on the information and knowledge available at the time of the forecast.
30) Ways of claulating EAC
a. EAC = AC + bottom-up ETCb. EAC = AC + BAC - EV ( when current cost performance will become better in the
future )
c. EAC = BAC/ Cumulative CPI ( when current cost performance continues in the future)
-
7/28/2019 GR Types Contd
4/27
d. EAC = AC + {( BAC EV) / ( cumulative CPI X Cumulative SPI ) } considering bothe
SPI and CPI
31) TCPI = (BAC-EV)/(BAC-AC) = Work remaining / Funds remaining
TCPI =(BAC EV) / (EAC AC)
32) Performance reviews
a. Compare cost performance over time
b. Schedule activities or work packages overrung or Underrunning budgetc. Estimated funds needed to complete the project
33) Info got in Performance review if EVM is useda. Variance analysis planned vs expected
b. Trend Analysis improve vs detiortate
c. Earned Value performance baseline vs actual
34) Percentage of acceptable variance will decrease as more work is accomplished
Quality management
35) Quality management processesa. Plan Quality identify Quality requirement , standards and documenting how they will
complyb. Perform QA Auditing to see if its followe
c. Perform Quality control Monitor and record results of executing Quality activities,
recommend corrective actions
36. Quality vs grade
Quality is the degree to which a set of inherent characteristics fulfill requirementsGrade is same functional use but different technical characteristics
37. Precion vs AccuracyPrecison less scatter
Accuracy closer to the true value
38. Quality management approaches bya. Proprietry
i. Deming PDCA
ii. Juran iii. Crosby
b. Non proprietry
i. TQM
ii. Six Sigmaiii. Failure mode and Effect Analysis (FMEA)
iv. Design reviews
v. Voice of Customervi. Cost of Quality
vii. Continuous Improvement
39) Modern Quality management and project management recognize the importance ofCustomer Satisfaction
Conformance to requirements
Fitness to usePrevention over Inspection
-
7/28/2019 GR Types Contd
5/27
Quality is planned, designed and built in not inspected
Cost of preventing mistake is much less than correcting them when found by inspectionContinuous Improvement
Deming/Shewhart PDCA
TQM and Six Sigma improve project management and product qualityProcess Improvement Models
Malcolm balridge
OPM3
CMMIManagement Responsibility
40) Quality Policy OPAa. Use performing organizations policy as is
b. If no formal policy or multiple performing organization Project management team
creates onec. Make it aware to all stake holders thru distribute information
41) Beneifits of Qualitya. Less rework
b. Increased productivityc. Lower costs
d. Increased stakeholder/customer satisfaction
42) Cost of quality
a. Cost of Conformancei. Prevention Cost (Build a Quality project)
1. Training
2. Document processes3. Equipment
4. Time to do it right
ii. Appraisal Cost (Assess The Quality)1. testing
2. Destructive testing loss
3. Inspections
b. Cost of non conformancei. Internal Failure Cost ( Failure Found by the Project)
1. rework
2. Scrapii. External Failure Cost ( Failure found by the Customer)
1. Liabilities
2. Warranty Work
3. Lost business
43. Control Charts
Upper and Lower Specification limit by requirementUpper and Lower Control limit By Project manager and Stakholders- Take corrective action
44) For repetitive processes the control limits are generally +-3 sigma
45) Process is out of control when
Data Point exceeds a control limit7 Consequitive points are above or below the mean
-
7/28/2019 GR Types Contd
6/27
46) Uses of Control chartsa. Monitor various type of output variables
b. Used most frequently to track repetitive activities required for manufacturing
c. Monitor Cost and Schedule varianced. Monitor Volume and frequency of Scope Changes
e. Other management results to Monitor Project management processes
47 ) benchmarkingCompare Actual or Planned project practices to those of comparable projects
Within the same org or outside
Within the same application area or different
48) Benchmarking helps to
Identify best practicesGenerate ideas for Improvements
Provides a basis for measuring performance
49) DOE
A statistical method .. Change more than 1 variable at a timeIdentify which factors influence which variable of a process or product
Used to determine number and type of test to be conductedReduces Sensitivity of product performance to source of variations
50) Statistical SamplingChoose a population of Interest
Sample frequency
Sample size
51) Flow Charting
Graphical rep of a processShows relationship among processes
Help anticipate Quality problems that occur better test cases
52) All Flowcharts showActivities
Decision Points
Order of processing
53) Additional Quality Planning Tools
Brainstorming
Affinity Diagram logical groupingNominal group technique
Force Field Analysis Diagram of the forces for and against change
Matrix diagram - factors vs causes or objectivesPrioritization matrices rank a diverse set of problems and/or issues by importance
54) Quality MetricsA project or product attribute defining a operational definition
How a Quality control process will measure it
55) Sample of Quality metrics
-
7/28/2019 GR Types Contd
7/27
On-time performance
Budget controlDefect frequency
Failure rate
AvailabilityReliability
Test Coverage
56) Process boundariesPurpose of process
Start and end of process
Inputs and OutputsData Required
Owner / Stakeholder
57) Quality Audit
Identify best practices and share them
Identify gap/short comingsProactively improve process
Highlight contribution of each audit
58) Quality Audits can beScheduled or Random
Internal or External
59) Quality Audits can confirm the implementation of approved change requests including corrective
action, preventive action, defect repair
60) Process Analysis
Examine Problems experienced
Constraints experiencedNon value added activities
61) Root Cause analysis
Identify the problemDiscover underlying causes
Develop preventive actions
62) Prevention vs Inspection
63) Sampling
Attribute Sampling ( result conforms or does not)Variables Sampling measures degree of conformity)
64) Tolerance vs Control limit
65) Ishikawas 7 basic tools of Qality
Cause and Effect DiagramC
F
HP
-
7/28/2019 GR Types Contd
8/27
R
SS
66) HistogramX axis attribute or characterisc
Y frequency
Common cause of problems - Tallest
66) Pareto
Histogram ordered by freq of occurrence
Rank ordering to focus corrective action80/20 ANALYSIS
67) Run ChartData poimts plotted in the order they cocur
Show History and pattern of variation
ShowTrends in a process over time
Variation over timeDeclines or improvements over time
68) Trends Analysis
Use Run charts
Involves mathematical technique to forecast future outcomes based on historical infoUsed to monitor
Technical performance
Cost and Schedule performance
69) Scatter Diagram
Shows relationship between 2 variablesStudy and identify relationship between 2 variables
Plot Dependent variable
Plot Independent variable
The Closer they are are to the diagonal line the more closely they are related
70) lessons learnt are documented throught the project life cycle but at a min during closure
71) Validated Deliverables
- Deliverables checked for correctness
Validated Change
- Changed or repaired items are inspected- Accept if ok
- Reject if not Send to rework
- Provide notification of the decision
72) HR management process
Develop Human resource Plan - identifying and documenting project Roles and RespRequired Skills
Reporting relationships
Creating a Staff Managmengment PlanAcquire team Confirming Availability and obtaining the team
-
7/28/2019 GR Types Contd
9/27
Develop project team Improve Competencies, team interaction, And overall team environment
Manage Project team Track team member performance, providing feedback, resolving issues,managing changes to optimize project performance
73) Other names for Project management team
a. Core team
b. Executive team
c. Leadership team
74) Role of Project Sponsor
a. Assists the Project management team ini. Project Funding
ii. Clarifying Scope
iii. Monitoring progressiv. Influencing others in order to benefit the project
75) Human resource factors that impact the project
a. Team environmentb. Geographical location of team members
c. Communication among stakeholdersd. Internal and External politics
e. Cultural issues
f. Organizational Uniqueness
76) The Management team should make sure that the project team does the following regarding
professional ethicsa. Aware of
b. Subscribe to
c. Ensure all team members follow
77) Things in the HR plan
a. Project roles and responsibilities
i. Roles (Designation)ii. Authority (Rights)
iii. Responsibilities
iv. Competencies (skill and capacity)b. Project Organization Chart
c. Staffing management plan
i. Staff acquisition
ii. Resource Calendars ( resource histogram)iii. Staff Release plan ( Monitor cost, boost morale)
iv. Identification of training needs ( Increase competencies, certifications)
v. Plans for Rewards and Recognitionvi. Compliance Consideration ( Union contract, govt regulation, other HR policies)
vii. Safety issue (protection)
d. Team building strategies
e. Impact of the staffing management plan on the organization
78) Types of Roles and responsibility charts
-
7/28/2019 GR Types Contd
10/27
a. Hierarchical
b. Matrixc. Text-oriented
79) Places where we can find Roles and responsibilitiesa. Organizational Chart
b. Subsidary plans like
i. Risk, - Risk Owners
ii. Quality or Who is responsible for QA , QCiii. Communication - Who is responsible for communicating
80) Types of Hierarchichal Type Resource Charts
a. WBS
b. OBSc. RBS
81) Types of matrix resource Chartsa. RAM responsibility Assignement Matrix
i. High level Ram Bu groupsii. Low level RAM By Roles, resp, authority
82) Types of RAM
a. RACI
b. By leadsc. By resource designation
83) usual information contained in Text oriented forma. responsibilities
b. authority
c. competenciesd. qualifications
84) Other names of text type formats
a. Position Description formb. Roles-Responsibility-Authority forms
85) Networking is thea. Formal and Informal interaction
b. With others in an
i. Organization
ii. Industryiii. Professional Environment
c. Constructive Way to understand political and Interpersonal factors that effect staffing
management
86) Human Resources networking Activities
a. Proactive Correspondenceb. Luncheon meeting
c. Informal Conversation
d. Meetings and Eventse. Trade Conferences
-
7/28/2019 GR Types Contd
11/27
f. Symposia
87) Uses of Networking
a. Useful technique at the beginning of project
b. Effective way to enhance Project management professional development during theproject and after it ends
88) Organizational theory provides information regarding the way in which people, team and
organizational units behave
89) Uses of knowing Organizational theory
a. Shortens the time cost and effort needed to create HR plan outputs
b. The likelihood the plan is effective increases
90) Resource Histogram
a. X axis , resource or by calendar
b. Y axis max number of hours available
91) Apply following resource leveling strategies when bars go beyond max hours availablea. Add More resources
b. Modify schedule
92) factors that may affect the Project management team in team members selection
a. Collective bargaining agreementsb. Use of Subcontractor personnel
c. Matrix project environment
d. Internal or External reporting relationshipse. Other reasons
93) factors to be considered during project acquiringa. PM should negotiate and influence in acquiring
b. HR acqusiotion results in proj success failures
c. Should settle for alternative resources if not available
94) Acquire Project team
a. Pre Assignement (selected in advance )
i. Becos they were promised as a part of a competitive proposalii. Project needs some expertise
iii. Staff assignments defined in the charter
b. Negotiation
i. Negotiate with Functional managerii. Negotiate with Performing organization
iii. Negotiate with External orgs, Contractors,
c. Acquisitioni. Hire Individual Consultants
ii. Sub contract
d. Virtual teams
95) Virtual teams becos
a. Teams in Diff geo areasb. Expert in diff geo area
-
7/28/2019 GR Types Contd
12/27
c. Work from home
d. Disabilitiese. Different shifts
f. Save Travel Expenses
96) Important Considerations for Virtual teams
a. Communication Planning - most imp
b. Set expectation
c. Facilititate communicationd. Develop protocol for resolving conflict
e. Include people in-decision making
f. Share credit in success
97) technology used in Virtual teams
a. e-mailb. Audio conferencing
c. Video conferencing
d. Web-Based meetings
98) Types of Project Staff assignment documentation
a. Project team directoryb. Memos to team members
c. Names inserted in proj management plan ( like Organization Charts and schedules)
99) factors to concentrate to create reliable Resource calendars/ schedule
a. Good Understanding of each persons schedule conflictb. Including Vacation times
c. Including Other Project time
d. Document team members availability
100) High Team performance can be achieved using
a. Open and Effective communicationb. Developing trust among team members
c. Managing conflicts in a constructive manner
d. Encouraging Colobarative problem solvinge. Encouraging Colaborative decision-making
101) PM roles to foster teamworka. Create an environment which facilitates team work
b. Motivate team by providing challenges and opportunities
c. Provide timely feedbackd. Provide timely support as needed
e. Recognize and reward good performance
102) Objectives of developing team
a. Improve Knowledge and skills of team members
b. Improve feeling of trust and agreement among team membersc. Create a dynamic and cohesive team culture
-
7/28/2019 GR Types Contd
13/27
d. Allows cross training
e. Allows mentoring
103) Develop project team Tools and techniquesa. Interpersonal skill (soft skills)
b. Training
c. Team Building activities
d. Ground Rulese. Co-location
f. Recognition and rewards
104) soft skills
a. Empathy
b. Influencec. Creativity
d. Group facilitation
e. Understand sentimentsf. Anticipate actions
g. Acknowledge their concersh. Followup on their issues
105) Training
a. Formal vs Informal
b. Scheduled vs Unplannedi. Scheduled : as per HR plan
ii. Unplanned
1. as a result of observation2. As a result of conversation
3. as a result of Project performance appraisals during managing
106) Team Building activities
a. Simple 5 minute agenda in a status review meeting
b. Professionaly facilitated experience
107) To build effective project teams, PM should
a. Obtain Top management support
b. Obtain Commitemnt of team membersc. Introduce appropriate rewards and recognition
d. Create a team identity
e. Manage conflict effectively
f. Promote trust and open communication among team membersg. Provide good ledership
108) 5 stages of team developmenta. Forming
b. Storming
c. Normingd. Performing
e. Adjourning
109) Duration of a team development stage depends on
-
7/28/2019 GR Types Contd
14/27
a. Team size
b. Team dynamicsc. Team leadership
110) Ground Rulesa. Acceptable behaiour
b. Decreases misunderstanding and increases productivity
c. Helps discover values important to one another
d. All team members enforce it
111) Co locationa. Temporary only during strategic important times in the project
b. Entire Project
112) Co location strategies
a. Team meeting roomb. Places to post schedules
c. Other conveniences that enhance Communicationd. Other conveniences that enhance a sense of community
113) Rewards and recognition
a. Should satisfy need values by the individualb. Consider Cultural differences
c. Reward only desirable behaviour
d. Should not be Win-Lose or zero Sum awards ie be acheivble by all
114) Types of rewards
a. Tangiblei. Money
b. In Tangible
i. Opportunity to Grow, accomplish
ii. Opportunity to apply their professional skills to meet new Challengesiii. Public recognition of Good performance
115) Team assement fill up later bored116) Manage Project team tools and techniques
a. Observation and Converstaion
b. Project Performance appraisals
c. Conflict managementd. Issue Log
e. Inter personal skills
117) Objectives for conducting Performance appraisals
a. Clarification of roles and responsibilities
b. Constructive feedback to team membersc. Discovery of unknown or Un resolved issues
d. Development of individual training plans
e. Establish specific goals for the future
-
7/28/2019 GR Types Contd
15/27
118) Sources of Conflict
a. Scarse resourcesb. Scheduling priorities
c. Personal work styles
119) Ways to reduce conflict
a. Team ground rules
b. Group norms
c. Solid project management practices like communication planning and role definition
120) Conflict resolution
a. First Project team membersb. If escalated , PM should facilitate resolution
121) Addressing Conflicts
a. Early
b. In privatec. Direct colborative approach
d. If distruptive follow formal procedures including disciplinary action
122) Characteristics of conflict and conflict management processa. Natural and forces a search of alternatives
b. Is a team issue
c. Openness resolves conflictd. Focus on issues not personalities
e. Focus on present not past
123) factors that Influence Conflict resolution methods
a. Importance
b. Intensityc. Urgency / Time pressure
d. Position of players involved
e. Motivation to solve it on a long term or short term basis
124) 6 GENERAL TECHNIQUES for resolving conflict
a. Withdrawing/Avoiding
b. Smoothing/Accomodating = emphasize areas of agreementc. Compromising brings some degree of satisfaction
d. Forcing
e. Collaborating Multiple viewpoint, perspectives then consensus
f. Confronting/Problem Solving Examine alterantiave , give and take , open dialog
125) Issue log
a. Issueb. Responsible person
c. Target Date
d. Issue resolution
126) Interpersonal skills
a. Leadershipb. Influencing
-
7/28/2019 GR Types Contd
16/27
c. Effective Decision making
127) Key influencing skills see page 240
128) Staffing changesa. By Choice or Uncontrolled
b. Includes
i. Moving people
ii. Outsourcing some workiii. Replacing team members who leave
129) Communication Management includes the timely and appropriate
a. Generation
b. Collectionc. Distribution
d. Storage
e. Retrievalf. Ultimate disposition
Of project information
130) Project Communication Management processesa. Identify stake holders Identifying and Documenting their I I I
b. Plan communication Determine stakeholder Information needs and Defining a
communication approachc. Distribute Information Making information available as planned
d. Manage Stakeholder Expectations Communicate and Working with stakeholder to meet
their needs and addressing issues as they occure. Report performance Collect and Distribute Performance Info(status report, forecasts,
Progress measurement)
131) Type of Communication
a. Type 1
i. Internal Within the project
ii. External Other Projects, media, public , Customerb. Type 2
i. Formal Reports , memos , briefings
ii. Informal email, ad-hoc discussionc. Type 3
i. Vertical Up and Down the org
ii. Horizontal With peers
d. Type 4i. Official Newsletter, Annual report
ii. Unofficial Of the record communication
e. Type 5i. Wriiten
ii. Oral
f. Type 6i. Verbal
ii. Non verbal Voice Inflections, Body Language
132) Stakeholder handling strategy
-
7/28/2019 GR Types Contd
17/27
a. Maximize positive influences
b. Mitigate potential negative impacts
133) Stake Holder Analyis
a. Identify all stake holders Their III, Roles, departments, Knowledge level, expectationi. Done by Interviewing
b. Classify them
i. Power Interst
ii. Power Influenceiii. Influence Impact
iv. Salience
1. Power (ability to influence their will)2. Urgency ( Need for Immediate attention)
3. legitimacy ( Involvement is appropriate)
c. Asses how they respond in various situation in order to plan to influence them
134) Power Interest grida. Low Interest Low Power Monitor
b. Low Interest High Power keep Satisfiedc. High Interest Low Power Keep Informed
d. High Interest High Power Manage Closely
135) Getting Expert Judgement
a. Individual Consultationi. One on One meeting
ii. Interview
b. Panel formati. Focus groups
ii. Surveys
iii. Etc
136) Stake holder register has
a. Identification Info
b. Assesment infoc. Stake Holder Classification
i. Internal / External
ii. Supportor/ neutral/ resistor
137) Stake Holder management strategy
a. Key stakeholders
b. Level of participation desiredc. Stake holders and their management (as groups)
138) Plan Communicationa. Who needs what
b. When
c. Who will give it to themd. How will it be given to them
139) Problems dues to Improper Communicationa. Delay in message delivery
-
7/28/2019 GR Types Contd
18/27
b. Communication of sensitive info to wrong audience
c. Lack of communication
140) Types of Communication
a. Effective Info is providedi. In the right time
ii. Right format
iii. Right Impact
b. Efficienti. Providing only the information which is needed
141) Plan Communication Tools and Techniquesa. Communication Requirement Analysis
b. Communication Methods
c. Communication technologyd. Communication Models
142) Communication requirement Analysis
a. N * (n-1)/2b. Who gets what
143) Communication Methods influencing factors
a. Urgency
b. Staffing ( Expertise and Experience)c. Availability ( Access to)
d. Duration
e. Project Environment (face to face or virtual)
144) Communication Model Components
a. Sender b. Receiver
c. Medium
d. Message
e. Noisef. Encode
g. Decode
h. Feedbacki. Feedback message
j. Acknowledge
k. response
145) Example of Noise
a. Distance
b. Unfamiliar technologyc. Lack of background information
146) Communication model responsibilitiesa. Sender - Information is clear and Complete so that the receiver can receive it correctly
Confirming its properly understood
b. Receiever Information is received in its entiretyUnderstood correctly
-
7/28/2019 GR Types Contd
19/27
Acknowledged
147) Communication methods
a. Interactive - meetings, phone calls, video confrencing
b. Push - letters, memos, reports, email, faxes, voice mails, press releases etcc. Pull Intranet, online learning, knowledge repositories
148) When pull communication is useda. Large Volumes of Info
b. Large Audiences
c. Access at their own discretion
149) Contents of a Communication management plan 0- refer page 257
150) Effective Information Distribution techniques
a. Sender receiver Modelsb. Choice of media
c. Writing styled. Meeting management technique
e. Presentation techniquef. Facilitation techniique
151) Distribute Information Communication methods
a. Individual/Group meeting
b. Video and Audio conferencesc. Computer Chats
d. Remote communication
152) Information Distribution Tools
a. Hard-copy documents
b. Electronic communication and conferencing toolsc. Electronic tools for Project management
153) Types of Logsa. Issue Log
b. Change Log
154) Variance analysisa. Verify Quality of Info
b. Determine variance
c. Determine the impact of the variances
155) Categories of forecasting methods
a. Time Series methods Use historical data for future out comeb. Causal/econometric - Forecast using influencing underlying factors
c. Judgemental method Intuitive judgement, opinion and probability estimates
d. Other methods
-
7/28/2019 GR Types Contd
20/27
156) Eg of Time Series Method
a. Earned valueb. Moving average
c. Extra polation
d. Linear predictione. Trend estimation
f. Growth Curve
157) Eg of causal/ Econometrica. Regression analysis using linear or non linear regression
b. ARMA autoregressive moving average
c. Econometrics
158) Eg of judgemental methods
a. Composite forcastsb. Surveys
c. Delphi method
d. Scenario buildinge. Technology forecasting
f. Forecast by analogy
159) Eg of other methodsa. Simulation
b. Probabilistic forecasting
c. Ensemble forecasting
160) Objectives of risk management
a. Increase the probability and impact of positive eventsb. Decrease the probability and Impact of negative events
161) Risk management processesa. Plan risk management
b. Identify risks
c. Perform Quality Risk Analysis
d. Perform Quantitative risk Analysise. Plan Risk responses
f. Monitor and Control risks
162) cause of risk
a. requirement
b. assumption
c. constraintd. condition
163) Risksa. In the future
b. Uncertain
c. Has impact on atleast one project ojectived. Has one or more causes
e. Has one or more impacts
164) Project or Org Environment factors that could contribute to risk
-
7/28/2019 GR Types Contd
21/27
a. Immature project management practices
b. Lack of integrated management systemsc. Concurrent multiple projects
d. Dependency on external participants who cannot be controlled
165) Risk tolerance
a. Helps determine Threats allowed
b. Should balance with rewards
166) Plan Risk Tool Planning meeting and Analysis
a. Held by project teams
b. To develop Risk management planc. High level plans for conducting risk management activities discussed
d. Risk management Cost elements discussed
e. Risk schedule activities discussedf. Risk management responsibities assigned
g. Organizational templates tailored or generated to specific project
167) Risk management plan
a. Methodolgyb. Roles and responsibilities
c. Budegtingd. Timing
e. Risk categories ( eg as a RBS)
f. Definition of Risk Probability and Impactsg. Probability and Impact Matrix prioritize to high moderate low
h. Revised Stakeholder Tolerances
i. Reporting formatsj. Tracking
168) RBSa. Identified project risks
b. Arranged by category and subcategory
c. That identifies the various areas and causes of potential risks
169) Identify Risk
a. Determine which risks affect the project
b. Documenting their characteristics
170) Identify Risks Tools and Techniques
a. Documentation reviewsb. Information gathering technique
c. Checklist Analysis
d. Expert Judgemente. Diagramming techniques
f. Assumption Analysis
g. SWOT analysis
171) Documenattion review Review of Documents
a. Plansb. Assumptions
-
7/28/2019 GR Types Contd
22/27
c. Previous project files
d. Contractse. Other information
172) Information gathering techniquesa. Brainstorming
b. Interviewing
c. Root Cause Analysis
d. Delphi technique
173) Root cause analysis
a. Identify a problemb. Discover the underlying causes that lead to it
c. Develop preventive action
174) Delphi Technique
a. Facilitator prepares a questionnaire
b. Circulated to anonymously to Risk expertsc. Get Responses
d. Responses are summarizede. Recirculated to experts for further comments
f. Repeat till consensus is reached
175) Brainstorming
a. Free form ideas contributed by participantsb. Structured mass interviewing like Nominal Group tech
176) Checklist Analysis prepare checklist froma. Historical Info
b. Lowest level of RBS
177) Assumption Analysis Risks identified from Assumptions
a. Inaccuracy
b. Instability
c. Inconsistencyd. Incompleteness
178) Diagramming techniques
a. Cause and Effect diagram
b. System or Process flow chart
c. Influence Diagram
179) SWOT analysis
a. Identify strength and weakness of organization ( Performing or Wider business) throughtechniques like brainstorming
b. Analyze Opportunities from strengths
c. Analyze Threats from weaknessd. Analyze degree to which strengths offset Threats
e. Analyze degree to which opportunities may overcome wekness
180) Risk register
-
7/28/2019 GR Types Contd
23/27
a. List of identified Risks
i. EVENT IMPACTii. CAUSE,EVENT - EFFECT
b. List of potential Responses
181) Projects having more uncertainities / risks
a. State of the art
b. First of its kind
c. Highly complex
182) Qualitative Risk Analysis Tools and Techniquesa. Risk probability and Impact Assesment
b. Probability and Impact matrix
c. Risk data Quality Assesmentd. Risk categorization
e. Risk Urgency Assesment
f. Exper Judgement
183) P&I Risk ratinga. Diff rating for cost, schedule, scope
b. Overall rating for each riskc. Organization rating
d. Project rating
184) Risk responses
a. Hig risk Threats
i. Priority actionii. Aggressive responsive strategies
b. Low risk threats
i. Add to watch listii. Add a contingency reserve
c. High Risk Opportunities
i. Targetted
d. Low risk Opportunitiesi. Monitored
185) Risks categorizationa. By Source (using RBS)
b. By Areas of Project affected (Using WBS)
c. Other useful category (By Project Phases)
186) Quantitative Risk Analysis Numerically analyzing the effect of identified risks on
overall project objectives
187) Perform Quantitative Risk analysis should be repeated after ( to check if risks have been
reduced)
a. Plan Risk responsesb. Monitor and Control Risks
188) Quantitative risk Analysis Tools and techniquesa. Data gathering and Representation techniques
-
7/28/2019 GR Types Contd
24/27
b. Quantitative Risk analysis and Modelling techniques
c. Expert Judgement
189) Data gathering and Representation techniquesa. Interviewing ( eg give an estimate of optimistic, pessimistic and most likely estimates)
b. Probability Distributions
190) Quantitative Risk analysis and Modelling techniquesa. Sensitivity Analysis
i. Which risks have the most impact
b. Expected Monetary Value Analysis
c. Modelling and Simulation
191) Types of Proabaility Distribution
a. Continuous Probability Distribution
i. Betaii. Triangular
b. Discrete Distributionc. Uniform Distribution
d. Normal Distributione. Lognormal Distribution
192) Tornado diagram
a. Compare Uncertain and certain/Stable Variables
b. Compare relative importance and Impact
193) EMV
a. Analysis Under Uncertainityb. Opportunities Positive
c. Threats negative
d. EMV = Sum of (Value of each Possible Outcome (Impact) * Probability of accurance)
e. Eg decision tree analysis
194) Modelling and Simulation see page 299
195) Rissk responses have to bea. Appropriate
b. Cost effective
c. Realistic
d. Agreed upone. Owned by 1
f. Timely
200) Plan risk responses Tools and techniques
a. Strategies for Negative risks
b. Strategies for Positive Risksc. Contingent response Strategies
d. Expert Judgement
201) Strategies for negative Risks
-
7/28/2019 GR Types Contd
25/27
a. Avoid
b. Transferc. Mitigate
d. Accept
202) Avoid
a. Involves changes to PM Plan
b. Shut down project
203) Transfer
a. Ownership of Response to third partyb. Management of response to third party
204) Eg of Risk transference toolsa. Insurance
b. Performance Bonds
c. Warrantiesd. Guarantees
e. Contracts
205) Mitigatea. Reduction in probability
b. Reduce Impact
206) Eg of Mitigation Options
a. Adopting less Complex processs
b. Conducting more testsc. Choosing a more stable supplier
d. Prototype development
207) Mitigation strategies
a. Reduces severity of Impact
b. Targets factors that determine severity
208) Accept
a. Passive Acceptance
i. No actionii. Just document the risk
iii. Wait for it to happen
iv. Project team handles it when it happens
b. Active Acceptence
i. Establish a Contingency reserve
ii. Reserve can be Time, Cost,. Or Resources
209) Strategies for Positive Risks or Opportunities
a. Exploit - make sure it really happens probabilityb. Share
c. Enhance
d. Accept
-
7/28/2019 GR Types Contd
26/27
210) eg of Exploit
a. assign talented resource to finish fastb. assign talented resource to lower cost
211) Sharinga. Allocate or share ownership with someone who is best able to capture the opportunity
b. All parties gain from the action
212) Eg of Sharing Actionsa. Forming Risk-sharing partnerships. teams
b. Special purpose companies
c. Joint ventures
213) Enhance
a. Increase Impactb. Identify and maximize key drivers
214) Accept Opportunitiesa. Take advantage when it comes
b. Dont pursue
215) Contingent response strategiesa. Execute only under some conditions
b. Event triggers should be defined an Tracked
216) Types of Risks
a. Known Risks
b. Unknown Rosksc. Residual risks
d. Secondry Risks
217) Types of Risk Plan
a. Contingency Plan
b. Fall back Plan
218) Eg of Enhance
a. Adding more resources to finish early
219) Monitoring and Controlling Risks
a. Implementing Risk response plan
b. Tracking identified risksc. Monitoring residual risks
d. Identifying new Risks
e. Evaluating Risk process effectiveness throughout the project
220) assessed Risk
a. Can Changeb. Can retire
221) Risk Response Ownersa. Reports periodically to the PM on the effectiveness of the plan
-
7/28/2019 GR Types Contd
27/27
b. Reports any unanticipated effects
c. Reports correction needed to handle the risk appropriately
222) Monitor and Control Risks Tools and techniques
a. Risk Reassesmentb. Risk audits
c. Variance and Trend analysis
d.
223) Risk Reassesment
a. Identify new risks
b. Reassess Current Risksc. Closing of Outdated Risks
224) Risk Audit
225) Corrective Risk Actionsa. Contingency plans
b. Workarounds not planned initially