government of india national institution for transforming...
TRANSCRIPT
1
Government of India
National Institution for Transforming India (NITI) Aayog
(Project Appraisal and Management Division)
*****
Subject: Guidelines for grant of In Principle Approval (IPA) and Appraisal of Schemes/
Programmes/ Projects in NITI Aayog for 2015-16 – regarding.
The 12th
Five Year Plan is now in its 4th
year of implementation and will conclude in
2016-17. Therefore, it is necessary to ensure that new Schemes/Programmes are not
introduced on a stand alone basis without adequate budget provisions in this year and the next
year. In the case of projects, since all cost estimates are contingent on timely completion of
the project any proposal for a new project needs to be justified in terms of its feasibility and
cost, subject to provision of funds for the entry project to be ringfenced and assured until
completion.
02. In addition, the Annual Plan discussions that were held with the erstwhile Planning
Commission by Ministries/Departments have been discontinued. The annual allocations
under Plan are now in accordance with BE 2015-16 for the respective Ministries
/Departments.
03. Vide Notification dated 21st March 2015, the Allocation of Business Rules 1961 have
been amended to delineate the functions to be performed by NITI Aayog, that, inter alia,
includes
“To actively monitor and evaluate the implementation of programmes and initiatives,
including the identification of the needed resources so as to strengthen the probability of
success and scope of delivery”.
04. In view of the above, the existing guidelines for grant for ‘In-Principle Approval’
(IPA) have been examined de novo. On overall consideration, it is felt that the IPA process
as was being followed here to before has lost its relevance. Now, therefore, it is advised that
the following procedure be followed for BE 2015-16 in respect of new
Schemes/Programmes/Projects, that are sent by Ministries/Departments.
05. Central Sector Schemes/Programmes
(i) New Central Sector schemes/programmes which have been included in the budget
of the respective Ministries/ Departments for 2015-16 with full provision of
resources will not require IPA. Such proposals will be taken up for appraisal by
the concerned SMD/PAMD, as the case may be, in line with the procedures
detailed in these guidelines.
(ii) New Central Sector schemes/programmes which have been provided only a token
provision in the budget for 2015-16 or no provision at all would require, the
concerned Ministry/Department to submit the proposal in the prescribed SFC/EFC
format indicating inter alia:
2
Whether scheme/project/programme is part of the Finance Minister’s
Budget Speech 2015-16 with a full reference to the para in the Speech;
Whether the Proposal is to merge and/or include the new
scheme/programme/project with an existing scheme/programme/project
being implemented in the Ministry/Department;
Whether funding proposed for the scheme/programme/project and budget
available in 2015-16;
Whether quantifiable outcomes are expected from the scheme/programme;
and
Whether Concurrence of FA/IFD of the Ministry/Department concerned
has been obtained.
06. Projects in the following cases, NITI will not be required to process the proposal for
IPA:
New Coal and Power projects;
New Railway projects of national and strategic importance, for which
selection criteria has been approved by the Cabinet; and
New projects which have been included in the budget of the respective
Ministries/ Departments for 2015-16.
07. Railway Projects: In the case of all new railway projects (barring national and
strategic projects) which have been included in the budget of Ministry of Railways for 2015-
16 the following procedure shall be followed:
Processing of proposals will be in a single batch for all new projects in each
category such as Electrification, Doubling, etc. so that an integrated and holistic
view can be taken of the project timelines and cost estimates, if available;
All project proposals shall first be examined by a group comprising Advisor
(Transport) and Adviser (FR) in NITI Aayog and ED (Planning)/ ED (Rly
Electrification)/ED (Works), Railway Board which will prepare a shortlist of
projects, their prioritization and commitment for availability of funds;
Subsequent to the above, the MOR will circulate the SFC/EFC/PIB memo, as
the case may be, for each of the projects separately for appraisal and approval by
the Competent Authority; and
Proposals for material modifications in the approved Railway projects would not
require IPA and shall be processed as per extant guidelines for Revised Cost
Estimates (RCE) proposals.
08. Centrally Sponsored Schemes (CSS) No proposal for a new Centrally Sponsored
Scheme or a Sub component thereof shall be considered during 2015-16, without due
approval of the Competent Authority.
09. Delegation: All SFC proposals (up to Rs.500 crore), will be submitted by SMD to
CEO, NITI Aayog for approval. PAMD will appraise the proposal and submit the case to
3
CEO, NITI Aayog for approval of all other cases to be processed in accordance with the
delegation orders of the Ministry of Finance (Annexure-I)
10. SFC proposals: As per revised financial threshold of SFC proposals w.e.f. 29th
August 2014, new/ongoing schemes/programmes/projects costing up to Rs.500 crore or less
are to be processed for comments by the SMD and comments will be issued by SMD with the
approval of CEO, NITI Aayog. The Appraisal Grid adopted by PAMD for EFCs at
Annexure-II may be adhered mutatis-mutandis by SMDs while appraising /commenting SFC
proposals valuing up to Rs.500 crore as per existing delegation orders.
11. EFC/PIB proposals: As per revised financial threshold of EFC/PIB proposals
PAMD is responsible for appraisal of EFC/PIB proposals valuing >Rs.500 crore including
Railway projects. All other cases, i.e., SFCs, Cabinet notes and proposals coming from the
Departments outside the purview of the EFC/PIB will be processed by the concerned SMDs.
12. Checklist: For facilitating scrutiny of proposals received from
Ministries/Departments, a checklist has been prepared and is attached with these guidelines at
Annexure-III. The SMDs shall submit the completed checklist along with their
comments/observations for both SFC and EFC proposals. Therefore, NITI Aayog will
continue as the secretariat for the Standing Finance Committee/Expenditure Finance
Committee/Public Investment Board/PPP Appraisal Committee chaired by Secretary of the
Ministry/Secretary, Department of Expenditure, Secretary, Department of Economic Affairs
respectively.
13. Time Frame: As per Cabinet Secretariat OM No. 1/28/1/2009-Cab dated 3rd
December 2009, the time limit for completion of appraisal by appraising agencies in the NITI
Aayog is 4 weeks.
14. Process: SMDs should send their comments to PAMD, and not to the
Ministry/Department, within ten days of receipt of the EFC/PIB Memo from the
Ministry/Department.
15. The Ministries/Departments are required to ensure that two copies of SFC/EFC/PIB
proposals are sent to the NITI Aayog, one copy to Adviser (PAMD) and the other to Adviser
of the concerned SMD. In the event that a scheme/programme/project proposal is received by
only one of the Divisions (PAMD/Subject Division), the receiving Division will forward a
copy of the proposal to the other Division immediately.
16. The Ministries/Departments would be requested to also send soft copies of all
EFC/PIB/EBR proposals to Adviser PAMD by email at: [email protected].
17. A copy of the Appraisal Note issued by NITI Aayog would be marked to Vice Chairman
(VC), CEO and concerned Adviser in NITI Aayog. The Adviser of the SMD may refer
recommendations made by EFC/PIB while commenting on the Note of CCEA/ Cabinet for
approval.
18. Tracking: Position of EFC/PIB/EBR proposals pending for appraisal and proposals
awaiting comments of Subject Divisions will be reviewed and report sent to CEO, NITI by
5th
of every month.
4
19. EFC/PIB/EBR Meetings: Representative of PAMD will attend the meetings of
EFC/PIB and representative of SMD will attend the meetings of SFC. Representatives of both
PAMD and Subject Matter Division will attend EFC (proposal costing between Rs.500 crore
and Rs.1000 crore) chaired by Secretary of the administrative Ministry/ Department and the
Pre-PIB meetings.
20. The above appraisal and approval procedure would also apply for proposals of
Revised Cost Estimates.
This issues with the approval of CEO, NITI Aayog.
Sd/
(Rakesh Ranjan)
Adviser (PAMD)
Principal Advisers/ Sr. Advisers/ Advisers/ Consultants of all Subject Divisions,
NITI Aayog.
-------------------------------------------------------------------------------------------------------
NITI U.O. No. O-14015/02/2015-PAMD dated 29th
June 2015
Copy for information to:
1. PS to Vice Chairman/ PS to MoS/ PS to All Members/ PPS to CEO/PS to SS&FA/
All PAMD Officers/Guard file (PAMD), NITI Aayog.
2. Joint Secretary (PF-II) Department of Expenditure, North Block New Delhi.
Copy forwarded for information and guidance to:
1. Secretaries of All Ministries/Departments
2. Chairman, Railway Board, Rail Bhawan.
3. All Financial Advisers of Central Ministries/ Departments.
4. Joint Secretary, PMO.
5. Joint Secretary, Cabinet Secretariat.
Sd/.
(Praveen Mahto)
Adviser (PAMD)
15th
July 2015
5
6
7
8
9
Annexure-II
IPA for new Schemes/Programmes: Checklist for SMDs
I. Possibility of Merging new Scheme with Existing Schemes/Programmes:
Check points Yes/No
i. Whether the existing schemes/programmes being implemented by the
Ministry / Department has been examined by the SMD?
ii. Whether any of the existing schemes/programmes have a similar/
overlapping objectives as proposed in the new scheme?
iii. If the answer to (ii) above is yes, then
a. Whether the Ministry /Department has examined the possibility of
merging the new scheme with the existing scheme or modifying the existing
scheme for meeting the objectives envisaged for the new scheme and the
details included in the SFC/EFC note.
b. If no, whether the SMD has taken the matter with the
Ministry/Department for furnishing the details?
c. Has the requisite information been received from the
Ministry/Department?
d. If the answer to (a) or (c) above is yes, then whether the SMD agrees with
the views of the Ministry/Department?
e. In case SMD does not agree with the views of the Ministry/Department,
whether the same has been conveyed to the Ministry/Department and the
outcome thereof?
iv. If the answer to (ii) above is no, whether the SMD agrees with the
justification provided by the Ministry/Department for introduction of the
new scheme.
v. In case SMD does not agree with the justification provided by Ministry/
Department for introduction of the new scheme, whether the same has been
conveyed to the Ministry/Department and the outcome thereof?
II. Funding arrangements:
i. Whether the Ministry/ Department has provided details on the funding
arrangements proposed for meeting the fund requirements?
ii. If yes, whether the SMD concurs with the proposed arrangements?
iii. In case SMD does not concur, whether the same has been conveyed to the
Ministry/Department and the outcome thereof?
10
Annexure-III
Appraisal Grid for SMDs on SFC Proposals
Part I-Project Profile:
1) Project Summary:
Table I
Title of the Scheme
Nature/type of scheme (Centrally Sponsored / Central Sector etc)
Cost of the scheme as proposed
Annual Plan/Budget allocation
Annual Phasing of Expenditure
Rs in cr
Rs in cr
Funding pattern Share of each contributor
Table II
Objectives of the
scheme
(Describe in bullets)
Outcomes (Describe in bullets)
Beneficiaries Targeted Farmer/ Manufacturer / BPL families etc
Spatial Coverage All States, select state/ region/ pilot
Implementing agency
Manpower Requirements Existing, New
2) Approval of SFC sought for-
3) Brief Background & Justification Problems to be addressed
Demand Supply Gap identified
Date of origin of scheme (if continuing), Need for continuation
Balance work/ committed liabilities of previous plan period/s
4) Alignment of scheme objectives with the plan objectives/ priorities
5) Evaluation report on past Performance (in case of on-going schemes) - details
including name of agency, time-period, methodology, sample size, major
findings, suggestions etc.
6) Physical and Financial Performance in previous Plan (if continuing scheme)
Table III
Component Physical Target Cost (Rs.)
1
2
3
7) Physical and Financial targets in XII plan
Table IV
Component Physical Target Cost (Rs.)
1
2
3
11
8) Scheme Design
Brief on Scheme design/ Business model
Alternatives available & Overlaps with other schemes
Proposed Administrative design & delivery mechanism
Status of Statutory/ Mandatory clearances
Project Preparedness details
9) Financial Aspects
Item-wise Cost estimates: Table V
Expenditure Head
(Non- Recurring / Recurring expenses)
Total
(Figs. in Rs. crore)
Item-wise Non-Recurring exp.
Item-wise Recurring exp.
Grand Total
Year-wise sources of Financing: Table VI
Source of Financing Year 1 Year 2 Year 3 Year-4 Year-5 Total
Budgetary support
IEBR/ Loan
Foreign funding (including
foreign aid/ grant)
State's contribution
Institutional agencies/
Voluntary bodies
Donation
User Charges/ Beneficiary
contribution
Private sector contribution
Others, (please specify)
Total
10) Proposed Fund-flow mechanism (preferably in form of flow-chart)
11) Project management
Implementation schedule- {PERT/Bar Chart)
Mode of Implementation
Implementing Agencies
Manpower Requirements (New, outsourced, deployment etc.)
12) Monitoring & Implementation
Monitoring Mechanism, whether MIS in place
Nodal Officer
13) Viability/ Cost Effective Analysis
Project Viability (for commercial projects)
Sensitivity analysis/Risk Analysis
Cost effective analysis (for Social Sector schemes/programmes)
12
Part II- Appraisal by NITI Aayog
14. Need & Justification (critical observations on plan priorities & demand-supply gaps
and alignment with RFD targets)
15. Funds Availability (need to ensure conformity with the Annual Plan /Budget
allocations)
16. Changes proposed in scheme- In case of ongoing schemes comparative statement
highlighting changes in the activities, coverage, cost, funding pattern etc.
17. Project Design
Observations/ comments on Scheme design/ business model/ Technical aspects/ site etc.
(consider those benchmarks relevant to the proposed scheme/project which would
enable progress towards Outcomes and Outputs).
Coverage/ Scope (to ensure inter-regional equity)
Critical evaluation and comparison of the alternatives
Overlap of the scheme with other schemes (suggest possible convergence of the
schemes)
Comments on status of Statutory & Mandatory clearances (Land Acquisition,
Environmental Forest, techno-economic clearances from CEA/ CWC, E&F etc.)
Delivery mechanism – highlight the strengths and weakness of the proposed delivery
mechanism
Observation/ comments on Sustainability and Exit Strategy of the scheme, if relevant
User charges vs. Subsidies
Whether scheme provides for Community partnership/ ownership
DBT mode of payment to individual beneficiaries
18. Project Management:
Commitment of State Governments to participate both in implementation & funding (in
case of CSS)
Human Resource Capabilities
Stakeholder’s Involvement and engagement
Capabilities of agencies involved & Mode of implementation
19. Cost Estimates
Validity of Cost Estimates: Are all aspects of cost taken into consideration and provided
for with reasonable estimations of various items?
Review of cost benchmarks (as per norms prescribed by CPWD, MCI, CEA etc.)
Basis of cost estimates (constant prices) - to check updatedness (preferably not more
than 6 months old)
Foreign exchange component, if applicable
20. Comments on additional Manpower requirements proposed for execution of the
project/ scheme considering the implementation mechanism, cost estimates and funds
availability.
13
21. Financial Aspects
Sources of Financing and Funding Gap in 12th
Plan/Annual Plan, if any, with details of
re-appropriation of funds within approved outlay of the Ministry/Department.
Comments on Funding pattern (sharing of funds)
22. Viability/ sustainability of parameters – FIRR, ERR, units of cost estimates, Benefit
cost ratio etc., as applicable.
23. Comments on following aspects of Evaluation report (for ongoing schemes):
Methodology
Sample size
Evaluation parameters
Findings/ recommendations
24. Suggestions for Evaluation criteria:
Success indicator as per RFD
Key Performance Indicator- derived as per XII Plan outlay
Sample size
Evaluation of weak Implementation areas
25. Comments/ Concurrence of the Financial Adviser obtained.
*****